Practical guide · Standard work, SOPs and training
Pilot run and line trial: what to time, what to record and when to pass it
Short answer
A pilot run builds a small batch on the real line with production tools, parts, instructions and operators. Time every element, log every defect and stoppage with its cause, and pass the line only when it meets criteria you wrote down before the run.
A pilot run is a rehearsal of production on the real line. Film or time every station for the whole run, so you have element times for each unit, and record defects by operation, stoppages with cause and duration, departures from the work instruction, and anything awkward to reach, lift or see. Plan enough units to get past the first clumsy builds: a few dozen for timing, a few hundred if you need evidence on defect rates. Plot the times unit by unit. Times that fall steadily are learning. Times that stay high or spike are a method, part or tooling problem, and those are what the pilot is there to find. Decide to go ahead against exit criteria set in advance.
Last reviewed:
What a pilot run is, and what it is not
Where the pilot run sits, what goes in and what comes out
- Prototype buildOff the line, any toolsDoes the design work?
- Line trialReal line, stop and startCan each step be done at all?
- Pilot runReal line, no stopping, production operatorsHow long, what goes wrong, is it ready?
- Run at ratePlanned rate for hoursCan it hold rate and quality?
- Ramp-upSaleable output, rising weeklyHow fast to standard?
What the pilot run records
Times
Every element, every station, every unit
Quality
Each defect, where made and where found
Stoppages
Each stop with cause and minutes
Method and people
Departures from the instruction, awkward reaches, what operators say
Fix
Method, part and tooling problems, before launch
Plan
Checked times, a learning rate and a stoppage factor for the ramp
Decide
Pass, pass with conditions or repeat, against the exit criteria
A pilot run is the first time the whole production system runs together: the real line, the production tooling, parts from the production suppliers, the written work instructions and the operators who will do the job. The product it makes matters less than what you learn about the process.
Its job is to find the problems while they are still cheap. A connector that will not seat, a fixture that blocks a hand, a station that runs 10 seconds over: each of these costs an afternoon to fix in a pilot and weeks of missed output once customers are waiting. The best launches aim for what TPM calls a vertical start-up, where the line reaches its planned rate almost at once. A pilot run is how you earn one.
Plants use several names for the builds before full production. They are different events with different questions.
| Build | Where and with what | The question it answers | Typical size |
|---|---|---|---|
| Prototype or engineering build | Off the line, by engineers or skilled builders, with any tools that work | Does the design work? | A handful |
| Line trial | On the real line and tooling, stop and start, engineers at every station | Do the equipment, the tooling and the parts fit together, and can the method be done at all? | A few units to a few dozen |
| Pilot run | On the real line, run without stopping, by production operators following the work instructions | How long does each step take, what goes wrong, and is the line ready? | Dozens to a few hundred |
| Run at rate | The finished line at its planned rate for a sustained period | Can it hold the rate and the quality for hours, not minutes? | One to eight hours of output |
| Ramp-up | Saleable production, volume rising week by week | How fast can the crew reach standard? | Weeks |
Names vary by company: pre-series, pre-production build, production trial run and line trial are all in use. In automotive supply, parts for PPAP must come from a significant production run of one to eight hours and at least 300 consecutive parts unless the customer agrees otherwise.
The line trial and the pilot run are often merged, and that is where pilots go wrong. If engineers are still adjusting fixtures during the run, the times mean nothing. Finish the trial, fix what it found, then run the pilot.
What to time and what to record
Time everything, for every unit. This is the one study where you want the early, slow cycles as well as the late ones, because the shape of the line from first unit to last is the evidence. Video is the practical way: a camera at each station for the whole run, analysed afterwards. A stopwatch can't watch five stations for three hours.
| What | How | What it is for |
|---|---|---|
| Every element at every station, every unit | Video, broken into the elements in the routing | Element times, the learning rate, and which elements do not settle |
| Station cycle time, unit by unit | From the same video: start of one unit to start of the next | Whether each station fits the planned cycle time |
| Machine cycles | Machine counter or the video | Whether each machine keeps up, and how long the operator waits for it |
| Waiting and walking | Video, coded as its own elements | Imbalance between stations, and parts or tools placed too far away |
| Stoppages | A log at the line: start, end, station, cause | The stoppage factor in the staffing plan, from evidence |
| Material replenishment | Time each bin or box change | Whether the material plan interrupts the operator |
| Start-up and first good unit | Clock time from start to the first unit that passes | How long the line takes to get going each shift |
| Output by quarter hour | Tally at the end of the line | The rate at the end of the run, which is the one that counts |
Times alone will not tell you why. Record these alongside, at the moment they happen.
- Every defect, with the operation it was made at and the operation it was found at.
- Every time an operator does a step differently from the work instruction, and why. Often the operator's way is the better one.
- Every missing, wrong or awkward tool, fixture and part container.
- Reaches, lifts, twists and forces that look hard. A posture nobody notices in ten units is an injury in ten thousand.
- Parts that are hard to pick up, tell apart or fit, with the part number.
- What the operators say. Ask each one at the end what they would change first.
A pilot data capture sheet, filled in for one station
Example numbersGive one person the job of logging and nothing else. The engineers at the line will be busy fixing things, and what gets fixed without being written down gets forgotten.
How many units does a pilot run need?
It depends on which question you are answering, and the questions need very different numbers. A pilot sized only for timing can say almost nothing about defect rates.
For times
The number of cycles to time an element is n = (t x s / (k x mean)) squared, where s is the standard deviation of the readings, k is the accuracy you want as a fraction and t is about 2 for 95% confidence. What drives it is the coefficient of variation, s / mean: how much the readings scatter.
| Coefficient of variation | For plus or minus 5% | For plus or minus 10% |
|---|---|---|
| 5% (a tight, simple element) | 4 | 1 |
| 10% | 16 | 4 |
| 15% | 35 | 9 |
| 20% | 62 | 16 |
| 30% (an element with a problem) | 139 | 35 |
Worked with 1.96 in place of t, which is close enough for planning. Check with t and your own readings afterwards, as in the time study guide.
Those are steady cycles, after the first clumsy ones. In a pilot the early units are slow, so plan to throw away the first third for this purpose. For planning accuracy of plus or minus 10%, 30 to 40 units usually gives enough steady cycles on every element. The time study sample size calculator does the sum from your readings.
For quality
Here small pilots mislead. If you build n units and find no defects, the most you can say with 95% confidence is that the defect rate is below about 3 / n. Statisticians call this the rule of three.
| Units built, none defective | The defect rate is below |
|---|---|
| 30 | 9.5% |
| 60 | 4.9% |
| 100 | 3.0% |
| 300 | 1.0% |
Exact values of 1 minus 0.05^(1/n). The shortcut 3 / n gives 10%, 5%, 3% and 1%.
So 30 clean units do not show a good process. They show the defect rate is probably under 10%. That is why quality sign-off runs are in the hundreds, and why a 40-unit pilot should be judged on the defects it did find and whether their causes are fixed.
How many units? It depends on the question
To time an element to plus or minus 5%
Steady cycles needed, 95% confidence
- Readings vary by 5%4 cycles
- Readings vary by 10%16 cycles
- Readings vary by 15%35 cycles
- Readings vary by 20%62 cycles
- Readings vary by 30%139 cycles
Vary by means the coefficient of variation: standard deviation over the average.
If no unit in the run is defective
The most the defect rate could still be, 95% confidence
- 30 clean unitsbelow 9.5%
- 60 clean unitsbelow 4.9%
- 100 clean unitsbelow 3.0%
- 300 clean unitsbelow 1.0%
The rule of three: about 3 divided by the number of units.
A practical plan
Run two pilots. The first is small, 30 to 50 units, and exists to find problems and get first times. Fix what it found. The second is long enough to be a rehearsal: several hours at the planned crew size, a few hundred units if the product allows. If one unit takes hours to build, count in units and accept wider uncertainty: five to ten units and a careful log.
How to run a pilot, step by step
A pilot run from the exit criteria to the decision
- 1
Write the exit criteria first
- 2
Check readiness
- 3
Brief the operators
- 4
Set up the recording
- 5
Run without helping
- 6
Debrief at the line the same day
- 7
Analyse the times unit by unit
- 8
Decide against the criteria
- 1
Write the exit criteria first
Agree what the line must show to pass, with numbers, before the run. Criteria written afterwards bend to fit the result.
- 2
Check readiness
Production tooling, parts from production suppliers, gauges checked, work instructions at each station, operators trained on them. Anything substituted gets written down, because it limits what the pilot proves.
- 3
Brief the operators
Say what the run is for, that the cameras are timing the job and not judging the person, and that every problem they raise is wanted. Agree a signal for stopping the line.
- 4
Set up the recording
One camera per station with hands and parts in view, a stoppage log, a defect log by operation, and a person to keep them.
- 5
Run without helping
Engineers watch and log. They step in for safety or a hard stop, not to hand over a part or do a tricky step for the operator. The run should show what production will be like.
- 6
Debrief at the line the same day
Ask each operator what was hard. Walk the stations with the logs. List every issue with a station, an owner and a priority.
- 7
Analyse the times unit by unit
Plot each element against unit number. Separate learning from method problems, compare the steady times with the routing, and rework the station balance.
- 8
Decide against the criteria
Pass, pass with named open items, or repeat. Write the decision and the reasons in the report.
How to separate learning from method problems
Every station is slow in a pilot. The question is why. If operators are still learning, time will fix it and you plan a ramp. If the method, a part or a tool is wrong, time will not fix it, and waiting only builds the problem into the launch. The two leave different marks in the data.
| Look at | Learning | Method, part or tooling problem |
|---|---|---|
| Time against unit number | Falls steadily, quickly at first and then more slowly | Stays flat, or jumps about with no trend |
| Scatter | Narrows as the run goes on | Stays wide. Most cycles are fine and some are far over |
| On log-log paper | A straight falling line | No line fits |
| Across operators | Each one improves. The experienced ones start lower | Everyone is slow at the same step |
| On the video | Hesitation, looking at the instruction, re-gripping, fumbling. Less of it each cycle | Waiting, searching, forcing a part, a second try, walking for something. The same every cycle |
| Against the planning time | The gap closes | The gap stays |
| Cycles the formula asks for | A small number once the times settle | A very large number, because the scatter never settles |
Here are two elements from the first pilot of the work light line, 40 units, both well over their planning times. The numbers are illustrative.
| Measure | O-10: fit bezel, tighten 6 screws | O-5: fit LED module, plug in the LED lead |
|---|---|---|
| Planning time | 30 s | 24 s |
| Average of the first 10 units | 48.6 s | 41.6 s |
| Average of the last 10 units | 30.9 s | 41.8 s |
| Fitted learning rate | 86% | 100% (flat) |
| How well a learning curve fits (R squared) | 0.96 | 0.00 |
| Coefficient of variation, last 20 units | 3.5% | 20.5% |
| Cycles the formula asks for, plus or minus 5% | 3 | 74 |
| Cycles over 50 s | 3, all in the first 3 units | 7, spread through the run |
| Verdict | Learning. It reached the planning time by the end | Method problem. It will not improve on its own |
Two slow elements, two different causes
Example numbersO-10: fit bezel, tighten 6 screws
Learning
Follows a learning curve of 86%, R squared 0.96
First 10 units average 48.6 s, last 10 average 30.9 s.
Scatter in the last 20 units: 3.5%. The formula asks for 3 cycles.
Action: none. Use the rate to plan the ramp.
O-5: fit LED module, plug in the LED lead
Method problem, then the fix
No curve fits: rate 100%, R squared 0.00
First 10 units average 41.6 s, last 10 average 41.8 s.
Scatter in the last 20 units: 20.5%. The formula asks for 74 cycles.
Action: lengthen the lead. Pilot 2: 25.3 s, scatter 5.6%.
- Measured time, unit by unit
- Fitted learning curve
- Planning time from the routing
- Cycle over 50 s
O-10 started at 66 seconds and was at 31 by the end, a smooth fall. Nothing needs fixing. It tells you the learning rate to plan the ramp with. O-5 averaged 41 seconds from start to finish. Most cycles took about 37, and on 7 of the 40 units it took 53 to 64. The video showed the cause: the LED lead was too short to reach its socket with the module seated, so operators plugged it in at an angle, and when it did not latch they pulled the module out and tried again.
The fix was a design change to the lead length and a routing clip. In the second pilot O-5 averaged 25.3 seconds over 20 timed units with a coefficient of variation of 5.6%. No amount of practice would have found those 16 seconds.
One caution. Do not set a standard from pilot times, even the late ones. Operators are still on the learning curve and the method is still changing. Use the pilot to check the planning times and to find problems. Set the standard time from a proper time study once the line is stable.
What goes in the pilot run report
Keep it to a few pages that someone who was not there can act on. The report is the record of why the line was passed, and the next launch team will read it.
| Section | What it holds |
|---|---|
| Conditions | Date, shift, units planned and built, crew and their experience, and anything that was not production-standard: a substitute part, a temporary tool, a missing gauge |
| Result against the exit criteria | One table: each criterion, the target, the result, pass or fail |
| Output | Units by quarter hour, the rate in the last hour against the planned rate, start-up time to the first good unit |
| Times | Steady time for each element against the planning time, station times against the planned cycle time, and the revised balance |
| Learning | The time-per-unit plot for each station, the fitted learning rate, and the expected weeks to standard |
| Quality | First pass yield, defects by operation made and operation found, and the cause and fix for each |
| Stoppages | Each stop with duration and cause, and the total as a share of run time |
| Safety and ergonomics | Each finding with the station and a risk rating |
| Open issues | Every issue with a station, an owner, a due date and a priority, and the top five per station |
| Changes to documents | Which routing times, PFMEA rows, control plan rows and work instructions change as a result |
| Decision | Pass, pass with conditions or repeat, with names and date |
The changes to documents line is the one that gets skipped. A pilot that finds a new failure and fixes it on the floor, without the PFMEA and the work instruction catching up, has only fixed it for the people who were there. The operation numbers from process planning are what make this quick.
Exit criteria: when to pass the line
Exit criteria turn "it went quite well" into a decision. Write them before the run, give each a number and a way to measure it, and keep the list short enough that every line gets checked.
| Criterion | Target | Pilot 1: 40 units | Pilot 2: 300 units |
|---|---|---|---|
| Rate in the last hour, against the planned 48 an hour | At least 80% | 26 an hour, 54% | 41 an hour, 85% |
| First pass yield at the final test | At least 95% | 33 of 40, 82.5% | 289 of 300, 96.3% |
| Stations inside the 69 s planned cycle time (average of the last 10 units) | 5 of 5 | 4 of 5. Station 3 at 78 s | 5 of 5. Longest 63 s |
| Elements with enough steady cycles for plus or minus 10% | 14 of 14 | 12 of 14 | 14 of 14 |
| High-risk safety or ergonomic findings open | 0 | 2 | 0 |
| Work instructions that match the method used | 5 of 5 stations | 3 of 5 | 5 of 5 |
| High-priority issues open | 0 | 9 | 0 |
| Decision | Repeat after fixes | Pass, 3 medium issues carried into ramp-up with owners |
The targets are examples. Set your own from what the customer and the business need. A rate target under 100% is deliberate: the crew is still learning, and the ramp plan covers the rest.
The exit gate: first pilot against second
Example numbersRate in the last hour
Target: at least 80% of 48 an hour
Pilot 1 26 an hour, 54%Pilot 2 41 an hour, 85%First pass yield at the final test
Target: at least 95%
Pilot 1 33 of 40, 82.5%Pilot 2 289 of 300, 96.3%Stations inside the 69 s planned cycle time
Target: 5 of 5
Pilot 1 4 of 5Pilot 2 5 of 5Elements with enough steady cycles
Target: 14 of 14
Pilot 1 12 of 14Pilot 2 14 of 14Work instructions that match the method
Target: 5 of 5 stations
Pilot 1 3 of 5Pilot 2 5 of 5High-risk safety or ergonomic findings open
Target: 0
Pilot 1 2Pilot 2 0High-priority issues open
Target: 0
Pilot 1 9Pilot 2 0
Pilot 1, 40 units
Repeat after fixes
Pilot 2, 300 units
Pass, 3 medium issues carried into ramp-up
Three rules keep the gate honest. A criterion with no number is not a criterion. Passing with conditions is fine, but each condition needs an owner and a date, and safety items are never conditions. And if the pilot was not run under production conditions, say which results that weakens.
After a pass, the line goes into ramp-up, and the staffing for those weeks comes from planning operators and stations for a new line and the ramp-up plan.
Pilot run checklist
| When | Check | Why it matters |
|---|---|---|
| Before | Exit criteria agreed and signed | So the decision is made against a fixed bar |
| Before | Line trial finished and its issues closed | So the pilot measures the line, not the debugging |
| Before | Production tooling, fixtures and gauges in place and checked | Times and defects from temporary tools do not carry over |
| Before | Parts from production suppliers in production packaging | Part fit and part presentation are half of what goes wrong |
| Before | Work instruction at every station, operators trained on it | You are testing the written method |
| Before | Routing with planning times and station balance printed | It is what the results are compared with |
| Before | Cameras, stoppage log and defect log ready, a logger named | What is not recorded during the run is lost |
| Before | Operators briefed on the purpose and on how to stop the line | People who know why they are filmed work normally |
| During | Every unit numbered, with start and finish time | It ties times, defects and stoppages to the same unit |
| During | Engineers observe and do not help | So the run shows production as it will be |
| During | Every stop logged with cause and duration | It becomes the stoppage factor |
| During | Every defect logged by operation made and found | It feeds the PFMEA and the control plan |
| During | Departures from the work instruction noted | Either the instruction or the training changes |
| After | Debrief with operators at the line, the same day | Detail fades overnight |
| After | Element times plotted by unit, learning separated from method problems | It decides what to fix and what to wait for |
| After | Issue list with station, owner, date and priority | It runs the daily launch meeting |
| After | Routing, PFMEA, control plan and instructions updated | So the fixes last |
| After | Report written and decision recorded | The next launch starts from it |
What a pilot can't tell you, and the people side
A pilot is short. It will not show tool wear, a supplier's bad batch, the night shift, the third week when the novelty has worn off, or a failure that happens once in two thousand units. It runs with engineers nearby and everyone paying attention. Treat a pass as permission to start the ramp with a daily review, not as proof the launch will go well.
It can also flatter the times. A hand-picked crew of the best operators will be faster than the crew that runs the line in month three. If you can, pilot with the people who will do the job.
For those people the pilot is their first sight of the new job, with cameras on them and managers watching. Tell them before the run what is being measured and what is not. The film is of the job. Slow early units are expected and nobody is ranked on them. Then make it true: fix something an operator raised before the second pilot, and say whose idea it was. Operators who see their first suggestion acted on will give you the next twenty.
Filming the stations makes most of this page easier. LeanSuite's Time and Motion Study breaks each station's video into timed elements, so the unit-by-unit plots come from the film and not from a clipboard. See the new product time study playbook for which study belongs at which stage.
Templates and tools for a pilot run
- Video time study filming checklist: where to put each camera and what to tell the crew.
- Time study sheet: element times by cycle, if you are timing by hand.
- Time study sample size calculator: cycles needed from your own readings.
- Learning curve and ramp-up workbook: fit a learning rate to the pilot's unit times.
- PFMEA template and control plan template: where pilot defects end up.
- PPAP checklist and APQP checklist: what the customer expects from the production trial run.
- New product introduction for industrial engineers: where the pilot sits in the launch.
Go deeper
This page is the short version. These guides cover each part in full.
- FMEA in Manufacturing: Failure Mode and Effects Analysis GuideWhere each pilot defect goes afterwards: a failure mode, a cause and a control.
- First Pass Yield: Definition, Calculation and ImprovementHow to measure the yield figure in the exit criteria properly.
- Work Instructions: Visual and Effective DocumentationWriting the instructions the pilot is meant to test.
- TWI Job Instruction: Training Method for Standard WorkTraining the pilot crew so the run tests the method and not the briefing.
All our articles on this subject are in the standard work, sops and training topic.
Free templates and tools
- Video time study filming checklistA pre-shoot checklist and shot log for filming a time study on video: camera, light, people, settings, power and review.
- Time study sheetTime each element over 10 cycles and work out the average, lowest repeatable and standard time. Excel does the sums.
- Learning curve and ramp-up workbookBoth learning curve models side by side, a fit from your own observed hours, batch hours, the unit that reaches standard and a weekly ramp plan.
- PFMEA template (process FMEA)Failure modes, effects and causes rated for severity, occurrence and detection, with RPN before and after action.
- Control plan templateWhat is checked at each step, against which limits, how, how often, and what to do when a result is out.
- PPAP checklistThe 18 PPAP elements with owner, due date and status, the five submission levels and a readiness count.
- APQP checklistThe five APQP phases as a checklist: deliverables, owners, due dates, gate reviews and an issues list.
- Time study sample size calculatorHow many cycles of an element to time, from your first readings, with the t formula, the ILO formula and the range method.
- First pass yield (FPY) calculatorFirst pass yield at each step and rolled throughput yield (RTY) across the whole process.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
Doing this in LeanSuite
Time and Motion Study
Film the station and the AI times every element on a timeline that links to the video, split into value-added, necessary and waste.
See Time and Motion StudyAI Video Analysis
Turns video of real work into time studies, line balance charts, changeover splits and other studies you review and certify.
See AI Video Analysis
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about pilot run and line trial
A pilot run is a small production batch built on the real line, with production tooling, parts, work instructions and operators, before full production starts. Its purpose is to test the process, not to make stock. The team times every station, records defects and stoppages with their causes, and decides against written criteria whether the line is ready to ramp up.
A line trial checks that the equipment, tooling and parts work together and that each step can be done. It is stop and start, with engineers at the stations. A pilot run comes after the trial's problems are fixed. It runs without stopping, with production operators following the work instructions, and measures times, quality and stoppages.
Enough for the question. For times, 30 to 40 units usually gives enough steady cycles on each element for planning accuracy. For quality it takes far more: no defects in 30 units only shows the defect rate is under about 10 percent, and it takes 300 clean units to show it is under 1 percent. Many plants run a small first pilot and a longer second one.
Element times at every station for every unit, station cycle times, machine cycles, waiting and walking, each stoppage with its cause and duration, each defect with the operation that made it and the one that found it, departures from the work instruction, tooling and part problems, ergonomic and safety observations, output by quarter hour and what the operators say.
Plot the time for each element against unit number. Learning falls steadily and the scatter narrows, and the points form a straight line on log-log paper. A method, part or tooling problem stays flat or spikes at random, is slow for every operator, and looks the same on video every cycle: waiting, forcing a part or a second try.
They are the measurable conditions the line must meet to move on, agreed before the run. Typical ones cover the output rate at the end of the run, first pass yield, every station fitting the planned cycle time, no open high-risk safety or ergonomic findings, work instructions that match the method, and no open high-priority issues. Each needs a number and an owner.
No. Operators are still learning and the method is still being changed, so pilot times run long and uneven. Use them to check the planning times, find problem elements and estimate the learning rate. Set the standard from a time study on the stable line, with trained operators and the final method.
A run at rate is a sustained production run at the planned rate, used to show the finished line can hold its quoted output and quality over hours. Some automotive customers require one. It is related to the PPAP significant production run, which is one to eight hours and at least 300 consecutive parts unless the customer agrees otherwise.
Related guides and tools
- New product time study playbook: which study to run at each stage of a launch
- Ramp-up plan and the learning curve: what happens after the pilot passes
- Process planning for a new product: the routing the pilot tests
- Planning operators and stations for a new line: the balance the pilot checks
- How to conduct a time study: setting the standard once the line is stable
- APQP: the five phases and where the production trial run sits
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk
Or browse the topics, the full library and the lean glossary.
Rather see it on your own problem?
Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.