Pilot run and line trial: what to time, what to record and when to pass it

Short answer

A pilot run builds a small batch on the real line with production tools, parts, instructions and operators. Time every element, log every defect and stoppage with its cause, and pass the line only when it meets criteria you wrote down before the run.

A pilot run is a rehearsal of production on the real line. Film or time every station for the whole run, so you have element times for each unit, and record defects by operation, stoppages with cause and duration, departures from the work instruction, and anything awkward to reach, lift or see. Plan enough units to get past the first clumsy builds: a few dozen for timing, a few hundred if you need evidence on defect rates. Plot the times unit by unit. Times that fall steadily are learning. Times that stay high or spike are a method, part or tooling problem, and those are what the pilot is there to find. Decide to go ahead against exit criteria set in advance.

Last reviewed:

What a pilot run is, and what it is not

Where the pilot run sits, what goes in and what comes out

  1. Prototype buildOff the line, any toolsDoes the design work?
  2. Line trialReal line, stop and startCan each step be done at all?
  3. Pilot runReal line, no stopping, production operatorsHow long, what goes wrong, is it ready?
  4. Run at ratePlanned rate for hoursCan it hold rate and quality?
  5. Ramp-upSaleable output, rising weeklyHow fast to standard?

What the pilot run records

Times

Every element, every station, every unit

Quality

Each defect, where made and where found

Stoppages

Each stop with cause and minutes

Method and people

Departures from the instruction, awkward reaches, what operators say

Fix

Method, part and tooling problems, before launch

Plan

Checked times, a learning rate and a stoppage factor for the ramp

Decide

Pass, pass with conditions or repeat, against the exit criteria

Five builds, five different questions. The pilot run is the first one that runs like production, so it is the first that can be timed. What it records feeds one decision, made against criteria written before the run.

A pilot run is the first time the whole production system runs together: the real line, the production tooling, parts from the production suppliers, the written work instructions and the operators who will do the job. The product it makes matters less than what you learn about the process.

Its job is to find the problems while they are still cheap. A connector that will not seat, a fixture that blocks a hand, a station that runs 10 seconds over: each of these costs an afternoon to fix in a pilot and weeks of missed output once customers are waiting. The best launches aim for what TPM calls a vertical start-up, where the line reaches its planned rate almost at once. A pilot run is how you earn one.

Plants use several names for the builds before full production. They are different events with different questions.

The builds before full production and what each one proves
BuildWhere and with whatThe question it answersTypical size
Prototype or engineering buildOff the line, by engineers or skilled builders, with any tools that workDoes the design work?A handful
Line trialOn the real line and tooling, stop and start, engineers at every stationDo the equipment, the tooling and the parts fit together, and can the method be done at all?A few units to a few dozen
Pilot runOn the real line, run without stopping, by production operators following the work instructionsHow long does each step take, what goes wrong, and is the line ready?Dozens to a few hundred
Run at rateThe finished line at its planned rate for a sustained periodCan it hold the rate and the quality for hours, not minutes?One to eight hours of output
Ramp-upSaleable production, volume rising week by weekHow fast can the crew reach standard?Weeks

Names vary by company: pre-series, pre-production build, production trial run and line trial are all in use. In automotive supply, parts for PPAP must come from a significant production run of one to eight hours and at least 300 consecutive parts unless the customer agrees otherwise.

The line trial and the pilot run are often merged, and that is where pilots go wrong. If engineers are still adjusting fixtures during the run, the times mean nothing. Finish the trial, fix what it found, then run the pilot.

What to time and what to record

Time everything, for every unit. This is the one study where you want the early, slow cycles as well as the late ones, because the shape of the line from first unit to last is the evidence. Video is the practical way: a camera at each station for the whole run, analysed afterwards. A stopwatch can't watch five stations for three hours.

What to time in a pilot run
WhatHowWhat it is for
Every element at every station, every unitVideo, broken into the elements in the routingElement times, the learning rate, and which elements do not settle
Station cycle time, unit by unitFrom the same video: start of one unit to start of the nextWhether each station fits the planned cycle time
Machine cyclesMachine counter or the videoWhether each machine keeps up, and how long the operator waits for it
Waiting and walkingVideo, coded as its own elementsImbalance between stations, and parts or tools placed too far away
StoppagesA log at the line: start, end, station, causeThe stoppage factor in the staffing plan, from evidence
Material replenishmentTime each bin or box changeWhether the material plan interrupts the operator
Start-up and first good unitClock time from start to the first unit that passesHow long the line takes to get going each shift
Output by quarter hourTally at the end of the lineThe rate at the end of the run, which is the one that counts

Times alone will not tell you why. Record these alongside, at the moment they happen.

  • Every defect, with the operation it was made at and the operation it was found at.
  • Every time an operator does a step differently from the work instruction, and why. Often the operator's way is the better one.
  • Every missing, wrong or awkward tool, fixture and part container.
  • Reaches, lifts, twists and forces that look hard. A posture nobody notices in ten units is an injury in ten thousand.
  • Parts that are hard to pick up, tell apart or fit, with the part number.
  • What the operators say. Ask each one at the end what they would change first.

A pilot data capture sheet, filled in for one station

Example numbers
Line LED work lightStation 3: housing, LED module, driver boardRun Pilot 1Times seconds, from video
UnitO-1O-5O-6StationDefect, stop or note
122363088First build. Read the instruction at each step
219352781
318352578
4176424105LED lead would not latch. Module pulled out, second try
517362376
616402379
716362274Screw bin ran empty: 40 s stop, logged
815412278
916582195Lead again. Too short to reach with the module seated
1015352171
Average17.141.623.882.5Units 1 to 10
Planning time14241856From the routing. Planned cycle time 69 s
Station 3 in the first pilot, units 1 to 10, times from the video. O-1 and O-6 fall unit by unit, which is learning. O-5 does not move, and twice it jumps: the yellow cells. The note written at the moment says why. Over these ten units the station averages 82.5 seconds against a planned cycle time of 69.

Give one person the job of logging and nothing else. The engineers at the line will be busy fixing things, and what gets fixed without being written down gets forgotten.

How many units does a pilot run need?

It depends on which question you are answering, and the questions need very different numbers. A pilot sized only for timing can say almost nothing about defect rates.

For times

The number of cycles to time an element is n = (t x s / (k x mean)) squared, where s is the standard deviation of the readings, k is the accuracy you want as a fraction and t is about 2 for 95% confidence. What drives it is the coefficient of variation, s / mean: how much the readings scatter.

Steady cycles needed at 95% confidence, by how much the element varies
Coefficient of variationFor plus or minus 5%For plus or minus 10%
5% (a tight, simple element)41
10%164
15%359
20%6216
30% (an element with a problem)13935

Worked with 1.96 in place of t, which is close enough for planning. Check with t and your own readings afterwards, as in the time study guide.

Those are steady cycles, after the first clumsy ones. In a pilot the early units are slow, so plan to throw away the first third for this purpose. For planning accuracy of plus or minus 10%, 30 to 40 units usually gives enough steady cycles on every element. The time study sample size calculator does the sum from your readings.

For quality

Here small pilots mislead. If you build n units and find no defects, the most you can say with 95% confidence is that the defect rate is below about 3 / n. Statisticians call this the rule of three.

What a run with zero defects proves about the defect rate (95% confidence)
Units built, none defectiveThe defect rate is below
309.5%
604.9%
1003.0%
3001.0%

Exact values of 1 minus 0.05^(1/n). The shortcut 3 / n gives 10%, 5%, 3% and 1%.

So 30 clean units do not show a good process. They show the defect rate is probably under 10%. That is why quality sign-off runs are in the hundreds, and why a 40-unit pilot should be judged on the defects it did find and whether their causes are fixed.

How many units? It depends on the question

To time an element to plus or minus 5%

Steady cycles needed, 95% confidence

  • Readings vary by 5%4 cycles
  • Readings vary by 10%16 cycles
  • Readings vary by 15%35 cycles
  • Readings vary by 20%62 cycles
  • Readings vary by 30%139 cycles

Vary by means the coefficient of variation: standard deviation over the average.

If no unit in the run is defective

The most the defect rate could still be, 95% confidence

  • 30 clean unitsbelow 9.5%
  • 60 clean unitsbelow 4.9%
  • 100 clean unitsbelow 3.0%
  • 300 clean unitsbelow 1.0%

The rule of three: about 3 divided by the number of units.

Left: a steady element needs only a handful of cycles to time, and one that scatters needs dozens. Right: clean units prove very little about quality until there are hundreds of them. A 40-unit pilot can settle most times and almost no defect rates.

A practical plan

Run two pilots. The first is small, 30 to 50 units, and exists to find problems and get first times. Fix what it found. The second is long enough to be a rehearsal: several hours at the planned crew size, a few hundred units if the product allows. If one unit takes hours to build, count in units and accept wider uncertainty: five to ten units and a careful log.

How to run a pilot, step by step

A pilot run from the exit criteria to the decision

  1. 1

    Write the exit criteria first

  2. 2

    Check readiness

  3. 3

    Brief the operators

  4. 4

    Set up the recording

  5. 5

    Run without helping

  6. 6

    Debrief at the line the same day

  7. 7

    Analyse the times unit by unit

  8. 8

    Decide against the criteria

Steps 1 to 4 happen before the first unit. Step 5 is the run. Steps 6 to 8 turn what was recorded into a decision.
  1. 1

    Write the exit criteria first

    Agree what the line must show to pass, with numbers, before the run. Criteria written afterwards bend to fit the result.

  2. 2

    Check readiness

    Production tooling, parts from production suppliers, gauges checked, work instructions at each station, operators trained on them. Anything substituted gets written down, because it limits what the pilot proves.

  3. 3

    Brief the operators

    Say what the run is for, that the cameras are timing the job and not judging the person, and that every problem they raise is wanted. Agree a signal for stopping the line.

  4. 4

    Set up the recording

    One camera per station with hands and parts in view, a stoppage log, a defect log by operation, and a person to keep them.

  5. 5

    Run without helping

    Engineers watch and log. They step in for safety or a hard stop, not to hand over a part or do a tricky step for the operator. The run should show what production will be like.

  6. 6

    Debrief at the line the same day

    Ask each operator what was hard. Walk the stations with the logs. List every issue with a station, an owner and a priority.

  7. 7

    Analyse the times unit by unit

    Plot each element against unit number. Separate learning from method problems, compare the steady times with the routing, and rework the station balance.

  8. 8

    Decide against the criteria

    Pass, pass with named open items, or repeat. Write the decision and the reasons in the report.

How to separate learning from method problems

Every station is slow in a pilot. The question is why. If operators are still learning, time will fix it and you plan a ramp. If the method, a part or a tool is wrong, time will not fix it, and waiting only builds the problem into the launch. The two leave different marks in the data.

Signs that a slow element is learning, and signs that it is a method problem
Look atLearningMethod, part or tooling problem
Time against unit numberFalls steadily, quickly at first and then more slowlyStays flat, or jumps about with no trend
ScatterNarrows as the run goes onStays wide. Most cycles are fine and some are far over
On log-log paperA straight falling lineNo line fits
Across operatorsEach one improves. The experienced ones start lowerEveryone is slow at the same step
On the videoHesitation, looking at the instruction, re-gripping, fumbling. Less of it each cycleWaiting, searching, forcing a part, a second try, walking for something. The same every cycle
Against the planning timeThe gap closesThe gap stays
Cycles the formula asks forA small number once the times settleA very large number, because the scatter never settles

Here are two elements from the first pilot of the work light line, 40 units, both well over their planning times. The numbers are illustrative.

Illustrative: two slow elements in the first pilot of 40 units
MeasureO-10: fit bezel, tighten 6 screwsO-5: fit LED module, plug in the LED lead
Planning time30 s24 s
Average of the first 10 units48.6 s41.6 s
Average of the last 10 units30.9 s41.8 s
Fitted learning rate86%100% (flat)
How well a learning curve fits (R squared)0.960.00
Coefficient of variation, last 20 units3.5%20.5%
Cycles the formula asks for, plus or minus 5%374
Cycles over 50 s3, all in the first 3 units7, spread through the run
VerdictLearning. It reached the planning time by the endMethod problem. It will not improve on its own

Two slow elements, two different causes

Example numbers

O-10: fit bezel, tighten 6 screws

Learning

O-10 in pilot 1O-10 in pilot 1 over 40 units: first unit 66 seconds, average of the first 10 48.6, average of the last 10 30.9, against a planning time of 30 seconds.0204060Planning time 30 s110203040Unit numberSeconds

Follows a learning curve of 86%, R squared 0.96

First 10 units average 48.6 s, last 10 average 30.9 s.

Scatter in the last 20 units: 3.5%. The formula asks for 3 cycles.

Action: none. Use the rate to plan the ramp.

O-5: fit LED module, plug in the LED lead

Method problem, then the fix

O-5 in pilot 1 and pilot 2O-5 in pilot 1 and pilot 2 over 40 units: first unit 36 seconds, average of the first 10 41.6, average of the last 10 41.8, against a planning time of 24 seconds. In the second pilot, after the fix, 20 units average 25.3 seconds.0204060Planning time 24 sPilot 1Pilot 212040Seconds

No curve fits: rate 100%, R squared 0.00

First 10 units average 41.6 s, last 10 average 41.8 s.

Scatter in the last 20 units: 20.5%. The formula asks for 74 cycles.

Action: lengthen the lead. Pilot 2: 25.3 s, scatter 5.6%.

  • Measured time, unit by unit
  • Fitted learning curve
  • Planning time from the routing
  • Cycle over 50 s
Both elements ran well over their planning time in the first pilot. O-10 falls along a smooth curve and reaches its planning time on its own. O-5 stays flat near 41 seconds with 7 spikes, the yellow dots, where the lead would not latch. Practice did nothing for it. A longer lead did: in the second pilot it averages 25.3 seconds.

O-10 started at 66 seconds and was at 31 by the end, a smooth fall. Nothing needs fixing. It tells you the learning rate to plan the ramp with. O-5 averaged 41 seconds from start to finish. Most cycles took about 37, and on 7 of the 40 units it took 53 to 64. The video showed the cause: the LED lead was too short to reach its socket with the module seated, so operators plugged it in at an angle, and when it did not latch they pulled the module out and tried again.

The fix was a design change to the lead length and a routing clip. In the second pilot O-5 averaged 25.3 seconds over 20 timed units with a coefficient of variation of 5.6%. No amount of practice would have found those 16 seconds.

One caution. Do not set a standard from pilot times, even the late ones. Operators are still on the learning curve and the method is still changing. Use the pilot to check the planning times and to find problems. Set the standard time from a proper time study once the line is stable.

What goes in the pilot run report

Keep it to a few pages that someone who was not there can act on. The report is the record of why the line was passed, and the next launch team will read it.

Contents of a pilot run report
SectionWhat it holds
ConditionsDate, shift, units planned and built, crew and their experience, and anything that was not production-standard: a substitute part, a temporary tool, a missing gauge
Result against the exit criteriaOne table: each criterion, the target, the result, pass or fail
OutputUnits by quarter hour, the rate in the last hour against the planned rate, start-up time to the first good unit
TimesSteady time for each element against the planning time, station times against the planned cycle time, and the revised balance
LearningThe time-per-unit plot for each station, the fitted learning rate, and the expected weeks to standard
QualityFirst pass yield, defects by operation made and operation found, and the cause and fix for each
StoppagesEach stop with duration and cause, and the total as a share of run time
Safety and ergonomicsEach finding with the station and a risk rating
Open issuesEvery issue with a station, an owner, a due date and a priority, and the top five per station
Changes to documentsWhich routing times, PFMEA rows, control plan rows and work instructions change as a result
DecisionPass, pass with conditions or repeat, with names and date

The changes to documents line is the one that gets skipped. A pilot that finds a new failure and fixes it on the floor, without the PFMEA and the work instruction catching up, has only fixed it for the people who were there. The operation numbers from process planning are what make this quick.

Exit criteria: when to pass the line

Exit criteria turn "it went quite well" into a decision. Write them before the run, give each a number and a way to measure it, and keep the list short enough that every line gets checked.

Illustrative: exit criteria for the work light line, first and second pilot
CriterionTargetPilot 1: 40 unitsPilot 2: 300 units
Rate in the last hour, against the planned 48 an hourAt least 80%26 an hour, 54%41 an hour, 85%
First pass yield at the final testAt least 95%33 of 40, 82.5%289 of 300, 96.3%
Stations inside the 69 s planned cycle time (average of the last 10 units)5 of 54 of 5. Station 3 at 78 s5 of 5. Longest 63 s
Elements with enough steady cycles for plus or minus 10%14 of 1412 of 1414 of 14
High-risk safety or ergonomic findings open020
Work instructions that match the method used5 of 5 stations3 of 55 of 5
High-priority issues open090
DecisionRepeat after fixesPass, 3 medium issues carried into ramp-up with owners

The targets are examples. Set your own from what the customer and the business need. A rate target under 100% is deliberate: the crew is still learning, and the ramp plan covers the rest.

The exit gate: first pilot against second

Example numbers
  • Rate in the last hour

    Target: at least 80% of 48 an hour

    Pilot 1 26 an hour, 54%
    Pilot 2 41 an hour, 85%
  • First pass yield at the final test

    Target: at least 95%

    Pilot 1 33 of 40, 82.5%
    Pilot 2 289 of 300, 96.3%
  • Stations inside the 69 s planned cycle time

    Target: 5 of 5

    Pilot 1 4 of 5
    Pilot 2 5 of 5
  • Elements with enough steady cycles

    Target: 14 of 14

    Pilot 1 12 of 14
    Pilot 2 14 of 14
  • Work instructions that match the method

    Target: 5 of 5 stations

    Pilot 1 3 of 5
    Pilot 2 5 of 5
  • High-risk safety or ergonomic findings open

    Target: 0

    Pilot 1 2
    Pilot 2 0
  • High-priority issues open

    Target: 0

    Pilot 1 9
    Pilot 2 0

Pilot 1, 40 units

Repeat after fixes

Pilot 2, 300 units

Pass, 3 medium issues carried into ramp-up

Each bar is a result and the yellow tick is its target. The first pilot missed every line, which is what a first pilot is for. Nine high-priority issues were fixed between the runs, and the second pilot cleared the gate. The targets were set before either run.

Three rules keep the gate honest. A criterion with no number is not a criterion. Passing with conditions is fine, but each condition needs an owner and a date, and safety items are never conditions. And if the pilot was not run under production conditions, say which results that weakens.

After a pass, the line goes into ramp-up, and the staffing for those weeks comes from planning operators and stations for a new line and the ramp-up plan.

Pilot run checklist

Pilot run checklist: before, during and after
WhenCheckWhy it matters
BeforeExit criteria agreed and signedSo the decision is made against a fixed bar
BeforeLine trial finished and its issues closedSo the pilot measures the line, not the debugging
BeforeProduction tooling, fixtures and gauges in place and checkedTimes and defects from temporary tools do not carry over
BeforeParts from production suppliers in production packagingPart fit and part presentation are half of what goes wrong
BeforeWork instruction at every station, operators trained on itYou are testing the written method
BeforeRouting with planning times and station balance printedIt is what the results are compared with
BeforeCameras, stoppage log and defect log ready, a logger namedWhat is not recorded during the run is lost
BeforeOperators briefed on the purpose and on how to stop the linePeople who know why they are filmed work normally
DuringEvery unit numbered, with start and finish timeIt ties times, defects and stoppages to the same unit
DuringEngineers observe and do not helpSo the run shows production as it will be
DuringEvery stop logged with cause and durationIt becomes the stoppage factor
DuringEvery defect logged by operation made and foundIt feeds the PFMEA and the control plan
DuringDepartures from the work instruction notedEither the instruction or the training changes
AfterDebrief with operators at the line, the same dayDetail fades overnight
AfterElement times plotted by unit, learning separated from method problemsIt decides what to fix and what to wait for
AfterIssue list with station, owner, date and priorityIt runs the daily launch meeting
AfterRouting, PFMEA, control plan and instructions updatedSo the fixes last
AfterReport written and decision recordedThe next launch starts from it

What a pilot can't tell you, and the people side

A pilot is short. It will not show tool wear, a supplier's bad batch, the night shift, the third week when the novelty has worn off, or a failure that happens once in two thousand units. It runs with engineers nearby and everyone paying attention. Treat a pass as permission to start the ramp with a daily review, not as proof the launch will go well.

It can also flatter the times. A hand-picked crew of the best operators will be faster than the crew that runs the line in month three. If you can, pilot with the people who will do the job.

For those people the pilot is their first sight of the new job, with cameras on them and managers watching. Tell them before the run what is being measured and what is not. The film is of the job. Slow early units are expected and nobody is ranked on them. Then make it true: fix something an operator raised before the second pilot, and say whose idea it was. Operators who see their first suggestion acted on will give you the next twenty.

Filming the stations makes most of this page easier. LeanSuite's Time and Motion Study breaks each station's video into timed elements, so the unit-by-unit plots come from the film and not from a clipboard. See the new product time study playbook for which study belongs at which stage.

Templates and tools for a pilot run

FAQ

Questions about pilot run and line trial

  1. A pilot run is a small production batch built on the real line, with production tooling, parts, work instructions and operators, before full production starts. Its purpose is to test the process, not to make stock. The team times every station, records defects and stoppages with their causes, and decides against written criteria whether the line is ready to ramp up.

  2. A line trial checks that the equipment, tooling and parts work together and that each step can be done. It is stop and start, with engineers at the stations. A pilot run comes after the trial's problems are fixed. It runs without stopping, with production operators following the work instructions, and measures times, quality and stoppages.

  3. Enough for the question. For times, 30 to 40 units usually gives enough steady cycles on each element for planning accuracy. For quality it takes far more: no defects in 30 units only shows the defect rate is under about 10 percent, and it takes 300 clean units to show it is under 1 percent. Many plants run a small first pilot and a longer second one.

  4. Element times at every station for every unit, station cycle times, machine cycles, waiting and walking, each stoppage with its cause and duration, each defect with the operation that made it and the one that found it, departures from the work instruction, tooling and part problems, ergonomic and safety observations, output by quarter hour and what the operators say.

  5. Plot the time for each element against unit number. Learning falls steadily and the scatter narrows, and the points form a straight line on log-log paper. A method, part or tooling problem stays flat or spikes at random, is slow for every operator, and looks the same on video every cycle: waiting, forcing a part or a second try.

  6. They are the measurable conditions the line must meet to move on, agreed before the run. Typical ones cover the output rate at the end of the run, first pass yield, every station fitting the planned cycle time, no open high-risk safety or ergonomic findings, work instructions that match the method, and no open high-priority issues. Each needs a number and an owner.

  7. No. Operators are still learning and the method is still being changed, so pilot times run long and uneven. Use them to check the planning times, find problem elements and estimate the learning rate. Set the standard from a time study on the stable line, with trained operators and the final method.

  8. A run at rate is a sustained production run at the planned rate, used to show the finished line can hold its quoted output and quality over hours. Some automotive customers require one. It is related to the PPAP significant production run, which is one to eight hours and at least 300 consecutive parts unless the customer agrees otherwise.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.