Short answer
Time enough cycles that the mean of the most variable element is within the accuracy you need, usually plus or minus 5 percent at 95 percent confidence. Time 10 cycles first, then apply n = (t × s ÷ (k × mean))². Before any readings, a 1 minute cycle is usually planned at 30 cycles.
There are two ways to get the number, and a careful study uses both. Before you have any readings, look the cycle length up in the General Electric guide: 30 cycles for a job of up to 1 minute, 15 for up to 5 minutes, 3 for over 40 minutes. Once you have 5 to 10 readings, use the statistical formula on each element: n = (t × s ÷ (k × mean))², where s is the standard deviation of the readings, k is the accuracy as a decimal (0.05 for plus or minus 5 percent) and t comes from the t table for the number of readings you have. The element that needs the most cycles sets the length of the study.
Last reviewed:
What you are deciding, and why it is not one number
From ten pilot cycles to the length of the study
Example numbers- 1
Time a pilot10 cycles, every element
- 2
Measure the spreadMean and standard deviation of each element
- 3
Apply the formulan = (t × s ÷ (k × mean))², with k = 0.05
- 10 cycles timed so far
- Enough already
- Needs more
- Sets the length of the study
Cycles needed for plus or minus 5 percent at 95 percent confidence, from ten pilot readings of each element: element 1, Seat housing, 15; element 2, Gasket and cover, 8; element 3, Start 4 bolts, 51; element 4, Run down bolts, 10; element 5, Start test, label, 19; element 6, Wait for test, 6; element 7, Unload, 18. Element 3 needs the most, so the study runs to 51 cycles.
Every reading in a time study is a little different from the last. The operator's hand lands slightly differently, a bolt catches the thread or does not. The mean of your readings is therefore an estimate of the true mean, and the more the readings scatter, the more of them you need before the estimate is worth using.
So the honest answer to "how many cycles?" is another question: how much do the times vary, and how close do you need to be? A power tool that takes the same time on every part is pinned down in a handful of cycles. Hand-fitting that depends on feel is not pinned down in ten. The number is a property of the element, which is why it cannot come from a single rule.
You state the target as an accuracy and a confidence level. Plus or minus 5 percent at 95 percent confidence means: if I repeated this study many times, 19 times out of 20 my mean would land within 5 percent of the true mean. That pairing is the convention in the textbooks (Barnes, Freivalds and the ILO all work their examples at 5 percent), and it is the default in our time study sample size calculator.
What each extra cycle buys, for element 3
Example numbers5 cycles
±19.5%
10 cycles
±11.2%
15 cycles
±8.7%
20 cycles
±7.3%
30 cycles
±5.9%
40 cycles
±5.0%
- Mean of the readings
- Target: ±5% of the mean
- 95% band, wider than the target
- Inside the target
The plus or minus band around the mean of element 3 at 95 percent confidence, if its spread stays the same: 5 cycles give plus or minus 19.5 percent, 10 cycles give plus or minus 11.2 percent, 15 cycles give plus or minus 8.7 percent, 20 cycles give plus or minus 7.3 percent, 30 cycles give plus or minus 5.9 percent, 40 cycles give plus or minus 5.0 percent.
The number is worked out for each element, not for the cycle. Since every element is timed in every cycle, the element that needs the most readings decides how long you stand there.
Before any readings: the General Electric guide
When you are planning the study you have no readings, so you cannot use a formula. The usual planning number comes from a table that depends only on how long the cycle is. The ILO's Introduction to Work Study prints it as its Table 15 and says that some authors, and companies such as General Electric, adopted it as a conventional guide; the ILO credits it to A. E. Shaw in Maynard's Industrial Engineering Handbook. Freivalds prints the same guide as coming from the time study manual of General Electric's Erie Works.
| Minutes per cycle, up to | Seconds per cycle, up to | Cycles to time |
|---|---|---|
| 0.10 | 6 | 200 |
| 0.25 | 15 | 100 |
| 0.50 | 30 | 60 |
| 0.75 | 45 | 40 |
| 1.0 | 60 | 30 |
| 2.0 | 120 | 20 |
| 5.0 | 300 | 15 |
| 10.0 | 600 | 10 |
| 20.0 | 1,200 | 8 |
| 40.0 | 2,400 | 5 |
| Over 40 | Over 2,400 | 3 |
Source: ILO, Introduction to Work Study, 4th edition, Table 15 (after A. E. Shaw in Maynard's Industrial Engineering Handbook). The seconds column is the minutes column multiplied by 60.
Read down the table and the logic is clear: it trades cycles against observing time. Each of the first six rows comes to between 20 and 40 minutes at the bench (200 cycles of 0.10 minutes is 20 minutes; 20 cycles of 2 minutes is 40). Short cycles are cheap to watch, so you watch many. Long cycles are expensive, so you settle for few and accept a rougher answer.
What the table cannot know is how steady your job is. It gives the same 30 cycles to a 50 second machine-paced operation and to 50 seconds of hand assembly. Freivalds calls it an approximate guide and says a more accurate number comes from statistics. Use it to book the time and brief the operator, then check it with the formula once you have readings.
Other rules of thumb, and whose they are
- Barnes: take 5 or 10 readings, then read the number needed from his table of range over mean. This is a pilot followed by a calculation, not a fixed count.
- The ILO: its worked example starts from 5 preliminary readings and then applies its formula. Again a pilot, not a count.
- Ten cycles: our own time study sheet has ten columns, as many observation forms do. Ten is a sensible pilot for a short job. It is a form layout, not a statistical rule, and the worked example below shows a job where ten is enough for three elements and far short for one.
After a pilot: the statistical formula
Time a pilot of 5 to 10 cycles. For each element work out the mean and the standard deviation of its readings, then apply the formula Freivalds gives in Niebel's Methods, Standards, and Work Design.
| Symbol | What it is | Where it comes from |
|---|---|---|
| n | Cycles needed in total, pilot included | The answer. Round it up. |
| s | Standard deviation of the pilot readings of this element | The sample standard deviation, with n minus 1 in the denominator (STDEV.S in a spreadsheet) |
| mean | Mean of the pilot readings of this element | Sum of the readings divided by how many there are |
| k | The accuracy you want, as a fraction of the mean | 0.05 for plus or minus 5 percent, 0.10 for plus or minus 10 percent |
| t | A multiplier for the confidence level and the size of the pilot | The t table, two-sided, at the number of pilot readings minus 1 degrees of freedom |
The formula is the confidence interval for a mean turned around. The interval is mean plus or minus t × s ÷ √n. Set the plus-or-minus part equal to k × mean, solve for n, and you have it.
t or z?
With a large sample the multiplier is z from the normal distribution: 1.645 for 90 percent confidence, 1.96 for 95 percent, 2.576 for 99 percent. A pilot of ten readings is not a large sample. Its standard deviation is itself a rough estimate, and t is larger than z to allow for that. Freivalds says to use t whenever there are fewer than 30 readings, which in a time study pilot is always.
| Pilot readings | Degrees of freedom | t | Effect on n against z = 1.96 |
|---|---|---|---|
| 5 | 4 | 2.776 | About double |
| 10 | 9 | 2.262 | About a third more |
| 15 | 14 | 2.145 | About a fifth more |
| 20 | 19 | 2.093 | About 14 percent more |
| 30 | 29 | 2.045 | About 9 percent more |
| Large | 1.960 | The same |
Standard t table values. The last column is (t ÷ 1.96)², since n depends on the square of the multiplier.
Because n depends on the square of everything, two shortcuts are worth knowing. Halving the variation cuts the cycles to a quarter. And loosening the accuracy from plus or minus 5 percent to plus or minus 10 percent also cuts them to a quarter, which Barnes states as a rule: for 10 percent precision, divide the number by 4.
Cycles needed rise with the square of the variation
Two older versions of the same idea
Before calculators, the same sum was packaged so it could be done on the study board. You will meet both versions in older studies and in exam questions, and the calculator shows both next to the main answer.
The ILO formula
The ILO prints n = (40 × √(n′ × Σx² minus (Σx)²) ÷ Σx)², where n′ is the number of pilot readings, Σx is their sum and Σx² is the sum of their squares. It is fixed at plus or minus 5 percent and a confidence level of 95.45 percent, which is exactly two standard errors. The 40 is 2 divided by 0.05. The ILO's own example takes five readings of 7, 6, 7, 7 and 6 hundredths of a minute and gets 8.81, so 9 readings.
It uses 2 where the t table would say 2.776 for five readings, so it gives a smaller number than the t version from the same pilot. Treat it as the least you should time, not the most.
Barnes's range method
Barnes avoids the standard deviation altogether. Take the range R of the pilot (largest reading minus smallest), divide by the mean, and estimate the spread as R ÷ d2, where d2 is a constant from quality control tables: 2.326 for a pilot of 5 and 3.078 for a pilot of 10. That gives n = (40 × R ÷ (d2 × mean))², again at plus or minus 5 percent and two standard errors. His book prints the results as a table that analysts kept on the board.
The range uses only two of the readings, so one odd cycle moves the answer a lot. It is quick, and it is rough.
A worked example: seven elements, ten pilot cycles
Illustrative example. An operator assembles and leak-tests a gear pump cover in a cycle of about 0.77 minutes (46 seconds). The job is split into seven elements in how to break a job into elements. At the planning stage the General Electric guide gives 30 cycles, because the cycle falls in the row for up to 1.0 minute. The analyst times a pilot of 10 cycles and applies the formula to each element at plus or minus 5 percent and 95 percent confidence, with t = 2.262 for ten readings.
| Element | Mean (min) | Std deviation (min) | Variation (s ÷ mean) | Formula result | Cycles needed |
|---|---|---|---|---|---|
| 1. Seat housing | 0.080 | 0.0067 | 8.3% | 14.2 | 15 |
| 2. Gasket and cover | 0.110 | 0.0067 | 6.1% | 7.5 | 8 |
| 3. Start four bolts by hand | 0.145 | 0.0227 | 15.7% | 50.3 | 51 |
| 4. Run down bolts | 0.170 | 0.0115 | 6.8% | 9.4 | 10 |
| 5. Start test, label | 0.070 | 0.0067 | 9.5% | 18.6 | 19 |
| 6. Wait for test | 0.130 | 0.0067 | 5.1% | 5.4 | 6 |
| 7. Unload | 0.061 | 0.0057 | 9.3% | 17.7 | 18 |
Each result is (2.262 × s ÷ (0.05 × mean))², rounded up. Computed from the unrounded standard deviations.
Ten cycles were already enough for elements 2, 4 and 6. Four elements need more, and one of them needs far more. The study runs to 51 cycles because of element 3, starting four bolts by hand.
Same ten cycles, two very different answers
Example numbers4Run down four bolts with the nutrunner
0.170
Mean, min
6.8%
Variation, s ÷ mean
10
Cycles needed
3Start four bolts by hand
0.145
Mean, min
15.7%
Variation, s ÷ mean
51
Cycles needed
Element 4, Run down four bolts with the nutrunner: readings from 0.15 to 0.19 minutes, mean 0.170, standard deviation 0.0115, needs 10 cycles. Element 3, Start four bolts by hand: readings from 0.12 to 0.19 minutes, mean 0.145, standard deviation 0.0227, needs 51 cycles
Element 3 by every method
The ten readings of element 3 are 0.14, 0.12, 0.17, 0.13, 0.15, 0.19, 0.12, 0.14, 0.16 and 0.13 minutes. Their sum is 1.45, the mean is 0.145, the sum of squares is 0.2149, the standard deviation is 0.02273 and the range is 0.19 minus 0.12 = 0.07.
| Method | Working | Result | Cycles |
|---|---|---|---|
| Statistical formula with t | (2.262 × 0.02273 ÷ (0.05 × 0.145))² | 50.3 | 51 |
| Statistical formula with z | (1.96 × 0.02273 ÷ (0.05 × 0.145))² | 37.8 | 38 |
| ILO formula | (40 × √(10 × 0.2149 minus 1.45²) ÷ 1.45)² | 35.4 | 36 |
| Range method (Barnes) | (40 × 0.07 ÷ (3.078 × 0.145))² | 39.4 | 40 |
| General Electric guide | Cycle of 0.77 min: row for up to 1.0 | 30 |
The first four are fixed at plus or minus 5 percent. The t and z rows are at 95 percent confidence, the ILO and range rows at 95.45 percent. Paste the ten readings into the calculator and it returns the same five numbers.
Five answers for element 3, start 4 bolts
Example numbersStatistical formula with t: 51 cycles. Range method (Barnes): 40 cycles. Statistical formula with z: 38 cycles. ILO formula: 36 cycles. General Electric guide: 30 cycles.
Quote the t answer, 51. The others are there to show that the spread between methods (36 to 51) is small next to the spread between elements (6 to 51). Which formula you pick matters much less than whether you looked at each element.
Then do what the ILO says to do next: time the extra 41 cycles, put all 51 readings back through the formula, and check again. The mean and the standard deviation will have moved, and t is smaller for a bigger sample, so the second answer is usually a little lower than the first. Stop when the readings you have are at least the readings you need.
The procedure, step by step
- 1
Decide the accuracy and confidence the decision needs
Plus or minus 5 percent at 95 percent confidence is the textbook default and suits a standard that will be used for pay, costing or a line balance. A first look at a job that is about to be redesigned can live with plus or minus 10 percent.
- 2
Get a planning number from the General Electric guide
Estimate the cycle time, find its row and book that much observing time. Tell the operator and the supervisor how long you expect to be there.
- 3
Time a pilot of 5 to 10 cycles
Time every element in every cycle. Circle any reading with a known cause, such as a dropped part or an interruption, and write the cause down.
- 4
Work out the mean and standard deviation of each element
Leave out only the circled readings with a recorded cause. Use the sample standard deviation.
- 5
Apply the formula to each element
Use t for the number of readings you have. Round up. The calculator does this from pasted readings and shows the working.
- 6
Take the largest answer and look hard at it
If one element is far above the rest, find out why before you time more. The next section covers what to check.
- 7
Time the remaining cycles and recalculate
Put all the readings through the formula again. If you now have at least as many as it asks for, stop. If not, time the difference and check once more.
What to do when one element varies too much
A large answer is a finding about the job before it is an instruction to keep timing. Work through these in order.
- Check the break points. If the end of the element is hard to see, part of the scatter is the observer's, not the operator's. Tighten the break point and time a few more.
- Check the watch against the element. Readings of 0.05, 0.06 and 0.07 on a 0.06 minute element vary by a sixth just from rounding to the nearest 0.01. Elements 5 and 7 in the example are this case. Combine the element with a neighbour, or time it from video.
- Look for two methods. Readings that fall in two clumps usually mean the operator does the element two ways, or two part variants are mixed. Split the data, or fix the method first.
- Look for a cause in the long readings. If the three longest all have a note beside them (bolt cross-threaded, gasket stuck to the liner), the variation has a name, and removing the cause is worth more than measuring it precisely.
- Ask whether the element is variable by nature. If the time moves with bolt count or part size, it needs a study across that range, not more cycles on one part.
- Only then decide between more cycles and less accuracy. At plus or minus 10 percent, element 3 needs 13 cycles in place of 51. That may be good enough for a line balance. It is not good enough for a piece rate.
It also matters how much of the cycle the element is. Element 3 is 0.145 of 0.766 minutes, about a fifth. A 10 percent error on a fifth of the cycle moves the total by about 2 percent. That is a judgement to make openly and write on the study, not a reason to ignore the formula.
Do not solve it by deleting the readings you do not like. The ILO is explicit that the statistics hold only if the variation is due to chance and is not introduced on purpose, and a study with its high readings trimmed away will pass the formula and still be wrong. Time study mistakes covers how that shows up later.
What the number of cycles cannot fix
The formula answers one narrow question: is the mean of these readings close to the true mean for this operator, on this day, using this method? More cycles make that answer better. They do nothing for the questions around it.
- The wrong operator. Fifty cycles of the fastest person on the line is a precise measure of the fastest person on the line.
- One sitting. Fifty cycles in the first hour of Monday's day shift say nothing about the last hour of a night shift. Spread the readings over the conditions the standard has to cover. How to plan a time study covers that.
- Rating. The formula treats the readings as facts. The pace rating applied afterwards has its own error, and no number of cycles reduces it.
- Occasional elements. A tote change that happens once in 24 cycles is seen twice in a 51 cycle study. Its time and its frequency need their own evidence.
- A method that is still changing. If the operator is still learning, or the layout is about to move, the readings describe a job that will not exist next month.
If the question is where a whole team's day goes, across many tasks, counting cycles is the wrong tool. That is a work sampling study, and it has its own sample size formula.
Do the sums with the calculator
The time study sample size calculator uses the methods on this page and nothing else. Paste the readings of one element (or type its mean and standard deviation), choose 90, 95 or 99 percent confidence and the accuracy, and it returns the t answer with the working shown, the z answer, the ILO formula, the range method for 2 to 10 pasted readings, the accuracy your readings already give, and the General Electric guide if you enter the whole cycle time. It also shows the reading furthest from the mean and the answer without it, and leaves the decision about that reading to you.
Counting cycles is cheaper from video, because the readings come from footage and not from an hour at the bench. In LeanSuite Time and Motion Study the AI times every element and every cycle in the video you film, so a longer study costs more filming and not more hours with a watch. You still decide how many cycles the job needs, and which shifts and operators they should come from.
Time and motion study software
Run a time study in LeanSuite
Time and motion study software that works from phone video: LeanSuite times every element, gives cycle and standard time, and draws a Yamazumi chart.
Go deeper
This page is the short version. These guides cover each part in full.
- Standard Work Tools: Combination Sheet, Standardized Work Chart, Job BreakdownThe documents the timed elements feed once the study has enough cycles.
- The Three Elements of Standard Work: Takt Time, Work Sequence, Standard WIPHow observed and timed work is loaded against takt time.
- Yamazumi Chart: What It Is and How to Make One in 7 StepsWhat the element times are used for next: stacking each operator's work against takt.
- Auditing Standard Work: Verification and Compliance ChecksChecking later that the job is still done the way it was timed.
All our articles on this subject are in the standard work, sops and training topic.
Free templates and tools
- Time study sheetTime each element over 10 cycles and work out the average, lowest repeatable and standard time. Excel does the sums.
- Video time study filming checklistA pre-shoot checklist and shot log for filming a time study on video: camera, light, people, settings, power and review.
- Standard work combination tableOne operator's manual, machine, walk and wait time on a time chart against takt, with machine cycles and a process capacity sheet.
- Time study sample size calculatorHow many cycles of an element to time, from your first readings, with the t formula, the ILO formula and the range method.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
- Takt time calculatorThe pace a line must hit to meet customer demand, from shift time, breaks and daily demand.
Doing this in LeanSuite
Time and Motion Study
Film the station and the AI times every element on a timeline that links to the video, split into value-added, necessary and waste.
See Time and Motion StudyAI Video Analysis
Turns video of real work into time studies, line balance charts, changeover splits and other studies you review and certify.
See AI Video Analysis
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about how many cycles to time
Enough that the mean of the most variable element is within your target accuracy, usually plus or minus 5 percent at 95 percent confidence. As a planning number, the General Electric guide suggests 30 cycles for a job of up to 1 minute and 15 for up to 5 minutes. After a pilot of 5 to 10 cycles, the statistical formula gives the number for your job.
n = (t × s ÷ (k × mean))², from Freivalds. s is the standard deviation of the pilot readings, mean is their average, k is the accuracy as a decimal (0.05 for plus or minus 5 percent) and t is the two-sided t value for the confidence level at the number of pilot readings minus 1. With 30 or more readings, z replaces t: 1.96 at 95 percent.
Sometimes. Ten cycles are enough for an element whose times vary by about 7 percent of the mean or less, at plus or minus 5 percent and 95 percent confidence. They are not enough for hand work that varies more. In the worked example on this page, ten cycles are enough for three of seven elements, and one element needs 51.
A guide to the number of cycles by the length of the whole cycle: 200 cycles for up to 0.10 minutes, 100 for 0.25, 60 for 0.50, 40 for 0.75, 30 for 1, 20 for 2, 15 for 5, 10 for 10, 8 for 20, 5 for 40 and 3 for longer. The ILO prints it as Table 15 of Introduction to Work Study. It ignores how variable the job is.
Because the pilot is small. With 5 or 10 readings the standard deviation is only an estimate, and the t distribution allows for that by using a larger multiplier: 2.776 for 5 readings and 2.262 for 10, against 1.96 for z at 95 percent confidence. Freivalds uses t for fewer than 30 readings. Using z on a small pilot understates the cycles needed.
n = (40 × √(n′ × Σx² minus (Σx)²) ÷ Σx)², where n′ is the number of preliminary readings, Σx their sum and Σx² the sum of their squares. It is fixed at plus or minus 5 percent and a 95.45 percent confidence level, and the 40 is 2 divided by 0.05. The ILO's example of readings 7, 6, 7, 7, 6 gives 8.81, so 9.
Treat it as a sign that something is wrong with the element before you time more. Check that the break points are clear, that the watch can resolve an element that short, that two methods or two part variants are not mixed, and whether the long readings share a cause. If the element is sound and simply variable, decide between more cycles and a wider accuracy.
The one that needs the most. Every element is timed in every cycle, so the study has to run until the most variable element has enough readings. The ILO says to base the sample size on the element that calls for the largest sample. It is often a short hand-fitting element, not the longest one.
Related guides and tools
- Time study sample size calculator: paste readings, get the number of cycles
- How to break a job into elements: the seven elements used in this example
- How to conduct a time study: the full procedure
- Stopwatch time study: taking the readings, continuous or snap-back
- Time study mistakes: too few cycles and eleven others
- Work sampling: the sample size formula for random observations
- Standard time: what the mean element times become
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk
Or browse the topics, the full library and the lean glossary.
Rather see it on your own problem?
Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.