The new product time study playbook: seven studies from quote to steady state

Short answer

Time a new product seven times, not once: estimate it at quote, time the prototype, film the pilot run, check launch week, study it at day 30, set the standard at day 90, then re-study after every change. Each study answers one decision.

A new product has no single cycle time. It has an estimate, then a prototype time, then a line that starts slow and speeds up. The playbook runs seven short studies at fixed points, each with its own method and its own decision: the quote, the design, the release to production, ramp staffing, the first balance, the locked standard, and every change after that. In the example below the estimate was 482 seconds, the first pilot units took 1,200, and the standard was locked at 528 on day 90.

Last reviewed:

Why a new product needs seven studies, not one

Seven studies, one launch: when each happens and what it found

Example numbers
The seven studies on a calendarA calendar axis from 48 weeks before start of production to week 26. Study 1, Estimate at quote, at 44 weeks before: 482 s. Study 2, Prototype timing, at 26 weeks before: 539 s. Study 3, Pilot run, at 6 weeks before: 1,200 s observed. Study 4, Launch week, at start of production: 850 s observed. Study 5, Day 30 study, at week 4: 628 s observed. Study 6, Day 90 study and lock, at week 13: 528 s. Study 7, Re-study after a change, at week 22: 541 s.Start of production40 wk beforeWk 201234567
  • Nothing to time yet: estimate
  • Bench builds and mock-ups: time them
  • The line runs: film it
  1. Estimate at quote

    482 s

    range 430 to 562

  2. Prototype timing

    539 s

    was 566 before a design change

  3. Pilot run

    1,200 s

    observed, working standard 548 s

  4. Launch week

    850 s

    observed, plan said 814 s

  5. Day 30 study

    628 s

    observed, plan said 608 s

  6. Day 90 study and lock

    528 s

    standard locked

  7. Re-study after a change

    541 s

    new standard, revision B

  8. Two numbers, not one

    Studies 1, 2, 6 and 7 give the standard: what a trained operator needs. Studies 3, 4 and 5 show what this team needs today while it learns.

A calendar axis from 48 weeks before start of production to week 26. Study 1, Estimate at quote, at 44 weeks before: 482 s. Study 2, Prototype timing, at 26 weeks before: 539 s. Study 3, Pilot run, at 6 weeks before: 1,200 s observed. Study 4, Launch week, at start of production: 850 s observed. Study 5, Day 30 study, at week 4: 628 s observed. Study 6, Day 90 study and lock, at week 13: 528 s. Study 7, Re-study after a change, at week 22: 541 s.

The first two studies happen before there is a line to watch, so they are estimates and bench timings. From the pilot on, every study is a film of the real stations. The standard is set at study 6, about 13 weeks after start, and reopened whenever the job changes. Takt stays at 120 s throughout.

Most plants time a new product once. Someone estimates it for the quote, and that number goes into the price, the headcount and the schedule. Nobody looks again until the line is missing its target, and by then the estimate has become the standard by default.

The trouble is that the answer keeps moving. The design changes after the quote. The first fixtures are not the final ones. New operators start slow and speed up for weeks. A single time study taken at any one of those moments is right for that moment only.

So treat timing as a routine with seven fixed points. Each study is small, each uses the cheapest method that can answer its question, and each one ends in a decision somebody has to make anyway.

  • Before the line exists, you cannot observe anything. You estimate from similar parts and predetermined times, and you report a range.
  • Once there is something to build, you time it, even if it is a bench prototype or a cardboard mock-up.
  • Once the line runs, you measure two different things: how long the method takes a trained person (the standard) and how long it takes this team today (the learning curve).
  • Once the standard is set, it belongs to one method. Change the method and you owe the job a new study.

The seven studies at a glance

The dates below count from start of production. Move them to fit your launch, but keep the order and keep all seven. The names are ours; the practice of estimating first, proving on a pilot run and setting the standard only when the work is stable is long-standing industrial engineering.

  1. 1

    Estimate at quote

    No part exists. Build the time from similar parts, your element library and a predetermined time system. Report a range with the assumptions written down. It feeds the price and the first headcount.

  2. 2

    Prototype or mock-up timing

    Time the first hand-built units and a mock-up of the station. This is the cheapest moment to change the design, so list every element that is slow because of the part, not the person.

  3. 3

    Pilot run or line trial

    Film every station on the real equipment with production operators. It tells you whether the line can be released, how to balance it and where the learning curve starts. It does not give you a standard.

  4. 4

    Launch week

    Count output every hour and film each station once or twice. Compare with the ramp plan and move the trainer and the extra hands to the station that is furthest behind.

  5. 5

    Day 30 study

    The operators are practised enough to rate. Run the first proper time study, rebalance the line, and decide whether the extra ramp labour can go.

  6. 6

    Day 90 study and standard lock

    Run a full study to your plant's normal accuracy, review it with the operators and the supervisor, and lock the standard. From here it is used for costing, capacity and scheduling.

  7. 7

    Re-study after every change

    An engineering change, a new fixture, a layout move or a new takt each open the standard again. Study the changed elements, update the standard and give it a revision and a date.

The seven studies: when, the question and the decision each one feeds
StudyWhenThe questionThe decision it feeds
1. Estimate at quoteBefore the order is wonAbout how much work is in one unit?Price, number of stations, capital
2. Prototype timingFirst hand-built unitsWhat did the estimate miss, and what can the design still fix?Design changes, process plan, fixture orders
3. Pilot runReal line, weeks before startCan this line make good parts, and how far from rate is it?Release to production, balance, ramp staffing
4. Launch weekFirst week of productionAre we on the ramp plan?Where the trainer and extra labour go
5. Day 30About 21 working days inWhat does a practised operator need?First balance, release of ramp labour
6. Day 90About 64 working days inWhat is the standard?Standard locked for costing and capacity
7. After a changeEvery change to part, tool, layout or taktWhat did the change do to the time?Revised standard and rebalance

Which method fits which stage

There are five ways to get a time, and each stage can only use some of them. You cannot film a station that has not been built. You should not pay for a predetermined time analysis of a job you can film tomorrow.

Method by stage
MethodWhat it isFits best atWeak when
Similar-part history and element libraryTimes you already hold for the same or nearly the same elements on other productsQuote, and any element carried over unchangedThe new part differs in ways the old times cannot show
Predetermined time system (MTM, MOST and others)A published table gives a time for each basic motion, so a job can be timed from a drawing or a method descriptionQuote and prototype, for elements nobody has done yetProcess time, machine time and anything where the method is still a guess
StopwatchAn observer times each element over several cycles on a sheetPrototype benches, one station at a timeSeveral stations at once, short elements, and when the result will be argued about later
VideoFilm the work and time the elements from the recordingPilot, launch, day 30, day 90 and every re-studyWork spread over a large area or hidden from the camera
Work sampling and output countsRandom looks that give the share of time in each activity, and units made per hourLaunch week and ramp, to see where time is lostSetting an element time. It gives shares, not seconds per element

The figure after this table shows the same thing by study. For the procedure behind each method see [how to conduct a time study](/learn/how-to-conduct-a-time-study) and [work sampling](/learn/work-sampling).

Method by stage: what you can use at each of the seven studies

  • Similar-part history and element library · times you already hold: Quote main method, Prototype supporting, Change supporting

  • Predetermined time system · MTM, MOST: timed from a drawing: Quote main method, Prototype supporting, Change supporting

  • Stopwatch · one station, on a sheet: Prototype main method, Day 30 supporting, Day 90 supporting

  • Video · film it, time it, keep it: Prototype supporting, Pilot main method, Launch main method, Day 30 main method, Day 90 main method, Change main method

  • Work sampling and output counts · where the time goes: Pilot supporting, Launch main method, Day 30 supporting

  • Main method
  • Supporting

1 Quote · 2 Prototype · 3 Pilot · 4 Launch · 5 Day 30 · 6 Day 90 · 7 Change

A grid of five timing methods against the seven studies. History and predetermined times are the main methods at the quote. Stopwatch is the main method at the prototype. Video is the main method from the pilot to every re-study. Work sampling and output counts are a main method in launch week.

Read down a column to plan a study. Before the line exists the left-hand methods are all you have. Once it runs, video takes over because the recording can be checked and compared later.

Video earns its place from the pilot onward for one reason: you keep the recording. When the day 90 number is questioned, or when a change arrives in month five, you can put the old film beside the new one and see exactly which element moved.

Each study in detail: purpose, method, who, record, decision, output

Study 1: the estimate at quote

The customer wants a price and the product is a drawing. You are estimating work content, the total hands-on time in one unit. The full method is in how to estimate cycle time for a new product.

  • Purpose: a work content figure good enough to price the labour and count the stations.
  • Method: similar-part history first, the element library next, a predetermined time system for anything new.
  • Who: the industrial engineer or estimator, with the design engineer in the room to say what the drawing does not.
  • Recorded: the element list, the basis for every time, a low, likely and high figure, and the assumptions (volume, shifts, tooling, level of automation).
  • Decision: the quoted labour, the number of stations and the capital request.
  • Output: an estimate sheet that shows a range, not one number.

Study 2: prototype or mock-up timing

The first units are built by hand, usually by engineers, on a bench that looks nothing like the line. The times are rough. What matters is that real hands are on real parts for the first time, and they will find what the drawing hid.

  • Purpose: test the estimate element by element and catch design problems while a change still costs little.
  • Method: stopwatch or phone video on the bench builds. A cardboard or plywood mock-up of the station for reach and layout. Predetermined times for elements the final tooling will change.
  • Who: the industrial engineer, the design engineer and one experienced operator doing the build.
  • Recorded: element times, and beside each one what made it slow: hard to grip, hard to see, no lead-in, needs two hands, awkward posture.
  • Decision: design changes, the process plan and the fixture orders.
  • Output: an updated work content sheet, a design feedback list and the first process plan.

Study 3: the pilot run or line trial

Now the line exists: production tooling, production operators, production parts. In automotive this is the significant production run, which the AIAG PPAP manual sets at one to eight hours and at least 300 consecutive parts unless the customer agrees otherwise. Other industries run fewer. Either way, film it. See pilot run and line trial for what to record.

  • Purpose: prove the line can make good parts, find the station that holds it back, and fix the starting point of the learning curve.
  • Method: video of every station at the same time, plus an hourly output count and a log of every stop.
  • Who: the industrial engineer and process engineer, with the supervisor, quality and the operators who will run the line.
  • Recorded: station cycle times by element, stops and their causes, first-pass yield, and where operators wait, search or struggle.
  • Decision: release to production or not, the first balance, and how many people the ramp needs.
  • Output: a pilot report, a first Yamazumi chart and a ramp plan.

Do not set a standard from pilot times. The operators have done the job a few dozen times. Rating someone who is still learning is guesswork, and a standard built on it will be wrong in a direction nobody can predict.

Study 4: launch week

This one is closer to a daily check than a study. The question is narrow: is the line following the ramp plan, and if not, which station is the reason?

  • Purpose: catch a ramp that is falling behind while a week of output can still be recovered.
  • Method: output per hour against the plan, one short video per station midweek, and work sampling if the team seems busy but output is low.
  • Who: the supervisor owns the count. The industrial engineer films and compares.
  • Recorded: units per hour, station cycle times against the planned curve, stop reasons.
  • Decision: where the trainer stands tomorrow, where the extra operator works, which fixes go first.
  • Output: a one-page ramp tracker, updated daily.

Study 5: day 30

After about a month the core operators have done several thousand cycles. They are steady enough to rate, so this is the first study that follows the full time study procedure.

  • Purpose: a first trustworthy figure for what a practised operator needs, and a check of the curve.
  • Method: a rated study of each station, by video or stopwatch, over enough cycles for your accuracy target.
  • Who: the industrial engineer, with the operators and supervisor reviewing the element list.
  • Recorded: element times, ratings, abnormal readings and their causes, and the improvement ideas the operators raise.
  • Decision: rebalance, release or keep the extra ramp labour, and which method improvements to make before day 90.
  • Output: a provisional standard, revised standard work sheets and an updated balance.

Study 6: day 90 and the standard lock

By now the method has stopped changing every week. This is the study that sets the standard time: the number costing, capacity planning and scheduling will use until something changes.

  • Purpose: a standard that will stand up when it is questioned.
  • Method: a full study with the number of cycles your plant requires, rating at the bench, and the agreed allowances.
  • Who: the industrial engineer runs it. Operators and the supervisor review it. Production and finance sign it.
  • Recorded: complete observation sheets or certified video studies, filed with the method, layout, tools and date.
  • Decision: lock the standard and the steady-state headcount.
  • Output: the standard time record, final standard work, the final Yamazumi chart, and updates to the PFMEA and control plan where the method changed.

Study 7: re-study after every change

A standard describes one method on one layout with one set of tools. The list of triggers is short and worth posting: an engineering change to the part, a new or modified tool or fixture, a layout move, a material or supplier change that alters handling, a new takt that forces a rebalance, and any improvement that changes the method. Add a calendar review as well (once a year is a common choice) to catch the slow drift nobody reported.

  • Purpose: keep the standard true to the job as it is done now.
  • Method: study only the elements that changed. Video is quickest because you can compare with the day 90 recording.
  • Who: the industrial engineer, started by whoever approves the change.
  • Recorded: the changed elements before and after, and the reason for the change.
  • Decision: the revised standard, and a rebalance if any station now sits too close to takt.
  • Output: the standard at a new revision with its date, and matching updates to the work instruction, PFMEA and control plan.

Worked example: one pump through all seven studies

The product is made up, but the arithmetic is real. A plant that builds a small coolant pump, the CP-30, is asked to quote its successor, the CP-40: one more gear, a new shaft seal and an electrical connector. Final assembly is manual.

  • Demand at steady state: 225 pumps a day.
  • Available time: one shift of 450 minutes after breaks, which is 27,000 seconds.
  • Takt time: 27,000 / 225 = 120 seconds. It stays fixed through the whole example.
  • Allowance: 12 percent, the plant's agreed figure, added as standard = normal time x 1.12.
  • Operators needed = work content / takt, rounded up.
Illustrative: the CP-40 through the seven studies
StudyWhat was measuredResultOperators at 120 s taktDecision
1. QuoteEstimate from CP-30 times and predetermined times482 s, range 430 to 562 s4.0, range 3.6 to 4.7. Plan 5Quote 5 operators on 5 stations
2. Prototype5 bench builds timed by element566 s. After a design change, 539 s4.7, then 4.5. Plan 5Cover goes from 8 screws to 6. Loose cable clip becomes a moulded one
3. Pilot60 units on the real line, all 5 stations filmed1,200 s a unit near unit 50. Working standard 548 s5 stations, 6 operators for the rampRelease with a 90 percent learning curve as the ramp plan
4. Launch weekHourly output, video on day 4850 s near unit 640. Plan said 814 s6Trainer moved to station 2, the furthest behind
5. Day 30First rated study of each station628 s near unit 4,400. Plan said 608 s. Provisional standard 536 s6, kept one more week5 operators at 628 s make about 215 a day, short of 225
6. Day 90Full rated study, 20 cycles a station462 s observed at rating 102 = 471 s normal. Standard 528 s4.4. Plan 5Standard locked at 528 s, revision A
7. ChangeStation 4 filmed after a connector change12 s of normal time added. Standard 541 s4.5. Plan 5Revision B. One 7 s element moved from station 4 to station 1

Times on the line (studies 3 to 5) are the five stations' average cycle times added together, with the 12 percent allowance added so they compare directly with the standard.

What happened to the work content

The estimate said 482 seconds. On its own that is 4.0 operators, and someone will always suggest quoting four and finding the last two seconds later. The range said 3.6 to 4.7, so the plant quoted five. That decision held through every later study.

The prototype came in at 566 seconds, just above the top of the range. The estimate had no line for routing the connector cable through a clip, because the clip was not on the drawing yet. A range covers the uncertainty in what you estimated. It cannot cover an element you left out. At 566 seconds five operators would be 94 percent loaded with 34 seconds of slack between them, so the team asked for two design changes, which brought it to 539.

The pilot added 8 seconds of normal time for connecting the test fixture, giving a working figure of 548. Day 30 trimmed it to 536 and day 90 to 528 as the operators and engineers took small wastes out of the method. Then a connector change in week 22 put 13 seconds back.

The standard after each study, against what four and five operators can absorb

Example numbers
Standard work content after each studyChart of the standard work content after each study, in seconds. Quote 482 with a range of 430 to 562. Prototype 566, then 539 after a design change. Pilot 548. Launch week unchanged. Day 30 536. Day 90 528, locked. After the change 541. Five operators at a 120 second takt can absorb 600 seconds and four can absorb 480.4404805205606005 operators = 600 s4 operators = 480 s562430566482 likely1539254835484536552865417Standard work content, seconds per unit

1 Quote · 2 Prototype · 3 Pilot · 4 Launch · 5 Day 30 · 6 Day 90 · 7 Change

Chart of the standard work content after each study, in seconds. Quote 482 with a range of 430 to 562. Prototype 566, then 539 after a design change. Pilot 548. Launch week unchanged. Day 30 536. Day 90 528, locked. After the change 541. Five operators at a 120 second takt can absorb 600 seconds and four can absorb 480.

Every figure after the quote sits in the shaded band between 480 and 600 seconds, so the answer was always five operators. The likely estimate alone, 482 s, sits on the four-operator line. The range is what made the right call. The hollow dot is the prototype as first built, 566 s, before two design changes took it to 539.

What happened on the line

The standard says what a trained operator needs. The pilot showed what this team needed on day one: 1,200 seconds a unit, more than twice the working standard. The gap between the two is learning, and it closes along a curve.

The plant assumed a 90 percent learning curve, taken from its own earlier launches: each time cumulative output doubles, the time per unit falls to 90 percent of what it was. In the unit form of the model, time at unit n = T1 x n^b, where b = log 0.90 / log 2 = minus 0.152. Anchored on 1,200 seconds at unit 50, T1 is 2,175 seconds and the curve predicts 814 seconds at unit 640, 608 at unit 4,400 and 600, the most five operators can absorb at a 120 second takt, at about unit 4,780.

The launch week and day 30 studies each landed a little above the curve: 850 against 814, then 628 against 608. That was enough to change a decision. The plan had the sixth operator leaving in week five. At 628 seconds five people make about 215 pumps a day, so the sixth stayed another week. Without the day 30 study the line would have dropped to five on the planned date and missed its rate.

The 90% learning curve drawn after the pilot, with the four study points

Example numbers
The learning curve of the example with the study points markedChart of time per unit against cumulative units on a log scale. The planned 90 percent learning curve starts from 1,200 seconds at unit 50, crosses 600 seconds at about unit 4,780 and meets the 528 second standard at about unit 11,080. Observed: Pilot 1,200 seconds near unit 50, Launch week 850 seconds near unit 640, Day 30 628 seconds near unit 4,400, Day 90 528 seconds near unit 14,200.4008001,2001001,00010,000Cumulative units built (log scale)Seconds per unitShaded: six operators needed600 s: 5 x takt528 s: the standard3456
  • Pilot: 1,200 snear unit 50, the anchor
  • Launch week: 850 snear unit 640, plan 814 s
  • Day 30: 628 snear unit 4,400, plan 608 s
  • Day 90: 528 snear unit 14,200, standard locked

Chart of time per unit against cumulative units on a log scale. The planned 90 percent learning curve starts from 1,200 seconds at unit 50, crosses 600 seconds at about unit 4,780 and meets the 528 second standard at about unit 11,080. Observed: Pilot 1,200 seconds near unit 50, Launch week 850 seconds near unit 640, Day 30 628 seconds near unit 4,400, Day 90 528 seconds near unit 14,200.

The line is the plan: a 90% curve through the pilot point (first-unit time 2,175 s), falling until it meets the standard. The numbered points are what studies 3 to 6 measured. Points 4 and 5 sit just above the line, and point 5 is still above 600 s, which is why the sixth operator stayed a week longer than planned.

What happened to the station plan

At the lock the five stations held 104, 110, 108, 100 and 106 seconds of standard work, 528 in all, every one under the 120 second takt. The connector change added 13 seconds to station 4, taking it to 113. That is still under takt, but with only 7 seconds to spare, so the re-study moved a 7 second element (8 seconds with the allowance) to station 1. The stations became 112, 110, 108, 105 and 106: the same 541 seconds, with the tightest station at 112.

The station plan before and after the connector change, against a 120 s takt

Example numbers

Day 90, revision A

528 s

  • S1104 s
  • S2110 s
  • S3108 s
  • S4100 s
  • S5106 s

Tightest station 110 s. Every station under takt.

After the connector change

541 s

  • S1104 s
  • S2110 s
  • S3108 s
  • S4113 s
  • S5106 s

Station 4 takes all 13 s and sits at 113 s.

After the re-study, revision B

541 s

  • S1112 s
  • S2110 s
  • S3108 s
  • S4105 s
  • S5106 s

One element moved from station 4 to station 1. Tightest station 112 s.

Three sets of five station bars against a takt line at 120 seconds. At the lock the stations hold 104, 110, 108, 100, 106 seconds, 528 in total. After the connector change station 4 rises to 113, total 541. After the re-study moved one element from station 4 to station 1 they hold 112, 110, 108, 105, 106, still 541.

The vertical line on each bar is takt. The change put all its extra time on one station, leaving 7 s of slack there. The re-study did not shorten the job. It moved one element so the tightest station has 8 s of slack instead.

How big is the gap between estimate and actual?

There is no honest general answer. We know of no published figure that holds across plants, and anyone quoting one is describing their own factory. The gap depends on how new the product is, how close the similar part really was, who estimated it, and how much the design moved after the quote.

What you can do is measure your own. Here is the example's record against the standard that was finally locked.

Illustrative: each study's figure against the locked standard of 528 s
StudyFigure after the studyGap to the locked 528 sWhy
1. Quote482 s8.7% lowCable routing element missing, seal press underestimated
2. Prototype, as built566 s7.2% highBench method, no fixtures, design not yet changed
2. Prototype, after design change539 s2.1% highMethod improvements still to come
3. Pilot548 s3.8% highTest fixture connection added
5. Day 30536 s1.5% highTwo small wastes not yet removed
6. Day 90528 sLockedThe reference

One product in one made-up plant. Your gaps will differ in size and in direction.

How far each study's figure was from the locked 528 s

Example numbers
  • 1 Quote482 s · 8.7% low
  • 2 Prototype, as built566 s · 7.2% high
  • 2 After design change539 s · 2.1% high
  • 3 Pilot548 s · 3.8% high
  • 5 Day 30536 s · 1.5% high
  • 6 Day 90, locked528 s · reference

Bars showing each study's figure as a percentage above or below the locked standard of 528 seconds. 1 Quote: 482 seconds, 8.7 percent low. 2 Prototype, as built: 566 seconds, 7.2 percent high. 2 After design change: 539 seconds, 2.1 percent high. 3 Pilot: 548 seconds, 3.8 percent high. 5 Day 30: 536 seconds, 1.5 percent high. 6 Day 90, locked: 528 seconds, the reference.

Bars to the left were too low, bars to the right too high. In this example the quote was the only figure below the final standard, and the error shrank at every study. Keep the same chart for each of your launches: its shape is your plant's estimating habit.

Keep this table for every launch. After three or four you will know two things no textbook can tell you: which way your quote estimates lean, and by how much. That is the correction to apply to the next quote, and it is the best argument for the playbook. A plant that studies only once never finds out how wrong the first number was.

Notice the other gap in the example, the one between the standard and the first real units: 548 against 1,200. That is not estimating error. It is learning, and it belongs in the ramp plan, not in the standard.

How the studies feed line balancing, standard work, the PFMEA and the control plan

The element list is the most reused thing a time study makes. The same list of steps, in the same order with the same names, sits under four other documents. If each is written separately they drift apart within a month. If they share the element list, a change to one shows up as a change owed to the others.

One element from the study, and what four documents take from it

Example numbers

Element 7 on the study sheet, station 2

Press the shaft seal into the housing

Starts when the hand touches the seal. Ends when the press ram returns.

Normal time

36 s

Seen on film

Seal re-seated on 2 of 20 cycles

  • Line balance

    Takes: The time

    Station 2 carries it: 110 s of a 120 s takt

  • Standard work

    Takes: The step and its key point

    Step 4. Key point: seal square to the bore before pressing

  • PFMEA

    Takes: What the film showed going wrong

    Failure mode: seal lip folded. Seen on 2 of 20 cycles

  • Control plan

    Takes: The check and where it sits

    Leak test on every unit at station 5. Reaction: hold and tag

A diagram of one timed element, press the shaft seal, feeding four documents. The line balance takes the time. Standard work takes the step and its key point. The PFMEA takes the failure seen on film. The control plan takes the check and where it sits.

Each document copies something different from the same row. When the method changes at study 7, the row changes once and all four are owed an update with the same revision.
One element list, four documents
DocumentWhat it takes from the studyWhich study first fills itWhat reopens it
[Line balance](/learn/line-balancing)Element times and the order they must happen inStudy 1 as a station count, study 3 as a real balanceA new takt, a changed element time, a station over takt
[Standard work](/learn/standard-work)The sequence, the time per step and the taktStudy 3 as a draft, study 6 as the released versionAny change to the method
[PFMEA](/learn/fmea)The process steps, and what the film showed going wrong: fumbles, rework, skipped checksStudy 2 as a first pass, study 3 with real failure modesA new step, a new failure seen on film, a changed tool
Control planWhere each check sits in the sequence and how long it takesStudy 3 for the pre-launch plan, study 6 for productionA check added, moved or retimed

Templates: [process flow diagram](/templates/process-flow-diagram-template), [PFMEA](/templates/pfmea-template), [control plan](/templates/control-plan-template), [standard work sheet](/templates/standard-work-sheet).

Two of these links are easy to miss. A check in the control plan takes time, so every inspection the quality engineer adds is an element the balance has to carry. And a time study film is good PFMEA evidence: a part that is fumbled on four cycles out of twenty is a failure mode with an observed frequency, which beats a guess in a meeting room.

The people side: what to tell operators at each stage

A new line is the easiest place to get this right, because nobody has a rate to defend yet. It is also where trust is lost fastest, if the first camera appears without a word.

  • Before the pilot, say what is being timed and why: the line and the method, to find what holds them back. Nobody's pace is being judged while they are learning.
  • Say when the standard will be set (day 90) and that the operators will see the sheet before anyone signs it.
  • Ask for ideas at every study and write down who gave them. Most of the seconds that came out between day 30 and day 90 in the example were operator ideas.
  • Agree how video is stored and who can see it. Tell the union representative before filming where there is one, and follow your site's rules on recording people.
  • Never use a pilot or launch week time in a conversation about one person's performance.

Common mistakes

Seven ways the routine goes wrong
MistakeWhat it costsDo this instead
Quoting one numberHeadcount is set on false precision and the first surprise breaks the planQuote a range and plan to the cautious end
Skipping the prototype studyDesign problems are found when tooling is already cutTime the first bench builds, however rough
Setting the standard at the pilotThe standard is loose or tight by an unknown amountUse pilot times for balance and the curve only
Calling slow launch output a standard problemThe standard is raised to match beginnersKeep the standard and the learning curve as two numbers
Cutting ramp labour by the calendarThe line drops below rate the week the extra operator leavesRelease labour when a study shows the time is there
Locking the standard and never looking againCosting and capacity run on a method that no longer existsTie a re-study to every change, plus a calendar review
Five documents, five element listsThe balance, work instruction, PFMEA and control plan disagreeOne element list, shared

Making seven studies cheap enough to repeat

The usual objection is time. Seven studies with a stopwatch and a spreadsheet is more engineering hours than most launches have, which is why most plants stop at one. The routine only survives if each study after the first costs little.

That is what video does for studies 3 to 7. In LeanSuite's time and motion study you film the station on a phone, the AI times every element and every cycle, and you review, correct and certify the result. Each study is stored under its process, so the pilot, day 30, day 90 and every re-study of a station sit together, and you can put two of them side by side to see what moved. The same upload can go through AI video analysis for a line balance and an ergonomic score, so one filming session answers more than one question.

It has limits. It reads video you upload, not a live camera, so studies 1 and 2 on a product that does not exist are still yours to estimate. And every study still needs an engineer to check it before it is certified.

Templates and related guides

FAQ

Questions about new product time study playbook

  1. Seven, at fixed points: an estimate at quote, a prototype timing, the pilot run, launch week, day 30, day 90 and a re-study after every change. They are small. The first two are estimates and bench timings, the middle three are short video checks, and only the day 90 study is a full rated time study that sets the standard.

  2. When the method has stopped changing and the operators are practised, which this playbook puts at about 90 days after start of production. Use pilot and launch times for balancing and for the ramp plan only. A standard set while people are still learning is loose or tight by an amount nobody can know, and it is hard to correct later.

  3. After every change to the method: an engineering change to the part, a new tool or fixture, a layout move, a material change that alters handling, or a new takt that forces a rebalance. Add a calendar review as well, often yearly, to catch slow drift. Study only the elements that changed and give the standard a new revision and date.

  4. It means that each time cumulative output doubles, the time per unit falls to 90 percent of what it was. If unit 50 takes 1,200 seconds, unit 100 takes 1,080 and unit 200 takes 972. An 85 percent curve falls faster. The rate is specific to your product and plant, so fit it to your own launch data instead of borrowing one.

  5. No. Pilot operators have done the job a few dozen times, so their pace cannot be rated fairly and their times are far above what the method needs. Use the pilot to check the sequence, find the slowest station, draw a first balance and fix the starting point of the learning curve. Set the standard later with a full rated study.

  6. It depends on your plant, and no published figure holds everywhere. Accuracy follows how similar the new part is to one you already time, and how much the design changes afterward. Report the estimate as a range with its assumptions, then compare it with the standard you finally lock. A few launches of that record give you your own error.

  7. Work study is the wider term. It covers method study, which examines how a job is done and improves it, and work measurement, which sets how long the job should take. Time study is one work measurement technique, alongside work sampling and predetermined time systems. On a new product you use all three at different stages.

  8. Any change to what the standard describes: the part, the tools and fixtures, the layout, the materials, the sequence or the takt. Build the trigger into your change approval, so an engineering change cannot close until the affected elements have been re-timed and the standard, work instruction, PFMEA and control plan carry the same revision.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.