3P production preparation process: try the line in cardboard before you buy equipment

Short answer

3P, the production preparation process, is a team method for designing a product and the line that will make it together, using cheap full-size mock-ups, often cardboard, that are timed and changed in rounds before any equipment is bought.

3P stands for production preparation process. A cross-functional team gets the demand, the takt time and the product drawings, builds the process in cardboard and tape at full size, has operators run it, times every element, then changes the layout or the product and times it again. Each round costs hours, not capital. In the worked example on this page three rounds took the work content from 212 s to 124 s and the cell from 5 operators to 3.

Last reviewed:

What is 3P?

A 3P event, day by day

Example numbers
  1. Day 1

    Learn the need

    Demand, takt, product drawings, the old way, the limits.

  2. Day 2

    Build in cardboard

    Rough stations and parts from boxes, tape and tubes.

  3. Day 3

    Run and time it

    Operators do the job. Time every element, film it.

  4. Day 4

    Change and rerun

    Fix the biggest time, move a bin, rerun and retime.

  5. Day 5

    Present the plan

    Show the cell, the numbers and the open list.

Five cards in order. Day 1, learn the need. Day 2, build the line in cardboard. Day 3, run and time it. Day 4, change and rerun. Day 5, present the plan. Days 3 and 4 repeat as many times as there is time for.

Days 3 and 4 are the method. The cardboard is cheap enough to change in minutes, so each round of timing buys a better design for the price of tape.

3P means production preparation process. It is a way of preparing to make something new: a new product, a new cell, a new line. A team designs how the thing will be made at the same time as the thing itself, and tests the idea at full size with cheap materials before anyone orders a machine or pours a floor.

It exists because the cost of a decision is lowest before it is built. A conveyor in the wrong place costs a week of cardboard to move at the start and a month of electricians later. Most plants plan a new line on paper, in CAD and in meetings, and find out on the pilot build that the parts are out of reach. 3P moves that discovery to the first week.

It is also a time study method in disguise. The mock-up is only useful if you time it. That is the part this page spends most words on, because a mock-up nobody times is a craft project. For the wider planning job around it, see process planning for a new product and the new product time study playbook.

Where 3P comes from, and what is settled

Several lean sources credit Chihiro Nakao, a contemporary of Taiichi Ohno and a founder of the consultancy Shingijutsu, with 3P. One practitioner account says it was first called new production preparation and was renamed 3P later. The same account says it reached the United States in the mid 1980s. Other accounts give different dates, and none of them cites a primary document, so treat the dates as unsettled.

Two more things to know before you quote anyone. First, 3P also gets read as people, process, product, or people, process, profits. The original and most common meaning is production preparation process, and that is the one used here. Second, Nakao is reported to have written 16 catchphrases that act as a checklist of ideas, such as making production preparation fast. The sources agree there are 16 and advise picking a few that fit the job rather than using them all.

What the sources agree on is the idea: rapid, integrated work on the product and the process together, in a short intensive event, by a mixed team. They do not agree on one fixed list of steps or an exact length, so the steps below are the method this guide recommends, not a quotation of a standard.

How to run a 3P event, step by step

Events like this commonly run about a week, but the length depends on the size of the job. A single cell can be done in days. A whole line needs longer, and sometimes two events.

  1. 1

    Fix the need before you design

    Write down the demand per day, the working time and the takt time, using the takt time arithmetic. Add the product volume mix, the quality limits and the budget ceiling. A team without a takt time will argue about taste.

  2. 2

    Pick a mixed team

    Include the operators who will run the line, a process engineer, a product designer, maintenance, quality and someone who moves material. Add one person from outside who has never seen the product. The operators are not guests: they will do the job during the trials.

  3. 3

    Go and see the current way

    Walk and film the nearest existing process. Note where parts are fetched, where people wait and where the product is handled twice. A spaghetti diagram of the current flow shows the waste the new design should not copy.

  4. 4

    Build the process in cardboard at full size

    Make benches, racks, bins, fixtures and even the machines from boxes, tubes, foam board and tape. Use real parts or weighted dummies. Build several versions of any hard idea, not one, so the team compares and does not defend.

  5. 5

    Run it and time it

    Operators perform the full cycle on the mock-up. Time each element over several cycles, film it, and total the work content. Compare the total with the takt time. The next section says how to time it fairly.

  6. 6

    Change one thing, then rerun

    Take the largest time on the sheet and ask what removes it: a closer bin, a different fixture, a part that needs fewer fasteners. Change it, run again, time again. Stop when the plan fits the takt time with room to spare, and present it with the numbers from every round.

Step 6 is where 3P differs from a normal design review. The review argues. The mock-up measures. Everyone in the room can see that moving the bin took 22 seconds off the walk.

How to build a cardboard mock-up that is worth timing

  • Build at full size. A model at one tenth scale teaches nothing about reach, walking or how heavy a tray feels.
  • Use the real part when you can, or a dummy of the same size and weight. A cardboard part that weighs nothing hides a lifting problem.
  • Mark the floor with tape for aisles, benches and the operator's standing spot. People will walk what the tape shows.
  • Mock the sequence, not the machine. A machine that runs on its own is a box with a card showing its cycle time. Take that time from the supplier's data or a trial, and do not guess it.
  • Give every part a home. If a part has no bin, the operator will invent one, and your timing will include the invention.
  • Leave it breakable. The mock-up is done when you cannot think of a cheaper change, not when it looks nice.

Check the posture and reach at the bench while the cardboard is still cheap. A bench that is a hand too high is a ten second fix now. For the method, see workstation design.

How to time a mock-up fairly

Timing a cardboard line gives indicative numbers, not standard times. The operators have not done the job before. The parts are dummies. The first cycles include thinking. You can still get a trustworthy comparison from round to round, if you hold the method the same each time.

  • Break the job into the same elements in every round, using the rules in how to break a job into elements. If the elements change, the rounds cannot be compared.
  • Time at least five cycles per round, and drop the first one or two while the operator finds the rhythm. Say which you dropped.
  • Use the same operator for the first comparison, then repeat with a second one. A change that only helps one person is not a design improvement.
  • Keep walking as its own element so you see it fall as bins move.
  • Do not apply a rating factor to learner times and call the result standard. Record observed times, say they are mock-up times, and plan to retime on the pilot build. See how to conduct a time study for the full method.

Expect real times to differ from the mock-up. Operators speed up with practice, so the mock-up may overstate the time. Real parts, real tools and real defects may add time the cardboard did not have. Put an honest range on the plan and close it with a pilot run and line trial.

Worked example: a sensor housing cell in three rounds

Illustrative numbers. A team plans a cell to assemble a sensor housing. Demand is 540 a day. One shift gives 27,000 seconds of working time, so takt is 27,000 divided by 540, which is 50 seconds. The team plans each operator to a load of 45 seconds, which is 90% of takt, to leave room for variation. That 90% is a planning choice, not a rule. The number of operators is the total work content divided by 45, rounded up.

Illustrative: element times in seconds, three mock-up rounds of the same sensor housing
ElementRound 1Round 2Round 3What changed
Seat housing in fixture886Added a stop so the housing seats first time
Fit sensor and press221815Guide pin on the fixture
Fasten sensor362212Four screws, then two, then a snap fit
Connect harness242420Keyed connector, clearer entry
Fit cover181414Chamfer on the cover edge
Fasten cover281410Screws replaced by clips in round 3
Walk and fetch parts30208Bins moved to the bench edge in use order
Test262624Test lead hung at the bench
Label and pack201715Label printer moved within reach
Total work content212163124
Operators (total / 45, rounded up)543

Mock-up times, not standard times. The snap fit and the clips are product changes, so they need the product engineer to confirm strength and cost before they count.

Total work content after each cardboard round

Example numbers

Round 1, first mock-up: 212 s, 5 operators

Round 2, after changes: 163 s, 4 operators

Round 3, final mock-up: 124 s, 3 operators

  • Work at the bench
  • Walk and fetch (element 7)

Three bars of work content for one sensor housing. Round 1: 212 seconds, 5 operators. Round 2: 163 seconds, 4 operators. Round 3: 124 seconds, 3 operators. Takt time is 50 seconds, and the plan keeps each operator under 45 seconds. The yellow segment is walking to fetch parts: 30, 20 and 8 seconds.

Walking to fetch parts is the yellow slice. It fell from 30 s to 8 s by moving bins, with no new equipment. Dividing by the 45 s planning load gives 5, 4 and 3 operators.

Check the arithmetic. Round 1: 212 divided by 45 is 4.7, so 5 operators. Round 2: 163 divided by 45 is 3.6, so 4. Round 3: 124 divided by 45 is 2.8, so 3. In round 3 each of the 3 operators then works about 41 seconds of a 50 second takt, which is 83% load.

The biggest single saving was not in the cardboard at all. Moving from four screws to a snap fit took 24 seconds out of the sensor fastening, and the cover clips took 18 more out of the cover. That is the 3P argument in one line: the process team and the product team were in the same room, so a time on the sheet turned into a change to the part. Moving the bins took another 22 seconds off the walk, which is 3.3 hours of walking a day gone at 540 pieces.

The same bench, seen from above, before and after

Example numbers

Round 1

Round 1Top view. A bench in the middle with one operator. The parts racks are against the far wall, and the operator walks there for parts: 30 seconds a piece.Bench (cardboard)OperatorParts rackswalk

Walking: 30 s a piece

Round 3

Round 3Top view. A bench in the middle with one operator. The parts bins sit at the bench edge in the order the parts are used: 8 seconds of walking a piece.Bench (cardboard)OperatorBins in use order

Walking: 8 s a piece

Two top views of the cardboard bench. In round 1 the parts racks are along the far wall and the operator walks 30 seconds a piece to fetch parts. In round 3 the bins sit at the bench edge in the order the parts are used, and walking is 8 seconds.

Nothing was bought. A few boxes were moved, and the timed walk dropped by 22 s a piece: 540 pieces a day is 3.3 hours of walking less.

Over the three rounds the work content fell by 88 seconds a piece. At 540 pieces that is 13.2 hours of labour a day that the cell does not need. The team spent a week and a few boxes. No equipment was ordered until the third round fixed the layout.

Where 3P goes wrong, and when not to use it

  • Timing the mock-up like a standard. Learners are slower, dummies are lighter. Use the numbers to compare designs, then retime on real parts.
  • A mock-up that nobody can break. If people are afraid to move the cardboard, the team will defend the first version.
  • A team of engineers only. The operator in the trial finds the reach problem a drawing cannot show.
  • Skipping the takt time. Without it the team optimises for what looks tidy.
  • Treating the event as the end. The plan still needs a pilot, standard work and a person who owns the open list.
  • Using it for a small change. For an existing line with a known fix, a normal kaizen or a line balance is cheaper than an event.

The people side is simple. Operators are the test crew, so tell them why: the mock-up is being judged, not them. Say the times will not be used to rate individuals. Run the trial with the same respect you would give a real shift.

A last honest limit: 3P suits a new product, a new cell or a major rebuild. It is heavy for a minor change, and the published guidance does not give reliable figures for how much it saves. Judge it on your own rounds, as in the example, not on a claimed average.

Tools and templates

FAQ

Questions about 3P production preparation process

  1. 3P stands for production preparation process. It is a team method for designing a product and the process that will make it together. The team builds the process at full size from cheap materials such as cardboard, has operators run it, times it, and changes it in rounds before any equipment is bought. Lean sources credit Chihiro Nakao with the method.

  2. Sources differ on one official list. A practical sequence is: fix the demand and takt time, pick a mixed team including operators, study the current process, build the new one in cardboard at full size, run and time it, then change the largest time and rerun. Repeat until the plan fits takt with room to spare, then present it with the numbers.

  3. Sources describe it as a short intensive event, commonly about a week, though one describes only a multi-day event. The right length depends on scope. One cell can be done in a few days, while a full line may need a longer event or two. Plan the event well ahead, because it needs the operators and engineers in the same room.

  4. Cardboard is cheap and quick to change. Moving a cardboard bench takes minutes and costs nothing, while moving a real one takes days and money. That lets a team test many layouts and time each one before committing. The mock-up must be full size and use real or equal-weight parts, or the times will not mean much.

  5. Yes, but the times are indicative, not standard. Operators are learning, and the parts and tools are stand-ins. Use the same elements every round, time at least five cycles, drop the warm-up cycles and say so. Use the times to compare designs, then retime on real parts during the pilot run before you set a standard.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.