To conduct a time study, settle the method, split the job into elements with clear end points, time each element over enough cycles, rate the operator's pace, set aside only the readings with a known cause, then add allowances to reach the standard time.

Ten steps: define the job and the goal, pick and brief the operator, standardize the method, break it into elements, choose the timing method and the number of cycles, observe and record, rate the pace, set aside abnormal readings, calculate, then review and file. On the sheet below, 20 cycles of a 65 second job give a standard time of 80.5 seconds.

Last reviewed:

What you need before you start

The ten steps in four phases, and what each leaves on the sheet

Example numbers
  1. 1Steps 1 to 3

    Prepare

    A defined job and goal, an operator who knows why you are there, and one written method.
  2. 2Steps 4 and 5

    Set up

    5 elements with break points, 20 cycles planned.
  3. 3Steps 6 to 8

    Observe

    100 readingsA rating for each element. One reading circled, with its cause.
  4. 4Steps 9 and 10

    Work out and file

    80.5 sstandard time, from 70.0 s normal. Reviewed and filed with the method.

Prepare, steps 1 to 3: a defined job, a briefed operator and one written method. Set up, steps 4 and 5: five elements with break points and 20 cycles planned. Observe, steps 6 to 8: 100 readings, a rating for each element and one circled reading. Work out, steps 9 and 10: 70.0 seconds normal and 80.5 seconds standard, filed with the method.

Half the steps happen before the timer starts. Skip the first two phases and careful timing cannot repair the standard afterwards.

This page is the procedure. If you are still deciding whether a time study is the right tool, or what the result will be used for, read time and motion study first.

  • An observation sheet on a board. The time study sheet has 12 elements by 10 cycles, and the Excel version does the sums.
  • A timer. A decimal-minute stopwatch reads to 0.01 minute, which is 0.6 seconds. Phone timers and video read in seconds. Pick one unit and write it at the top of the sheet.
  • Or a phone on a tripod, if you will time from video.
  • The written method for the job, if there is one, and the drawing or work instruction.
  • A place to stand where you can see the hands and the parts without being in the operator's way.

How to conduct a time study in 10 steps

The sections after this one go deeper on the four steps people get wrong most often: elements, timing method, number of cycles and the calculation.

  1. 1

    Define the job and the goal

    Write down the job, the part, the station and the start and end of one cycle. Then write what the time is for and how exact it has to be. Within 5 percent at 95 percent confidence is a common target for a standard.

  2. 2

    Pick the operator and tell them

    Choose a trained operator who works at a steady pace, not the fastest and not the newest. Explain what you are measuring, why, and what happens with the result. Tell the supervisor, and the union representative where there is one, before you start.

  3. 3

    Standardize the method first

    Watch or film a few cycles. Fix what is plainly wasteful, agree one method with the operator and write it down. If the job is done differently on each cycle, stop here and settle it.

  4. 4

    Break the job into elements

    Split the cycle into elements that each end at a break point you can see or hear. Keep hand work apart from machine time, and list work that happens only every so often.

  5. 5

    Choose the timing method and the number of cycles

    Decide between continuous timing, snap-back timing and video. Take the planned number of cycles from the General Electric guide, then check it with the formula once you have the first ten readings.

  6. 6

    Observe and record

    Let two or three cycles pass before you write anything. Then record every element of every cycle, and write a note beside anything unusual at the moment it happens.

  7. 7

    Rate the pace

    While you watch, rate each element against your plant's definition of normal pace, with 100 as normal. Do it at the bench. A rating added from memory back at the desk is a guess.

  8. 8

    Set aside abnormal readings

    Circle any reading that is far from the rest. Leave it out of the average only if you saw the cause and noted it. Keep it on the sheet either way.

  9. 9

    Calculate normal and standard time

    Average the good readings for each element, multiply by the rating to get normal time, add the elements together, then add the allowance: standard time = normal time x (1 + allowance).

  10. 10

    Review, sign off and file

    Go through the sheet with the operator and the supervisor. Compare the standard with real output. File the sheet with the method, the layout and the date, so the next person knows what the number belongs to.

How to break a job into elements

An element is a piece of the job with a clear start and a clear end. You time elements instead of whole cycles for three reasons: you can rate each one separately, you can see which one varies, and you can reuse the time when the same element turns up in another job.

  • End each element at a break point: an instant you can see or hear, such as a part touching the fixture, a hand letting go, a tool clicking back into its holder.
  • Keep elements long enough to time. Textbooks put the floor for a stopwatch at about 0.04 minute, roughly 2.4 seconds. Video can go shorter.
  • Separate hand work from machine time. The machine's part of the cycle is not rated, and it does not get the same allowances.
  • Separate constant elements from variable ones. Driving four screws takes the same time on every model. Fitting a gasket may depend on the size.
  • List occasional elements with how often they happen: a tote change every 20 units, a gauge check every tenth part.
  • Anything that is not part of the job is a foreign element: a question from a colleague, a dropped part. Record it, with its time, and keep it out of the element averages.

One cycle split into five elements at its break points

Example numbers
  1. Get housing and seat it in the fixtureEnds at 9 s: housing clicks into the fixture.

  2. Fit gasket and position coverEnds at 24 s: hand leaves the cover.

  3. Drive four screwsEnds at 47 s: driver is back in its holder.

  4. Apply label and checkEnds at 59 s: hand leaves the label.

  5. Place unit in toteEnds at 65 s: unit is released into the tote.

Cycle 1 of the junction box job, 65 seconds. The break points fall at 9, 24, 47, 59, 65 seconds on a running watch.

Each line between two blocks is a break point: one instant that two observers would agree on. The numbers under the bar are the running watch at each one.
Illustrative: elements and break points for the junction box job
ElementStarts whenEnds when (the break point)Type
1. Get housing and seat it in the fixtureHand reaches for a housingHousing clicks into the fixtureManual, constant
2. Fit gasket and position coverHand reaches for a gasketHand leaves the coverManual, constant
3. Drive four screwsHand reaches for the driverDriver is back in its holderManual with a power tool
4. Apply label and checkHand reaches for a labelHand leaves the labelManual, constant
5. Place unit in toteHand grips the finished unitUnit is released into the toteManual, constant
Swap tote and restock screwsTote is fullEmpty tote is in placeOccasional: once every 20 units

The end of one element is the start of the next, so there are no gaps in the cycle.

Continuous or snap-back timing

With a stopwatch there are two ways to time elements. In continuous timing the watch runs for the whole study. You write the reading at each break point and subtract afterwards. In snap-back timing you read the watch at each break point and return it to zero, so each reading is the element time.

Continuous and snap-back timing on the same cycle

Example numbers

Continuous

The watch never stops. Write the reading at each break point.

Continuous timing: watch readings and the element times found by subtraction
Element12345
Watch reading924475965
Minus the one before09244759
Element time91523126
  • Delays and interruptions stay on the sheet, with their times.
  • The readings add up to the length of the session, so the study can be audited.
  • You subtract afterwards, or let a spreadsheet do it.

Snap-back

Read the watch at each break point and return it to zero.

Snap-back timing: each watch reading is the element time
Element12345
Watch reading91523126
Element time91523126
  • No arithmetic: you see each element time, and how it varies, as you go.
  • The instant spent resetting is never recorded. It matters most on short elements.
  • A delay you choose not to time leaves no trace on the sheet.

Cycle 1 of the junction box job, 65 seconds, split into five elements of 9, 15, 23, 12, 6 seconds. With continuous timing the watch readings at the break points are 9, 24, 47, 59, 65, and each element time is a reading minus the one before. With snap-back timing the watch returns to zero at each break point, so the readings are the element times.

Same cycle, same 65 seconds, two ways of writing it down. Continuous timing costs you a subtraction and keeps every second on the record. Snap-back saves the subtraction and loses whatever passes while the watch resets.

Continuous timing is the safer default. Every second of the session is on the sheet, including delays and foreign elements, so nobody can say time went missing. Snap-back is quicker to work with and lets you see variation as you go, but the moment spent resetting the watch is never recorded, and that matters most on short elements.

Timing from video removes the choice. You mark each break point on the timeline, the element times fall out, and anyone can replay a cycle to check where you put the mark.

How many cycles to time

There are two accepted ways to decide. Use the first to plan the session and the second to decide when you can stop.

The General Electric guide

This table gives a number of cycles from the length of the whole cycle. It appears in the ILO's Introduction to Work Study and in Niebel's Methods, Standards, and Work Design, which credits General Electric. It is a convention, not a calculation: it knows nothing about how much your readings vary.

The General Electric guide: cycles to time by cycle length

  1. Up to 0.10 min200cycles
  2. Up to 0.25 min100cycles
  3. Up to 0.50 min60cycles
  4. Up to 0.75 min40cycles
  5. Up to 1.00 min30cycles
  6. Up to 2.00 min20cyclesThis job: 1.08 min
  7. Up to 5.00 min15cycles
  8. Up to 10.00 min10cycles
  9. Up to 20.00 min8cycles
  10. Up to 40.00 min5cycles
  11. Over 40.00 min3cycles
The shorter the cycle, the more of them you time: short cycles vary more in proportion, and they cost little to watch. The junction box cycle averages 65 seconds, which is 1.08 minutes, so the guide gives 20 cycles.

The statistical formula

The formula uses your own readings. Time a first set of cycles, then for each element work out n = (t x s / (k x mean)) squared. Here s is the standard deviation of the readings, mean is their average, k is the accuracy you want as a fraction (0.05 for 5 percent) and t comes from the t table for your confidence level and the number of readings less one. Do it for every element and take the largest answer.

On the junction box job, the first 10 cycles say element 5 needs 13 cycles and element 1 needs 12. So 10 is not enough, and the engineer carries on to the planned 20. Checked again at 20 cycles, the worst element needs 11. The study can stop.

Checking the number of cycles with the formula

Example numbers

n = (t × s ÷ (k × mean))²

t is for 95% confidence and the number of readings less one. s is the standard deviation of the readings. k is 0.05, for 5% accuracy.

  1. Element 5 after 10 cycles =(2.262 × 0.471 ÷ (0.05 × 6.0))²= 12.6, so 13 cycles
  2. Element 1 after 10 cycles =(2.262 × 0.667 ÷ (0.05 × 9.0))²= 11.2, so 12 cycles
  3. Element 5 after 20 cycles =(2.093 × 0.459 ÷ (0.05 × 6.0))²= 10.2, so 11 cycles
Cycles timed20
After 10 cycles the two shortest elements both ask for more than 10, so the study carries on. After 20 cycles the same element asks for 11, and 20 have been timed. Short elements decide the answer because one second is a bigger share of a 6 second element than of a 23 second one.

The ILO prints a version of the same formula for 95.45 percent confidence and 5 percent accuracy, and Barnes gives a quick method that uses the range of the first 5 or 10 readings. The time study sample size calculator runs all three on readings you paste in.

Two cautions. The formula assumes the variation is chance, so it means little if the operator is changing pace on purpose or the method is not settled. And when the table and the formula disagree, take the larger number for any standard that affects pay.

A filled-in observation sheet

Illustrative example: the junction box job, 20 cycles, element times in seconds. Each cell holds two readings, the first ten cycles on the top line and cycles 11 to 20 underneath.

Time study observation sheet, filled in

Example numbers
Job
Junction box assembly
Operator
Trained, steady pace
Timing
Continuous, in seconds
Cycles timed
20

Scroll the sheet sideways to see every cycle.

Element times in seconds for 20 cycles. Each cell holds two readings: the top line is cycles 1 to 10, the bottom line cycles 11 to 20.
Elementand its break pointCycle (top line 1 to 10, bottom line 11 to 20)UsedAverageRatingNormal
1112123134145156167178189191020
1. Get housing and seat it in the fixtureEnds: housing clicks into the fixtureCycle 1: 9. Cycle 11: 9. Cycle 2: 8. Cycle 12: 9. Cycle 3: 9. Cycle 13: 8. Cycle 4: 10. Cycle 14: 9. Cycle 5: 9. Cycle 15: 10. Cycle 6: 9. Cycle 16: 9. Cycle 7: 8. Cycle 17: 9. Cycle 8: 9. Cycle 18: 9. Cycle 9: 10. Cycle 19: 8. Cycle 10: 9. Cycle 20: 10. 209.01109.9
2. Fit gasket and position coverEnds: hand leaves the coverCycle 1: 15. Cycle 11: 15. Cycle 2: 14. Cycle 12: 16. Cycle 3: 16. Cycle 13: 15. Cycle 4: 15. Cycle 14: 14. Cycle 5: 15. Cycle 15: 15. Cycle 6: 14. Cycle 16: 15. Cycle 7: 15. Cycle 17: 16. Cycle 8: 16. Cycle 18: 15. Cycle 9: 15. Cycle 19: 15. Cycle 10: 15. Cycle 20: 14. 2015.011016.5
3. Drive four screwsEnds: driver is back in its holderCycle 1: 23. Cycle 11: 23. Cycle 2: 22. Cycle 12: 24. Cycle 3: 24. Cycle 13: 23. Cycle 4: 23. Cycle 14: 22. Cycle 5: 23. Cycle 15: 23. Cycle 6: 23. Cycle 16: 23. Cycle 7: 24. Cycle 17: 24. Cycle 8: 36, circled, dropped screw. Cycle 18: 23. Cycle 9: 23. Cycle 19: 22. Cycle 10: 22. Cycle 20: 23. 1923.010023.0
4. Apply label and checkEnds: hand leaves the labelCycle 1: 12. Cycle 11: 12. Cycle 2: 12. Cycle 12: 13. Cycle 3: 13. Cycle 13: 12. Cycle 4: 12. Cycle 14: 12. Cycle 5: 11. Cycle 15: 11. Cycle 6: 12. Cycle 16: 12. Cycle 7: 13. Cycle 17: 12. Cycle 8: 12. Cycle 18: 12. Cycle 9: 12. Cycle 19: 12. Cycle 10: 11. Cycle 20: 12. 2012.010012.0
5. Place unit in toteEnds: unit is released into the toteCycle 1: 6. Cycle 11: 6. Cycle 2: 6. Cycle 12: 5. Cycle 3: 5. Cycle 13: 6. Cycle 4: 6. Cycle 14: 6. Cycle 5: 6. Cycle 15: 6. Cycle 6: 7. Cycle 16: 7. Cycle 7: 6. Cycle 17: 6. Cycle 8: 6. Cycle 18: 6. Cycle 9: 6. Cycle 19: 6. Cycle 10: 6. Cycle 20: 6. 206.01006.0
Cycle totalCycle 1: 65. Cycle 11: 65Cycle 2: 62. Cycle 12: 67Cycle 3: 67. Cycle 13: 64Cycle 4: 66. Cycle 14: 63Cycle 5: 64. Cycle 15: 65Cycle 6: 65. Cycle 16: 66Cycle 7: 66. Cycle 17: 67Cycle 8: 79. Cycle 18: 65Cycle 9: 66. Cycle 19: 63Cycle 10: 63. Cycle 20: 6565.067.4
Remarks
Cycle 8, element 3: dropped screw, 36 s. Circled and left out of the average.
Occasional element
Swap tote and restock screws: timed 3 times (50, 53, 53 s), average 52.0 s. Once every 20 units: 52.0 ÷ 20 = 2.6 s a unit, rated 100.
Normal time per unit
67.4 + 2.6 = 70.0 s

A sheet of five elements by 20 cycles, in seconds. The averages are 9.0, 15.0, 23.0, 12.0, 6.0 seconds, 65.0 in all. One reading, 36 seconds for element 3 in cycle 8, is circled and left out. With ratings of 110, 110, 100, 100, 100 the normal times add up to 67.4 seconds.

The yellow column is the average of the good readings. Element 3 uses 19 readings, not 20, because of the circled one. The cycle totals at the foot make an odd cycle easy to spot: cycle 8 is 79 s against 62 to 67 s for the rest of that line.

Read it from left to right. Each row is one element. The readings are the element times for each cycle. The four columns on the right are the result: how many readings were used, their average, the rating given at the bench and the normal time.

The circled reading

In cycle 8 the operator dropped a screw and element 3 took 36 seconds against a usual 22 to 24. The engineer circled it, wrote the cause in the remarks and left it out of the average, so element 3 has 19 good readings. The reading stays on the sheet. If dropped screws turned out to be common, that would be a finding about the job, and the time belongs in the delay allowance, not in the bin.

The rule for abnormal readings is short: circle it, note the cause, and leave it out only when you know the cause and it is not part of the job. A long reading with no explanation stays in. Removing every high reading is the quickest way to set a standard nobody can meet.

The occasional element

Swapping the tote and restocking screws happened once in these 20 cycles, which is not enough to time it. The engineer timed it on three occasions (50, 53 and 53 seconds, an average of 52.0) and spread it over the 20 units it serves: 52.0 / 20 = 2.6 seconds a unit. Leave this out and the standard is 3.7 percent short.

Rating and allowances, in brief

Rating answers one question: was this person working faster or slower than normal while I timed them? You give each element a number, with 100 as normal pace, and multiply. An element timed at 9.0 seconds and rated 110 has a normal time of 9.9 seconds.

What a rating does to the same observed time

Example numbers
  1. Rated 90Slower than normal: 9.0 × 90 ÷ 100

    8.1 s

  2. Rated 100Normal pace: 9.0 × 100 ÷ 100

    9.0 s

  3. Rated 110Faster than normal: 9.0 × 110 ÷ 100

    9.9 s

  4. Dashed line: the observed time, 9.0 s

Element 1 was timed at 9.0 seconds. Rated 90 it becomes 8.1 seconds of normal time, rated 100 it stays 9.0, and rated 110 it becomes 9.9.

The timer said 9.0 s in all three cases. A fast operator took less time than normal, so the normal time is longer than the reading. A slow one took more, so it is shorter. On the sheet this element was rated 110.

Normal has to be defined before you rate, or 100 means whatever the observer feels that day. A common benchmark in American textbooks is walking at 3 miles an hour on level ground, or dealing a deck of 52 cards into four piles in half a minute. The ILO uses a 0 to 100 scale on which 100 is standard performance. Use your plant's definition, and practice rating the same film with a colleague until your numbers agree.

Allowances are time added for things that are part of working a shift but not part of the cycle. There are three kinds: personal needs, fatigue and unavoidable delays. The example table in the ILO's book starts with 5 to 7 percent for personal needs and 4 percent for basic fatigue, then adds for standing, posture, force and conditions. The junction box plant uses 15 percent in total. Yours should come from your own conditions and be agreed before the study, not chosen afterwards to make the number fit.

Standard time covers rating scales, allowance tables and the two ways of applying an allowance.

Calculate normal and standard time

Three formulas turn the sheet into a standard. Normal time = average observed time x rating / 100. Normal time per unit = the sum of the element normal times, including each occasional element divided by how often it happens. Standard time = normal time per unit x (1 + allowance).

Illustrative: from the sheet to a standard time

Example numbers

Standard time = normal time × (1 + allowance)

Check: 80.5 seconds is 1.34 minutes a unit, or 2.24 standard hours per 100 units.

  1. Average observed time, five elements =9.0 + 15.0 + 23.0 + 12.0 + 6.0= 65.0 s
  2. Occasional element per unit =52.0 / 20= 2.6 s
  3. Observed time per unit =65.0 + 2.6= 67.6 s
  4. Normal time, elements 1 and 2 =(9.0 + 15.0) x 110 / 100= 26.4 s
  5. Normal time, the rest =(23.0 + 12.0 + 6.0 + 2.6) x 100 / 100= 43.6 s
  6. Normal time per unit =26.4 + 43.6= 70.0 s
  7. Standard time =70.0 x (1 + 0.15)= 80.5 s
  8. Units an hour =3,600 / 80.5= 44.7
Standard time80.5 s
Read down the yellow line: averages first, then the occasional element, then rating, then the allowance. Every figure comes from the sheet above.

Before you publish, test the number against the floor. If the bench has been turning out about 45 units an hour on a good day, 44.7 is believable. If it has been making 60, either the study or the output count is wrong, and you need to know which before anyone sees the standard.

The same procedure from video

Steps 1 to 4 and 7 to 10 do not change when a camera does the watching. Steps 5 and 6 do.

  • Agree the filming with the operator first: what is in frame, who will see it and when it is deleted.
  • Film one continuous take from a fixed position, with the hands, the parts and the full reach in frame.
  • Film more cycles than you plan to use. Extra cycles cost nothing, and you can drop the first few while the operator settles.
  • Mark break points on the timeline, not with a watch. At 30 frames a second one frame is 1/30 of a second.
  • Rate the pace from the film, and ask a second person to rate the same cycles.
  • Keep the film with the study, for as long as your retention rule allows. It is the evidence behind the standard.

One stopwatch tick against video frames

Stopwatch: 1 tick = 0.01 min = 0.6 s

Video: 0.6 s × 30 frames a second = 18 frames

Each frame is 1/30 of a second.

One tick of a decimal-minute stopwatch is 0.01 minute, which is 0.6 seconds. Video at 30 frames a second has 18 frames in that time.

A decimal-minute stopwatch cannot place a break point more finely than one tick. Video at 30 frames a second gives 18 places to put it inside the same tick, and you can go back and check which one you chose.

In LeanSuite's time and motion study software, the marking and timing in steps 5 and 6 are drafted from the video: it times every element and cycle, and you correct the timeline and certify the study. The filming guide covers camera angle and distance.

Checklist: mistakes to catch before you sign the study

Go down this list with the finished sheet in front of you. It works just as well on a study someone else did.

Time study mistakes and what to do instead

  • Mistake

    The method was not settled

    What it does: The average mixes two or three ways of doing the job, and the spread between readings is wide

    Do this instead

    Agree and write down one method, then start the timing again

  • Mistake

    Break points are vague

    What it does: Two observers get different element times from the same cycle

    Do this instead

    Write the break point for each element as something seen or heard

  • Mistake

    Too few cycles

    What it does: The average can be several percent off and nobody knows

    Do this instead

    Plan from the General Electric guide and check with the formula before you stop

  • Mistake

    No rating, or 100 for everything

    What it does: The standard is the pace of one person on one day

    Do this instead

    Rate each element at the bench against a written definition of normal

  • Mistake

    High readings deleted with no cause

    What it does: The standard comes out too tight and the operator loses trust in it

    Do this instead

    Circle the reading and leave it out only with a noted cause

  • Mistake

    Occasional work left out

    What it does: Tote changes, restocking and checks are missing from the standard

    Do this instead

    Time each one and divide by the units it serves

  • Mistake

    Machine time rated like hand work

    What it does: Machine time gets stretched or shrunk by a rating that cannot apply to it

    Do this instead

    Time machine elements apart and leave them at 100

  • Mistake

    Allowance chosen after the result

    What it does: The allowance becomes a way to reach the number someone wanted

    Do this instead

    Use the plant's agreed allowance for that kind of work

  • Mistake

    The operator was not told

    What it does: The pace is unnatural, and the standard is disputed from the first day

    Do this instead

    Brief the operator and the supervisor before the study, and show them the sheet after

  • Mistake

    The sheet has no method or date

    What it does: Nobody can tell later whether the standard still applies

    Do this instead

    File the sheet with the method, layout, tools and date

Each row is a check you can make on a finished sheet. The yellow box is what a sound study shows in its place.

Tools and templates for running a time study

Time and motion study software

Run a time study in LeanSuite

Time and motion study software that works from phone video: LeanSuite times every element, gives cycle and standard time, and draws a Yamazumi chart.

FAQ

Questions about how to conduct a time study

  1. Settle the method first. Then split the job into elements with clear end points, time each element over enough cycles, and rate the operator's pace while you watch. Average the good readings, multiply by the rating to get normal time, and add the plant's allowance for personal needs, fatigue and delays. The result is the standard time for the job.

  2. Ten steps: define the job and the goal, pick and brief the operator, standardize the method, break the job into elements, choose the timing method and the number of cycles, observe and record, rate the pace, set aside abnormal readings, calculate normal and standard time, then review and file. Some textbooks group the same work into five steps.

  3. It depends on the cycle length and on how much the readings vary. The General Electric guide gives 30 cycles for a job of up to one minute, 20 for up to two minutes and 15 for up to five. The statistical formula, n = (t x s / (k x mean)) squared, uses your own first readings. Take the larger of the two for a standard that affects pay.

  4. Normal time = average observed time x rating / 100. Standard time = normal time x (1 + allowance). For example, 67.6 seconds observed with two elements rated 110 gives 70.0 normal seconds, and a 15 percent allowance gives a standard time of 80.5 seconds. Some plants divide by 1 minus the allowance, so check which convention yours uses.

  5. In continuous timing the stopwatch runs for the whole study and you write the reading at each break point, then subtract to get element times. In snap-back timing you return the watch to zero at each break point, so each reading is the element time. Continuous keeps every second on record. Snap-back is quicker but loses the time taken to reset.

  6. Frederick W. Taylor. He began timing work with a stopwatch at the Midvale Steel Company in Philadelphia in 1881, splitting jobs into elements and timing each one. Frank and Lillian Gilbreth added motion study soon after, which is why the two are usually named together as time and motion study.

  7. Use an observation sheet with the elements down the side and the cycles across the top. Fill in the job, operator, date and unit of time, then record each element of each cycle and a rating for each element. Note anything unusual as it happens. Afterwards, average the good readings, apply the rating and the allowance, and review the sheet with the operator.

  8. Circle it on the sheet and write down what happened. Leave it out of the average only if you saw the cause and the cause is not part of the job, such as a dropped part or an interruption. A long reading with no known cause stays in. If the same problem keeps happening, it belongs in the delay allowance or on the improvement list.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.