How to conduct a time study: 10 steps with a filled-in sheet
Short answer
To conduct a time study, settle the method, split the job into elements with clear end points, time each element over enough cycles, rate the operator's pace, set aside only the readings with a known cause, then add allowances to reach the standard time.
Ten steps: define the job and the goal, pick and brief the operator, standardize the method, break it into elements, choose the timing method and the number of cycles, observe and record, rate the pace, set aside abnormal readings, calculate, then review and file. On the sheet below, 20 cycles of a 65 second job give a standard time of 80.5 seconds.
Last reviewed:
What you need before you start
The ten steps in four phases, and what each leaves on the sheet
Example numbers- 1Steps 1 to 3
Prepare
A defined job and goal, an operator who knows why you are there, and one written method. - 2Steps 4 and 5
Set up
5 elements with break points, 20 cycles planned. - 3Steps 6 to 8
Observe
100 readingsA rating for each element. One reading circled, with its cause. - 4Steps 9 and 10
Work out and file
80.5 sstandard time, from 70.0 s normal. Reviewed and filed with the method.
Prepare, steps 1 to 3: a defined job, a briefed operator and one written method. Set up, steps 4 and 5: five elements with break points and 20 cycles planned. Observe, steps 6 to 8: 100 readings, a rating for each element and one circled reading. Work out, steps 9 and 10: 70.0 seconds normal and 80.5 seconds standard, filed with the method.
This page is the procedure. If you are still deciding whether a time study is the right tool, or what the result will be used for, read time and motion study first.
- An observation sheet on a board. The time study sheet has 12 elements by 10 cycles, and the Excel version does the sums.
- A timer. A decimal-minute stopwatch reads to 0.01 minute, which is 0.6 seconds. Phone timers and video read in seconds. Pick one unit and write it at the top of the sheet.
- Or a phone on a tripod, if you will time from video.
- The written method for the job, if there is one, and the drawing or work instruction.
- A place to stand where you can see the hands and the parts without being in the operator's way.
How to conduct a time study in 10 steps
The sections after this one go deeper on the four steps people get wrong most often: elements, timing method, number of cycles and the calculation.
- 1
Define the job and the goal
Write down the job, the part, the station and the start and end of one cycle. Then write what the time is for and how exact it has to be. Within 5 percent at 95 percent confidence is a common target for a standard.
- 2
Pick the operator and tell them
Choose a trained operator who works at a steady pace, not the fastest and not the newest. Explain what you are measuring, why, and what happens with the result. Tell the supervisor, and the union representative where there is one, before you start.
- 3
Standardize the method first
Watch or film a few cycles. Fix what is plainly wasteful, agree one method with the operator and write it down. If the job is done differently on each cycle, stop here and settle it.
- 4
Break the job into elements
Split the cycle into elements that each end at a break point you can see or hear. Keep hand work apart from machine time, and list work that happens only every so often.
- 5
Choose the timing method and the number of cycles
Decide between continuous timing, snap-back timing and video. Take the planned number of cycles from the General Electric guide, then check it with the formula once you have the first ten readings.
- 6
Observe and record
Let two or three cycles pass before you write anything. Then record every element of every cycle, and write a note beside anything unusual at the moment it happens.
- 7
Rate the pace
While you watch, rate each element against your plant's definition of normal pace, with 100 as normal. Do it at the bench. A rating added from memory back at the desk is a guess.
- 8
Set aside abnormal readings
Circle any reading that is far from the rest. Leave it out of the average only if you saw the cause and noted it. Keep it on the sheet either way.
- 9
Calculate normal and standard time
Average the good readings for each element, multiply by the rating to get normal time, add the elements together, then add the allowance: standard time = normal time x (1 + allowance).
- 10
Review, sign off and file
Go through the sheet with the operator and the supervisor. Compare the standard with real output. File the sheet with the method, the layout and the date, so the next person knows what the number belongs to.
How to break a job into elements
An element is a piece of the job with a clear start and a clear end. You time elements instead of whole cycles for three reasons: you can rate each one separately, you can see which one varies, and you can reuse the time when the same element turns up in another job.
- End each element at a break point: an instant you can see or hear, such as a part touching the fixture, a hand letting go, a tool clicking back into its holder.
- Keep elements long enough to time. Textbooks put the floor for a stopwatch at about 0.04 minute, roughly 2.4 seconds. Video can go shorter.
- Separate hand work from machine time. The machine's part of the cycle is not rated, and it does not get the same allowances.
- Separate constant elements from variable ones. Driving four screws takes the same time on every model. Fitting a gasket may depend on the size.
- List occasional elements with how often they happen: a tote change every 20 units, a gauge check every tenth part.
- Anything that is not part of the job is a foreign element: a question from a colleague, a dropped part. Record it, with its time, and keep it out of the element averages.
One cycle split into five elements at its break points
Example numbersGet housing and seat it in the fixtureEnds at 9 s: housing clicks into the fixture.
Fit gasket and position coverEnds at 24 s: hand leaves the cover.
Drive four screwsEnds at 47 s: driver is back in its holder.
Apply label and checkEnds at 59 s: hand leaves the label.
Place unit in toteEnds at 65 s: unit is released into the tote.
Cycle 1 of the junction box job, 65 seconds. The break points fall at 9, 24, 47, 59, 65 seconds on a running watch.
| Element | Starts when | Ends when (the break point) | Type |
|---|---|---|---|
| 1. Get housing and seat it in the fixture | Hand reaches for a housing | Housing clicks into the fixture | Manual, constant |
| 2. Fit gasket and position cover | Hand reaches for a gasket | Hand leaves the cover | Manual, constant |
| 3. Drive four screws | Hand reaches for the driver | Driver is back in its holder | Manual with a power tool |
| 4. Apply label and check | Hand reaches for a label | Hand leaves the label | Manual, constant |
| 5. Place unit in tote | Hand grips the finished unit | Unit is released into the tote | Manual, constant |
| Swap tote and restock screws | Tote is full | Empty tote is in place | Occasional: once every 20 units |
The end of one element is the start of the next, so there are no gaps in the cycle.
Continuous or snap-back timing
With a stopwatch there are two ways to time elements. In continuous timing the watch runs for the whole study. You write the reading at each break point and subtract afterwards. In snap-back timing you read the watch at each break point and return it to zero, so each reading is the element time.
Continuous and snap-back timing on the same cycle
Example numbersContinuous
The watch never stops. Write the reading at each break point.
| Element | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| Watch reading | 9 | 24 | 47 | 59 | 65 |
| Minus the one before | 0 | 9 | 24 | 47 | 59 |
| Element time | 9 | 15 | 23 | 12 | 6 |
- Delays and interruptions stay on the sheet, with their times.
- The readings add up to the length of the session, so the study can be audited.
- You subtract afterwards, or let a spreadsheet do it.
Snap-back
Read the watch at each break point and return it to zero.
| Element | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| Watch reading | 9 | 15 | 23 | 12 | 6 |
| Element time | 9 | 15 | 23 | 12 | 6 |
- No arithmetic: you see each element time, and how it varies, as you go.
- The instant spent resetting is never recorded. It matters most on short elements.
- A delay you choose not to time leaves no trace on the sheet.
Cycle 1 of the junction box job, 65 seconds, split into five elements of 9, 15, 23, 12, 6 seconds. With continuous timing the watch readings at the break points are 9, 24, 47, 59, 65, and each element time is a reading minus the one before. With snap-back timing the watch returns to zero at each break point, so the readings are the element times.
Continuous timing is the safer default. Every second of the session is on the sheet, including delays and foreign elements, so nobody can say time went missing. Snap-back is quicker to work with and lets you see variation as you go, but the moment spent resetting the watch is never recorded, and that matters most on short elements.
Timing from video removes the choice. You mark each break point on the timeline, the element times fall out, and anyone can replay a cycle to check where you put the mark.
How many cycles to time
There are two accepted ways to decide. Use the first to plan the session and the second to decide when you can stop.
The General Electric guide
This table gives a number of cycles from the length of the whole cycle. It appears in the ILO's Introduction to Work Study and in Niebel's Methods, Standards, and Work Design, which credits General Electric. It is a convention, not a calculation: it knows nothing about how much your readings vary.
The General Electric guide: cycles to time by cycle length
- Up to 0.10 min200cycles
- Up to 0.25 min100cycles
- Up to 0.50 min60cycles
- Up to 0.75 min40cycles
- Up to 1.00 min30cycles
- Up to 2.00 min20cyclesThis job: 1.08 min
- Up to 5.00 min15cycles
- Up to 10.00 min10cycles
- Up to 20.00 min8cycles
- Up to 40.00 min5cycles
- Over 40.00 min3cycles
The statistical formula
The formula uses your own readings. Time a first set of cycles, then for each element work out n = (t x s / (k x mean)) squared. Here s is the standard deviation of the readings, mean is their average, k is the accuracy you want as a fraction (0.05 for 5 percent) and t comes from the t table for your confidence level and the number of readings less one. Do it for every element and take the largest answer.
On the junction box job, the first 10 cycles say element 5 needs 13 cycles and element 1 needs 12. So 10 is not enough, and the engineer carries on to the planned 20. Checked again at 20 cycles, the worst element needs 11. The study can stop.
Checking the number of cycles with the formula
Example numbersn = (t × s ÷ (k × mean))²
t is for 95% confidence and the number of readings less one. s is the standard deviation of the readings. k is 0.05, for 5% accuracy.
- Element 5 after 10 cycles =(2.262 × 0.471 ÷ (0.05 × 6.0))²= 12.6, so 13 cycles
- Element 1 after 10 cycles =(2.262 × 0.667 ÷ (0.05 × 9.0))²= 11.2, so 12 cycles
- Element 5 after 20 cycles =(2.093 × 0.459 ÷ (0.05 × 6.0))²= 10.2, so 11 cycles
The ILO prints a version of the same formula for 95.45 percent confidence and 5 percent accuracy, and Barnes gives a quick method that uses the range of the first 5 or 10 readings. The time study sample size calculator runs all three on readings you paste in.
Two cautions. The formula assumes the variation is chance, so it means little if the operator is changing pace on purpose or the method is not settled. And when the table and the formula disagree, take the larger number for any standard that affects pay.
A filled-in observation sheet
Illustrative example: the junction box job, 20 cycles, element times in seconds. Each cell holds two readings, the first ten cycles on the top line and cycles 11 to 20 underneath.
Time study observation sheet, filled in
Example numbers- Job
- Junction box assembly
- Operator
- Trained, steady pace
- Timing
- Continuous, in seconds
- Cycles timed
- 20
Scroll the sheet sideways to see every cycle.
| Elementand its break point | Cycle (top line 1 to 10, bottom line 11 to 20) | Used | Average | Rating | Normal | |||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 111 | 212 | 313 | 414 | 515 | 616 | 717 | 818 | 919 | 1020 | |||||
| 1. Get housing and seat it in the fixtureEnds: housing clicks into the fixture | Cycle 1: 9. Cycle 11: 9. | Cycle 2: 8. Cycle 12: 9. | Cycle 3: 9. Cycle 13: 8. | Cycle 4: 10. Cycle 14: 9. | Cycle 5: 9. Cycle 15: 10. | Cycle 6: 9. Cycle 16: 9. | Cycle 7: 8. Cycle 17: 9. | Cycle 8: 9. Cycle 18: 9. | Cycle 9: 10. Cycle 19: 8. | Cycle 10: 9. Cycle 20: 10. | 20 | 9.0 | 110 | 9.9 |
| 2. Fit gasket and position coverEnds: hand leaves the cover | Cycle 1: 15. Cycle 11: 15. | Cycle 2: 14. Cycle 12: 16. | Cycle 3: 16. Cycle 13: 15. | Cycle 4: 15. Cycle 14: 14. | Cycle 5: 15. Cycle 15: 15. | Cycle 6: 14. Cycle 16: 15. | Cycle 7: 15. Cycle 17: 16. | Cycle 8: 16. Cycle 18: 15. | Cycle 9: 15. Cycle 19: 15. | Cycle 10: 15. Cycle 20: 14. | 20 | 15.0 | 110 | 16.5 |
| 3. Drive four screwsEnds: driver is back in its holder | Cycle 1: 23. Cycle 11: 23. | Cycle 2: 22. Cycle 12: 24. | Cycle 3: 24. Cycle 13: 23. | Cycle 4: 23. Cycle 14: 22. | Cycle 5: 23. Cycle 15: 23. | Cycle 6: 23. Cycle 16: 23. | Cycle 7: 24. Cycle 17: 24. | Cycle 8: 36, circled, dropped screw. Cycle 18: 23. | Cycle 9: 23. Cycle 19: 22. | Cycle 10: 22. Cycle 20: 23. | 19 | 23.0 | 100 | 23.0 |
| 4. Apply label and checkEnds: hand leaves the label | Cycle 1: 12. Cycle 11: 12. | Cycle 2: 12. Cycle 12: 13. | Cycle 3: 13. Cycle 13: 12. | Cycle 4: 12. Cycle 14: 12. | Cycle 5: 11. Cycle 15: 11. | Cycle 6: 12. Cycle 16: 12. | Cycle 7: 13. Cycle 17: 12. | Cycle 8: 12. Cycle 18: 12. | Cycle 9: 12. Cycle 19: 12. | Cycle 10: 11. Cycle 20: 12. | 20 | 12.0 | 100 | 12.0 |
| 5. Place unit in toteEnds: unit is released into the tote | Cycle 1: 6. Cycle 11: 6. | Cycle 2: 6. Cycle 12: 5. | Cycle 3: 5. Cycle 13: 6. | Cycle 4: 6. Cycle 14: 6. | Cycle 5: 6. Cycle 15: 6. | Cycle 6: 7. Cycle 16: 7. | Cycle 7: 6. Cycle 17: 6. | Cycle 8: 6. Cycle 18: 6. | Cycle 9: 6. Cycle 19: 6. | Cycle 10: 6. Cycle 20: 6. | 20 | 6.0 | 100 | 6.0 |
| Cycle total | Cycle 1: 65. Cycle 11: 65 | Cycle 2: 62. Cycle 12: 67 | Cycle 3: 67. Cycle 13: 64 | Cycle 4: 66. Cycle 14: 63 | Cycle 5: 64. Cycle 15: 65 | Cycle 6: 65. Cycle 16: 66 | Cycle 7: 66. Cycle 17: 67 | Cycle 8: 79. Cycle 18: 65 | Cycle 9: 66. Cycle 19: 63 | Cycle 10: 63. Cycle 20: 65 | 65.0 | 67.4 | ||
- Remarks
- Cycle 8, element 3: dropped screw, 36 s. Circled and left out of the average.
- Occasional element
- Swap tote and restock screws: timed 3 times (50, 53, 53 s), average 52.0 s. Once every 20 units: 52.0 ÷ 20 = 2.6 s a unit, rated 100.
- Normal time per unit
- 67.4 + 2.6 = 70.0 s
A sheet of five elements by 20 cycles, in seconds. The averages are 9.0, 15.0, 23.0, 12.0, 6.0 seconds, 65.0 in all. One reading, 36 seconds for element 3 in cycle 8, is circled and left out. With ratings of 110, 110, 100, 100, 100 the normal times add up to 67.4 seconds.
Read it from left to right. Each row is one element. The readings are the element times for each cycle. The four columns on the right are the result: how many readings were used, their average, the rating given at the bench and the normal time.
The circled reading
In cycle 8 the operator dropped a screw and element 3 took 36 seconds against a usual 22 to 24. The engineer circled it, wrote the cause in the remarks and left it out of the average, so element 3 has 19 good readings. The reading stays on the sheet. If dropped screws turned out to be common, that would be a finding about the job, and the time belongs in the delay allowance, not in the bin.
The rule for abnormal readings is short: circle it, note the cause, and leave it out only when you know the cause and it is not part of the job. A long reading with no explanation stays in. Removing every high reading is the quickest way to set a standard nobody can meet.
The occasional element
Swapping the tote and restocking screws happened once in these 20 cycles, which is not enough to time it. The engineer timed it on three occasions (50, 53 and 53 seconds, an average of 52.0) and spread it over the 20 units it serves: 52.0 / 20 = 2.6 seconds a unit. Leave this out and the standard is 3.7 percent short.
Rating and allowances, in brief
Rating answers one question: was this person working faster or slower than normal while I timed them? You give each element a number, with 100 as normal pace, and multiply. An element timed at 9.0 seconds and rated 110 has a normal time of 9.9 seconds.
What a rating does to the same observed time
Example numbersRated 90Slower than normal: 9.0 × 90 ÷ 100
8.1 s
Rated 100Normal pace: 9.0 × 100 ÷ 100
9.0 s
Rated 110Faster than normal: 9.0 × 110 ÷ 100
9.9 s
- Dashed line: the observed time, 9.0 s
Element 1 was timed at 9.0 seconds. Rated 90 it becomes 8.1 seconds of normal time, rated 100 it stays 9.0, and rated 110 it becomes 9.9.
Normal has to be defined before you rate, or 100 means whatever the observer feels that day. A common benchmark in American textbooks is walking at 3 miles an hour on level ground, or dealing a deck of 52 cards into four piles in half a minute. The ILO uses a 0 to 100 scale on which 100 is standard performance. Use your plant's definition, and practice rating the same film with a colleague until your numbers agree.
Allowances are time added for things that are part of working a shift but not part of the cycle. There are three kinds: personal needs, fatigue and unavoidable delays. The example table in the ILO's book starts with 5 to 7 percent for personal needs and 4 percent for basic fatigue, then adds for standing, posture, force and conditions. The junction box plant uses 15 percent in total. Yours should come from your own conditions and be agreed before the study, not chosen afterwards to make the number fit.
Standard time covers rating scales, allowance tables and the two ways of applying an allowance.
Calculate normal and standard time
Three formulas turn the sheet into a standard. Normal time = average observed time x rating / 100. Normal time per unit = the sum of the element normal times, including each occasional element divided by how often it happens. Standard time = normal time per unit x (1 + allowance).
Illustrative: from the sheet to a standard time
Example numbersStandard time = normal time × (1 + allowance)
Check: 80.5 seconds is 1.34 minutes a unit, or 2.24 standard hours per 100 units.
- Average observed time, five elements =9.0 + 15.0 + 23.0 + 12.0 + 6.0= 65.0 s
- Occasional element per unit =52.0 / 20= 2.6 s
- Observed time per unit =65.0 + 2.6= 67.6 s
- Normal time, elements 1 and 2 =(9.0 + 15.0) x 110 / 100= 26.4 s
- Normal time, the rest =(23.0 + 12.0 + 6.0 + 2.6) x 100 / 100= 43.6 s
- Normal time per unit =26.4 + 43.6= 70.0 s
- Standard time =70.0 x (1 + 0.15)= 80.5 s
- Units an hour =3,600 / 80.5= 44.7
Before you publish, test the number against the floor. If the bench has been turning out about 45 units an hour on a good day, 44.7 is believable. If it has been making 60, either the study or the output count is wrong, and you need to know which before anyone sees the standard.
The same procedure from video
Steps 1 to 4 and 7 to 10 do not change when a camera does the watching. Steps 5 and 6 do.
- Agree the filming with the operator first: what is in frame, who will see it and when it is deleted.
- Film one continuous take from a fixed position, with the hands, the parts and the full reach in frame.
- Film more cycles than you plan to use. Extra cycles cost nothing, and you can drop the first few while the operator settles.
- Mark break points on the timeline, not with a watch. At 30 frames a second one frame is 1/30 of a second.
- Rate the pace from the film, and ask a second person to rate the same cycles.
- Keep the film with the study, for as long as your retention rule allows. It is the evidence behind the standard.
One stopwatch tick against video frames
Stopwatch: 1 tick = 0.01 min = 0.6 s
Video: 0.6 s × 30 frames a second = 18 frames
Each frame is 1/30 of a second.
One tick of a decimal-minute stopwatch is 0.01 minute, which is 0.6 seconds. Video at 30 frames a second has 18 frames in that time.
In LeanSuite's time and motion study software, the marking and timing in steps 5 and 6 are drafted from the video: it times every element and cycle, and you correct the timeline and certify the study. The filming guide covers camera angle and distance.
Checklist: mistakes to catch before you sign the study
Go down this list with the finished sheet in front of you. It works just as well on a study someone else did.
Time study mistakes and what to do instead
Mistake
The method was not settled
What it does: The average mixes two or three ways of doing the job, and the spread between readings is wide
Do this instead
Agree and write down one method, then start the timing again
Mistake
Break points are vague
What it does: Two observers get different element times from the same cycle
Do this instead
Write the break point for each element as something seen or heard
Mistake
Too few cycles
What it does: The average can be several percent off and nobody knows
Do this instead
Plan from the General Electric guide and check with the formula before you stop
Mistake
No rating, or 100 for everything
What it does: The standard is the pace of one person on one day
Do this instead
Rate each element at the bench against a written definition of normal
Mistake
High readings deleted with no cause
What it does: The standard comes out too tight and the operator loses trust in it
Do this instead
Circle the reading and leave it out only with a noted cause
Mistake
Occasional work left out
What it does: Tote changes, restocking and checks are missing from the standard
Do this instead
Time each one and divide by the units it serves
Mistake
Machine time rated like hand work
What it does: Machine time gets stretched or shrunk by a rating that cannot apply to it
Do this instead
Time machine elements apart and leave them at 100
Mistake
Allowance chosen after the result
What it does: The allowance becomes a way to reach the number someone wanted
Do this instead
Use the plant's agreed allowance for that kind of work
Mistake
The operator was not told
What it does: The pace is unnatural, and the standard is disputed from the first day
Do this instead
Brief the operator and the supervisor before the study, and show them the sheet after
Mistake
The sheet has no method or date
What it does: Nobody can tell later whether the standard still applies
Do this instead
File the sheet with the method, layout, tools and date
Tools and templates for running a time study
- Time study sheet: the observation sheet in PDF and Excel.
- Time study sample size calculator: paste your first readings and get the number of cycles.
- Video time study filming checklist: 25 checks before you film.
- Time and motion study: what the study is for and when another method fits better.
- Standard time: rating and allowances in depth.
- Standard work: writing the method down once the times are set.
- Takt time: the number to compare your standard with.
Time and motion study software
Run a time study in LeanSuite
Time and motion study software that works from phone video: LeanSuite times every element, gives cycle and standard time, and draws a Yamazumi chart.
Go deeper
This page is the short version. These guides cover each part in full.
- Standard Work Tools: Combination Sheet, Standardized Work Chart, Job BreakdownWhere the element times go next: the combination table, the work chart and the job breakdown.
- The Three Elements of Standard Work: Takt Time, Work Sequence, Standard WIPSetting the timed work sequence against takt time.
- Value-Added vs Non-Value-Added Time in ManufacturingSorting each element on the sheet into value-added work, necessary work and waste.
- Yamazumi Chart: What It Is and How to Make One in 7 StepsDrawing the element times as a stacked bar for each operator.
All our articles on this subject are in the standard work, sops and training topic.
Free templates and tools
- Time study sheetTime each element over 10 cycles and work out the average, lowest repeatable and standard time. Excel does the sums.
- Video time study filming checklistA pre-shoot checklist and shot log for filming a time study on video: camera, light, people, settings, power and review.
- Standard work combination tableOne operator's manual, machine, walk and wait time on a time chart against takt, with machine cycles and a process capacity sheet.
- Standard work sheet templateTakt time, each element's manual, machine and walk time on a time chart, key points and standard WIP.
- Time study sample size calculatorHow many cycles of an element to time, from your first readings, with the t formula, the ILO formula and the range method.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
- Takt time calculatorThe pace a line must hit to meet customer demand, from shift time, breaks and daily demand.
Doing this in LeanSuite
Time and Motion Study
Film the station on a phone and LeanSuite times every element and cycle, gives cycle time and standard time, and draws a Yamazumi chart.
See Time and Motion StudyAI Video Analysis
Upload one process video and get time and motion, SMED, ergonomic and line balancing studies to review and certify.
See AI Video Analysis
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about how to conduct a time study
Settle the method first. Then split the job into elements with clear end points, time each element over enough cycles, and rate the operator's pace while you watch. Average the good readings, multiply by the rating to get normal time, and add the plant's allowance for personal needs, fatigue and delays. The result is the standard time for the job.
Ten steps: define the job and the goal, pick and brief the operator, standardize the method, break the job into elements, choose the timing method and the number of cycles, observe and record, rate the pace, set aside abnormal readings, calculate normal and standard time, then review and file. Some textbooks group the same work into five steps.
It depends on the cycle length and on how much the readings vary. The General Electric guide gives 30 cycles for a job of up to one minute, 20 for up to two minutes and 15 for up to five. The statistical formula, n = (t x s / (k x mean)) squared, uses your own first readings. Take the larger of the two for a standard that affects pay.
Normal time = average observed time x rating / 100. Standard time = normal time x (1 + allowance). For example, 67.6 seconds observed with two elements rated 110 gives 70.0 normal seconds, and a 15 percent allowance gives a standard time of 80.5 seconds. Some plants divide by 1 minus the allowance, so check which convention yours uses.
In continuous timing the stopwatch runs for the whole study and you write the reading at each break point, then subtract to get element times. In snap-back timing you return the watch to zero at each break point, so each reading is the element time. Continuous keeps every second on record. Snap-back is quicker but loses the time taken to reset.
Frederick W. Taylor. He began timing work with a stopwatch at the Midvale Steel Company in Philadelphia in 1881, splitting jobs into elements and timing each one. Frank and Lillian Gilbreth added motion study soon after, which is why the two are usually named together as time and motion study.
Use an observation sheet with the elements down the side and the cycles across the top. Fill in the job, operator, date and unit of time, then record each element of each cycle and a rating for each element. Note anything unusual as it happens. Afterwards, average the good readings, apply the rating and the allowance, and review the sheet with the operator.
Circle it on the sheet and write down what happened. Leave it out of the average only if you saw the cause and the cause is not part of the job, such as a dropped part or an interruption. A long reading with no known cause stays in. If the same problem keeps happening, it belongs in the delay allowance or on the improvement list.
Related guides and tools
- Time and motion study: what it is, why to do one and when to use another method
- Standard time: rating, allowances and the formula in depth
- Time study sample size calculator: how many cycles to time
- Time study sheet: the observation sheet in PDF and Excel
- Work sampling: for work too long or irregular to time cycle by cycle
- Line balancing: using the element times to share work across stations
- Standard work: the method the standard time belongs to
- How to film a time study the AI can read
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk
Or browse the topics, the full library and the lean glossary.
Rather see it on your own problem?
Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.