Practical guide · Standard work, SOPs and training
How to plan a time study: scope, operator, shift and the talk before it
Short answer
Plan a time study in this order: name the decision it feeds, pick the job, make the method stable, choose a trained operator who works at a normal pace, choose the shift and the product mix, and tell the operators and their supervisor why before anything is timed.
Most time studies that fail were lost before the first reading. The method changed halfway, the wrong person was timed, the hard product variant never ran, or the operators were not told and slowed down. Planning fixes all of that in a few hours. Write down the decision the study feeds and where the job starts and ends. Study the jobs with the most labour hours first. Standardise the method and the workplace before timing. Time a qualified operator, and more than one if you can, across the normal mix of products and times of day. Say what the study is for, and what it is not for, in person. Then set a date to check the standard again.
Last reviewed:
Why a time study is won or lost in the planning
The plan in one picture: nine steps in three phases, all before the first reading
Phase 1
Decide
Is this the right study?
- 1Name the decision
- 2Set the scope
- 3Check the job is worth it
Phase 2
Stabilise
Is the job ready to be timed?
- 4Make the method stable
- 5Choose the operator
- 6Choose the shift and the product mix
- 7Choose the method and the number of cycles
Phase 3
Tell and test
Do the people know, and does the setup work?
- 8Tell the people
- 9Run a short pilot
Time the job
Three phases in order. Decide: Name the decision, Set the scope, Check the job is worth it. Stabilise: Make the method stable, Choose the operator, Choose the shift and the product mix, Choose the method and the number of cycles. Tell and test: Tell the people, Run a short pilot. Then the study itself.
The timing is the easy part. Thirty cycles of a one minute job take half an hour to watch. What decides whether those thirty readings are worth anything was settled earlier: whether the method was stable, whether the person was the right one, whether the day was a normal day, and whether the operator trusted the reason for the study enough to work as they usually do.
A study that skips the planning still produces a number, and the number looks exactly as precise as a good one. That is the danger. This guide covers everything that happens before the watch starts. The timing itself is in how to conduct a time study.
How to plan a time study: nine steps
Allow two to four hours of planning for a first study of a job, spread over a few days so that people have time to hear about it before it happens.
- 1
Name the decision
Write one sentence: what will be decided with the result, and by whom. A quote, a headcount, a line balance and a pay standard need different accuracy, so this sets how careful the study must be.
- 2
Set the scope
Define the job, the product or family, the station, and the exact start and end points of the cycle. Say what is left out, such as material replenishment or changeovers.
- 3
Check the job is worth it
Rank it against the other jobs by labour hours a year. If it runs a few hours a year, estimate it and spend the study somewhere bigger.
- 4
Make the method stable
Watch the job. If two operators do it two ways, or the layout changes next week, fix that first and write the method down. A standard is only valid for the method that was timed.
- 5
Choose the operator
A qualified worker, trained and practised, who works at a normal pace and is willing. More than one where you can.
- 6
Choose the shift and the product mix
Pick times that cover the normal day, and the products that make up most of the volume, plus the hardest variant.
- 7
Choose the method and the number of cycles
Stopwatch or video, and how many cycles. How many cycles to time has the rule, and stopwatch time study covers the timing methods.
- 8
Tell the people
The supervisor first, then the union representative where there is one, then the operators, in person, at least a day ahead. Say what it is for and what it is not for.
- 9
Run a short pilot
Time five cycles. Check that your elements and break points work, that the camera sees both hands, and that nothing unusual is going on. Then book the study.
Scope: the decision, the boundaries and the accuracy
Scope answers three questions on half a page.
- What is the result for? Name the decision. The guide to why do a time study lists the eight it usually feeds.
- Where does the job start and stop? Give a break point you can see or hear: from picking up the housing to placing the finished valve in the tote. Without it, two studies of the same job will not agree.
- What is in and what is out? Fetching a new box of screws every 50 units is part of the job and has to be captured, as an occasional element spread over the 50. A changeover is a different job with its own study. Waiting for a late pallet is a delay to record, not work to time.
The decision sets the accuracy. A standard that will drive pay or a customer price on a high-volume part deserves more cycles, more than one operator and a second engineer checking the rating. A rough answer to whether a second person is needed can come from ten cycles. Decide which you are doing before you start, and write it on the study.
Which job to study first
There are always more jobs than engineer hours. The fair way to choose is by what an error would cost, and the simplest measure of that is labour hours a year: units a year x minutes a unit / 60. A 5 percent error on a job that uses 6,000 hours a year is 300 hours. The same error on a job that uses 300 hours is 15.
| Job | Units a year | Minutes a unit today | Labour hours a year | Share | Decision |
|---|---|---|---|---|---|
| Valve assembly | 288,000 | 1.40 | 6,720 | 44.6% | Study first |
| Packing | 288,000 | 0.78 | 3,744 | 24.8% | Study second |
| Housing deburr | 144,000 | 0.90 | 2,160 | 14.3% | Study third |
| Leak test | 288,000 | 0.35 | 1,680 | 11.1% | Mostly machine time: use the tester's cycle, study the load and unload |
| Kitting | 2,400 kits | 12.0 | 480 | 3.2% | Long and irregular: work sampling or an estimate |
| Rework bench | 6,000 | 3.0 | 300 | 2.0% | Do not set a standard. Reduce the rework |
| Total | 15,084 | 100% |
The first two jobs hold 69 percent of the labour hours and the first three hold 84 percent. Minutes a unit today can be a rough figure. It is only there to rank the jobs.
Rank the jobs by labour hours a year, then study from the top
Example numbersValve assembly
6,720 h · 45% so far
Time studyStudy first
Packing
3,744 h · 69% so far
Time studyStudy second
Housing deburr
2,160 h · 84% so far
Time studyStudy third
Leak test
1,680 h · 95% so far
Machine cycle: study the load and unload only
Kitting
480 h · 98% so far
Irregular: work sampling or an estimate
Rework bench
300 h · 100% so far
No standard. Reduce the rework
Six bars, longest first. Valve assembly: 6,720 hours. Packing: 3,744 hours. Housing deburr: 2,160 hours. Leak test: 1,680 hours. Kitting: 480 hours. Rework bench: 300 hours. Total 15,084 hours. The first three jobs hold 84 percent.
Hours are the first filter. A few other reasons move a job up the list whatever its hours.
- It is the bottleneck, so its time sets the output of everything else.
- It is new, and running on an estimate.
- Its method or tooling has changed since the last study.
- Operators or the union have challenged the standard.
- It is about to be quoted, moved, automated or rebalanced.
- It has an injury or a discomfort complaint attached, and the study can be combined with an ergonomic review.
And some jobs should come off the list. Work that is long and irregular suits work sampling better. Work that should not exist, such as sorting and rework, deserves a fix and not a standard.
Which operator to study
Study a qualified worker. In the ILO's definition that is someone with the physical attributes, the intelligence and education, and the skill and knowledge to do the job to satisfactory standards of safety, quantity and quality. In plain terms: trained, past the learning curve, and doing the job the standard way.
- Not the fastest person on the shift. Their pace is real but few can hold it, and a rating far above 100 is the least reliable kind. Their method is worth studying, though. If it is better, make it the standard method and teach it.
- Not the newest. Someone still learning hesitates, corrects and checks, and no rating repairs that.
- Someone who works at a steady, normal pace. Rating is most accurate close to 100 and gets worse the further the pace is from it.
- Someone who is willing. Ask them. A reluctant operator gives you a strained performance, fast or slow.
- Someone who follows the written method. If your best candidate has a private shortcut, settle the method first.
Who to time: the middle of the pace scale
Below normal pace
Still learning
Hesitates, corrects, checks the sheet
Do not study yet. No rating repairs a method that is not learned.
Near 100: normal pace
Qualified and steady
Trained, follows the written method, same rhythm all shift
Study this person. Rating is most accurate close to 100.
Well above normal pace
The fastest on the shift
A pace few can hold, often a private method
Study the method, not the time. If it is better, make it the standard and teach it.
A pace scale in three zones with 100, normal pace, in the middle. Below normal pace: Still learning. Do not study yet. No rating repairs a method that is not learned. Near 100: normal pace: Qualified and steady. Study this person. Rating is most accurate close to 100. Well above normal pace: The fastest on the shift. Study the method, not the time. If it is better, make it the standard and teach it.
More than one, if you can
One operator gives you that person's motion pattern, height, reach and rhythm. Two or three operators, on different shifts, average those out and make the standard easier to defend. The cost is a longer study. For a job done by one person it is not an option. For a job done by twenty, it is worth it.
Rating exists to correct for pace: observed time x rating = normal time. It corrects for speed of movement. It does not correct for a different method, an untrained hand or a bad day. Choosing the operator well is what keeps the rating close to 100, where it is trustworthy. Standard time covers rating in full.
Which shift, which day and which products
A study is a sample of the job, and the standard will be applied to all of it. So the sample has to look like the whole.
- Time of day. Do not take every reading in the first hour, when people are fresh and material is full, or in the last. Spread the cycles, or do two short sittings.
- Shift. If nights run with fewer material handlers or a different supervisor, the job is different there. Study both, or say on the study which shift it covers.
- Day. Avoid the day after a shutdown, a launch week, a stock count and any day with trainees on the line.
- Batch position. The first units after a changeover are slower than the steady state. Time the steady state, and treat the start-up as part of the changeover.
- Material. Parts from two suppliers can fit differently. Note the lot. If one is harder, it belongs in the mix.
- Product mix. Where several variants run on one station, study the high runner and the hardest variant at least, and weight the result by volume.
Weighting a standard by product mix
Illustrative example. A station builds three variants of a valve. Timed one by one, the standard times are 1.20, 1.50 and 2.10 minutes. They run in the proportions 70, 25 and 5 percent.
| Variant | Share of volume | Standard time | Share x time |
|---|---|---|---|
| A, the high runner | 70% | 1.20 min | 0.840 |
| B | 25% | 1.50 min | 0.375 |
| C, with the extra seal | 5% | 2.10 min | 0.105 |
| Weighted standard | 100% | 1.32 min |
Timing only variant A would have set 1.20 minutes, 9 percent under the real mix. Keep the three separate standards as well: the weighted figure is only right while the mix holds, and should be recalculated when it shifts.
A standard for the mix, not for the easy variant
Example numbersVariant A
0.70 x 1.20 min
= 0.840
Variant B
0.25 x 1.50 min
= 0.375
Variant C
0.05 x 2.10 min
= 0.105
Weighted standard
1.32 min
0.840 + 0.375 + 0.105
If only A is timed
1.20 min
9 percent under the real mix
A bar split by volume share: variant A 70 percent at 1.20 minutes, variant B 25 percent at 1.50 minutes, variant C 5 percent at 2.10 minutes. Share times standard time for each, added up, gives a weighted standard of 1.32 minutes. Timing only variant A would give 1.20 minutes.
Prepare the workplace: standardise before you time
A standard time belongs to one method under stated conditions. If the conditions on the day of the study are not the ones you intend to run with, the study measures the wrong job. Walk the station a day or two before and check it against this list.
- One method. Every operator on the job does the steps in the same order with the same hands. If not, agree the method with them and the supervisor, and write it on a standard work sheet.
- Obvious waste removed. If parts are behind the operator and could be in front, move them now. Timing first and improving later means doing the study twice. The guide to time study vs motion study vs method study explains why the method comes first.
- Material at the point of use, in the normal containers, at the normal fill level.
- Tools and fixtures in good order. No worn bit, no jammed clamp, no borrowed torque wrench.
- Machine at its standard speeds and feeds, with the correct program.
- Quality normal. If the line is fighting a defect, the extra checks and rework will be in the readings.
- The workplace in its normal state: lighting, bench height, floor mats, protective equipment. A quick 5S check is enough.
- Conditions recorded. Write down the layout, the tools, the material and the machine settings, with a photo. Without that record nobody can tell later whether the job has changed.
If the job fails several of these, the right output of the visit is a list of fixes, not a study date. That is still progress. It is method study doing its job.
Telling the operators: a script, and what never to say
Being timed is uncomfortable. People hear time study and think rate cut, or job cut, and plants have earned that reaction over a hundred years. An operator who believes it will not work at a normal pace, and you will not be able to tell by how much. So the talk before the study is not a courtesy. It is part of the measurement.
Do it in person, at the station or in the team's own meeting, at least a day ahead. The supervisor should be there and should have heard it first. Keep it to two minutes and leave time for questions. Something like this:
- What and when. "On Thursday morning I'd like to time the valve assembly job for about forty minutes. I'll set up a camera on a tripod here, pointed at the bench and your hands."
- Why. "We're quoting two new valve sizes next month and the time we hold for this job is an estimate from three years ago. I need the real one."
- What it measures. "I'm timing the job, not you. I'll split it into steps and time each step over about thirty cycles."
- What I need from you. "Please work the way you normally do, at the pace you'd keep up all day. Not faster for my benefit. If something goes wrong, a jammed part or a missing box, just deal with it as you normally would and I'll note it."
- What happens to it. "I'll bring the results back to you before they go anywhere else. If a step looks wrong to you, I want to hear it. The video stays with engineering and is used for this study."
- What it is not for. Say this only if it is true: "This is not about your pay and it is not about cutting people from this cell."
- Questions. "What would you like to know?" Then wait.
| Say | Never say | Why |
|---|---|---|
| "I'm timing the job, not you." | "Just ignore me, pretend I'm not here." | Nobody can ignore being timed. Admit it is odd and explain what you are doing. |
| "Work at the pace you'd keep up all day." | "Let's see how fast you can go." | You want a normal pace near a rating of 100. A sprint gives a time nobody can hold. |
| "It's for the quote on the new sizes." | "It's just routine." or "Management wants it." | A vague purpose sounds like a hidden one. Name the decision. |
| "This won't affect pay or headcount here." Only if true. | "Nothing will change." | Something will change, or there would be no study. A promise you break once ends every later study. |
| "You'll see the results first, and you can challenge them." | "The numbers don't lie." | They can. Break points, rating and allowances are judgements. Let the person who does the job check them. |
| "If something goes wrong, handle it as usual." | "Try to keep it clean for the camera." | The delays are part of the job. Hiding them makes the standard too tight. |
| "Do you mind being the one I time?" | "You've been picked." | A willing operator works normally. A drafted one does not. |
The questions you will get
- "Will this be used to raise the rate?" Answer with what you know. If the standard may change, say that it may go either way, that it will be set for a normal pace with allowances, and how it can be challenged.
- "Why me?" Because you are trained on the job and work at a steady pace, which is what the method asks for. Say that it is a compliment, because it is.
- "What if I have a bad morning?" Then we stop and do it another day. One bad run is no use to either of us.
- "Who sees the video?" Name the people and the purpose, and say how long it is kept. If you do not know your site's rule on filming employees, find out before you film.
- "What do I get out of it?" Usually the fixes. Studies turn up the missing fixture and the rack in the wrong place. Promise to bring back the list of problems you saw, and do.
The conversation skills are the same as for any hard talk on the floor. The guides to difficult conversations at work and resistance to change on the shop floor go deeper, and language barriers on the shop floor covers the case where the operator and the engineer do not share a first language.
Unions, consent and the observer effect
Where there is a union or works council
This is general practice, not legal advice. Rules differ by country and by agreement, so read yours and ask your HR or labour relations lead before the first study.
- Read the agreement. Many contain clauses on work measurement: notice before a study, who may be studied, the union's right to see the data or to have its own time study representative check it, and how a standard is challenged.
- Tell the representative before the operators hear it from someone else. Explain the purpose and the method, and invite them to watch.
- Never time in secret. A hidden stopwatch or camera is the fastest way to lose the right to study at all, and in some places it is unlawful.
- Share the working, not only the answer: the elements, the readings, the rating and the allowances.
- Agree how a disputed standard is reviewed before there is a dispute. A joint re-study is the usual route.
- Ask about filming. Recording people at work can need notice, consent or consultation depending on where you are.
The history is worth knowing because the people across the table know it. In 1911 a time study began at the US Army's Watertown Arsenal without the workforce being prepared for it, and the moulders walked out. Congress went on to bar stopwatch timing in army arsenals and navy yards for decades. The method was the same one used peacefully elsewhere. What differed was how it was introduced.
The observer effect
People work differently when they are watched. It is often called the Hawthorne effect, after studies at Western Electric's Hawthorne Works in the 1920s. On the floor it goes both ways: some people speed up to look good, and some slow down to protect the standard. You cannot remove it. You can shrink it and check for it.
- Explain the purpose properly. Most deliberate slowing comes from fear of what the number will be used for.
- Let the first cycles go. People settle after a few minutes. Start recording, and start counting later.
- Take more cycles, over more than one sitting. An act is hard to keep up.
- Study more than one operator.
- Use video left running on a tripod. A camera in the corner is forgotten sooner than a person standing at your shoulder with a watch. It must still be announced.
- Rate the pace. That is what rating is for. A second engineer rating the same footage is a useful check.
- Compare with the output records. If the study says 1.40 minutes and the cell has averaged 1.9 for a year, either there are losses the study did not see or the study day was not normal. Find out which before issuing anything.
The observer effect on a cycle chart: let the first cycles go
Example numbers- Settling, not counted
- Counted cycles, minutes each
- Mean of the counted cycles: 1.25 min
A column chart of 35 cycle times. The first 5 cycles are fast, from 1.06 to 1.22 minutes, while the operator is aware of being timed, and are not counted. The next 30 cycles settle around a mean of 1.25 minutes and are the ones used.
The time study request form
When more than one person asks engineering for studies, a one page request form stops the queue being run by whoever shouts. It also forces the requester to name the decision, which removes about half the requests. These are the fields that earn their place.
| Field | What goes in it | Why it is there |
|---|---|---|
| Requested by, date | Name, role, department | Someone owns the question |
| Job and station | Operation name and number, line, part numbers or family | Sets the scope |
| Decision the result feeds | Quote, headcount, balance, layout change, standard update, ergonomic review | Sets the accuracy and the priority |
| Needed by | A date, and what happens on that date | Separates real deadlines from preferences |
| Volume | Units a year and current minutes a unit, if known | Gives labour hours a year, for ranking |
| Current standard | The time in the system, its date and its source: study, estimate or history | Shows whether this is a first study or a re-study |
| What has changed | Method, tooling, material, layout, product, volume, or nothing | A change is a trigger. Nothing changed means ask why now |
| Method status | Is there a current written method? Do all operators follow it? | If not, the first job is method work, not timing |
| Shifts and variants to cover | Which shifts run the job, and the product mix | Plans the sittings |
| People informed | Supervisor, union representative, operators: yes or no, and by whom | No study is booked until this says yes |
| Engineering use | Priority, method chosen, study date, analyst, date issued | Tracks the request to a result |
How often to re-study, and what triggers it
A time standard has no fixed shelf life. It is valid for as long as the method it describes is the method in use. So the real answer to how often is: whenever the job changes, and on a schedule as a backstop for the changes nobody reported.
Triggers: re-study when one of these happens
| Trigger | Example | What to do |
|---|---|---|
| Method change | Steps added, removed or reordered; a kaizen on the station | Re-study the changed elements |
| Tooling or equipment change | A new fixture, a powered driver in place of a manual one, a faster machine cycle | Re-study the elements that use it |
| Layout change | The rack moved, the cell rearranged, a conveyor added | Re-study the walking and handling elements |
| Material or design change | A new supplier, a different fastener, an engineering change to the part | Check the affected elements. Re-study if they differ |
| Quality requirement change | An added inspection, a tighter torque check | Add or re-time the element |
| Batch size or mix change | Smaller lots, a new variant, the mix shifting toward the hard one | Recalculate the weighted standard. Study any new variant |
| Performance out of line | The cell runs well above or well below 100 percent of standard for weeks | Audit the standard. Something has changed, or the standard was wrong |
| A challenge | An operator, supervisor or union representative disputes the time | Review it with them. Re-study jointly if it does not hold up |
Link the first five to your change process. If an engineering change or a 4M change form asks whether a time standard is affected, most triggers report themselves.
The schedule: audit by how much the standard is used
Small changes creep in without a form: a different glove, a tote moved a step further away, a shortcut that became the method. A periodic audit catches them. A common rule of thumb in the industrial engineering handbooks sets the interval by how many labour hours a year the standard governs.
| Hours a year the standard is applied to | Audit at least every |
|---|---|
| More than 600 hours | 6 months |
| 50 to 600 hours | 12 months |
| Less than 50 hours | 24 months |
A convention from the time standards chapter of the Handbook of Industrial Engineering. Niebel and Freivalds give a similar table. Treat it as a starting point and set your own.
How often to audit a standard: the more hours it governs, the shorter the interval
More than 600 hours a year
Every 6 months: 4 in two years
50 to 600 hours a year
Every 12 months: 2 in two years
Less than 50 hours a year
Every 24 months: 1 in two years
Three 24 month timelines. More than 600 hours a year: an audit every 6 months, 4 in two years. 50 to 600 hours a year: an audit every 12 months, 2 in two years. Less than 50 hours a year: an audit every 24 months, 1 in two years.
An audit is not a full study. Watch ten cycles, compare the method with the one on file, and compare the cycle time with the standard. If the method matches and the time is close, sign and date it. If not, book a re-study. Fifteen minutes at the station is usually enough to tell.
An annual study plan
Put the triggers and the schedule together once a year and you have a plan engineering can staff. Build it in four passes.
- 1
List every standard
Job, standard time, date set, source (study, estimate, history), date of last audit, and labour hours a year.
- 2
Band them by hours
Over 600 hours, 50 to 600, under 50. The top band is short and carries most of the labour.
- 3
Add the known changes
New products, planned layout moves, kaizen events and equipment arriving in the year. Each one is a study with a date.
- 4
Add up the hours and spread them
Audits by band, plus the re-studies you expect, plus the new jobs. Spread them across the months and name an owner for each.
| Band | Standards | Audits a year | Working |
|---|---|---|---|
| Over 600 hours a year | 8 | 16 | 8 x 2 a year |
| 50 to 600 hours a year | 22 | 22 | 22 x 1 a year |
| Under 50 hours a year | 30 | 15 | 30 / 2, one every two years |
| Total | 60 | 53 | 53 audits x 1.5 hours = 79.5 hours |
| Re-studies from failed audits | 11 | Assume 1 in 5 fails: 53 x 0.2 = 10.6, so 11 x 6 hours = 66 hours | |
| Engineering hours for the year | 79.5 + 66 = 145.5 hours |
The 1.5 hours an audit, 6 hours a re-study and the 1 in 5 failure rate are planning assumptions for this example. Replace them with your own after the first year. New products and planned changes come on top.
About 146 hours is under a month of one engineer's year, to keep 60 standards honest. Plants that skip it do not save the month. They spend it later in arguments about numbers nobody trusts.
Time study planning checklist
One page to fill in before the study. If any line is a no, the study is not ready.
Time study planning checklist
Job and station
Study date
Analyst
1The study
Purpose. The decision the result feeds is written down. Ready when: one sentence, with the name of the person who will use it.
Scope. Job, product, station, start point and end point are defined. Ready when: two engineers would time the same thing.
Priority. The job is worth a study. Ready when: ranked by labour hours a year, or a named trigger applies.
2The job
Method. There is one current written method and operators follow it. Ready when: watched on the floor, not assumed.
Workplace. Material, tools, machine settings and quality are normal. Ready when: walked the day before. Conditions recorded with a photo.
Timing. Shift, day and time are typical. Ready when: no launch, trainee, stock count or start-up in the window.
Product mix. Variants to cover are listed with their volume shares. Ready when: high runner and hardest variant both scheduled.
Method of timing. Stopwatch or video chosen. Number of cycles set. Ready when: sheet prepared, or camera position tested.
Elements. A first element list with break points exists. Ready when: tried on five pilot cycles.
3The people
Operator. A qualified operator at a normal pace has agreed to be studied. Ready when: asked, not assigned. A second operator named if possible.
Supervisor. Briefed, and agrees the date. Ready when: before the operators are told.
Union or works council. Informed as the agreement requires. Ready when: before the operators are told. Invited to observe.
Operators. Told what, why, when, and what it is not for. Ready when: in person, at least a day ahead. Questions answered.
Filming. Site rule on recording people checked. Ready when: notice or consent in place.
4Afterwards
Afterwards. Date set to share results with the operators. Ready when: before the standard is issued.
Review date. Next audit date decided. Ready when: written on the study.
Templates and tools
With video, most of the plan is the same and one part is easier: the readings can be checked afterwards by the operator, the supervisor and a second engineer. LeanSuite's time and motion study times each element on a timeline linked to the footage you upload, for an engineer to review and certify. The filming guide covers where to put the camera.
- Video time study filming checklist: camera position, what to tell the team and what to check before you leave the station.
- Time study sheet: elements, cycles, rating and allowances.
- Standard work sheet: to write the method down before timing it.
- 4M change management sheet: the change record that should trigger a re-study.
- Time study sample size calculator: how many cycles to time.
- Time study mistakes: what to look for in a finished study.
Time and motion study software
Run a time study in LeanSuite
Time and motion study software that works from phone video: LeanSuite times every element, gives cycle and standard time, and draws a Yamazumi chart.
Go deeper
This page is the short version. These guides cover each part in full.
- Standard Work in Manufacturing: A Complete GuideWriting the method down, which has to happen before a time is put on it.
- Auditing Standard Work: Verification and Compliance ChecksHow to check on the floor that the method on file is the method in use.
- How to Improve Shop Floor ProductivityWhat to do with the losses the study turns up.
- The Three Elements of Standard Work: Takt Time, Sequence and WIPWhere the timed sequence goes once the study is done.
All our articles on this subject are in the standard work, sops and training topic.
Free templates and tools
- Video time study filming checklistA pre-shoot checklist and shot log for filming a time study on video: camera, light, people, settings, power and review.
- Time study sheetTime each element over 10 cycles and work out the average, lowest repeatable and standard time. Excel does the sums.
- Standard work sheet templateTakt time, each element's manual, machine and walk time on a time chart, key points and standard WIP.
- 4M change management sheet (change point)A shift log of every change to Man, Machine, Material, Method or Design, the extra checks after it and when normal checks resume, with a change point board.
- Time study sample size calculatorHow many cycles of an element to time, from your first readings, with the t formula, the ILO formula and the range method.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
- Takt time calculatorThe pace a line must hit to meet customer demand, from shift time, breaks and daily demand.
Doing this in LeanSuite
Time and Motion Study
Film the station and the AI times every element on a timeline that links to the video, split into value-added, necessary and waste.
See Time and Motion StudyAI Video Analysis
Turns video of real work into time studies, line balance charts, changeover splits and other studies you review and certify.
See AI Video Analysis
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about how to plan a time study
Name the decision the result feeds, define where the job starts and ends, check the job is worth studying by its labour hours a year, make the method stable and write it down, choose a trained operator who works at a normal pace, pick a typical shift and the real product mix, tell the supervisor and operators why in person, and run five pilot cycles before the study.
A qualified worker: trained, past the learning curve, following the standard method and working at a steady, normal pace. Not the fastest person and not the newest. Ask them, do not assign them. Where several people do the job, study two or three on different shifts so the standard does not rest on one person's rhythm.
Tell them in person, at least a day ahead: what will be timed and when, the decision the result is for, that the job is being timed and not the person, that you want their normal all-day pace, that they will see the results first and can challenge them, and what the study will not be used for, if that is true.
Whenever the method, tooling, layout, material or product changes, and on a schedule as a backstop. A common rule of thumb from the industrial engineering handbooks is to audit a standard every 6 months if it governs more than 600 labour hours a year, every 12 months for 50 to 600 hours, and every 24 months below 50 hours.
A change to the method, the tooling or equipment, the layout, the material or part design, the quality checks, or the batch size and product mix. Also a cell that runs well above or below the standard for weeks, and a challenge from an operator, supervisor or union representative. Tie the first group to your engineering change process.
Yes. A standard time is only valid for the method that was timed. If two operators do the job in two ways, or parts and tools are not in their normal places, the study measures something that will not be repeated. Agree the method, remove the obvious waste, write it down, and then time it.
As general practice, not legal advice: read the agreement for clauses on work measurement, tell the union representative before the operators hear of it, invite them to observe, never time in secret, share the readings, rating and allowances as well as the result, and agree in advance how a disputed standard will be reviewed.
Often, yes. Some speed up and some slow down. Reduce it by explaining the purpose, letting the first few cycles go, taking more cycles over more than one sitting, studying more than one operator, and rating the pace. Then compare the result with the cell's output records. A large gap means the study day was not normal.
Related guides and tools
- How to conduct a time study: the timing itself, step by step
- How to break a job into elements, with break points
- How many cycles to time: the sample size rule
- Why do a time study: the eight decisions it feeds
- Time study mistakes and how to spot them in a finished study
- Difficult conversations at work: scripts for the shop floor
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk
Or browse the topics, the full library and the lean glossary.