Practical guide · Standard work, SOPs and training
From time study to standard work: the three documents, filled in from one study
Short answer
A time study becomes standard work through three documents, filled in order. The process capacity table shows whether the machines can keep up. The combination table shows whether one operator can do the work inside takt time. The standard work chart shows the result on the layout.
Take three kinds of time from the study for every element: manual time, machine time and walking time. Put manual and machine time on the process capacity table to find what each machine can make in a shift. Put all three on the standard work combination table and draw them against takt time. If the operator's work fits, draw the standard work chart with the sequence, the walking path and the standard in-process stock, train every operator on it and post it at the cell. In the example on this page, 57 seconds of manual work and 14 seconds of walking fit an 80 second takt time, and the slowest machine can make 405 pieces a shift against 345 needed.
Last reviewed:
What a time study turns into
One time study, three documents, one posted standard
Example numbersStart: the time study
Six elements timed over several cycles at the valve body cell
Manual work 57 s, walking 14 s, four machine cycles from 20 s to 55 s. Takt time is 80 s.
- 1
Process capacity table
Can every machine make enough?
From the study
Manual time and machine time at each machine, plus tool changes.
The mill is the limit: 405 pieces a shift against 345 needed.
- 2
Standard work combination table
Can one person do it inside takt time?
From the study
Manual, machine and walking time for every element, in sequence.
71 s of work and walking inside an 80 s takt time.
- 3
Standard work chart
Where does the operator go, and where do the parts sit?
From the study
The sequence and the cycle time from the table, drawn on the layout.
One loop of six stops, with 4 pieces of standard in-process stock.
Finish: the handover
Operators on every shift are trained on the sequence, and the chart is posted at the cell
The capacity table and the combination table stay in the engineer's file. The chart is the one people work to.
A flow from top to bottom. A time study of six elements gives manual time 57 seconds, walking 14 seconds and four machine cycles. Those times fill three documents in order: the process capacity table, the standard work combination table and the standard work chart. The chart is then taught to the operators and posted at the cell.
A time study ends with a sheet of element times. That sheet is evidence, not a standard. Nobody can work to it, and nobody can audit against it. Standard work is what you build from it: an agreed sequence that one person can repeat inside takt time, with a fixed number of pieces in the process.
The Lean Enterprise Institute's Lean Lexicon names three basic forms for building it, and they are used together. Each one takes different numbers from the study and answers a different question. The order matters, because each answer is needed by the next sheet.
| Document | Question it answers | Numbers it takes from the study | Who uses it |
|---|---|---|---|
| 1. [Process capacity table](/templates/process-capacity-sheet) | Can every machine make what the customer needs in a shift? | Manual time and machine time at each machine, tool change time and how often. | The engineer and the supervisor, when the cell is set up and whenever demand changes. |
| 2. [Standard work combination table](/templates/standard-work-combination-table) | Can one operator do the whole sequence inside takt time? | Manual, machine and walking time for every element, in the order they are done. | Whoever designs the job. It is the working drawing. |
| 3. [Standard work chart](/templates/standard-work-sheet) | Where does the operator go, and where do the parts sit? | The sequence and cycle time from the combination table, plus the layout. | Operators, team leaders and anyone auditing the cell. It is posted. |
Names vary. The capacity table is also called a process capacity sheet or production capacity sheet, the combination table a combination sheet, and the chart a standard work sheet or layout sheet.
What to bring from the time study
Most studies that fail to turn into standard work were timed the wrong way for it. One stopwatch reading per element is not enough, because the three documents need the element split by who or what is doing the work.
- Manual time for each element: hands on the part or the machine. Loading, unloading, pressing start, deburring, gauging, packing.
- Machine time for each machine: from start pressed to cycle finished, with the operator gone. If the operator has to stand and hold something while it runs, that is manual time.
- Walking time between each pair of stops, written on the element the operator walks away from.
- Tool change time at each machine, and how many pieces are made between changes.
- The working time in a shift and the customer demand for the same shift, to get takt time.
- A sketch of the layout with the stops numbered in the order the operator visits them.
One choice has to be made before you start: which time to write down. Toyota-style standard work usually takes the shortest time the operator can repeat cycle after cycle, with no allowances added, and treats waiting as something to show on the sheet. Classic work measurement builds a standard time from a rated average plus allowances. Both can be defended. Pick one for all three documents and write on the sheet which it is, or the capacity table and the combination table will not agree with each other.
Document 1: the process capacity table
Start with the machines, because a person cannot make up for a machine that is too slow. The Lexicon describes this form as calculating the capacity of each machine in a linked set of processes, to confirm true capacity and find bottlenecks. It has one row per machine.
For each machine, add the manual time and the machine time to get the completion time for one piece. Then spread the tool change over the pieces made between changes: a 300 second change every 150 pieces costs 2 seconds a piece. Capacity for the shift is the working time divided by the sum. In words: capacity = working time in the shift / (manual time + machine time + tool change time / pieces between changes).
| Machine | Manual (s) | Machine (s) | Tool change | Time per piece (s) | Capacity per shift |
|---|---|---|---|---|---|
| Lathe | 9 | 42 | 120 s every 100 pieces = 1.2 s | 52.2 | 528 |
| Mill | 11 | 55 | 300 s every 150 pieces = 2.0 s | 68.0 | 405 |
| Drill | 8 | 28 | 180 s every 200 pieces = 0.9 s | 36.9 | 747 |
| Leak tester | 7 | 20 | None | 27.0 | 1,022 |
The shift is 460 minutes of working time: 460 x 60 = 27,600 seconds. Demand is 345 pieces, so takt time is 27,600 / 345 = 80 seconds. Capacities are rounded down to whole pieces.
The process capacity table, drawn
Example numbers- Manual (load, unload, start)
- Machine cycle
- Tool change, per piece
- Takt time, 80 s
Lathe9 + 42 + 120 / 100 = 52.2 s a piece27,600 / 52.2 = 528 pieces a shift
MillLowest capacity11 + 55 + 300 / 150 = 68.0 s a piece27,600 / 68.0 = 405 pieces a shift
Drill8 + 28 + 180 / 200 = 36.9 s a piece27,600 / 36.9 = 747 pieces a shift
Leak tester7 + 20 = 27.0 s a piece27,600 / 27.0 = 1,022 pieces a shift
Demand is 345 pieces a shift. The lowest capacity in the cell is 405, so the machines pass. If any machine came out under 345, the fix belongs at that machine before anyone draws a combination table.
Four machines as bars of time per piece against a takt time of 80 seconds. Lathe: 52.2 seconds a piece, 528 pieces a shift. Mill: 68.0 seconds a piece, 405 pieces a shift. Drill: 36.9 seconds a piece, 747 pieces a shift. Leak tester: 27.0 seconds a piece, 1022 pieces a shift. The mill is the slowest and still clears the 345 pieces needed.
Read the last column against demand. The mill is the limit at 405 pieces, 60 more than the 345 needed, so the machines pass. Read the time per piece against takt time too: 68.0 seconds is under 80. If a machine came out below demand, stop here. The choices are a faster cycle, fewer or quicker tool changes, a second machine or overtime, and none of them is fixed by rearranging the operator's work.
What this table leaves out: breakdowns, scrap and minor stops. It gives the capacity of a machine that runs all shift. If your mill loses a tenth of its time to stops, its real capacity is nearer 365 than 405, and the gap to 345 is thin. Use your own downtime records, not a rule of thumb.
Document 2: the standard work combination table
Now the operator. List the elements in the order they are done and write the three times beside each one. The Lexicon describes this form as showing the combination of manual work time, walk time and machine processing time. It is the only one of the three that shows a person and several machines working at the same moment.
| Element | Manual | Machine runs alone | Walk to next |
|---|---|---|---|
| 1. Unload and load the lathe, start it | 9 | 42 | 2 |
| 2. Unload and load the mill, start it | 11 | 55 | 2 |
| 3. Unload and load the drill, start it | 8 | 28 | 3 |
| 4. Unload and load the leak tester, start it | 7 | 20 | 2 |
| 5. Deburr and gauge the bore | 14 | 0 | 2 |
| 6. Pack the part, pick up a casting | 8 | 0 | 3 |
Manual: 9 + 11 + 8 + 7 + 14 + 8 = 57 seconds. Walking: 2 + 2 + 3 + 2 + 2 + 3 = 14 seconds. Operator cycle: 57 + 14 = 71 seconds.
The combination table for the valve body cell
Example numbers- Manual work
- Machine runs alone
- Walking
- Waiting
- Takt time
1. Unload and load the lathe, start itManual 9 s, machine 42 s, walk 2 s
2. Unload and load the mill, start itManual 11 s, machine 55 s, walk 2 s
3. Unload and load the drill, start itManual 8 s, machine 28 s, walk 3 s
4. Unload and load the leak tester, start itManual 7 s, machine 20 s, walk 2 s
5. Deburr and gauge the boreManual 14 s, walk 2 s
6. Pack the part, pick up a castingManual 8 s, walk 3 s
Operator cycleManual 57 s + walk 14 s = 71 s, wait 9 s
Six elements on a time line from 0 to 90 seconds. Manual work and walking run end to end and finish at 71 seconds, 9 seconds before the takt line at 80 seconds. The four machines run on their own after the operator walks away, and each has finished before the operator comes back to it.
The operator's cycle is manual time plus walking: 71 seconds, which is 9 seconds inside the 80 second takt time. Machine time is not added, because the operator has walked on while each machine runs. Then check each dashed line: has the machine finished before the operator comes back to it? The mill takes 11 + 55 = 66 seconds from the moment the operator arrives, and the operator is back 71 seconds later. It has, with 5 seconds to spare.
The 9 seconds left over are waiting. Write them on the sheet as waiting. They are the first thing to use if demand rises, and the honest thing to show if it does not. For how to draw each line, what to do when a machine runs past the end of the cycle and how to read the finished sheet, see the guide to the standard work combination table.
Document 3: the standard work chart
The first two documents are for working the job out. The third is for running it. The Lexicon describes the standardized work chart as showing operator movement and material location in relation to the machines and the layout, and says it should show takt time, cycle time, work sequence and standard in-process stock. It is the one posted at the cell.
- The layout, seen from above, with each machine and bench as a box in roughly the right place.
- The stops numbered in the order of the combination table, joined by arrows for the walking path.
- Takt time and cycle time: here 80 seconds and 71 seconds.
- Standard in-process stock, marked where it sits. Here it is 4 pieces, one in each machine. How to calculate standard WIP covers cells where the count is less obvious.
- Quality checks and safety points, each marked at the stop where it applies. A diamond for a quality check and a cross for a safety point are common marks, and they are a convention: use whatever your plant already recognises.
- The revision, the date and who approved it.
The standard work chart for the same cell
Example numbersLathe
9 s hand, 42 s machine
Mill
11 s hand, 55 s machine
Drill
8 s hand, 28 s machine
Takt 80 s
Cycle 71 s
Stock 4
Pack
8 s by hand
Deburr and gauge
14 s by hand
Leak tester
7 s hand, 20 s machine
- Standard in-process stock
- Quality check
- Safety point
- Walk, with seconds
The cell seen from above. The operator walks one loop: lathe, mill and drill along the top, then the leak tester, deburr and gauge, and pack along the bottom, and back to the lathe. Each of the four machines holds one piece of standard in-process stock. Takt time 80 seconds, cycle time 71 seconds.
Keep it to one page that can be read from where the team leader stands. Step by step detail does not belong on it. If an element needs a knack, a setting or a photo, that goes on a work instruction or a job breakdown sheet, and the chart just names the element. Standard work vs SOP vs work instruction shows how the three fit together.
Three checks before you post it
The three documents exist to settle three questions. If you only remember one thing from this page, remember these, because a standard that fails any of them cannot be followed no matter how well it is drawn.
- Machine against takt time. The slowest machine's time per piece, tool changes included, must be under takt time. Here: 68.0 seconds against 80.
- Operator against takt time. Manual time plus walking must be at or under takt time. Here: 71 seconds against 80.
- Machine against the operator's return. Each machine must finish before the operator comes back to unload it. Here: the mill needs 66 seconds and the operator is back in 71.
Three checks before the standard is posted
Example numbers1. Slowest machine against takt
From the capacity table: the mill needs 68.0 s a piece, tool changes included.
12 s inside
2. Operator cycle against takt
From the combination table: 57 s manual plus 14 s walking is 71 s.
9 s inside
3. Machine done before return
From the combination table: the mill takes 66 s from load to finish, and the operator is back every 71 s.
5 s inside
Three bars, each against a limit. The slowest machine takes 68.0 seconds a piece against a takt time of 80 seconds. The operator's cycle is 71 seconds against the same takt time. The mill needs 66 seconds from load to finish, and the operator is back at it every 71 seconds.
When a check fails, the fix is on the floor, not on the paper. Shorten a walk, move a check to a different stop, change the order, take a tool change offline. Then time it again and redraw.
The handover to operators
A standard that arrives from the engineering office on a Monday morning gets followed while someone is watching. The handover is where it becomes the operators' own method, and it starts before the chart is finished.
The handover, from draft to audited standard
- 1
Walk the draft with the operators
- 2
Run a trial
- 3
Train with a job breakdown
- 4
Sign and date it
- 5
Post the chart, file the tables
- 6
Audit in the first week
- 1
Walk the draft with the operators
Take the combination table and the draft chart to the cell and walk the loop with the people who run it, on each shift. Ask what is awkward and what gets skipped late in the shift. Change the draft where they are right.
- 2
Run a trial
Run the sequence for a shift with the draft marked TRIAL. Time ten cycles. If the times do not match the table, find out why before you go further.
- 3
Train with a job breakdown
Teach each operator with a job breakdown sheet: the important steps, the key points and the reasons. TWI Job Instruction's four steps fit this well: prepare the worker, present the operation, try out performance, follow up.
- 4
Sign and date it
The supervisor, the engineer and quality sign the chart. Give it a revision letter and a date. An unsigned chart is a suggestion.
- 5
Post the chart, file the tables
Post the chart at the cell where it can be read from the aisle. File the capacity table and the combination table with the study, because you will need them the day demand changes.
- 6
Audit in the first week
Stand at the cell with the chart and time a few cycles. Where the work and the chart differ, decide which one is wrong and fix that one.
Operators are wary of time studies, usually for good reason: they have seen a stopwatch followed by a higher target. Say plainly what the times are for. Share the sheet. Make it clear that the time belongs to the method, not to the person, and that a slow cycle is a question about the job. Do not build the standard on the best cycle of your fastest operator and hold everyone else to it.
After the handover the standard is a baseline, and it is expected to change. Updating standard work after an improvement covers the loop of study, change, re-study and reissue.
Common mistakes
- Skipping the capacity table. The combination table then shows an operator who fits takt time at a machine that cannot.
- Timing each element as one number. Without manual, machine and walking time split out, the combination table cannot be drawn.
- Adding machine time to the operator's cycle. The cell looks overloaded when the operator is free for most of every machine run.
- Leaving tool changes out of capacity. Without them the mill in the example looks good for 418 pieces a shift. With them it is 405.
- Drawing the chart from the layout drawing instead of the floor. The bench that was moved last year is still on the drawing.
- Posting all three documents. The wall fills with paper nobody reads. Post the chart and keep the other two in the file.
- Using it where nothing repeats. A changeover, a repair or a job shop one-off has no cycle to pace against takt time. Use an SOP or a checklist there.
Where software helps
The slow part of all this is the timing. In LeanSuite's Time and Motion Study you film the work, the AI drafts the element times on a timeline that links back to the video, and you check and certify the study. That gives you the element list and the times this page starts from. The process capacity table, the combination table and the standard work sheet themselves are free LeanSuite templates, not modules in the software. Standardized work software explains what each part does and does not do.
Standardized work software
Keep standard work current in LeanSuite
LeanSuite covers most of the cycle in one platform: working out the standard with Vision AI, keeping it current with SOPs and work instructions, and training and auditing it.
Go deeper
This page is the short version. These guides cover each part in full.
- Standard Work Tools: Combination Sheet, Standardized Work Chart, Job BreakdownMore on each form, including the job breakdown sheet used in the handover.
- The Three Elements of Standard Work: Takt Time, Work Sequence, Standard WIPThe three elements the documents record, each in more depth.
- TWI Job Instruction: The Training Method Behind Standard WorkThe four-step method for teaching the standard to each operator.
- Auditing Standard Work: Verification and Compliance ChecksHow to check, after the handover, that the posted method is the one being followed.
All our articles on this subject are in the standard work, sops and training topic.
Free templates and tools
- Process capacity sheet templateEach machine in a part's routing with manual, auto and tool change time, its capacity per shift, and the step that limits the cell against demand.
- Standard work combination tableOne operator's manual, machine, walk and wait time on a time chart against takt, with machine cycles and a process capacity sheet.
- Standard work sheet templateTakt time, each element's manual, machine and walk time on a time chart, key points and standard WIP.
- Time study sheetTime each element over 10 cycles and work out the average, lowest repeatable and standard time. Excel does the sums.
- TWI job breakdown sheetThe TWI Job Instruction breakdown of a job into important steps, key points and reasons, with a worked example and the four steps.
- Standard work audit checklist24 checks of a job against its written standard, ten timed cycles, and each gap sorted by cause before anyone acts.
- Takt time calculatorThe pace a line must hit to meet customer demand, from shift time, breaks and daily demand.
- Standard time calculatorObserved times, a rating and an allowance in; normal time, standard time, units per hour, pieces per shift and labour cost per unit out, with the working.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
Doing this in LeanSuite
Time and Motion Study
Film the station and the AI times every element on a timeline that links to the video. You check it and certify it.
See Time and Motion StudyStandardized work software
Working out the standard with Vision AI, keeping it current with SOPs and work instructions, and training and auditing it.
See Standardized work softwareDigital work instructions
Puts the current work instruction in front of the operator at the station.
See Digital work instructions
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about from time study to standard work
The process capacity table, the standard work combination table and the standard work chart. The Lean Lexicon names them as the three basic forms used together. The first gives each machine's capacity per shift, the second draws manual, machine and walking time against takt time, and the third shows the sequence, walking path and standard in-process stock on the layout.
Split each element's time into manual, machine and walking. Use manual and machine time to fill the process capacity table. Use all three to draw the combination table against takt time. If the operator's work fits, draw the standard work chart, train every operator on it and post it at the cell. Then audit it in the first week.
Divide the working time in a shift by the time one piece needs at the machine. That time is manual time plus machine time plus the tool change time spread over the pieces made between changes. A machine with 11 seconds manual, 55 seconds machine and a 300 second change every 150 pieces needs 68 seconds a piece, which is 405 pieces in a 27,600 second shift.
The standard work chart, also called the standard work sheet. It is one page with the layout, the numbered sequence, the walking path, takt time, cycle time and the standard in-process stock. The process capacity table and the combination table are working documents and usually stay in the file with the time study.
No. The operator's cycle is manual time plus walking time. Machine time is drawn on the combination table as a dashed line because the operator has walked away while the machine runs. Adding it makes one operator look overloaded when most of that time is free for other work.
Toyota-style standard work usually takes the shortest time an operator can repeat cycle after cycle, without allowances. Classic work measurement uses a rated average plus allowances to set a standard time. Either works if you use the same basis on every document and write on the sheet which one it is. Never use one person's single best cycle.
Related guides and tools
- Standard work: the three elements and what the method is for
- Standard work combination table: how to draw every line and read the result
- Standard WIP: how to calculate the pieces a cell needs
- How to conduct a time study: getting the element times this page starts from
- Standard time: rating and allowances, if you build the standard that way
- Takt time: the formula behind the red line on every sheet
- How many operators a line needs: when the work does not fit one person
- Yamazumi chart: balancing the work between several operators
- Line balancing: assigning elements to stations on a paced line
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk
Or browse the topics, the full library and the lean glossary.
Rather see it on your own problem?
Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.