Skip to content
LeanSuite

From time study to standard work: the three documents, filled in from one study

Short answer

A time study becomes standard work through three documents, filled in order. The process capacity table shows whether the machines can keep up. The combination table shows whether one operator can do the work inside takt time. The standard work chart shows the result on the layout.

Take three kinds of time from the study for every element: manual time, machine time and walking time. Put manual and machine time on the process capacity table to find what each machine can make in a shift. Put all three on the standard work combination table and draw them against takt time. If the operator's work fits, draw the standard work chart with the sequence, the walking path and the standard in-process stock, train every operator on it and post it at the cell. In the example on this page, 57 seconds of manual work and 14 seconds of walking fit an 80 second takt time, and the slowest machine can make 405 pieces a shift against 345 needed.

Last reviewed:

What a time study turns into

One time study, three documents, one posted standard

Example numbers

Start: the time study

Six elements timed over several cycles at the valve body cell

Manual work 57 s, walking 14 s, four machine cycles from 20 s to 55 s. Takt time is 80 s.

  1. 1

    Process capacity table

    Can every machine make enough?

    From the study

    Manual time and machine time at each machine, plus tool changes.

    The mill is the limit: 405 pieces a shift against 345 needed.

  2. 2

    Standard work combination table

    Can one person do it inside takt time?

    From the study

    Manual, machine and walking time for every element, in sequence.

    71 s of work and walking inside an 80 s takt time.

  3. 3

    Standard work chart

    Where does the operator go, and where do the parts sit?

    From the study

    The sequence and the cycle time from the table, drawn on the layout.

    One loop of six stops, with 4 pieces of standard in-process stock.

Finish: the handover

Operators on every shift are trained on the sequence, and the chart is posted at the cell

The capacity table and the combination table stay in the engineer's file. The chart is the one people work to.

A flow from top to bottom. A time study of six elements gives manual time 57 seconds, walking 14 seconds and four machine cycles. Those times fill three documents in order: the process capacity table, the standard work combination table and the standard work chart. The chart is then taught to the operators and posted at the cell.

Fill them in this order. Each document answers one question, and a no sends you back to the floor before you draw the next one.

A time study ends with a sheet of element times. That sheet is evidence, not a standard. Nobody can work to it, and nobody can audit against it. Standard work is what you build from it: an agreed sequence that one person can repeat inside takt time, with a fixed number of pieces in the process.

The Lean Enterprise Institute's Lean Lexicon names three basic forms for building it, and they are used together. Each one takes different numbers from the study and answers a different question. The order matters, because each answer is needed by the next sheet.

The three documents, in the order you fill them in
DocumentQuestion it answersNumbers it takes from the studyWho uses it
1. [Process capacity table](/templates/process-capacity-sheet)Can every machine make what the customer needs in a shift?Manual time and machine time at each machine, tool change time and how often.The engineer and the supervisor, when the cell is set up and whenever demand changes.
2. [Standard work combination table](/templates/standard-work-combination-table)Can one operator do the whole sequence inside takt time?Manual, machine and walking time for every element, in the order they are done.Whoever designs the job. It is the working drawing.
3. [Standard work chart](/templates/standard-work-sheet)Where does the operator go, and where do the parts sit?The sequence and cycle time from the combination table, plus the layout.Operators, team leaders and anyone auditing the cell. It is posted.

Names vary. The capacity table is also called a process capacity sheet or production capacity sheet, the combination table a combination sheet, and the chart a standard work sheet or layout sheet.

What to bring from the time study

Most studies that fail to turn into standard work were timed the wrong way for it. One stopwatch reading per element is not enough, because the three documents need the element split by who or what is doing the work.

  • Manual time for each element: hands on the part or the machine. Loading, unloading, pressing start, deburring, gauging, packing.
  • Machine time for each machine: from start pressed to cycle finished, with the operator gone. If the operator has to stand and hold something while it runs, that is manual time.
  • Walking time between each pair of stops, written on the element the operator walks away from.
  • Tool change time at each machine, and how many pieces are made between changes.
  • The working time in a shift and the customer demand for the same shift, to get takt time.
  • A sketch of the layout with the stops numbered in the order the operator visits them.

One choice has to be made before you start: which time to write down. Toyota-style standard work usually takes the shortest time the operator can repeat cycle after cycle, with no allowances added, and treats waiting as something to show on the sheet. Classic work measurement builds a standard time from a rated average plus allowances. Both can be defended. Pick one for all three documents and write on the sheet which it is, or the capacity table and the combination table will not agree with each other.

Document 1: the process capacity table

Start with the machines, because a person cannot make up for a machine that is too slow. The Lexicon describes this form as calculating the capacity of each machine in a linked set of processes, to confirm true capacity and find bottlenecks. It has one row per machine.

For each machine, add the manual time and the machine time to get the completion time for one piece. Then spread the tool change over the pieces made between changes: a 300 second change every 150 pieces costs 2 seconds a piece. Capacity for the shift is the working time divided by the sum. In words: capacity = working time in the shift / (manual time + machine time + tool change time / pieces between changes).

Illustrative: process capacity table for the valve body cell, 27,600 seconds a shift
MachineManual (s)Machine (s)Tool changeTime per piece (s)Capacity per shift
Lathe942120 s every 100 pieces = 1.2 s52.2528
Mill1155300 s every 150 pieces = 2.0 s68.0405
Drill828180 s every 200 pieces = 0.9 s36.9747
Leak tester720None27.01,022

The shift is 460 minutes of working time: 460 x 60 = 27,600 seconds. Demand is 345 pieces, so takt time is 27,600 / 345 = 80 seconds. Capacities are rounded down to whole pieces.

The process capacity table, drawn

Example numbers
  • Manual (load, unload, start)
  • Machine cycle
  • Tool change, per piece
  • Takt time, 80 s
  1. Lathe9 + 42 + 120 / 100 = 52.2 s a piece27,600 / 52.2 = 528 pieces a shift

  2. MillLowest capacity11 + 55 + 300 / 150 = 68.0 s a piece27,600 / 68.0 = 405 pieces a shift

  3. Drill8 + 28 + 180 / 200 = 36.9 s a piece27,600 / 36.9 = 747 pieces a shift

  4. Leak tester7 + 20 = 27.0 s a piece27,600 / 27.0 = 1,022 pieces a shift

Demand is 345 pieces a shift. The lowest capacity in the cell is 405, so the machines pass. If any machine came out under 345, the fix belongs at that machine before anyone draws a combination table.

Four machines as bars of time per piece against a takt time of 80 seconds. Lathe: 52.2 seconds a piece, 528 pieces a shift. Mill: 68.0 seconds a piece, 405 pieces a shift. Drill: 36.9 seconds a piece, 747 pieces a shift. Leak tester: 27.0 seconds a piece, 1022 pieces a shift. The mill is the slowest and still clears the 345 pieces needed.

Every bar ends left of the red takt line, so every machine can keep up. The mill is closest: 405 pieces a shift is 60 more than the 345 needed, and that gap is all the room the cell has if demand grows.

Read the last column against demand. The mill is the limit at 405 pieces, 60 more than the 345 needed, so the machines pass. Read the time per piece against takt time too: 68.0 seconds is under 80. If a machine came out below demand, stop here. The choices are a faster cycle, fewer or quicker tool changes, a second machine or overtime, and none of them is fixed by rearranging the operator's work.

What this table leaves out: breakdowns, scrap and minor stops. It gives the capacity of a machine that runs all shift. If your mill loses a tenth of its time to stops, its real capacity is nearer 365 than 405, and the gap to 345 is thin. Use your own downtime records, not a rule of thumb.

Document 2: the standard work combination table

Now the operator. List the elements in the order they are done and write the three times beside each one. The Lexicon describes this form as showing the combination of manual work time, walk time and machine processing time. It is the only one of the three that shows a person and several machines working at the same moment.

Illustrative: work sequence for the valve body cell, times in seconds
ElementManualMachine runs aloneWalk to next
1. Unload and load the lathe, start it9422
2. Unload and load the mill, start it11552
3. Unload and load the drill, start it8283
4. Unload and load the leak tester, start it7202
5. Deburr and gauge the bore1402
6. Pack the part, pick up a casting803

Manual: 9 + 11 + 8 + 7 + 14 + 8 = 57 seconds. Walking: 2 + 2 + 3 + 2 + 2 + 3 = 14 seconds. Operator cycle: 57 + 14 = 71 seconds.

The combination table for the valve body cell

Example numbers
  • Manual work
  • Machine runs alone
  • Walking
  • Waiting
  • Takt time
  1. 1. Unload and load the lathe, start itManual 9 s, machine 42 s, walk 2 s

  2. 2. Unload and load the mill, start itManual 11 s, machine 55 s, walk 2 s

  3. 3. Unload and load the drill, start itManual 8 s, machine 28 s, walk 3 s

  4. 4. Unload and load the leak tester, start itManual 7 s, machine 20 s, walk 2 s

  5. 5. Deburr and gauge the boreManual 14 s, walk 2 s

  6. 6. Pack the part, pick up a castingManual 8 s, walk 3 s

  7. Operator cycleManual 57 s + walk 14 s = 71 s, wait 9 s

Six elements on a time line from 0 to 90 seconds. Manual work and walking run end to end and finish at 71 seconds, 9 seconds before the takt line at 80 seconds. The four machines run on their own after the operator walks away, and each has finished before the operator comes back to it.

Read down the dark bars like a staircase: the operator is in one place at a time and gets back to the lathe at 71 s. The dashed lines are the machines. The longest, the mill, is started at 22 s and done at 77 s, before the operator is back to unload it at 82 s.

The operator's cycle is manual time plus walking: 71 seconds, which is 9 seconds inside the 80 second takt time. Machine time is not added, because the operator has walked on while each machine runs. Then check each dashed line: has the machine finished before the operator comes back to it? The mill takes 11 + 55 = 66 seconds from the moment the operator arrives, and the operator is back 71 seconds later. It has, with 5 seconds to spare.

The 9 seconds left over are waiting. Write them on the sheet as waiting. They are the first thing to use if demand rises, and the honest thing to show if it does not. For how to draw each line, what to do when a machine runs past the end of the cycle and how to read the finished sheet, see the guide to the standard work combination table.

Document 3: the standard work chart

The first two documents are for working the job out. The third is for running it. The Lexicon describes the standardized work chart as showing operator movement and material location in relation to the machines and the layout, and says it should show takt time, cycle time, work sequence and standard in-process stock. It is the one posted at the cell.

  • The layout, seen from above, with each machine and bench as a box in roughly the right place.
  • The stops numbered in the order of the combination table, joined by arrows for the walking path.
  • Takt time and cycle time: here 80 seconds and 71 seconds.
  • Standard in-process stock, marked where it sits. Here it is 4 pieces, one in each machine. How to calculate standard WIP covers cells where the count is less obvious.
  • Quality checks and safety points, each marked at the stop where it applies. A diamond for a quality check and a cross for a safety point are common marks, and they are a convention: use whatever your plant already recognises.
  • The revision, the date and who approved it.

The standard work chart for the same cell

Example numbers
1+

Lathe

9 s hand, 42 s machine

2 s
2+

Mill

11 s hand, 55 s machine

2 s
3+

Drill

8 s hand, 28 s machine

3 s

Takt 80 s

Cycle 71 s

Stock 4

3 s
6

Pack

8 s by hand

2 s
5

Deburr and gauge

14 s by hand

2 s
4

Leak tester

7 s hand, 20 s machine

  • Standard in-process stock
  • Quality check
  • Safety point
  • Walk, with seconds

The cell seen from above. The operator walks one loop: lathe, mill and drill along the top, then the leak tester, deburr and gauge, and pack along the bottom, and back to the lathe. Each of the four machines holds one piece of standard in-process stock. Takt time 80 seconds, cycle time 71 seconds.

This is the sheet that goes on the wall. Someone who has never seen the cell can stand in front of it and check three things in a minute: is the operator walking this loop, is there one part in each machine, and are the checks being done where the diamonds are.

Keep it to one page that can be read from where the team leader stands. Step by step detail does not belong on it. If an element needs a knack, a setting or a photo, that goes on a work instruction or a job breakdown sheet, and the chart just names the element. Standard work vs SOP vs work instruction shows how the three fit together.

Three checks before you post it

The three documents exist to settle three questions. If you only remember one thing from this page, remember these, because a standard that fails any of them cannot be followed no matter how well it is drawn.

  • Machine against takt time. The slowest machine's time per piece, tool changes included, must be under takt time. Here: 68.0 seconds against 80.
  • Operator against takt time. Manual time plus walking must be at or under takt time. Here: 71 seconds against 80.
  • Machine against the operator's return. Each machine must finish before the operator comes back to unload it. Here: the mill needs 66 seconds and the operator is back in 71.

Three checks before the standard is posted

Example numbers
  1. 1. Slowest machine against takt

    From the capacity table: the mill needs 68.0 s a piece, tool changes included.

    12 s inside

  2. 2. Operator cycle against takt

    From the combination table: 57 s manual plus 14 s walking is 71 s.

    9 s inside

  3. 3. Machine done before return

    From the combination table: the mill takes 66 s from load to finish, and the operator is back every 71 s.

    5 s inside

Three bars, each against a limit. The slowest machine takes 68.0 seconds a piece against a takt time of 80 seconds. The operator's cycle is 71 seconds against the same takt time. The mill needs 66 seconds from load to finish, and the operator is back at it every 71 seconds.

Each document settles one of these. If a dark bar crosses its red line, the standard cannot be run as drawn, and no amount of training will fix it.

When a check fails, the fix is on the floor, not on the paper. Shorten a walk, move a check to a different stop, change the order, take a tool change offline. Then time it again and redraw.

The handover to operators

A standard that arrives from the engineering office on a Monday morning gets followed while someone is watching. The handover is where it becomes the operators' own method, and it starts before the chart is finished.

The handover, from draft to audited standard

  1. 1

    Walk the draft with the operators

  2. 2

    Run a trial

  3. 3

    Train with a job breakdown

  4. 4

    Sign and date it

  5. 5

    Post the chart, file the tables

  6. 6

    Audit in the first week

Steps 1 and 2 change the draft. Steps 3 to 5 make it the standard. Step 6 finds out whether it is.
  1. 1

    Walk the draft with the operators

    Take the combination table and the draft chart to the cell and walk the loop with the people who run it, on each shift. Ask what is awkward and what gets skipped late in the shift. Change the draft where they are right.

  2. 2

    Run a trial

    Run the sequence for a shift with the draft marked TRIAL. Time ten cycles. If the times do not match the table, find out why before you go further.

  3. 3

    Train with a job breakdown

    Teach each operator with a job breakdown sheet: the important steps, the key points and the reasons. TWI Job Instruction's four steps fit this well: prepare the worker, present the operation, try out performance, follow up.

  4. 4

    Sign and date it

    The supervisor, the engineer and quality sign the chart. Give it a revision letter and a date. An unsigned chart is a suggestion.

  5. 5

    Post the chart, file the tables

    Post the chart at the cell where it can be read from the aisle. File the capacity table and the combination table with the study, because you will need them the day demand changes.

  6. 6

    Audit in the first week

    Stand at the cell with the chart and time a few cycles. Where the work and the chart differ, decide which one is wrong and fix that one.

Operators are wary of time studies, usually for good reason: they have seen a stopwatch followed by a higher target. Say plainly what the times are for. Share the sheet. Make it clear that the time belongs to the method, not to the person, and that a slow cycle is a question about the job. Do not build the standard on the best cycle of your fastest operator and hold everyone else to it.

After the handover the standard is a baseline, and it is expected to change. Updating standard work after an improvement covers the loop of study, change, re-study and reissue.

Common mistakes

  • Skipping the capacity table. The combination table then shows an operator who fits takt time at a machine that cannot.
  • Timing each element as one number. Without manual, machine and walking time split out, the combination table cannot be drawn.
  • Adding machine time to the operator's cycle. The cell looks overloaded when the operator is free for most of every machine run.
  • Leaving tool changes out of capacity. Without them the mill in the example looks good for 418 pieces a shift. With them it is 405.
  • Drawing the chart from the layout drawing instead of the floor. The bench that was moved last year is still on the drawing.
  • Posting all three documents. The wall fills with paper nobody reads. Post the chart and keep the other two in the file.
  • Using it where nothing repeats. A changeover, a repair or a job shop one-off has no cycle to pace against takt time. Use an SOP or a checklist there.

Where software helps

The slow part of all this is the timing. In LeanSuite's Time and Motion Study you film the work, the AI drafts the element times on a timeline that links back to the video, and you check and certify the study. That gives you the element list and the times this page starts from. The process capacity table, the combination table and the standard work sheet themselves are free LeanSuite templates, not modules in the software. Standardized work software explains what each part does and does not do.

Standardized work software

Keep standard work current in LeanSuite

LeanSuite covers most of the cycle in one platform: working out the standard with Vision AI, keeping it current with SOPs and work instructions, and training and auditing it.

FAQ

Questions about from time study to standard work

  1. The process capacity table, the standard work combination table and the standard work chart. The Lean Lexicon names them as the three basic forms used together. The first gives each machine's capacity per shift, the second draws manual, machine and walking time against takt time, and the third shows the sequence, walking path and standard in-process stock on the layout.

  2. Split each element's time into manual, machine and walking. Use manual and machine time to fill the process capacity table. Use all three to draw the combination table against takt time. If the operator's work fits, draw the standard work chart, train every operator on it and post it at the cell. Then audit it in the first week.

  3. Divide the working time in a shift by the time one piece needs at the machine. That time is manual time plus machine time plus the tool change time spread over the pieces made between changes. A machine with 11 seconds manual, 55 seconds machine and a 300 second change every 150 pieces needs 68 seconds a piece, which is 405 pieces in a 27,600 second shift.

  4. The standard work chart, also called the standard work sheet. It is one page with the layout, the numbered sequence, the walking path, takt time, cycle time and the standard in-process stock. The process capacity table and the combination table are working documents and usually stay in the file with the time study.

  5. No. The operator's cycle is manual time plus walking time. Machine time is drawn on the combination table as a dashed line because the operator has walked away while the machine runs. Adding it makes one operator look overloaded when most of that time is free for other work.

  6. Toyota-style standard work usually takes the shortest time an operator can repeat cycle after cycle, without allowances. Classic work measurement uses a rated average plus allowances to set a standard time. Either works if you use the same basis on every document and write on the sheet which one it is. Never use one person's single best cycle.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.