Worked examples · Standard work, SOPs and training
Time study examples: five jobs timed and worked to a standard time
Short answer
A time study turns a timed job into one number you can plan with. These five examples show it done on five different jobs, from the readings to the standard time, and then the decision the number fed.
A time study example needs four things: the observed times of each element, a rating for the pace, an allowance, and a decision. Observed time x rating / 100 gives normal time. Normal time x (1 + allowance) gives standard time. On this page a bench assembly works out at 32.82 seconds against a 36 second takt, a machine-tending job shows one operator cannot serve two machines until deburring moves off the machine, packing needs 4 packers for 1,800 cartons, a 12 line pick takes 6.23 minutes, and a changeover of 42.80 minutes can lose 5.72 by fetching tooling while the line runs.
Last reviewed:
Five jobs, one method
Five jobs, the same three steps
Example numbersBench assembly
Observed28.00 sNormal28.54 sStandard32.82 sMachine tending (operator work)
Observed41.00 sNormal41.45 sStandard46.42 sPacking a carton
Observed48.55 sNormal47.43 sStandard55.02 sWarehouse pick, one line
Observed21.00 sNormal21.20 sStandard24.80 sChangeover
Observed39.50 minNormal38.91 minStandard42.80 min
Each job goes from the observed time, to normal time after rating, to standard time after the allowance. Bench assembly: 28.0, 28.5, 32.8 s. Machine tending (operator work): 41.0, 41.5, 46.4 s. Packing a carton: 48.5, 47.4, 55.0 s. Warehouse pick, one line: 21.0, 21.2, 24.8 s. Changeover: 39.5, 38.9, 42.8 min.
Every example below follows the same path. The elements of the job are timed over several cycles. Each element's average is multiplied by the observer's rating of the pace to get normal time. The allowance is added to get standard time. Then the number is used for something, and that last step is the one most write-ups leave out.
| Job | Standard time | Decision it fed |
|---|---|---|
| Bench assembly of a sensor bracket | 32.82 s per piece | One operator holds a 36 s takt. No second bench. |
| Tending a CNC lathe | 79.92 s machine cycle, 31.86 s of operator time per machine | Two machines per operator only after deburring and the tote leave the machine. |
| Packing a 12 piece carton | 55.02 s per carton | 4 packers for 1,800 cartons a shift, not 3. |
| Picking a 12 line order | 24.80 s per line, 373.70 s per order | A pick standard of about 115 lines an hour for planning and feedback. |
| A packaging line changeover | 42.80 min | Fetch tooling while the line runs and save 5.72 min a stop. |
All the figures are made up for teaching, and each was recomputed before it went on the page. Your readings will differ, and so will the allowances. What carries over is the way each sheet is set out and what each result was used for.
The conventions the examples use
Rating is a number for pace, where 100 is normal. Normal time is the observed time x rating / 100, so a slow operator rated 90 has their time cut and a quick one rated 110 has it lengthened. The scale and its anchors come from the ILO, whose standard rating is the pace of a qualified worker on piecework, and from Niebel and Freivalds. Standard time covers the scales in full.
The allowance is added on top of normal time for personal needs, fatigue and delays, in the add-on form that Niebel and Freivalds use: standard time = normal time x (1 + allowance). The percentages in these examples are the example plants' own. They are not from a published table, and your plant should use its own agreed table. If a union agreement fixes the allowances, that agreement wins; see time study in a union plant.
Two more conventions matter here. Machine-controlled time is not rated and carries no allowance, because the machine runs at its own speed whoever is watching. And elements that do not happen every cycle, such as changing a tape roll, are timed on their own and spread over the pieces they serve. The stopwatch time study guide shows how to take the readings, and how many cycles to time tells you how many are enough.
Example 1: bench assembly
Illustrative. An operator fits a sensor bracket with two screws at a bench. The cell makes 750 pieces a shift of 450 minutes, 27,000 seconds, so takt time is 27,000 / 750 = 36 seconds. Ten cycles were timed with a stopwatch, and the average of the readings kept for each element is below, after throwing out two cycles where a screw was dropped.
| Element | Observed (s) | Rating | Normal (s) |
|---|---|---|---|
| Pick bracket and two screws | 6.0 | 100 | 6.00 |
| Fit and start the screws | 9.5 | 110 | 10.45 |
| Drive the screws | 8.2 | 95 | 7.79 |
| Place in the tray | 4.3 | 100 | 4.30 |
| Total | 28.0 | 28.54 |
Allowance 15 percent: 28.54 x 1.15 = 32.82 s standard time, which is 3,600 / 32.82 = 109.7 pieces an hour.
Bench assembly: standard time against a 36 second takt
Example numbersStandard time 32.82 s, spare 3.18 s
- Pick bracket and two screws 6.00 s
- Fit and start the screws 10.45 s
- Drive the screws 7.79 s
- Place in the tray 4.30 s
- Allowance 15% 4.28 s
The four elements, rated, add to 28.54 seconds. The 15 percent allowance adds 4.28. The standard time is 32.82 seconds against a takt time of 36 seconds, so 3.18 seconds are spare.
The fit was rated 110 because the operator was quick and sure on it, and the drive 95 because the powered driver kept slipping off the screw head. Normal time comes out at 28.54 seconds, slightly above the 28.0 observed, because the fast element outweighed the slow one.
The decision: 32.82 seconds is under the 36 second takt by 3.18 seconds, about 9 percent. One operator holds takt, so there is no case for a second bench. The 3.18 seconds are the margin for a bad day. If demand rose to 820 pieces a shift, takt would fall to 32.9 seconds and the margin to about 0.1 seconds, and the driver, the element rated slow, would be the first thing to look at.
Example 2: machine tending
Illustrative. One operator loads and unloads a CNC lathe whose run takes 62 seconds. While it runs, the operator gauges the last part, deburrs it and puts it in a tote. The question is whether one person can serve two lathes. The machine run is not rated, because the machine sets its pace. The operator's work is rated, and carries a 12 percent allowance.
| Element | While the machine is | Observed (s) | Rating | Normal (s) |
|---|---|---|---|---|
| Unload, load, start | Stopped | 16.0 | 100 | 16.00 |
| Machine runs alone | Running | 62.0 | Not rated | 62.00 |
| Gauge the part | Running | 9.0 | 105 | 9.45 |
| Deburr the part | Running | 11.0 | 100 | 11.00 |
| Place in the tote | Running | 5.0 | 100 | 5.00 |
Operator elements x 1.12. Unload, load and start: 17.92 s. Gauge, deburr and tote: 25.45 x 1.12 = 28.50 s. Machine cycle: 17.92 + 62 = 79.92 s, or 45.0 parts an hour.
Can one operator tend two machines?
Example numbersAs timed
Operator needs 92.85 s per round, 12.93 s too long
Deburring and tote moved to another station
Operator needs 63.73 s per round, 16.19 s to spare
- load and unload 17.92 s
- gauge and walk 13.94 s
The machine cycle is 79.92 seconds. As timed, one operator needs 92.85 seconds to serve two machines, which is 12.93 seconds too long. With deburring and the tote moved off the machine, two machines need 63.73 seconds, which leaves 16.19 seconds.
Within one machine's 62 second run the operator has 28.50 seconds of work, so 33.5 seconds go idle. That looks like room for a second machine. But serving two means doing the stopped-machine work twice: 2 x (17.92 + 28.50) = 92.85 seconds in a round, against a machine cycle of 79.92. The operator is 12.93 seconds too slow, and each machine stands waiting for them.
The decision: move deburring and the tote to another station. What is left is the loading, the 9.45 seconds of gauging and a 3 second walk between machines: (16 + 9.45 + 3) x 1.12 = 31.86 seconds per machine, and 63.73 for two. That fits inside 79.92 with 16.19 seconds to spare, 79.7 percent loaded, and one operator makes 2 x 3,600 / 79.92 = 90.1 parts an hour in place of 45.0. A man-machine chart draws this on one page.
Example 3: packing, with elements that do not happen every cycle
Illustrative. A packer erects a carton, loads 12 pieces, adds a leaflet, tapes and labels it and stacks it on a pallet. Two elements happen only now and then: a new roll of tape every 100 cartons, and a full pallet taken away and an empty one brought every 48 cartons. The allowance is 16 percent because the work is on the feet and repetitive.
| Element | Observed (s) | Rating | Normal (s) |
|---|---|---|---|
| Erect the carton | 7.50 | 100 | 7.50 |
| Load the 12 pieces | 21.00 | 90 | 18.90 |
| Insert the leaflet | 3.20 | 100 | 3.20 |
| Tape and label | 9.80 | 110 | 10.78 |
| Stack on the pallet | 5.50 | 100 | 5.50 |
| Change the tape roll: 30 s / 100 cartons | 0.30 | 100 | 0.30 |
| Change the pallet: 60 s / 48 cartons | 1.25 | 100 | 1.25 |
| Total | 48.55 | 47.43 |
Allowance 16 percent: 47.43 x 1.16 = 55.02 s per carton, or 65.4 cartons an hour.
Packing a carton, and how many packers the shift needs
Example numbersStandard time 55.02 s per carton
- Erect the carton 7.50 s
- Load the 12 pieces 18.90 s
- Insert the leaflet 3.20 s
- Tape and label 10.78 s
- Stack on the pallet 5.50 s
- Change the tape roll (30 s every 100 cartons) 0.30 s
- Change the pallet (60 s every 48 cartons) 1.25 s
- Allowance 16% 7.59 s
1800 cartons x 55.02 s / 27000 s = 3.67 packers
Four packers: the first three are full, the fourth carries the rest.
One carton takes 55.02 seconds of standard time, including 1.55 seconds spread from the tape and pallet changes. 1800 cartons need 3.67 packers for a 27000 second shift, so four packers are rostered, each loaded to 91.7 percent.
The two occasional elements add 1.55 seconds to every carton, 3.3 percent of normal time. A study that timed only ten consecutive cartons would have missed both. To catch them, time them on their own when they occur, then divide by the number of cartons between them.
The decision: the plan is 1,800 cartons in a 27,000 second shift. 1,800 x 55.02 / 27,000 = 3.67 packers, so the shift needs 4, each loaded to 91.7 percent. Three packers would have been short by about 18 percent of the output. For a line that feeds the packers, line balancing is the next step.
Example 4: a warehouse pick
Illustrative. A picker builds a pallet of cases from an order of 12 lines. The work has a variable part, which repeats for every line, and a fixed part, which happens once per order. Walking is rated against a normal pace like any element, and the allowance is 17 percent for the walking and lifting.
| Element | Observed (s) | Rating | Normal (s) |
|---|---|---|---|
| Read the label | 2.5 | 100 | 2.50 |
| Walk to the location | 9.0 | 100 | 9.00 |
| Pick the case | 4.0 | 105 | 4.20 |
| Scan | 2.0 | 100 | 2.00 |
| Place on the pallet | 3.5 | 100 | 3.50 |
| One line | 21.0 | 21.20 | |
| Per order: collect order and label, then wrap and label the pallet | 65.0 | 100 | 65.00 |
Allowance 17 percent. One line: 21.20 x 1.17 = 24.80 s. Fixed work: 65.0 x 1.17 = 76.05 s.
One pick line, then a 12 line order
Example numbersOne order line
Standard time 24.80 s per line
- Read the label 2.50 s
- Walk to the location 9.00 s
- Pick the case 4.20 s
- Scan 2.00 s
- Place on the pallet 3.50 s
- Allowance 17% 3.60 s
One order of 12 lines
Standard time 373.70 s (6.23 min) per order
- Fixed work per order 76.05 s
- 12 order lines 297.65 s
One order line takes 24.80 seconds of standard time. An order has 76.05 seconds of fixed work, so 12 lines take 373.70 seconds, which is 6.23 minutes.
An order of 12 lines takes 76.05 + 12 x 24.80 = 373.70 seconds, 6.23 minutes. That is 12 x 3,600 / 373.70 = 115.6 lines an hour. Timing the line alone would have said 145.1, 25 percent too many, because it leaves out the fixed work at each end of the order.
The decision: the site uses 115 lines an hour as the pick standard for planning labor and for feedback to pickers, and keeps a separate standard for each order size. Walking depends on the slotting, so the standard is only good until the layout changes. The share of the shift a picker actually spends picking is better found by work sampling. More on this in time study in warehouse operations.
Example 5: a changeover
Illustrative. A packaging line changes from one product format to the next. The job is rare and not paced, so the study is three filmed changeovers, with the average of the three used for each element, and the allowance is 10 percent. Rating is less certain on a job like this, so say how it was done and keep the ratings close to 100.
| Element | Observed (min) | Rating | Normal (min) |
|---|---|---|---|
| Remove old tooling, clear the line | 6.4 | 100 | 6.40 |
| Fetch new tooling from the store | 5.2 | 100 | 5.20 |
| Fit tooling, set the guides | 11.8 | 95 | 11.21 |
| Settings at the HMI | 4.6 | 100 | 4.60 |
| Trial run and first-off check | 9.0 | 100 | 9.00 |
| Record and release | 2.5 | 100 | 2.50 |
| Total | 39.5 | 38.91 |
Allowance 10 percent: 38.91 x 1.10 = 42.80 min standard time for the changeover.
Changeover: what stays inside the stop
Example numbersAs timed
Line stopped 42.80 min
Tooling fetched while the line runs
Line stopped 37.08 min, 5.72 min saved
- Remove old tooling, clear the line 6.40 min
- Fetch new tooling from the store 5.20 min
- Fit tooling, set the guides 11.21 min
- Settings at the HMI 4.60 min
- Trial run and first-off check 9.00 min
- Record and release 2.50 min
- Allowance 10% 3.89 min
The fetch element comes out whole, with its share of the allowance: 5.20 x 1.10 = 5.72 minutes.
The changeover has a standard time of 42.80 minutes with the line stopped. Fetching tooling can be done while the line runs, which removes 5.72 minutes, so the stop is 37.08 minutes.
The decision: the fetch is done by the same person while the line is stopped, yet nothing about it needs the line to be stopped. Moving it to before the stop takes out 5.20 x 1.10 = 5.72 minutes, 13.4 percent, and the stop is 37.08 minutes. At six changeovers a week that is 34 minutes of running time. This is the first move in SMED, and the study found it by writing each element on its own line. The same method on repair work is in time study in maintenance work.
What the five examples have in common
- The standard time was never the end. Each one was compared with something: takt time, a machine cycle, a shift of demand, a stop time.
- The job was split into elements before it was timed. Every decision above came from one element or a group of them, not from the total.
- Rating moved the answer both ways. A slow element was rated under 100 and a fast one over 100, so normal time differs from observed time by a few percent either way.
- The allowance is the same for the whole sheet but different between jobs, because the work differs.
- Machine time was not rated. Only the operator's work was.
- Occasional work was timed on its own and spread over the pieces it serves.
The mistakes that most often spoil a study like these are in time study mistakes. Taking a standard time from an unstable method, rating at the end instead of during the observation and forgetting the occasional elements account for most of them.
Doing your own: the steps
- 1
Pick a job and a question.
Write down the decision the number is for before you start: takt, crew size, a quote, a changeover target. It tells you how exact the study needs to be.
- 2
Fix the method and split it into elements.
Time the job as it should be done, in clear steps with a start and a stop you can see. How to break a job into elements has the rules.
- 3
Time enough cycles.
Time them with a stopwatch or a video, enough cycles for the confidence you need. The sample size calculator tells you how many.
- 4
Rate the pace during the observation.
Write the rating beside each element while you watch, against a scale you and the operator both know. Rate only what the operator controls.
- 5
Work out normal time and add the allowance.
Observed x rating / 100, then x (1 + allowance). Use the standard time calculator to check your arithmetic.
- 6
Use it, and write down what you used it for.
Compare the standard with takt or capacity, make the decision, and file the sheet with the date so the next person knows how the number was made.
The procedure is covered in full in how to conduct a time study, and the family of methods in time and motion study.
Where software helps
The slow part of every example above is getting the element times: standing at the job with a stopwatch, or going through footage frame by frame. LeanSuite's Time and Motion Study times each element from one phone video and links every time back to its frame, for you to check, rate and certify. The sheet and the decision are still yours. The time study sheet is a free template with the columns used on this page.
Time and motion study software
Run a time study in LeanSuite
Time and motion study software that works from phone video: LeanSuite times every element, gives cycle and standard time, and draws a Yamazumi chart.
Go deeper
This page is the short version. These guides cover each part in full.
- The Three Elements of Standard Work: Takt Time, Work Sequence, Standard WIPWhere a standard time goes next: takt time, the work sequence and standard in-process stock.
- Standard Work Tools: Combination Sheet, Standardized Work Chart, Job BreakdownThe forms that carry element times from the study to the floor.
- Yamazumi Chart: What It Is and How to Make One in 7 StepsStacking element times against takt, as in the bench and packing examples.
- Standard Work in Manufacturing: A Complete GuideHow a studied job becomes written standard work.
All our articles on this subject are in the standard work, sops and training topic.
Free templates and tools
- Time study sheetTime each element over 10 cycles and work out the average, lowest repeatable and standard time. Excel does the sums.
- Video time study filming checklistA pre-shoot checklist and shot log for filming a time study on video: camera, light, people, settings, power and review.
- Changeover checklist25 checks for every changeover, a record of planned and actual times, and a log of changeover time against target.
- Process capacity sheet templateEach machine in a part's routing with manual, auto and tool change time, its capacity per shift, and the step that limits the cell against demand.
- Standard time calculatorObserved times, a rating and an allowance in; normal time, standard time, units per hour, pieces per shift and labour cost per unit out, with the working.
- Time study sample size calculatorHow many cycles of an element to time, from your first readings, with the t formula, the ILO formula and the range method.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
- Takt time calculatorThe pace a line must hit to meet customer demand, from shift time, breaks and daily demand.
Doing this in LeanSuite
Time and Motion Study
Times every element from one phone video of the process and reports cycle time, standard time, takt and units per hour, each linked to its video frame.
See Time and Motion StudyLine Balancing
Drop in a video of your line and get a Yamazumi chart, a takt comparison and rebalancing recommendations.
See Line Balancing
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about time study examples
A packer is timed over several cartons. Each element is timed on its own: erecting the carton took 7.5 seconds, loading 21.0, taping 9.8. Each is rated against normal pace, the normal times add to 47.43 seconds, and a 16 percent allowance makes the standard time 55.02 seconds. That number then sets how many packers a shift of 1,800 cartons needs.
Five are worked on this page: a bench assembly set against a 36 second takt, a machine-tending job that shows whether one operator can serve two machines, a packing job that sets crew size, a warehouse pick that gives a lines-per-hour standard, and a changeover that shows which element can come out of the stop. Each ends in a decision, not just a number.
Pick the job and the decision the number is for. Split the job into elements with clear start and stop points. Time each element over enough cycles, rating the operator's pace as you go. Multiply observed time by rating over 100 to get normal time, add the allowance to get standard time, and compare the result with takt, capacity or demand.
Standard time = observed time x (rating / 100) x (1 + allowance). On the bench assembly example, the elements add to 28.54 seconds of normal time, and a 15 percent allowance gives 28.54 x 1.15 = 32.82 seconds. Machine time that runs on its own is not rated and takes no allowance.
No. A machine runs at its own set speed whoever is watching, so rating its time would only add error. Rate only the elements the operator controls, and add the allowance to those. In the machine-tending example the 62 second run is left as timed, and the operator's elements are rated and carry a 12 percent allowance.
Related guides and tools
- Standard time: the rating scales and allowances behind every sheet here
- How to conduct a time study: the procedure, start to finish
- Time and motion study: the methods and when to use each
- Work sampling: when sampling the shift beats timing the job
- Time study in warehouse operations: picking, travel and labor standards
- Time study in maintenance work: timing jobs that are not repeated
- Line balancing: using standard times to even out the stations
- Standard time calculator: readings, rating and allowance in, standard time out
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk
Or browse the topics, the full library and the lean glossary.
Rather see it on your own problem?
Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.