Time study examples: five jobs timed and worked to a standard time

Short answer

A time study turns a timed job into one number you can plan with. These five examples show it done on five different jobs, from the readings to the standard time, and then the decision the number fed.

A time study example needs four things: the observed times of each element, a rating for the pace, an allowance, and a decision. Observed time x rating / 100 gives normal time. Normal time x (1 + allowance) gives standard time. On this page a bench assembly works out at 32.82 seconds against a 36 second takt, a machine-tending job shows one operator cannot serve two machines until deburring moves off the machine, packing needs 4 packers for 1,800 cartons, a 12 line pick takes 6.23 minutes, and a changeover of 42.80 minutes can lose 5.72 by fetching tooling while the line runs.

Last reviewed:

Five jobs, one method

Five jobs, the same three steps

Example numbers
  • Bench assembly

    Observed28.00 s
    Normal28.54 s
    Standard32.82 s
  • Machine tending (operator work)

    Observed41.00 s
    Normal41.45 s
    Standard46.42 s
  • Packing a carton

    Observed48.55 s
    Normal47.43 s
    Standard55.02 s
  • Warehouse pick, one line

    Observed21.00 s
    Normal21.20 s
    Standard24.80 s
  • Changeover

    Observed39.50 min
    Normal38.91 min
    Standard42.80 min

Each job goes from the observed time, to normal time after rating, to standard time after the allowance. Bench assembly: 28.0, 28.5, 32.8 s. Machine tending (operator work): 41.0, 41.5, 46.4 s. Packing a carton: 48.5, 47.4, 55.0 s. Warehouse pick, one line: 21.0, 21.2, 24.8 s. Changeover: 39.5, 38.9, 42.8 min.

Rating moves the time up or down depending on pace. The allowance always adds. The standard time is the one you plan with.

Every example below follows the same path. The elements of the job are timed over several cycles. Each element's average is multiplied by the observer's rating of the pace to get normal time. The allowance is added to get standard time. Then the number is used for something, and that last step is the one most write-ups leave out.

Illustrative: the five jobs, their standard time and the decision each one fed
JobStandard timeDecision it fed
Bench assembly of a sensor bracket32.82 s per pieceOne operator holds a 36 s takt. No second bench.
Tending a CNC lathe79.92 s machine cycle, 31.86 s of operator time per machineTwo machines per operator only after deburring and the tote leave the machine.
Packing a 12 piece carton55.02 s per carton4 packers for 1,800 cartons a shift, not 3.
Picking a 12 line order24.80 s per line, 373.70 s per orderA pick standard of about 115 lines an hour for planning and feedback.
A packaging line changeover42.80 minFetch tooling while the line runs and save 5.72 min a stop.

All the figures are made up for teaching, and each was recomputed before it went on the page. Your readings will differ, and so will the allowances. What carries over is the way each sheet is set out and what each result was used for.

The conventions the examples use

Rating is a number for pace, where 100 is normal. Normal time is the observed time x rating / 100, so a slow operator rated 90 has their time cut and a quick one rated 110 has it lengthened. The scale and its anchors come from the ILO, whose standard rating is the pace of a qualified worker on piecework, and from Niebel and Freivalds. Standard time covers the scales in full.

The allowance is added on top of normal time for personal needs, fatigue and delays, in the add-on form that Niebel and Freivalds use: standard time = normal time x (1 + allowance). The percentages in these examples are the example plants' own. They are not from a published table, and your plant should use its own agreed table. If a union agreement fixes the allowances, that agreement wins; see time study in a union plant.

Two more conventions matter here. Machine-controlled time is not rated and carries no allowance, because the machine runs at its own speed whoever is watching. And elements that do not happen every cycle, such as changing a tape roll, are timed on their own and spread over the pieces they serve. The stopwatch time study guide shows how to take the readings, and how many cycles to time tells you how many are enough.

Example 1: bench assembly

Illustrative. An operator fits a sensor bracket with two screws at a bench. The cell makes 750 pieces a shift of 450 minutes, 27,000 seconds, so takt time is 27,000 / 750 = 36 seconds. Ten cycles were timed with a stopwatch, and the average of the readings kept for each element is below, after throwing out two cycles where a screw was dropped.

Illustrative: observation sheet for the bracket assembly, 10 cycles
ElementObserved (s)RatingNormal (s)
Pick bracket and two screws6.01006.00
Fit and start the screws9.511010.45
Drive the screws8.2957.79
Place in the tray4.31004.30
Total28.028.54

Allowance 15 percent: 28.54 x 1.15 = 32.82 s standard time, which is 3,600 / 32.82 = 109.7 pieces an hour.

Bench assembly: standard time against a 36 second takt

Example numbers

Standard time 32.82 s, spare 3.18 s

  • Pick bracket and two screws 6.00 s
  • Fit and start the screws 10.45 s
  • Drive the screws 7.79 s
  • Place in the tray 4.30 s
  • Allowance 15% 4.28 s

The four elements, rated, add to 28.54 seconds. The 15 percent allowance adds 4.28. The standard time is 32.82 seconds against a takt time of 36 seconds, so 3.18 seconds are spare.

One person holds takt with a little room. The spare seconds are the margin for a bad day, not a second bench.

The fit was rated 110 because the operator was quick and sure on it, and the drive 95 because the powered driver kept slipping off the screw head. Normal time comes out at 28.54 seconds, slightly above the 28.0 observed, because the fast element outweighed the slow one.

The decision: 32.82 seconds is under the 36 second takt by 3.18 seconds, about 9 percent. One operator holds takt, so there is no case for a second bench. The 3.18 seconds are the margin for a bad day. If demand rose to 820 pieces a shift, takt would fall to 32.9 seconds and the margin to about 0.1 seconds, and the driver, the element rated slow, would be the first thing to look at.

Example 2: machine tending

Illustrative. One operator loads and unloads a CNC lathe whose run takes 62 seconds. While it runs, the operator gauges the last part, deburrs it and puts it in a tote. The question is whether one person can serve two lathes. The machine run is not rated, because the machine sets its pace. The operator's work is rated, and carries a 12 percent allowance.

Illustrative: observation sheet for one lathe, with the operator's work split into stopped and running
ElementWhile the machine isObserved (s)RatingNormal (s)
Unload, load, startStopped16.010016.00
Machine runs aloneRunning62.0Not rated62.00
Gauge the partRunning9.01059.45
Deburr the partRunning11.010011.00
Place in the toteRunning5.01005.00

Operator elements x 1.12. Unload, load and start: 17.92 s. Gauge, deburr and tote: 25.45 x 1.12 = 28.50 s. Machine cycle: 17.92 + 62 = 79.92 s, or 45.0 parts an hour.

Can one operator tend two machines?

Example numbers

As timed

Operator needs 92.85 s per round, 12.93 s too long

Deburring and tote moved to another station

Operator needs 63.73 s per round, 16.19 s to spare

  • load and unload 17.92 s
  • gauge and walk 13.94 s

The machine cycle is 79.92 seconds. As timed, one operator needs 92.85 seconds to serve two machines, which is 12.93 seconds too long. With deburring and the tote moved off the machine, two machines need 63.73 seconds, which leaves 16.19 seconds.

The machine run is not rated and gets no allowance. The operator's own work is rated, and it is the only part that decides how many machines one person can serve.

Within one machine's 62 second run the operator has 28.50 seconds of work, so 33.5 seconds go idle. That looks like room for a second machine. But serving two means doing the stopped-machine work twice: 2 x (17.92 + 28.50) = 92.85 seconds in a round, against a machine cycle of 79.92. The operator is 12.93 seconds too slow, and each machine stands waiting for them.

The decision: move deburring and the tote to another station. What is left is the loading, the 9.45 seconds of gauging and a 3 second walk between machines: (16 + 9.45 + 3) x 1.12 = 31.86 seconds per machine, and 63.73 for two. That fits inside 79.92 with 16.19 seconds to spare, 79.7 percent loaded, and one operator makes 2 x 3,600 / 79.92 = 90.1 parts an hour in place of 45.0. A man-machine chart draws this on one page.

Example 3: packing, with elements that do not happen every cycle

Illustrative. A packer erects a carton, loads 12 pieces, adds a leaflet, tapes and labels it and stacks it on a pallet. Two elements happen only now and then: a new roll of tape every 100 cartons, and a full pallet taken away and an empty one brought every 48 cartons. The allowance is 16 percent because the work is on the feet and repetitive.

Illustrative: observation sheet for packing one carton
ElementObserved (s)RatingNormal (s)
Erect the carton7.501007.50
Load the 12 pieces21.009018.90
Insert the leaflet3.201003.20
Tape and label9.8011010.78
Stack on the pallet5.501005.50
Change the tape roll: 30 s / 100 cartons0.301000.30
Change the pallet: 60 s / 48 cartons1.251001.25
Total48.5547.43

Allowance 16 percent: 47.43 x 1.16 = 55.02 s per carton, or 65.4 cartons an hour.

Packing a carton, and how many packers the shift needs

Example numbers

Standard time 55.02 s per carton

  • Erect the carton 7.50 s
  • Load the 12 pieces 18.90 s
  • Insert the leaflet 3.20 s
  • Tape and label 10.78 s
  • Stack on the pallet 5.50 s
  • Change the tape roll (30 s every 100 cartons) 0.30 s
  • Change the pallet (60 s every 48 cartons) 1.25 s
  • Allowance 16% 7.59 s

1800 cartons x 55.02 s / 27000 s = 3.67 packers

Four packers: the first three are full, the fourth carries the rest.

One carton takes 55.02 seconds of standard time, including 1.55 seconds spread from the tape and pallet changes. 1800 cartons need 3.67 packers for a 27000 second shift, so four packers are rostered, each loaded to 91.7 percent.

The two occasional elements add 1.55 seconds to every carton. Left out, the standard would run about 3 percent light.

The two occasional elements add 1.55 seconds to every carton, 3.3 percent of normal time. A study that timed only ten consecutive cartons would have missed both. To catch them, time them on their own when they occur, then divide by the number of cartons between them.

The decision: the plan is 1,800 cartons in a 27,000 second shift. 1,800 x 55.02 / 27,000 = 3.67 packers, so the shift needs 4, each loaded to 91.7 percent. Three packers would have been short by about 18 percent of the output. For a line that feeds the packers, line balancing is the next step.

Example 4: a warehouse pick

Illustrative. A picker builds a pallet of cases from an order of 12 lines. The work has a variable part, which repeats for every line, and a fixed part, which happens once per order. Walking is rated against a normal pace like any element, and the allowance is 17 percent for the walking and lifting.

Illustrative: observation sheet for one order line and the fixed work of an order
ElementObserved (s)RatingNormal (s)
Read the label2.51002.50
Walk to the location9.01009.00
Pick the case4.01054.20
Scan2.01002.00
Place on the pallet3.51003.50
One line21.021.20
Per order: collect order and label, then wrap and label the pallet65.010065.00

Allowance 17 percent. One line: 21.20 x 1.17 = 24.80 s. Fixed work: 65.0 x 1.17 = 76.05 s.

One pick line, then a 12 line order

Example numbers

One order line

Standard time 24.80 s per line

  • Read the label 2.50 s
  • Walk to the location 9.00 s
  • Pick the case 4.20 s
  • Scan 2.00 s
  • Place on the pallet 3.50 s
  • Allowance 17% 3.60 s

One order of 12 lines

Standard time 373.70 s (6.23 min) per order

  • Fixed work per order 76.05 s
  • 12 order lines 297.65 s

One order line takes 24.80 seconds of standard time. An order has 76.05 seconds of fixed work, so 12 lines take 373.70 seconds, which is 6.23 minutes.

The fixed work per order is why lines per hour falls as orders get shorter. Time the line and the order separately.

An order of 12 lines takes 76.05 + 12 x 24.80 = 373.70 seconds, 6.23 minutes. That is 12 x 3,600 / 373.70 = 115.6 lines an hour. Timing the line alone would have said 145.1, 25 percent too many, because it leaves out the fixed work at each end of the order.

The decision: the site uses 115 lines an hour as the pick standard for planning labor and for feedback to pickers, and keeps a separate standard for each order size. Walking depends on the slotting, so the standard is only good until the layout changes. The share of the shift a picker actually spends picking is better found by work sampling. More on this in time study in warehouse operations.

Example 5: a changeover

Illustrative. A packaging line changes from one product format to the next. The job is rare and not paced, so the study is three filmed changeovers, with the average of the three used for each element, and the allowance is 10 percent. Rating is less certain on a job like this, so say how it was done and keep the ratings close to 100.

Illustrative: sheet for the changeover, averages of three changeovers, in minutes
ElementObserved (min)RatingNormal (min)
Remove old tooling, clear the line6.41006.40
Fetch new tooling from the store5.21005.20
Fit tooling, set the guides11.89511.21
Settings at the HMI4.61004.60
Trial run and first-off check9.01009.00
Record and release2.51002.50
Total39.538.91

Allowance 10 percent: 38.91 x 1.10 = 42.80 min standard time for the changeover.

Changeover: what stays inside the stop

Example numbers

As timed

Line stopped 42.80 min

Tooling fetched while the line runs

Line stopped 37.08 min, 5.72 min saved

  • Remove old tooling, clear the line 6.40 min
  • Fetch new tooling from the store 5.20 min
  • Fit tooling, set the guides 11.21 min
  • Settings at the HMI 4.60 min
  • Trial run and first-off check 9.00 min
  • Record and release 2.50 min
  • Allowance 10% 3.89 min

The fetch element comes out whole, with its share of the allowance: 5.20 x 1.10 = 5.72 minutes.

The changeover has a standard time of 42.80 minutes with the line stopped. Fetching tooling can be done while the line runs, which removes 5.72 minutes, so the stop is 37.08 minutes.

The study does not fix the changeover. It shows which element can leave the stop, and how much it is worth.

The decision: the fetch is done by the same person while the line is stopped, yet nothing about it needs the line to be stopped. Moving it to before the stop takes out 5.20 x 1.10 = 5.72 minutes, 13.4 percent, and the stop is 37.08 minutes. At six changeovers a week that is 34 minutes of running time. This is the first move in SMED, and the study found it by writing each element on its own line. The same method on repair work is in time study in maintenance work.

What the five examples have in common

  • The standard time was never the end. Each one was compared with something: takt time, a machine cycle, a shift of demand, a stop time.
  • The job was split into elements before it was timed. Every decision above came from one element or a group of them, not from the total.
  • Rating moved the answer both ways. A slow element was rated under 100 and a fast one over 100, so normal time differs from observed time by a few percent either way.
  • The allowance is the same for the whole sheet but different between jobs, because the work differs.
  • Machine time was not rated. Only the operator's work was.
  • Occasional work was timed on its own and spread over the pieces it serves.

The mistakes that most often spoil a study like these are in time study mistakes. Taking a standard time from an unstable method, rating at the end instead of during the observation and forgetting the occasional elements account for most of them.

Doing your own: the steps

  1. 1

    Pick a job and a question.

    Write down the decision the number is for before you start: takt, crew size, a quote, a changeover target. It tells you how exact the study needs to be.

  2. 2

    Fix the method and split it into elements.

    Time the job as it should be done, in clear steps with a start and a stop you can see. How to break a job into elements has the rules.

  3. 3

    Time enough cycles.

    Time them with a stopwatch or a video, enough cycles for the confidence you need. The sample size calculator tells you how many.

  4. 4

    Rate the pace during the observation.

    Write the rating beside each element while you watch, against a scale you and the operator both know. Rate only what the operator controls.

  5. 5

    Work out normal time and add the allowance.

    Observed x rating / 100, then x (1 + allowance). Use the standard time calculator to check your arithmetic.

  6. 6

    Use it, and write down what you used it for.

    Compare the standard with takt or capacity, make the decision, and file the sheet with the date so the next person knows how the number was made.

The procedure is covered in full in how to conduct a time study, and the family of methods in time and motion study.

Where software helps

The slow part of every example above is getting the element times: standing at the job with a stopwatch, or going through footage frame by frame. LeanSuite's Time and Motion Study times each element from one phone video and links every time back to its frame, for you to check, rate and certify. The sheet and the decision are still yours. The time study sheet is a free template with the columns used on this page.

Time and motion study software

Run a time study in LeanSuite

Time and motion study software that works from phone video: LeanSuite times every element, gives cycle and standard time, and draws a Yamazumi chart.

FAQ

Questions about time study examples

  1. A packer is timed over several cartons. Each element is timed on its own: erecting the carton took 7.5 seconds, loading 21.0, taping 9.8. Each is rated against normal pace, the normal times add to 47.43 seconds, and a 16 percent allowance makes the standard time 55.02 seconds. That number then sets how many packers a shift of 1,800 cartons needs.

  2. Five are worked on this page: a bench assembly set against a 36 second takt, a machine-tending job that shows whether one operator can serve two machines, a packing job that sets crew size, a warehouse pick that gives a lines-per-hour standard, and a changeover that shows which element can come out of the stop. Each ends in a decision, not just a number.

  3. Pick the job and the decision the number is for. Split the job into elements with clear start and stop points. Time each element over enough cycles, rating the operator's pace as you go. Multiply observed time by rating over 100 to get normal time, add the allowance to get standard time, and compare the result with takt, capacity or demand.

  4. Standard time = observed time x (rating / 100) x (1 + allowance). On the bench assembly example, the elements add to 28.54 seconds of normal time, and a 15 percent allowance gives 28.54 x 1.15 = 32.82 seconds. Machine time that runs on its own is not rated and takes no allowance.

  5. No. A machine runs at its own set speed whoever is watching, so rating its time would only add error. Rate only the elements the operator controls, and add the allowance to those. In the machine-tending example the 62 second run is left as timed, and the operator's elements are rated and carry a 12 percent allowance.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.