Flow process chart and operation process chart: symbols, how to build them, and an example

Short answer

A flow process chart lists every step an item goes through, from raw rack to finished rack, using five symbols: operation, transportation, inspection, delay and storage. An operation process chart keeps only the operations and inspections, so you see the shape of the whole product.

Build a flow process chart by following one item through the process and writing down every step in order: what happens, which symbol it is, how far it moves and how long it takes. The operation process chart is the short version, with only operations and inspections, and a line for each part that joins the main line where the parts meet. In the example on this page, 295 minutes of elapsed time hold 25 minutes of actual operations, and the chart shows where the other 270 minutes go.

Last reviewed:

What are a flow process chart and an operation process chart?

A process chart is a record of what happens to one thing as it moves through a process. The thing is a part, a patient, a form or an operator. You follow it, and you write down each step as one of a few standard symbols. The result is a column of symbols down a page that you can count, add up and challenge.

There are two charts, and they answer different questions. The flow process chart records every step, including the moves, the waits and the storage. It answers "where does the time and distance go?" The operation process chart records only the operations and the inspections, and shows how the parts come together. It answers "how is this product made, and in what order do the parts join?" Some books call it an outline process chart.

Method study teaches both as the first step before a detailed look at motions. A flow process chart can follow a worker, a material or a piece of equipment. Most plant studies follow the material, because that is where the waiting shows up. This page is about the material type.

The symbols, and what each one means

The six symbols on a process chart

  • Operation

    Work that changes the item or adds to it.

    Turn, drill, weld, assemble, pack

  • Transportation

    The item moves from one place to another.

    Forklift to the saw, 40 m

  • Inspection

    The item is checked for quality or quantity.

    Gauge the bore, count the pieces

  • Delay

    The item waits and the next step cannot start.

    Parts queued at the lathe

  • Storage

    The item is held under control until it is asked for.

    Finished goods rack

  • Combined activity

    Two activities done at once, here an operation and an inspection.

    Operator machines and gauges in one step

Six symbols. A circle is an operation. An arrow is a transportation. A square is an inspection. A capital D is a delay. An inverted triangle is storage. A circle inside a square is a combined activity, such as an operation and an inspection done together.

Five symbols come from the ASME process chart standard, the sixth joins two of them. If you cannot decide between a circle and a D, ask whether the item is being worked on or just sitting.

The American Society of Mechanical Engineers adopted a standard set of process chart symbols in 1947, built on the work of Frank and Lillian Gilbreth. The standard was revised in later editions, but the symbols are the ones still taught in method study and used on the sheets in the textbooks. Five of them describe what happens to the item. A sixth joins two of them.

The process chart symbols and when to use each
SymbolNameUse it whenDo not use it for
CircleOperationWork changes the item or adds to it: a cut, a weld, a fill, a label, a form being completed.Walking to fetch material, or checking the result.
ArrowTransportationThe item moves from one place to another, by hand, by cart, by forklift or by conveyor.Small moves inside one workstation: those belong inside the operation.
SquareInspectionThe item is checked against a standard for quality or quantity.An operator glancing at the part as part of the work. That is inside the operation.
Capital DDelayThe item waits and the next step cannot start, such as a queue in front of a machine.Planned storage, where the item is held under control until it is called for.
Inverted triangleStorageThe item is held under control until someone asks for it, such as a rack or a stockroom.Waiting in a queue between two steps.
Circle inside a squareCombined activityTwo activities happen together at one place, such as an operator who machines and gauges in one step.Two activities done one after the other. Those get two symbols.

Definitions are restated in plain words. Check your own company's chart standard if it has one, because some plants add a symbol for rework or scrap.

The hard call is delay against storage. A delay is waiting that nobody chose: parts piled up because the next machine is busy. Storage is waiting that someone chose and controls: parts in a rack with a count, taken out on a signal. If you cannot tell which it is, ask whether anybody would notice if the parts were not there. In a rack with a count, they would. In a queue, they would not.

How to build a flow process chart

  1. 1

    Choose one item and fix the start and the end

    A single part number, a single order or a single batch. Write where the chart starts and where it ends, for example from the raw rack to the finished goods rack. Charts without a clear start and end cannot be compared later.

  2. 2

    Walk the route and write every step in order

    Follow the item, not the layout drawing. Write each step as it actually happens, including the waits and the moves nobody had on the routing. Number the steps.

  3. 3

    Give each step one symbol

    Circle, arrow, square, D or triangle. If a step seems to be two things, split it. Use the combined symbol only when two things really happen at once.

  4. 4

    Record distance and time

    Measure each move in metres with a tape or a wheel. Time each operation with a stopwatch or from video (see how to conduct a time study). For the waits, note when the item arrived and when it was picked up, not a guess.

  5. 5

    Total by symbol

    Count the steps and add the minutes and the metres for each symbol. Put the totals under the chart. Work out what share of the elapsed time was operations.

  6. 6

    Challenge every row, then chart the new way

    Ask of each step: why is it done, why there, why then, why this way? Remove what you can, combine what you can, and redraw the chart for the improved flow with the same totals.

Time and distance are what turn the chart into an argument. A list of steps says what happens. A list with 255 minutes of waiting next to 25 minutes of work says what to fix first.

Worked example: a turned housing

This is an invented example, built to show the arithmetic. A small plant makes a turned aluminium housing from bar stock. One batch of parts is followed from the raw rack to the finished goods rack. The clock starts when the bar is taken from the rack and the storage rows carry no time.

The chart has 17 rows. Five are operations (cut, turn, deburr, wash, pack), five are transportations, two are inspections, three are delays and two are storage. The delays are 45 minutes at the saw, 120 at the lathe and 90 waiting for a full wash batch.

A flow process chart, filled in: a turned housing, raw rack to finished rack

Example numbers
No.StepMetresMinutes
  1. 1Bar stock in the raw rack
  2. 2Forklift to the saw403
  3. 3Wait for the saw45
  4. 4Cut to length4
  5. 5Cart to the lathe122
  6. 6Wait at the lathe120
  7. 7Turn the housing9
  8. 8Check the diameters2
  9. 9Cart to deburr81
  10. 10Deburr3
  11. 11Wait for a full wash batch90
  12. 12Cart to the washer152
  13. 13Wash5
  14. 14Final inspection3
  15. 15Cart to packing202
  16. 16Pack4
  17. 17Finished goods rack
Total95295

Seventeen steps down a vertical line: 5 operations, 5 transportations over 95 metres, 2 inspections, 3 delays and 2 storages. The three delays are 45, 120 and 90 minutes. Elapsed time from release to packed is 295 minutes, of which 25 are operations.

The delay rows, shaded, are 255 of the 295 minutes. The operations that make the part are 25. That gap is what the chart exists to show.
Illustrative. Totals of the flow process chart, by symbol
SymbolStepsMinutesMetresShare of elapsed time
Operation52508.5%
Transportation510953.4%
Inspection2501.7%
Delay3255086.4%
Storage2000%
Total1729595100%

Elapsed time is the sum of every row. The storage rows carry no time because the clock starts when the bar leaves the rack and stops when the packed part is put away.

Read the totals before you read the rows. Operations are 25 of the 295 minutes, 8.5%. Delays are 255. Nobody has to be working slowly for this to happen: the saw, the lathe and the washer each run in batches, so parts queue. The cart move to the lathe (12 m) exists only because the saw is in a different bay from the lathe.

Where the 295 minutes went, before and after

Example numbers

Before: 295 min elapsed, 95 m walked or driven

After: 84 min elapsed, 83 m walked or driven

  • Operation
  • Inspection
  • Transport
  • Delay

Two bars on one scale. Before: 25 minutes of operation, 5 of inspection, 10 of transport and 255 of delay, 295 in all, over 95 metres. After the saw moves next to the lathe and the queues shrink: 25, 5, 8 and 46, 84 minutes in all, over 83 metres. Operations go from 8.5 percent of elapsed time to 29.8 percent.

Nothing was made faster. The operations take the same 25 minutes both times. The time came out of the waiting and one move.

Now the change. Put the saw next to the lathe, which removes the 12 m cart move and its 2 minutes. Cut the queue at the saw to 11 minutes, at the lathe to 15 and at the washer to 20 by releasing smaller batches and washing when 10 pieces are ready rather than a full tray. The chart is redrawn: transportation is now 8 minutes and 83 m, delay 46 minutes. Elapsed time falls from 295 to 84 minutes, 71.5% less. The operations still take 25 minutes. They are now 29.8% of the elapsed time.

That is the most useful thing a flow process chart does. It shows that the elapsed time and the work content are very different numbers, and that the biggest saving is rarely in the operations. The same idea is why a value stream map draws a lead time ladder under the process boxes.

How to build an operation process chart

The operation process chart keeps only two symbols, the circle and the square. It is drawn as a tree. The main line runs down the right side. Each part or sub-assembly gets its own line that comes in from the side and joins the main line at the operation where the parts meet. Material goes in horizontal lines at the top of each line, with a short label such as the stock and size.

Take the same housing and add a stamped steel cover. The housing line has four steps: cut to length (4 min), turn (9), check the diameters (2) and deburr (3). The cover line has two: stamp (2) and deburr (1). They meet at assembly (6), followed by final inspection (3) and pack (4).

  • Number the operations in order down the chart (O-1, O-2 and so on) and the inspections separately (I-1, I-2).
  • Show time beside each symbol. The chart is not to scale, only to order.
  • Add a summary at the bottom: 7 operations (29 minutes), 2 inspections (5 minutes), 34 minutes of work content in all.
  • Leave out moves, delays and storage. They belong on the flow process chart.

An operation process chart: housing and cover, joined at assembly

Example numbers

HousingAluminium bar, 60 mm

  1. O-1 Cut bar to length4 min
  2. O-2 Turn the housing9 min
  3. I-1 Check diameters2 min
  4. O-3 Deburr3 min

CoverSteel sheet, 2 mm

  1. O-4 Stamp the cover2 min
  2. O-5 Deburr the cover1 min

Both lines join here

  1. O-6 Assemble cover to housing6 min
  2. I-2 Final inspection3 min
  3. O-7 Pack4 min

Summary: 7 operations (29 min), 2 inspections (5 min), 34 min of work content.

Two feeder lines run down and join. The housing line has cut to length 4 minutes, turn 9, check diameters 2 and deburr 3. The cover line has stamp 2 and deburr 1. They join at assemble 6, then final inspection 3 and pack 4. In all there are 7 operations, 29 minutes, and 2 inspections, 5 minutes.

Only operations and inspections appear: no moves, no waits. Each feeder line joins the main line where the parts meet, so the shape of the product shows.

Its main use is early. When you plan a new product, the chart shows how many operations it needs, which parts can be made in parallel, where the parts join and where the inspections sit. It is the starting point for the process planning of a new product, and for splitting the work into stations in line balancing.

Process charts compared with other flow tools

Which tool answers which question
ToolFollowsShowsBest question
Flow process chartOne item, step by stepEvery operation, move, check, wait and store, with time and distanceWhere do the minutes and the metres go for this item?
Operation process chartOne product and its partsOperations and inspections, and where parts joinHow is this product made, in what order?
Flowchart (decision flow)A procedure or a decisionSteps and yes or no branches, with no standard time or distance columnsWhat are the rules and who does what?
Value stream mapOne product family, with the information that triggers itProcess boxes, inventory between them, the lead time ladderHow long does an order take across the whole stream?
Spaghetti diagramOne item or person on a floor planThe actual path walked or driven, drawn on the layoutWhich routes are long, and where do they cross?

They work together. The flow process chart gives the list of moves and the total distance. The spaghetti diagram draws those moves on the floor plan so you can see the crossings and the backtracking. A flowchart, as in the flowchart guide, documents a decision procedure. A value stream map takes the view across the whole stream, and the process chart zooms in on one stretch of it.

Common mistakes

  • Charting the routing instead of the item. The routing leaves out the waits and the unplanned moves, which are most of what you are looking for.
  • Following a different part each time. Pick one part number and one batch. Mix them and the totals mean nothing.
  • Guessing the delays. A queue is timed from when the item arrives to when it is picked up. Recorded waits are usually the number people argue about, so have them on paper.
  • Using the circle for everything. Walking to fetch a tool is not an operation. Checking is not an operation. The chart only helps if the symbols are used strictly.
  • Stopping at the chart. The totals only show where to look. The next step is to ask why each move and each wait exists, and to draw the improved flow.
  • Treating the chart as the whole picture. It follows one item. It does not show the capacity of a machine, the mix of products or what the operator does with their hands. For hands and motions, use a two-handed process chart or a time study.

Be careful with the people side. A chart that follows a worker records what one person did in the hour you watched. Say what it is for before you start, show the chart to the people on it, and chart the material first, not the operator.

Tools and templates

FAQ

Questions about flow process chart and operation process chart

  1. Five ASME symbols describe what happens to an item. A circle is an operation, an arrow is a transportation, a square is an inspection, a capital D is a delay and an inverted triangle is storage. A circle inside a square marks a combined activity, such as an operation and an inspection done together at one place.

  2. A flow process chart records every step one item goes through, including moves, delays and storage, with distance and time. An operation process chart records only operations and inspections, and shows how the parts of a product join. Use the first to find where time and distance go, and the second to understand how a product is made.

  3. Pick one item and fix where the chart starts and ends. Follow it and write every step in order, give each step one symbol, and record the distance and time of each. Total the steps, minutes and metres by symbol, work out what share of elapsed time is operations, then challenge each step and chart the improved flow.

  4. A process flow chart usually means a general flowchart of steps and decisions, often drawn with boxes and diamonds. A flow process chart is the method study tool: one item, ASME symbols, and columns for distance and time. Only the second gives you totals of delay and travel, which is what you need to improve a flow.

  5. A flow process chart follows one item through one stretch of the process in detail, with every move and wait. A value stream map shows a whole product family from supplier to customer, including the information that triggers each step and the inventory between them. Start with the map to find the stretch, then use the chart to study it.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.