Process planning for a new product: routing, work content and stations

Short answer

Process planning turns a product design into a list of operations in order, each with a station, equipment and a time. That list is the routing. Add up the operator times and you have the work content, the number every staffing and capacity sum starts from.

To plan the process for a new product, break the product into its parts and sub-assemblies, list every operation and inspection needed to make it, and put them in the order the build forces. Give each one a number, a station type, the equipment and tooling, the parts it consumes and an estimated time. Draw the result as an operation process chart, add up the operator time to get the work content, check each machine against the rate you need, then carry the same operation numbers into the PFMEA, the control plan and the work instructions. Replace the estimated times with studied ones at the pilot run.

Last reviewed:

What is process planning?

The whole plan in one picture: an operation process chart

Example numbers
Operation process chart for the LED work lightOperation process chart with three vertical lines. On the right the main line: O-1 Housing in fixture, seal, 14 seconds; O-5 LED module in, plug lead, 24 seconds; O-6 Driver board, 2 screws, 18 seconds; O-9 Handle on, 4 screws, 28 seconds; O-10 Front bezel, 6 screws, 30 seconds; I-2 Function and leak test, 16 seconds; O-11 Label, scan serial, 10 seconds; O-12 Battery, bag, box, 27 seconds. The LED module, O-2 Pad and LED board, 22 seconds; O-3 4 board screws, 18 seconds; O-4 Lens, gasket, ring, 20 seconds; I-1 Light-up test, 12 seconds, joins the main line before O-5. The handle, O-7 Switch, lead in handle, 26 seconds; O-8 Close handle, 3 screws, 21 seconds, joins before O-9. 12 operations take 258 seconds and 2 inspections 28 seconds: 286 seconds of work content.LED module72 sHandle47 sMain line167 sO-114 sO-222 sO-318 sO-420 sI-112 sO-524 sO-618 sO-726 sO-821 sO-928 sO-1030 sI-216 sO-1110 sO-1227 sFinished work light
  1. O-1 Housing in fixture, seal
  2. O-2 Pad and LED board
  3. O-3 4 board screws
  4. O-4 Lens, gasket, ring
  5. I-1 Light-up test
  6. O-5 LED module in, plug lead
  7. O-6 Driver board, 2 screws
  8. O-7 Switch, lead in handle
  9. O-8 Close handle, 3 screws
  10. O-9 Handle on, 4 screws
  11. O-10 Front bezel, 6 screws
  12. I-2 Function and leak test
  13. O-11 Label, scan serial
  14. O-12 Battery, bag, box

12 operations 258 s + 2 inspections 28 s = 286 s of work content

Read each line from the top. Circles are operations, squares are inspections, and the number to the left of each is operator seconds. A horizontal line is material coming in. The LED module and the handle are built on their own and join the main line where they are used. Everything on this page hangs off these 14 numbered steps and their total, 286 seconds.

Process planning is deciding how a product will be made before anyone makes it. The design says what the product is. The process plan says which operations turn parts into that product, in what order, where, with what equipment and in how much time.

It exists because every later decision leans on it. You can't size a line without knowing the work content. You can't buy a tester without knowing how many units an hour it has to pass. You can't write a PFMEA without a list of process steps to ask "what can go wrong here?" about. A weak process plan shows up months later as a station that doesn't fit takt or a control plan that skips an operation.

The plan is a small set of linked documents. They are easy to mix up, because plants and ERP systems use the names loosely.

The documents a process plan is made of
DocumentWhat it holdsWho uses it
Bill of materials (BOM)The parts and quantities in one unit, level by level. It says what goes in, not howDesign, purchasing, materials
Operation sequenceEvery operation and inspection in the order the build forcesManufacturing and industrial engineering
Operation process chartThe sequence drawn with symbols, showing where each part and sub-assembly joins, with a time on every stepEngineering, layout, launch team
RoutingThe sequence as a table: operation number, description, work centre or station, equipment, tooling, setup and run timePlanning, costing, scheduling, ERP
Bill of process (BOP)The routing with everything each operation needs attached: parts consumed, tools, fixtures, programs, skills, quality checksManufacturing engineering, MES and PLM
Process flow chartEvery step including moves, waits and storage, used as the backbone of the PFMEA and the control planQuality, APQP team
Work instructionHow to do one operation, step by step, for the person doing itOperators, trainers, team leaders

Routing is the older ERP word and bill of process the newer PLM one. Many plants use them for the same table. What matters is that there is one master list of operations and every other document points at it.

Work content is the total operator time one unit needs, found by adding the operator time of every operation. It is not the same as cycle time or lead time. Machine time that runs with nobody attending is listed beside it, not inside it, because it does not use up a person.

How to plan the process, step by step

Do these in order, with the design engineer, a quality engineer and someone who has built a similar product at the table. The first pass takes a day or two for a product of this size. Expect to redo parts of it each time the design changes.

Process planning from the product structure to linked documents

  1. 1

    Start from the product structure

  2. 2

    List every operation and inspection

  3. 3

    Put them in the order the build forces

  4. 4

    Number the steps and draw the operation process chart

  5. 5

    Choose the station type and equipment for each operation

  6. 6

    Estimate the time for each operation

  7. 7

    Add up the work content and check the machines

  8. 8

    Carry the operation numbers into every other document

Steps 1 to 4 decide what the work is. Steps 5 to 7 decide where it happens and how long it takes. Step 8 keeps every other document in line.
  1. 1

    Start from the product structure

    Take the bill of materials and the drawings or the CAD model. Mark which parts are bought finished, which are made in house, and which groups of parts can be built up as a sub-assembly away from the main line.

  2. 2

    List every operation and inspection

    For each part and each joint, write what has to happen: place, fasten, press, apply, connect, test, label, pack. One line per operation. If a line needs the word "and" twice, split it.

  3. 3

    Put them in the order the build forces

    For each operation ask what must already be done before it can start. That gives the precedence. Anything the product does not force is a choice you can use later to balance the line.

  4. 4

    Number the steps and draw the operation process chart

    Main component on the right, sub-assemblies to its left, each feeding in where it joins. Circles for operations, squares for inspections, a number in every symbol.

  5. 5

    Choose the station type and equipment for each operation

    Hand work at a bench, a fixture, a powered tool, a semi-automatic machine or full automation. Decide from the force and precision needed, the quality risk, the volume and the ergonomics, in that order.

  6. 6

    Estimate the time for each operation

    Use predetermined times, times from similar jobs or a timed mock-up. Record operator time and unattended machine time in separate columns, and write down where each number came from.

  7. 7

    Add up the work content and check the machines

    Total the operator time. Then check every machine: the time it is tied up per unit must be less than the time you have per unit, or you need a second one.

  8. 8

    Carry the operation numbers into every other document

    The PFMEA, the control plan, the work instructions and the time study all use the same numbers. Then keep the routing under change control, so a design change updates all of them together.

Step 6 is the one people worry about, because the product does not exist yet. A separate guide covers how to estimate cycle time for a new product. The short version: an estimate that is honest about its source is good enough to plan with, as long as you replace it at the pilot run.

The operation process chart and its symbols

An operation process chart shows the whole build on one page: every operation and inspection, in order, with the point where each part and sub-assembly enters. The ILO's work study manual calls the same thing an outline process chart. It is the fastest way to explain a product's process to someone who has never seen it.

The symbols come from the American Society of Mechanical Engineers. Frank and Lillian Gilbreth presented process charts to the society in 1921 with a long list of symbols. In 1947 the society published ASME Standard 101, Operation and Flow Process Charts, which cut the list to five. Those five are still the ones in the textbooks.

The five ASME process chart symbols
SymbolNameWhat it meansOn an operation process chart?
CircleOperationThe work changes something: a part is formed, fastened, assembled, taken apart or prepared for the next stepYes
SquareInspectionThe work is checked for quality or quantity against a standard, and nothing is changedYes
ArrowTransportationThe object moves from one place to another, other than a move that is part of an operationNo
Capital DDelayThe object waits because the next step can't start yetNo
Triangle, point downStorageThe object is kept and protected, and needs a release to moveNo

A square drawn around a circle is a combined activity: an operation and an inspection done together at one place, such as a press that checks its own force.

The five ASME symbols, and the two the operation process chart uses

Operation

Something is changed: formed, fastened, assembled

On the operation process chart

Inspection

Checked against a standard, nothing changed

On the operation process chart

Transportation

Moved from one place to another

Flow process chart only

Delay

Waiting because the next step can't start

Flow process chart only

Storage

Kept and protected until released

Flow process chart only

Combined

An operation and an inspection done together at one place

Circle inside a square

An operation process chart shows the work a product needs, so it uses only the circle and the square. Moves, waits and storage depend on the layout and go on the flow process chart.

The operation process chart uses only the first two. That is deliberate. It shows the work the product needs, not the layout it happens in. Moves, waits and storage belong on the flow process chart, which you draw later for one part or one person once there is a layout to follow. The same idea in general form is on the flowchart guide.

The drawing rules

  • Vertical lines are the flow of the work, top to bottom in the order it is done.
  • Horizontal lines are material coming in. A bought part or a finished sub-assembly joins the vertical line just above the operation that uses it.
  • The component with the most operations goes on the right, as the main line. Sub-assemblies sit to its left and feed in where they join.
  • Operations are numbered in one series and inspections in another, in the order they are charted: start at the top of the main line, and when a sub-assembly joins, number its steps before going on down.
  • Write the time to the left of each symbol and a short description to the right.
  • Lines should not cross. If two must, draw a small bridge on the horizontal one so nobody reads it as a junction.
  • Finish with a summary: the count of operations and inspections and the total time.

The commonest mistake is to draw a flowchart with boxes and diamonds and call it an operation process chart. Boxes hide the difference between making and checking, and that difference is what quality and industrial engineering both need to see.

Worked example: a routing for an LED work light

The product is a rechargeable LED work light: a rear housing, an LED module on a heat sink, a driver board, a handle with a switch, a front bezel and a battery. It is illustrative, not a real product. The LED module and the handle can each be built on their own, so the chart has three columns.

Numbering follows the drawing rules. The main line starts with O-1 on the rear housing. The LED module joins next, so its steps are O-2 to O-4 and I-1. Then the main line carries on with O-5 and O-6, the handle is built in O-7 and O-8, and it joins at O-9.

Illustrative: routing for the LED work light, with planning times in seconds
No.OperationLineStation and equipmentOperator timeMachine time
O-1Load rear housing in fixture, fit sealMainBench with holding fixture14
O-2Apply thermal pad, place LED board on heat sinkLED moduleBench with locating nest22
O-3Drive 4 board screwsLED moduleElectric screwdriver, torque controlled18
O-4Fit lens and gasket, clip on the lens ringLED moduleBench20
I-1Light-up test of the LED moduleLED moduleTest fixture with light sensor12
O-5Fit LED module into housing, plug in the LED leadMainBench with holding fixture24
O-6Fit driver board, drive 2 screwsMainElectric screwdriver, torque controlled18
O-7Fit switch and lead into the handle halvesHandleBench26
O-8Close the handle, drive 3 screwsHandleElectric screwdriver, torque controlled21
O-9Attach handle, plug in the switch lead, drive 4 screwsMainHolding fixture, screwdriver28
O-10Fit front bezel, tighten 6 screws in sequenceMainDC tool with torque and angle check30
I-2Function and leak test: unload, load, startMainAutomatic tester1640
O-11Apply rating label, scan the serial numberMainLabel printer and scanner10
O-12Fit battery, bag, box with the manualMainPacking bench27
Total12 operations and 2 inspections28640

Times are planning estimates at standard pace with allowances included. The tester's 40 seconds run with nobody attending, so they are not work content.

The work content is 286 seconds, or 4.77 minutes, of operator time for one light. The table below shows where it sits.

Illustrative: work content of the LED work light by line and by type
GroupStepsOperator timeShare
LED module sub-assemblyO-2, O-3, O-4, I-172 s25.2%
Handle sub-assemblyO-7, O-847 s16.4%
Main lineO-1, O-5, O-6, O-9, O-10, I-2, O-11, O-12167 s58.4%
Total work content14 steps286 s100%
Of which operations12258 s90.2%
Of which inspections228 s9.8%

Where the 286 seconds of work content sit

Example numbers

LED module72 s

  • O-2 Pad and LED board22 s
  • O-3 4 board screws18 s
  • O-4 Lens, gasket, ring20 s
  • I-1 Light-up test12 s

Handle47 s

  • O-7 Switch, lead in handle26 s
  • O-8 Close handle, 3 screws21 s

Main line167 s

  • O-1 Housing in fixture, seal14 s
  • O-5 LED module in, plug lead24 s
  • O-6 Driver board, 2 screws18 s
  • O-9 Handle on, 4 screws28 s
  • O-10 Front bezel, 6 screws30 s
  • I-2 Function and leak test16 s
  • O-11 Label, scan serial10 s
  • O-12 Battery, bag, box27 s

LED module 25.2%, Handle 16.4%, Main line 58.4%. Total 286 s, or 4.77 minutes.

  • Operation
  • Inspection
  • Longest step
Each bar is one step's operator time, drawn to the same scale. The two sub-assemblies hold 119 seconds that need not happen on the main line. The longest step, O-10 at 30 seconds, is the fastest the line could ever cycle without splitting it.

Three things fall out of this at once. The sub-assemblies hold 119 seconds, 42 percent of the work, that does not have to happen on the main line. Screwdriving appears in five operations and 19 screws, so one screw type and one driver would be worth asking the designer for. And O-10 at 30 seconds is the longest single step, which sets a floor: the line can't make a light more often than every 30 seconds unless that step is split or done at two stations.

Choosing stations and equipment

For each operation the question is how much of it a person does and how much a tool or machine does. Go up a level only when there is a reason, because every level adds cost, lead time and one more thing to break.

Levels of station and equipment, and when each one earns its place
LevelWhat it isChoose it when
Hand work at a benchParts, bins and hand toolsThe step is light, simple and easy to see is right
Fixture or nestThe part is held and located, both hands are freePosition matters, or the operator would otherwise hold the part with one hand
Powered tool with a checkA driver, press or dispenser that controls and records torque, force or volumeThe result can't be seen or felt reliably, or the PFMEA rates the failure as severe
Semi-automatic machineThe operator loads and starts it, then it runs aloneThe step is long, repetitive or needs the same conditions every time. The operator can work elsewhere while it runs
Automatic stationLoads, runs and unloads with no operatorVolume is high and stable, the design is frozen and the step is hard or unsafe for a person

Volume alone is a poor reason to automate a new product. Early volumes are a forecast, and the design usually still moves.

Machines need a check that hand work does not. A machine is tied up for a fixed time per unit, and that time has to be less than the time you have per unit. On the work light the tester is tied up for 56 seconds a unit: 16 seconds while the operator unloads the last one and loads the next, then 40 seconds running. If the plan is 360 lights in a 27,000 second shift, each unit has 75 seconds, so one tester is enough. It could pass 27,000 / 56 = 482 units in a shift if it never stopped.

The 40 seconds matter for the operator too. While the tester runs, the operator labels and packs the unit that just came off: 10 + 27 = 37 seconds of work inside a 40 second machine run. That is how one person can hold I-2, O-11 and O-12 and why the three belong at one station.

Operator time and machine time are different things

Example numbers
Operator time and machine time at the final test stationTwo lanes over one 75 second takt. Operator: unload and load the tester 16 seconds, label 10 seconds, pack 27 seconds, then 22 seconds free. Tester: being loaded 16 seconds, runs alone 40 seconds, idle 19 seconds. The tester is tied up 56 seconds a unit, which fits a 75 second takt but not the 50 second takt of 540 a day.Operator16102722Tester164019Takt 75 s at 360 a dayTakt 50 s at 540020406080Seconds in one cycle
  • Operator at the tester: unload and load, 16 s
  • Operator's other work: label 10 s, pack 27 s
  • Tester runs unattended, 40 s
  • Tester being loaded, 16 s
  • Free or idle: operator 22 s, tester 19 s
While the tester runs for 40 seconds on its own, the operator labels and packs the last unit, 37 seconds of work. So the station needs 53 seconds of a person and the tester is tied up for 56. Both fit a 75 second takt. At 540 a day the takt is 50 seconds, the dashed line, and one tester no longer fits.

Write the machine's capacity next to it in the routing. If demand later rises to 540 a day, the time per unit drops to 50 seconds and a 56 second tester can't keep up. That is a second tester, and somebody needs to know months ahead. The sums for people are in planning operators and stations for a new line, and the process capacity sheet does the machine check station by station.

Think about the person at the station while you choose. Reach, force, posture and where the parts sit are far cheaper to fix on paper than on the floor. See designing a future workstation and workstation design.

Common mistakes

  • Planning stations before operations. Decide what the work is first, then how to group it. A layout drawn too early freezes a bad sequence.
  • Adding machine run time into work content. It inflates the headcount. Keep operator time and unattended machine time in separate columns.
  • Leaving out the small steps: unpacking, scanning, label printing, getting rid of packaging. On a new line they are often a tenth of the work.
  • Treating an estimate as a standard. Write the source beside every time, and plan the date it will be replaced by a study.
  • Forgetting inspections added late. A check that quality adds after a pilot defect is real work and needs a number, a time and a station.
  • Separate step lists in the PFMEA, the control plan and the instructions. Within a year they disagree, and an auditor will find it before you do.
  • No owner for changes. Every design change should ask one question of the routing: which operation numbers does this touch?

What a process plan can't tell you

A routing is a model, and the first one is always partly wrong. It can't know which connector will be stiff, which part arrives in awkward packaging, or which step operators will find a better way to do in the first week. Plan for that. Hold a line trial and a pilot run, and treat the differences as findings, not failures.

It also says little about people. The plan gives a time at standard pace for a trained operator. New operators on a new product are slower for weeks, and how fast they close the gap is a planning question of its own, covered in ramp-up plan and the learning curve.

Bring operators and team leaders in early. People who build similar products know where the plan is optimistic, and a plan they helped shape is one they will run. Tell them plainly that the times are for sizing the line, that the times will be studied again on the real job, and that nobody is being measured against an estimate.

For a one-off or a very low volume product, a full bill of process is more than you need. A sequence, a parts list per step and a rough time per step will do. The detail on this page pays back when the product repeats.

Templates and tools for process planning

FAQ

Questions about process planning for a new product

  1. Process planning is deciding how a product will be made: which operations and inspections it needs, in what order, at which stations, with what equipment and tooling, and in how much time. Its main output is the routing. For a new product it is done before the line exists, from the drawings and the bill of materials, and it is updated as the design changes.

  2. A routing is the ordered list of operations needed to make a part or product. Each line has an operation number, a description, the work centre or station, the equipment and tooling, and the setup and run time. Planning systems use it to schedule work, cost the product and work out capacity. Every other process document should use its operation numbers.

  3. A bill of process is the routing with everything each operation needs attached to it: the parts it consumes, tools and fixtures, machine programs, skills, quality checks and the time. Where the bill of materials says what goes into the product, the bill of process says how it is put together. Many plants use routing and bill of process for the same table.

  4. The bill of materials lists the parts and quantities in one unit of product. The bill of process lists the operations that turn those parts into the product, in order, with the station, equipment and time for each. The two are linked: each operation names the parts from the bill of materials that it uses, so every part is consumed somewhere.

  5. An operation process chart is a one-page drawing of how a product is made. It shows every operation as a circle and every inspection as a square, in order from top to bottom, with horizontal lines where parts and sub-assemblies join and a time beside each step. It leaves out moves, waits and storage. The ILO calls it an outline process chart.

  6. Five, from ASME Standard 101 of 1947: a circle for an operation, a square for an inspection, an arrow for transportation, a capital D for a delay and a triangle pointing down for storage. An operation process chart uses only the circle and the square. A flow process chart uses all five. A circle inside a square means an operation and an inspection done together.

  7. Work content is the total operator time needed to make one unit, found by adding the operator time of every operation in the routing. Machine time that runs unattended is not included. Divide work content by takt time and you get the least number of operators the line needs, which is why it is the first number to pin down for a new product.

  8. Through the operation numbers. Each step in the routing is one step in the process flow chart, one or more rows in the PFMEA and one or more rows in the control plan, in the same order. When an operation is added, split or removed, all of them change together. Separate step lists drift apart and are a common audit finding.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.