Short answer

In welding, the arc is on for a minority of the shift. Measure that share, the operator factor, by work sampling or from the power source. Estimate a job as arc time, from weld length and travel speed, divided by the operator factor. Then go after the time outside the arc.

Fabrication work is long, varied and rarely repeats, so a classic stopwatch study of one cycle says little. The useful measure for welding is the operator factor: arc-on time divided by total time. Find it by work sampling the welders over one or two weeks, or from arc-time data on the power source. Estimate a weldment by working out the arc time from weld length and travel speed, then dividing by the operator factor to get labor time. Most of a welder's day is fit-up, handling, grinding, fetching and waiting, and that is where the improvement is. Do not confuse the operator factor with duty cycle, which is a rating of the welding machine.

Last reviewed:

What makes fabrication different

A time study was designed for a job that repeats every minute. A fabrication shop offers the opposite. A welder may spend forty minutes on one frame and not see the same frame again for a month. The job after it is a different size, with different joints, in a different position.

  • Cycles are long and few. Thirty cycles of a 40 minute job is twenty hours of observation for one part number.
  • The value-adding moment is narrow. Metal is joined only while the arc is on. Everything else, from fitting the parts to chipping spatter, surrounds it.
  • The work content depends on the weld, not the part. Time follows weld length, joint type, position and plate thickness, which is good news: those can be read off a drawing.
  • The welder moves. Fetching parts, waiting for a crane, walking to the wire store: a camera fixed on the booth sees only part of the day.
  • Machines set part of the pace. A laser cuts at the speed of its program, and a press brake bends in seconds but takes many minutes to set up.

So fabrication uses a different mix of methods. A direct study still fits the repeating jobs, such as a robot cell or a bracket welded all week. For everything else, the tools are work sampling, machine data and estimating from standard data.

What gets timed, process by process

Fabrication processes: what paces each one and how to measure it
ProcessPaced byWhat to measureMethod
Laser, plasma or punchThe programCut time per nest, sheet load and unload, part sortingMachine data for the cut. Video for loading and sorting, which is where the labor is.
Press brakeSetup, then handsTool change and first-part time per job, seconds per bend, handling per partA changeover study for the setup. A short video study for the bend cycle.
Fit-up and tackHands, fixtures, the craneTime per part located and tacked, waiting for lifting gearWork sampling across the shop, video for a repeating fixture job
Manual and semi-automatic weldingThe welderArc-on time, operator factor, time per metre of weld by joint typeWork sampling or power source data, plus standard data per metre
Robot weldingThe programRobot cycle, load and unload, operator work during the cycleMachine data and a man-machine chart
Grinding and cleaningHandsTime per metre of weld dressed, time on spatter and reworkVideo, or sampling for the share of the day
Inspection and handlingPeople and cranesWaiting time, crane moves per jobWork sampling

Two of these rows repay study faster than the rest. The press brake, because in a job shop its setup can take longer than the run, and that is a SMED problem. And manual welding, because it is the most labor in the building and the least measured. The rest of this guide is mostly about the second.

A robot cell is machine-paced, so treat it like a CNC machine: the robot cycle comes from the controller and the operator's loading and tacking are timed against it. The method is in time study in CNC machining.

The operator factor: the one number to know

The operator factor, also called the operating factor, is the share of a welder's time in which the arc is on.

Operator factor = arc time / total time.

It exists because weld metal goes down only while the arc is on, and the arc time for a given weld is close to fixed by the procedure. So the operator factor is what turns a calculated arc time into the labor time you pay for: labor time = arc time / operator factor.

What is a normal figure? It depends heavily on the process and the kind of work. The Welding Institute (TWI) job knowledge note on welding costs lists the share of working time the arc is burning at 15 to 30 percent for manual metal arc welding, 30 to 45 for manual MIG/MAG and 25 to 40 for TIG, excluding set-up and assembly time. TWI calls that share the duty cycle, which is not the machine rating covered below. Those ranges are wide for a reason. Treat any published figure as a starting guess and measure your own shop, because the number you assume goes straight into every quote.

It is not the duty cycle

The two terms are mixed up constantly, and they measure different things.

Operator factor and duty cycle compared
Operator factorDuty cycle
What it describesHow the welder's time was spentWhat the welding power source can stand
DefinitionArc time / total time, over a shift or a jobMinutes in a ten minute period the machine can run at a rated current
Example28 percent: the arc was on for 28 percent of the time studied60 percent at 300 amps: six minutes welding, four minutes cooling
Where it comes fromWork sampling or arc-time data from your shopThe machine's rating plate and manual
Used forEstimating labor and finding lost timeChoosing a machine that will not overheat

The ten minute period is the convention in the equipment standard EN 60974-1. Some makers rate on a different period, so check the manual.

A machine with a 60 percent duty cycle does not mean the welder welds 60 percent of the time. In most manual work the welder's own stops keep the machine well inside its rating.

Two clocks that people mix up

Duty cycle: what the machine can stand

Operator factor: how the welder's time was spent

Duty cycle is a machine rating: at 60 percent and 300 amps the power source can weld 6 minutes of every 10 and must cool for 4. Operator factor is a measure of the shop: in the example the arc was on 28 percent of the time studied, and 72 percent was fit-up, handling, grinding and waiting.

Duty cycle is on the rating plate and protects the machine. Operator factor is in your tally and tells you what the labor costs. A 60 percent machine does not mean a welder who welds 60 percent of the time.

Measuring the operator factor by work sampling

Work sampling suits welding well. The work is long and irregular, several welders can be covered on one round, and a glance is enough to tell whether the arc is on. The full method, with the sample size formula and a random schedule, is in the work sampling guide. The steps for a weld shop:

  1. 1

    Set the categories

    Seven is enough: arc on, fit-up and tack, grinding and cleaning, handling and positioning, getting parts and consumables, waiting, and personal or other. Write a one-line definition for each.

  2. 2

    Tell the welders

    Explain that the tally is by activity and not by name, and that the aim is to find what keeps them from welding. Most welders have a list ready.

  3. 3

    Decide the number of observations

    About 500 gives a margin of around 4 points on a category near 30 percent. The work sampling observations calculator gives the number for your target.

  4. 4

    Make rounds at random times

    Spread them over at least ten shifts, including the start and end of shifts. On each round, record what each welder is doing at the instant you first see them.

  5. 5

    Tally and calculate

    The operator factor is the arc-on count divided by all observations. Report it with its margin of error.

  6. 6

    Rank what is not arc time

    Sort the other categories from largest to smallest. The top two are your improvement project.

Illustrative: a work sampling tally for a welding bay, 500 observations over ten shifts
ActivityObservationsShare of time
Arc on14028.0%
Fit-up and tack11022.0%
Grinding and cleaning7515.0%
Handling and positioning7014.0%
Getting parts and consumables459.0%
Waiting: crane, inspection, instructions408.0%
Personal and other204.0%
Total500100.0%

Operator factor = 140 / 500 = 28 percent. Margin at 95 percent confidence = 1.96 x the square root of 0.28 x 0.72 / 500 = 3.9 points, so between 24.1 and 31.9 percent.

Where a welder's day goes: 500 observations

Example numbers
  • Arc on140 of 500

    28.0%
  • Fit-up and tack110 of 500

    22.0%
  • Grinding and cleaning75 of 500

    15.0%
  • Handling and positioning70 of 500

    14.0%
  • Getting parts and consumables45 of 500

    9.0%
  • Waiting: crane, inspection, instructions40 of 500

    8.0%
  • Personal and other20 of 500

    4.0%

95% margin on the arc share: 1.96 x the square root of 0.28 x 0.72 / 500 = 3.9 points, so 24.1 to 31.9 percent.

Work sampling of a welding bay, 500 observations over ten shifts. Arc on: 140, 28.0%. Fit-up and tack: 110, 22.0%. Grinding and cleaning: 75, 15.0%. Handling and positioning: 70, 14.0%. Getting parts and consumables: 45, 9.0%. Waiting: crane, inspection, instructions: 40, 8.0%. Personal and other: 20, 4.0%. The arc was on 28.0% of the time, with a 95 percent margin of 3.9 points, between 24.1 and 31.9 percent.

The operator factor is 28%, give or take 3.9 points. The other 72 percent has a list of causes, and the top three after the arc (fit-up, grinding, handling) are the improvement project.

The shortcut: arc-time data

Many modern power sources log arc-on time, and some shops fit a simple arc timer. Arc hours divided by paid hours gives the operator factor with no observer and no sampling error. Use it when you have it. Its limit is the same as any machine data: it tells you the arc was off for 72 percent of the time and nothing about why. The sampling study, or a day of video, is what splits the 72 percent into causes.

A worked example: estimating a frame, then improving it

Illustrative example. A shop welds a steel base frame with 3,200 millimetres of fillet weld. The weld procedure gives a travel speed of 400 millimetres a minute. The bay's operator factor is the 28 percent measured above.

Illustrative: labor time for the base frame
StepWorkingResult
Arc time3,200 mm / 400 mm per minute8.0 min
Labor time8.0 min / 0.2828.6 min
Time outside the arc28.6 minus 8.020.6 min
Frames per welder in a 450 minute shift450 / 28.615.8

Travel speed comes from the weld procedure for the joint, position and process. Where welds differ, calculate the arc time for each and add them.

From weld length to frames per shift

Example numbers
  1. Arc time

    3,200 mm / 400 mm a min

    8.0 min

  2. Labor time

    8.0 / 0.28

    28.6 min

  3. Outside the arc

    28.6 minus 8.0

    20.6 min

  4. Frames per shift

    450 / 28.6

    15.8

Arc time is 3200 millimetres divided by 400 millimetres a minute, 8.0 minutes. Labor time is 8.0 divided by an operator factor of 0.28, 28.6 minutes, of which 20.6 are outside the arc. A welder makes 15.8 frames in a 450 minute shift.

The arc time is fixed by the weld procedure. The operator factor is what turns it into the labor you pay for, so it belongs on its own line in every quote.

Now the question every shop asks: how do we make it faster? There are two levers, and they are not equal.

Illustrative: two ways to cut the labor time of the frame
OptionArc timeTime outside the arcLabor timeSaving
Today8.0 min20.6 min28.6 min
Weld 10 percent faster7.3 min20.6 min27.8 min2.5%
Raise the operator factor to 40 percent8.0 min12.0 min20.0 min30.0%

Welding faster changes only the arc time: 3,200 / 440 = 7.3 minutes. Raising the operator factor changes only the time outside the arc: 8.0 / 0.40 = 20.0 minutes.

Two ways to cut the labor time of the frame

Example numbers

Today

28.6 min

Weld 10 percent faster (saves 2.5%)

27.8 min

Operator factor 40 percent (saves 30.0%)

20.0 min

  • Arc time (the weld)
  • Time outside the arc: fit-up, handling, fetching, waiting

Today: arc 8.0 minutes, outside the arc 20.6, labor 28.6 minutes. Weld 10 percent faster: arc 7.3 minutes, outside the arc 20.6, labor 27.8 minutes, a saving of 2.5%. Operator factor 40 percent: arc 8.0 minutes, outside the arc 12.0, labor 20.0 minutes, a saving of 30.0%.

Welding a tenth faster saves 2.5 percent. Taking 8.6 minutes out of fetching, handling and waiting saves 30 percent, and the weld is untouched. The welder is rarely slow at welding. The shop is slow at letting the welder weld.

Pushing travel speed up by a tenth, if the procedure and the quality allow it at all, saves 2.5 percent. Taking 8.6 minutes out of the handling, fetching and waiting saves 30 percent, and the weld itself is untouched. In the sampling tally those three categories were 31 percent of the day. A positioner that turns the frame, a kit of cut parts delivered to the booth and wire stocked at the point of use go after exactly those.

This is the main lesson of a welding study. The welder is rarely slow at welding. The shop is slow at letting the welder weld.

Building standard data for quoting

A fabricator quotes jobs it has never built, so it needs times it can read off a drawing. Build them the same way, piece by piece: minutes per metre of weld by joint type, size and position from the procedures; minutes per part for fit-up and tack from a few video studies; minutes per bend and per setup at the brake; minutes per metre of weld dressed. Check the total against the hours booked on finished jobs and correct the pieces that are off. Keep the operator factor as its own line, so that when you improve it every quote improves with it.

Ergonomics of welding and fabrication

Welding loads the body in a way assembly does not: the posture is held still. A welder may hold a torch steady with the neck bent and the arms unsupported for minutes at a time, and the worst positions, overhead and inside a structure, are the ones the work forces.

  • Static postures: a bent neck under a helmet, a bent back over a low weldment, arms held out with no support.
  • Awkward positions: kneeling, squatting and overhead welding on large fabrications.
  • Force and weight: lifting plate and parts, pulling cables, and the weight of the torch and its lead over a shift.
  • Vibration and grip: long periods on a grinder.
  • Heat, fume and light: these are occupational hygiene matters with their own rules and limits. They are outside a time study, and they are not optional.

The best fix is also the best productivity fix: a positioner or a turning fixture that brings the joint to the welder at bench height, flat and in front. It removes handling time from the tally and the bent back from the posture score in one move. Score the job with the method in ergonomic assessment in manufacturing, and plan the booth with workstation design. This is general practice, not medical or safety advice for your site.

The people side

Welders are skilled, certified and proud of the work, and a number like 28 percent is easy to hear as an accusation. Present it the right way round from the first day.

  • Say what the number is: a measure of the shop, not of the welder. Nobody chooses to wait for a crane.
  • Show the whole tally, not only the arc share. The other six rows are where the welders will recognise their day.
  • Never rank individuals by arc time. It punishes whoever got the awkward job and rewards rushing a weld.
  • Keep quality in the room. A higher arc share from skipping interpass cleaning is not an improvement.
  • Follow any agreement that covers work measurement, and tell people before the first round.

Mistakes specific to welding and fabrication

Welding and fabrication time study mistakes and what to do in their place
MistakeWhat goes wrongDo this
Assuming an operator factorA quote built on 50 percent is far too low if the shop runs at 28.Measure it, by sampling or arc-time data, and update it each year.
Confusing duty cycle with operator factorA machine rating is read as a measure of the welder.Keep them apart: one is on the rating plate, the other is in your tally.
Stopwatch study of a one-off jobHours of observation produce a time for a job that will not run again.Sample the bay, and build standard data per metre of weld.
Chasing travel speedA few percent of labor is saved and weld quality is put at risk.Work on the time outside the arc first.
Timing only the weld boothFetching, crane waits and inspection queues happen out of frame.Use sampling for the whole route, video for the booth.
Ranking welders by arc timePeople rush, hide problems and avoid the hard jobs.Report by bay and by activity, never by name.
Leaving brake setup out of part costSmall batches of bent parts look cheap and the brake is always changing over.Divide the setup by the batch and study the changeover.

Templates, tools and related guides

LeanSuite's time and motion study times the elements of a repeating fabrication job from a phone video and splits them into value-added, necessary and waste, and the ergonomic study scores the postures from video. SMED covers the press brake and fixture changeovers. For how plants in the sector use the platform, see LeanSuite for metal fabrication.

FAQ

Questions about time study in metal fabrication and welding

  1. Arc-on time is the time during which the welding arc is burning and weld metal is being deposited. It is the value-adding part of a welder's day. Divided by the total time, it gives the operator factor. It can be measured by work sampling, by a timer on the welding machine or from the data log of a modern power source.

  2. The operator factor, or operating factor, is arc time divided by total time, usually shown as a percentage. It turns a calculated arc time into labor time: labor time = arc time / operator factor. The Welding Institute lists the arc-on share at 15 to 30 percent for manual metal arc and 30 to 45 percent for manual MIG/MAG, so measure your own.

  3. Duty cycle is a rating of the welding machine: the minutes in a ten minute period it can run at a stated current without overheating. A 60 percent duty cycle at 300 amps means six minutes of welding and four of cooling. Operator factor describes the welder's time: the share of a shift or a job in which the arc was on.

  4. Work out the arc time for each weld as its length divided by the travel speed in the weld procedure, and add them. Divide the total by your shop's operator factor to get labor time. For 3,200 mm of weld at 400 mm a minute the arc time is 8.0 minutes, and at an operator factor of 28 percent the labor time is 28.6 minutes.

  5. For a repeating job in a fixture, film it and time the elements as for any manual job. For varied work, use work sampling: make random rounds over about ten shifts, tally each welder as arc on, fit-up, grinding, handling, fetching, waiting or other, and report the arc share with its margin of error. Then work on the largest non-arc categories.

  6. Raise the share of time the arc is on before trying to weld faster. In the worked example, a 10 percent rise in travel speed saves 2.5 percent of labor, while lifting the operator factor from 28 to 40 percent saves 30 percent. Positioners, kitted parts, consumables at the booth and less waiting for cranes and inspection are the usual means.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.