SMV and SAM in garment manufacturing: what they mean and how to calculate them
Short answer
SMV, the standard minute value, is the time in minutes a trained operator needs to do one operation at standard pace, with allowances included. SAM, the standard allowed minute, means the same in most factories. SMV = basic time + allowances.
To calculate SMV, time the operation over several cycles and average it: that is observed time. Multiply by the operator's rating to get basic time, then add allowances for bundle handling, personal needs and fatigue, and machine delay. An operation observed at 0.40 minutes and rated at 90 has a basic time of 0.36 minutes, and with allowances its SMV comes to 0.45. Add the SMVs of all operations to get the garment SMV. Then line efficiency = pieces made x garment SMV / (people x minutes worked). A line of 24 people that makes 960 T-shirts of 7.50 SMV in 480 minutes runs at 7,200 / 11,520 = 62.5%.
Last reviewed:
What SMV and SAM mean
How 0.40 observed minutes become an SMV of 0.45
Example numbersWhat the stopwatch showed: 0.40 min, operator rated at 90
The SMV: 0.449 min, published as 0.45
- Pick up and position (manual): 0.108
- Topstitch (machine): 0.180
- Trim and put aside (manual): 0.072
- Bundle handling: 0.025
- Personal and fatigue, 12%: 0.046
- Machine delay, 10% of sewing: 0.018
Observed time 0.40 minutes. Basic time at a rating of 90 is 0.360. Bundle handling adds 0.025, personal and fatigue allowance 0.046 and machine delay allowance 0.018, giving an SMV of 0.449 minutes.
SMV stands for standard minute value. It is the time, in minutes, that a trained operator working at a standard pace needs to complete one operation on one garment, with allowances included for rest, small machine delays and handling. An SMV of 0.45 means one piece should take 0.45 minutes, which is 27 seconds.
SAM stands for standard allowed minute. In most factories, and in most buyers' costing sheets, SAM and SMV are two names for the same number. You will meet people who draw a line between them: some call the value before certain allowances the SMV and the value after them the SAM, and some use SAM for a figure with a factory policy allowance added. There is no single agreed rule. Ask how your factory and your buyer define each one, and write the definition on the operation bulletin.
Garment factories run on this number. Add the SMVs of every operation and you have the garment SMV: the standard labor content of the style. From it come the line target, the number of operators and machines, the line efficiency, the labor cost quoted to the buyer and, in many factories, the incentive. Outside the garment industry the same thing is called standard time.
How an SMV is built: basic time and allowances
An SMV has two layers. The first is the work itself at a standard pace. The second is time that a person and a machine need over a day but that does not show in any single cycle.
| Part | What it is | How you get it |
|---|---|---|
| Observed time | The average time the operator took for one cycle while you watched | Time 10 or more good cycles and average them |
| Rating | How the operator's pace compares with standard pace. 100 is standard | Your judgment during the study, trained against rated film or a second observer |
| Basic time | The time the cycle would take at standard pace | Observed time x rating / 100 |
| Bundle allowance | Time to untie, move and re-tie a bundle, and to fill in the bundle ticket, shared over the pieces in it | Time the bundle handling and divide by pieces per bundle, or use a factory percentage |
| Personal and fatigue allowance | Time for drinking water, the toilet and recovery from tiring work. Also called relaxation allowance | A percentage of basic time, from the factory's allowance policy |
| Machine delay allowance | Time lost to thread breaks, bobbin changes and needle changes | A percentage applied to the sewing part of the cycle only. It differs by machine type |
| SMV | The standard time for one piece | Basic time + all allowances |
Basic time is the International Labour Organization's term. American textbooks call it normal time. They are the same thing.
Rating is the step people find hardest. You are judging pace, not skill and not effort, against the pace a trained operator could keep up all day without harm. A fast, smooth operator may be 110 or 120. A learner may be 70. If you time a slow operator and do not rate, the SMV comes out too long. If you time your fastest operator and do not rate, it comes out too short and the whole line is judged against a pace only one person can hold.
Why you rate: three operators, one basic time
Example numbersBasic time: 0.36 min
A learner, rated 80: observed 0.45 minutes, basic time 0.36. Standard pace, rated 100: observed 0.36 minutes, basic time 0.36. A fast operator, rated 120: observed 0.30 minutes, basic time 0.36
Allowances are a policy, so take them from a written table and apply them the same way to every operation. Machine delay allowance belongs only on the part of the cycle where the machine is sewing. Personal and fatigue allowance goes on everything. The percentages used on this page are examples, not a recommendation.
How to calculate the SMV of an operation, step by step
From watching an operation to its SMV
- 1
Fix the method first
- 2
Choose a trained operator and explain the study
- 3
Break the operation into elements
- 4
Time the cycles and rate the pace
- 5
Work out basic time
- 6
Add the allowances
- 7
Check it and publish it
- 1
Fix the method first
Agree how the operation should be done: machine, attachment, stitch type, how the parts are picked up and put down. An SMV belongs to one method. If the method is poor, improve it before you time it.
- 2
Choose a trained operator and explain the study
Pick someone who knows the operation and works at a steady pace. Tell them what you are doing and why. You are timing the operation, not judging the person.
- 3
Break the operation into elements
Usually three: pick up and position the parts, sew, and dispose of the piece. Split the sewing if there is more than one burst. Elements let you put machine allowance where it belongs.
- 4
Time the cycles and rate the pace
Record each element over at least 10 cycles. Leave out cycles with a thread break or a dropped piece and note them. Write a rating while you watch, not afterward.
- 5
Work out basic time
Average the observed times for each element and multiply by rating / 100.
- 6
Add the allowances
Add bundle handling per piece, the personal and fatigue allowance on all elements, and the machine delay allowance on the sewing elements.
- 7
Check it and publish it
Compare with the SMV of similar operations and with what good operators are making per hour. Put it on the operation bulletin with the method, the machine and the date.
Worked example: the SMV of one operation
Illustrative example. The operation is topstitching the neck seam of a basic T-shirt on a flatlock machine. The engineer times 10 cycles and rates the operator at 90, a little slower than standard pace.
| Element | Type | Observed time (min) | Rating | Basic time (min) |
|---|---|---|---|---|
| Pick up the body and position the neck under the foot | Manual | 0.12 | 90 | 0.108 |
| Topstitch around the neck | Machine | 0.20 | 90 | 0.180 |
| Trim the thread and put the piece aside | Manual | 0.08 | 90 | 0.072 |
| One cycle | 0.40 | 0.360 |
| Line | Sum | Minutes |
|---|---|---|
| Basic time for the cycle | 0.40 x 90 / 100 | 0.360 |
| Bundle handling | 36 seconds per bundle of 24 pieces = 1.5 s a piece | 0.025 |
| Personal and fatigue allowance | 12% of 0.385 (cycle + bundle handling) | 0.046 |
| Machine delay allowance | 10% of 0.180 (the sewing element) | 0.018 |
| SMV | 0.360 + 0.025 + 0.046 + 0.018 | 0.449, published as 0.45 |
At 0.45 SMV one operator at 100% makes 60 / 0.45 = 133 pieces an hour.
Notice what the rating did. The operator took 0.40 minutes, but the basic time is 0.36, because the engineer judged that a trained operator at standard pace would be a little faster. The allowances then add 0.089 minutes, about 25% on top of basic time. The SMV is not the time you saw. It is the time the job should take, hour after hour.
From operation SMV to garment SMV
The garment SMV is the sum of the SMVs of every operation on the operation bulletin, including manual work such as trimming and checking if those people are counted on the line. Here is the T-shirt.
| No. | Operation | Machine | SMV (min) | Target per hour at 100% |
|---|---|---|---|---|
| 1 | Join shoulders | Overlock | 0.40 | 150 |
| 2 | Attach neck rib | Overlock | 0.55 | 109 |
| 3 | Topstitch neck | Flatlock | 0.45 | 133 |
| 4 | Attach neck tape | Lockstitch | 0.50 | 120 |
| 5 | Attach label | Lockstitch | 0.30 | 200 |
| 6 | Attach sleeves | Overlock | 0.90 | 67 |
| 7 | Close side seams | Overlock | 0.95 | 63 |
| 8 | Hem sleeves | Flatlock | 0.70 | 86 |
| 9 | Hem bottom | Flatlock | 0.60 | 100 |
| 10 | Tack sleeve and neck ends | Lockstitch | 0.45 | 133 |
| 11 | Trim threads | Manual | 0.70 | 86 |
| 12 | Final check and fold | Manual | 1.00 | 60 |
| Garment SMV | 7.50 |
Target per hour at 100% = 60 / operation SMV, for one operator, rounded to a whole piece.
The T-shirt's 7.50 standard minutes, operation by operation
Example numbers- Machine operations 1 to 10: 5.80 min
- Manual operations 11 and 12: 1.70 min
Twelve operations add up to a garment SMV of 7.50 minutes: 1 Join shoulders 0.40, 2 Attach neck rib 0.55, 3 Topstitch neck 0.45, 4 Attach neck tape 0.50, 5 Attach label 0.30, 6 Attach sleeves 0.90, 7 Close side seams 0.95, 8 Hem sleeves 0.70, 9 Hem bottom 0.60, 10 Tack sleeve and neck ends 0.45, 11 Trim threads 0.70, 12 Final check and fold 1.00.
The garment SMV of 7.50 minutes says that one T-shirt holds seven and a half standard minutes of work. It does not say a shirt takes 7.5 minutes to come off the line. With 24 people working at once, the line finishes a shirt far more often than that.
Line target and line efficiency: the formulas
Three formulas turn the garment SMV into the numbers a supervisor uses every hour.
| What you want | Formula | On the T-shirt line |
|---|---|---|
| Minutes produced | Pieces made x garment SMV | 960 x 7.50 = 7,200 |
| Minutes attended | People on the line x minutes worked | 24 x 480 = 11,520 |
| Line efficiency | Minutes produced / minutes attended x 100 | 7,200 / 11,520 = 62.5% |
| Line target for the day | People x minutes worked x target efficiency / garment SMV | 24 x 480 x 0.65 / 7.50 = 998 |
| Line target per hour | People x 60 x target efficiency / garment SMV | 24 x 60 x 0.65 / 7.50 = 124 |
| Operator efficiency | Pieces made x operation SMV / minutes attended x 100 | 960 x 0.45 / 480 = 90% |
| On-standard efficiency | Minutes produced / (minutes attended minus off-standard minutes) x 100 | 7,200 / (11,520 minus 960) = 68.2% |
Count everyone whose work is in the garment SMV. If trimming and checking are in the SMV, the people doing them are in the head count. Include overtime minutes in minutes worked.
Illustrative example. The line has 24 people, 19 at machines and 5 on manual work, and works 480 minutes. It made 960 good T-shirts. It produced 7,200 standard minutes from 11,520 attended minutes, so it ran at 62.5%. The other 4,320 minutes went somewhere: waiting for cut panels, machine breakdowns, rework, learning a new style, a slow operation holding the others up.
Where the line's 11,520 minutes went
Example numbers- Minutes produced: 7,200
- Off-standard time, booked: 960
- Other lost minutes: 3,360
Line efficiency
62.5%
7,200 / 11,520
On-standard efficiency
68.2%
7,200 / 10,560
Of 11,520 attended minutes, 7,200 were produced as standard minutes, 960 were booked as off-standard time and 3,360 were lost in other ways. Line efficiency 62.5%, on-standard efficiency 68.2%.
Off-standard time is the part of that loss the operators could not help and that was recorded, such as a breakdown or no feeding. This line booked 960 minutes of it, so its on-standard efficiency is 68.2%. Use on-standard efficiency to judge how people performed while they could work, and overall line efficiency to judge how the factory performed. Both need honest booking.
The same number prices the garment. Labor cost per garment = garment SMV x cost per attended minute / line efficiency. At a cost of 0.05 per minute in any currency, this shirt costs 7.50 x 0.05 / 0.625 = 0.60 to sew at 62.5% efficiency and 0.50 at 75%. That is why buyers ask for your SMV and your efficiency in the same breath.
What the same 24 people make in a day at each efficiency
Example numbersAt 50% efficiency: 768 pieces. Today: 62.5%: 960 pieces. Target: 65%: 998 pieces. At 75%: 1,152 pieces. At 100%: every minute on standard: 1,536 pieces
How many operators each operation needs
Operations do not all take the same time, so they cannot each have one operator. Divide the garment SMV by the number of people to get the pitch time: the SMV one person carries if the work is shared perfectly. Here it is 7.50 / 24 = 0.3125 minutes. An operation needs its SMV divided by the pitch time.
| Operation | SMV (min) | Operators needed | Assigned | Capacity per hour at 100% |
|---|---|---|---|---|
| Join shoulders | 0.40 | 1.28 | 1 | 150 |
| Attach neck rib | 0.55 | 1.76 | 2 | 218 |
| Topstitch neck | 0.45 | 1.44 | 1 | 133 |
| Attach neck tape | 0.50 | 1.60 | 2 | 240 |
| Attach label | 0.30 | 0.96 | 1 | 200 |
| Attach sleeves | 0.90 | 2.88 | 3 | 200 |
| Close side seams | 0.95 | 3.04 | 3 | 189 |
| Hem sleeves | 0.70 | 2.24 | 2 | 171 |
| Hem bottom | 0.60 | 1.92 | 2 | 200 |
| Tack sleeve and neck ends | 0.45 | 1.44 | 2 | 267 |
| Trim threads | 0.70 | 2.24 | 2 | 171 |
| Final check and fold | 1.00 | 3.20 | 3 | 180 |
| Total | 7.50 | 24.00 | 24 |
Operators needed = operation SMV / pitch time of 0.3125 min. Capacity per hour = assigned operators x 60 / SMV, rounded to a whole piece.
How hard each operation has to work for 120 pieces an hour
Example numbersLine efficiency today: 62.5%
The number in brackets is the operators assigned.
Join shoulders: 1 operator, 80%. Attach neck rib: 2 operators, 55%. Topstitch neck: 1 operator, 90%. Attach neck tape: 2 operators, 50%. Attach label: 1 operator, 60%. Attach sleeves: 3 operators, 60%. Close side seams: 3 operators, 63%. Hem sleeves: 2 operators, 70%. Hem bottom: 2 operators, 60%. Tack sleeve and neck ends: 2 operators, 45%. Trim threads: 2 operators, 70%. Final check and fold: 3 operators, 67%
People come in whole numbers, so some operations get a little less than they need and some a little more. Topstitching the neck needs 1.44 operators and has one. That one person can make 133 an hour at 100%, the lowest capacity on the line, so this is the bottleneck. To reach the line's 120 an hour, that operator has to work at 120 / 133 = 90% efficiency. Put one of your best operators there, give the tacking operators the skill to step in, and you have balanced the line without adding anyone.
This is line balancing, and a yamazumi chart of each operator's load makes the picture clear. LeanSuite's Line Balancing builds that chart from a video of the line and lets you move work between operators to see the effect before anyone changes seats.
How SMV relates to time study and GSD
SMV is the result. Time study is one way to get it. There are three routes, and good factories use more than one.
| Route | How it works | Good for | Watch out for |
|---|---|---|---|
| Stopwatch or video time study | Time a real operator over several cycles, rate the pace, add allowances | Operations that are running, checking other SMVs, finding lost motion | Needs the operation to exist. Rating takes training. Results differ between observers |
| Predetermined times such as GSD | Describe the method as coded motions. Each code has a fixed time in TMU. Add them up and add allowances | Costing a style before it is in production, comparing methods, consistency between factories | Needs trained and licensed users. Only as good as the method description |
| Standard data from past styles | Reuse the SMV of the same operation from an earlier style, adjusted for seam length and fabric | Fast estimates for merchandisers | Carries old methods and old errors forward |
GSD stands for General Sewing Data, a predetermined motion time system for sewing based on MTM. One TMU (time measurement unit) is 0.0006 minutes.
A sensible routine is to quote from predetermined times or standard data, then confirm with a time study in the first days of production and correct the SMV if the method on the floor is different. The steps for the study itself are in the guides to time and motion study and standard time.
Video makes the study easier to trust. You can replay a cycle, agree the element breaks with the operator and the supervisor, and rate the pace together. LeanSuite's Time and Motion Study times each element from the video on a timeline, and the footage stays on file for the next time the SMV is questioned.
What SMV does not tell you, and the people side
- It is true for one method. Change the folder, the attachment, the fabric or the seam length and the SMV changes. An SMV without a method description is only a number.
- It assumes a trained operator. In the first days of a new style, people are learning and will not reach it. Plan a build-up over the first days and do not judge those days against the full target.
- It leaves out lost time. Waiting for cutting, breakdowns and rework are not in the SMV. They show up as low efficiency. Fixing them is management's work, not the operator's.
- It is a line average only on paper. The slowest operation sets the output, whatever the garment SMV says.
- It is not a quality measure. A line can hit 75% efficiency and send a tenth of its pieces for alteration. Count good pieces.
Operators often fear the stopwatch, and with reason. In many factories a study has meant a higher target the next day. Handle it openly. Explain before you start what the study is for. Show the operator the result and the allowances. Do not set the SMV from the fastest person on their best hour. Do not raise a target because people are meeting it. Raise it when the method or the machine has changed, and say so. An SMV that operators believe is fair is worth more than a tighter one they fight.
Where SMV is used for piece rates or production bonuses, wages are also governed by law and by any agreement with workers or their union. Minimum wage and overtime rules apply whatever the efficiency. This page is general guidance, not legal advice.
Common mistakes
- Using observed time as the SMV. No rating and no allowances means a target nobody can hold for a shift.
- Putting machine allowance on manual elements, or forgetting bundle handling altogether.
- Timing three cycles. A few cycles can be lucky or unlucky. Take at least 10, and more when the times vary a lot.
- Leaving helpers out of the head count while their work is in the SMV, which makes efficiency look better than it is.
- Comparing efficiency between factories that define SMV, SAM and allowances differently.
- Copying an SMV from another style without checking seam length, fabric and machine.
- Never updating it. Review the SMV when the method, machine, attachment or fabric changes.
Tools and templates
- Standard time calculator: observed time, rating and allowance in, standard time and pieces per hour out.
- Time study sheet: record elements and cycles for an operation.
- Time study sample size calculator: how many cycles to time for the accuracy you want.
- Line balancing calculator: station times and takt in, efficiency and idle time out.
- Yamazumi and operator balance chart template: each operator's load against the pitch time.
- Operator staffing calculator: work content and demand in, crew out.
Go deeper
This page is the short version. These guides cover each part in full.
- The Three Elements of Standard Work: Takt Time, Work Sequence, Standard WIPHow a time per operation becomes standard work an operator can follow.
- Yamazumi Chart: What It Is and How to Make One in 7 StepsDrawing each operator's load against the pitch time to see where the line is uneven.
- How to Improve Shop Floor ProductivityPractical ways to raise line efficiency once the lost minutes are visible.
- Standard Work Tools: Combination Sheet, Standardized Work Chart, Job BreakdownThe documents that record the method an SMV belongs to.
All our articles on this subject are in the standard work, sops and training topic.
Free templates and tools
- Time study sheetTime each element over 10 cycles and work out the average, lowest repeatable and standard time. Excel does the sums.
- Operator staffing calculatorTakt, work content, the operators a line needs, a check of your station plan and the roster with absence cover, from your own demand and element times.
- Standard time calculatorObserved times, a rating and an allowance in; normal time, standard time, units per hour, pieces per shift and labour cost per unit out, with the working.
- Time study sample size calculatorHow many cycles of an element to time, from your first readings, with the t formula, the ILO formula and the range method.
- Line balancing calculatorLine efficiency, balance delay and the minimum number of stations from station times and takt.
Doing this in LeanSuite
Time and Motion Study
Film the station and the AI times every element on a timeline that links to the video, split into value-added, necessary and waste.
See Time and Motion StudyLine Balancing
Drop in a video of your line and get a Yamazumi chart, a takt comparison and rebalancing recommendations.
See Line Balancing
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about sMV and SAM in garment manufacturing
SMV means standard minute value. It is the time in minutes that a trained operator, working at standard pace, needs to complete one operation on one garment, including allowances for personal needs, fatigue, machine delay and bundle handling. The SMVs of all operations added together give the garment SMV, which is used for targets, costing and efficiency.
In most garment factories there is none: standard minute value and standard allowed minute both mean the standard time for an operation or a garment. Some factories and trainers use SMV for the value before certain allowances and SAM for the value after them. There is no single agreed rule, so check the definition your factory and buyer use.
Time the operation over at least 10 cycles and average it to get observed time. Multiply by the operator's rating divided by 100 to get basic time. Then add allowances for bundle handling, personal needs and fatigue, and machine delay. For example, 0.40 minutes observed at a rating of 90 gives 0.36 basic minutes, and about 0.45 SMV after allowances.
Line efficiency = total minutes produced / total minutes attended x 100. Minutes produced are pieces made x garment SMV. Minutes attended are people on the line x minutes worked. A line of 24 people working 480 minutes that makes 960 pieces of a 7.50 SMV garment has an efficiency of 7,200 / 11,520 = 62.5%.
Daily line target = number of people x minutes worked x target efficiency / garment SMV. With 24 people, 480 minutes, a 65% target efficiency and a garment SMV of 7.50, the target is 24 x 480 x 0.65 / 7.50 = 998 pieces. For one operation, the hourly target at 100% is 60 / operation SMV.
Observed time is what the stopwatch showed for one cycle. Basic time is observed time adjusted to standard pace: observed time x rating / 100. SMV is basic time plus allowances for bundle handling, personal needs, fatigue and machine delay. Only the SMV is fit to use as a target, because it is the only one a trained operator can sustain for a whole shift.
GSD is General Sewing Data, a predetermined motion time system made for sewing and based on MTM. The engineer describes an operation as a series of coded motions, each with a fixed time in TMU, where one TMU is 0.0006 minutes. Adding the codes and the allowances gives an SMV without a stopwatch, which makes it useful for costing a style before production.
Related guides and tools
- Standard time: the same calculation outside the garment industry, with rating and allowances in depth
- Time and motion study: how to run the study behind an SMV
- Line balancing: sharing operations among operators so none holds the line up
- Yamazumi chart: each operator's load drawn against the pitch time
- How many operators a line needs: work content, takt, losses and the roster
- Labor efficiency and labor variance: earned minutes against attended minutes, in money
- Labor cost and quoting: from standard minutes to a price
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk
Or browse the topics, the full library and the lean glossary.
Rather see it on your own problem?
Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.