SMV and SAM in garment manufacturing: what they mean and how to calculate them

Short answer

SMV, the standard minute value, is the time in minutes a trained operator needs to do one operation at standard pace, with allowances included. SAM, the standard allowed minute, means the same in most factories. SMV = basic time + allowances.

To calculate SMV, time the operation over several cycles and average it: that is observed time. Multiply by the operator's rating to get basic time, then add allowances for bundle handling, personal needs and fatigue, and machine delay. An operation observed at 0.40 minutes and rated at 90 has a basic time of 0.36 minutes, and with allowances its SMV comes to 0.45. Add the SMVs of all operations to get the garment SMV. Then line efficiency = pieces made x garment SMV / (people x minutes worked). A line of 24 people that makes 960 T-shirts of 7.50 SMV in 480 minutes runs at 7,200 / 11,520 = 62.5%.

Last reviewed:

What SMV and SAM mean

How 0.40 observed minutes become an SMV of 0.45

Example numbers

What the stopwatch showed: 0.40 min, operator rated at 90

0.40 min observed

The SMV: 0.449 min, published as 0.45

Basic time 0.360
Allowances 0.089
0.108
0.180
0.072
  • Pick up and position (manual): 0.108
  • Topstitch (machine): 0.180
  • Trim and put aside (manual): 0.072
  • Bundle handling: 0.025
  • Personal and fatigue, 12%: 0.046
  • Machine delay, 10% of sewing: 0.018

Observed time 0.40 minutes. Basic time at a rating of 90 is 0.360. Bundle handling adds 0.025, personal and fatigue allowance 0.046 and machine delay allowance 0.018, giving an SMV of 0.449 minutes.

Rating shrinks the time you saw to the time at standard pace. Allowances then add back what a person and a machine need over a full day. Both bars are on the same scale.

SMV stands for standard minute value. It is the time, in minutes, that a trained operator working at a standard pace needs to complete one operation on one garment, with allowances included for rest, small machine delays and handling. An SMV of 0.45 means one piece should take 0.45 minutes, which is 27 seconds.

SAM stands for standard allowed minute. In most factories, and in most buyers' costing sheets, SAM and SMV are two names for the same number. You will meet people who draw a line between them: some call the value before certain allowances the SMV and the value after them the SAM, and some use SAM for a figure with a factory policy allowance added. There is no single agreed rule. Ask how your factory and your buyer define each one, and write the definition on the operation bulletin.

Garment factories run on this number. Add the SMVs of every operation and you have the garment SMV: the standard labor content of the style. From it come the line target, the number of operators and machines, the line efficiency, the labor cost quoted to the buyer and, in many factories, the incentive. Outside the garment industry the same thing is called standard time.

How an SMV is built: basic time and allowances

An SMV has two layers. The first is the work itself at a standard pace. The second is time that a person and a machine need over a day but that does not show in any single cycle.

The parts of an SMV
PartWhat it isHow you get it
Observed timeThe average time the operator took for one cycle while you watchedTime 10 or more good cycles and average them
RatingHow the operator's pace compares with standard pace. 100 is standardYour judgment during the study, trained against rated film or a second observer
Basic timeThe time the cycle would take at standard paceObserved time x rating / 100
Bundle allowanceTime to untie, move and re-tie a bundle, and to fill in the bundle ticket, shared over the pieces in itTime the bundle handling and divide by pieces per bundle, or use a factory percentage
Personal and fatigue allowanceTime for drinking water, the toilet and recovery from tiring work. Also called relaxation allowanceA percentage of basic time, from the factory's allowance policy
Machine delay allowanceTime lost to thread breaks, bobbin changes and needle changesA percentage applied to the sewing part of the cycle only. It differs by machine type
SMVThe standard time for one pieceBasic time + all allowances

Basic time is the International Labour Organization's term. American textbooks call it normal time. They are the same thing.

Rating is the step people find hardest. You are judging pace, not skill and not effort, against the pace a trained operator could keep up all day without harm. A fast, smooth operator may be 110 or 120. A learner may be 70. If you time a slow operator and do not rate, the SMV comes out too long. If you time your fastest operator and do not rate, it comes out too short and the whole line is judged against a pace only one person can hold.

Why you rate: three operators, one basic time

Example numbers
A learner, rated 800.45 x 80 / 100 = 0.36 min
Standard pace, rated 1000.36 x 100 / 100 = 0.36 min
A fast operator, rated 1200.30 x 120 / 100 = 0.36 min

Basic time: 0.36 min

A learner, rated 80: observed 0.45 minutes, basic time 0.36. Standard pace, rated 100: observed 0.36 minutes, basic time 0.36. A fast operator, rated 120: observed 0.30 minutes, basic time 0.36

The bars are what the stopwatch showed for the same operation. After rating, all three give a basic time of 0.36 minutes. Skip the rating and the SMV depends on who happened to be sitting at the machine.

Allowances are a policy, so take them from a written table and apply them the same way to every operation. Machine delay allowance belongs only on the part of the cycle where the machine is sewing. Personal and fatigue allowance goes on everything. The percentages used on this page are examples, not a recommendation.

How to calculate the SMV of an operation, step by step

From watching an operation to its SMV

  1. 1

    Fix the method first

  2. 2

    Choose a trained operator and explain the study

  3. 3

    Break the operation into elements

  4. 4

    Time the cycles and rate the pace

  5. 5

    Work out basic time

  6. 6

    Add the allowances

  7. 7

    Check it and publish it

Fix the method before you time it. The arithmetic in steps 5 and 6 takes minutes. Steps 1 to 4 decide whether the answer is worth anything.
  1. 1

    Fix the method first

    Agree how the operation should be done: machine, attachment, stitch type, how the parts are picked up and put down. An SMV belongs to one method. If the method is poor, improve it before you time it.

  2. 2

    Choose a trained operator and explain the study

    Pick someone who knows the operation and works at a steady pace. Tell them what you are doing and why. You are timing the operation, not judging the person.

  3. 3

    Break the operation into elements

    Usually three: pick up and position the parts, sew, and dispose of the piece. Split the sewing if there is more than one burst. Elements let you put machine allowance where it belongs.

  4. 4

    Time the cycles and rate the pace

    Record each element over at least 10 cycles. Leave out cycles with a thread break or a dropped piece and note them. Write a rating while you watch, not afterward.

  5. 5

    Work out basic time

    Average the observed times for each element and multiply by rating / 100.

  6. 6

    Add the allowances

    Add bundle handling per piece, the personal and fatigue allowance on all elements, and the machine delay allowance on the sewing elements.

  7. 7

    Check it and publish it

    Compare with the SMV of similar operations and with what good operators are making per hour. Put it on the operation bulletin with the method, the machine and the date.

Worked example: the SMV of one operation

Illustrative example. The operation is topstitching the neck seam of a basic T-shirt on a flatlock machine. The engineer times 10 cycles and rates the operator at 90, a little slower than standard pace.

Illustrative: observed and basic time for topstitching the neck, by element
ElementTypeObserved time (min)RatingBasic time (min)
Pick up the body and position the neck under the footManual0.12900.108
Topstitch around the neckMachine0.20900.180
Trim the thread and put the piece asideManual0.08900.072
One cycle0.400.360
Illustrative: from basic time to SMV for topstitching the neck
LineSumMinutes
Basic time for the cycle0.40 x 90 / 1000.360
Bundle handling36 seconds per bundle of 24 pieces = 1.5 s a piece0.025
Personal and fatigue allowance12% of 0.385 (cycle + bundle handling)0.046
Machine delay allowance10% of 0.180 (the sewing element)0.018
SMV0.360 + 0.025 + 0.046 + 0.0180.449, published as 0.45

At 0.45 SMV one operator at 100% makes 60 / 0.45 = 133 pieces an hour.

Notice what the rating did. The operator took 0.40 minutes, but the basic time is 0.36, because the engineer judged that a trained operator at standard pace would be a little faster. The allowances then add 0.089 minutes, about 25% on top of basic time. The SMV is not the time you saw. It is the time the job should take, hour after hour.

From operation SMV to garment SMV

The garment SMV is the sum of the SMVs of every operation on the operation bulletin, including manual work such as trimming and checking if those people are counted on the line. Here is the T-shirt.

Illustrative: operation bulletin for a basic crew neck T-shirt
No.OperationMachineSMV (min)Target per hour at 100%
1Join shouldersOverlock0.40150
2Attach neck ribOverlock0.55109
3Topstitch neckFlatlock0.45133
4Attach neck tapeLockstitch0.50120
5Attach labelLockstitch0.30200
6Attach sleevesOverlock0.9067
7Close side seamsOverlock0.9563
8Hem sleevesFlatlock0.7086
9Hem bottomFlatlock0.60100
10Tack sleeve and neck endsLockstitch0.45133
11Trim threadsManual0.7086
12Final check and foldManual1.0060
Garment SMV7.50

Target per hour at 100% = 60 / operation SMV, for one operator, rounded to a whole piece.

The T-shirt's 7.50 standard minutes, operation by operation

Example numbers
1
2
3
4
5
6
7
8
9
10
11
12
0 minGarment SMV 7.50 min
  • Machine operations 1 to 10: 5.80 min
  • Manual operations 11 and 12: 1.70 min

Twelve operations add up to a garment SMV of 7.50 minutes: 1 Join shoulders 0.40, 2 Attach neck rib 0.55, 3 Topstitch neck 0.45, 4 Attach neck tape 0.50, 5 Attach label 0.30, 6 Attach sleeves 0.90, 7 Close side seams 0.95, 8 Hem sleeves 0.70, 9 Hem bottom 0.60, 10 Tack sleeve and neck ends 0.45, 11 Trim threads 0.70, 12 Final check and fold 1.00.

Each block is one operation, numbered as in the table and drawn to scale. Sleeves, side seams and the final check take 2.85 of the 7.50 minutes, so they need the most people.

The garment SMV of 7.50 minutes says that one T-shirt holds seven and a half standard minutes of work. It does not say a shirt takes 7.5 minutes to come off the line. With 24 people working at once, the line finishes a shirt far more often than that.

Line target and line efficiency: the formulas

Three formulas turn the garment SMV into the numbers a supervisor uses every hour.

Sewing line formulas (example values are illustrative)
What you wantFormulaOn the T-shirt line
Minutes producedPieces made x garment SMV960 x 7.50 = 7,200
Minutes attendedPeople on the line x minutes worked24 x 480 = 11,520
Line efficiencyMinutes produced / minutes attended x 1007,200 / 11,520 = 62.5%
Line target for the dayPeople x minutes worked x target efficiency / garment SMV24 x 480 x 0.65 / 7.50 = 998
Line target per hourPeople x 60 x target efficiency / garment SMV24 x 60 x 0.65 / 7.50 = 124
Operator efficiencyPieces made x operation SMV / minutes attended x 100960 x 0.45 / 480 = 90%
On-standard efficiencyMinutes produced / (minutes attended minus off-standard minutes) x 1007,200 / (11,520 minus 960) = 68.2%

Count everyone whose work is in the garment SMV. If trimming and checking are in the SMV, the people doing them are in the head count. Include overtime minutes in minutes worked.

Illustrative example. The line has 24 people, 19 at machines and 5 on manual work, and works 480 minutes. It made 960 good T-shirts. It produced 7,200 standard minutes from 11,520 attended minutes, so it ran at 62.5%. The other 4,320 minutes went somewhere: waiting for cut panels, machine breakdowns, rework, learning a new style, a slow operation holding the others up.

Where the line's 11,520 minutes went

Example numbers
Produced: 960 x 7.50 = 7,200
Lost: 4,320
7,200
960
3,360
  • Minutes produced: 7,200
  • Off-standard time, booked: 960
  • Other lost minutes: 3,360

Line efficiency

62.5%

7,200 / 11,520

On-standard efficiency

68.2%

7,200 / 10,560

Of 11,520 attended minutes, 7,200 were produced as standard minutes, 960 were booked as off-standard time and 3,360 were lost in other ways. Line efficiency 62.5%, on-standard efficiency 68.2%.

Minutes produced are pieces x garment SMV. Everything to the right of the ink block is paid time that made no garment. Line efficiency counts all of it. On-standard efficiency leaves out the booked lost time.

Off-standard time is the part of that loss the operators could not help and that was recorded, such as a breakdown or no feeding. This line booked 960 minutes of it, so its on-standard efficiency is 68.2%. Use on-standard efficiency to judge how people performed while they could work, and overall line efficiency to judge how the factory performed. Both need honest booking.

The same number prices the garment. Labor cost per garment = garment SMV x cost per attended minute / line efficiency. At a cost of 0.05 per minute in any currency, this shirt costs 7.50 x 0.05 / 0.625 = 0.60 to sew at 62.5% efficiency and 0.50 at 75%. That is why buyers ask for your SMV and your efficiency in the same breath.

What the same 24 people make in a day at each efficiency

Example numbers
At 50% efficiency768 pieces
Today: 62.5%960 pieces
Target: 65%998 pieces
At 75%1,152 pieces
At 100%: every minute on standard1,536 pieces

At 50% efficiency: 768 pieces. Today: 62.5%: 960 pieces. Target: 65%: 998 pieces. At 75%: 1,152 pieces. At 100%: every minute on standard: 1,536 pieces

Target = people x minutes x efficiency / garment SMV. Every point of efficiency on this line is about 15 T-shirts a day, with the same people and the same hours.

How many operators each operation needs

Operations do not all take the same time, so they cannot each have one operator. Divide the garment SMV by the number of people to get the pitch time: the SMV one person carries if the work is shared perfectly. Here it is 7.50 / 24 = 0.3125 minutes. An operation needs its SMV divided by the pitch time.

Illustrative: operators needed and assigned on the T-shirt line
OperationSMV (min)Operators neededAssignedCapacity per hour at 100%
Join shoulders0.401.281150
Attach neck rib0.551.762218
Topstitch neck0.451.441133
Attach neck tape0.501.602240
Attach label0.300.961200
Attach sleeves0.902.883200
Close side seams0.953.043189
Hem sleeves0.702.242171
Hem bottom0.601.922200
Tack sleeve and neck ends0.451.442267
Trim threads0.702.242171
Final check and fold1.003.203180
Total7.5024.0024

Operators needed = operation SMV / pitch time of 0.3125 min. Capacity per hour = assigned operators x 60 / SMV, rounded to a whole piece.

How hard each operation has to work for 120 pieces an hour

Example numbers
Join shoulders (1)80%
Attach neck rib (2)55%
Topstitch neck (1)90%
Attach neck tape (2)50%
Attach label (1)60%
Attach sleeves (3)60%
Close side seams (3)63%
Hem sleeves (2)70%
Hem bottom (2)60%
Tack sleeve and neck ends (2)45%
Trim threads (2)70%
Final check and fold (3)67%

Line efficiency today: 62.5%

The number in brackets is the operators assigned.

Join shoulders: 1 operator, 80%. Attach neck rib: 2 operators, 55%. Topstitch neck: 1 operator, 90%. Attach neck tape: 2 operators, 50%. Attach label: 1 operator, 60%. Attach sleeves: 3 operators, 60%. Close side seams: 3 operators, 63%. Hem sleeves: 2 operators, 70%. Hem bottom: 2 operators, 60%. Tack sleeve and neck ends: 2 operators, 45%. Trim threads: 2 operators, 70%. Final check and fold: 3 operators, 67%

Efficiency needed = 120 x operation SMV / (operators x 60). Topstitching the neck, with one operator, needs 90%: it is the bottleneck. Tacking needs 45%, so that is where the spare skill is.

People come in whole numbers, so some operations get a little less than they need and some a little more. Topstitching the neck needs 1.44 operators and has one. That one person can make 133 an hour at 100%, the lowest capacity on the line, so this is the bottleneck. To reach the line's 120 an hour, that operator has to work at 120 / 133 = 90% efficiency. Put one of your best operators there, give the tacking operators the skill to step in, and you have balanced the line without adding anyone.

This is line balancing, and a yamazumi chart of each operator's load makes the picture clear. LeanSuite's Line Balancing builds that chart from a video of the line and lets you move work between operators to see the effect before anyone changes seats.

How SMV relates to time study and GSD

SMV is the result. Time study is one way to get it. There are three routes, and good factories use more than one.

Three ways to set an SMV
RouteHow it worksGood forWatch out for
Stopwatch or video time studyTime a real operator over several cycles, rate the pace, add allowancesOperations that are running, checking other SMVs, finding lost motionNeeds the operation to exist. Rating takes training. Results differ between observers
Predetermined times such as GSDDescribe the method as coded motions. Each code has a fixed time in TMU. Add them up and add allowancesCosting a style before it is in production, comparing methods, consistency between factoriesNeeds trained and licensed users. Only as good as the method description
Standard data from past stylesReuse the SMV of the same operation from an earlier style, adjusted for seam length and fabricFast estimates for merchandisersCarries old methods and old errors forward

GSD stands for General Sewing Data, a predetermined motion time system for sewing based on MTM. One TMU (time measurement unit) is 0.0006 minutes.

A sensible routine is to quote from predetermined times or standard data, then confirm with a time study in the first days of production and correct the SMV if the method on the floor is different. The steps for the study itself are in the guides to time and motion study and standard time.

Video makes the study easier to trust. You can replay a cycle, agree the element breaks with the operator and the supervisor, and rate the pace together. LeanSuite's Time and Motion Study times each element from the video on a timeline, and the footage stays on file for the next time the SMV is questioned.

What SMV does not tell you, and the people side

  • It is true for one method. Change the folder, the attachment, the fabric or the seam length and the SMV changes. An SMV without a method description is only a number.
  • It assumes a trained operator. In the first days of a new style, people are learning and will not reach it. Plan a build-up over the first days and do not judge those days against the full target.
  • It leaves out lost time. Waiting for cutting, breakdowns and rework are not in the SMV. They show up as low efficiency. Fixing them is management's work, not the operator's.
  • It is a line average only on paper. The slowest operation sets the output, whatever the garment SMV says.
  • It is not a quality measure. A line can hit 75% efficiency and send a tenth of its pieces for alteration. Count good pieces.

Operators often fear the stopwatch, and with reason. In many factories a study has meant a higher target the next day. Handle it openly. Explain before you start what the study is for. Show the operator the result and the allowances. Do not set the SMV from the fastest person on their best hour. Do not raise a target because people are meeting it. Raise it when the method or the machine has changed, and say so. An SMV that operators believe is fair is worth more than a tighter one they fight.

Where SMV is used for piece rates or production bonuses, wages are also governed by law and by any agreement with workers or their union. Minimum wage and overtime rules apply whatever the efficiency. This page is general guidance, not legal advice.

Common mistakes

  • Using observed time as the SMV. No rating and no allowances means a target nobody can hold for a shift.
  • Putting machine allowance on manual elements, or forgetting bundle handling altogether.
  • Timing three cycles. A few cycles can be lucky or unlucky. Take at least 10, and more when the times vary a lot.
  • Leaving helpers out of the head count while their work is in the SMV, which makes efficiency look better than it is.
  • Comparing efficiency between factories that define SMV, SAM and allowances differently.
  • Copying an SMV from another style without checking seam length, fabric and machine.
  • Never updating it. Review the SMV when the method, machine, attachment or fabric changes.

Tools and templates

FAQ

Questions about sMV and SAM in garment manufacturing

  1. SMV means standard minute value. It is the time in minutes that a trained operator, working at standard pace, needs to complete one operation on one garment, including allowances for personal needs, fatigue, machine delay and bundle handling. The SMVs of all operations added together give the garment SMV, which is used for targets, costing and efficiency.

  2. In most garment factories there is none: standard minute value and standard allowed minute both mean the standard time for an operation or a garment. Some factories and trainers use SMV for the value before certain allowances and SAM for the value after them. There is no single agreed rule, so check the definition your factory and buyer use.

  3. Time the operation over at least 10 cycles and average it to get observed time. Multiply by the operator's rating divided by 100 to get basic time. Then add allowances for bundle handling, personal needs and fatigue, and machine delay. For example, 0.40 minutes observed at a rating of 90 gives 0.36 basic minutes, and about 0.45 SMV after allowances.

  4. Line efficiency = total minutes produced / total minutes attended x 100. Minutes produced are pieces made x garment SMV. Minutes attended are people on the line x minutes worked. A line of 24 people working 480 minutes that makes 960 pieces of a 7.50 SMV garment has an efficiency of 7,200 / 11,520 = 62.5%.

  5. Daily line target = number of people x minutes worked x target efficiency / garment SMV. With 24 people, 480 minutes, a 65% target efficiency and a garment SMV of 7.50, the target is 24 x 480 x 0.65 / 7.50 = 998 pieces. For one operation, the hourly target at 100% is 60 / operation SMV.

  6. Observed time is what the stopwatch showed for one cycle. Basic time is observed time adjusted to standard pace: observed time x rating / 100. SMV is basic time plus allowances for bundle handling, personal needs, fatigue and machine delay. Only the SMV is fit to use as a target, because it is the only one a trained operator can sustain for a whole shift.

  7. GSD is General Sewing Data, a predetermined motion time system made for sewing and based on MTM. The engineer describes an operation as a series of coded motions, each with a fixed time in TMU, where one TMU is 0.0006 minutes. Adding the codes and the allowances gives an SMV without a stopwatch, which makes it useful for costing a style before production.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.