Timing long-cycle, non-repetitive and team work

Short answer

For long-cycle, non-repetitive or crew work, stop timing whole cycles. Break the job into a few large elements, chart who does what when, and build standards from a library of element times. Use sampling or video where nobody can watch the whole job.

A stopwatch study assumes a short cycle that repeats. Maintenance, setups, kitting and team assembly break that assumption: cycles run 20 minutes to several hours, no two are the same, and several people share the work. Use four tools instead. Time the few cycles you can get with coarse elements of a minute or more. Draw a crew chart to see who waits for whom. Sample the crew at fixed intervals to split working from waiting. And build a library of element times, such as minutes per pick or per bolt, so a standard for the next job is a sum, not a new study.

Last reviewed:

Why long-cycle and team work need a different approach

Four tools, four questions

  1. How long does one repeatable job take?

    Time a few cycles

    Coarse elements of a minute or more, read off a running clock.

  2. Who waits for whom?

    A crew chart

    One bar per person on a common time scale, working or waiting.

  3. How much of the crew's time is work?

    Group timing

    Look at each person at a fixed short interval and tally.

  4. What will the next, different job take?

    An element library

    Minutes per pick or per bolt, so a standard is a sum, not a study.

For long-cycle and crew work, time a few cycles with coarse elements to find how long a repeatable job takes, draw a crew chart to see who waits for whom, use group timing to find how much of the crew's time is work, and build an element library so the next different job is a sum.

Use them together: the crew chart and video fix the method, then the library means the next job needs no new study.

A classic time study watches one person repeat a short cycle 20 or 30 times in an hour. Average the cycles, rate the pace, add allowances, and you have a standard. That works at an assembly station. It falls apart on a preventive maintenance job, a die change, a kitting round or a four-person final assembly.

  • You cannot get enough cycles. A 40 minute job done twice a shift gives ten cycles a week. A statistical sample would take a month.
  • No two cycles match. The seized bolt, the missing part and the different product make each run its own job.
  • The work is shared. With three people on a job, the elapsed time says little about the work content, and somebody is always waiting.
  • People move. A maintenance technician covers half the plant. One observer cannot follow, and a fixed camera loses them.
  • Pace is hard to rate. Rating assumes a steady rhythm. Diagnosing a fault has none.

None of this means the work cannot be measured. It means the unit of measurement changes: from the cycle to the element, and from one study to a library you add to over time. The standards will be coarser than at an assembly station. They are still far better than the guess they replace.

Which approach for which job

Approaches for long-cycle, non-repetitive and crew work
ApproachHow it worksBest forWhat you get
Direct time study with coarse elementsTime a few whole cycles, with elements of a minute or moreLong jobs that repeat the same way: a standard setup, a test sequence, a large assemblyElement times and a standard for that job
Crew chart (gang process chart)Chart each person's activity on one time scaleAny job done by two or more peopleWho waits for whom, the right crew size, a better sequence
Group timing techniqueNote what each crew member is doing at a fixed short intervalCrews on jobs of 30 minutes to a shiftWorking and waiting shares per person, and work content
Work samplingRandom observations over days or weeksRoving and irregular work: maintenance, material handling, team leadersWhere the hours go across a whole department
Time lapse videoFilm the whole job, review at speed, time the elements from the clipLong jobs in one area: changeovers, cell setups, line clearanceA record of the job you can replay, with times
Element library and slottingAdd up standard times for the elements a job contains, or slot it against benchmark jobsWork that never repeats but is built from repeating pieces: picks, bolts, liftsA standard for a job nobody has timed
Predetermined times for long cyclesA motion-based system built for long work, such as MaxiMOSTPlants that already use a predetermined time systemA standard from the method description

Most real programmes mix them: a crew chart and video to fix the method, then a library so the next job needs no study.

The time and motion study guide sets these against the stopwatch study, and work sampling has the full method for random observations.

Timing a long cycle directly

If the job repeats the same way each time, time it. The method is the ordinary one with three adjustments.

  • Use bigger elements. On a 40 minute job, elements of one to five minutes are fine. Ten to fifteen elements is plenty. Break at natural handovers: guards off, old part out, new part in, tested.
  • Use the continuous method. Let the clock run and read it at each break point. On a long job, snapping back loses time and loses interruptions.
  • Log every interruption with its cause. On long work the foreign elements are often the finding: the walk to the crib, the wait for a forklift, the missing gasket.

How many cycles? A long cycle averages out its own small variations, so fewer are needed. A guide table from General Electric, reproduced in Niebel and Freivalds, is the usual starting point.

Cycles to observe by cycle time: the General Electric guide table as given in Niebel and Freivalds
Cycle time, minutesCycles to observe
Up to 0.10200
Up to 0.25100
Up to 0.5060
Up to 0.7540
Up to 1.0030
Up to 2.0020
Up to 5.0015
Up to 10.0010
Up to 20.008
Up to 40.005
Over 40.003

A company's rule of thumb, not a law. If your three cycles differ widely, three is not enough: find out why they differ before averaging them.

The longer the cycle, the fewer cycles to observe

  • Up to 0.10 min
    200
  • Up to 0.25 min
    100
  • Up to 0.50 min
    60
  • Up to 0.75 min
    40
  • Up to 1.00 min
    30
  • Up to 2.00 min
    20
  • Up to 5.00 min
    15
  • Up to 10.00 min
    10
  • Up to 20.00 min
    8
  • Up to 40.00 min
    5
  • Over 40.00 min
    3
  • Cycle time, then cycles to observe.

The General Electric guide table as given in Niebel and Freivalds. A cycle up to 0.10 minute needs 200 cycles. Up to 1.00 minute needs 30. Up to 10 minutes needs 10. Over 40 minutes needs 3.

A rule of thumb from one company, not a law. A long cycle averages out its own small variations, so fewer are needed. If your three cycles differ widely, find out why before averaging.

Three cycles of a 45 minute job is more than two hours of watching, and it is worth it once. But be honest about what three readings can carry. Report the range along with the average, and treat the result as a first standard to be confirmed as more runs are logged.

Team work: the crew chart

With a crew, the question changes from how long does it take to who is doing what while the clock runs. The tool is the crew chart, which Barnes calls the gang process chart: one bar per person on a common time scale, shaded for working and blank for waiting. It is a multiple activity chart with people in every column.

Two numbers come out of it. Elapsed time is how long the job takes on the clock. Work content is the sum of everyone's working time, in person-minutes. A crew of three on a 42 minute job spends 126 person-minutes. How many of them are work is what the chart shows.

A worked crew chart

Illustrative example. A planned job on a packaging machine: change the dust filter and the drive belt. Two technicians and the line operator do it in 42 minutes. An engineer films the job and charts it.

Illustrative: the filter and belt change as done today, three people, 42 minutes
MinutesTechnician ATechnician BOperator C
0 to 4Lock out the machineWaits for the lockoutFetches the parts cart
4 to 10Removes guardsWaits: no room at the guardsHelps remove guards
10 to 16Replaces the filterReplaces the drive beltCleans the filter housing
16 to 22Replaces the filterReplaces the drive beltWaits
22 to 30Waits for the belt to be finishedReplaces the drive beltWaits
30 to 36Refits guardsHelps refit guardsWaits
36 to 42Removes locks and test runsWaitsChecks the test run
Working, minutes342622
Waiting, minutes81620

Work content = 34 + 26 + 22 = 82 person-minutes. Paid time = 3 x 42 = 126 person-minutes. Waiting = 44 person-minutes, or 35 percent.

More than a third of the paid time is waiting, and nobody on the crew is slow. The job is sequenced so that people queue for the same space. The fix is on paper before it is on the floor: stage the parts cart at the machine before the stop, and let Technician A do the cleaning in the gap after the filter.

Illustrative: the same job re-sequenced for two people, 42 minutes
MinutesTechnician ATechnician B
0 to 4Lock out the machinePositions the staged parts cart and tools
4 to 10Removes guardsRemoves guards
10 to 22Replaces the filterReplaces the drive belt
22 to 28Cleans the filter housingReplaces the drive belt
28 to 30WaitsReplaces the drive belt
30 to 36Refits guardsRefits guards
36 to 42Removes locks and test runsChecks the test run
Working, minutes4042
Waiting, minutes20

Work content is still 82 person-minutes. Paid time falls from 126 to 84 person-minutes, and the operator stays on other work. The stop is no longer, because the belt was always the longest task.

Filter and belt change: the crew chart, before and after

Example numbers
  • Working
  • Waiting

Today: three people, 42 minutes

126 paid person-minutes, 82 work, 44 waiting (35%).

Technician A: working 34, waiting 8 min

Technician B: working 26, waiting 16 min

Operator C: working 22, waiting 20 min

Re-sequenced: two people, 42 minutes

84 paid person-minutes, 82 work, 2 waiting. The operator stays on other work.

Technician A: working 40, waiting 2 min

Technician B: working 42, waiting 0 min

Minutes from the start of the job. Labelled bars are the filter and the drive belt.

Before: three people take 42 minutes, which is 126 paid person-minutes, of which 82 are work and 44 are waiting, 35 percent. After re-sequencing: two technicians take the same 42 minutes, 84 paid person-minutes, of which 82 are work and 2 are waiting. The belt change takes 20 minutes and only one person can reach it, so it sets the length of the job.

Work content is 82 person-minutes both times. Paid time falls from 126 to 84 because nobody queues for the same space. The belt, 20 minutes for one person, is the critical path.

The chart also shows the limit. The belt change takes 20 minutes and only one person can reach it. Until that task is shortened or split, a third person adds cost and no speed. That is the critical path, and it is where the next improvement has to come from.

Group timing and work sampling for crews

Charting every minute of every person is practical for three people for 40 minutes. For six people over a shift it is not. The group timing technique is the shortcut. At a fixed short interval, say every minute or every two, the observer looks at each crew member in turn and tallies one thing: working or waiting, or a short list of activities. Maynard's handbook describes it as work sampling at a fixed short interval.

The share of tallies is the share of time. Working time = share working x total paid time. Run it on the example job with a look every two minutes, at minutes 1, 3, 5 and so on to 41: 21 rounds of three people, 63 observations.

Illustrative: group timing of the three-person job, one look every two minutes
PersonObservationsWorkingWaitingShare working
Technician A2117481%
Technician B2113862%
Operator C21111052%
Crew63412265%

Estimated work content = 41 / 63 x 126 = 82 person-minutes, the same as the full chart. The match is exact here only because the example's tasks start and end on even minutes. On a real job expect a few points of error.

Group timing: one look every two minutes

Example numbers
  • Looked: working
  • Looked: waiting
  • Technician A, 17 working, 4 waiting: 81%

  • Technician B, 13 working, 8 waiting: 62%

  • Operator C, 11 working, 10 waiting: 52%

41 of 63 looks working = 65%. Work content = 41 / 63 x 126 = 82 person-minutes.

The observer looks at each of the three people at minutes 1, 3, 5 and so on to 41, which is 21 looks each and 63 in all. Technician A is working in 17 looks, Technician B in 13 and Operator C in 11. That is 41 of 63 looks working, 65 percent, and 41 / 63 x 126 = 82 person-minutes of work.

The share of looks is the share of time. Here the sample matches the full chart exactly because the tasks start and end on even minutes. On a real job expect a few points of error.
  • Keep the interval short against the tasks. A look every two minutes cannot see a 30 second task.
  • A fixed interval is safe on a one-off job. On work with its own rhythm it can lock onto the rhythm, and random times are safer. Work sampling explains why.
  • Add a reason code for waiting: for a person, for a part, for a tool, for access. The reasons are the action list.
  • Group timing gives shares, not the sequence. Use it to size the waste, and the crew chart or video to see how to remove it.

For work that roams, such as a maintenance department over a month, use full work sampling with random rounds. It will not give a standard for one job. It will tell you how much of the department's time is wrench time, travel, waiting for parts and paperwork, which is usually the more valuable answer.

Using video on long jobs

Video suits long work for a simple reason: nobody can watch three people closely for 40 minutes, and a camera can. Film once, then watch each person in turn.

  • Film wide and fixed, so that everyone on the job stays in the frame. A changeover or a machine PM usually fits in one view. Add a second camera for the far side.
  • For jobs of an hour or more, time lapse or a low frame rate keeps the file small. Mundel's memomotion study used 60 or 100 frames a minute for exactly this: long cycles and crews.
  • Review at four or eight times speed to map the job, then at normal speed for the parts that matter.
  • Draw the crew chart from the clip. The timecode gives each start and end.
  • Show the crew the footage first. They will see the waiting faster than you do, and they know why it happens.

Time study from video covers camera position, consent and logging. For changeovers, the same footage feeds a SMED study. LeanSuite's time and motion study accepts single uploads of up to four hours and times each person's elements on a timeline linked to the video, which removes most of the charting by hand.

Element libraries: standards without a new study

Long jobs rarely repeat. Their pieces do. Every kit is different, but each one is some number of picks. Every PM is different, but each one is some number of guards, bolts and filters. Time the pieces once, keep them in a library, and a standard for a new job becomes a sum.

Textbooks call the library standard data. Each entry is a normal time for one element, tied to a count you can read off the work order: per kit, per line, per location, per bolt. Job time = the sum of element time x count. Then add allowances.

Illustrative example. A kitting area builds kits for an assembly line. Studies of the kitters over several weeks give five library elements. A new kit has 24 lines picked from 18 locations.

Illustrative: a kit standard built from a five-element library
Library elementNormal minutesPerCount for this kitMinutes
Travel to the kitting aisle and back with the cart1.20kit11.20
Move between pick locations0.15location182.70
Pick a line: locate, pick and count0.22line245.28
Scan and confirm0.08line241.92
Label and close the kit0.60kit10.60
Normal time11.70
Standard time with a 15 percent allowance11.70 x 1.1513.46

A smaller kit of 10 lines from 8 locations comes to 1.20 + 1.20 + 2.20 + 0.80 + 0.60 = 6.00 normal minutes, 6.90 standard, with no new study. The 15 percent is an example allowance.

Two kits, one library of five elements

Example numbers
  • Kit of 24 lines, 18 locations
  • Kit of 10 lines, 8 locations
  • Travel to the aisle and back

    1.20 min (1.20 x 1 kit)
    1.20 min (1.20 x 1 kit)
  • Move between pick locations

    2.70 min (0.15 x 18)
    1.20 min (0.15 x 8)
  • Pick a line

    5.28 min (0.22 x 24)
    2.20 min (0.22 x 10)
  • Scan and confirm

    1.92 min (0.08 x 24)
    0.80 min (0.08 x 10)
  • Label and close the kit

    0.60 min (0.60 x 1 kit)
    0.60 min (0.60 x 1 kit)

Kit of 24 lines

Normal 11.70 min. Standard 11.70 x 1.15 = 13.46 min.

Kit of 10 lines

Normal 6.00 min. Standard 6.00 x 1.15 = 6.90 min.

A kit of 24 lines from 18 locations comes to 11.70 normal minutes and 13.46 standard minutes with a 15 percent allowance. A smaller kit of 10 lines from 8 locations comes to 6.00 normal minutes and 6.90 standard minutes, from the same five library elements and with no new study.

Each bar is a library time multiplied by a count read off the pick list. The second kit needed no stopwatch: it is the same five elements with different counts.
  • Pick drivers people can count. Lines and locations are on the pick list. Metres walked are not.
  • Keep the library small. Five to fifteen elements cover most of a job family. A hundred entries nobody trusts are worth less than ten that are right.
  • Check it against reality. Time a few whole jobs and compare with the sum. If the sum and the clock agree closely, the library is good enough for planning. If they do not, an element or a driver is missing.
  • Record the method with each element. A pick from a flow rack at waist height is a different element from a pick out of a floor-level tote.

Slotting, for work too varied for a library

Maintenance repair is too varied even for element sums. The classic answer, from Maynard's Universal Maintenance Standards in the 1950s, is slotting. You measure a set of benchmark jobs carefully and sort them into time bands, such as up to half an hour, half an hour to an hour, one to two hours. A planner then compares each new job with the benchmarks and drops it in the band it most resembles. Any one job will be off. Over a week of jobs the errors cancel, which is all a maintenance schedule needs. The same idea appears in British texts as comparative estimating. Its cousin, analytical estimating, builds the time element by element from experience and whatever standard data exists.

How to set a standard for long-cycle or crew work

A standard for long-cycle or crew work, in seven steps

  1. 1

    Pick the job family, not the job

  2. 2

    Talk to the crew

  3. 3

    Record two or three whole jobs

  4. 4

    Chart the crew

  5. 5

    Fix the method first

  6. 6

    Build the element library

  7. 7

    Assemble, add allowances and check

Fix the method in step 5 before you build the library in step 6. Do not set a standard on a method you know is wasteful.
  1. 1

    Pick the job family, not the job

    Choose a group of jobs that share elements, such as all filter changes or all kits for one line. A standard for one job is used once. A library for a family is used every day.

  2. 2

    Talk to the crew

    Say what you are studying and why, and that the aim is the method and the plan, not a judgment on anyone. On long work people have many honest reasons for delay, and you need them to tell you.

  3. 3

    Record two or three whole jobs

    Film them, or observe with a clock and coarse elements. Log every interruption and its cause.

  4. 4

    Chart the crew

    Draw each person's working and waiting time on one scale. Total the work content and the waiting.

  5. 5

    Fix the method first

    Re-sequence, stage parts and tools, and settle the crew size with the people who do the job. Do not set a standard on a method you already know is wasteful.

  6. 6

    Build the element library

    Split the improved job into elements tied to countable drivers. Give each a normal time from your recordings, rated for pace where you can.

  7. 7

    Assemble, add allowances and check

    Sum the elements for each job, add allowances, and compare the result with the next few real runs. Adjust the library, not the individual standard.

Notes by type of work

What usually works for each type of long-cycle or crew job
WorkUsual approachWatch for
Changeovers and setupsVideo, crew chart, then split internal from external workThe run-up and first good part are part of the changeover. Keep filming.
Planned maintenanceCoarse-element timing of a few jobs, then a library by taskTravel, permits and waiting for parts often exceed wrench time.
Breakdown repairSlotting against benchmark jobs. Work sampling for the departmentDiagnosis time cannot be standardized. Measure it, do not target it.
Kitting and order pickingElement library with lines and locations as driversTravel depends on layout. Re-time it when the layout changes.
Team assembly of large productsCrew chart per station, then balance work content across peopleShared lifts and two-person tasks tie the crew together.
Material handling and line supplyWork sampling, then route timingEmpty running and waiting at docks.
Inspection and testingDirect timing with coarse elements. Machine or cure time noted separatelyDo not rate a wait for a test to finish.

For changeovers, the SMED guide takes over where this page stops.

The people side

Skilled trades and crews often have more to lose from a careless study than line operators. Their work has long been judged by results, and a stopwatch can look like a demotion. They also hold the knowledge you need.

  • Study the job, not the tradesperson. Report crew totals and method findings, never a ranking of individuals.
  • Start with the waiting they complain about. Parts not kitted, permits not ready, no forklift. Fixing those wins more goodwill than any speech.
  • Use standards for planning and scheduling first. A maintenance standard that makes the weekly plan achievable is welcomed. One used to chase a technician on a bad job is not.
  • Accept ranges. Tell people the standard for a varied job is an average across many jobs and will be wrong on any single one.
  • Where there is a union, agree the approach before filming. See time study in a union plant.

Traps

  • Averaging three unlike cycles and calling it a standard.
  • Dividing elapsed time by nothing. A 42 minute job by three people is 126 person-minutes, and labor plans need person-minutes.
  • Setting the standard on today's sequence, waiting included.
  • Adding people to shorten a job whose longest task only one person can reach.
  • Rating the pace of diagnosis, waiting or machine time.
  • A library with drivers nobody records, so the standard cannot be calculated from the work order.
  • Holding one job to a slotted standard. Slotting is right on average and wrong in particular.
  • Leaving out travel, permits, clean-up and paperwork because they are not real work. They are paid time and they belong in the standard or in the improvement list.

Templates and tools

FAQ

Questions about timing long-cycle and team work

  1. Time a few whole cycles with coarse elements of a minute or more, using continuous timing, and log every interruption with its cause. A widely used guide table calls for 5 cycles when the cycle is 20 to 40 minutes and 3 when it is over 40. Report the range as well as the average, and confirm the standard as more runs are logged.

  2. Measure the pieces that do repeat. Break the work into elements tied to something countable, such as picks, bolts or metres of weld, time those elements, and keep them in a library. A standard for a new job is then the sum of element time x count, plus allowances. For work too varied even for that, slot each job into a time band by comparing it with measured benchmark jobs.

  3. Chart each person on a common time scale, marking working and waiting, from direct observation or from video. Add up the working time for the work content in person-minutes, and compare it with paid time, which is crew size x elapsed time. For larger crews, note what each person is doing at a fixed short interval and use the shares.

  4. A gang process chart, or crew chart, shows the activity of each member of a group working together, side by side against one time scale. It is used to find waiting within the crew, to settle the crew size and to re-sequence the job. It is a multiple activity chart with a person in every column.

  5. The group timing technique is work sampling at a fixed short interval, used on crews. Every minute or two the observer notes what each crew member is doing. The share of observations in each category estimates the share of time. Sixty-three observations of a three-person crew with 41 working gives 65 percent working, or 82 of 126 person-minutes.

  6. Yes, as planning standards. Planned tasks can be timed with coarse elements and built into a library by task. Repair work is usually slotted into time bands against benchmark jobs, an approach that goes back to Universal Maintenance Standards in the 1950s. The standard is right on average over many jobs and should not be used to judge one job or one technician.

  7. Fewer than for a short one. The General Electric guide table reproduced in Niebel and Freivalds gives 10 cycles for a cycle of 5 to 10 minutes, 8 for 10 to 20 minutes, 5 for 20 to 40 minutes and 3 for more than 40 minutes. It is a rule of thumb. If the cycles you time differ widely, find out why before averaging.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.