Worked examples · Standard work, SOPs and training
Standard work examples: three jobs in three industries, worked through
Short answer
Standard work examples are easiest to learn from when the arithmetic is shown. Here are three jobs in three industries: a food tray cell, an electronics bench and a warehouse pack bench. Each is taken from takt time to the posted chart, with its cycle, its spare seconds and its stock.
A standard work example has the same parts whatever the industry: takt time, a work sequence with manual, machine and walking seconds, standard in-process stock, and the three documents that carry them (the process capacity sheet, the combination table and the standard work chart). Here a food tray pack cell runs a 36 second cycle against a 40 second takt time with 2 pieces of stock. An electronics bench runs 94 against 100 with 1 piece. A warehouse pack bench runs 34 seconds plus 4 per order line against 60, so it holds takt time up to 6 lines. All three are illustrative.
Last reviewed:
What the three examples show
Three jobs, three industries, one test
Example numbersFood: Tray pack cell675 trays a shift, takt 40 s, cycle 36 s, wait 4 s
Electronics: Power module bench270 modules a shift, takt 100 s, cycle 94 s, wait 6 s
Warehouse: Outbound pack bench, 3 line order450 orders a shift, takt 60 s, cycle 46 s, wait 14 s
Three bars, each drawn as a share of its own takt time. The tray pack cell runs 36 seconds against a 40 second takt time. The power module bench runs 94 against 100. The outbound pack bench runs 46 against 60 for a three line order. All three fit, with 4, 6 and 14 seconds to spare.
Every example on this page follows the same route. Takt time comes first, because it is the target. Then the work sequence is timed element by element, split into manual seconds, machine seconds and walking seconds. Then the standard in-process stock is counted. The Lean Enterprise Institute's Lean Lexicon names these as the three elements of standardized work, and a 2001 SAE paper on lean tools lists the same three. Three forms carry them: the process capacity sheet, the combination table and the standard work chart.
The jobs here are different on purpose. The food cell has a short cycle and two machines. The electronics bench has a long cycle and almost no walking. The warehouse bench has work that changes with every order. If you have read standard work, the combination table and standard WIP, these are three more jobs to practise on. The numbers are made up for teaching, and the arithmetic has been checked.
| Tray pack cell (food) | Power module bench (electronics) | Pack bench (warehouse) | |
|---|---|---|---|
| Demand a shift | 675 trays | 270 modules | 450 orders |
| Takt time | 27,000 / 675 = 40 s | 27,000 / 270 = 100 s | 27,000 / 450 = 60 s |
| Operator cycle | 29 + 7 = 36 s | 82 + 12 = 94 s | 34 s + 4 s a line, 46 s for 3 lines |
| Spare seconds | 4 s | 6 s | 14 s for 3 lines, 2 s for 6 |
| Standard in-process stock | 2 pieces | 1 piece | 0 at the bench |
Example 1, food: a tray pack cell
Illustrative numbers. One operator runs the end of a yogurt tray line: a tray sealer, an inspection table, a checkweigher and a case packing spot. The plant needs 675 trays in a 450 minute shift of 27,000 seconds, so takt time is 27,000 / 675 = 40 seconds. Each element was timed over many cycles and the times below are the selected ones.
| Element | Manual | Machine | Walk | Starts at |
|---|---|---|---|---|
| 1. Unload and load the tray sealer, start it | 7 s | 25 s | 2 s | 0 s |
| 2. Inspect seals and date code | 8 s | none | 2 s | 9 s |
| 3. Unload and load the checkweigher, start it | 5 s | 12 s | 1 s | 19 s |
| 4. Case the tray, tape and label the case | 9 s | none | 2 s | 25 s |
| Total | 29 s | 7 s | cycle 36 s |
Takt time 40 s minus cycle 36 s leaves 4 s of wait.
Combination table: tray pack cell
Example numbers- Manual work
- Machine runs alone
- Walking
- Waiting
- Takt time
1. Unload and load the tray sealer, start itManual 7 s, machine 25 s, walk 2 s
2. Inspect seals and date codeManual 8 s, walk 2 s
3. Unload and load the checkweigher, start itManual 5 s, machine 12 s, walk 1 s
4. Case the tray, tape and label the caseManual 9 s, walk 2 s
Operator cycleManual 29 s + walk 7 s = 36 s, wait 4 s
Four elements on a time line from 0 to 50 seconds. Manual work and walking add up to 36 seconds, 4 seconds before the takt line at 40 seconds. The tray sealer runs on its own from 7 to 32 seconds and the checkweigher from 24 to 36 seconds, both done before the operator returns.
Read the combination table for two checks. First, the operator's cycle: 29 seconds of manual work plus 7 of walking is 36, 4 under takt time. Second, each machine against the operator's return. The sealer is loaded at 7 seconds, runs 25 and is done at 32. The operator is back at 36. The checkweigher is loaded at 24 and finished at 36, and the operator does not return to it until 19 seconds into the next cycle. Both machines are ready before the operator comes back, so nobody stands and waits.
| Document | What it holds | What it showed here |
|---|---|---|
| Process capacity sheet | Manual plus machine time per piece, for each machine | The sealer needs 7 + 25 = 32 s a piece. On its own it could make 27,000 / 32 = 843 trays a shift, so the machine is not the limit. The operator is. |
| Combination table | The four elements on a time line against takt time | Cycle 36 s against 40 s. Output at that cycle is 27,000 / 36 = 750 trays against 675 needed. |
| Standard work chart | The layout, the walking loop, the stock and the quality point | A loop of four stops, one piece in the sealer and one in the checkweigher, a quality check at the inspection table. |
Standard work chart: tray pack cell
Example numbers- 1
Tray sealer
7 s by hand, 25 s machine
Then walk 2 s
- 2
Inspection table
8 s by hand
Then walk 2 s
- 3
Checkweigher
5 s by hand, 12 s machine
Then walk 1 s
- 4
Case packing
9 s by hand
Then walk 2 s
- Standard in-process stock
- Quality check
The sheet that goes on the wall. Four stops in a loop: tray sealer, inspection table, checkweigher, case packing. The sealer and the checkweigher each hold one piece of standard in-process stock. The inspection is marked as a quality check. Takt time 40 seconds, cycle time 36 seconds, standard in-process stock 2.
The decision it fed: one operator holds this cell, and the 4 spare seconds are not a target to fill. The inspection element is the one most likely to stretch when a film roll runs out or a seal looks marginal, and it is a quality check, so it is protected. A film change goes to someone else on a set round, so the operator does not leave the loop. Standard in-process stock is 2: one piece in each machine, with the operator walking with the flow.
Example 2, electronics: a power module bench
Illustrative numbers. One operator builds a power module at a bench: a heatsink and thermal pad, four screws, a wire harness, a functional tester and a pack tray. The customer needs 270 modules in the same 27,000 seconds, so takt time is 100 seconds. The cycle is long, the work is almost all by hand, and one machine, the tester, runs for 40 seconds.
| Element | Manual | Machine | Walk | Starts at |
|---|---|---|---|---|
| 1. Fit the heatsink and thermal pad | 18 s | none | 2 s | 0 s |
| 2. Drive four screws in cross order (torque check) | 20 s | none | 2 s | 20 s |
| 3. Connect and route the harness | 18 s | none | 2 s | 42 s |
| 4. Unload and load the tester, start it | 8 s | 40 s | 2 s | 62 s |
| 5. Read the result, label, scan the serial | 12 s | none | 2 s | 72 s |
| 6. Pack in the ESD tray | 6 s | none | 2 s | 86 s |
| Total | 82 s | 12 s | cycle 94 s |
Takt time 100 s minus cycle 94 s leaves 6 s of wait.
Combination table: power module bench
Example numbers- Manual work
- Machine runs alone
- Walking
- Waiting
- Takt time
1. Fit the heatsink and thermal padManual 18 s, walk 2 s
2. Drive four screws in cross orderManual 20 s, walk 2 s
Torque check
3. Connect and route the harnessManual 18 s, walk 2 s
4. Unload and load the tester, start itManual 8 s, machine 40 s, walk 2 s
5. Read the result, label, scan the serialManual 12 s, walk 2 s
6. Pack in the ESD trayManual 6 s, walk 2 s
Operator cycleManual 82 s + walk 12 s = 94 s, wait 6 s
Six elements on a time line from 0 to 110 seconds. Manual work and walking add up to 94 seconds, 6 seconds before the takt line at 100 seconds. The tester is loaded at 70 seconds, runs 40 seconds on its own and finishes 10 seconds into the next cycle, well before the operator is back at 62 seconds.
The tester is loaded at 70 seconds and finishes at 110, which is 10 seconds into the next 100 second cycle. The operator is back at it at 62, 52 seconds after it finished. So the machine is never the constraint here, and its capacity sheet says why: 8 + 40 = 48 seconds a piece, 562 modules a shift. The operator at 94 seconds a cycle makes 27,000 / 94 = 287 modules against 270 needed. Standard in-process stock is 1: the module in the tester.
The sequence is itself a decision. The screws, with their torque check, come before the harness because the harness covers the screws and a missed one cannot be seen afterwards. Element 2 gets a quality mark on the chart and a work instruction with the screw order, because a mistake there is a defect. Elements 1 and 6 need only the chart. That is the split to look for in any long-cycle assembly: the combination table says when, the work instruction says how.
Example 3, warehouse: an outbound pack bench
Illustrative numbers. One packer at a bench scans a tote, checks the items against the order, chooses a carton, seals and labels it, weighs it and sends it down a conveyor. The site ships 450 orders a shift from this bench, so takt time is 27,000 / 450 = 60 seconds. The trouble for standard work is that the content changes: an order can have 1 line or 8, and each line takes 4 seconds to check and scan.
| Element | Manual | Walk |
|---|---|---|
| 1. Scan the tote and pull the order | 5 s | 1 s |
| 2. Check each line against the screen and scan it | 4 s a line | 1 s |
| 3. Choose the carton and place the items with fill | 9 s | 2 s |
| 4. Seal, print and apply the label | 8 s | 1 s |
| 5. Weigh and place on the conveyor | 6 s | 1 s |
| Fixed work | 28 s | 6 s |
Cycle = 28 + 6 + 4 x lines = 34 s plus 4 s a line. For a 3 line order that is 46 s.
One number cannot describe this bench, so the standard states a rule. The room left under takt time after the fixed work is 60 - 34 = 26 seconds. At 4 seconds a line, 26 / 4 = 6.5, so a whole order of up to 6 lines fits, at 58 seconds with 2 spare. A 7 line order runs 62, 2 seconds over, and an 8 line order runs 66. A 3 line order runs 46 seconds, 14 under takt time and 77 percent of it. Before you set a limit like this, pull the real order profile from the order system, so you know how many orders fall above it.
Pack bench: cycle time by number of lines in the order
Example numbers- Fixed manual work, 28 s
- Walking, 6 s
- Check and scan, 4 s a line
Eight bars for orders of 1 to 8 lines. The cycle is 28 seconds of fixed manual work and 6 of walking, plus 4 seconds per line. It rises from 38 seconds for one line to 66 for eight. Orders up to 6 lines fit inside the 60 second takt time. Orders of 7 and 8 lines run 2 and 6 seconds over.
The decision it fed is a route, not a time. The standard says: orders of 1 to 6 lines are packed at this bench to this sequence. Orders of 7 lines or more go to a named second bench, or are split at the pick, so they do not push the bench behind takt time. The chart also sets how many totes may wait at the bench, for example 2. That is a queue limit and not standard in-process stock, because totes waiting to be packed are not pieces sitting inside the process.
What changes by industry
The method is the same. What you spend your effort on is not. These are the differences the three examples show, and how they carry over to other plants with similar jobs.
| Food and packaging | Electronics and medical assembly | Warehouse and logistics | |
|---|---|---|---|
| Cycle length | Short, 36 seconds in the example | Long, 94 seconds in the example | Varies with the order |
| Where the risk is | A machine that is slow to refill or clear | A missed step the cover hides, a damaged part | Orders bigger than the bench was set for |
| Key document | The combination table, to check each machine is ready | The work instruction behind each quality element | The sequence plus a rule for order size |
| Quality marks go on | Seal inspection, weight check | Torque, serial scan, test result | Item scan, carton check, weigh check |
| What the stock means | A piece in each machine | A piece in the tester | A queue limit on totes |
| Who usually writes it | Line lead with the operator | The process engineer with the operator | The shift lead with the packer, using the system's order profile |
For more on timing these jobs, see the guides on time study in food and beverage manufacturing, time study in electronics assembly and time study in warehouse operations.
How to write yours from these examples
- 1
Work out takt time
Divide available working time in seconds by the demand for that shift. The examples used 27,000 seconds, but subtract breaks, meetings and planned stops for your own shift, and use the demand the customer actually wants.
- 2
Time each element with the operator
Break the job into elements and time them over enough cycles to trust the result. Record manual, machine and walking seconds separately. How to conduct a time study shows the procedure.
- 3
Fill the process capacity sheet
For each machine, add its manual and machine seconds. If a machine is slower than takt time, it is the limit, whatever the operator does, and you fix it before anything else.
- 4
Draw the combination table
Put the elements in the order the operator does them, then add the machine bars and the takt line. Check that every machine is finished before the operator returns, and that the total is under takt time.
- 5
Count the standard in-process stock
Count the pieces the cell needs inside it to run, as set out in standard WIP, and mark where each one sits.
- 6
Draw the chart, post it and audit it
Put the loop, the seconds, the stock and the quality and safety points on one sheet at the job. Walk the job with the operator against it within the first week, and again each month. Updating standard work covers what to do when the job changes.
Do the study with the operator, not behind them. Operators often worry that a time study is a tool for cutting jobs. Say what it will be used for, show them the sheet, use a normal pace for a trained person and not the fastest, and let them correct the sequence. A standard the operator helped write is followed. One handed down on paper is not.
When standard work is the wrong tool
Standard work is built on a repeating cycle and a takt time. A job without them gets a different document. A changeover, a repair, a monthly audit and a one-off inspection are work with a start and an end but no cycle, so a checklist or an SOP fits better. Standard work, SOPs and work instructions sets out which to write and when to write all three. The three questions below sort most jobs.
Is standard work the right document for this job?
Does one person repeat the same sequence all shift?
If no
Write an SOP, with a checklist if the order matters. Repairs, changeovers and one-off jobs have no cycle to time.
Is the content the same each cycle, or does a rule cover the differences?
If no
Set the rule first, as in the pack bench: a standard for up to 6 lines and a named route for the rest. Until then, an SOP fits better.
Do all shifts do it the same way?
If no
Agree the best way first, with the people who do it. Timing three different methods gives a standard that fits none of them.
Every answer right
Write standard work: the capacity table, the combination table and the chart. Add a work instruction for any element where a mistake causes a defect or an injury.
Three questions in order. If the job is not repeated in a cycle, write an SOP or a checklist. If the content changes from one cycle to the next with no rule for it, set a rule first or write an SOP. If the people doing it change the method each shift, fix the method before timing it. If every answer is yes, write standard work.
Even a repeating job can fail the test. If the people on three shifts do it three ways, timing it records a mixture. If the content swings widely with no rule, as the pack bench would without its 6 line limit, a single time misleads. Fix those first, then write the standard.
Common mistakes when copying an example
- Copying the times. Your elements take what they take. The examples show the method, not the numbers.
- Filling the spare seconds. The 4, 6 or 14 seconds are what absorbs a slow cycle. A cycle exactly at takt time breaks the first time anything varies.
- Writing one time for work that varies. Where content changes with the order, the standard needs a rule for the range.
- Drawing the chart and not counting the stock. Without the pieces marked, a wrong count is invisible.
- Skipping the walk. In the electronics example walking is 12 of 94 seconds. Leave it out and the cycle reads 82 and looks far more comfortable than it is.
- Writing it once and leaving it. Take a measured cycle from the floor every month. If it drifts, find out why before you change the paper.
Where software helps
The timing is the slow part. LeanSuite's Time and Motion Study drafts element times from a video of the station, on a timeline that links back to the footage, for you to check and certify. Standardized work software covers keeping the documents current and auditing them. The standard work combination table and process capacity sheet are free templates for drawing your own.
Standardized work software
Keep standard work current in LeanSuite
LeanSuite covers most of the cycle in one platform: working out the standard with Vision AI, keeping it current with SOPs and work instructions, and training and auditing it.
Go deeper
This page is the short version. These guides cover each part in full.
- The Three Elements of Standard Work: Takt Time, Work Sequence, Standard WIPThe three elements each example is built from.
- Standard Work Tools: Combination Sheet, Standardized Work Chart, Job BreakdownThe forms used in the three examples.
- Standard Work in Manufacturing: The Complete GuideRolling the examples out across a plant.
All our articles on this subject are in the standard work, sops and training topic.
Free templates and tools
- Standard work sheet templateTakt time, each element's manual, machine and walk time on a time chart, key points and standard WIP.
- Standard work combination tableOne operator's manual, machine, walk and wait time on a time chart against takt, with machine cycles and a process capacity sheet.
- Process capacity sheet templateEach machine in a part's routing with manual, auto and tool change time, its capacity per shift, and the step that limits the cell against demand.
- Standard work audit checklist24 checks of a job against its written standard, ten timed cycles, and each gap sorted by cause before anyone acts.
- Takt time calculatorThe pace a line must hit to meet customer demand, from shift time, breaks and daily demand.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
Doing this in LeanSuite
Time and Motion Study
Film the station and the AI times every element on a timeline that links to the video. You check it and certify it.
See Time and Motion StudyStandardized work software
Working out the standard with Vision AI, keeping it current with SOPs and work instructions, and training and auditing it.
See Standardized work software
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about standard work examples
A packer at a pack bench who scans the tote, checks each order line, picks a carton, seals and labels it, then weighs it, always in that order, with each element timed and the cycle held under takt time. In the example here the cycle is 34 seconds plus 4 per order line against a 60 second takt time. The sequence, the seconds and the stock are written on one chart at the job.
Takt time, work sequence and standard in-process stock. Takt time is the customer's pace and is calculated. The work sequence is the order and timing of the operator's steps. Standard in-process stock is the fewest pieces the process needs inside it to run without waiting. The Lean Enterprise Institute's Lean Lexicon names the same three elements.
Three forms carry it. The process capacity sheet shows each machine's capacity and finds the limit. The combination table shows the operator and machines on a time line against takt time. The standard work chart shows the layout, walking path, stock and quality points. A time observation sheet comes first, and work instructions sit underneath for the hard elements.
Split the work into fixed elements and elements that vary with the order, then time each part. At a pack bench, 34 seconds is fixed and each order line adds 4. Then state the range the standard covers. Under a 60 second takt time that is 6 lines. Orders above it go to a named route, so they do not break the standard.
No. Standard work is a timed, repeating cycle for one operator at a station, balanced to takt time. An SOP describes how to carry out a broader activity and has no cycle or takt time. A changeover or a repair suits an SOP. A work instruction goes deeper still, into one element. Many jobs need more than one of the three.
The people who do the job, led by the supervisor or an engineer who knows how to time it. An engineer alone writes a paper standard that the floor ignores. Time it with the operator, agree the sequence with them, and have them sign it. Then audit it against the real job at set intervals so it stays true.
Related guides and tools
- Standard work: the three elements and the documents, with one worked cell
- From time study to standard work: the handover step by step
- Standard work combination table: how to build and read one
- Standard WIP: how to count the pieces the cell needs
- Updating standard work after an improvement
- Time study in food and beverage manufacturing
- Time study in electronics assembly
- Time study in warehouse operations
- Standard work vs SOP vs work instruction: which document for which job
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk
Or browse the topics, the full library and the lean glossary.
Rather see it on your own problem?
Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.