Skip to content
LeanSuite

Standard work examples: three jobs in three industries, worked through

Short answer

Standard work examples are easiest to learn from when the arithmetic is shown. Here are three jobs in three industries: a food tray cell, an electronics bench and a warehouse pack bench. Each is taken from takt time to the posted chart, with its cycle, its spare seconds and its stock.

A standard work example has the same parts whatever the industry: takt time, a work sequence with manual, machine and walking seconds, standard in-process stock, and the three documents that carry them (the process capacity sheet, the combination table and the standard work chart). Here a food tray pack cell runs a 36 second cycle against a 40 second takt time with 2 pieces of stock. An electronics bench runs 94 against 100 with 1 piece. A warehouse pack bench runs 34 seconds plus 4 per order line against 60, so it holds takt time up to 6 lines. All three are illustrative.

Last reviewed:

What the three examples show

Three jobs, three industries, one test

Example numbers
  • Food: Tray pack cell675 trays a shift, takt 40 s, cycle 36 s, wait 4 s

  • Electronics: Power module bench270 modules a shift, takt 100 s, cycle 94 s, wait 6 s

  • Warehouse: Outbound pack bench, 3 line order450 orders a shift, takt 60 s, cycle 46 s, wait 14 s

Three bars, each drawn as a share of its own takt time. The tray pack cell runs 36 seconds against a 40 second takt time. The power module bench runs 94 against 100. The outbound pack bench runs 46 against 60 for a three line order. All three fit, with 4, 6 and 14 seconds to spare.

The jobs share no work, but standard work asks the same thing of each: does one operator's cycle fit inside takt time, with a little room left? The red line is takt time at 100%.

Every example on this page follows the same route. Takt time comes first, because it is the target. Then the work sequence is timed element by element, split into manual seconds, machine seconds and walking seconds. Then the standard in-process stock is counted. The Lean Enterprise Institute's Lean Lexicon names these as the three elements of standardized work, and a 2001 SAE paper on lean tools lists the same three. Three forms carry them: the process capacity sheet, the combination table and the standard work chart.

The jobs here are different on purpose. The food cell has a short cycle and two machines. The electronics bench has a long cycle and almost no walking. The warehouse bench has work that changes with every order. If you have read standard work, the combination table and standard WIP, these are three more jobs to practise on. The numbers are made up for teaching, and the arithmetic has been checked.

Illustrative: the three examples at a glance, 450 minute shift
Tray pack cell (food)Power module bench (electronics)Pack bench (warehouse)
Demand a shift675 trays270 modules450 orders
Takt time27,000 / 675 = 40 s27,000 / 270 = 100 s27,000 / 450 = 60 s
Operator cycle29 + 7 = 36 s82 + 12 = 94 s34 s + 4 s a line, 46 s for 3 lines
Spare seconds4 s6 s14 s for 3 lines, 2 s for 6
Standard in-process stock2 pieces1 piece0 at the bench

Example 1, food: a tray pack cell

Illustrative numbers. One operator runs the end of a yogurt tray line: a tray sealer, an inspection table, a checkweigher and a case packing spot. The plant needs 675 trays in a 450 minute shift of 27,000 seconds, so takt time is 27,000 / 675 = 40 seconds. Each element was timed over many cycles and the times below are the selected ones.

Illustrative: work sequence for the tray pack cell, takt time 40 s
ElementManualMachineWalkStarts at
1. Unload and load the tray sealer, start it7 s25 s2 s0 s
2. Inspect seals and date code8 snone2 s9 s
3. Unload and load the checkweigher, start it5 s12 s1 s19 s
4. Case the tray, tape and label the case9 snone2 s25 s
Total29 s7 scycle 36 s

Takt time 40 s minus cycle 36 s leaves 4 s of wait.

Combination table: tray pack cell

Example numbers
  • Manual work
  • Machine runs alone
  • Walking
  • Waiting
  • Takt time
  1. 1. Unload and load the tray sealer, start itManual 7 s, machine 25 s, walk 2 s

  2. 2. Inspect seals and date codeManual 8 s, walk 2 s

  3. 3. Unload and load the checkweigher, start itManual 5 s, machine 12 s, walk 1 s

  4. 4. Case the tray, tape and label the caseManual 9 s, walk 2 s

  5. Operator cycleManual 29 s + walk 7 s = 36 s, wait 4 s

Four elements on a time line from 0 to 50 seconds. Manual work and walking add up to 36 seconds, 4 seconds before the takt line at 40 seconds. The tray sealer runs on its own from 7 to 32 seconds and the checkweigher from 24 to 36 seconds, both done before the operator returns.

The sealer is the one to watch. It is loaded at 7 s, finishes at 32 s and the operator is back at 36 s. A 4 second gap is thin, so a slow film change shows up here first.

Read the combination table for two checks. First, the operator's cycle: 29 seconds of manual work plus 7 of walking is 36, 4 under takt time. Second, each machine against the operator's return. The sealer is loaded at 7 seconds, runs 25 and is done at 32. The operator is back at 36. The checkweigher is loaded at 24 and finished at 36, and the operator does not return to it until 19 seconds into the next cycle. Both machines are ready before the operator comes back, so nobody stands and waits.

Illustrative: what each of the three documents says for the tray pack cell
DocumentWhat it holdsWhat it showed here
Process capacity sheetManual plus machine time per piece, for each machineThe sealer needs 7 + 25 = 32 s a piece. On its own it could make 27,000 / 32 = 843 trays a shift, so the machine is not the limit. The operator is.
Combination tableThe four elements on a time line against takt timeCycle 36 s against 40 s. Output at that cycle is 27,000 / 36 = 750 trays against 675 needed.
Standard work chartThe layout, the walking loop, the stock and the quality pointA loop of four stops, one piece in the sealer and one in the checkweigher, a quality check at the inspection table.

Standard work chart: tray pack cell

Example numbers
  1. 1

    Tray sealer

    7 s by hand, 25 s machine

    Then walk 2 s

  2. 2

    Inspection table

    8 s by hand

    Then walk 2 s

  3. 3

    Checkweigher

    5 s by hand, 12 s machine

    Then walk 1 s

  4. 4

    Case packing

    9 s by hand

    Then walk 2 s

Takt 40 sCycle 36 sStandard stock 2
  • Standard in-process stock
  • Quality check

The sheet that goes on the wall. Four stops in a loop: tray sealer, inspection table, checkweigher, case packing. The sealer and the checkweigher each hold one piece of standard in-process stock. The inspection is marked as a quality check. Takt time 40 seconds, cycle time 36 seconds, standard in-process stock 2.

Four things on one page: the walking order, the seconds, where the two pieces of stock sit and where the quality check is. The operator walks from stop 4 back to stop 1 in 2 seconds.

The decision it fed: one operator holds this cell, and the 4 spare seconds are not a target to fill. The inspection element is the one most likely to stretch when a film roll runs out or a seal looks marginal, and it is a quality check, so it is protected. A film change goes to someone else on a set round, so the operator does not leave the loop. Standard in-process stock is 2: one piece in each machine, with the operator walking with the flow.

Example 2, electronics: a power module bench

Illustrative numbers. One operator builds a power module at a bench: a heatsink and thermal pad, four screws, a wire harness, a functional tester and a pack tray. The customer needs 270 modules in the same 27,000 seconds, so takt time is 100 seconds. The cycle is long, the work is almost all by hand, and one machine, the tester, runs for 40 seconds.

Illustrative: work sequence for the power module bench, takt time 100 s
ElementManualMachineWalkStarts at
1. Fit the heatsink and thermal pad18 snone2 s0 s
2. Drive four screws in cross order (torque check)20 snone2 s20 s
3. Connect and route the harness18 snone2 s42 s
4. Unload and load the tester, start it8 s40 s2 s62 s
5. Read the result, label, scan the serial12 snone2 s72 s
6. Pack in the ESD tray6 snone2 s86 s
Total82 s12 scycle 94 s

Takt time 100 s minus cycle 94 s leaves 6 s of wait.

Combination table: power module bench

Example numbers
  • Manual work
  • Machine runs alone
  • Walking
  • Waiting
  • Takt time
  1. 1. Fit the heatsink and thermal padManual 18 s, walk 2 s

  2. 2. Drive four screws in cross orderManual 20 s, walk 2 s

    Torque check

  3. 3. Connect and route the harnessManual 18 s, walk 2 s

  4. 4. Unload and load the tester, start itManual 8 s, machine 40 s, walk 2 s

  5. 5. Read the result, label, scan the serialManual 12 s, walk 2 s

  6. 6. Pack in the ESD trayManual 6 s, walk 2 s

  7. Operator cycleManual 82 s + walk 12 s = 94 s, wait 6 s

Six elements on a time line from 0 to 110 seconds. Manual work and walking add up to 94 seconds, 6 seconds before the takt line at 100 seconds. The tester is loaded at 70 seconds, runs 40 seconds on its own and finishes 10 seconds into the next cycle, well before the operator is back at 62 seconds.

The tester run crosses the end of the cycle and carries on from 0, as it does on a paper sheet. It is finished 52 seconds before the operator gets back to it, so the tester is never the constraint. The operator's hands are.

The tester is loaded at 70 seconds and finishes at 110, which is 10 seconds into the next 100 second cycle. The operator is back at it at 62, 52 seconds after it finished. So the machine is never the constraint here, and its capacity sheet says why: 8 + 40 = 48 seconds a piece, 562 modules a shift. The operator at 94 seconds a cycle makes 27,000 / 94 = 287 modules against 270 needed. Standard in-process stock is 1: the module in the tester.

The sequence is itself a decision. The screws, with their torque check, come before the harness because the harness covers the screws and a missed one cannot be seen afterwards. Element 2 gets a quality mark on the chart and a work instruction with the screw order, because a mistake there is a defect. Elements 1 and 6 need only the chart. That is the split to look for in any long-cycle assembly: the combination table says when, the work instruction says how.

Example 3, warehouse: an outbound pack bench

Illustrative numbers. One packer at a bench scans a tote, checks the items against the order, chooses a carton, seals and labels it, weighs it and sends it down a conveyor. The site ships 450 orders a shift from this bench, so takt time is 27,000 / 450 = 60 seconds. The trouble for standard work is that the content changes: an order can have 1 line or 8, and each line takes 4 seconds to check and scan.

Illustrative: work sequence for the pack bench, takt time 60 s
ElementManualWalk
1. Scan the tote and pull the order5 s1 s
2. Check each line against the screen and scan it4 s a line1 s
3. Choose the carton and place the items with fill9 s2 s
4. Seal, print and apply the label8 s1 s
5. Weigh and place on the conveyor6 s1 s
Fixed work28 s6 s

Cycle = 28 + 6 + 4 x lines = 34 s plus 4 s a line. For a 3 line order that is 46 s.

One number cannot describe this bench, so the standard states a rule. The room left under takt time after the fixed work is 60 - 34 = 26 seconds. At 4 seconds a line, 26 / 4 = 6.5, so a whole order of up to 6 lines fits, at 58 seconds with 2 spare. A 7 line order runs 62, 2 seconds over, and an 8 line order runs 66. A 3 line order runs 46 seconds, 14 under takt time and 77 percent of it. Before you set a limit like this, pull the real order profile from the order system, so you know how many orders fall above it.

Pack bench: cycle time by number of lines in the order

Example numbers
  • Fixed manual work, 28 s
  • Walking, 6 s
  • Check and scan, 4 s a line

Eight bars for orders of 1 to 8 lines. The cycle is 28 seconds of fixed manual work and 6 of walking, plus 4 seconds per line. It rises from 38 seconds for one line to 66 for eight. Orders up to 6 lines fit inside the 60 second takt time. Orders of 7 and 8 lines run 2 and 6 seconds over.

Standard work for a job whose content varies is a rule, not one number: up to 6 lines the bench holds takt time. Seven lines or more is a different job, so the standard says where it goes.

The decision it fed is a route, not a time. The standard says: orders of 1 to 6 lines are packed at this bench to this sequence. Orders of 7 lines or more go to a named second bench, or are split at the pick, so they do not push the bench behind takt time. The chart also sets how many totes may wait at the bench, for example 2. That is a queue limit and not standard in-process stock, because totes waiting to be packed are not pieces sitting inside the process.

What changes by industry

The method is the same. What you spend your effort on is not. These are the differences the three examples show, and how they carry over to other plants with similar jobs.

Where the work goes in each industry, drawn from the three examples
Food and packagingElectronics and medical assemblyWarehouse and logistics
Cycle lengthShort, 36 seconds in the exampleLong, 94 seconds in the exampleVaries with the order
Where the risk isA machine that is slow to refill or clearA missed step the cover hides, a damaged partOrders bigger than the bench was set for
Key documentThe combination table, to check each machine is readyThe work instruction behind each quality elementThe sequence plus a rule for order size
Quality marks go onSeal inspection, weight checkTorque, serial scan, test resultItem scan, carton check, weigh check
What the stock meansA piece in each machineA piece in the testerA queue limit on totes
Who usually writes itLine lead with the operatorThe process engineer with the operatorThe shift lead with the packer, using the system's order profile

For more on timing these jobs, see the guides on time study in food and beverage manufacturing, time study in electronics assembly and time study in warehouse operations.

How to write yours from these examples

  1. 1

    Work out takt time

    Divide available working time in seconds by the demand for that shift. The examples used 27,000 seconds, but subtract breaks, meetings and planned stops for your own shift, and use the demand the customer actually wants.

  2. 2

    Time each element with the operator

    Break the job into elements and time them over enough cycles to trust the result. Record manual, machine and walking seconds separately. How to conduct a time study shows the procedure.

  3. 3

    Fill the process capacity sheet

    For each machine, add its manual and machine seconds. If a machine is slower than takt time, it is the limit, whatever the operator does, and you fix it before anything else.

  4. 4

    Draw the combination table

    Put the elements in the order the operator does them, then add the machine bars and the takt line. Check that every machine is finished before the operator returns, and that the total is under takt time.

  5. 5

    Count the standard in-process stock

    Count the pieces the cell needs inside it to run, as set out in standard WIP, and mark where each one sits.

  6. 6

    Draw the chart, post it and audit it

    Put the loop, the seconds, the stock and the quality and safety points on one sheet at the job. Walk the job with the operator against it within the first week, and again each month. Updating standard work covers what to do when the job changes.

Do the study with the operator, not behind them. Operators often worry that a time study is a tool for cutting jobs. Say what it will be used for, show them the sheet, use a normal pace for a trained person and not the fastest, and let them correct the sequence. A standard the operator helped write is followed. One handed down on paper is not.

When standard work is the wrong tool

Standard work is built on a repeating cycle and a takt time. A job without them gets a different document. A changeover, a repair, a monthly audit and a one-off inspection are work with a start and an end but no cycle, so a checklist or an SOP fits better. Standard work, SOPs and work instructions sets out which to write and when to write all three. The three questions below sort most jobs.

Is standard work the right document for this job?

  1. Does one person repeat the same sequence all shift?

    If no

    Write an SOP, with a checklist if the order matters. Repairs, changeovers and one-off jobs have no cycle to time.

  2. Is the content the same each cycle, or does a rule cover the differences?

    If no

    Set the rule first, as in the pack bench: a standard for up to 6 lines and a named route for the rest. Until then, an SOP fits better.

  3. Do all shifts do it the same way?

    If no

    Agree the best way first, with the people who do it. Timing three different methods gives a standard that fits none of them.

  4. Every answer right

    Write standard work: the capacity table, the combination table and the chart. Add a work instruction for any element where a mistake causes a defect or an injury.

Three questions in order. If the job is not repeated in a cycle, write an SOP or a checklist. If the content changes from one cycle to the next with no rule for it, set a rule first or write an SOP. If the people doing it change the method each shift, fix the method before timing it. If every answer is yes, write standard work.

All three examples on this page pass. A line changeover, a repair and a monthly audit would not.

Even a repeating job can fail the test. If the people on three shifts do it three ways, timing it records a mixture. If the content swings widely with no rule, as the pack bench would without its 6 line limit, a single time misleads. Fix those first, then write the standard.

Common mistakes when copying an example

  • Copying the times. Your elements take what they take. The examples show the method, not the numbers.
  • Filling the spare seconds. The 4, 6 or 14 seconds are what absorbs a slow cycle. A cycle exactly at takt time breaks the first time anything varies.
  • Writing one time for work that varies. Where content changes with the order, the standard needs a rule for the range.
  • Drawing the chart and not counting the stock. Without the pieces marked, a wrong count is invisible.
  • Skipping the walk. In the electronics example walking is 12 of 94 seconds. Leave it out and the cycle reads 82 and looks far more comfortable than it is.
  • Writing it once and leaving it. Take a measured cycle from the floor every month. If it drifts, find out why before you change the paper.

Where software helps

The timing is the slow part. LeanSuite's Time and Motion Study drafts element times from a video of the station, on a timeline that links back to the footage, for you to check and certify. Standardized work software covers keeping the documents current and auditing them. The standard work combination table and process capacity sheet are free templates for drawing your own.

Standardized work software

Keep standard work current in LeanSuite

LeanSuite covers most of the cycle in one platform: working out the standard with Vision AI, keeping it current with SOPs and work instructions, and training and auditing it.

FAQ

Questions about standard work examples

  1. A packer at a pack bench who scans the tote, checks each order line, picks a carton, seals and labels it, then weighs it, always in that order, with each element timed and the cycle held under takt time. In the example here the cycle is 34 seconds plus 4 per order line against a 60 second takt time. The sequence, the seconds and the stock are written on one chart at the job.

  2. Takt time, work sequence and standard in-process stock. Takt time is the customer's pace and is calculated. The work sequence is the order and timing of the operator's steps. Standard in-process stock is the fewest pieces the process needs inside it to run without waiting. The Lean Enterprise Institute's Lean Lexicon names the same three elements.

  3. Three forms carry it. The process capacity sheet shows each machine's capacity and finds the limit. The combination table shows the operator and machines on a time line against takt time. The standard work chart shows the layout, walking path, stock and quality points. A time observation sheet comes first, and work instructions sit underneath for the hard elements.

  4. Split the work into fixed elements and elements that vary with the order, then time each part. At a pack bench, 34 seconds is fixed and each order line adds 4. Then state the range the standard covers. Under a 60 second takt time that is 6 lines. Orders above it go to a named route, so they do not break the standard.

  5. No. Standard work is a timed, repeating cycle for one operator at a station, balanced to takt time. An SOP describes how to carry out a broader activity and has no cycle or takt time. A changeover or a repair suits an SOP. A work instruction goes deeper still, into one element. Many jobs need more than one of the three.

  6. The people who do the job, led by the supervisor or an engineer who knows how to time it. An engineer alone writes a paper standard that the floor ignores. Time it with the operator, agree the sequence with them, and have them sign it. Then audit it against the real job at set intervals so it stays true.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.