New product introduction (NPI) in manufacturing: the industrial engineer's part

Short answer

New product introduction (NPI) is the gated process that takes a product from concept to stable volume production. The industrial engineer's part is to say how the product will be built, by how many people, on what layout, and at what rate, before each gate.

NPI runs through eight stages: concept, design for manufacture and assembly, process plan, prototype, pilot, production readiness, ramp and handover. Each ends at a gate. At every gate the industrial engineer brings the same seven things at a higher level of proof: the process flow, the work content, the takt and capacity plan, the line plan, the layout, the ergonomic checks and the standards. They start as estimates on paper and end as a measured, signed standard that production owns.

Last reviewed:

What NPI is, and what the industrial engineer does in it

Eight stages, eight gates: what the industrial engineer brings to each

  1. Gate 1

    Concept

    Work content range, takt, first headcount

    Estimated
  2. Gate 2

    Design for manufacture and assembly

    Design concerns in seconds and cost, estimate re-run

    Estimated
  3. Gate 3

    Process plan

    Process flow, stations, block layout, capacity plan

    Estimated
  4. Gate 4

    Prototype

    Bench timings, station mock-ups, reach and posture

    Timed off the line
  5. Gate 5

    Pilot

    Film of every station, first balance, ramp staffing

    Measured on the line
  6. Gate 6

    Production readiness

    Demonstrated rate, released instructions, trained operators

    Measured on the line
  7. Gate 7

    Ramp

    Output against plan, day 30 study, rebalance

    Measured on the line
  8. Gate 8

    Handover

    Day 90 study, locked standard, lessons learned

    Signed standard

Eight stages in order, each ending at a gate. 1, Concept: the industrial engineer brings work content range, takt, first headcount. Level of proof: estimated. 2, Design for manufacture and assembly: the industrial engineer brings design concerns in seconds and cost, estimate re-run. Level of proof: estimated. 3, Process plan: the industrial engineer brings process flow, stations, block layout, capacity plan. Level of proof: estimated. 4, Prototype: the industrial engineer brings bench timings, station mock-ups, reach and posture. Level of proof: timed off the line. 5, Pilot: the industrial engineer brings film of every station, first balance, ramp staffing. Level of proof: measured on the line. 6, Production readiness: the industrial engineer brings demonstrated rate, released instructions, trained operators. Level of proof: measured on the line. 7, Ramp: the industrial engineer brings output against plan, day 30 study, rebalance. Level of proof: measured on the line. 8, Handover: the industrial engineer brings day 90 study, locked standard, lessons learned. Level of proof: signed standard.

The questions do not change from gate to gate. The proof does: the four-step meter on each card fills as an estimate becomes a bench timing, then a film of the real line, then a signed standard.

New product introduction is how a company gets a product from an idea into steady production at the planned cost, quality and rate. It is run as a series of stages with a gate after each one. At a gate, the team shows evidence and a manager decides whether the project goes on, goes on with conditions, or waits.

People use NPI and new product development (NPD) loosely. Where a company separates them, NPD is the whole journey from market idea to finished design, and NPI is the part that puts the design into production. This page is about the second.

Program managers own the schedule. Design engineers own the product. Quality owns the control of it. The industrial engineer owns the work: what the people and stations will do, how long it takes, how many of each you need, where they stand, and whether a person can do the job all shift without being hurt. Nobody else at the gate review will answer those questions if you do not.

  • How will it be built? The process flow and the sequence of work.
  • How much work is in it? The work content, first estimated, later measured.
  • How fast must it go, and can it? Takt and the capacity plan.
  • How many people and stations? The line plan.
  • Where does everything go? The layout.
  • Can people do it safely all shift? The ergonomic checks.
  • What is the agreed way and time? The standards.

The eight stages and their gates

Companies name and count the stages differently. Five, six and eight are all common. The eight below are a fair picture of how a discrete manufacturer launches an assembled product, and they map onto the five phases of APQP if you work in automotive.

  1. 1

    Concept

    The product is a specification and a target cost. The gate asks whether it is worth quoting and roughly what it takes to make. You bring a first work content estimate and a first headcount.

  2. 2

    Design for manufacture and assembly

    The design is still soft. You review it for how it will be built: part count, fasteners, access, orientation, handling. Every change you win here is far cheaper than the same change after tooling.

  3. 3

    Process plan

    The design is firm enough to plan around. You write the process flow, split the work into stations, draw a block layout and fix the takt and capacity plan. Tooling and fixtures are ordered against it.

  4. 4

    Prototype

    The first units are built by hand. You time them, try the stations as mock-ups, and correct the plan with what real parts teach you.

  5. 5

    Pilot

    The real line runs for the first time with production tools, parts and operators. You film every station, balance the line and find where the learning curve starts.

  6. 6

    Production readiness

    A formal review before start of production. Everything the line needs is checked as present and proven: people trained, instructions released, capacity shown, open issues owned.

  7. 7

    Ramp

    Production starts below rate and climbs. You track output against the ramp plan, study the stations at about day 30, rebalance and release the extra labour when the times allow.

  8. 8

    Handover

    The line holds rate. You set the standard with a full time study, release final standard work, record the lessons, and production takes ownership.

The eight stages: the gate question and the nearest APQP phase
StageThe gate asksNearest APQP phase
1. ConceptIs it worth doing, and about what will it take?1. Plan and define the program
2. Design for manufacture and assemblyCan this design be built at the target cost?2. Product design and development
3. Process planDo we have a process worth buying tools for?3. Process design and development
4. PrototypeDid real parts confirm the plan?2 and 3. Prototype builds sit between them
5. PilotCan the real line make good parts?4. Product and process validation
6. Production readinessIs everything in place to start?4. Ends with the quality planning sign-off
7. RampAre we climbing as planned?5. Feedback, assessment and corrective action
8. HandoverIs it stable, and who owns it now?5. Continues for the life of the part

The APQP column is a guide, not a rule. The AIAG manual lists prototype builds under phase 2, and its phases overlap on purpose.

The eight stages against the five APQP phases and the timing studies

NPI stage

1
2
3
4
5
6
7
8

APQP phase

P1
P2
P3
P4
P5

Timing study

1
2
3
4, 5
6

Stages: 1 Concept · 2 DFMA · 3 Process plan · 4 Prototype · 5 Pilot · 6 Readiness · 7 Ramp · 8 Handover. Studies: 1 estimate · 2 prototype · 3 pilot · 4 launch week · 5 day 30 · 6 day 90.

Study 7, the re-study, follows every change after handover.

Three aligned rows. The eight stages: 1 Concept, 2 Design for manufacture and assembly, 3 Process plan, 4 Prototype, 5 Pilot, 6 Production readiness, 7 Ramp, 8 Handover. The APQP phases: phase 1, Plan and define, covers stage 1; phase 2, Product design, covers stage 2; phase 3, Process design, covers stages 3 and 4; phase 4, Validation, covers stages 5 and 6; phase 5, Feedback and corrective action, covers stages 7 and 8. The timing studies: Study 1: estimate at stages 1 and 2; Study 2: prototype at stage 4; Study 3: pilot at stage 5; Studies 4 and 5: launch week, day 30 at stage 7; Study 6: day 90 at stage 8. Study 7 follows every change after handover.

Read down any column: the stage, the APQP phase it sits in and the timing study that belongs there. Stages 3 and 6 have no study of their own. They use the numbers from the study before.

The industrial engineer's seven deliverables, gate by gate

You do not produce seven different things at eight gates. You produce the same seven things eight times, each time with better evidence. A work content figure is an estimate at concept, a bench timing at prototype, a film at pilot and a signed standard at handover. The skill is knowing how good each one has to be at each gate, and not polishing a number that is about to change.

IE deliverables at each gate
StageWhat the IE bringsLevel of proof
1. ConceptWork content estimate as a range. Takt from the quoted volume. First operator and station countEstimated from similar parts and predetermined times
2. Design for manufacture and assemblyDesign review notes: parts to combine, fasteners to remove, access and handling problems. Work content updated for each change. First posture and force concernsReasoned from the model, with the estimate re-run
3. Process planProcess flow. Work split into stations on paper. Block layout. Takt and capacity plan including machines and testers. Fixture and tool requirementsCalculated. Released for tooling
4. PrototypeElement times from bench builds. Mock-up of each station with reach and posture checked. Corrected work content and line planTimed on real parts, not on the real line
5. PilotVideo of every station. First real balance. Stop log. Ergonomic assessment on the real station. Draft standard work. Learning curve and ramp staffingMeasured on the real line, operators still learning
6. Production readinessCapacity shown against the launch volume. Work instructions released. Operators trained to them. Layout complete. Open issues with owners and datesDemonstrated and signed
7. RampOutput against the ramp plan. Day 30 study. Rebalance. Provisional standard. Ergonomic re-check after the rebalanceMeasured on practised operators
8. HandoverDay 90 time study. Locked standard time. Final standard work and balance. Lessons learned, including estimate against actualMeasured, reviewed with operators, signed by production and finance

The timing studies behind these rows are the seven in the [new product time study playbook](/learn/new-product-time-study-playbook).

Seven deliverables across eight gates: first draft, update, release

  • Process flow: Concept first draft, DFMA updated, Process plan released, Prototype updated, Pilot updated, Handover released

  • Work content · estimate, then measured: Concept first draft, DFMA updated, Prototype updated, Pilot updated, Readiness updated, Ramp updated, Handover released

  • Takt and capacity plan: Concept first draft, Process plan released, Prototype updated, Readiness updated, Handover released

  • Line plan · operators, stations, balance: Concept first draft, Process plan updated, Prototype updated, Pilot updated, Ramp updated, Handover released

  • Layout: Process plan first draft, Prototype updated, Pilot updated, Readiness released

  • Ergonomic checks: DFMA first draft, Prototype updated, Pilot updated, Ramp updated, Handover released

  • Standards · standard time and standard work: Pilot first draft, Readiness released, Ramp updated, Handover released

  • First draft
  • Updated
  • Released

1 Concept · 2 DFMA · 3 Process plan · 4 Prototype · 5 Pilot · 6 Readiness · 7 Ramp · 8 Handover

A grid of the seven industrial engineering deliverables against the eight stages. Process flow, work content, the takt and capacity plan and the line plan start at concept. Ergonomic checks start at the design review. Layout starts at the process plan. Standards start at the pilot. Everything is released in its final form by handover.

Each line starts where the first draft is due and ends where the final version is released. Four of the seven start at gate 1, long before there is anything to measure. Standards start latest, because they need a running line.

The seven, one at a time

The takt and capacity plan, worked

Of the seven, this is the one a gate review leans on hardest, because it turns a volume into people and equipment. It is a short chain of divisions. The example is a made-up coolant pump, the CP-40, at the process plan gate.

Illustrative: the CP-40 takt and capacity plan at the process plan gate
StepCalculationResult
DemandFrom the quoted volume225 pumps a day
Available timeOne shift of 450 minutes after breaks27,000 s
Takt time27,000 / 225120 s
Work contentEstimate, standard time482 s (range 430 to 562)
Operators482 / 120 = 4.01, rounded up5
Average station cycle482 / 596 s, 80% of takt
Tester cycle45 s handling + 45 s machine90 s
Tester capacity27,000 / 90300 a day, 75% used at 225

Capacity here is before downtime and scrap. Add your own availability and yield figures before you commit to one tester.

The takt and capacity plan as one chain

Example numbers
  1. Demand

    225 a day

    In 27,000 s: one 450 minute shift.

  2. Takt

    120 s

    27,000 / 225.

  3. Work content

    482 s

    430 to 562 s

    Standard time, estimated.

  4. Operators

    5

    482 / 120 = 4.02, rounded up.

Average station96 s of 120 s takt · 80%
Tester90 s of 120 s takt · 75%

The vertical line is takt. Tester capacity: 27,000 / 90 = 300 a day, so 225 a day uses 75% of it, before downtime and scrap.

A chain of calculations. Demand 225 a day and 27,000 seconds available give a takt of 120 seconds. Work content of 482 seconds divided by takt is 4.02, so 5 operators. The average station is 96 seconds. The tester cycle is 90 seconds, so it can test 300 a day.

People and machines are checked against the same takt line. The average station uses 80% of it and the tester 75%. Any bar that crosses the line means another operator, another machine or a shorter job.

Two things in that table are worth saying out loud at the gate. The work content is a range, and at its top end (562 seconds) five operators would be 94 percent loaded, which leaves little room for an uneven balance. And the plan has to be checked for every resource, not only the people. Here the single tester has room. If the test ran 90 seconds instead of 45, its cycle would be 135 seconds, over takt, and the line would need a second tester however well the operators were balanced.

The plan describes steady state. The first weeks need their own version, because new operators take longer. In the playbook's example the same line needed six operators for about its first six weeks.

Why the early gates matter most: front loading

A design problem costs little to fix while it is a line on a drawing. The same problem costs a tool change once the mould is cut, and a containment action once parts are shipping. Programmes that launch well find most of their problems in the first three stages. Programmes that launch badly find them at the pilot. Moving that discovery earlier is called front loading.

Front loading: the same problems, found at a different stage

Before: found at the pilot

Before: problems found at the pilotA schematic curve of problems found by stage. It is low through the design stages, peaks at the pilot and stays high into the ramp.Tooling orderedLaunch12345678Stage

The industrial engineer first sees the design after release.

After: found in the design reviews

After: problems found in the design reviewsA schematic curve of problems found by stage. It peaks at stages 2 and 3, before tooling is ordered, and is low from the pilot on.Tooling orderedLaunch12345678Stage

Production, quality and the IE review the design at gates 1 to 3.

Two schematic curves of problems found by stage. Before: few problems are found in the design stages and most appear at the pilot and during the ramp, after tooling is ordered. After front loading: most problems are found at stages 2 and 3, before tooling is ordered, and few remain at the pilot.

Shape only, no scale: the curves show when problems surface, not how many. Left of the first dashed line a fix is a drawing change. Between the lines it is a tooling change. Right of the second it reaches the customer.

For an industrial engineer, front loading means three habits. Sit in the design reviews, not only the process ones. Bring the last launch's problems as a checklist, so the same awkward fastener is not designed in twice. And turn every concern into a number the design team can weigh: 14 seconds a unit and one more operator is an argument, while a remark that something looks hard to assemble is not.

The aim has a name in TPM plants: vertical start-up. It means the line reaches its planned rate and quality almost as soon as it starts, because the problems were designed out instead of found on the floor. Few launches are truly vertical, but it is the right target to measure a ramp against.

Design for manufacture and assembly in practice

  • Count parts and ask of each one whether it has to be separate. Boothroyd and Dewhurst's test: does it move relative to its neighbours, must it be a different material, or must it come apart for assembly or service? If none applies, it is a candidate to combine.
  • Count fasteners and types. Every screw is an element, and every extra type is another tool and another bin.
  • Look for one assembly direction, ideally straight down, so the unit is not turned over between steps.
  • Look for parts that can go in the wrong way round. Ask for them to be symmetrical, or so obviously asymmetrical that they cannot be misfitted.
  • Check access for hands and tools at each step in the order the build will happen.
  • Flag anything flexible: cables, hoses, seals, gaskets. They are slow to handle and hard to estimate.

Who signs what

Sign-off rules belong to your company's procedure, and in regulated industries to your customer and your standard. The table is a common split in a discrete manufacturing plant. Use it to check that every deliverable has one name on it.

A typical sign-off split for the IE deliverables
DeliverablePrepared byReviewed withApproved by
Work content estimate and rangeIndustrial engineerDesign engineerProgram manager, for the quote
Process flowProcess or industrial engineerQuality, productionEngineering manager
Takt and capacity planIndustrial engineerPlanning, financeOperations manager
Line plan and balanceIndustrial engineerSupervisor, operatorsProduction manager
LayoutIndustrial engineerSafety, maintenance, materialsOperations manager
Ergonomic assessmentIndustrial engineer or ergonomistSafety, operatorsEHS manager
Work instructions and standard workProcess or industrial engineerOperators, trainer, qualityProduction manager
Standard timeIndustrial engineerOperators, supervisorProduction and finance
Production readiness reviewProgram managerEvery functionPlant manager

The PFMEA and control plan are led by quality or process engineering in most plants. The IE supplies the process steps and the time each check takes.

Gate checklist for the industrial engineer

Take this into each gate review. A gate passes on evidence, so each line asks for something you can show.

IE gate checklist
GateShow thisIt is not ready if
1. ConceptWork content as a range with its basis. Takt at the quoted volume. Operator count at the low and high endThere is one number and no assumptions
2. Design for manufacture and assemblyList of design concerns, each with seconds and cost. Which were accepted. Re-run estimateThe IE first saw the design after release
3. Process planProcess flow. Stations with their elements and times. Block layout. Capacity check for every machine and tester. Tool and fixture listA resource has no capacity line, or a station is planned above takt
4. PrototypeElement times from the builds against the estimate. Mock-up photos with reach and posture findings. Updated planNobody timed the builds
5. PilotStation times from video. Balance chart against takt. Stop log with causes. Ergonomic scores. Learning curve and ramp headcountThe pilot ran on prototype tools or with engineers building
6. Production readinessDemonstrated rate against the launch plan. Released instructions. Training records. Open issues with owner and dateOpen issues have no owner, or operators have not built a unit
7. RampWeekly output against plan. Day 30 study. Rebalance done. Labour release decision with the numbers behind itExtra labour is leaving by the calendar, not by the study
8. HandoverDay 90 study. Signed standard. Final standard work. Estimate against actual. Lessons fed into the design checklistThe standard is still the quote estimate

For the whole launch across functions, see the [APQP checklist](/templates/apqp-checklist) and the [PPAP checklist](/templates/ppap-checklist).

Common failure modes

How NPI goes wrong on the IE side, and the early sign
FailureEarly signWhat to do
The IE joins after design releaseFirst design review invitation arrives with tooling dates on itAsk for a seat at concept, and bring the last launch's problem list
The quote estimate becomes the standardNobody can say when the standard will be setPut the day 90 study in the programme plan as a deliverable
Capacity is checked for people onlyThe tester, oven or press has no line in the planAdd a capacity line for every resource, with its cycle against takt
The pilot is run by engineersOperators first touch the product in launch weekInsist on production operators, and film them
Ergonomics is left to the first complaintNo posture or force check before the pilotCheck the mock-up at prototype and assess the real station at pilot
Ramp labour is not plannedThe headcount is one number from day oneDraw the learning curve after the pilot and staff the ramp from it
Documents drift apartThe work instruction and the PFMEA list different stepsOne process flow, and a change to it reopens the rest
Lessons are not carried forwardThe same design problem appears on the next productClose each launch by updating the design review checklist

There is a people side to every row. Operators and supervisors who meet the product at the pilot will run it for years. Bring them in at the mock-up, ask what is awkward, and say plainly that nothing timed before day 90 is a judgement of anyone's pace. A line that its operators helped design starts faster, and they will tell you what is wrong with it while it can still be fixed.

Tools and related guides

From the pilot onward, most of the IE's evidence is video. In LeanSuite's time and motion study you film a station on a phone, the AI times every element and cycle, and you review and certify the study. Studies are kept under their process, so the pilot, day 30 and day 90 studies of a station sit together. The same footage can go through AI video analysis for a line balance and for REBA and RULA scores, which covers three of the seven deliverables from one filming session. It analyses video you upload, so the estimates at the first three gates are still yours to make.

Free templates and tools

FAQ

Questions about new product introduction for industrial engineers

  1. New product introduction is the gated process that takes a product from concept into stable volume production. It runs through stages such as concept, design for manufacture, process planning, prototype, pilot, production readiness, ramp and handover. At each gate the team shows evidence that the product can be built at the planned cost, quality and rate before more money is committed.

  2. The industrial engineer plans the work. That means the process flow, the work content in each unit, takt time and capacity, the number of operators and stations, the layout, the ergonomic checks and finally the standard time and standard work. Each starts as an estimate at the concept gate and ends as a measured, signed standard at handover.

  3. A common set is eight: concept, design for manufacture and assembly, process plan, prototype, pilot, production readiness, ramp and handover. Companies name and count them differently, and automotive suppliers follow the five phases of APQP. What they share is a gate after each stage where evidence is reviewed before the next one starts.

  4. The terms overlap and many companies use them as one. Where they are kept apart, new product development (NPD) is the whole journey from a market idea to a finished design, and new product introduction (NPI) is the part that takes the design into production: process planning, tooling, pilot builds, launch and ramp to full rate.

  5. APQP is the automotive industry's version of a gated launch, written by AIAG, with five phases and a defined set of quality documents. NPI is the general term used in every industry. The stages line up closely: concept with phase 1, design with phase 2, process planning with phase 3, pilot and readiness with phase 4, ramp and handover with phase 5.

  6. It is the formal check before start of production that everything the line needs is in place and proven: tooling and gauges, trained operators, released work instructions, material supply, demonstrated capacity and a list of open issues with owners and dates. The industrial engineer shows the demonstrated rate, the line balance and the ramp staffing plan.

  7. DFMA is reviewing a design for how it will be made and put together while it can still be changed cheaply. Design for assembly looks at part count, fasteners, handling and insertion. Design for manufacture looks at how each part is produced. The usual wins are fewer parts, fewer fastener types, one assembly direction and parts that cannot be fitted wrongly.

  8. Front loading means finding and fixing problems in the early stages of a launch, when a change is a line on a drawing, instead of at the pilot or after start of production, when it means new tooling. In practice it puts production, quality and industrial engineering into the design reviews and uses the problems of past launches as a checklist.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?