Method guide · Standard work, SOPs and training
New product introduction (NPI) in manufacturing: the industrial engineer's part
Short answer
New product introduction (NPI) is the gated process that takes a product from concept to stable volume production. The industrial engineer's part is to say how the product will be built, by how many people, on what layout, and at what rate, before each gate.
NPI runs through eight stages: concept, design for manufacture and assembly, process plan, prototype, pilot, production readiness, ramp and handover. Each ends at a gate. At every gate the industrial engineer brings the same seven things at a higher level of proof: the process flow, the work content, the takt and capacity plan, the line plan, the layout, the ergonomic checks and the standards. They start as estimates on paper and end as a measured, signed standard that production owns.
Last reviewed:
What NPI is, and what the industrial engineer does in it
Eight stages, eight gates: what the industrial engineer brings to each
- Gate 1
Concept
Work content range, takt, first headcount
Estimated - Gate 2
Design for manufacture and assembly
Design concerns in seconds and cost, estimate re-run
Estimated - Gate 3
Process plan
Process flow, stations, block layout, capacity plan
Estimated - Gate 4
Prototype
Bench timings, station mock-ups, reach and posture
Timed off the line - Gate 5
Pilot
Film of every station, first balance, ramp staffing
Measured on the line - Gate 6
Production readiness
Demonstrated rate, released instructions, trained operators
Measured on the line - Gate 7
Ramp
Output against plan, day 30 study, rebalance
Measured on the line - Gate 8
Handover
Day 90 study, locked standard, lessons learned
Signed standard
Eight stages in order, each ending at a gate. 1, Concept: the industrial engineer brings work content range, takt, first headcount. Level of proof: estimated. 2, Design for manufacture and assembly: the industrial engineer brings design concerns in seconds and cost, estimate re-run. Level of proof: estimated. 3, Process plan: the industrial engineer brings process flow, stations, block layout, capacity plan. Level of proof: estimated. 4, Prototype: the industrial engineer brings bench timings, station mock-ups, reach and posture. Level of proof: timed off the line. 5, Pilot: the industrial engineer brings film of every station, first balance, ramp staffing. Level of proof: measured on the line. 6, Production readiness: the industrial engineer brings demonstrated rate, released instructions, trained operators. Level of proof: measured on the line. 7, Ramp: the industrial engineer brings output against plan, day 30 study, rebalance. Level of proof: measured on the line. 8, Handover: the industrial engineer brings day 90 study, locked standard, lessons learned. Level of proof: signed standard.
New product introduction is how a company gets a product from an idea into steady production at the planned cost, quality and rate. It is run as a series of stages with a gate after each one. At a gate, the team shows evidence and a manager decides whether the project goes on, goes on with conditions, or waits.
People use NPI and new product development (NPD) loosely. Where a company separates them, NPD is the whole journey from market idea to finished design, and NPI is the part that puts the design into production. This page is about the second.
Program managers own the schedule. Design engineers own the product. Quality owns the control of it. The industrial engineer owns the work: what the people and stations will do, how long it takes, how many of each you need, where they stand, and whether a person can do the job all shift without being hurt. Nobody else at the gate review will answer those questions if you do not.
- How will it be built? The process flow and the sequence of work.
- How much work is in it? The work content, first estimated, later measured.
- How fast must it go, and can it? Takt and the capacity plan.
- How many people and stations? The line plan.
- Where does everything go? The layout.
- Can people do it safely all shift? The ergonomic checks.
- What is the agreed way and time? The standards.
The eight stages and their gates
Companies name and count the stages differently. Five, six and eight are all common. The eight below are a fair picture of how a discrete manufacturer launches an assembled product, and they map onto the five phases of APQP if you work in automotive.
- 1
Concept
The product is a specification and a target cost. The gate asks whether it is worth quoting and roughly what it takes to make. You bring a first work content estimate and a first headcount.
- 2
Design for manufacture and assembly
The design is still soft. You review it for how it will be built: part count, fasteners, access, orientation, handling. Every change you win here is far cheaper than the same change after tooling.
- 3
Process plan
The design is firm enough to plan around. You write the process flow, split the work into stations, draw a block layout and fix the takt and capacity plan. Tooling and fixtures are ordered against it.
- 4
Prototype
The first units are built by hand. You time them, try the stations as mock-ups, and correct the plan with what real parts teach you.
- 5
Pilot
The real line runs for the first time with production tools, parts and operators. You film every station, balance the line and find where the learning curve starts.
- 6
Production readiness
A formal review before start of production. Everything the line needs is checked as present and proven: people trained, instructions released, capacity shown, open issues owned.
- 7
Ramp
Production starts below rate and climbs. You track output against the ramp plan, study the stations at about day 30, rebalance and release the extra labour when the times allow.
- 8
Handover
The line holds rate. You set the standard with a full time study, release final standard work, record the lessons, and production takes ownership.
| Stage | The gate asks | Nearest APQP phase |
|---|---|---|
| 1. Concept | Is it worth doing, and about what will it take? | 1. Plan and define the program |
| 2. Design for manufacture and assembly | Can this design be built at the target cost? | 2. Product design and development |
| 3. Process plan | Do we have a process worth buying tools for? | 3. Process design and development |
| 4. Prototype | Did real parts confirm the plan? | 2 and 3. Prototype builds sit between them |
| 5. Pilot | Can the real line make good parts? | 4. Product and process validation |
| 6. Production readiness | Is everything in place to start? | 4. Ends with the quality planning sign-off |
| 7. Ramp | Are we climbing as planned? | 5. Feedback, assessment and corrective action |
| 8. Handover | Is it stable, and who owns it now? | 5. Continues for the life of the part |
The APQP column is a guide, not a rule. The AIAG manual lists prototype builds under phase 2, and its phases overlap on purpose.
The eight stages against the five APQP phases and the timing studies
NPI stage
APQP phase
Timing study
Stages: 1 Concept · 2 DFMA · 3 Process plan · 4 Prototype · 5 Pilot · 6 Readiness · 7 Ramp · 8 Handover. Studies: 1 estimate · 2 prototype · 3 pilot · 4 launch week · 5 day 30 · 6 day 90.
Study 7, the re-study, follows every change after handover.
Three aligned rows. The eight stages: 1 Concept, 2 Design for manufacture and assembly, 3 Process plan, 4 Prototype, 5 Pilot, 6 Production readiness, 7 Ramp, 8 Handover. The APQP phases: phase 1, Plan and define, covers stage 1; phase 2, Product design, covers stage 2; phase 3, Process design, covers stages 3 and 4; phase 4, Validation, covers stages 5 and 6; phase 5, Feedback and corrective action, covers stages 7 and 8. The timing studies: Study 1: estimate at stages 1 and 2; Study 2: prototype at stage 4; Study 3: pilot at stage 5; Studies 4 and 5: launch week, day 30 at stage 7; Study 6: day 90 at stage 8. Study 7 follows every change after handover.
The industrial engineer's seven deliverables, gate by gate
You do not produce seven different things at eight gates. You produce the same seven things eight times, each time with better evidence. A work content figure is an estimate at concept, a bench timing at prototype, a film at pilot and a signed standard at handover. The skill is knowing how good each one has to be at each gate, and not polishing a number that is about to change.
| Stage | What the IE brings | Level of proof |
|---|---|---|
| 1. Concept | Work content estimate as a range. Takt from the quoted volume. First operator and station count | Estimated from similar parts and predetermined times |
| 2. Design for manufacture and assembly | Design review notes: parts to combine, fasteners to remove, access and handling problems. Work content updated for each change. First posture and force concerns | Reasoned from the model, with the estimate re-run |
| 3. Process plan | Process flow. Work split into stations on paper. Block layout. Takt and capacity plan including machines and testers. Fixture and tool requirements | Calculated. Released for tooling |
| 4. Prototype | Element times from bench builds. Mock-up of each station with reach and posture checked. Corrected work content and line plan | Timed on real parts, not on the real line |
| 5. Pilot | Video of every station. First real balance. Stop log. Ergonomic assessment on the real station. Draft standard work. Learning curve and ramp staffing | Measured on the real line, operators still learning |
| 6. Production readiness | Capacity shown against the launch volume. Work instructions released. Operators trained to them. Layout complete. Open issues with owners and dates | Demonstrated and signed |
| 7. Ramp | Output against the ramp plan. Day 30 study. Rebalance. Provisional standard. Ergonomic re-check after the rebalance | Measured on practised operators |
| 8. Handover | Day 90 time study. Locked standard time. Final standard work and balance. Lessons learned, including estimate against actual | Measured, reviewed with operators, signed by production and finance |
The timing studies behind these rows are the seven in the [new product time study playbook](/learn/new-product-time-study-playbook).
Seven deliverables across eight gates: first draft, update, release
Process flow: Concept first draft, DFMA updated, Process plan released, Prototype updated, Pilot updated, Handover released
Work content · estimate, then measured: Concept first draft, DFMA updated, Prototype updated, Pilot updated, Readiness updated, Ramp updated, Handover released
Takt and capacity plan: Concept first draft, Process plan released, Prototype updated, Readiness updated, Handover released
Line plan · operators, stations, balance: Concept first draft, Process plan updated, Prototype updated, Pilot updated, Ramp updated, Handover released
Layout: Process plan first draft, Prototype updated, Pilot updated, Readiness released
Ergonomic checks: DFMA first draft, Prototype updated, Pilot updated, Ramp updated, Handover released
Standards · standard time and standard work: Pilot first draft, Readiness released, Ramp updated, Handover released
- First draft
- Updated
- Released
1 Concept · 2 DFMA · 3 Process plan · 4 Prototype · 5 Pilot · 6 Readiness · 7 Ramp · 8 Handover
A grid of the seven industrial engineering deliverables against the eight stages. Process flow, work content, the takt and capacity plan and the line plan start at concept. Ergonomic checks start at the design review. Layout starts at the process plan. Standards start at the pilot. Everything is released in its final form by handover.
The seven, one at a time
- Process flow: every step in order, including moves, checks and rework loops. It is the spine the PFMEA, the control plan and the work instructions hang from. See process planning for a new product and the process flow diagram template.
- Work content: total manual time in one unit. See how to estimate cycle time for a new product.
- Takt and capacity plan: demand turned into a pace, and a check that people, machines and testers can each hold it. See takt time.
- Line plan: operators, stations and which elements each station does. See planning operators and stations for a new line and line balancing.
- Layout: where stations, parts and people go, and how material arrives. See workstation design.
- Ergonomic checks: reach, posture, force and repetition at every station. See ergonomic assessment in manufacturing.
- Standards: the standard time and the standard work that goes with it.
The takt and capacity plan, worked
Of the seven, this is the one a gate review leans on hardest, because it turns a volume into people and equipment. It is a short chain of divisions. The example is a made-up coolant pump, the CP-40, at the process plan gate.
| Step | Calculation | Result |
|---|---|---|
| Demand | From the quoted volume | 225 pumps a day |
| Available time | One shift of 450 minutes after breaks | 27,000 s |
| Takt time | 27,000 / 225 | 120 s |
| Work content | Estimate, standard time | 482 s (range 430 to 562) |
| Operators | 482 / 120 = 4.01, rounded up | 5 |
| Average station cycle | 482 / 5 | 96 s, 80% of takt |
| Tester cycle | 45 s handling + 45 s machine | 90 s |
| Tester capacity | 27,000 / 90 | 300 a day, 75% used at 225 |
Capacity here is before downtime and scrap. Add your own availability and yield figures before you commit to one tester.
The takt and capacity plan as one chain
Example numbers- Demand
225 a day
In 27,000 s: one 450 minute shift.
- Takt
120 s
27,000 / 225.
- Work content
482 s
430 to 562 s
Standard time, estimated.
- Operators
5
482 / 120 = 4.02, rounded up.
The vertical line is takt. Tester capacity: 27,000 / 90 = 300 a day, so 225 a day uses 75% of it, before downtime and scrap.
A chain of calculations. Demand 225 a day and 27,000 seconds available give a takt of 120 seconds. Work content of 482 seconds divided by takt is 4.02, so 5 operators. The average station is 96 seconds. The tester cycle is 90 seconds, so it can test 300 a day.
Two things in that table are worth saying out loud at the gate. The work content is a range, and at its top end (562 seconds) five operators would be 94 percent loaded, which leaves little room for an uneven balance. And the plan has to be checked for every resource, not only the people. Here the single tester has room. If the test ran 90 seconds instead of 45, its cycle would be 135 seconds, over takt, and the line would need a second tester however well the operators were balanced.
The plan describes steady state. The first weeks need their own version, because new operators take longer. In the playbook's example the same line needed six operators for about its first six weeks.
Why the early gates matter most: front loading
A design problem costs little to fix while it is a line on a drawing. The same problem costs a tool change once the mould is cut, and a containment action once parts are shipping. Programmes that launch well find most of their problems in the first three stages. Programmes that launch badly find them at the pilot. Moving that discovery earlier is called front loading.
Front loading: the same problems, found at a different stage
Before: found at the pilot
The industrial engineer first sees the design after release.
After: found in the design reviews
Production, quality and the IE review the design at gates 1 to 3.
Two schematic curves of problems found by stage. Before: few problems are found in the design stages and most appear at the pilot and during the ramp, after tooling is ordered. After front loading: most problems are found at stages 2 and 3, before tooling is ordered, and few remain at the pilot.
For an industrial engineer, front loading means three habits. Sit in the design reviews, not only the process ones. Bring the last launch's problems as a checklist, so the same awkward fastener is not designed in twice. And turn every concern into a number the design team can weigh: 14 seconds a unit and one more operator is an argument, while a remark that something looks hard to assemble is not.
The aim has a name in TPM plants: vertical start-up. It means the line reaches its planned rate and quality almost as soon as it starts, because the problems were designed out instead of found on the floor. Few launches are truly vertical, but it is the right target to measure a ramp against.
Design for manufacture and assembly in practice
- Count parts and ask of each one whether it has to be separate. Boothroyd and Dewhurst's test: does it move relative to its neighbours, must it be a different material, or must it come apart for assembly or service? If none applies, it is a candidate to combine.
- Count fasteners and types. Every screw is an element, and every extra type is another tool and another bin.
- Look for one assembly direction, ideally straight down, so the unit is not turned over between steps.
- Look for parts that can go in the wrong way round. Ask for them to be symmetrical, or so obviously asymmetrical that they cannot be misfitted.
- Check access for hands and tools at each step in the order the build will happen.
- Flag anything flexible: cables, hoses, seals, gaskets. They are slow to handle and hard to estimate.
Who signs what
Sign-off rules belong to your company's procedure, and in regulated industries to your customer and your standard. The table is a common split in a discrete manufacturing plant. Use it to check that every deliverable has one name on it.
| Deliverable | Prepared by | Reviewed with | Approved by |
|---|---|---|---|
| Work content estimate and range | Industrial engineer | Design engineer | Program manager, for the quote |
| Process flow | Process or industrial engineer | Quality, production | Engineering manager |
| Takt and capacity plan | Industrial engineer | Planning, finance | Operations manager |
| Line plan and balance | Industrial engineer | Supervisor, operators | Production manager |
| Layout | Industrial engineer | Safety, maintenance, materials | Operations manager |
| Ergonomic assessment | Industrial engineer or ergonomist | Safety, operators | EHS manager |
| Work instructions and standard work | Process or industrial engineer | Operators, trainer, quality | Production manager |
| Standard time | Industrial engineer | Operators, supervisor | Production and finance |
| Production readiness review | Program manager | Every function | Plant manager |
The PFMEA and control plan are led by quality or process engineering in most plants. The IE supplies the process steps and the time each check takes.
Gate checklist for the industrial engineer
Take this into each gate review. A gate passes on evidence, so each line asks for something you can show.
| Gate | Show this | It is not ready if |
|---|---|---|
| 1. Concept | Work content as a range with its basis. Takt at the quoted volume. Operator count at the low and high end | There is one number and no assumptions |
| 2. Design for manufacture and assembly | List of design concerns, each with seconds and cost. Which were accepted. Re-run estimate | The IE first saw the design after release |
| 3. Process plan | Process flow. Stations with their elements and times. Block layout. Capacity check for every machine and tester. Tool and fixture list | A resource has no capacity line, or a station is planned above takt |
| 4. Prototype | Element times from the builds against the estimate. Mock-up photos with reach and posture findings. Updated plan | Nobody timed the builds |
| 5. Pilot | Station times from video. Balance chart against takt. Stop log with causes. Ergonomic scores. Learning curve and ramp headcount | The pilot ran on prototype tools or with engineers building |
| 6. Production readiness | Demonstrated rate against the launch plan. Released instructions. Training records. Open issues with owner and date | Open issues have no owner, or operators have not built a unit |
| 7. Ramp | Weekly output against plan. Day 30 study. Rebalance done. Labour release decision with the numbers behind it | Extra labour is leaving by the calendar, not by the study |
| 8. Handover | Day 90 study. Signed standard. Final standard work. Estimate against actual. Lessons fed into the design checklist | The standard is still the quote estimate |
For the whole launch across functions, see the [APQP checklist](/templates/apqp-checklist) and the [PPAP checklist](/templates/ppap-checklist).
Common failure modes
| Failure | Early sign | What to do |
|---|---|---|
| The IE joins after design release | First design review invitation arrives with tooling dates on it | Ask for a seat at concept, and bring the last launch's problem list |
| The quote estimate becomes the standard | Nobody can say when the standard will be set | Put the day 90 study in the programme plan as a deliverable |
| Capacity is checked for people only | The tester, oven or press has no line in the plan | Add a capacity line for every resource, with its cycle against takt |
| The pilot is run by engineers | Operators first touch the product in launch week | Insist on production operators, and film them |
| Ergonomics is left to the first complaint | No posture or force check before the pilot | Check the mock-up at prototype and assess the real station at pilot |
| Ramp labour is not planned | The headcount is one number from day one | Draw the learning curve after the pilot and staff the ramp from it |
| Documents drift apart | The work instruction and the PFMEA list different steps | One process flow, and a change to it reopens the rest |
| Lessons are not carried forward | The same design problem appears on the next product | Close each launch by updating the design review checklist |
There is a people side to every row. Operators and supervisors who meet the product at the pilot will run it for years. Bring them in at the mock-up, ask what is awkward, and say plainly that nothing timed before day 90 is a judgement of anyone's pace. A line that its operators helped design starts faster, and they will tell you what is wrong with it while it can still be fixed.
Tools and related guides
From the pilot onward, most of the IE's evidence is video. In LeanSuite's time and motion study you film a station on a phone, the AI times every element and cycle, and you review and certify the study. Studies are kept under their process, so the pilot, day 30 and day 90 studies of a station sit together. The same footage can go through AI video analysis for a line balance and for REBA and RULA scores, which covers three of the seven deliverables from one filming session. It analyses video you upload, so the estimates at the first three gates are still yours to make.
- The new product time study playbook: the seven timing studies across these gates.
- How to estimate cycle time for a new product: the concept gate estimate, worked.
- Pilot run and line trial and ramp-up and the learning curve.
- APQP and FMEA: the quality planning the IE deliverables feed.
- Designing a future workstation and time study and ergonomic study in one pass.
- Templates: process flow diagram, operator staffing calculator, process capacity sheet, ergonomic risk assessment checklist, learning curve workbook.
Go deeper
This page is the short version. These guides cover each part in full.
- FMEA in Manufacturing: Failure Mode and Effects Analysis Complete GuideThe PFMEA that is built on the IE's process flow.
- Cell Design for JIT Flow: Step-by-Step Layout PlanningLaying out the cell at the process plan gate.
- Takt Time in JIT: Matching Production to DemandTakt, the first number in the capacity plan.
- Visual Work Instructions: Effective DocumentationWriting the instructions that must be released before production readiness.
All our articles on this subject are in the standard work, sops and training topic.
Free templates and tools
- APQP checklistThe five APQP phases as a checklist: deliverables, owners, due dates, gate reviews and an issues list.
- Process flow diagram templateA squared sheet to draw the flow with a symbol key, and a step table that counts operations, moves, checks, waits and storage.
- Operator staffing calculatorTakt, work content, the operators a line needs, a check of your station plan and the roster with absence cover, from your own demand and element times.
- Process capacity sheet templateEach machine in a part's routing with manual, auto and tool change time, its capacity per shift, and the step that limits the cell against demand.
- Ergonomic risk assessment checklistScreen a task for 21 ergonomic risk factors, score how long each lasts, and rank tasks so the worst get controls first.
- Learning curve and ramp-up workbookBoth learning curve models side by side, a fit from your own observed hours, batch hours, the unit that reaches standard and a weekly ramp plan.
- Takt time calculatorThe pace a line must hit to meet customer demand, from shift time, breaks and daily demand.
- Line balancing calculatorLine efficiency, balance delay and the minimum number of stations from station times and takt.
- Standard time calculatorObserved times, a rating and an allowance in; normal time, standard time, units per hour, pieces per shift and labour cost per unit out, with the working.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
Doing this in LeanSuite
Time and Motion Study
Film a station on a phone at the pilot, at day 30 and at day 90. LeanSuite times every element and keeps each study under its process.
See Time and Motion StudyAI Video Analysis
One process video gives time and motion, line balancing and ergonomic studies to review and certify.
See AI Video AnalysisErgonomic Study
REBA and RULA scores from video, by body region and task element.
See Ergonomic Study
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about new product introduction for industrial engineers
New product introduction is the gated process that takes a product from concept into stable volume production. It runs through stages such as concept, design for manufacture, process planning, prototype, pilot, production readiness, ramp and handover. At each gate the team shows evidence that the product can be built at the planned cost, quality and rate before more money is committed.
The industrial engineer plans the work. That means the process flow, the work content in each unit, takt time and capacity, the number of operators and stations, the layout, the ergonomic checks and finally the standard time and standard work. Each starts as an estimate at the concept gate and ends as a measured, signed standard at handover.
A common set is eight: concept, design for manufacture and assembly, process plan, prototype, pilot, production readiness, ramp and handover. Companies name and count them differently, and automotive suppliers follow the five phases of APQP. What they share is a gate after each stage where evidence is reviewed before the next one starts.
The terms overlap and many companies use them as one. Where they are kept apart, new product development (NPD) is the whole journey from a market idea to a finished design, and new product introduction (NPI) is the part that takes the design into production: process planning, tooling, pilot builds, launch and ramp to full rate.
APQP is the automotive industry's version of a gated launch, written by AIAG, with five phases and a defined set of quality documents. NPI is the general term used in every industry. The stages line up closely: concept with phase 1, design with phase 2, process planning with phase 3, pilot and readiness with phase 4, ramp and handover with phase 5.
It is the formal check before start of production that everything the line needs is in place and proven: tooling and gauges, trained operators, released work instructions, material supply, demonstrated capacity and a list of open issues with owners and dates. The industrial engineer shows the demonstrated rate, the line balance and the ramp staffing plan.
DFMA is reviewing a design for how it will be made and put together while it can still be changed cheaply. Design for assembly looks at part count, fasteners, handling and insertion. Design for manufacture looks at how each part is produced. The usual wins are fewer parts, fewer fastener types, one assembly direction and parts that cannot be fitted wrongly.
Front loading means finding and fixing problems in the early stages of a launch, when a change is a line on a drawing, instead of at the pilot or after start of production, when it means new tooling. In practice it puts production, quality and industrial engineering into the design reviews and uses the problems of past launches as a checklist.
Related guides and tools
- The new product time study playbook: seven studies from quote to steady state
- How to estimate cycle time for a new product, with a worked example
- APQP: the five phases, the gates and APQP vs PPAP
- FMEA: how the process steps become a PFMEA
- Process planning for a new product: routing, work content, stations
- Planning operators and stations for a new line
- Pilot run and line trial: what to time and what to record
- Workstation design: reach, posture and layout
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk