Practical guide · Safety management
Job safety analysis from video: one study, three outputs
Short answer
A time study, a job safety analysis and an ergonomic assessment all start by filming a job and splitting it into steps. Film once, break the job down once, and write seconds, hazards and posture scores on one sheet. The steps that are slow, risky and awkward at once show up side by side.
Film at least ten cycles of the job with the whole body, the hands and the danger zones in frame, and tell the operator why. Break the cycle into elements, splitting wherever the hazard changes as well as where the timing does. Add the irregular elements a short film misses, such as clearing a jam. For each element record the seconds and the value class, the hazard with its severity times likelihood and today's control, and the worst posture score. Read across each row: an element that is waste, high risk and a bad posture is the first to change. Choose the change from the top of the hierarchy of controls, then film and score all three again. The team writes the JSA with the operator. Video is the evidence for it and cannot replace that conversation. This is general guidance, and rules on risk assessment and on filming people differ by country.
Last reviewed:
One video, one job breakdown, three studies
Three people study the same workstation for three reasons. The industrial engineer runs a time study to set a standard and find wasted seconds. The safety lead writes a job safety analysis, a JSA, to list what could hurt someone at each step and what stops it. The ergonomist, or whoever has the worksheet, scores the postures with REBA or RULA. Look at how each one starts: watch the job, split it into steps, write something against every step.
That shared start is the whole idea of this guide. Film the job once. Break it into elements once. Then give every element three readings: how long it takes and whether it adds value, what the hazard is and how big the risk, and how hard the posture is on the body. One sheet holds all three, and the three studies stop contradicting each other.
One film, one element list, three readings
Example numbers1. Film the job once
Ten or more cycles, whole body, hands and danger zone in frame.
2. Break it into elements once
Eight elements for the trim press, split wherever the hazard changes.
Time study
Columns: Seconds, value class
48 s cycle, 16 s value added
Job safety analysis
Columns: Hazard, severity x likelihood, control
Highest risk score 15
Ergonomic score
Columns: REBA of the worst posture
Highest REBA 10
A film of the trim press job becomes one list of eight elements. Each element gets three readings: seconds and value class for the time study, hazard and risk score for the job safety analysis, and a REBA posture score.
The example that runs through the page is a trim press cell. One operator takes a 9 kg (20 lb) die-cast housing from a cooling conveyor, trims the flash in a press, deburrs two edges and stacks the housing on a pallet. The cycle is 48 seconds in eight elements. All the numbers are illustrative, and they are the same numbers used on our JSA, JSRA and management of change pages, so you can follow one job through every method.
Why the three studies are usually done apart, and what that costs
They sit in different departments. Time standards belong to industrial engineering or production, the JSA to safety, the posture scores to safety or occupational health. Each has its own form, its own calendar and its own trigger: a new product for the time study, an audit or an injury for the JSA, a complaint of pain for the ergonomic assessment. So the same operator is watched three times, months apart, by people who never compare notes.
| What happens | Why it happens | What it costs |
|---|---|---|
| The standard time is set on a job that is about to change | The time study ran in March, the JSA found the hand-in-die step in June | A second time study, a second round of training and a standard nobody trusts |
| A safety fix adds seconds nobody planned for | The guard or lift assist was chosen without the cycle in front of the team | A missed rate, pressure on the operator and a fix that gets bypassed |
| A faster method adds risk nobody scored | The method change came out of the time study and never reached the JSA | A new hazard running for months with no control |
| Three different step lists for one job | Each study broke the job down its own way | The work instruction, the JSA and the standard cannot be laid side by side |
| The operator explains the job three times | Three visits, three clipboards | Patience, and the feeling that nobody listened the first time |
None of these needs new software to fix. It needs one film, one element list and one meeting.
There is a quieter cost too. Awkward work is usually slow work, and the step people get hurt on is often a step that adds nothing for the customer. When the seconds and the risk are on different sheets, nobody sees that the best safety project and the best productivity project on the station are the same project.
The method in nine steps
Here is the whole route. The sections after it take each part slowly, with the trim press job worked through.
- 1
Agree the purpose with the operator and the supervisor
Say what the film is for: timing the job, finding what could hurt someone and scoring the postures, so the workstation can be changed. Say who will see it and when it is deleted. Ask the operator to work the usual way, shortcuts included, because the shortcuts are what you need to see.
- 2
Film the job once, for all three studies
One fixed camera for the timing, with the whole body, both hands and the danger zone in frame. A second angle for twisting and reach. At least ten cycles, plus every irregular task you can catch.
- 3
Break the cycle into elements
End each element at a break point you can see in a paused frame. Then check the list a second time for safety: split an element wherever the hazard, the body part at risk or the control changes.
- 4
Add what the film did not catch
Ask the operator what happens when the step goes wrong: a jam, a dropped part, a fault reset, a full scrap bin. Write each as its own element with how often it happens. These get a JSA row even though they are outside the timed cycle.
- 5
Time each element and give it a value class
Mean seconds over the cycles you kept, then value added, needed without adding value, or waste. That is the time study's column.
- 6
Go through each element frame by frame for hazards
With the operator in the room, pause on every element and ask what could hurt someone here. Record the hazard, score severity times likelihood on your site's scale and write down today's control.
- 7
Score the worst posture in each element
Freeze the worst frame and score it with REBA, or RULA for seated arm and hand work. That is the ergonomic column.
- 8
Read the sheet across and choose the changes
Find the rows that are bad in two or three columns at once. Pick the change from the top of the hierarchy of controls: remove the element if you can.
- 9
Make the change under control, then study all three again
A new method is a change: assess it before it runs. Then film the new method and fill in the same sheet. Keep both sheets with both films.
How to film so one take serves all three
A film shot only for timing often cuts off the feet, or frames the hands so tightly you cannot see the trunk. A film shot for posture often loses the hands inside the machine. Each study needs something slightly different from the footage, so plan the shot for the most demanding of the three.
| Study | It needs to see | So when you film |
|---|---|---|
| Time study | Every break point: the instant a part touches a fixture, a hand lets go, a button is pressed | One continuous take from a fixed camera. Never stop the recording between cycles |
| Job safety analysis | Hands near the point of operation, the path of anything that moves, the floor, what the operator does when a step fails | Keep the danger zone and the floor in frame. Keep filming through jams and interruptions, because that footage is the most useful |
| Ergonomic score | The whole body, feet included, side on for trunk, shoulder and elbow angles | Camera at about 45 degrees to the work or side on, far enough back for head and feet. Add a front or overhead angle for twist and reach |
The [video time study filming checklist](/templates/video-time-study-filming-checklist) has the camera set-up, the pause test and a shot log.
- Fix the camera on a tripod or mount, at head height or a little above, with the light behind it. A hand-held phone ruins break points and joint angles alike.
- Do a pause test before the real take: record 30 seconds, freeze one frame at full screen and check you can see both hands, the feet and the inside of the danger zone.
- Film at least ten cycles and drop the first few while the operator settles. Extra cycles cost nothing.
- Film every variant: the heavy part number and the light one, the first layer of the pallet and the last. The bottom layer is where the back bends furthest.
- Stay for one irregular event if you can: a pallet swap, a scrap bin change, a jam. If none happens, ask the operator to walk you through one slowly and film that, marked as a demonstration.
- Say the date, the station, the part number and the operator's agreement on the recording or in the shot log. A film nobody can identify is no use as a record.
OSHA's own booklet on job hazard analysis (OSHA 3071) suggests photographing or videotaping the worker as a reference for the detailed analysis, so filming a job for safety is not a new idea. What is new is using the same film for the timing and the posture scores. The planning side of a study, including what to tell operators and how to handle a union or works council, is in how to plan a time study.
How the time study's elements become the JSA's steps
A time study element and a JSA step are the same kind of thing: a piece of the job with a visible start and end. A JSA with five vague steps ("load", "run", "unload") hides the hazards inside them. A time study's element list is finer and has break points you can point to on the film, which makes it a better step list than most JSAs start with.
But the two studies cut for different reasons. The time study cuts where the timing can be read. The JSA must cut where the hazard changes. So take the timing elements and test each one with three questions.
- Does the hazard change inside this element? Unloading a housing (a cut from a sharp edge) and clearing flash from the die (a hand in the die) happen at the same place, seconds apart, and a stopwatch would happily merge them. Keep them apart: the harm, the severity and the control are all different.
- Does the body part at risk change? Turning to the pallet loads the back, placing the housing on the stack loads the shoulders and fingers. If one row cannot describe both, split it for the JSA and add the seconds back together for the time study.
- Does the control change? Loading the die is behind a light curtain and a two-hand start. The moment the press is cycling, the control is distance and a shield. Different control, different row.
- Is a machine element empty for safety? An automatic machine cycle with the operator standing clear may need one row, however many timing elements it has.
- Never merge away a hand going into a danger zone. However short it is, it gets its own row.
| # | Element | Ends when (break point) | Seconds | Hazard |
|---|---|---|---|---|
| 1 | Pick the housing from the cooling conveyor | Housing clears the conveyor | 4 | Contact with a warm part (burn) |
| 2 | Load it into the trim die | Hands leave the housing | 6 | Hands in the point of operation (caught in) |
| 3 | Step back, press the two-hand start, press trims | Press is back at the top | 7 | Ejected flash; noise |
| 4 | Unload the trimmed housing | Housing is on the bench | 5 | Sharp flash edge (cut) |
| 5 | Clear trimmed flash from the die by hand | Hand is out of the die | 5 | Hand in the die; sharp scrap |
| 6 | Deburr two edges with a hand file | File is back on the bench | 9 | Repeated wrist motion; sharp edge |
| 7 | Turn, bend and stack on a pallet on the floor | Hands leave the housing | 8 | Back strain from a twisted lift to floor level |
| 8 | Walk back to the conveyor | Hand reaches for the next housing | 4 | Trip on flash on the floor |
| Cycle | 48 |
Mean times over 10 cycles, operator at a normal pace. Elements 4 and 5 would pass as one timing element. They are split because the hazard changes.
The 48 second cycle, eight elements, drawn to scale
Example numbers- Pick the housing from the cooling conveyor4 s
- Load it into the trim die6 s
- Step back, two-hand start, press trims7 s
- Unload the trimmed housing5 s
- Clear trimmed flash from the die by hand5 s
- Deburr two edges with a hand file9 s
- Turn, bend and stack on a floor pallet8 s
- Walk back to the conveyor4 s
A strip of eight segments whose widths follow the element seconds: 4, 6, 7, 5, 5, 9, 8 and 4, for a total of 48 seconds.
The irregular elements: where people get hurt, and what a short film misses
A time study records occasional elements with their frequency, such as a tote change every 20 units, and spreads their time across the cycle. For the JSA these are not a footnote. Clearing a jam, resetting a fault, changing a die and cleaning are where hands go into places the normal cycle keeps them out of, often in a hurry, often with a guard open. A ten-cycle film of the trim press is 8 minutes long. Here is what it probably did not catch.
| Irregular element | How often | What could go wrong | How to capture it |
|---|---|---|---|
| Free a housing stuck in the die | About one cycle in 50, so every 40 minutes | Hand and forearm in the die, pulling hard; a pry bar that slips | Film until one happens, or film a slow walk-through with the press locked out |
| Swap the full pallet | Every 40 housings, so every 32 minutes | Forklift in the cell; operator steps into the aisle | Stay for one swap |
| Empty the scrap bin | About every 2 hours | Heavy bin, sharp flash, awkward tip into the skip | Plan the film around one change |
| Reset the press after a light curtain trip | Varies by shift | Reaching past the curtain to reset; restarting with a hand still near the die | Ask the operator to show the reset |
| Change the trim die | At changeover | Stored energy, a heavy die, pinch points | A separate JSA and the lockout procedure: do not fold it into this one |
Each of these gets its own JSA rows. None is part of the 48 second cycle, and none is scored in this example.
Ask one question at every element, and write the answer down even if the film shows nothing: what do you do when this step goes wrong? The honest answers ("I knock it out with the file", "I reach round the back") are the hazards no camera angle would have found. Non-routine work needs its own assessment and often a permit; see permit to work and lockout tagout.
What to look for, frame by frame
Play each element at normal speed once, then step through it paused. Video gives you two things a floor walk cannot: you can stop on the worst instant, and three people can look at the same instant and agree what they see. Go down this list on every element.
| Look for | The question to ask on the paused frame | At the trim press |
|---|---|---|
| Hands in the point of operation | Is any part of a hand or arm where a tool, die or blade closes? | Elements 2 and 5: both hands in the die to load, one hand in the die to clear flash |
| Line of fire | If something moved, fell, flew or released now, is a body part in its path? | Element 3: flash can be thrown from the die as the press trims |
| Reaches | Is the hand beyond a forearm's length, above the shoulder or below the knee? | Element 7: hands at floor level on the bottom layer of the pallet |
| Lifts and carries | What is the weight, how far from the body, and is the trunk twisted? | Element 7: 9 kg, lowered to the floor with a twist |
| Energy | What here is hot, moving, pressurised, sprung, raised or electrically live? | Element 1: the housing is still warm. Element 3: the press stroke |
| Sharp edges and surfaces | What does the bare or gloved hand touch? | Elements 4, 5 and 6: flash edges on the part and loose flash in the die |
| Housekeeping and footing | What is on the floor along the walking path? Is anything stored in it? | Element 8: flash on the floor between the bench and the conveyor |
| Repetition | Which small motion repeats inside the element, and how many times a cycle? | Element 6: file strokes on two edges, every cycle |
| What happens when the step goes wrong | Where do the hands go if the part sticks, drops or sits crooked? | Elements 2 and 5: a housing that will not seat, flash that will not come out |
| Workarounds | Is there tape, a home-made hook, a propped guard, a glove off for one step? | Ask. The film only shows the ones used in those ten cycles |
The first eight can be seen. The last two have to be asked.
Unsafe conditions and unsafe acts: two passes over the same film
A risk assessment mostly scores conditions: the unguarded die, the pallet on the floor, the flash underfoot. Some plants add a second pass that works at the level of single movements and asks a different question: at this movement, what could a person do that puts them in harm's way? World class manufacturing programmes call this risk prediction, to tell it apart from risk assessment. You list the movements inside an element, predict the risky act at each, score it and set a countermeasure.
Take element 5. The movements are: reach into the die, sweep the flash toward the front, pull the hand out. The predictable act is sweeping with the hand while the other hand is already moving toward the start buttons, or reaching in from the side to save a step. The countermeasure that works is not a reminder. It is taking the hand out of the die altogether, which is what the worked example does. Video makes this pass practical, because you can count how often the predicted act happens across ten cycles and show it to the team without naming anyone as careless. More on the two categories in unsafe acts and unsafe conditions.
The combined sheet: seconds, hazard and posture on one row
The sheet has one row for each element and three groups of columns. From the time study: seconds and value class. From the JSA: the hazard, severity times likelihood, and today's control. From the ergonomic assessment: the REBA score of the worst posture in the element. Here is the trim press job filled in.
The combined sheet: seconds, hazard and posture on one row
Example numbersPick the housing from the cooling conveyor
Hazard: Contact with a warm part (burn)
Control today: Heat-resistant gloves
Load it into the trim die
Hazard: Hands in the point of operation (caught in)
Control today: Light curtain and two-hand start
Step back, press the two-hand start, press trims
Hazard: Ejected flash; noise
Control today: Safety glasses, hearing protection
Unload the trimmed housing
Hazard: Sharp flash edge (cut)
Control today: General purpose gloves
Clear trimmed flash from the die by hand
Hazard: Hand in the die; sharp scrap
Control today: None of its own
Deburr two edges with a hand file
Hazard: Repeated wrist motion; sharp edge
Control today: Gloves
Turn, bend and stack on a pallet on the floor
Hazard: Back strain from a twisted lift to floor level
Control today: None
Walk back to the conveyor
Hazard: Trip on flash on the floor
Control today: None
Eight element cards with seconds, value class, risk score and REBA. Totals: 48 seconds, highest risk 15, highest REBA 10.
A word on each group of columns, so you can fill in your own.
- Seconds: the mean of the cycles you kept, as in any time study. The 48 seconds here is observed time. A standard time would add a rating and allowances, which are covered in how to conduct a time study.
- Value class: value added changes the part in a way the customer pays for (trimming, deburring: 16 of the 48 seconds, 33 percent). Needed without value has to happen with today's process (picking, loading, unloading, stacking: 23 seconds). Waste could stop tomorrow with no loss to the product (clearing flash by hand, walking back: 9 seconds).
- Hazard: say what could hurt, and how. "Hands in the point of operation (caught in)" is a hazard. "Be careful" is not.
- S x L: score the risk as it is today, with today's controls. Element 2 has the worst possible outcome on the sheet (severity 5), and it scores below element 5 because a light curtain and a two-hand start make it unlikely.
- Control today: write what is really there, and be honest when the answer is "none". A blank here is a finding.
- REBA: freeze the worst frame in the element and score it. Element 7 scores 10, high risk, from a trunk bent past 60 degrees with a twist, a 9 kg load and a fast change of posture. The full scoring method is in the REBA guide.
If your site scores risk on a three-factor scale (probability, gravity, and measures and controls), the sheet works the same way with that score in the risk column. The trim press job is scored that way on the JSRA page.
Reading the sheet across: where waste, risk and posture meet
Read down a column and you get the three studies you would have had anyway: a 48 second cycle that is one third value added, a top risk score of 15, a top REBA of 10. The reason to put them on one sheet is to read across.
- Element 5, clear flash by hand: waste, the highest risk on the job (15) and a REBA of 7. Bad in all three columns. Nobody would defend this step, and yet it survives on many lines because the time study saw 5 seconds and the JSA saw a row among eight.
- Element 7, stack on the floor pallet: the worst posture on the job (REBA 10), the second highest risk (12) and 8 seconds that add no value. Bad in all three again.
- Element 2, load the die: a risk score of 10 with the worst possible outcome, but it is already behind an engineered control and the seconds are needed. Leave the method, keep checking the control.
- Element 6, deburr: the longest element at 9 seconds, value added, low risk, REBA 4. A time study alone would start here because it is the biggest bar. The combined sheet says it can wait.
- Element 8, walk back: 4 seconds of waste with a trip hazard whose cause is the same flash that element 5 handles. Fix where the flash goes and two rows improve.
Reading across: which rows trip all three flags
Example numbers| Element | Adds no value | Risk score 10 or more | REBA 7 or more |
|---|---|---|---|
| 1. Pick (4 s, 6, REBA 3) | |||
| 2. Load die (6 s, 10, REBA 5) | |||
| 3. Press (7 s, 9, REBA 1) | |||
| 4. Unload (5 s, 8, REBA 5) | |||
| 5. Clear flash (5 s, 15, REBA 7) | |||
| 6. Deburr (9 s, 6, REBA 4) | |||
| 7. Stack (8 s, 12, REBA 10) | |||
| 8. Walk back (4 s, 6, REBA 1) |
A grid of eight elements against three flags: adds no value, risk score of 10 or more, REBA of 7 or more. Only elements 5 and 7 have all three.
Elements 5 and 7 together are 13 of the 48 seconds, 27 percent of the cycle, and they carry 27 of the 72 risk points and the two worst postures. That is the pattern to look for on your own sheet: the rows where a single change pays three times.
It also protects you from two classic mistakes. A time study on its own would have tried to speed up the stacking. A JSA on its own would have added a second pair of gloves and a warning sign at the die. Neither would have removed the step.
Choosing the changes, then studying all three again
Work down the hierarchy of controls for each bad row: eliminate the hazard, substitute something safer, engineer it out, then administrative controls, and personal protective equipment last. Start by asking whether the element needs to exist at all. In lean terms that is the same question as "is this waste?", which is why the top of the hierarchy and the top of the waste list so often point at the same step.
| Change | Hierarchy level | Seconds | S x L | REBA |
|---|---|---|---|---|
| An air blast and a scrap chute clear the flash, so element 5 disappears | Elimination | 5 to 0 | 15 to none | 7 to none |
| The pallet sits on a spring lift table turned to face the operator (element 7) | Engineering | 8 to 6 | 3 x 4 = 12 to 3 x 2 = 6 | 10 to 3 |
| The chute keeps flash off the floor (element 8) | Engineering | 4, unchanged | 2 x 3 = 6 to 2 x 1 = 2 | 1, unchanged |
| Cut-resistant gloves and sleeves at unload (element 4) | PPE | 5, unchanged | 2 x 4 = 8 to 2 x 2 = 4 | 5, unchanged |
Elements 1, 2, 3 and 6 are unchanged. The gloves are the weakest control on the list: they depend on being worn every cycle, and they are there because nobody has yet found a way to remove the sharp edge before unloading.
Then do the step most teams skip. Film the new method and fill in the same sheet, all three groups of columns. A change made for safety can add seconds, and a change made for speed can add a hazard. The lift table has moving parts and the air blast makes noise, and both have to be assessed before the new method runs. That is what management of change is for, and that page takes these two changes through it.
| Measure | Before | After | Change |
|---|---|---|---|
| Cycle time | 48 s | 41 s | 7 s shorter, 15 percent |
| Value added share of the cycle | 16 of 48 s, 33 percent | 16 of 41 s, 39 percent | Same work, less around it |
| Highest risk score | 15 (element 5) | 10 (element 2) | Top severity is still on the job |
| Sum of risk scores | 72 | 43 | 29 points lower |
| Highest REBA | 10 (element 7) | 5 (elements 2 and 4) | High to medium |
After: 6 + 10 + 9 + 4 + 6 + 6 + 2 = 43 for elements 1, 2, 3, 4, 6, 7 and 8. The sum of scores is only a way to compare one job with itself. It is not a measure of safety.
The trim press job before and after, all three studies
Example numbersCycle time
7 s shorter, 15 percent
Sum of risk scores
29 points lower
Highest risk score
Element 5 gone; loading the die is now top
Highest REBA
High to medium
Cycle time falls from 48 to 41 seconds, the sum of risk scores from 72 to 43, the highest risk score from 15 to 10 and the highest REBA from 10 to 5.
Read the after column with the same care as the before. The highest risk is now loading the die, at 10. Its severity cannot fall while hands load the part, so that score will stay until loading is automated, and the control behind it (the light curtain and the two-hand start) needs its checks to stay on the maintenance plan. Element 3 is still at 9 and is the next planned fix: a fixed shield at the die. A REBA of 5 is still "action necessary". The sheet tells you what to do next as well as what you did.
What video sees, what it misses, and who writes the JSA
Video is evidence of what happened in the cycles you filmed. That is a great deal, and it is not everything. Know the edges before you sign a JSA that was built from a film.
| Video shows | Video does not show | How to cover the gap |
|---|---|---|
| The cycles that were filmed | Rare events: the jam, the dropped part, the fault that comes once a week | Ask at every element what happens when it goes wrong. Check near miss and first aid records for the station |
| Routine work | Non-routine work: changeover, cleaning, maintenance, start-up after a stop | Separate assessments for those tasks, with the people who do them |
| Postures, reaches, hand positions | Noise, fumes, dust, heat, vibration, how heavy a part is | Measure them: a sound level meter, air sampling, a scale, the safety data sheet |
| What is in front of the lens | What is behind a guard, inside a machine or behind the operator | Walk the station. Open the cabinet. Add a second angle |
| How the operator worked while being filmed | How the job is done on nights, by a new starter, or when the line is behind | Film more than one person and shift. Compare with what supervisors and operators tell you |
| That a control exists | Whether it works: an interlock that is bypassed looks the same on film | Test it. Put the check on the inspection round |
A JSA built only from film is a JSA of ten good cycles. The one to worry about is the eleventh, the cycle with the jam.
People work differently on camera
For a time study the worry is pace. For a JSA it is the reverse problem: people follow the procedure when they are filmed. The glove goes on, the hook gets used, the shortcut disappears. You cannot remove this, but you can shrink it. Explain that the study is of the job and that shortcuts are what you most need to see, because a shortcut marks a step that is harder than it should be. Leave the camera running on a tripod long enough to be forgotten. And never use the footage to discipline anyone. Do that once and you have filmed your last honest cycle. A just culture is the condition for this method to work at all.
Consent and privacy when you film people
- Never film in secret. Tell the operator, the supervisor and any worker representative before the camera goes up.
- Say in writing what the film is for, who can see it, where it is stored and when it is deleted. Then keep to it.
- Frame the job and no more. Keep bystanders, screens and noticeboards out of shot where you can.
- Give people a real way to say no, and study someone else if they do.
- Check your own rules first. Recording people at work can need notice, consent or consultation with a union or works council, and data protection law in many countries treats video of an identifiable person as personal data. This is general practice, not legal advice, and the rules differ from one country and one agreement to the next.
The JSA is written by people, with the operator
A film can list the steps. Software can time them and score the postures. Neither knows that the guard was propped open last winter, that the night shift runs a different part, or that the file gets used as a hammer when a housing sticks. Hazard identification and the judgement of severity and likelihood belong to a small team that includes someone who does the job, and the JSA carries their names. Treat anything a tool drafts as a draft.
That is also how the LeanSuite part of this works. You upload the film of the job. The time and motion study times every element and cycle, and the ergonomic study scores REBA and RULA on every frame, by task element, from the same footage with no second shoot. Both are part of AI video analysis, both analyse files you upload, not a live camera, and both are drafts that you review, correct and certify. The element list they produce is the step list for your JSA. LeanSuite does not write the JSA: your team does, with the operator, using that list and the film.
Common mistakes
- Filming for one study and hoping it serves the others. Hands only, no feet, no danger zone: decide the framing for all three before you press record.
- Using the timing elements unchanged as JSA steps. Check every element for a change of hazard, body part or control, and split where you find one.
- Stopping at the cycle. The jam, the reset and the changeover are missing from a ten-cycle film, and they belong in the JSA.
- Scoring the risk as if the controls were perfect. Score what is there today, and check that it works.
- Reaching for PPE and a sign. If the row is waste, remove the element. The hierarchy starts at elimination for a reason.
- Setting the standard time before the fix. A standard set on a job with a REBA of 10 builds the bad posture into the plan, with a fatigue allowance to cover for it.
- Fixing safety and forgetting the seconds, or the other way round. Every change gets all three columns filled in again.
- Writing the JSA at a desk from the film, without the operator. You get the steps right and miss the reasons.
- Keeping the film without a retention rule, or using it for something the operator did not agree to.
- One sheet, done once. A new part number, a new fixture or a rebalanced line makes the sheet out of date. Tie the re-study to your management of change process.
Templates and related guides
- Video time study filming checklist: camera position, the pause test and a shot log.
- Job safety analysis template: a JSA form to take the hazard, risk and control columns once the element list is settled.
- Time study sheet: the observation sheet for the seconds.
- REBA worksheet: the posture score, with the tables built in.
- Risk matrix calculator: severity times likelihood on a 3x3, 4x4 or 5x5 grid with your own bands.
- Job safety analysis: the JSA itself, step by step.
- JSA vs JHA vs JSRA: which document to use when.
- Ergonomic assessment in manufacturing: which posture or lifting method fits which task.
Go deeper
This page is the short version. These guides cover each part in full.
- Top Five Common Manufacturing HazardsThe hazard families to have in mind while you step through the film.
- 7 Preventable Shop Floor Incidents Most Plants MissThe incidents that come from irregular work, the part of the job a short film misses.
- Top Ergonomic Practices for Manufacturing TeamsWhat to do on the floor once the posture scores show where the strain is.
- Why Most Manufacturing Hazards Go UnreportedWhy operators hold back the shortcuts and workarounds you most need to hear about.
All our articles on this subject are in the safety management topic.
Free templates and tools
- Video time study filming checklistA pre-shoot checklist and shot log for filming a time study on video: camera, light, people, settings, power and review.
- Job safety analysis (JSA) templateJob steps, hazards, risk scored before and after the controls, the hierarchy of controls, PPE and sign-off.
- Time study sheetTime each element over 10 cycles and work out the average, lowest repeatable and standard time. Excel does the sums.
- REBA worksheet (Rapid Entire Body Assessment)Score up to six postures with REBA: body-part drop-downs, Tables A, B and C as lookups, final score and action level, and a before and after comparison.
- Risk matrix calculatorSeverity times likelihood on a 3 x 3, 4 x 4 or 5 x 5 risk matrix, the band and its action, editable banding, and the score after further controls.
Doing this in LeanSuite
Time and Motion Study
Film a station on a phone and get element times, cycle time, standard time and a Yamazumi chart.
See Time and Motion StudyErgonomic Study
Maps 18 body joints from video, scores REBA and RULA automatically and flags the postures that need a fix.
See Ergonomic StudyAI Video Analysis
One process video becomes a time and motion study, an ergonomic study, line balancing and more.
See AI Video Analysis
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about job safety analysis from video
Yes, as long as the video is the evidence and not the author. Film several cycles, break the job into steps you can point to on the film, and go through each step paused with the operator, asking what could hurt someone there. Then add what the film could not show: jams, changeovers, noise, fumes and anything behind a guard. The team writes and signs the JSA.
No. A time study measures how long each element of a job takes so you can set a standard and find waste. A job safety analysis lists the hazards at each step and the controls for them. They share a starting point, the breakdown of the job into steps, so one film and one element list can serve both, with the seconds in one column and the hazards in the next.
Film at least ten cycles of the routine job, and more if the work varies by part or by pallet layer. That is enough to see the normal method and time it. It is not enough for safety on its own: also capture, or have the operator walk through, the irregular tasks such as clearing a jam, changing a scrap bin and resetting a fault, because those rarely fall inside a short film.
The job and where it is done, the date and the people who wrote it, each step in order, the hazards at each step, how severe and how likely the harm is, the controls in place and the controls to add, with an owner and a date for each. On a combined sheet you add the seconds, the value class and the posture score for each step, so time, risk and strain can be read together.
Software can draft parts of it. It can split a film into elements, time them and score postures with REBA or RULA, which gives you an accurate step list and the ergonomic column. Deciding what could go wrong at each step, how bad it would be and whether a control really works takes people who know the job. Treat any automated output as a draft for the team to review.
Treat it as needed everywhere. Tell the operator and any worker representative before filming, explain what the film is for, who will see it and when it will be deleted, and let people decline. The legal position differs by country and by union agreement: recording people at work can require notice, consent or consultation, and video of an identifiable person is often personal data. Check your own rules first.
Related guides and tools
- Job safety analysis: what a JSA is and how to write one
- How to conduct a time study: elements, break points and timing
- REBA assessment: scoring a whole-body posture step by step
- JSRA: the same trim press job on the three-factor risk score
- Management of change: assessing the new method before it runs
- Hierarchy of controls: ranking the fixes from elimination to PPE
- Job hazard analysis: the JHA method and a coil-loading example
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk
Or browse the topics, the full library and the lean glossary.