Time study in aerospace assembly and MRO: long cycles, touch labor and the learning curve
Short answer
You can't time an aerospace job the way you time a 40 second cycle. Split it into operations, measure each from video or booked hours, keep touch labor apart from waiting and rework, and state the result at a unit number, because the hours keep falling along a learning curve.
Aerospace assembly and maintenance work runs for hours or days, is built a few times a month and is done by crews, so a classic stopwatch study never sees enough cycles. Measure in three layers instead. Take total hours per unit from the work order. Film or record each operation to get its hours and what interrupted it. Time only the repeating elements, such as drilling a hole or installing a fastener, with a stopwatch, video or a predetermined time system. Report touch labor separately from waiting, rework and out-of-station work. Then place the result on a learning curve: a time measured at unit 12 is the time for unit 12, not for unit 50. In maintenance checks, routine task cards can carry planned hours, but non-routine work from findings has to be planned from history.
Last reviewed:
Why the stopwatch study breaks down here
One panel, six shifts: where a crew of two spent the time
Example numbers- Touch labor, numbered by operation: 33.0 h
- Waiting for inspection or parts: 5.0 h
- Rework: 2.5 h
- Cure, crew on another job: 6.0 h
- Finished out of station: 1.5 h
- 1Load skin and stringers, locate and clamp, 3.0 h
- 2Drill and ream fastener holes, 7.0 h
- 3Take apart, deburr and clean, 3.5 h
- 4Apply sealant and reassemble, 4.5 h
- 5Install fasteners, 8.0 h
- 6Install frames and clips, 5.0 h
- 7Support inspection, touch up, unload, 2.0 h
A fuselage panel job drawn shift by shift for a crew of two. Of 46.5 clock hours in the station, 33.0 are hands-on work across seven operations, 5.0 are waiting for inspection and parts, 2.5 are rework and 6.0 are sealant cure with the crew on another job. A further 1.5 hours of open work were finished at the next station.
A time study was designed for work that repeats. The observer watches thirty cycles of the same job in an afternoon, averages them, rates the pace and adds allowances. Aerospace work breaks every one of those assumptions. Installing a wing-to-body fairing, closing a fuselage panel or working a zone of a heavy maintenance check takes a crew hours or days, and the plant may do it four times a month.
That doesn't mean the work can't be measured. It means the question changes. On a short cycle you ask how long the job takes. On a long cycle you ask where the hours of this unit went, which of them were the job, and what the next unit should take.
- The cycle is hours to days. One observer with a stopwatch gets one or two cycles a week, and nobody can hold attention for a full shift.
- Volume is low. There may never be thirty cycles of the same configuration to average.
- The work is done by crews. Two to six people work in and around each other, and the time of the job is the sum of several people who are not always busy at once.
- The design keeps moving. Engineering changes and customer options mean unit 14 is not quite the job unit 12 was.
- Work travels. Tasks that could not be finished because a part was short move with the airframe and get done at a later station, often by a different crew.
- Quality loops interrupt. A hole out of tolerance stops the operation until the nonconformance is dispositioned, and the rework may be longer than the original task.
- Each unit is faster than the last. Hours per unit fall as the crew, the tooling and the planning improve, so a single measurement dates quickly.
The general technique for timing long cycles and crews is covered in timing long-cycle and team work. This page is about what is particular to aerospace: how the industry names its hours, how it handles improvement from unit to unit, and how maintenance, repair and overhaul (MRO) differs from new build. For the industry's wider operating problems, see aerospace and defense.
Touch labor and the hours around it
Touch labor is the hands-on work that changes the product: drilling, fastening, sealing, wiring, installing, testing. The term comes from defense and aerospace cost estimating, where it separates the people who work on the aircraft from the labor that supports them, such as planning, tooling, quality engineering and supervision. Most plants outside aerospace would call it direct labor.
The distinction matters for a study because the hours booked to a work order are not all touch. A mechanic clocked on to a job may be waiting for an inspector, looking for a tool or fixing a defect. If you set a standard from booked hours you bake those losses in. If you set it from touch time alone and say nothing about the rest, the plan will always run late. So measure both, and keep them in separate buckets.
| Bucket | What goes in it | Who can reduce it |
|---|---|---|
| Touch labor | Hands on the product, doing a planned operation by the planned method | Methods and tooling engineering, and the learning of the crew |
| Waiting | Clocked on to the job but stopped: for parts, tools, a crane, an inspector, an engineering answer | Planning, supply and the inspection schedule |
| Rework | Repeating or repairing work after a nonconformance | Quality, and the cause of the defect |
| Out-of-station work | Tasks that travelled with the unit and were done later, somewhere else | Whoever caused the shortage that made it travel |
| Support labor | Planning, tooling, inspection, supervision. Usually not booked to the job at all | Outside the scope of a job study; measure with work sampling if needed |
This is the same idea as sorting a short cycle into value added, necessary and waste, scaled up to a job where the waste comes in blocks of an hour and not in seconds.
The methods that fit, layer by layer
No single method covers a job that lasts a week. Think of the job in three layers and use a different tool on each.
Three layers of a long job, and the method that fits each
Days to weeks
The whole job or check
Measure with: Hours booked to the work order, plus work sampling of the crew
You get: Total hours per unit and the share that is touch labor
30 minutes to a shift
One operation or task card
Measure with: Video of the whole operation, or actual hours by operation from the shop system
You get: Hours per operation, the method as done, and what interrupted it
Seconds to minutes, hundreds of times
A repeating element inside it
Measure with: Stopwatch or video time study, or a predetermined time system
You get: A time per hole, per fastener or per metre of sealant to build operation times from
| Layer | Method | What it gives | What it misses |
|---|---|---|---|
| The whole job or check, from records | Hours booked to the work order or task cards, from the shop system | Actual hours per unit, for every unit, at no extra cost | Why. And it is only as honest as the clocking |
| The whole job or check, by sampling | Work sampling of the crew over the build | The share of crew time that is touch, waiting, walking and rework, with a margin | Element times and the method |
| One operation or task card | Video of the full operation, reviewed afterwards | Hours for the operation, the method as it was done, each interruption and its length | Anything outside the frame, such as trips to the crib |
| A repeating element, measured | Stopwatch or video time study | A time per hole, per fastener, per clamp, with enough cycles to trust | The irregular work between the repeats |
| A repeating element, built from tables | A predetermined time system | A time built from the motions, before the job exists | Fitting, adjusting and troubleshooting, which no table predicts |
The bottom layer is where classic work measurement still works. A panel may need 600 holes drilled and 600 fasteners installed. Those are short, repeating elements, and thirty cycles of them go by in minutes. Time them properly, apply a rating and allowances as you would for any standard time, and multiply by the count on the drawing. That gives a defensible time for the countable part of an operation and leaves only the uncountable part, the locating, fitting and checking, to be measured from video.
Predetermined time systems have versions built for this kind of work. MaxiMOST is the level of the MOST family meant for long, non-identical cycles, and the MTM Association publishes MTM-MEK for one-of-a-kind and small-batch production. Both trade precision for speed of analysis. The guide to predetermined motion time systems explains how the families differ. Use them for estimating before first build; replace the estimate with measured times once units are flowing.
Video earns its place in the middle layer. A camera on the fixture for a full shift records what a person with a clipboard cannot keep up with, and the crew, the engineer and the planner can replay a disputed hour together. LeanSuite's time and motion study is built on this: film the station and the AI times every element on a timeline that links back to the footage, for an engineer to review and certify.
How to study a long-cycle assembly job
Plan the study around one unit going through one station. Agree it with the crew and their supervisor first; the planning guide covers that conversation.
- 1
Start from the work instructions
List the operations from the planning or the work order, in sequence, with the planned hours if there are any. These are your elements. Five to ten operations is a workable number for one station.
- 2
Record the unit number and the configuration
Write down which unit this is in the series, which options it carries and which engineering changes are in. Without the unit number the result can't be placed on a learning curve.
- 3
Capture the whole job
Film the station across every shift the job runs, or have an observer log the start and stop of each operation and every interruption with its reason. Note the crew size on each operation.
- 4
Split the hours into buckets
For each operation, separate touch labor from waiting, rework and travelled work. Multiply clock hours by the crew working to get labor hours.
- 5
Time the repeating elements
Inside the long operations, find the short elements that repeat: drill, deburr, install, torque. Time enough cycles of each and build the countable part of the operation from the count.
- 6
Reconcile with booked hours
Compare your total with the hours clocked to the work order. A gap means either the clocking or the study missed something. Find out which before anyone uses the number.
- 7
State the result at its unit number
Report touch labor for this unit, the other buckets beside it, and where the unit sits on the learning curve. Then project the hours for the units still to build.
Layout studies still pay on long jobs. A spaghetti diagram of one mechanic's shift around a fuselage section often shows the trips to the tool crib and the kit cart that sit inside the waiting bucket, and better workstation design, with point-of-use tools and kits, removes them.
The learning curve: why a time needs a unit number
The learning curve is the aerospace industry's own contribution to work measurement. In 1936 T. P. Wright published what he had seen in airframe production: each time the cumulative number of aircraft built doubled, the labor per aircraft fell to a constant percentage of what it had been, about 80 percent in his data. The idea has been the convention for estimating and negotiating aerospace labor ever since.
The formula is Y = A x X^b. X is the unit number, A is the time of the first unit, and b is the logarithm of the learning rate divided by the logarithm of 2. For an 80 percent curve, b is log 0.80 / log 2 = minus 0.3219. For 85 percent it is minus 0.2345, and for 90 percent minus 0.1520. A lower percentage means faster learning. What Y stands for depends on which of two models you are using.
- The cumulative average model (Wright). Y is the average time of all units from the first to unit X. Each doubling takes the running average down to the learning rate.
- The unit model (Crawford). Y is the time of unit X itself. Each doubling takes the time of the individual unit down to the learning rate.
Same first unit, same 80 percent: two different forecasts
Example numbersCrawford
Unit model
The time of the unit itself falls to 80 percent at each doubling.
| Unit | That unit | Average so far |
|---|---|---|
| 1 | 100.0 h | 100.0 h |
| 2 | 80.0 h | 90.0 h |
| 3 | 70.2 h | 83.4 h |
| 4 | 64.0 h | 78.6 h |
Wright
Cumulative average model
The average time of all units so far falls to 80 percent at each doubling.
| Unit | That unit | Average so far |
|---|---|---|
| 1 | 100.0 h | 100.0 h |
| 2 | 60.0 h | 80.0 h |
| 3 | 50.6 h | 70.2 h |
| 4 | 45.4 h | 64.0 h |
With a first unit of 100 hours and an 80 percent curve, the unit model gives unit 4 as 64.0 hours and the cumulative average model gives unit 4 as 45.4 hours, because the second model applies the 80 percent to the running average and not to the unit.
The two give different answers from the same inputs. With a first unit of 100 hours and an 80 percent rate, the unit model puts unit 2 at 80 hours. The cumulative average model puts the average of units 1 and 2 at 80 hours, which makes unit 2 itself 60 hours. So a quoted rate means nothing until you know the model behind it. Fit the curve to your own hours by unit; don't borrow a percentage from another program. The learning curve workbook runs both models and fits a rate from your data.
Stating a standard at a unit number
On a short-cycle line the standard is one number. On a learning curve it is a number at a unit: 66 hours at unit 12. Aerospace planning usually handles this in one of two ways. Either the standard is set for a mature unit far down the curve, and early units are budgeted as that standard plus an allowance read off the curve. Or each lot gets its own target, taken from the curve at the lot's midpoint.
The curve is a fit to history, not a law. It flattens when improvement work stops, steps up after a long break in production or a large design change, and it describes touch labor much better than it describes waiting or rework. Don't apply it to machine-paced work, where the cycle is fixed. And never read the forecast as a reason to push people to go faster: the fall in hours comes from better methods, tooling, kitting and planning as much as from individual skill.
Worked example: a fuselage panel at unit 12
Illustrative example. A crew of two assembles a fuselage side panel in a fixture: skin, stringers, frames and clips. The plant runs several fixtures, builds about three panels a week and is on unit 12. An engineer films the station across all six shifts the panel is in it, logs each operation and every stop, and gets this.
| Operation | Clock hours | Labor hours |
|---|---|---|
| 1. Load skin and stringers, locate and clamp | 3.0 | 6.0 |
| 2. Drill and ream fastener holes | 7.0 | 14.0 |
| 3. Take apart, deburr and clean | 3.5 | 7.0 |
| 4. Apply sealant and reassemble | 4.5 | 9.0 |
| 5. Install fasteners | 8.0 | 16.0 |
| 6. Install frames and clips | 5.0 | 10.0 |
| 7. Support inspection, touch up and unload | 2.0 | 4.0 |
| Touch labor | 33.0 | 66.0 |
Labor hours = clock hours x 2 people. Operations 2 and 5 are mostly repeating elements and were checked against element times x the hole and fastener counts.
The same footage shows what else was booked to the job. The crew waited twice for an inspector and once, for three hours, for a clip kit that came short. Eleven oversize holes were written up and reworked. And the panel left the station with one bracket not fitted, which the next station's crew installed.
| Bucket | Labor hours | Share |
|---|---|---|
| Touch labor | 66.0 | 78.6% |
| Waiting for inspection (2 clock hours) and parts (3 clock hours) | 10.0 | 11.9% |
| Rework of oversize holes | 5.0 | 6.0% |
| Out-of-station work | 3.0 | 3.6% |
| Booked to the work order | 84.0 | 100% |
The six hours of sealant cure are not in the table: the crew was moved to another job and booked there. Shares are rounded and add to 100.1.
84.0 labor hours booked to unit 12, split four ways
Example numbersTouch labor: 66.0 h (78.6%)
The seven operations. This is what the standard and the learning curve describe.
Waiting: 10.0 h (11.9%)
Inspection queue and a short kit. A planning loss, not a job time.
Rework: 5.0 h (6.0%)
Oversize holes on a nonconformance. A quality loss with its own record.
Out of station: 3.0 h (3.6%)
Open work finished at the next station. It belongs to this job.
Of 84.0 labor hours booked to the panel, 66.0 are touch labor, 10.0 waiting, 5.0 rework and 3.0 work finished out of station. Touch labor is 78.6 percent.
So the work order says 84 hours and the job is 66. The other 18 hours, 21.4 percent, have three different owners. Now the unit number. The plant's hours by unit for panels 1 to 12 fit an 85 percent unit curve, so b = log 0.85 / log 2 = minus 0.2345. Putting the curve through the studied point gives a first-unit value of 66.0 / 12^(minus 0.2345) = 118.2 hours, and the hours for later units follow.
| Unit | Touch labor, hours | With a 15% allowance |
|---|---|---|
| 12 (studied) | 66.0 | 75.9 |
| 13 | 64.8 | 74.5 |
| 16 | 61.7 | 70.9 |
| 24 | 56.1 | 64.5 |
| 50 | 47.2 | 54.3 |
| Units 13 to 24, total of 12 panels | 719.3 | 827.2 |
Unit hours = 118.2 x unit number^(minus 0.2345). The 15 percent personal, fatigue and delay allowance is an example; use your plant's own allowance policy. Doubling from unit 12 to unit 24 takes 66.0 down to 56.1, which is 85 percent.
The panel's touch labor on an 85 percent unit curve
Example numbersVertical axis: touch labor hours per panel. Dashed line: every later panel planned at the unit 12 time of 66.0 hours.
An 85 percent unit learning curve through the studied point of 66.0 touch hours at unit 12. The curve starts at 118.2 hours for unit 1 and falls to 56.1 hours at unit 24 and 47.2 hours at unit 50. Units 13 to 24 need 719.3 hours on the curve against 792 if every unit were planned at the unit 12 time.
Planning the next 12 panels at the unit 12 time would budget 12 x 66.0 = 792 touch hours. The curve says 719.3, which is 72.7 hours or 9.2 percent less. Going the other way, anyone who had set a standard from unit 1 would have written down 118.2 hours for a job that takes 66. Neither figure is wrong as a measurement. Each is right for one unit only. The waiting, rework and travelled hours get their own targets: they should fall because the kit and inspection problems get fixed, not because a curve says so.
MRO: routine cards, non-routine findings and turnaround time
Maintenance, repair and overhaul has the long cycle of new build without its repetition. A maintenance check is a package of task cards. Each card is one inspection, service or replacement, and a hangar may run the same check type only a few times a year, each time on an aircraft with its own history.
- Routine cards are known before the aircraft arrives. They come from the maintenance programme, and each can carry planned man-hours. The same card recurs across aircraft and checks, so its actual hours build into a usable history.
- Non-routine cards are raised when a routine inspection finds something: corrosion, a crack, a chafed harness, a worn fitting. Nobody can list them in advance. Their number can only be estimated, and the time each one takes varies widely.
- Turnaround time is the elapsed time from the aircraft arriving to its release. It depends on the labor hours, but also on how many people can work in a zone at once, on parts lead times and on the sequence of access, so cutting task hours does not always cut days.
This shapes what you can measure. Routine cards behave like the operations in the panel example: compare booked hours with planned hours card by card, film the cards that run over most often, and fix the access, tooling or kitting problem behind them. Non-routine work can't be given a standard time, because there is no standard job. Plan it as a ratio from history, for the same check on the same fleet at a similar age, and watch that ratio during the check as findings come in.
| Man-hours | |
|---|---|
| Routine task cards, planned | 1,200 |
| Routine task cards, actual | 1,290 |
| Non-routine cards from findings, actual | 510 |
| Total at close | 1,800 |
| Routine actual against plan | 7.5% over |
| Non-routine share of the total | 28.3% |
| Non-routine hours per routine hour | 0.40 |
Illustrative numbers for one check. Non-routine ratios differ by aircraft type, age, operator and check; use your own records and do not treat this one as typical.
A maintenance check: the plan covers the routine cards only
Example numbers- Routine task cards
- Non-routine cards raised from findings
- Non-routine share of the check: 28.3%
- Non-routine hours per routine hour: 0.40
A check planned at 1,200 man-hours of routine task cards closed at 1,800: 1,290 on routine cards and 510 on non-routine cards raised from findings, which is 28.3 percent of the total.
A stopwatch has almost no role in a hangar. Technicians move between zones, cards are interrupted by access and by other trades, and a large part of the day is reading the manual, getting parts and completing records, all of which is required work. Work sampling answers the useful question, which is what share of a shift is hands-on and what the rest goes on. Task-card actuals answer the other one, which cards to look at first. Checks also have a changeover of their own, the opening up and closing of the aircraft, and the split of SMED into work that can be prepared before the aircraft arrives and work that can't applies directly.
Mistakes that are specific to this kind of work
Common mistakes in aerospace work measurement and what to do in their place
Mistake
Setting the standard from the first unit
What goes wrong: Unit 1 carries the most learning, the most fitting and the most surprises. Every later unit beats it and the standard tells you nothing.
Do this
Study a unit after the early turbulence, and state the unit number with the result.
Mistake
Averaging hours across units on a curve
What goes wrong: The average of units 1 to 12 is higher than unit 12 and far higher than unit 24. The plan built on it is always too generous.
Do this
Fit a curve to the hours by unit and read the unit you are planning off it.
Mistake
Quoting a learning rate without the model
What goes wrong: An 80 percent cumulative average curve and an 80 percent unit curve forecast different hours.
Do this
Name the model, the first-unit value and the units the rate was fitted to.
Mistake
Timing only the touch work
What goes wrong: The study says 66 hours, the order closes at 84, and the plan built on 66 runs late on every unit.
Do this
Record waiting, rework and travelled work in the same study, in their own buckets.
Mistake
Ignoring travelled work
What goes wrong: The station looks faster than it is because someone downstream finished its job, usually in a worse position and for more hours.
Do this
Charge out-of-station work back to the operation it came from.
Mistake
Treating one crew as the standard
What goes wrong: The best crew on the day shift sets a time the others can't meet for reasons of skill mix, not effort.
Do this
Study more than one crew, and record the licence and skill mix with the result.
Mistake
Giving non-routine work a standard time
What goes wrong: Each finding is a different job. A fixed time is wrong in both directions.
Do this
Plan non-routine work as a ratio from history and manage it as it emerges.
Mistake
Updating nothing after an engineering change
What goes wrong: The curve and the element counts describe a configuration that is no longer built.
Do this
Tie each study to a configuration and re-measure the operations a change touches.
The people side: skilled trades and safety-critical work
The people in this study are skilled, often licensed, and personally sign for their work. A time study that reads as pressure to go faster is worse than no study. Aviation regulators treat time pressure and fatigue as human factors that lead to maintenance error. EASA's Part-145, in point 145.A.47, requires maintenance planning to take account of human performance limitations, including fatigue. In the United States, 14 CFR 121.377 requires air carriers to give maintenance personnel at least 24 consecutive hours free of duty in any seven days, or the equivalent within a calendar month.
- Say what the study is for before the camera goes up: finding where hours are lost to waiting, shortages and rework. Then make sure that is what it gets used for.
- Don't set individual pace targets on safety-critical tasks. Use the times to plan and to staff, and to find the problems that stop people working.
- Never time, shorten or skip an inspection, a torque check or a required record to make a number. If the study shows a required step is slow, fix the access, the tooling or the paperwork.
- Ask the mechanics what stopped them. They know which kit is always short and which jig never fits, and the footage will back them up.
- Look at posture while you are there. Overhead drilling, work inside a wing box and long spells kneeling are common, and an ergonomic assessment of the worst operation often gives back more than a method change.
- Show the crew the results first, and agree what is filmed, who sees it and how long it is kept.
Quality systems matter here too. A plant certified to AS9100 already controls its work instructions and its nonconforming product, so the operation list and the rework record a study needs should exist. Use them, and don't build a parallel set.
This is general practice, not legal, regulatory or labor relations advice. Your approved procedures, your regulator's rules and any labor agreement in force come first.
Related guides, templates and tools
- Time and motion study: the whole family of methods and when to use each.
- Timing long-cycle and team work: the general technique for jobs that last hours and for crews.
- Time study from video: filming a job and timing it afterwards.
- Work sampling: the number of observations, the random schedule and a worked study.
- Standard time: rating and allowances for the repeating elements.
- Line balancing: once operation times are known, spreading them across stations on a moving or pulse line.
- Learning curve workbook: both models, a fit from your own hours and a ramp plan.
- Time study sheet and video time study filming checklist.
If you want the footage to do more of the work, LeanSuite's AI video analysis turns video of real work into time studies and other studies you review and certify. The same footage can feed a line balancing chart, an ergonomic study or a changeover study.
Go deeper
This page is the short version. These guides cover each part in full.
- Standard Work in Manufacturing: A Complete GuideWriting the method down once the operations are measured, so the next crew starts from it.
- Value-Added vs Non-Value-Added Time in ManufacturingThe classification behind the touch, waiting and rework buckets.
- Closing Plant-Wide Skill Gaps in 90 DaysThe skill mix that sits behind crew-to-crew differences in hours.
- How to Improve Shop Floor ProductivityWhat to do about the waiting and shortages once the study has sized them.
All our articles on this subject are in the standard work, sops and training topic.
Free templates and tools
- Learning curve and ramp-up workbookBoth learning curve models side by side, a fit from your own observed hours, batch hours, the unit that reaches standard and a weekly ramp plan.
- Time study sheetTime each element over 10 cycles and work out the average, lowest repeatable and standard time. Excel does the sums.
- Video time study filming checklistA pre-shoot checklist and shot log for filming a time study on video: camera, light, people, settings, power and review.
- Skills matrix templatePeople by tasks on a 0 to 4 scale, coverage and gaps per task and shift, and a training plan that closes them.
- Standard time calculatorObserved times, a rating and an allowance in; normal time, standard time, units per hour, pieces per shift and labour cost per unit out, with the working.
- Time study sample size calculatorHow many cycles of an element to time, from your first readings, with the t formula, the ILO formula and the range method.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
Doing this in LeanSuite
Time and Motion Study
Film the station and the AI times every element on a timeline that links to the video, split into value-added, necessary and waste.
See Time and Motion StudyAI Video Analysis
Turns video of real work into time studies, line balance charts, changeover splits and other studies you review and certify.
See AI Video Analysis
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about time study in aerospace assembly and MRO
Touch labor is the hands-on work that changes the product: drilling, fastening, sealing, wiring, assembling and testing. The term is used in aerospace and defense cost estimating to separate it from support labor such as planning, tooling, quality engineering and supervision. Outside aerospace it is usually called direct labor. In a time study, touch labor is kept apart from waiting, rework and travelled work booked to the same job.
Y = A x X^b, where X is the unit number, A is the time of the first unit and b is the logarithm of the learning rate divided by the logarithm of 2. For an 85 percent curve b is minus 0.2345. In the unit model Y is the time of unit X. In the cumulative average model Y is the average time of units 1 to X. Each doubling of output takes Y down to the learning rate.
Wright's model applies the learning rate to the cumulative average time of all units built so far. Crawford's model applies it to the time of each individual unit. With a first unit of 100 hours and an 80 percent rate, Crawford's model puts unit 2 at 80 hours, while Wright's puts the average of units 1 and 2 at 80 hours, so unit 2 itself is 60. Always state which model a rate belongs to.
On an 80 percent learning curve, each time the cumulative number of units doubles, the time falls to 80 percent of what it was. If unit 1 takes 100 hours under the unit model, unit 2 takes 80, unit 4 takes 64 and unit 8 takes 51.2. A lower percentage means faster learning. Wright reported about 80 percent for airframe labor in 1936; fit your own rate from your own hours.
Don't try to stopwatch the whole job. Break it into the operations in the work instructions, film or log each one across every shift, and split the hours into touch labor, waiting, rework and out-of-station work. Time only the short repeating elements, such as drilling or fastening, with a stopwatch or video. Reconcile the total with the hours booked to the work order, and record the unit number.
Routine tasks are the inspections, services and replacements listed in the maintenance programme. They are known before the aircraft arrives and can carry planned man-hours. Non-routine tasks are raised during the check when an inspection finds a defect, such as corrosion or a worn part. Their number and length can only be estimated, so they are planned from the history of similar checks and not from a time standard.
For routine task cards, yes: planned man-hours per card, compared with actual hours, show which cards need attention. For non-routine work, no fixed standard fits, because each finding is a different job. Standards in maintenance are for planning, staffing and finding delays. They should not be used to pressure individuals on safety-critical tasks, and regulators require planning to take human performance limits such as fatigue into account.
Related guides and tools
- Timing long-cycle and team work: the general method
- Time and motion study: the family of methods and when to use each
- How to conduct a time study, step by step
- Work sampling: measuring what a crew's time goes on
- Standard time: observed time, rating and allowances
- Time study from video: filming and timing afterwards
- Workstation design: point-of-use tools, kits and reach
- LeanSuite for aerospace and defense manufacturers
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk
Or browse the topics, the full library and the lean glossary.
Rather see it on your own problem?
Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.