Time study in aerospace assembly and MRO: long cycles, touch labor and the learning curve

Short answer

You can't time an aerospace job the way you time a 40 second cycle. Split it into operations, measure each from video or booked hours, keep touch labor apart from waiting and rework, and state the result at a unit number, because the hours keep falling along a learning curve.

Aerospace assembly and maintenance work runs for hours or days, is built a few times a month and is done by crews, so a classic stopwatch study never sees enough cycles. Measure in three layers instead. Take total hours per unit from the work order. Film or record each operation to get its hours and what interrupted it. Time only the repeating elements, such as drilling a hole or installing a fastener, with a stopwatch, video or a predetermined time system. Report touch labor separately from waiting, rework and out-of-station work. Then place the result on a learning curve: a time measured at unit 12 is the time for unit 12, not for unit 50. In maintenance checks, routine task cards can carry planned hours, but non-routine work from findings has to be planned from history.

Last reviewed:

Why the stopwatch study breaks down here

One panel, six shifts: where a crew of two spent the time

Example numbers
Shift 1
Shift 2
Shift 3
Shift 4
Shift 5
Shift 6
Next station
0 h2468 h
  • Touch labor, numbered by operation: 33.0 h
  • Waiting for inspection or parts: 5.0 h
  • Rework: 2.5 h
  • Cure, crew on another job: 6.0 h
  • Finished out of station: 1.5 h
  1. 1Load skin and stringers, locate and clamp, 3.0 h
  2. 2Drill and ream fastener holes, 7.0 h
  3. 3Take apart, deburr and clean, 3.5 h
  4. 4Apply sealant and reassemble, 4.5 h
  5. 5Install fasteners, 8.0 h
  6. 6Install frames and clips, 5.0 h
  7. 7Support inspection, touch up, unload, 2.0 h

A fuselage panel job drawn shift by shift for a crew of two. Of 46.5 clock hours in the station, 33.0 are hands-on work across seven operations, 5.0 are waiting for inspection and parts, 2.5 are rework and 6.0 are sealant cure with the crew on another job. A further 1.5 hours of open work were finished at the next station.

A stopwatch study assumes a cycle you can watch many times in one sitting. This one cycle fills a week, and more than a quarter of it is not planned work on the panel.

A time study was designed for work that repeats. The observer watches thirty cycles of the same job in an afternoon, averages them, rates the pace and adds allowances. Aerospace work breaks every one of those assumptions. Installing a wing-to-body fairing, closing a fuselage panel or working a zone of a heavy maintenance check takes a crew hours or days, and the plant may do it four times a month.

That doesn't mean the work can't be measured. It means the question changes. On a short cycle you ask how long the job takes. On a long cycle you ask where the hours of this unit went, which of them were the job, and what the next unit should take.

  • The cycle is hours to days. One observer with a stopwatch gets one or two cycles a week, and nobody can hold attention for a full shift.
  • Volume is low. There may never be thirty cycles of the same configuration to average.
  • The work is done by crews. Two to six people work in and around each other, and the time of the job is the sum of several people who are not always busy at once.
  • The design keeps moving. Engineering changes and customer options mean unit 14 is not quite the job unit 12 was.
  • Work travels. Tasks that could not be finished because a part was short move with the airframe and get done at a later station, often by a different crew.
  • Quality loops interrupt. A hole out of tolerance stops the operation until the nonconformance is dispositioned, and the rework may be longer than the original task.
  • Each unit is faster than the last. Hours per unit fall as the crew, the tooling and the planning improve, so a single measurement dates quickly.

The general technique for timing long cycles and crews is covered in timing long-cycle and team work. This page is about what is particular to aerospace: how the industry names its hours, how it handles improvement from unit to unit, and how maintenance, repair and overhaul (MRO) differs from new build. For the industry's wider operating problems, see aerospace and defense.

Touch labor and the hours around it

Touch labor is the hands-on work that changes the product: drilling, fastening, sealing, wiring, installing, testing. The term comes from defense and aerospace cost estimating, where it separates the people who work on the aircraft from the labor that supports them, such as planning, tooling, quality engineering and supervision. Most plants outside aerospace would call it direct labor.

The distinction matters for a study because the hours booked to a work order are not all touch. A mechanic clocked on to a job may be waiting for an inspector, looking for a tool or fixing a defect. If you set a standard from booked hours you bake those losses in. If you set it from touch time alone and say nothing about the rest, the plan will always run late. So measure both, and keep them in separate buckets.

The buckets to split a long job's hours into
BucketWhat goes in itWho can reduce it
Touch laborHands on the product, doing a planned operation by the planned methodMethods and tooling engineering, and the learning of the crew
WaitingClocked on to the job but stopped: for parts, tools, a crane, an inspector, an engineering answerPlanning, supply and the inspection schedule
ReworkRepeating or repairing work after a nonconformanceQuality, and the cause of the defect
Out-of-station workTasks that travelled with the unit and were done later, somewhere elseWhoever caused the shortage that made it travel
Support laborPlanning, tooling, inspection, supervision. Usually not booked to the job at allOutside the scope of a job study; measure with work sampling if needed

This is the same idea as sorting a short cycle into value added, necessary and waste, scaled up to a job where the waste comes in blocks of an hour and not in seconds.

The methods that fit, layer by layer

No single method covers a job that lasts a week. Think of the job in three layers and use a different tool on each.

Three layers of a long job, and the method that fits each

  1. Days to weeks

    The whole job or check

    Measure with: Hours booked to the work order, plus work sampling of the crew

    You get: Total hours per unit and the share that is touch labor

  2. 30 minutes to a shift

    One operation or task card

    Measure with: Video of the whole operation, or actual hours by operation from the shop system

    You get: Hours per operation, the method as done, and what interrupted it

  3. Seconds to minutes, hundreds of times

    A repeating element inside it

    Measure with: Stopwatch or video time study, or a predetermined time system

    You get: A time per hole, per fastener or per metre of sealant to build operation times from

No single method covers a job that lasts a week. Measure the total from records, the operations from video, and only the repeating elements with a stopwatch.
Which measurement method fits which layer of a long-cycle job
LayerMethodWhat it givesWhat it misses
The whole job or check, from recordsHours booked to the work order or task cards, from the shop systemActual hours per unit, for every unit, at no extra costWhy. And it is only as honest as the clocking
The whole job or check, by samplingWork sampling of the crew over the buildThe share of crew time that is touch, waiting, walking and rework, with a marginElement times and the method
One operation or task cardVideo of the full operation, reviewed afterwardsHours for the operation, the method as it was done, each interruption and its lengthAnything outside the frame, such as trips to the crib
A repeating element, measuredStopwatch or video time studyA time per hole, per fastener, per clamp, with enough cycles to trustThe irregular work between the repeats
A repeating element, built from tablesA predetermined time systemA time built from the motions, before the job existsFitting, adjusting and troubleshooting, which no table predicts

The bottom layer is where classic work measurement still works. A panel may need 600 holes drilled and 600 fasteners installed. Those are short, repeating elements, and thirty cycles of them go by in minutes. Time them properly, apply a rating and allowances as you would for any standard time, and multiply by the count on the drawing. That gives a defensible time for the countable part of an operation and leaves only the uncountable part, the locating, fitting and checking, to be measured from video.

Predetermined time systems have versions built for this kind of work. MaxiMOST is the level of the MOST family meant for long, non-identical cycles, and the MTM Association publishes MTM-MEK for one-of-a-kind and small-batch production. Both trade precision for speed of analysis. The guide to predetermined motion time systems explains how the families differ. Use them for estimating before first build; replace the estimate with measured times once units are flowing.

Video earns its place in the middle layer. A camera on the fixture for a full shift records what a person with a clipboard cannot keep up with, and the crew, the engineer and the planner can replay a disputed hour together. LeanSuite's time and motion study is built on this: film the station and the AI times every element on a timeline that links back to the footage, for an engineer to review and certify.

How to study a long-cycle assembly job

Plan the study around one unit going through one station. Agree it with the crew and their supervisor first; the planning guide covers that conversation.

  1. 1

    Start from the work instructions

    List the operations from the planning or the work order, in sequence, with the planned hours if there are any. These are your elements. Five to ten operations is a workable number for one station.

  2. 2

    Record the unit number and the configuration

    Write down which unit this is in the series, which options it carries and which engineering changes are in. Without the unit number the result can't be placed on a learning curve.

  3. 3

    Capture the whole job

    Film the station across every shift the job runs, or have an observer log the start and stop of each operation and every interruption with its reason. Note the crew size on each operation.

  4. 4

    Split the hours into buckets

    For each operation, separate touch labor from waiting, rework and travelled work. Multiply clock hours by the crew working to get labor hours.

  5. 5

    Time the repeating elements

    Inside the long operations, find the short elements that repeat: drill, deburr, install, torque. Time enough cycles of each and build the countable part of the operation from the count.

  6. 6

    Reconcile with booked hours

    Compare your total with the hours clocked to the work order. A gap means either the clocking or the study missed something. Find out which before anyone uses the number.

  7. 7

    State the result at its unit number

    Report touch labor for this unit, the other buckets beside it, and where the unit sits on the learning curve. Then project the hours for the units still to build.

Layout studies still pay on long jobs. A spaghetti diagram of one mechanic's shift around a fuselage section often shows the trips to the tool crib and the kit cart that sit inside the waiting bucket, and better workstation design, with point-of-use tools and kits, removes them.

The learning curve: why a time needs a unit number

The learning curve is the aerospace industry's own contribution to work measurement. In 1936 T. P. Wright published what he had seen in airframe production: each time the cumulative number of aircraft built doubled, the labor per aircraft fell to a constant percentage of what it had been, about 80 percent in his data. The idea has been the convention for estimating and negotiating aerospace labor ever since.

The formula is Y = A x X^b. X is the unit number, A is the time of the first unit, and b is the logarithm of the learning rate divided by the logarithm of 2. For an 80 percent curve, b is log 0.80 / log 2 = minus 0.3219. For 85 percent it is minus 0.2345, and for 90 percent minus 0.1520. A lower percentage means faster learning. What Y stands for depends on which of two models you are using.

  • The cumulative average model (Wright). Y is the average time of all units from the first to unit X. Each doubling takes the running average down to the learning rate.
  • The unit model (Crawford). Y is the time of unit X itself. Each doubling takes the time of the individual unit down to the learning rate.

Same first unit, same 80 percent: two different forecasts

Example numbers

Crawford

Unit model

The time of the unit itself falls to 80 percent at each doubling.

UnitThat unitAverage so far
1100.0 h100.0 h
280.0 h90.0 h
370.2 h83.4 h
464.0 h78.6 h

Wright

Cumulative average model

The average time of all units so far falls to 80 percent at each doubling.

UnitThat unitAverage so far
1100.0 h100.0 h
260.0 h80.0 h
350.6 h70.2 h
445.4 h64.0 h

With a first unit of 100 hours and an 80 percent curve, the unit model gives unit 4 as 64.0 hours and the cumulative average model gives unit 4 as 45.4 hours, because the second model applies the 80 percent to the running average and not to the unit.

The highlighted column is the one the formula gives directly. Always say which model a quoted percentage belongs to, or the two sides of a negotiation are reading different curves.

The two give different answers from the same inputs. With a first unit of 100 hours and an 80 percent rate, the unit model puts unit 2 at 80 hours. The cumulative average model puts the average of units 1 and 2 at 80 hours, which makes unit 2 itself 60 hours. So a quoted rate means nothing until you know the model behind it. Fit the curve to your own hours by unit; don't borrow a percentage from another program. The learning curve workbook runs both models and fits a rate from your data.

Stating a standard at a unit number

On a short-cycle line the standard is one number. On a learning curve it is a number at a unit: 66 hours at unit 12. Aerospace planning usually handles this in one of two ways. Either the standard is set for a mature unit far down the curve, and early units are budgeted as that standard plus an allowance read off the curve. Or each lot gets its own target, taken from the curve at the lot's midpoint.

The curve is a fit to history, not a law. It flattens when improvement work stops, steps up after a long break in production or a large design change, and it describes touch labor much better than it describes waiting or rework. Don't apply it to machine-paced work, where the cycle is fixed. And never read the forecast as a reason to push people to go faster: the fall in hours comes from better methods, tooling, kitting and planning as much as from individual skill.

Worked example: a fuselage panel at unit 12

Illustrative example. A crew of two assembles a fuselage side panel in a fixture: skin, stringers, frames and clips. The plant runs several fixtures, builds about three panels a week and is on unit 12. An engineer films the station across all six shifts the panel is in it, logs each operation and every stop, and gets this.

Illustrative: touch labor by operation for panel unit 12, crew of two
OperationClock hoursLabor hours
1. Load skin and stringers, locate and clamp3.06.0
2. Drill and ream fastener holes7.014.0
3. Take apart, deburr and clean3.57.0
4. Apply sealant and reassemble4.59.0
5. Install fasteners8.016.0
6. Install frames and clips5.010.0
7. Support inspection, touch up and unload2.04.0
Touch labor33.066.0

Labor hours = clock hours x 2 people. Operations 2 and 5 are mostly repeating elements and were checked against element times x the hole and fastener counts.

The same footage shows what else was booked to the job. The crew waited twice for an inspector and once, for three hours, for a clip kit that came short. Eleven oversize holes were written up and reworked. And the panel left the station with one bracket not fitted, which the next station's crew installed.

Illustrative: all labor hours booked to panel unit 12
BucketLabor hoursShare
Touch labor66.078.6%
Waiting for inspection (2 clock hours) and parts (3 clock hours)10.011.9%
Rework of oversize holes5.06.0%
Out-of-station work3.03.6%
Booked to the work order84.0100%

The six hours of sealant cure are not in the table: the crew was moved to another job and booked there. Shares are rounded and add to 100.1.

84.0 labor hours booked to unit 12, split four ways

Example numbers
  • Touch labor: 66.0 h (78.6%)

    The seven operations. This is what the standard and the learning curve describe.

  • Waiting: 10.0 h (11.9%)

    Inspection queue and a short kit. A planning loss, not a job time.

  • Rework: 5.0 h (6.0%)

    Oversize holes on a nonconformance. A quality loss with its own record.

  • Out of station: 3.0 h (3.6%)

    Open work finished at the next station. It belongs to this job.

Of 84.0 labor hours booked to the panel, 66.0 are touch labor, 10.0 waiting, 5.0 rework and 3.0 work finished out of station. Touch labor is 78.6 percent.

The work order says 84.0 hours. Only 66.0 of them are the job. Keep the four buckets apart and each one gets its own owner and its own fix.

So the work order says 84 hours and the job is 66. The other 18 hours, 21.4 percent, have three different owners. Now the unit number. The plant's hours by unit for panels 1 to 12 fit an 85 percent unit curve, so b = log 0.85 / log 2 = minus 0.2345. Putting the curve through the studied point gives a first-unit value of 66.0 / 12^(minus 0.2345) = 118.2 hours, and the hours for later units follow.

Illustrative: touch labor per panel on an 85 percent unit curve through unit 12
UnitTouch labor, hoursWith a 15% allowance
12 (studied)66.075.9
1364.874.5
1661.770.9
2456.164.5
5047.254.3
Units 13 to 24, total of 12 panels719.3827.2

Unit hours = 118.2 x unit number^(minus 0.2345). The 15 percent personal, fatigue and delay allowance is an example; use your plant's own allowance policy. Doubling from unit 12 to unit 24 takes 66.0 down to 56.1, which is 85 percent.

The panel's touch labor on an 85 percent unit curve

Example numbers
Unit 1: 118.2 hUnit 12, studied: 66.0 hUnit 24: 56.1 hUnit 50: 47.2 h

Vertical axis: touch labor hours per panel. Dashed line: every later panel planned at the unit 12 time of 66.0 hours.

An 85 percent unit learning curve through the studied point of 66.0 touch hours at unit 12. The curve starts at 118.2 hours for unit 1 and falls to 56.1 hours at unit 24 and 47.2 hours at unit 50. Units 13 to 24 need 719.3 hours on the curve against 792 if every unit were planned at the unit 12 time.

A study gives one point on a moving curve. Planning the next 12 panels at the unit 12 time asks for 792 hours; the curve says 719.3, which is 72.7 fewer.

Planning the next 12 panels at the unit 12 time would budget 12 x 66.0 = 792 touch hours. The curve says 719.3, which is 72.7 hours or 9.2 percent less. Going the other way, anyone who had set a standard from unit 1 would have written down 118.2 hours for a job that takes 66. Neither figure is wrong as a measurement. Each is right for one unit only. The waiting, rework and travelled hours get their own targets: they should fall because the kit and inspection problems get fixed, not because a curve says so.

MRO: routine cards, non-routine findings and turnaround time

Maintenance, repair and overhaul has the long cycle of new build without its repetition. A maintenance check is a package of task cards. Each card is one inspection, service or replacement, and a hangar may run the same check type only a few times a year, each time on an aircraft with its own history.

  • Routine cards are known before the aircraft arrives. They come from the maintenance programme, and each can carry planned man-hours. The same card recurs across aircraft and checks, so its actual hours build into a usable history.
  • Non-routine cards are raised when a routine inspection finds something: corrosion, a crack, a chafed harness, a worn fitting. Nobody can list them in advance. Their number can only be estimated, and the time each one takes varies widely.
  • Turnaround time is the elapsed time from the aircraft arriving to its release. It depends on the labor hours, but also on how many people can work in a zone at once, on parts lead times and on the sequence of access, so cutting task hours does not always cut days.

This shapes what you can measure. Routine cards behave like the operations in the panel example: compare booked hours with planned hours card by card, film the cards that run over most often, and fix the access, tooling or kitting problem behind them. Non-routine work can't be given a standard time, because there is no standard job. Plan it as a ratio from history, for the same check on the same fleet at a similar age, and watch that ratio during the check as findings come in.

Illustrative: man-hours on one maintenance check
Man-hours
Routine task cards, planned1,200
Routine task cards, actual1,290
Non-routine cards from findings, actual510
Total at close1,800
Routine actual against plan7.5% over
Non-routine share of the total28.3%
Non-routine hours per routine hour0.40

Illustrative numbers for one check. Non-routine ratios differ by aircraft type, age, operator and check; use your own records and do not treat this one as typical.

A maintenance check: the plan covers the routine cards only

Example numbers
Planned: routine task cards1,200 h
Actual at close1,800 h
  • Routine task cards
  • Non-routine cards raised from findings
  • Non-routine share of the check: 28.3%
  • Non-routine hours per routine hour: 0.40

A check planned at 1,200 man-hours of routine task cards closed at 1,800: 1,290 on routine cards and 510 on non-routine cards raised from findings, which is 28.3 percent of the total.

Routine cards ran 7.5 percent over plan. The larger gap is work nobody could list before the panels came off. Plan it from the non-routine history of the same check on the same fleet, not from a time study.

A stopwatch has almost no role in a hangar. Technicians move between zones, cards are interrupted by access and by other trades, and a large part of the day is reading the manual, getting parts and completing records, all of which is required work. Work sampling answers the useful question, which is what share of a shift is hands-on and what the rest goes on. Task-card actuals answer the other one, which cards to look at first. Checks also have a changeover of their own, the opening up and closing of the aircraft, and the split of SMED into work that can be prepared before the aircraft arrives and work that can't applies directly.

Mistakes that are specific to this kind of work

Common mistakes in aerospace work measurement and what to do in their place

  • Mistake

    Setting the standard from the first unit

    What goes wrong: Unit 1 carries the most learning, the most fitting and the most surprises. Every later unit beats it and the standard tells you nothing.

    Do this

    Study a unit after the early turbulence, and state the unit number with the result.

  • Mistake

    Averaging hours across units on a curve

    What goes wrong: The average of units 1 to 12 is higher than unit 12 and far higher than unit 24. The plan built on it is always too generous.

    Do this

    Fit a curve to the hours by unit and read the unit you are planning off it.

  • Mistake

    Quoting a learning rate without the model

    What goes wrong: An 80 percent cumulative average curve and an 80 percent unit curve forecast different hours.

    Do this

    Name the model, the first-unit value and the units the rate was fitted to.

  • Mistake

    Timing only the touch work

    What goes wrong: The study says 66 hours, the order closes at 84, and the plan built on 66 runs late on every unit.

    Do this

    Record waiting, rework and travelled work in the same study, in their own buckets.

  • Mistake

    Ignoring travelled work

    What goes wrong: The station looks faster than it is because someone downstream finished its job, usually in a worse position and for more hours.

    Do this

    Charge out-of-station work back to the operation it came from.

  • Mistake

    Treating one crew as the standard

    What goes wrong: The best crew on the day shift sets a time the others can't meet for reasons of skill mix, not effort.

    Do this

    Study more than one crew, and record the licence and skill mix with the result.

  • Mistake

    Giving non-routine work a standard time

    What goes wrong: Each finding is a different job. A fixed time is wrong in both directions.

    Do this

    Plan non-routine work as a ratio from history and manage it as it emerges.

  • Mistake

    Updating nothing after an engineering change

    What goes wrong: The curve and the element counts describe a configuration that is no longer built.

    Do this

    Tie each study to a configuration and re-measure the operations a change touches.

Most of these come from treating a moving, interrupted job as if it were a short repeating cycle.

The people side: skilled trades and safety-critical work

The people in this study are skilled, often licensed, and personally sign for their work. A time study that reads as pressure to go faster is worse than no study. Aviation regulators treat time pressure and fatigue as human factors that lead to maintenance error. EASA's Part-145, in point 145.A.47, requires maintenance planning to take account of human performance limitations, including fatigue. In the United States, 14 CFR 121.377 requires air carriers to give maintenance personnel at least 24 consecutive hours free of duty in any seven days, or the equivalent within a calendar month.

  • Say what the study is for before the camera goes up: finding where hours are lost to waiting, shortages and rework. Then make sure that is what it gets used for.
  • Don't set individual pace targets on safety-critical tasks. Use the times to plan and to staff, and to find the problems that stop people working.
  • Never time, shorten or skip an inspection, a torque check or a required record to make a number. If the study shows a required step is slow, fix the access, the tooling or the paperwork.
  • Ask the mechanics what stopped them. They know which kit is always short and which jig never fits, and the footage will back them up.
  • Look at posture while you are there. Overhead drilling, work inside a wing box and long spells kneeling are common, and an ergonomic assessment of the worst operation often gives back more than a method change.
  • Show the crew the results first, and agree what is filmed, who sees it and how long it is kept.

Quality systems matter here too. A plant certified to AS9100 already controls its work instructions and its nonconforming product, so the operation list and the rework record a study needs should exist. Use them, and don't build a parallel set.

This is general practice, not legal, regulatory or labor relations advice. Your approved procedures, your regulator's rules and any labor agreement in force come first.

Related guides, templates and tools

If you want the footage to do more of the work, LeanSuite's AI video analysis turns video of real work into time studies and other studies you review and certify. The same footage can feed a line balancing chart, an ergonomic study or a changeover study.

FAQ

Questions about time study in aerospace assembly and MRO

  1. Touch labor is the hands-on work that changes the product: drilling, fastening, sealing, wiring, assembling and testing. The term is used in aerospace and defense cost estimating to separate it from support labor such as planning, tooling, quality engineering and supervision. Outside aerospace it is usually called direct labor. In a time study, touch labor is kept apart from waiting, rework and travelled work booked to the same job.

  2. Y = A x X^b, where X is the unit number, A is the time of the first unit and b is the logarithm of the learning rate divided by the logarithm of 2. For an 85 percent curve b is minus 0.2345. In the unit model Y is the time of unit X. In the cumulative average model Y is the average time of units 1 to X. Each doubling of output takes Y down to the learning rate.

  3. Wright's model applies the learning rate to the cumulative average time of all units built so far. Crawford's model applies it to the time of each individual unit. With a first unit of 100 hours and an 80 percent rate, Crawford's model puts unit 2 at 80 hours, while Wright's puts the average of units 1 and 2 at 80 hours, so unit 2 itself is 60. Always state which model a rate belongs to.

  4. On an 80 percent learning curve, each time the cumulative number of units doubles, the time falls to 80 percent of what it was. If unit 1 takes 100 hours under the unit model, unit 2 takes 80, unit 4 takes 64 and unit 8 takes 51.2. A lower percentage means faster learning. Wright reported about 80 percent for airframe labor in 1936; fit your own rate from your own hours.

  5. Don't try to stopwatch the whole job. Break it into the operations in the work instructions, film or log each one across every shift, and split the hours into touch labor, waiting, rework and out-of-station work. Time only the short repeating elements, such as drilling or fastening, with a stopwatch or video. Reconcile the total with the hours booked to the work order, and record the unit number.

  6. Routine tasks are the inspections, services and replacements listed in the maintenance programme. They are known before the aircraft arrives and can carry planned man-hours. Non-routine tasks are raised during the check when an inspection finds a defect, such as corrosion or a worn part. Their number and length can only be estimated, so they are planned from the history of similar checks and not from a time standard.

  7. For routine task cards, yes: planned man-hours per card, compared with actual hours, show which cards need attention. For non-routine work, no fixed standard fits, because each finding is a different job. Standards in maintenance are for planning, staffing and finding delays. They should not be used to pressure individuals on safety-critical tasks, and regulators require planning to take human performance limits such as fatigue into account.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?