Skip to content
LeanSuite

Practical guide · Safety management

Safe work method statement (SWMS): what it contains and how to write one

Short answer

A safe work method statement (SWMS) is a short document for one high-risk job. It lists the job's steps in order, the hazards at each step and the controls the crew will use, and it names who checks them. The crew signs it before starting and stops when the work no longer matches it.

In Australia a SWMS is a legal document: the model Work Health and Safety Regulations require one before high risk construction work starts, and Safe Work Australia lists 18 such activities. In Great Britain the same idea is called a method statement, usually paired with the risk assessment as RAMS, and HSE says it is not required by law for most work. Elsewhere it is a contractor work plan. In every case it holds the same three columns: step, hazard, control. Write it from the real step sequence of the job, keep it to a few pages, brief it at the job, and revise it when the work changes. This is general guidance, not legal advice. Check the rules where your site is.

Last reviewed:

What is a safe work method statement?

A safe work method statement, SWMS for short (people say "swims"), is a written plan for one job that could seriously hurt someone. Safe Work Australia describes it as a document that sets out the high risk construction work to be done, the hazards that come from it and the measures that will control the risks. On the page that turns into three columns: what we will do, what could go wrong, what we will do about it.

It exists because higher-risk work is usually one-off. A production job gets a standard and an operator who does it four hundred times a shift. A roof fan replacement gets a crew that has never seen your roof. The method statement is how that crew, their supervisor and the site agree on the method before anyone climbs, and it is what the supervisor holds in their hand when they check the job an hour later.

Safe Work Australia is blunt about what it is not. It classes a SWMS as an administrative control that supports stronger ones such as guardrails and isolation, and says it is not meant to be a procedure. It is a tool for supervisors and workers to confirm and monitor the controls at the workplace. A SWMS that nobody reads at the job has no effect on the job.

Five names for a written safe method, and where each is used
NameWhere you hear itWhat it means
Safe work method statement (SWMS)AustraliaThe document the work health and safety regulations require before high risk construction work. Step, hazard, control, who is responsible, signed by the crew.
Method statementUK, Ireland, the Gulf, India, much of AsiaA description, in logical order, of exactly how a job will be done safely. It draws on the risk assessment. Not tied to a list of activities.
RAMS (risk assessment and method statement)UK construction and facilities workThe two documents handed over as one pack: the risk assessment says what could harm people and how bad, the method statement says how the job will be done.
Safe system of workUK law and older site rulesThe whole arrangement that makes a job safe: method, equipment, training, supervision, permits. A method statement is one written part of it.
Safe work procedureCanada, Australia, miningA standing written procedure for a task that is done repeatedly. Closer to an SOP than to a one-job method statement.

The first three are written for one job at one place. The last two describe how a kind of work is always done.

Where a SWMS or method statement is required

The answer depends on the country, and inside Australia on the state. What follows is what the regulators' own pages say. It is general information, the rules change, and you should read the regulation that applies to your site.

Australia: required for high risk construction work

Under the model Work Health and Safety Regulations, which most Australian states and territories have adopted, regulation 291 defines high risk construction work and regulation 299 requires a SWMS to be prepared before that work starts. Regulations 300 to 303 cover following it, giving a copy to the principal contractor, reviewing it and keeping it. Safe Work Australia's information sheet counts 18 high risk construction work activities and says a SWMS is not required for other construction work, although the duty to manage risk still applies.

  • What it must do: identify the work that is high risk construction work, state the hazards and the risks to health and safety, describe the measures that will control the risks, and describe how those measures will be put in place, monitored and reviewed.
  • Who writes it: the business doing the high-risk work, in consultation with the workers who will do it. Safe Work Australia says the person responsible for carrying out the work is best placed to prepare it.
  • The principal contractor: on a construction project of $250,000 or more, the principal contractor has to take all reasonable steps to get the SWMS before the work starts.
  • If the work departs from it: the work must stop immediately, or as soon as it is safe to stop, and must not restart until it can be done in line with the SWMS, revised if need be.
  • Keeping it: until the high-risk work is finished, and for at least 2 years if a notifiable incident happens during the work.

Victoria has not adopted the model laws. It has its own Occupational Health and Safety Regulations 2017, and WorkSafe Victoria lists 19 high-risk construction work activities, with tunnelling counted on its own. The duty is close to the model one: prepare the SWMS before the work, stop if it is not being followed, keep it for the length of the work. WorkSafe Victoria also says a SWMS should not carry risk matrices or risk scores. The height trigger differs too: the model list says a fall of more than 2 metres, and some jurisdictions have used 3 metres, so check the figure in your own state.

The 18 high risk construction work activities in Safe Work Australia's SWMS template
GroupActivities
Height and structureA risk of a person falling more than 2 metres. Work on a telecommunication tower. Demolition of a load-bearing structure. Temporary load-bearing support for structural alterations or repairs. Tilt-up or precast concrete.
Ground and enclosed spacesWork in or near a confined space. Work in or near a shaft or trench deeper than 1.5 metres, or a tunnel. Use of explosives.
Services and substancesWork likely to disturb asbestos. Work on or near pressurised gas mains or piping. Work on or near chemical, fuel or refrigerant lines. Work on or near energised electrical installations or services. Work in an area that may have a contaminated or flammable atmosphere.
Traffic and plantWork on, in or next to a road, railway, shipping lane or other traffic corridor in use. Work in an area with movement of powered mobile plant.
EnvironmentWork in areas with artificial extremes of temperature. Work in or near water or other liquid with a risk of drowning. Diving work.

Wording shortened from the tick list in Appendix A of Safe Work Australia's information sheet. The grouping is ours. Read regulation 291 in your own state or territory for the legal text.

The 18 high risk construction work activities, by group

Height and structure
5
Services and substances
5
Ground and enclosed spaces
3
Environment
3
Traffic and plant
2

Bar chart of the 18 activities in Safe Work Australia's template grouped by us: height and structure 5, services and substances 5, ground and enclosed spaces 3, environment 3, traffic and plant 2.

Counted from the tick list in Appendix A of Safe Work Australia's information sheet. The grouping is ours. Victoria lists 19.

Great Britain: the risk assessment is the legal duty

British law does not ask for a method statement by name for most work. What it asks for is a risk assessment: regulation 3 of the Management of Health and Safety at Work Regulations 1999 requires every employer to make a suitable and sufficient one, and to record the significant findings when five or more people are employed. The Health and Safety at Work etc. Act 1974, in section 2, also puts a duty on employers to provide systems of work that are safe so far as is reasonably practicable. That is where the phrase safe system of work comes from.

HSE's construction pages describe a method statement as a document that sets out in a logical sequence exactly how a job is to be carried out safely, pulling together the hazards and controls from the risk assessment. HSE says they are not required by law for most construction activities, and are a practical way to plan, manage and monitor higher-risk, complex or unusual work. There is one firm exception on that page: the arrangements for demolition, dismantling or structural alteration must be recorded in writing before the work begins.

RAMS is trade shorthand for the pair. We did not find the term on the HSE pages we read for this guide, which name the two documents separately. In practice a client who asks for "your RAMS" wants both, and it is the client's contract, not a regulation, that makes the method statement compulsory for that job.

Everywhere else, and inside a factory

In the United States and Canada you will rarely meet the words. The same job is covered by a job hazard analysis, a contractor's work plan or a site-specific safety plan, with permits on top. The format in this guide still works. For a plant manager the useful question is not what the document is called. It is whether the crew about to cut a hole in your roof has written down their method and shown it to you.

One caution for Australian plants. The SWMS duty attaches to construction work, and whether a maintenance or installation job inside a factory counts as construction work depends on the definitions in your state's regulations. Ask your regulator's guidance before deciding a SWMS is not needed. Asking for one anyway costs an hour.

What a SWMS contains

A good SWMS fits on two or three pages. Safe Work Australia says it should be short and should focus on the hazards and controls of the high-risk work, and warns that a long, detailed one is hard to understand, apply, monitor and review. Its template has a header, three columns and a sign-on block.

The parts of a SWMS and what each is for
PartWhat goes in itWhy it is there
Who and whereThe business doing the work, the principal contractor or host site, the works manager with a phone number, the workplace location, the date it was given to the hostSo anyone who finds a problem knows whose document it is and who to call
The jobA plain description of the work activityLimits the document to one job. Work outside this line is not covered
High-risk activitiesA tick against each high risk construction work activity the job involvesShows why the document is required and which controls must not be missing
Tasks in orderThe steps of the job in the sequence they will be doneThe spine of the document. Hazards belong to steps
Hazards and risksFor each step, what could harm workers or the publicMakes the crew look at each step, not at the job as a blur
Control measuresFor each hazard, exactly what will be done, specific enough to check by lookingThis column is the method. Everything else supports it
Compliance and reviewWho makes sure the SWMS is followed and how, who reviews the controls, how and whenThe model regulations ask for how the controls will be implemented, monitored and reviewed
Sign-onName and signature of every worker, and the date they received itEvidence that each person was briefed, and a list of who is on the job

Based on the template in Appendix A of Safe Work Australia's information sheet. The template marks which fields the regulations require and which are good practice, such as who was consulted.

One SWMS, part by part, with the roof fan job

Example numbers
Who and where

Mechanical contractor. Host plant, paint mixing room. Works manager and phone number.

Whose document it is, and who to call.

The job

Replace the roof extraction fan on the paint mixing room, Saturday 07:00 to 11:00.

One job. Work outside this line is not covered.

High-risk activities

Fall of more than 2 m. Energised electrical. Powered mobile plant. Flammable atmosphere.

Shows why the document is needed.

Task, hazard, control

2. Isolate the fan. Shock, fan starts. Locked off at the roof isolator by two people, tested dead.

The method. Every control must be checkable by looking.

Check and review

Host shift lead visits at steps 3 and 5. Any change stops the job.

How the controls are monitored and reviewed.

Sign-on

Name, signature and date for each worker, after the briefing.

Proof each person heard it.

Six bands of a safe work method statement: who and where, the job, the high-risk activities, the task hazard and control columns, the check and review arrangements, and the sign-on block. Each band shows a sample line from the roof fan job and why the part exists.

Six parts, two or three pages. The task, hazard and control band is the method. The rest tells you whose job it is, why it is high risk and who checks.

Two things are often added and should be kept small. A person responsible for each control helps, and WorkSafe Victoria asks for it. A risk score for each row usually does not: the regulators do not ask for it, WorkSafe Victoria advises against it, and the score tends to become the thing people argue about while the control column stays vague. If your client's form has a risk rating column, fill it in and spend your effort on the controls.

What to leave out: copied pages of general site rules, hazards that have nothing to do with this job, and references to standards the crew will never open. Safe Work Australia notes that hazards such as noise and manual handling have their own legal requirements and do not need to be in a SWMS unless they are part of the high-risk work.

How to write a SWMS from the job's step sequence

The hard part of a method statement is the first column. If the steps are wrong or too coarse, the hazards attach to nothing and the controls read like a poster. The step list is the same element breakdown a time study or a job safety analysis uses: observable actions, in order, each with a clear start and end. If the job has been done before and somebody filmed it, you already have the list. The guide to writing a JSA from video shows how one recording gives you the steps, the times and the hazards together.

Eight steps from a walk of the job to a revised SWMS

  1. 1

    Define the job and walk the place

  2. 2

    List the steps in the order they will be done

  3. 3

    Mark the high-risk steps

  4. 4

    Write the hazards for each step

  5. 5

    Choose controls you can check by looking

  6. 6

    Name who does it and who checks it

  7. 7

    Consult the crew and the host, then sign

  8. 8

    Use it, and revise it when the job changes

Steps 1 to 4 build the first column and the hazards. Steps 5 and 6 are the controls and who checks them. The last step is the one that keeps the paper true.
  1. 1

    Define the job and walk the place

    Write one sentence that says what will be done, where, and what is not included. Then go and look, with the person who will lead the work and someone who runs the area. Look up, look underneath, and ask what will be running nearby on the day.

  2. 2

    List the steps in the order they will be done

    Aim for 6 to 12 steps for most jobs. Each step is an action you could watch: isolate the fan, lift the old unit off the roof. Include setting up and clearing away, because access and housekeeping are where many injuries happen.

  3. 3

    Mark the high-risk steps

    Tick the high-risk activities the job involves, then put a mark against each step where one of them is live. Those rows get the most attention when the document is written and when it is checked.

  4. 4

    Write the hazards for each step

    Ask what could hurt someone during this step, including people who are not on the crew: the operators below, the forklift driver passing, the public at the fence. Write the hazard as an event, such as a fall through a skylight, not as a word such as height.

  5. 5

    Choose controls you can check by looking

    Work down the hierarchy of controls: remove the hazard, engineer it out, and only then rely on rules and protective equipment. Write each control so a supervisor can see whether it is in place. "Edge protection on the north and east sides before anyone leaves the walkway" can be checked. "Take care at edges" cannot.

  6. 6

    Name who does it and who checks it

    Put a name or a role against each control, and say how the controls will be monitored: who visits, how often, what they look at. This is the part of the SWMS that the Australian regulations ask for and most documents skip.

  7. 7

    Consult the crew and the host, then sign

    Read the draft through with the people who will do the work and with the site. They will find the step you missed and the control that cannot work on this roof. Every worker signs on once they have been briefed. Give the host or principal contractor a copy before the work starts.

  8. 8

    Use it, and revise it when the job changes

    Keep it at the job. Check the work against it. When the method has to change, stop, rewrite the rows that changed, brief everyone again and get the new version signed. Keep the old version.

A generic SWMS bought from a template shop is a starting point and nothing more. Safe Work Australia says a generic SWMS used at different workplaces may not meet the law unless it has first been reviewed against the hazards of the specific workplace and amended. The test is simple: could this document have been written without visiting the site? If so, it has not been finished.

A filled extract: contractors replacing a roof extraction fan

Illustrative example. A plant's paint mixing room has a roof-mounted extraction fan with a failed bearing. A mechanical contractor will swap it for a new unit of the same size on a Saturday morning. The fan weighs 85 kg (187 lb), the roof is 7 m (23 ft) above the yard, and a truck-mounted crane will lift the old fan off and the new one on. The duct below the fan carries solvent vapour when the mixers run.

Three of the 18 high-risk activities are live on this job: a risk of falling more than 2 metres, work on or near an energised electrical installation, and work in an area with movement of powered mobile plant. A fourth, a flammable atmosphere, is possible if the duct is opened before it has been purged, so the SWMS treats it as live too.

The job in section: where the controls sit

Example numbers
Roof fan job in sectionMixing room with a roof fan, isolator, covered skylights and stair tower, a truck crane in a closed yard, and the lift path.Paint mixing roomClosed yard1235
  1. Crane set up in the yard; yard and mixing room closed
  2. Roof isolator locked off by two people, tested dead
  3. Stair tower is the only way up; skylights covered
  4. Lift path kept clear; rigger gives the only signals

Side view of the plant. The paint mixing room has a roof with a fan on a platform, an isolator, two covered skylights and a fixed stair tower. A truck crane stands in a closed yard area on the right with its boom over the fan. A dashed line shows the lift path from the roof to the yard.

Four of the controls in the extract, drawn where they apply. The numbers match the task rows.
SWMS extract: replace the roof extraction fan on the paint mixing room (illustrative)
#TaskHazardsControl measuresWho
1Set up the crane in the yard and close the areas belowVehicles and people in the crane's working area. People under the load path, in the yard and in the mixing roomYard gate closed to deliveries from 07:00 to 11:00. Barriers and signs around the crane and under the load path. Mixing room emptied and locked for the lift. Crane on all four outriggers with mats, on the marked hardstandHost shift lead closes the yard and the room. Crane operator sets up
2Isolate the fanElectric shock. The fan starting while hands are in itFan switched off at the mixing room panel, local isolator on the roof locked off and tagged with the host electrician's lock and the contractor's lock. Tested dead at the motor terminals before any cable is touchedHost electrician isolates and tests. Contractor lead adds own lock
3Get people and tools onto the roofA fall from the roof edge. A fall through a skylight or a brittle roof sheetAccess by the fixed stair tower only. Work stays on the guardrailed walkway and the fan platform. The two skylights within 2 m of the platform are covered and marked before work starts. Tools go up in a lifting bag on the crane, not by hand on the stairsContractor lead checks covers and rails before the crew goes up
4Disconnect the duct and the cable, unbolt the fanSolvent vapour in the duct catching fire. Sparks from cutting seized boltsMixers stopped and the extraction run for 30 minutes before isolation. Gas test at the open duct reads clear before any bolt is cut. Seized bolts are split cold with a nut splitter. No grinding or flame: that would need a hot work permit and is not part of this methodHost safety coordinator does the gas test. Fitters do the work
5Lift the old fan off and lower it to the yardA dropped load. The load swinging into the crew or the roof edgeLift plan signed by the crane operator: 85 kg plus slings, inside the crane's rated capacity at the working radius. Four-leg sling on the fan's lifting lugs. One tag line. The rigger gives the only signals. Nobody stands between the load and the edgeCrane operator and rigger
6Lift the new fan on, bolt it down, seal the ductAs step 5. Fingers trapped between the fan base and the platform as it landsFan lowered to 100 mm above the platform and steadied with the tag line and push sticks, hands clear until it is landed. Bolts torqued to the maker's figureRigger and fitters
7Reconnect, remove locks, test runThe fan starting with a guard off or a person at the unit. Wrong rotationInlet guard and belt guard fitted and checked before the locks come off. Each person removes their own lock. Crew off the platform for the first start. Rotation checked by a short bump startHost electrician reconnects. Contractor lead confirms guards
8Clear the roof and hand backTools or fixings left on the roof. Skylight covers left on or removed too earlyTool count against the list in the lifting bag. Skylight covers removed last, by a person on the walkway. Barriers removed after the crane has packed up. Host walks the roof and the mixing room before the area is releasedContractor lead and host shift lead, together

Compliance check: the host shift lead visits the roof at steps 3 and 5 and signs the SWMS at each visit. Review: any change to the crane position, the access or the method stops the job until the rows are rewritten.

Which high-risk activity is live at which step

Example numbers
TaskFall over 2 mEnergised electricalPowered mobile plantFlammable atmosphere
1 Set up the crane, close the areas..Live.
2 Isolate the fan.Live..
3 Get people and tools onto the roofLive...
4 Disconnect the duct, unbolt the fanLive..Live
5 Lift the old fan offLive.Live.
6 Lift the new fan on, bolt it downLive.Live.
7 Reconnect, remove locks, test runLiveLive..
8 Clear the roof and hand backLive...
Steps affected6 of 82 of 83 of 81 of 8

Matrix of the eight tasks against four high-risk activities. Fall over 2 metres is live at steps 3 to 8, energised electrical at steps 2 and 7, powered mobile plant at steps 1, 5 and 6, and a flammable atmosphere at step 4.

Step 4 is the only one with a flammable atmosphere, and steps 5 and 6 carry two activities at once. Those rows get the most attention when the SWMS is written and when it is checked.

Read the control column again and notice how much of it can be checked from ten metres away. Are the skylights covered? Are there two locks on the isolator? Is anyone under the load path? A supervisor with this page can audit the job in two minutes, which is what the document is for.

On the day: the job changes

At 08:40 the crane arrives and the hardstand is half blocked by a trailer that was dropped overnight. The crane could set up further out, at a longer radius. The crew suggests a quicker fix: carry the new fan up the stair tower in two pieces and skip the crane.

Neither option is in the SWMS, so the job stops. Carrying 85 kg up a stair tower removes the dropped-load hazard and adds a worse manual handling one, with a fall risk on the stairs. A longer radius changes the lift plan. The contractor lead and the host shift lead choose the third option: move the trailer. It costs 35 minutes. Row 1 is amended to say who confirms the hardstand is clear the evening before, both initial the change, and the crew is told. A change that small still goes on paper, because the next crew will be handed this document as the method that worked.

SWMS vs JSA vs SOP vs method statement vs permit

These documents overlap, and on a contractor job you may hold four of them at once. They answer different questions. The comparison below is the short version. The guide to JSA vs JHA vs JSRA goes through the risk assessment family in detail.

SWMS, method statement, JSA, SOP and permit to work compared
SWMSMethod statement (RAMS)JSA or JHASOPPermit to work
Question it answersHow will this high-risk job be done safely, and who checks?Exactly how will this job be done?What can hurt someone at each step of this task?What is the standard way to do this routine task?Is this job allowed to start here, now?
Written forOne job at one workplaceOne job at one siteOne task, often reusedA repeating taskOne job, one place, one period
Written byThe business doing the work, with its workersThe contractor, from its risk assessmentSupervisor and operatorsThe process ownerIssued by the site, accepted by the crew
Legal statusRequired in Australia for high risk construction workNot required by name in Great Britain for most workDepends on the country and the hazardA company documentNamed in some rules, for example confined space entry in the US
Typical length2 to 3 pages2 to 10 pages1 page1 to 5 pages1 page
Signed byEvery worker on the jobContractor, then the client's reviewerThe team that wrote itApproverIssuer and the person in charge of the work

Typical lengths are our own rule of thumb, not a requirement from any regulator.

The practical differences are scope and timing. A JSA looks at one task and can be reused each time the task is done. A SWMS covers a whole job at a particular place, so it is rewritten or at least reviewed for every site. An SOP tells a trained operator how to run a routine task and assumes the conditions are stable. A permit to work does not describe the method at all. It confirms that the plant has been made safe for the method and that the people in charge of the area know the job is on. On the morning of the work, the crew's pre-task plan checks all of it against the conditions they find.

Which document works at which moment of a job

DocumentPlanning, days beforeStart of the jobDuring the workHand-back
JSA or SOPHow is this kind of task done safely?Write onceRead
SWMS or method statementHow will this high-risk job be done?Write for the jobBrief and signCheck the work against it
Permit to workIs the plant safe, and may the job start?RequestIssue at the jobHold, suspend, hand overHand back and cancel
Pre-task planWhat is different today?Brief the crew
Field level risk assessmentIs this step safe right now?Before each step

A table of five safety documents against four moments: planning, the start of the job, during the work and hand-back. The job safety analysis and the method statement are written in planning. The permit is requested in planning, issued at the start, held during the work and handed back at the end. The pre-task plan is a briefing at the start. The field level risk assessment is a check before each step.

The SWMS is written before the job and used during it. It is the only document in the row that is both briefed at the start and checked against while the work goes on.

How a SWMS is used on the day

A method statement has its effect on the day or it has none. Four habits make the difference.

  • Brief it at the job, not in the office. The person leading the work reads the steps aloud where the crew can see the roof, the crane and the isolator, and asks each person what their part is. Ten minutes is enough for a three-page SWMS.
  • Sign on after the briefing, never before. A signature means I heard it and I know my part. Anyone who joins the job later gets the same briefing and signs before they start.
  • Keep it where the work is. Safe Work Australia says the SWMS should be kept at the workplace, or where it can be delivered quickly, and an electronic copy is fine. A copy in the site office is not at the job.
  • Check the work against it. The supervisor or host visits at the high-risk steps and looks for the controls in the third column. A visit that only checks that the form exists teaches the crew that the form is the point.
  • Stop and revise when the work changes. New equipment, a different access route, a missing person, weather, something found when the plant is opened: each is a reason to stop, rewrite the affected rows, brief again and sign again. Anyone on the crew can call the stop. See stop-work authority.

The person at the tools still does their own last look before each step. That is the field level risk assessment: thirty seconds, in the head or on a pocket card, asking what has changed since the briefing.

When a method statement is the right document in a factory

Most work in a plant is routine and is covered by standard work, SOPs and a JSA for each job. A method statement earns its place when the job is unusual, involves more than one employer, or changes as it goes. If you run a plant outside Australia, nobody may require one from you. Ask for one anyway in these cases.

  • Contractor jobs with any of the high-risk activities in the list above: roof work, crane lifts, work on live services, excavation in the yard, entry to tanks and pits.
  • Machine installation, relocation and removal, where rigging, floor loading, temporary supports and energy connections all change during the job.
  • Shutdown and turnaround work, when many crews work near each other and the usual guards and interlocks are off.
  • Non-routine maintenance that your own team does once a year or less: relining a furnace, changing a press bolster, cleaning a dust collector. Infrequent does not mean low risk. People have the least practice at exactly these jobs.
  • Any job where the method was argued about in the planning meeting. If two competent people pictured it differently, write it down.

Reviewing a contractor's method statement takes ten minutes if you know what to look for. Does it name your site and your equipment? Are the steps in an order that could work here? Is every control something you could check by looking? Does it say what your people have to do, such as isolating, closing an area or stopping a line? Does it say when the job stops? If the answers are no, send it back before the day, not on it. The wider process, from prequalification to the review after the job, is in the guide to contractor safety management, and the contractor safety checklist has the questions on one page.

For your own maintenance crews, the step list is often the missing piece, because the job is done so rarely that nobody remembers the sequence. Film it the next time it is done. LeanSuite's time and motion study breaks an uploaded video into elements with their times, and that element list is a ready first column for the method statement. The hazards and controls are still written by the team: the software does not write a SWMS or a JSA.

Common mistakes

  • The 40-page SWMS. Length is not care. Nobody briefs forty pages at a roof hatch, so the crew signs the back page and the controls go unread.
  • A generic document with the site name pasted in. The giveaway is a hazard that cannot exist on this job, or a missing one that obviously does.
  • Controls that are wishes. "Be aware of overhead services", "use correct manual handling", "ensure area is safe". None can be checked, so none will be.
  • Every control is PPE. Harnesses, gloves and glasses are the last line. If the control column has no barrier, cover, isolation or change of method in it, the job has not been planned.
  • Steps that are too big. "Replace fan" as one row hides the isolation, the lift and the test run, which is where the hazards are.
  • Signed in the car park. Sign-on before the briefing, or without one, turns the document into a liability waiver in the crew's eyes.
  • Never revised. The job changed at 08:40 and the paper still describes the plan from Thursday.
  • Treating it as the permit. A method statement describes how the crew will work. It does not isolate anything, and it does not tell the control room the job has started.

What a SWMS cannot do

A SWMS is an administrative control. It does not hold a load, stop a fall or de-energise a motor. Its value is that it makes people decide on those controls before the job and gives the supervisor something to check against. If the engineering controls are not there on the day, the paper changes nothing.

It is also only as good as the people in the room when it was written. A method statement prepared by a safety adviser who has not seen the job, and signed by a crew who were not asked, will miss the things only the crew knows. And it records a plan. Work drifts, which is why the stop and revise rule matters more than any row in the table.

This guide is general practice. It is not legal advice, and it does not tell you whether a particular document satisfies the regulations where you work. For that, read the regulation and your regulator's guidance, or ask a qualified adviser.

Templates and related guides

FAQ

Questions about safe work method statement (SWMS)

  1. SWMS stands for safe work method statement. It is a short document for one high-risk job that lists the steps of the work, the hazards at each step and the control measures the crew will use, and names who is responsible for them. In Australia it is required by the work health and safety regulations before high risk construction work starts. Elsewhere the same document is usually called a method statement.

  2. Yes. A job safety analysis breaks one task into steps and lists the hazards and controls, and it is often reused each time that task is done. A SWMS covers a whole high-risk job at one workplace, says how the controls will be put in place, monitored and reviewed, and in Australia is a legal requirement for high risk construction work. Safe Work Australia says a SWMS is generally different from a JSA or a safe operating procedure.

  3. Under Australia's model Work Health and Safety Regulations, a SWMS must be prepared before high risk construction work starts. Safe Work Australia's information sheet lists 18 such activities, including a risk of falling more than 2 metres, work in or near a confined space, work near energised electrical services and work around powered mobile plant. Victoria has its own regulations and lists 19. Check the regulations in your state or territory.

  4. Not by name for most work. The legal duty is to carry out a suitable and sufficient risk assessment and, with five or more employees, to record its significant findings. HSE says method statements are not required by law for most construction activities, and that the arrangements for demolition, dismantling or structural alteration must be recorded in writing before work begins. A client's contract often makes one compulsory for the job.

  5. A risk assessment identifies what could cause harm in the work, who could be harmed and what precautions are needed. A method statement takes those precautions and sets out, step by step and in order, how the job will be done. The risk assessment answers what could go wrong. The method statement answers how we will do it. Handed over together they are called RAMS.

  6. The business that will carry out the high-risk work, together with the workers who will do it. Safe Work Australia says the person responsible for carrying out the work is best placed to prepare it, and that managers, contractors, leading hands and workers should all be involved. On a subcontracted job that usually means the subcontractor writes it and gives a copy to the principal contractor before starting.

  7. The work must stop. Safe Work Australia's guidance says that if high risk construction work is not being carried out in accordance with the SWMS it must stop immediately, or as soon as it is safe to do so. The SWMS is then reviewed and, if needed, revised, and work must not resume until it can be done in line with the document. The crew is briefed on the revised version and signs it again.

  8. An SOP is a standing instruction for a routine task done the same way every time by trained people. A SWMS is written for one high-risk job at one place and is rewritten or reviewed for each site, because the hazards depend on where the work is. Safe Work Australia says a SWMS is not meant to be a procedure. It is a tool for confirming and monitoring the control measures at the workplace.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.