Short answer

Production capacity is the most good units a process can make in a period. For one step it is available time divided by the time one unit takes, times the number of machines or people. For a line it is the capacity of the slowest step, the bottleneck.

Machine capacity = available time / cycle time per unit x number of machines. Labor capacity = people x available time / standard time per unit. Work it out for every step: the lowest number is the capacity of the line. A test rig with a 54 second cycle and 27,000 seconds in the shift can make 27,000 / 54 = 500 units. That is before anything goes wrong. Take off planned stops to get effective capacity (483 in the example on this page) and look at what the step has really averaged to get demonstrated capacity (430). Plan with the demonstrated number and improve toward the effective one.

Last reviewed:

What is production capacity?

One test rig, three honest capacity numbers

Example numbers
Theoretical capacity533 a shift

The whole 480 minutes at a 54 second cycle, no stops

Effective capacity483 a shift

After planned stops: breaks and start-up calibration

Demonstrated capacity430 a shift

What the rig has averaged over the last 20 shifts

Demand: 440 a shift

Where the 103 units between 430 and 533 go

Unplanned losses: 53
Planned stops: 50
9
14
30
17
33
  • Rejects: 9
  • Slow cycles and short stops: 14
  • Breakdowns: 30
  • Start-up calibration: 17
  • Breaks: 33

Theoretical capacity 533 units a shift, effective capacity 483 and demonstrated capacity 430, against a demand of 440. Of the 103 units between the top and bottom numbers, 50 are planned stops and 53 are unplanned losses.

Demand of 440 sits below effective capacity and above demonstrated capacity. The rig is big enough. It is the 53 units of unplanned loss that put the cell into overtime.

Production capacity is the largest number of good units a machine, a line or a plant can make in a set period: an hour, a shift, a week. It answers a plain question that sales, planning and finance all ask in different words. Can we make what the customer wants with what we have?

The trouble is that one process has several honest answers, depending on what you count as lost time. A rig that could test 533 units if it never stopped can be planned for 483 once breaks and calibration come off, and may have averaged 430 over the last month. All three are capacity. Arguments about capacity are usually two people quoting different ones. So the first job is to name which number you mean.

Capacity is also not the same as takt time. Takt is what the customer needs from you: available time divided by demand. Capacity is what you can supply. You compare the two, step by step, and the gap tells you where to work.

Theoretical, effective and demonstrated capacity

Operations textbooks and the APICS Dictionary use slightly different names, but they describe the same ladder. Each rung takes off one kind of loss.

The capacity numbers, what each leaves out and when to use it (example values are illustrative)
CapacityAlso calledWhat it assumesUse it forOn the test rig
TheoreticalDesign capacity, maximum capacityThe whole period runs at the ideal cycle with no stops of any kindThe ceiling. Sizing equipment and showing how much is lost28,800 s / 54 s = 533 a shift
EffectivePlanned capacityPlanned stops come off: breaks, changeovers, planned maintenance, set-up checks. Nothing unplanned happensThe target a well-run shift should hit26,100 s / 54 s = 483 a shift
DemonstratedActual output, proven capacityNothing. It is the average good output over recent periodsPromising dates and loading the schedule430 a shift, 20-shift average
RatedCalculated capacityAvailable time x utilization x efficiency, in standard hoursLabor-paced work centers, before you have historySee the labor formula below

Design and effective capacity are the textbook terms (Stevenson; Heizer and Render). Demonstrated and rated capacity are APICS Dictionary terms.

People often ask for the four types of capacity. There is no single official list. The four in the table are the ones you will meet in a plant, and some courses swap rated capacity for safety or protective capacity, which is spare capacity kept on purpose to absorb variation. What matters is the ladder: a ceiling, a plan and a proven number.

The gap between effective and demonstrated capacity is where improvement lives. It is made of breakdowns, short stops, slow cycles, waiting for material and rejects. On a machine these are the losses OEE measures. On manual work they show up as labor losses.

The formulas: machine capacity and labor capacity

A step is paced either by a machine or by people. The sum is the same idea both times, time you have divided by time one unit takes, but the inputs come from different places.

Machine capacity

Machine capacity = available time / time per unit x number of machines. Time per unit is the completion time (the operator's load and unload time at the machine plus the automatic cycle) plus any tool change time spread over the pieces between changes. This is the sum on a process capacity sheet, one of the standardized work forms. Round down: you cannot ship part of a unit.

Labor capacity

Labor capacity = number of people x available time per person / standard time per unit. The standard time already holds a normal pace and the allowances for personal needs, fatigue and small delays. If you want a number to plan with before you have any history, multiply the available hours by utilization (the share of paid hours spent on direct work) and efficiency (standard hours earned per hour worked). APICS calls the result rated capacity.

Capacity formulas for one step (example values are illustrative)
What you wantFormulaExample
Machine capacity per shiftAvailable time / (completion time + tool change time per unit) x machines27,000 / (96 + 4) x 2 = 540
Tool change time per unitTool change time / pieces between changes600 s / 150 = 4 s
Labor capacity per shiftPeople x available minutes / standard minutes per unit3 x 450 / 2.25 = 600
Rated capacity (standard hours)Available hours x utilization x efficiency22.5 x 0.90 x 0.95 = 19.24 h
Rated capacity (units)Rated standard hours x 60 / standard minutes per unit19.24 x 60 / 2.25 = 513
Line capacityThe lowest step capacityThe test rig: 500

Available time here is 480 minutes less 30 minutes of breaks: 450 minutes, or 27,000 seconds.

The same sum for a machine step and a labor step

Example numbers

Machine capacity = available time / time per unit x machines

CNC machining: two machines, tool change every 150 pieces

  1. Time per unit =96 s + 600 s / 150= 100 s
  2. One machine =27,000 s / 100 s= 270
  3. Two machines =270 x 2= 540
Per shift540

Labor capacity = people x available time / standard time

Assembly: three operators, 2.25 standard minutes a unit

  1. At 100% =3 x 450 min / 2.25 min= 600
  2. Rated hours =22.5 h x 0.90 x 0.95= 19.24 h
  3. Rated units =19.24 h x 60 / 2.25 min= 513
Per shift, rated513
Both divide the time you have by the time one unit takes. The machine sum uses a measured cycle. The labor sum uses the standard time, and rated capacity then allows for hours that are not direct work.

Batch steps such as ovens and washers need one more input, the load size: capacity = available time / cycle time per load x units per load. And where yield is below 100%, multiply by the yield, because capacity counts good units.

How to calculate production capacity, step by step

Do this for one product family at a time. A plant-wide number that mixes products with different routings hides the step that matters.

Capacity in seven steps

  1. 1

    List the steps in the routing

  2. 2

    Set the available time

  3. 3

    Get the time per unit

  4. 4

    Work out each step's capacity

  5. 5

    Find the lowest number

  6. 6

    Take off the losses you really have

  7. 7

    Compare with demand

Steps 1 to 5 give the calculated number. Steps 6 and 7 compare it with what the floor has proven and with demand.
  1. 1

    List the steps in the routing

    Every machine and manual step the product passes through, in order. Note how many machines or people each step has and whether it is shared with other products.

  2. 2

    Set the available time

    Shift length less planned stops: breaks, meetings, planned maintenance, changeovers. Use the same time base for every step, or say clearly where one differs.

  3. 3

    Get the time per unit

    For a machine, the manual time at the machine plus the automatic cycle, timed over several pieces. For manual work, the standard time from a time and motion study. Do not use the nameplate rate or the fastest cycle you ever saw.

  4. 4

    Work out each step's capacity

    Available time divided by time per unit, times the number of machines or people. Add tool change time per unit and load size where they apply.

  5. 5

    Find the lowest number

    That step is the bottleneck, and its capacity is the capacity of the line. Check the second lowest too. If it is close, fixing the first will just move the problem there.

  6. 6

    Take off the losses you really have

    Compare the calculated number with what the bottleneck has produced over the last few weeks. The difference is unplanned stops, slow running and rejects. Write down each one.

  7. 7

    Compare with demand

    Set demonstrated capacity against demand per shift. If it is short, you now know how many units, at which step, and which loss is biggest.

Worked example: a four-step valve body cell

Illustrative example. A cell machines, washes, assembles and pressure tests a brass valve body. It runs one shift of 480 minutes with 30 minutes of breaks, so 450 minutes, or 27,000 seconds, are available. Customers take 440 valves a shift, which makes takt time 27,000 / 440 = 61.4 seconds.

Illustrative: capacity of each step in the valve body cell, per shift
StepPaced byResourcesTime per unitSumCapacity per shift
1. CNC machiningMachine2 machines96 s + 4 s tool change27,000 / 100 x 2540
2. WashMachine1 washer45 s27,000 / 45600
3. AssemblyPeople3 operators2.25 standard minutes3 x 450 / 2.25600
4. Pressure testMachine1 rig54 s (12 s manual + 42 s automatic)27,000 / 54500

The pressure test is the bottleneck at 500 a shift. Machining is next at 540. Demand is 440.

Capacity of each step in the valve body cell

Example numbers
1. CNC machining540 a shift

2 machines, 100 s a unit with tool changes

2. Wash600 a shift

1 washer, 45 s a unit

3. Assembly600 a shift

3 operators, 2.25 standard minutes a unit

4. Pressure test500 a shift

1 rig, 54 s a unit. The bottleneck: the cell can ship no more than this

Demand: 440 a shift

Capacity per shift: 1. CNC machining 540, 2. Wash 600, 3. Assembly 600, 4. Pressure test 500. Demand is 440. The pressure test is the lowest and limits the cell.

The shortest bar is the capacity of the whole cell. Every calculated bar clears demand, which is why the problem only shows when you look at what the rig really produces.

On paper the cell is fine. The slowest step makes 500 and the customer wants 440. Every step's time per unit is under the 61.4 second takt. Yet the cell runs overtime most weeks. The reason is in the gap between the calculated number and the proven one.

From theoretical to demonstrated at the test rig

Take the rig through the ladder. Each line takes off one loss, converted to units at 54 seconds each.

Illustrative: the test rig's capacity from theoretical to demonstrated, per shift
StageWhat comes offUnits lostUnits left
Theoretical capacityNothing: 28,800 s / 54 s533
After breaks30 minutes of paid breaks33500
Effective capacity15 minutes of start-up leak calibration17483
After breakdowns27 minutes of unplanned stops a shift, on average30453
After slow cyclesShort stops and re-clamping, about 12.6 minutes14439
Demonstrated capacity9 rejects that have to be reworked and retested9430

Demonstrated capacity is the average of good units per shift over the last 20 shifts. It is 10 short of the demand of 440.

So the honest answer to "what is our capacity?" is 430 a shift, and the plan should be loaded to that. The answer to "what could it be without buying anything?" is 483. The 53 units between them are the first place to look, and winning them back costs far less than a second rig.

Utilization and efficiency: two ratios people mix up

Two ratios describe how much of the capacity you are getting. They share a numerator, actual output, and differ in what they divide by.

Utilization and efficiency of capacity (example values are illustrative)
RatioFormulaWhat it tells youOn the test rig
UtilizationActual output / theoretical (design) capacityHow much of the ceiling you use. Low utilization can be a choice: one shift, long breaks, planned maintenance430 / 533 = 80.7%
EfficiencyActual output / effective capacityHow well you ran against the plan. This one is about problems, not choices430 / 483 = 89.0%

These are the capacity ratios from operations management texts. Labor reporting uses the same two words for different ratios, covered in the guide to labor efficiency and labor variance.

Same output, two different yardsticks

Example numbers

Utilization = actual output / theoretical capacity

80.7%

Actual 430 / theoretical 533

Efficiency = actual output / effective capacity

89.0%

Actual 430 / effective 483

Utilization is 430 over 533, 80.7%. Efficiency is 430 over 483, 89.0%.

Utilization measures against the ceiling, so it falls when you choose to stop. Efficiency measures against the plan, so it only falls when something went wrong.

Read them together. High utilization with poor efficiency means the asset is busy and badly run. Good efficiency with low utilization means it runs well when it runs, and the question is whether you need more hours from it. For labor-paced steps the same words mean something else: utilization is direct hours over paid hours, and efficiency is standard hours earned over hours worked. The labor efficiency and labor variance guide works those through.

Do not chase 100% utilization everywhere. A step that is not the bottleneck should be idle some of the time. Running it flat out builds stock in front of the step that cannot keep up.

The bottleneck sets the capacity of the line

A line can only ship what its slowest step lets through. That step is the bottleneck, and three things follow from it.

  • An hour lost at the bottleneck is an hour lost for the whole line. The valve cell loses 27 minutes a shift at the rig, and that is 30 valves nobody can make up downstream.
  • An hour saved anywhere else changes nothing you can ship. Speeding up the washer from 600 to 700 a shift adds no valves.
  • The bottleneck moves. Lift the rig above 540 and machining becomes the limit. Always look at the next lowest step before you spend money on the lowest.

Find it with numbers, then confirm it with your eyes. Stock piles up in front of a bottleneck and the steps after it wait. The bottleneck calculator does the sum for a routing with cycle times, machine counts and uptime. Where one machine serves several products, load it with the whole mix: its capacity for this product is only what is left after the others.

Labor bottlenecks behave differently from machine ones. You can move a person to an overloaded manual step in minutes, so labor capacity bends with the roster, cross-training and overtime. A machine's capacity only changes when its cycle, its uptime or its hours change. That is why you balance the manual work and check each machine against takt separately.

How to build capacity from standard times

For work that people pace, the standard time is the capacity calculation. One standard, set properly, turns into units per hour, people needed and a plan for next month.

  1. 1

    Start from the standard time per unit

    Observed time, rated to a normal pace, plus allowances. For the valve assembly that is 2.25 standard minutes.

  2. 2

    Turn it into a rate at 100%

    60 / 2.25 = 26.7 units per person per hour. This is what one trained person makes in an hour of direct work at standard performance.

  3. 3

    Multiply by the hours you have

    3 people x 7.5 available hours = 22.5 hours. At 100% that is 22.5 x 26.7 = 600 units.

  4. 4

    Apply utilization and efficiency

    Not every paid hour is direct work, and not every direct hour earns a standard hour. With 90% utilization and 95% efficiency, rated capacity is 22.5 x 0.90 x 0.95 = 19.24 standard hours, or 513 units.

  5. 5

    Check it against history and against takt

    If the team has been averaging 510, the standard and the ratios are sound. Then turn the question round: how many operators does 440 a shift need?

From one standard time to a capacity you can plan with

Example numbers
  1. 2.25 minStandard time per unit

    From the time study of the assembly job

  2. 60 / 2.25
    26.7 an hourOne person at 100% performance
  3. x 3 people x 7.5 hours
    600 a shiftLabor capacity at 100%
  4. x 0.90 utilization x 0.95 efficiency
    513 a shiftRated capacity

    19.24 standard hours. This is the number to load the plan to until you have history

A standard time of 2.25 minutes gives 26.7 units per person per hour, 600 units a shift for three people at 100 percent, and a rated capacity of 513 units after 90 percent utilization and 95 percent efficiency.

Each step adds one assumption. Write all four down, because when the plan is wrong it is one of these that was wrong.

Where you have several products on one team, do the sum in standard hours. Load = the sum of each product's forecast x its standard hours per unit. Capacity = rated standard hours. Load over capacity above 100% in any week is a problem you can see a month ahead. For a product that is not in production yet, the new product time study playbook covers how to estimate the standard before there is anything to time.

The weak point is the standard itself. A capacity plan built on standards from before the last method change, or on times nobody measured, is a guess with decimals. Video helps here: with LeanSuite's Time and Motion Study you film the station and get every element timed on a timeline, so the time per unit behind the capacity number can be checked by anyone who doubts it.

When capacity is short: what to do, in order

Work down this list. The early items are cheap and fast. The last one is a purchase order.

  • Win back unplanned losses at the bottleneck. Breakdowns, short stops and rejects at that one step. In the example they cost 53 units a shift.
  • Shrink planned stops at the bottleneck. Shorten the changeover or the start-up check, and cover breaks with a relief operator so the step keeps running.
  • Cut the time per unit at the bottleneck. Move manual work off the machine cycle, shorten clamp and unload, review the program.
  • Take work away from it. Inspect before the bottleneck so it never spends time on a part that is already scrap. Route what you can to another resource.
  • Add hours at that step only. Overtime or a second shift on the one machine costs far less than running the whole line longer.
  • Add equipment or people. Last, and only after the sums above show the gap that is left.

On the valve cell, two changes close the gap. A master part cuts the start-up calibration from 15 minutes to 5, and a new clamp seal halves the breakdowns from 27 minutes to 13.5. Effective capacity rises from 483 to 494, and demonstrated capacity from 430 to 456 against a demand of 440. No overtime, no second rig.

The test rig before and after two changes

Example numbers

Before

Calibration 15 minutes. Breakdowns 27 minutes a shift.

Effective483
Demonstrated430

Demand: 440

10 short of demand

After

Calibration 5 minutes. Breakdowns 13.5 minutes a shift.

Effective494
Demonstrated456

Demand: 440

16 above demand

Before: effective capacity 483, demonstrated 430, 10 short of demand. After: effective 494, demonstrated 456, 16 above demand.

No new equipment. One planned stop was shortened and one unplanned loss was halved, both at the bottleneck.

Common mistakes and the limits of the sum

  • Quoting theoretical capacity as a promise. Sales hears 533, the floor makes 430, and the gap becomes overtime and late orders.
  • Using the average of all steps. A line's capacity is its lowest step, not the mean.
  • Using nameplate speeds. The rate in the manual was measured on another product in another plant. Time your own.
  • Forgetting the mix. Capacity in units only means something for one product, or for a stated mix. Change the mix and the bottleneck can move.
  • Counting bad units. Capacity is good output. A step with 5% scrap has 5% less capacity than its cycle time suggests.
  • Ignoring changeovers. On a machine that runs several products, changeover time comes straight off available time, and it grows as batches shrink.
  • Treating the number as fixed. Demonstrated capacity drifts with wear, staffing and product changes. Recalculate it on a rhythm, and after any change to the method or the equipment.

The sum also has limits you should say out loud. It assumes steady conditions, so it will not tell you how much stock builds up when times vary from cycle to cycle. It treats people as available hours, when skills, absence and fatigue decide what a shift can really do. And it says nothing about whether the demand figure is right. Use it to find the step to work on and the size of the gap, then go and watch that step.

Tools and templates for capacity

FAQ

Questions about production capacity calculation

  1. Divide the time you have by the time one unit takes, then multiply by the number of machines or people. A machine with a 54 second cycle and 27,000 seconds available in the shift can make 27,000 / 54 = 500 units. Do this for every step in the routing. The lowest result is the capacity of the line.

  2. There is no single official list. The four most used are theoretical or design capacity (no stops at all), effective capacity (after planned stops such as breaks and changeovers), demonstrated capacity (what the process has really averaged) and rated capacity (available time x utilization x efficiency). Some courses list protective or safety capacity in place of rated capacity.

  3. List the steps a product goes through. For each one, work out available time / time per unit x number of machines or people, using cycle times for machines and standard times for manual work. The step with the lowest capacity is the bottleneck and sets the line's capacity. Then compare that number with what the step has really produced and with demand.

  4. Production capacity is the most good units a machine, line or plant can make in a set period, such as a shift or a week. It is quoted at three levels: theoretical capacity with no losses, effective capacity after planned stops, and demonstrated capacity, the output the process has actually proven it can sustain.

  5. Machine capacity = available time / time per unit. Time per unit is the operator's load and unload time at the machine plus the automatic cycle, plus tool change time divided by the pieces between changes. A machine with 27,000 seconds available, a 96 second completion time and 4 seconds of tool change per piece can make 27,000 / 100 = 270 units a shift.

  6. Capacity planning compares load with capacity over time. Load is the forecast for each product multiplied by its standard hours per unit, added up by work center and by week. Capacity is the rated or demonstrated standard hours of that work center. Where load is above capacity you move work, add hours or people, or change the plan.

  7. Utilization is actual output divided by theoretical (design) capacity. Efficiency is actual output divided by effective capacity. A rig that could make 533 units with no stops, is planned for 483 and makes 430 has a utilization of 80.7% and an efficiency of 89.0%. Utilization reflects choices about hours as well as problems. Efficiency reflects problems.

  8. OEE = availability x performance x quality. It measures how much of a machine's planned production time turns into good units at the ideal cycle, so it describes the gap between effective capacity and demonstrated capacity. A machine with an effective capacity of 483 units a shift and an OEE of 89% will average about 430.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.