Predetermined motion time systems (PMTS): what they are, how they work and when to use one
Short answer
A predetermined motion time system (PMTS) sets the time for a manual job without a stopwatch. You break the job into basic motions such as reach, grasp and move, look up a published time for each, and add them up. MTM, MOST and MODAPTS are the best known.
A PMTS is a catalogue of times for basic human motions, measured once from film of many workers and levelled to a normal pace. To use it you describe the method motion by motion, give each motion its code, read the time for that code and add the times. The total is the normal time for the job. You then add allowances, the same way as after a stopwatch study, to get standard time. Because the times come from the method and not from a person, you can set a standard before the job exists. The price is training, analysis time and a method that has to be described exactly.
Last reviewed:
What is a predetermined motion time system?
A PMTS in one picture: the method goes in, a time comes out
Example numbers- 1Describe the method
Right hand takes a bracket from the bench and seats it on a pin, 10 inches each way.
- 2Break it into motions
reach, grasp, move, position, release.
- 3Code each motion
R10B G1A M10C P1SE RL1
- 4Read a time for each code
12 + 2 + 12 + 6 + 2 TMU
- 5Add them: normal time
34 TMU x 0.036 = 1.22 s for this element; 380 TMU for the whole job.
- 6Add allowances: standard time
380 TMU = 0.228 min, x 1.15 = 0.2622 min.
Six steps: describe the method, break it into motions, code each motion, read a time for each code, add them to get normal time (34 TMU for one element, 380 TMU for the job), then add allowances for a standard time of 0.2622 minutes.
A predetermined motion time system is a set of tables. Each row is a basic human motion done under stated conditions, such as reaching 10 inches to an object that sits alone on the bench, and each row carries a time. The times were predetermined: somebody measured them once, from film of many people at work, so you do not have to measure them again. You will also see the names predetermined time system (PTS), predetermined time standards and synthetic times. They all mean the same thing.
The idea rests on one claim that has held up well: a trained person doing the same motion under the same conditions takes close to the same time. If that is true, the time for a whole job is the sum of the times of its motions, and the job's time depends on its method and its layout, not on who was watched on which day.
That is what makes a PMTS different from a time study. A time study measures a person and then rates their pace. A PMTS describes a method and looks the time up. There is no stopwatch and no performance rating, because the rating was done once, when the tables were built.
A note on the search term. People who type motion time into a search box are sometimes after the physics of motion, and MTM and MOST are also the names of unrelated companies and products. This page is about work measurement in manufacturing: how long a manual job should take.
How a PMTS works, step by step
Every system follows the same six steps. What changes from one system to the next is how small the motions are and how the codes are written.
- 1
Fix the method and the layout
Write down where every part, tool and container sits, in inches or centimetres, and which hand does what. A PMTS times a method. If the method is vague, the time is a guess with decimals.
- 2
Break the job into motions
Go through the cycle in order, for each hand. In a detailed system the motions are as small as reach, grasp, move, position and release. In a coarser system one line covers a whole get and place.
- 3
Code each motion
Give each motion the code that matches its conditions: the distance, how exact the placement is, how hard the part is to grasp, the weight. Choosing the right case is the skill of the job and the reason analysts are trained and certified.
- 4
Read the time for each code
Look up the time on the system's data card or in its software. Most systems count in TMU, time measurement units: 1 TMU is 0.00001 hour, which is 0.036 seconds. MODAPTS counts in MODs of 0.129 seconds.
- 5
Add the times, counting simultaneous motions once
When both hands move at the same time, only the longer motion takes time. Multiply by frequency for anything done more than once per piece. The total is the normal time for the cycle.
- 6
Add allowances to get standard time
PMTS times are for work at normal pace with no breaks and no interruptions. Add your site's allowance for personal needs, fatigue and delays exactly as you would after a stopwatch study. The standard time guide covers both allowance formulas.
Machine time is not in any PMTS. If the cycle includes a press stroke, a weld or a cure, take that time from the machine or the process sheet and add it as its own line.
Where predetermined times came from
The root is the Gilbreths. Frank and Lillian Gilbreth filmed work in the 1910s and showed that any manual task is built from a small set of basic motions, which they called therbligs. If the motions are standard, somebody was going to try to give each one a standard time. Asa Segur did it first, with Motion-Time Analysis in the 1920s, and kept his data private.
Two systems then opened the field. Work-Factor, developed by Joseph Quick and colleagues, was published in 1945. Methods-Time Measurement followed in 1948, when Harold Maynard, Gustave Stegemerten and John Schwab of the Methods Engineering Council published the book of the same name. They had filmed operations at Westinghouse at 16 frames a second, counted frames for each motion, and levelled every time to normal pace with the Westinghouse rating system that Maynard and Stegemerten had helped write twenty years earlier. Unlike Segur, they printed their tables. MTM became the reference that most later systems were built on or checked against.
The original MTM is accurate and slow to apply. Most of the history since 1948 is people trading a little accuracy for a lot of speed: Master Standard Data in 1962, MTM-2 in 1965, MODAPTS in Australia in 1966, MOST in Sweden in 1972 and the United States in 1974, MTM-UAS in the mid-1970s. By 1992 the ILO's Introduction to Work Study counted about 200 systems. A handful are in real use today.
From the Gilbreths' film to MOST: sixty-five years of making it faster
1915
First list of 16 basic elements of work
Frank and Lillian Gilbreth
1920s
Motion-Time Analysis, the first system with times. Kept private
Asa Segur
1924
The therblig system published
The Gilbreths
1945
Work-Factor published
Quick, Shea and Koehler
1948
Methods-Time Measurement (MTM), with its tables in print
Maynard, Stegemerten and Schwab
1962
Master Standard Data
Crossan and Nance
1965
MTM-2
International MTM Directorate
1966
MODAPTS
G. C. Heyde, Australia
1972
BasicMOST released in Sweden; United States in 1974
Kjell Zandin, H. B. Maynard and Company
Mid-1970s
MTM-UAS
German, Swiss and Austrian MTM associations
1980
MiniMOST and MaxiMOST
H. B. Maynard and Company
The main systems and how they differ
The systems differ in one thing above all: how big the smallest building block is. Small blocks describe a short cycle precisely and take a long time to write out. Big blocks are quick to apply and blur the detail of a short cycle. Pick the level by how long the cycle is and how often it repeats.
The family map: the bigger the building block, the longer the job it suits
Basic motions
One line per reach, grasp, move, position or release
Fits: Short cycles, very high volume
Combined motions
One line per get or put
Fits: Cycles of about a minute, bench work
Sequences and operations
One line per object moved or tool used
Fits: General assembly, batch production
Large operations
One line per whole activity
Fits: Long, varied or one-off work
Four levels of detail. Basic motions: MTM-1, Work-Factor and MiniMOST, for short high-volume cycles. Combined motions: MTM-2, MSD and MODAPTS. Sequences and operations: BasicMOST and MTM-UAS, for general assembly and batch production. Large operations: MaxiMOST and MTM-MEK, for long or one-off work.
| System | Origin | Building block | Time unit | Fits |
|---|---|---|---|---|
| MTM-1 | Maynard, Stegemerten and Schwab, USA, 1948 | Basic motions: reach, move, turn, grasp, position, release, disengage and others | TMU | Short cycles repeated in very high volume |
| Work-Factor (WF) | J. H. Quick and colleagues, USA, 1945 | Basic motions, with work factors for weight and control | Work-Factor time unit of 0.0001 minute | The same ground as MTM-1; rarely used now |
| MTM-2 | International MTM Directorate, 1965 | Combined motions: get, put and nine others | TMU | Cycles of about a minute and more |
| MSD (Master Standard Data) | Crossan and Nance, USA, 1962 | Combined MTM motions | TMU | Batch work; largely replaced by later systems |
| MODAPTS | G. C. Heyde, Australia, 1966 | Movements sized by the body part that moves | MOD of 0.129 second | Hand and bench work; quick to learn |
| MOST (Basic, Mini, Maxi) | Kjell Zandin, H. B. Maynard and Company, Sweden, 1972 | Whole sequences: move an object, move it along a path, use a tool | TMU | MiniMOST for short cycles, BasicMOST for most assembly, MaxiMOST for long jobs |
| MTM-UAS | German, Swiss and Austrian MTM associations, mid-1970s | Basic operations such as get and place, handle tool, operate | TMU | Batch production with trained operators |
| MTM-MEK | German MTM association | Larger operations than UAS | TMU | One-off and small-batch work |
MTM systems are the property of the MTM associations, MOST of Accenture (which acquired H. B. Maynard and Company) and MODAPTS of the International MODAPTS Association. Each sells training and licensed data.
The detailed pages go further: MTM, with MTM-1, MTM-2, MTM-UAS and the TMU, and MOST and MODAPTS. The motion vocabulary underneath all of them is on the therbligs and motion economy page.
A worked example: from a sum of elements to a standard
Illustrative example. An operator fastens a small bracket to a plate with two screws, seated, with a powered driver hanging in front of them. The job does not run yet, so there is nothing to time. The analyst writes the method from the drawing and a bench mock-up, codes each motion and adds the times by element. The TMU values below are made up for teaching and do not come from any system's data card.
| Element | What the motion analysis covers | TMU | Seconds |
|---|---|---|---|
| 1. Get bracket, place on locating pin | Reach, grasp, move, position, release | 34 | 1.22 |
| 2. Get two screws, start each by hand | Reach to tray, grasp, move, position, turn, twice | 96 | 3.46 |
| 3. Get driver, run both screws, let go | Reach, grasp, move, position on screw, run, twice, release | 210 | 7.56 |
| 4. Put assembly in tote | Grasp, move, release | 40 | 1.44 |
| Cycle total | 380 | 13.68 |
Seconds = TMU x 0.036. The driver's run time in element 3 would come from the tool, not from the motion tables.
| Step | Working | Result |
|---|---|---|
| Normal time in seconds | 380 x 0.036 | 13.68 s |
| Normal time in minutes | 380 x 0.0006 | 0.228 min |
| Standard time, 15% allowance added to normal time | 0.228 x 1.15 | 0.2622 min (15.7 s) |
| Units per hour | 60 / 0.2622 | 228.8 |
| Pieces per 480 minute shift | 480 / 0.2622 | 1,830 |
The 15% is an example. Use your site's allowance and check whether it is added to normal time or is a share of the shift.
Where the 380 TMU go, and how they become a standard
Example numbers- 1Get bracket, place on locating pin34 TMU
- 2Get two screws, start each by hand96 TMU
- 3Get driver, run both screws, let go210 TMU
- 4Put assembly in tote40 TMU
Sum of elements
380 TMU
x 0.036
13.68 s
x 0.0006
0.228 min normal
x 1.15 allowance
0.2622 min standard
60 / standard
228.8 units an hour
The bracket job has four elements: Get bracket, place on locating pin 34 TMU; Get two screws, start each by hand 96 TMU; Get driver, run both screws, let go 210 TMU; Put assembly in tote 40 TMU. Total 380 TMU, 13.68 seconds, 0.228 minutes normal time, 0.2622 minutes standard time with a 15 percent allowance, 228.8 units an hour.
Look at where the time is. Element 3 is 210 of the 380 TMU, 55% of the cycle, and most of it is getting the driver and finding the screw head twice. A stopwatch would have given you 13.7 seconds and no reason. The motion analysis tells you that a driver held in a fixed position above the part, or a two-spindle head, is where the next second comes from. That is the second use of a PMTS, and often the more valuable one: it is a design tool for the method, not only a ruler for it.
Advantages and limits
What a PMTS does well
- It works before the job exists. You can cost a quote, balance a line and compare two layouts from drawings, weeks before the first part is made.
- It needs no performance rating. Nobody has to judge how fast a person was working, which removes the most argued step of a time study.
- It is consistent. Two trained analysts given the same method should land close to each other, and a standard set in one plant can be read in another.
- It forces the method onto paper. You cannot code a motion you have not described, so gaps in the method show up while they are still cheap to fix.
- It shows where the time goes inside a short cycle, motion by motion, which a stopwatch cannot do for anything shorter than a few seconds.
What it does badly
- It only knows manual, repeatable motions. Machine time, process time, waiting and anything done by thinking have to come from somewhere else.
- It times the method on paper, not the job on the floor. If parts stick, bins are placed differently or operators have found a better way, the standard and the work drift apart and nobody is told.
- It takes training. Choosing the wrong case for a reach or a position is easy and each wrong choice is small, so errors hide. Every system owner runs courses and exams for this reason.
- It is slow at the detailed end. Writing out one minute of work in MTM-1 can take a trained analyst hours. That is why the faster systems exist.
- The data is licensed. You may not copy the tables into your own spreadsheet and pass them around, and the software costs money.
- It says nothing about variation. Real cycles vary with the part, the person and the hour. A PMTS gives one figure for a clean cycle.
One more limit is easy to miss. The times assume a trained operator who already knows the job. A new person on a new product will be well above the PMTS figure for the first days or weeks, so plan the ramp separately. The page on estimating cycle time for a new product shows how to combine a PMTS figure with a learning curve.
When to use a PMTS, a stopwatch or video
The three methods answer the same question from different evidence. A PMTS reasons from the method. A stopwatch measures a person at the station. Video measures the same thing and keeps the recording, so the timing can be checked and the motions can be studied afterwards.
| Situation | Best fit | Why |
|---|---|---|
| The job does not exist yet | PMTS | There is nothing to time. Build the standard from the planned method and check it by timing once the job runs. |
| Comparing two layouts or two methods on paper | PMTS | The difference shows up motion by motion, with no need to build both. |
| A short, manual cycle made in very high volume | PMTS at the detailed level, checked with video | A tenth of a second matters, and only motion analysis sees it. |
| A running job that needs a standard this week | Stopwatch or video time study | Faster than a PMTS analysis and it includes what really happens at the station. |
| Operators and engineers disagree about a standard | Video | Everybody can watch the same cycle again and see which reading was kept and why. |
| Long, irregular work such as maintenance or material handling | Work sampling, or a coarse system such as MaxiMOST | Too long and too varied to code motion by motion or to time cycle by cycle. |
| Machine-paced work | Machine data plus a time study of the manual part | A PMTS has nothing to say about the machine. |
PMTS, stopwatch or video: four questions
Is the job not running yet, or only on paper?
Yes → PMTS: build the time from the planned method
No ↓
Is the work long, irregular or different every time?
Yes → Work sampling, or a coarse system such as MaxiMOST
No ↓
Is the cycle short and made in very high volume?
Yes → Detailed PMTS for the method, checked against video
No ↓
Will the timing be questioned, or do the motions need study?
Yes → Video time study: everyone can watch the same cycle again
No → A stopwatch time study is enough
If the job is not running yet, use a PMTS. If the work is long and irregular, use work sampling or a coarse system. If the standard is likely to be questioned or the motions need study, use video. If you only need a rate for a running job quickly, use a stopwatch study. Otherwise a video time study.
In practice the methods work together. Set the first standard for a new job with a PMTS. When the job is running, film a few cycles and time them. If the two figures agree, you have a standard you can defend from both sides. If they do not, the gap is the interesting part: either the method on the floor is not the method on paper, or the analysis missed something. The comparison of time study, motion study and method study explains which question each one answers, and work sampling covers the long, irregular jobs.
The people side
A standard built at a desk can feel like a number handed down from nowhere. Operators cannot see how it was made, and unlike a time study nobody stood at the station and asked them anything. That is a real weakness, and it is fixed by how you introduce the standard, not by the arithmetic.
- Walk the method with the people who do the job before you publish a time. They will tell you about the bin that is always on the wrong side and the part that needs a second push.
- Show the analysis. A sheet that lists each motion with its time is easier to accept than a single figure, because anyone can point at the line they disagree with.
- Train operators to the method the standard assumes. A PMTS time is only fair to a person who has been shown that method and given time to learn it.
- Check the standard against the running job and change it when the method changes, in both directions.
- Where a collective agreement covers work measurement, it may name the systems that can be used and how a standard is challenged. Follow it. This is general practice, not legal advice.
How to start, and what to use meanwhile
- Pick one system and stay with it. Mixed systems make standards that cannot be compared. Let cycle length and volume decide: detailed systems for short, high-volume cycles; sequence systems such as BasicMOST or MTM-UAS for general assembly.
- Send the people who will set standards on the owner's course. A system applied from a photocopied table by an untrained person gives numbers nobody can stand behind.
- Build standard data. Once you have analysed loading a fixture or fastening a screw of each size, the next part number takes minutes.
- Until then, measure what you have. The time study sheet and the standard time calculator turn timed cycles into a standard, and the new product time study playbook covers jobs that are just starting.
For jobs that are already running, LeanSuite's Time and Motion Study times every element from one phone video and reports cycle time, standard time, takt and units per hour, each linked to its video frame. It is a quick way to check a PMTS standard against what really happens at the station. The wider guide to time and motion study shows where each of these methods sits.
Go deeper
This page is the short version. These guides cover each part in full.
- Standard Work in Manufacturing: A Complete GuideWriting down the method that a predetermined time describes, and keeping it followed on the floor.
- The Three Elements of Standard Work: Takt Time, Work Sequence, Standard WIPWhere the element times go next: takt time, the work sequence and standard in-process stock.
- Standard Work Tools: Combination Sheet, Standardized Work Chart, Job BreakdownThe documents that carry manual, walk and machine times to the station.
- Yamazumi Chart: What It Is and How to Make One in 7 StepsStacking element times by operator against takt, which works the same with PMTS times as with timed ones.
All our articles on this subject are in the standard work, sops and training topic.
Free templates and tools
- Time study sheetTime each element over 10 cycles and work out the average, lowest repeatable and standard time. Excel does the sums.
- Process capacity sheet templateEach machine in a part's routing with manual, auto and tool change time, its capacity per shift, and the step that limits the cell against demand.
- Standard time calculatorObserved times, a rating and an allowance in; normal time, standard time, units per hour, pieces per shift and labour cost per unit out, with the working.
- Time study sample size calculatorHow many cycles of an element to time, from your first readings, with the t formula, the ILO formula and the range method.
- Line balancing calculatorLine efficiency, balance delay and the minimum number of stations from station times and takt.
Doing this in LeanSuite
Time and Motion Study
Times every element from one phone video of the process and reports cycle time, standard time, takt and units per hour, each linked to its video frame.
See Time and Motion StudyAI Video Analysis
One process video becomes a time and motion study, an ergonomic study, line balancing and more.
See AI Video Analysis
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about predetermined motion time systems (PMTS)
PMTS stands for predetermined motion time system. It is a way to set the time for a manual job without a stopwatch: the job is broken into basic motions such as reach, grasp, move and position, each motion gets a published time from the system's tables, and the times are added. MTM, MOST and MODAPTS are the best known systems. The result is a normal time, to which allowances are added.
Predetermined standards, or predetermined time standards, are time standards built from published times for basic motions, not from timing a person. The motion times were measured once from film of many workers and levelled to a normal pace. An analyst describes the method, codes each motion, adds the times and applies allowances. Because nothing is timed, a standard can be set before the job runs.
Normal time = the sum of the motion times x their frequency per piece. Standard time = normal time x (1 + allowance). In systems that count in TMU, seconds = TMU x 0.036 and minutes = TMU x 0.0006. A cycle of 380 TMU is 13.68 seconds or 0.228 minutes, and with a 15% allowance added the standard is 0.2622 minutes, about 229 units an hour.
Methods-Time Measurement (MTM) is the classic example. Published in 1948 by Maynard, Stegemerten and Schwab, it gives times for reach, move, turn, grasp, position, release and other basic motions in TMU, where 1 TMU is 0.036 seconds. MOST, from H. B. Maynard and Company, and MODAPTS, from Australia, are faster systems built on the same idea. Work-Factor and Master Standard Data are older ones.
A time study measures a real operator with a stopwatch or video and adjusts for their pace with a performance rating. A PMTS measures nobody: it describes the method motion by motion and looks up a time for each motion. A time study needs a running job and captures what really happens. A PMTS works from a drawing or a mock-up and captures only what the method says should happen.
No. MTM, MOST and MODAPTS times are for work at a normal pace with no breaks and no interruptions, so they are normal times. To get a standard time you add your site's allowances for personal needs, fatigue and unavoidable delays, exactly as you would after a stopwatch study. Machine and process times are not in the tables either and are added as separate lines.
Related guides and tools
- MTM: MTM-1, MTM-2, MTM-UAS and what a TMU is
- MOST and MODAPTS: sequence models, index values and MODs
- Therbligs and motion economy: the motions underneath every system
- Standard time: adding allowances to a normal time
- How to conduct a time study with a stopwatch or video
- How to estimate cycle time for a product that does not exist yet
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk
Or browse the topics, the full library and the lean glossary.
Rather see it on your own problem?
Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.