Practical guide · TPM and maintenance

Time study in maintenance work: wrench time, DILO studies and planned job times

Short answer

Most maintenance work is too long and too varied to time with a stopwatch. Measure it two ways. Use work sampling to find wrench time, the share of paid hours spent with tools on the job. Use planner estimates and comparison with known jobs to put a planned time on each work order.

A production time study needs a short job that repeats. Maintenance jobs run for hours, differ every time and are spread across the plant, so the two questions are answered separately. Where does the crew's time go is a work sampling question: tally what each person is doing at random moments over two weeks, and the share found on the tools is wrench time. A day in the life of study, where one person is followed for a shift, then shows why the rest was lost. How long should this job take is an estimating question: a planner estimates a smooth job by a qualified technician, checked against work order history or slotted against benchmark jobs. Stopwatch and video studies still fit the maintenance work that repeats, such as lubrication routes and bench rebuilds.

Last reviewed:

Why a stopwatch time study does not fit most maintenance work

Where a maintenance crew's paid hours go

Example numbers
  • Wrench time: hands on tools at the job34.0% · 163.0 h
  • Travel to and between jobs15.0% · 72.0 h
  • Getting parts and materials11.0% · 53.0 h
  • Getting tools6.0% · 29.0 h
  • Waiting: permit, lockout, equipment release12.0% · 57.5 h
  • Instructions and job assignment7.0% · 33.5 h
  • Breaks and personal time10.0% · 48.0 h
  • No job in hand: late start, early finish, idle5.0% · 24.0 h

A bar of 480 paid hours a week for a crew of 12, split by what 960 random observations found. Wrench time is 34.0%, or 163 hours. The rest is travel, getting parts and tools, waiting, instructions, breaks and time with no job in hand.

Wrench time is the dark part: 163 of 480 paid hours. Everything else is time the crew was at work but not on the tools, and most of it is set by how jobs are planned and scheduled, not by how hard anyone works.

A time study works on a job that repeats: the observer breaks it into elements, times a run of cycles and builds a standard time. An assembly station gives you 60 cycles in an hour. A gearbox change gives you one cycle in a shift, and the next gearbox change will be on a different machine, with different access, and a seized bolt that was not there last time.

A production job and a maintenance job, as things to measure

  • Production job

    Cycle
    Seconds to minutes, the same each time
    Place
    One station
    Method
    Fixed and written down
    Volume
    Hundreds of cycles a shift
    Biggest loss
    Inside the cycle: reaches, walks, waits
    Method that fits
    Time study, video or a predetermined time system
  • Maintenance job

    Cycle
    Minutes to days, different each time
    Place
    Anywhere on site, plus the shop and the stores
    Method
    Partly decided at the job, after the fault is found
    Volume
    Often one of a kind this month
    Biggest loss
    Around the job: travel, parts, permits, instructions
    Method that fits
    Work sampling for the crew, estimating for the job
The loss in a production job is inside the cycle. In a maintenance job it is around the job, which is why the method changes.

The fifth row matters most. On a line, the waste is inside the cycle, so you study the cycle. In maintenance, the hands-on work is often done well and the loss sits around it: the walk to the job, the trip to stores, the wait for a permit. A stopwatch pointed at the repair itself measures the part that was fine.

So maintenance measurement splits in two. One question is about the crew: of the hours we pay for, how many reach the tools? That is wrench time, and work sampling answers it. The other is about the job: how many hours should the schedule allow for this work order? That is a planned job time, and estimating answers it. The wider family of methods is in the guide to time and motion study.

What is wrench time?

Wrench time is the share of a maintenance crew's paid time spent at the job with tools in hand. It is also called hands-on tool time, or tool time. Doc Palmer, whose Maintenance Planning and Scheduling Handbook is the usual reference, defines it as a measure of craftspeople at work, using tools, in front of jobs.

What counts as wrench time and what does not
Counts as wrench timeDoes not count
Repairing, replacing, adjusting or aligning at the equipmentTravel to the job, between jobs and back to the shop
Inspecting and measuring as part of the jobGetting parts and materials, and waiting at the stores counter
Lubricating, cleaning and tightening on a PMGetting tools, or going back for one
Fault finding at the machine with a meter or by testWaiting for a permit, a lockout, a crane or for operations to release the machine
Bench work in the shop on a removed partGetting instructions or a job assignment
Breaks, late starts, early finishes and time with no job in hand

The right column follows Palmer's list of what wrench time leaves out. Sites differ at the edges, for example on job paperwork, which Palmer's handbook counts as direct work. Write your own rules down before the study and keep them the same for every study after it.

The wrench time calculation

Wrench time is a percentage: the number of observations that found a person on the tools, divided by all observations, x 100. If 326 of 960 random observations of a crew find someone working hands-on, wrench time is 326 / 960 = 34.0 percent. To turn it into hours, multiply by paid hours: a crew of 12 on 40 hours each is paid for 480 hours a week, and 34.0 percent of that is 163 hours on the tools.

What is a typical wrench time?

Palmer writes that industry experience puts typical wrench time between 25 and 35 percent, and that planning and scheduling can lift it above 50 percent. His later columns use 35 percent as the usual figure and 55 as what good planning and scheduling reach. Treat these as one experienced practitioner's range and not as a benchmark from a published survey: an Automation World review of the figures in circulation found very few backed by a study a reader can check. Your own number, measured the same way twice, is worth more than anyone's benchmark.

A low figure does not mean the crew is slow. Palmer's point is the opposite: the question a wrench time study asks is what delays keep skilled people away from the job. Whether the hands-on work itself is done efficiently is a different question, and wrench time does not answer it.

How to run a wrench time study with work sampling

Nobody can follow a whole crew around a plant with a stopwatch. Work sampling gets the same answer from glances: at random moments an observer notes what each person is doing at that instant, and the tallies give the share of time on each activity. The guide to work sampling covers the method in general. For a maintenance crew it runs like this.

A wrench time study in seven steps

  1. 1

    Agree the purpose with the crew

  2. 2

    Define the categories

  3. 3

    Set the number of observations

  4. 4

    Draw random round times

  5. 5

    Observe and tally

  6. 6

    Calculate shares and margins

  7. 7

    Act on the delays, then repeat

The first step and the last decide whether the study is worth doing: the crew has to trust it, and something has to change because of it.
  1. 1

    Agree the purpose with the crew

    Say what the study is for: finding the delays that keep people off the tools. Say what it is not for: rating individuals. Agree it with the supervisor and, where there is one, the union, before the first round.

  2. 2

    Define the categories

    Six to ten, each with a written rule an observer can apply in a second: wrench time, travel, getting parts, getting tools, waiting, instructions and assignment, breaks, no job in hand. Split a category only if you would act differently on the two halves.

  3. 3

    Set the number of observations

    Decide how tight the answer has to be and work back from the formula in the next part. About 1,000 observations gives plus or minus 3 points on a wrench time near 35 percent.

  4. 4

    Draw random round times

    Pick the times of each round from a random number table or a spreadsheet, across the whole shift including the first and last half hour, on every day of the week. Fixed rounds catch the same point of every routine.

  5. 5

    Observe and tally

    At each time, find each person on the list and record what they are doing at the instant you first see them. Do not wait to see what they do next. Tally by category. Do not write names on the sheet.

  6. 6

    Calculate shares and margins

    Divide each category's tallies by the total. Put the 95 percent margin next to every percentage, and convert the big ones into hours a week.

  7. 7

    Act on the delays, then repeat

    Take the largest delay categories to the planner, the stores and operations. Change one or two things. Run the same study again, with the same rules, to see whether wrench time moved.

How many observations a wrench time study needs

A sampling result is a percentage with a margin of error. At 95 percent confidence, the number of observations needed is n = 1.96 squared x p x (1 minus p) / e squared, where p is the share you expect and e is the margin you can accept, both as decimals. With an expected wrench time of 35 percent, p x (1 minus p) is 0.35 x 0.65 = 0.2275, and the numbers come out as below.

Observations needed for a wrench time near 35 percent, at 95 percent confidence
Margin you can acceptObservations neededWhat that looks like for a crew of 12
Plus or minus 5 points350About 30 rounds: 4 days at 8 rounds a day
Plus or minus 4 points547About 46 rounds: 6 days at 8 rounds a day
Plus or minus 3 points972About 81 rounds: 10 days at 8 rounds a day
Plus or minus 2 points2,185About 182 rounds: 23 days at 8 rounds a day

Calculated from the formula above with p = 0.35. Halving the margin takes four times the observations.

How sure a wrench time of 35 percent is, by number of observations

Example numbers
  • 100 observations (± 9.3 points)25.7% to 44.3%
  • 200 observations (± 6.6 points)28.4% to 41.6%
  • 400 observations (± 4.7 points)30.3% to 39.7%
  • 960 observations (± 3.0 points)32.0% to 38.0%
  • 2,000 observations (± 2.1 points)32.9% to 37.1%
  • 4,000 observations (± 1.5 points)33.5% to 36.5%

For a true wrench time of 35 percent, the 95 percent range from 100 observations is plus or minus 9.3 points, 200 observations is plus or minus 6.6 points, 400 observations is plus or minus 4.7 points, 960 observations is plus or minus 3.0 points, 2000 observations is plus or minus 2.1 points, 4000 observations is plus or minus 1.5 points.

Each bar is the range the true figure sits in, 95 times in 100. A one-day walk-round gives a range too wide to act on. Around 1,000 observations gives plus or minus 3 points, which is enough to tell 35 percent from 45.

Two cautions. First, the formula assumes every observation is independent, and twelve people seen in one round are not quite that, because a plant-wide event such as a line stop moves several of them at once. So spread the rounds over more days sooner than adding rounds to one day, and treat the margin as a little wider than the formula says. Second, a small study is nearly useless for comparing before and after. Palmer's own short design, two people sampled every half hour for five days, is about 160 observations and he gives it as accurate to about plus or minus 7 percent. That will tell you wrench time is nearer 30 than 60. It will not show a 5 point improvement.

A worked wrench time study

Illustrative example. A plant has a day crew of 12 mechanics and electricians, each paid for 40 hours a week, so 480 paid hours. The reliability engineer wants wrench time to within 3 points, so she plans 8 random rounds a day for 10 working days: 8 x 12 x 10 = 960 observations. The category rules are agreed with the crew and the tally sheet carries no names.

The tally sheet: day 1 of 10, then the whole study

Example numbers
Seen at the instant of the round07:2208:0509:4110:1311:0212:4813:3714:54Day 110 daysShare
Wrench time254553543332634.0%
Travel322113211514415.0%
Getting parts112121111010611.0%
Getting tools210101016586.0%
Waiting221211211211512.0%
Instructions201111017677.0%
Breaks0020211179610.0%
No job in hand010101126485.0%
People tallied121212121212121296960100%

A tally sheet with eight activity categories down the side and eight random round times across. Each round records what all 12 people were doing, so each column adds to 12. Day 1 has 96 observations, 33 of them wrench time. The whole study has 960, 326 of them wrench time.

Each column is one round at a random time, and each column adds to 12 because every person on the crew is tallied once. Note what is missing: there are no names on the sheet.
Illustrative: the wrench time study, 960 observations over 10 days
CategoryObservationsShareMargin at 95%Hours a week (of 480)
Wrench time32634.0%± 3.0163.0
Travel to and between jobs14415.0%± 2.372.0
Waiting: permit, lockout, equipment release11512.0%± 2.157.5
Getting parts and materials10611.0%± 2.053.0
Breaks and personal time9610.0%± 1.948.0
Instructions and job assignment677.0%± 1.633.5
Getting tools586.0%± 1.529.0
No job in hand485.0%± 1.424.0
Total960100%480.0

Margin = 1.96 x the square root of p x (1 minus p) / 960, in percentage points. Hours = share x 480.

Wrench time is 34.0 percent, give or take 3.0, so somewhere between 31.0 and 37.0. In hours, the crew is on the tools for 163 of the 480 hours the plant pays for. The two categories a planner can attack directly, waiting and getting parts, add up to 23.0 percent, or 110.5 hours a week. Travel is larger still, but some travel is unavoidable on a spread-out site, so it comes second.

What the plant changed, and the second study

The plant makes two changes. Parts for every planned job are kitted and staged the day before, so nobody walks to stores mid-job. Permits and lockouts for the next morning's jobs are booked with operations the afternoon before. Eight weeks later the same engineer repeats the study: the same categories, the same rules, 960 observations.

Illustrative: the crew before and after kitting and booked permits
BeforeAfter
Observations960960
Wrench time observations326422
Wrench time34.0%44.0%
95 percent range31.0% to 37.0%40.8% to 47.1%
Getting parts11.0% (53.0 h)6.5% (31.0 h)
Waiting12.0% (57.5 h)7.5% (36.0 h)
Wrench hours a week163211

The two wrench time ranges do not overlap, so the rise is more than sampling noise.

Two studies, same crew, same paid hours

Example numbers
  • Before: 326 of 960 observations31.0% to 37.0%
  • After: 422 of 960 observations40.8% to 47.1%
  • Before

    163 h

    wrench time a week at 34.0%

  • After

    211 h

    wrench time a week at 44.0%

  • Gain

    48 h

    a week, the hands-on hours of 3.5 more people at the old rate

Before, wrench time was 34.0% with a 95 percent range of 31.0% to 37.0%. After kitting parts and booking permits, it was 44.0% with a range of 40.8% to 47.1%. The ranges do not overlap. Hands-on hours went from 163 to 211 a week.

The two ranges do not overlap, so the rise is more than sampling noise. Nobody worked faster. The crew of 12 did 48 more hours of hands-on work a week because parts were kitted and permits were ready.

The crew now does 211 hands-on hours a week where it did 163: 48 more, from the same 12 people and the same paid hours. At the old rate of 163 / 12 = 13.6 hands-on hours per person, that is the tool time of 3.5 more people. Palmer makes the same point with rounder numbers: a workforce that goes from 25 to 50 percent wrench time does twice the work, so 30 people do the work of 60. The gain is only real if there is planned work ready to fill the hours, which is what a planned maintenance backlog is for.

The DILO study: a day in the life of one technician

A DILO study, short for day in the life of, is the opposite of sampling. An observer stays with one person for a whole shift and writes down everything that happens with the time it started. Sampling tells you 11 percent of the crew's time goes on getting parts. A DILO shows you the mechanic leaving a half-stripped gearbox at 08:50 to fetch a gasket that should have been in the kit.

Illustrative example. One mechanic from the same crew is followed from 07:00 to 15:30, with his agreement. Of 480 paid minutes, 185 are on the tools: 38.5 percent. That is close to the crew's sampled figure, but the single number is not what the day is for. One person on one day proves nothing about the crew. What it gives is the list of causes, in order, with times.

A day in the life of one mechanic

Example numbers
  1. 07:00Shift meeting, jobs handed out15 min
  2. 07:15Collect tools, walk to job 120 min
  3. 07:35Wait for the permit and lockout25 min
  4. 08:00Job 1: strip the gearbox coupling50 min
  5. 08:50Walk to stores for a gasket that was not in the kit30 min
  6. 09:20Break15 min
  7. 09:35Job 1: rebuild and close up45 min
  8. 10:20Walk to job 2 at the far end of the plant25 min
  9. 10:45Look for the drawing, ask the supervisor25 min
  10. 11:10Job 2: remove the valve actuator20 min
  11. 11:30Lunch (unpaid)30 min
  12. 12:00Job 2: fit the new actuator30 min
  13. 12:30Fetch a torque multiplier from the shop25 min
  14. 12:55Wait for operations to release the line for a test35 min
  15. 13:30Job 2: stroke test and adjust25 min
  16. 13:55Break15 min
  17. 14:10Walk back to the shop15 min
  18. 14:25No next job assigned25 min
  19. 14:50Called to a conveyor stop, walk there10 min
  20. 15:00Reset and re-track the belt15 min
  21. 15:15Wash up, end of shift15 min

A timeline of one mechanic's shift from 07:00 to 15:30. Of 480 paid minutes, 185 are wrench time, which is 38.5%. The wrench time comes in six blocks, the longest 50 minutes, broken up by a trip to stores, a hunt for a drawing, a trip for a tool and two waits.

The strip shows what a tally cannot: the order of events. Wrench time (dark) came to 185 of 480 paid minutes, in six pieces, and every break in it has a cause a planner could have removed: a part missing from the kit, a drawing not attached, a tool not listed, a permit not ready.

Work sampling and a DILO study on a maintenance crew

  • Work sampling

    Covers
    The whole crew, for two weeks or more
    Gives
    The share of time in each category, with a margin
    Good for
    The wrench time figure, and before and after comparison
    Weak at
    Saying why a delay happened
    Observer time
    Minutes per round, many rounds
  • DILO study

    Covers
    One person, for one shift
    Gives
    The sequence of events and the cause of each delay
    Good for
    Finding what to fix, and explaining the figure to managers
    Weak at
    Being typical: one day, one person, and they know they are watched
    Observer time
    A full shift per study
Sampling gives the number. The DILO gives the reasons. Run them in that order.
  • Run sampling first for the number, then two or three DILO days on different crafts and shifts for the causes.
  • Ask for volunteers and tell them the delays are the subject. The observer is there to see what gets in the way, and should say so.
  • Log what happened and the reason, as the technician gives it. Do not coach, help or hurry the job.
  • Share the day's log with the person who was followed before anyone else sees it.
  • Never quote a DILO percentage as the crew's wrench time. It is a sample of one.

Planned job times: how a maintenance job gets its hours

Wrench time is about the crew. The second measurement is about each job: the hours a planner writes on the work order so that the scheduler can fill the week. There are five ways to get that number, and most plants use the first three.

Five ways to set a planned time for a maintenance job

  • Planner's estimate

    How it works
    A planner who has done the trade estimates the hours for a smooth job by a qualified technician, and keeps the estimate with the job plan for next time.
    Use it for
    Most corrective work. Fast, and good enough to schedule with.
  • Work order history

    How it works
    Take the actual hours booked to the same job on the same equipment the last few times it was done. Use the middle value, not the average, so one bad job does not set the time.
    Use it for
    Repeating PMs and common repairs, where hours are booked honestly to the right work order.
  • Comparative estimating (slotting)

    How it works
    Keep a library of benchmark jobs with known work content, grouped into time ranges. Compare the new job with the benchmarks, drop it into the range it fits and give it that range's slot time.
    Use it for
    Sites that want consistent times across planners. This is the idea behind Universal Maintenance Standards.
  • Standard data

    How it works
    Build the job from published or in-house element times for tasks such as removing a flange or pulling cable, then add travel and allowances.
    Use it for
    Large organizations with an engineered standards program, such as the US Navy's Engineered Performance Standards.
  • Direct time study or video

    How it works
    Time the job itself over several cycles, as you would a production job.
    Use it for
    Only the maintenance work that repeats: routes, changeovers, bench rebuilds.
Most plants live on the first three. Direct timing is for the maintenance work that repeats.

What are Universal Maintenance Standards?

Universal Maintenance Standards, or UMS, is a comparative estimating system that has been in use since the mid 1950s and was described by William Hodson of H. B. Maynard and Company in a 1962 SAE paper. It rests on four things: standard work groupings, spread sheets, bench mark jobs and standard times. The work content of a set of benchmark jobs is measured carefully once. Each benchmark is placed on a spread sheet in a time range. A planner then estimates any new job by finding the benchmarks it most resembles and giving it the standard time of that range. The insight is that a planner cannot tell a 2.4 hour job from a 2.6 hour job, but can reliably tell that a job belongs with the 2 to 3 hour jobs and not with the 4 to 6 hour jobs.

What a planned job time includes and leaves out

  • Include the hands-on work content, for the number of people the job needs. Two people for three hours is six labor hours and three hours of duration: write both.
  • Include job preparation and travel if your system adds them per job, as UMS does. If your scheduler handles travel as a general loading factor, leave them out. Do not do both.
  • Include an allowance for personal time and minor delays if your standards use one, and say what it is.
  • Leave out the delays that planning exists to prevent: waiting for parts, hunting for drawings, a permit that was not ready. Padding the estimate for them hides the problem the wrench time study is trying to find.
  • Leave out the unknowable. If the job may turn into a bigger repair once the cover is off, plan the inspection and plan the repair as a separate job.

A PM job time built up

Illustrative example. A planner needs a time for the quarterly PM on a process pump. She lists the hands-on tasks and estimates each: lock out and prove dead 0.3 hours, remove the guard and inspect the coupling 0.4, change the bearing housing oil 0.5, check and record alignment 0.8, grease the motor bearings 0.2, refit the guard and test run 0.4. That is 2.6 hours of work content, which sits in the plant's 2.0 to 3.0 hour benchmark group, so it takes that group's slot time of 2.5 hours.

Illustrative: the planned time for the quarterly pump PM
StepHoursRunning total
Work content of six tasks2.6
Slot time for the 2.0 to 3.0 hour group2.52.5
Job preparation: read the plan, collect the kit+ 0.32.8
Travel to the pump house and back+ 0.33.1
Allowance at 15 percent of 3.1+ 0.473.57
Planned time, rounded to the half hour3.5

One mechanic, so 3.5 labor hours and 3.5 hours of duration. The slot ranges and the 15 percent allowance are this example plant's own; use yours.

Building the planned time for one PM job

Example numbers
  • Work content: six tasks at the pump2.6 h
  • Slotted: benchmark group 2.0 to 3.0 h2.5 h
  • Add job preparation+ 0.3 h
  • Add travel to the pump house and back+ 0.3 h
  • Add the 15% allowance+ 0.47 h
  • Planned time, to the nearest half hour3.5 h

The work content of the pump PM is 2.6 hours, which falls in the 2.0 to 3.0 hour benchmark group and takes its slot time of 2.5 hours. Adding 0.3 hours of job preparation, 0.3 hours of travel and a 15% allowance gives 3.57 hours, planned as 3.5 hours.

The estimate is built for a smooth job by a qualified mechanic. It leaves out waiting for parts or permits on purpose: those are for the planner to prevent, not to budget for. And it is rounded to the half hour, because a maintenance estimate is not accurate to the minute.

Do not chase accuracy beyond that. Palmer notes that planner estimates for single jobs can be off by as much as plus or minus 100 percent, a five hour job taking two hours or nine, and that this is fine because as many jobs run over as under. Across a week of 40 jobs the errors mostly cancel, and the week is what the schedule needs. He also warns against scoring planners or crafts on actual against planned hours for each job: it teaches planners to pad. The maintenance job plan template has a place for the estimate, the crew size and the feedback from the last time the job was done.

Where a stopwatch or a camera does fit in maintenance

Some maintenance work repeats often enough to study like production work. For these jobs a normal time study, or a study from video, gives a better time than any estimate, and it shows the method as well.

  • Lubrication and inspection routes. The same route every week is a cycle. Film or walk it, draw the path on a spaghetti diagram and re-sequence the stops.
  • PMs done many times a year on identical equipment, such as filter changes on 30 air handlers. Time three or four and use the result for all of them.
  • Changeovers and cleaning between runs. These are maintenance-like work with a production clock running, and the method is in the guide to SMED.
  • Bench work in the shop: rebuilding the same pump, valve or motor model. The bench is a workstation, and the ideas in workstation design apply to it.
  • Planned shutdown tasks done by a team in a fixed order. The guide to timing long-cycle and team work covers jobs that run for hours with several people.

Video suits these jobs because a single cycle can run for an hour and nobody wants to repeat it for the observer's benefit. The guide to a time study from video covers how to film and break down a job. LeanSuite's time and motion study works this way: film the job on a phone and the AI times every element on a timeline that links back to the footage, split into value-added, necessary and waste, for an engineer to review and certify. It measures the job in the frame. It does not replace a wrench time study, because work that roams across a plant cannot be filmed from one spot.

Maintenance work also puts people in bad positions: overhead, kneeling, inside machines. If a repeating job is awkward as well as slow, an ergonomic assessment of the same footage is worth the extra hour.

The people side: why crafts distrust being measured

Skilled trades have long memories of studies that ended in headcount cuts, and a figure like 34 percent sounds like an accusation when it is read out without context. If the crew decides the study is about them, they will change what they do when the observer appears and the number will be worthless. Most of the work of a wrench time study is done before the first round.

  • Say what the number means before anyone sees it. Wrench time measures the system around the crew: planning, stores, permits, scheduling. Skilled people standing at a stores counter are not the cause of the queue.
  • Tally by activity, never by name, and show the blank sheet to the crew so they can see there is no name column.
  • Do not use the result in appraisals, discipline or comparisons between individuals. Say so in writing, and keep to it.
  • Involve the crew in setting the categories. They know where the time goes and will name delays an engineer would not think of.
  • Give the results to the crew first, with the list of delays and what management will do about each one.
  • Where a union agreement or works council covers work measurement or observation, follow it and bring the representatives in at the start.

This is general practice, not legal or labor relations advice. The guide to resistance to change on the shop floor covers the wider conversation.

Mistakes in maintenance time studies

Maintenance measurement mistakes and what to do in their place

  • Mistake

    Using wrench time to rank individuals

    What goes wrong: The crew performs for the observer, the data is useless and the next study is refused.

    Do this

    Tally by activity with no names. Report the crew figure and the delays only.

  • Mistake

    Sampling on fixed rounds

    What goes wrong: A round at ten past every hour catches the same point of every routine, and people learn when to expect it.

    Do this

    Draw random times across the whole shift, including the start and the end.

  • Mistake

    Treating wrench time as an efficiency target

    What goes wrong: A target of 55 percent gets met by looking busy, or by skipping the permit and the planning that make the job safe.

    Do this

    Use it as a measure of planning and scheduling. Set targets on the delays: parts kitted, permits ready, jobs planned.

  • Mistake

    Estimating to the minute

    What goes wrong: A plan of 3 hours 12 minutes claims an accuracy no maintenance estimate has, and invites arguments over each job.

    Do this

    Estimate in half hours or in slot times. Judge the estimates over a week of jobs, not one.

  • Mistake

    Padding estimates for delays

    What goes wrong: The schedule fills up with waiting time, wrench time stays low and nobody can see why.

    Do this

    Estimate a smooth job. Fix the delays where the wrench time study found them.

  • Mistake

    Reading wrench time from the CMMS

    What goes wrong: Booked hours show what was charged to a work order, not how much of it was hands-on.

    Do this

    Use booked hours for job history. Measure wrench time by observation.

  • Mistake

    Too few observations

    What goes wrong: A one day study of 100 observations gives 35 percent, give or take 9 points. Nothing can be compared with that.

    Do this

    Decide the margin first, then the number of observations. Around 1,000 for plus or minus 3.

  • Mistake

    Studying once

    What goes wrong: The first figure starts an argument about whether it is good or bad.

    Do this

    Repeat the study after each change, with the same rules. The trend is the result.

Most of these come from treating wrench time as a score for people when it is a measure of the system around them.

Templates and related guides

FAQ

Questions about time study in maintenance work

  1. Wrench time is the share of a maintenance crew's paid time spent at the job with tools in hand. It leaves out travel, getting parts and tools, waiting for permits or instructions, and breaks. It is measured by work sampling, and it describes how well planning, scheduling and stores support the crew, not how hard individuals work.

  2. Divide the number of random observations that found a person working hands-on by the total number of observations, then multiply by 100. If 326 of 960 observations are hands-on, wrench time is 34.0 percent. Multiply by paid hours for hours on the tools: 34.0 percent of 480 paid hours a week is 163 hours. Quote the margin too, here plus or minus 3 points.

  3. There is no audited industry benchmark. Doc Palmer, author of the Maintenance Planning and Scheduling Handbook, writes that industry experience puts typical wrench time at 25 to 35 percent and that good planning and scheduling can lift it above 50 percent. Treat that as an experienced guide. Your own figure, measured the same way before and after a change, is the useful one.

  4. A DILO study, for day in the life of, follows one technician for a whole shift and logs every activity with its start time. It shows the order of events and the cause of each delay, such as a part missing from a kit. It covers one person on one day, so it explains a wrench time figure but cannot replace the sampling study that produces it.

  5. Only on the part that repeats. Lubrication routes, identical PMs, changeovers and bench rebuilds can be timed with a stopwatch or from video like production jobs. Most repair work is long, varied and spread across the site, so it is measured in two other ways: work sampling for the crew's wrench time, and planner estimates or comparative estimating for the hours on each job.

  6. Universal Maintenance Standards, or UMS, is a comparative estimating method from H. B. Maynard and Company. A library of benchmark jobs with measured work content is grouped into time ranges. A planner estimates a new job by comparing it with the benchmarks and assigning the standard time of the range it fits, then adding job preparation, travel and allowances.

  7. It depends on the margin you can accept. At 95 percent confidence and a wrench time near 35 percent, about 350 observations give plus or minus 5 points, about 970 give plus or minus 3 and about 2,200 give plus or minus 2. For a crew of 12, 970 observations is roughly 8 random rounds a day for 10 days.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.