The observer effect in time studies: why pace changes and how to spot it

Short answer

People change how they work when they are watched, usually in pace and sometimes in method. You cannot remove it, so reduce it (longer visits, video left running, several days) and check for it in the data by comparing early cycles with later ones.

The observer effect is the change in how a person works because they know they are being observed. In a time study it shows up as a different pace, usually slower and more careful or faster and more showy, and sometimes a different method, such as following the written steps exactly. It is often called the Hawthorne effect, but that story is shakier than it is told: the original lighting data, re-examined in 2011, do not show the famous pattern, and a 2014 review found only that taking part in research does change behavior, with little known about when or by how much. So do not claim a size. Reduce it by staying long enough for people to settle, filming and discarding the first minutes, studying on several days, and telling people what the study is for. Then check for it by comparing early cycles with later ones, and the studied day with output counts from unobserved days.

Last reviewed:

What matters, in one page

  • It is real, but its size is not known. Nobody can tell you that people work 10 percent faster when watched. Be wary of any page that does.
  • It shows up in pace and in method. Pace you can rate. A different method you have to catch.
  • It fades with time in the room. It rarely goes to zero. Early cycles are the least reliable ones.
  • Video helps because the camera can run before the part you will use and because the times can be checked later. It does not make the effect disappear.
  • A study of one person on one day is exposed. Several people, several days and a check against output counts are better.
  • The best protection is not technical. It is an operator who knows why the study is happening and has no reason to perform.

This page is about the pace and method side. The people side, including what to say to the operator and how to behave on the day, is in explaining a time study to a worried operator. For the method, see how to conduct a time study and time study mistakes, where ignoring the observer effect is one of twelve.

What the observer effect is, and what it looks like on the floor

A time study works only if the cycles you time are the cycles the operator would work anyway. The observer effect is the reason they sometimes are not. The person knows you are there, knows what you are measuring and has views about why. Any of these can change what they do.

  • Slowing down: taking care over every step, checking the part twice, working to the letter of the written method, or slowing on purpose in case the number is used against them.
  • Speeding up: showing what they can do, getting it over with, or skipping the things they would usually do.
  • Changing the method: doing it the official way for once, using a tool they normally skip, or skipping the check they normally do.
  • Tidying the station: cleaning, getting the bin emptied, having parts ready. This makes the cycle look better than a normal one.
  • Different mix of cycles: avoiding the awkward part, or asking for the easy order.
  • Everyone around them changes too: the supervisor appears, maintenance fixes the machine, material turns up on time.

Not all of these are the operator. Several are the plant around the study. A study day with perfect parts, a supervisor on hand and the machine just serviced is not a normal day, whatever the operator does. That is part of the same problem and part of the same remedy.

The Hawthorne studies: what the record shows

The label comes from the Hawthorne Works, a Western Electric factory near Chicago, where a series of experiments ran from 1924 to 1932. The usual telling is that workers got more productive whatever the researchers changed, including when the lights were dimmed, because someone was paying attention to them. It is in most textbooks. It is also a good example of a story that has grown past its evidence.

The popular Hawthorne story, and what the record supports

  • The popular story

    Output rose whatever the lighting was, even when it was dimmed.

    What the record shows: The original lighting data were long thought lost. Levitt and List found them and, in a 2011 paper, reported that the striking pattern in the popular account does not appear in them. They found weaker signs of a more subtle effect.

    Use it this way

    Do not quote the lighting story as proof of anything.

  • The popular story

    Being watched and cared about raised output in the relay assembly room.

    What the record shows: Later analyses of that room's data, such as Franke and Kaul in 1978, argued that measured changes in working conditions explained most of the variation in output. Others have challenged their analysis in turn. The picture is mixed.

    Use it this way

    Treat the relay room as contested, not as settled proof of an effect.

  • The popular story

    So being observed makes people more productive.

    What the record shows: A 2014 systematic review (McCambridge, Witton and Elbourne) of 19 studies, mostly in health research, concluded that taking part in research does affect behavior, but little is securely known about when it happens, how it works or how big it is.

    Use it this way

    Assume some change in behavior. Do not assume the direction or the size.

Assume some change in behavior when people are watched. Do not assume its direction or its size. Read the papers rather than the summaries. Levitt and List (2011) is open on the NBER site as working paper 15016. The Hawthorne effect is a real topic of study but not a number to apply to your plant.

The practical reading for a time study is plain. The belief that people behave differently when watched is easy to support from everyday experience and from the review above. The belief that it makes them faster, or slower, by a known amount is not supported. The direction depends on the person, the reason they think you are there and what they stand to lose. A person who fears a speed-up slows down. A person who wants to impress speeds up. Your job is to find out which is happening in your study, and the data can tell you.

How to see it in the data

The simplest check is to compare early cycles with later ones. Operators usually settle in. The cycles they work when they have stopped thinking about you are the ones you want. Below is an invented study of one operator inserting clips into a harness: 30 consecutive cycles, in seconds.

Thirty cycles in order: the first few are not the job

Example numbers
Thirty cycle times of one operator in the order they were workedCycles 1 to 5 average 40.0 seconds, cycles 6 to 10 climb, cycles 11 to 30 average 46.05 seconds.36404448Settled run: 46.05 sFirst five: 40.0 s1102030Cycle numbers
  • Cycles 1 to 5
  • Cycles 6 to 10
  • Cycles 11 to 30

A dot for each of 30 timed cycles of one operator, in seconds, in the order they were worked. Cycles 1 to 5 sit near 40.0 seconds, cycles 6 to 10 climb, and cycles 11 to 30 stay close to 46.05 seconds.

Plot the cycles in the order they happened. A climb at the start and then a flat run is an operator settling in. Keep the flat run, discard the climb and say how many cycles you discarded.
Illustrative: 30 timed cycles of one operator, in five-cycle blocks
CyclesTimes (s)Average (s)Reading
1 to 538, 40, 39, 41, 4240.0Fast and short. Possibly showing what they can do.
6 to 1043, 44, 45, 44, 4644.4Climbing toward a steady level.
11 to 1545, 47, 46, 45, 4645.8Steady.
16 to 2047, 46, 45, 47, 4646.2Steady.
21 to 2546, 47, 45, 46, 4746.2Steady.
26 to 3046, 46, 45, 47, 4646.0Steady.

Cycles 11 to 30 average 46.05 s with a sample standard deviation of 0.76 s. The first five average 40.0 s, 13.1 percent below that.

If you had stopped at five cycles and used them, the cycle time would have been 13 percent too short: 40.0 against 46.05 seconds. A standard built on that would have been unachievable for a normal day and the operator would have been right to say so. This is the commonest form of the problem, and it costs nothing to check.

What stopping at five cycles would have done

Example numbers

Cycles 1 to 5 only

Cycles 11 to 30 (the settled run)

Two bars. A cycle time built on the first five cycles is 40.0 seconds. One built on cycles 11 to 30 is 46.05 seconds. The first is 13.1 percent shorter.

The early cycles would have set the cycle time 13.1 percent short. Same operator, same job, same day.

Six checks

  • Early against late. Plot the cycles in order, as above. A drift in the first several cycles, then a flat run, is a settling operator. Discard the drift, keep the flat run, and note that you did.
  • Spread. Real work has scatter from small differences in parts, position and attention. Cycles that are unusually even can mean the person is working to a deliberate rhythm. Judge by comparing with the same job on a normal day, or other operators on the job. There is no universal cut-off, so do not invent one.
  • Studied day against unobserved days. Compare the pieces per hour on the study day with the output counts or machine data for the days before and after. If the study day is well above or below its neighbors, find out why before you use the study.
  • Operator against operator. Two or three people on the same job and method should be in the same neighborhood. A person who is far from the rest needs explaining, in either direction.
  • Method against the written method. Compare what you saw with the standard work sheet and with what the operator and supervisor say is the usual way. A step that appeared for the study, or one that disappeared, is a sign.
  • Early video against late video. If you filmed for hours, compare the first quarter hour with the last. After a while people forget the camera.

None of these proves anything alone. If several point the same way, you have found it. If none does, you have still done the work to say the study is probably typical, which is stronger than hoping.

What rating can and cannot fix

Performance rating exists to correct for pace: an observer judges whether the operator worked faster or slower than a normal pace for a qualified person, and scales the observed time to a normal time. So a slow, careful operator can be rated above or below 100, depending on how the observer judges the pace. That is a real correction, and it is why a sound study reports both the observed and the rated time. Standard time covers the arithmetic.

Rating has limits against the observer effect. It is a judgment, and a judgment made by the person whose presence caused the change. It cannot correct a different method, because the elements timed are no longer the elements of the job. It cannot correct an unusual day. And an observer rating a person they have been watching for an hour has been influenced by that hour. If the pace is far from normal, the better answer is to study again another day, not to rate harder.

How to reduce it

You cannot stop people noticing they are observed. You can make it less important and shorter lived. These methods are standard practice in work measurement and research methods generally, and none is a complete answer.

Ways to reduce the observer effect, why each helps and its limit

  • Stay long enough and discard the start

    Why it helps
    People settle. A run in period before the readings you use lets the first self-conscious cycles pass.
    The limit
    Settling is usually partial. It does not guarantee a normal pace after it.
  • Study on more than one day

    Why it helps
    A good or bad day, a mood or a one-off part is averaged out. The effect is smaller on the second and third visit.
    The limit
    Costs more time. Returning every day to the same person can feel like pressure.
  • Use video, and leave it running

    Why it helps
    The camera runs before and after the cycles you use. You can check any reading later. The operator can see and challenge them. A fixed camera is less intrusive than a person standing at the elbow.
    The limit
    People do notice a camera, especially at first. Video needs consent and rules about use. See time study from video.
  • Choose the time of day with care

    Why it helps
    Study at a normal point in the shift and not at the start-up rush or the last hour. Avoid the day of an audit or a visitor.
    The limit
    A normal time for one job is not normal for another. Know the shift pattern.
  • Tell people why, and keep to it

    Why it helps
    A person who knows the study is not about them and has no reason to perform will drift back to normal faster.
    The limit
    Only works if what you say is true. See explaining a time study.
  • Study several operators

    Why it helps
    A single person's reaction to being watched is not the whole sample. Comparing operators exposes the outlier.
    The limit
    Different people react in different directions, so averaging is only a start.
  • Back it with data nobody watched

    Why it helps
    Output counts, machine data and scrap records from ordinary days show the plain pace. Use them to sense-check the study.
    The limit
    Counts include delays and stoppages the study treats separately, so compare like with like.
  • Use [work sampling](/learn/work-sampling) for non-cyclic work

    Why it helps
    Spread-out, brief random observations give people little to react to. See time study vs work sampling.
    The limit
    It gives proportions of time and not element times.
None of these removes the effect. Used together they make it smaller and easier to see.

Nothing on the list asks you to hide. Studying someone without their knowledge to avoid the effect is a poor idea and often barred by agreements and laws, and the study loses far more than it gains in the trust it costs. Secret timing is out. Time study in a union plant covers the rules around notice.

How to check a study for the observer effect

Checking a study for the observer effect

  1. 1

    Plot the cycles in order

  2. 2

    Mark the settled run

  3. 3

    Check the spread

  4. 4

    Compare with unobserved output

  5. 5

    Check the method and the day

  6. 6

    Decide: use, rate, or repeat

Run these before rating the readings. Most take a few minutes with the sheet in front of you.
  1. 1

    Plot the cycles in order

    Cycle number across, seconds up. Look for a drift at the start, one-off spikes and a flat run. A table of block averages is enough if you have no chart.

  2. 2

    Mark the settled run

    Decide where the cycles stop drifting. Write down where and why. Keep it, discard the drift, and state the number discarded in the report.

  3. 3

    Check the spread

    Compare the scatter of the settled run with the same job on other days, or other operators. Note anything unusually flat or ragged.

  4. 4

    Compare with unobserved output

    Pieces per hour from counters or machine data for the study day against the days before and after. Explain any big gap.

  5. 5

    Check the method and the day

    Compare what you saw with the standard work sheet. Note anything that was unusual about the day: visitors, parts, repairs, staffing.

  6. 6

    Decide: use, rate, or repeat

    If the settled run is clean and consistent with the other checks, use it. If the pace is plainly unusual, rate it and say so. If the method or the day was off, study again.

What to do with the operator

The most common reason people change how they work under observation is that they are not sure what the observation is for. The remedy is to tell them, early and plainly, and to keep to it. Show the operator the plot of their own cycles. Ask whether the first few were normal. People are usually happy to say, and what they tell you is often the best piece of evidence you have.

  • Never say they are going too fast or too slow. Ask whether it is a typical day.
  • Do not praise a quick cycle or frown at a slow one. Your face is part of the study.
  • Stand or sit where you are least in the way, and do not hover over each reading.
  • Let them see the sheet or the screen.
  • If their pace is not what you would call normal and they confirm it is not, say so in the report and study again. That is not a failure of the study. It is the study working.

If the study is going to be used for pay, the worry about being watched is strong, and the pace is likely to be pushed one way or the other. Time standards and incentive pay covers that case.

Limits and honest caveats

  • No one can tell you the size. The reviews say research participation changes behavior and that little is known about how much, so a stated percentage should be treated as a guess.
  • Your plant is not the Hawthorne Works. The original experiments were in a different time, with different pay systems and management. Do not reason from them to your floor.
  • Detecting the effect needs a baseline of unobserved behavior. Output counts and machine data are the nearest you have, and they are imperfect.
  • Video lowers the problem and moves it. A camera is lighter than a person, but a recording can be kept and watched later, which raises other worries. See time study from video.
  • Learning is not the observer effect. A new operator or a new method gets faster over weeks. That is a learning curve, which is a separate thing to measure.

FAQ

Questions about the observer effect in time studies

  1. It is the change in how a person works because they know they are being observed. In a time study it shows as a different pace, slower and more careful or faster and showy, and sometimes a different method. You cannot remove it. You reduce it with longer visits, video and several days, and check for it by comparing early cycles with later ones.

  2. Partly. A 2014 systematic review of 19 studies concluded that taking part in research does affect behavior, but little is known about when or how much. The famous lighting experiments are weaker: when Levitt and List found and analysed the original data in 2011, the pattern in the popular story did not appear. Treat it as likely, not as a number.

  3. Sometimes, but not reliably. Some work faster to show what they can do, some slow down because they fear the number will be used against them, and some change their method. The direction depends on the person and on what they think the study is for. Check each study for it rather than assuming a direction or a percentage.

  4. There is no reliable figure. In practice most people settle after the first several cycles, which is why the early cycles are the least trustworthy and a run in period is worth discarding. Settling is usually partial, so keep checking. Filming and leaving the camera running makes the settled stretch easy to find afterward.

  5. It helps, but does not remove it. A fixed camera is less intrusive than a person at the elbow, it can run before the cycles you use, and any reading can be checked against the frame afterward. People still notice a camera, especially at first, and it needs consent and clear rules on who views it and when it is deleted.

  6. Plot the cycles in order and look for a drift at the start. Compare the spread with other days or operators, the pieces per hour with unobserved output counts, and the method with the standard work sheet. If the pace or method looks unusual, discard the drift, rate the pace or repeat the study on another day.

  7. Only for pace. Rating scales an observed time to a normal pace, which can offset a slower or faster operator. It cannot fix a changed method or an unusual day, and the observer doing the rating has been influenced by watching. If the pace or method was far from normal, study again on another day.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.