Manpower planning from standard time: from a month of orders to a headcount

Short answer

To plan manpower from standard time, multiply each product's units by its standard minutes, add them up, divide by your planned efficiency, then divide by the productive hours one person really gives in the month. Round up. That is the headcount.

Required hours = sum of (units x standard minutes) / 60 / planned efficiency. Productive hours per person = attendance hours x (1 minus absence rate) minus training and meeting hours. Headcount = required hours / productive hours per person, rounded up. In the example on this page, 950 standard hours at 85 percent efficiency is 1,117.6 hours on the clock. One person gives 140.8 productive hours in a 20 day month. 1,117.6 / 140.8 = 7.94, so 8 people. Efficiency and absence are your own numbers, not constants: move them and the answer moves by a person.

Last reviewed:

The short version: three divisions

From the month's orders to a number of people

Example numbers

1. Demand x standard time

  • Product A: 9,000 x 2.4 min360 h
  • Product B: 6,000 x 3.5 min350 h
  • Product C: 2,400 x 6 min240 h

950 standard hours

divide by planned efficiency, 85%

2. Hours on the clock

1,117.6 hours

950 / 0.85. This is the labour you must pay for to earn 950 standard hours.

divide by productive hours per person, 140.8

3. People

7.94, so 8 people

1,117.6 / 140.8. Rounded up, because a fraction of a person is not a roster.

Three products, 9,000, 6,000 and 2,400 units, at standard times of 2.4, 3.5 and 6 minutes, come to 950 standard hours. Divided by a planned efficiency of 85 percent that is 1,117.6 hours on the clock. Divided by 140.8 productive hours per person it is 7.94, so 8 people.

Three divisions turn demand into people. Each one is an input you set and write down, and each one can move the answer by a person.

Manpower planning from standard time answers a different question from line balancing. How many operators a line needs starts from takt time and asks how many people one line needs to hit it. This page starts from a month of orders, often several products on one or more lines, and asks how many people to have on the payroll to make them. The line sums are done. What is left is turning hours into people.

The method is three steps of arithmetic. Demand times standard time gives the standard hours the orders contain. Dividing by the efficiency you expect gives the hours you will pay for. Dividing by the productive hours one person gives in the month gives people. Every plan that goes wrong goes wrong in one of the divisors, not in the times.

A standard time is the time a trained operator needs at a normal pace, plus allowances for personal needs, fatigue and unavoidable delay. That is why breaks do not come off the hours later, and why the plan still needs an efficiency factor: nobody earns exactly 100 percent of standard hours every day.

Step 1: required hours from demand and standard times

Take the forecast or the order book for the period you are staffing. For each product, multiply the units by the standard minutes per unit, add the products, and divide by 60. The result is the standard hours of work in the plan, also called earned hours when you measure them after the fact.

Illustrative: standard hours in one month for three products on one assembly area
ProductUnitsStandard minutes per unitStandard minutesStandard hours
Product A9,0002.421,600360
Product B6,0003.521,000350
Product C2,4006.014,400240
Total17,40057,000950

Use the standard minutes of the current method, with the allowances already in them. A time that has not been checked since the method changed will put the plan out before any assumption does.

Then divide by the efficiency you plan for. Labour efficiency is standard hours earned divided by hours worked, so the hours on the clock are the standard hours divided by it. At 85 percent, 950 / 0.85 = 1,117.6 hours. Both Niebel and Freivalds and Groover work staffing problems this way: workload in standard time, divided by an efficiency factor, then by the time one worker has. The 85 percent is an input, not a rule. Take it from your own records: see labor efficiency and labor variance for how to measure it, and use last quarter's number for the same area, not a target you hope to reach.

Step 2: productive hours per person

A person on the roster for a 20 day month is not 160 hours of production. Some of those hours are gone before the first piece is made. The ones to take off are the ones the standard time does not already cover.

Illustrative: from attendance to productive hours for one person, 20 working days
LineHoursWhere the number comes from
Scheduled hours, 20 days x 8160.0The shift pattern
Planned absence, 7%: leave, sickness, otherminus 11.2Your absence tracker, same area, same season
After absence148.8
Training, safety talks, team meetings, 5S: 2 hours a weekminus 8.0The calendar, not a guess
Productive hours per person140.8

Breaks, personal needs and fatigue are not taken off. They are inside the standard time already. Taking them off again counts the same loss twice.

One person's month: 160 paid hours, 140.8 that count

Example numbers
  • Attendance, 20 days x 8 h160.0 h
  • Absence at 7%: leave, sickness, otherminus 11.2 h
  • Training, meetings, 5S, 2 h a weekminus 8.0 h
  • Productive hours per person140.8 h

A person attends 160 hours in a 20 day month. Absence at 7 percent takes 11.2, leaving 148.8. Eight hours of training and meetings leave 140.8 productive hours.

Breaks are not on this list. A standard time already carries the allowance for them, so taking them out again would count the same loss twice.

The 7 percent is illustrative. There is no standard absence rate: it depends on your site, your season and your people, so the number belongs in your own absenteeism tracker, not in a guide. Say which period you averaged. Anything else that is regular and not in the standard belongs on the list too: changeovers if the standard excludes them, material handling, cleaning, waiting on the forklift. Labor losses in manufacturing is the checklist of where paid hours go. Count each loss once, here or in the efficiency factor, not both.

Step 3: divide, then decide how to round

Headcount = hours on the clock / productive hours per person = 1,117.6 / 140.8 = 7.94. Round up to 8. With 8 people the area has 8 x 140.8 = 1,126.4 productive hours against 1,117.6 needed, 8.8 hours of slack, a planned load of 99.2 percent.

Rounding is a decision, so write the rule down. Rounding up is the safe default because a fraction of a person does not exist on a roster. If the fraction is small, say 7.25, you can choose 7 people and cover the 0.25 x 140.8 = 35.2 hours with overtime, about 5 hours each for the month. If it is 7.94, as here, there is nothing to save: the extra person costs 0.06 of a head in slack and removes the overtime.

A 99 percent load is not comfortable. It means every assumption holds, nobody is out more than planned, no order moves. The next section shows what happens when they do not. Treat any result within a few percent of a whole person as a prompt to test the two divisors, not as a finished answer.

Two assumptions can move the answer by almost two people

Run the same 950 standard hours with a different efficiency and a different absence rate. The times did not change. The plan did.

Illustrative: unrounded headcount for 950 standard hours, by planned efficiency and absence
Planned efficiencyAbsence 4%Absence 7%Absence 12%
80%8.168.438.94
85%7.687.948.42
90%7.257.507.95

The 7% row is the plan in this guide. Productive hours per person are 145.6, 140.8 and 132.8 for 4%, 7% and 12% absence, each less the same 8 hours of training and meetings.

Two assumptions, up to a person each

Example numbers
Planned efficiencyAbsence 4%Absence 7%Absence 12%
80%8.169 people8.439 people8.949 people
85%7.688 people7.948 people8.429 people
90%7.258 people7.508 people7.958 people

Outlined cell: the plan in this guide. Shaded cells need a ninth person.

Unrounded headcount for 950 standard hours. At 80 percent efficiency and 4, 7 and 12 percent absence: 8.16, 8.43 and 8.94. At 85 percent: 7.68, 7.94 and 8.42. At 90 percent: 7.25, 7.50 and 7.95.

The same orders need 7.25 to 8.94 people depending on two inputs. Say which you used and where it came from, because the plan is only as good as those two numbers.

That is 7.25 to 8.94 people for the same orders. Which cell you are in depends on two numbers that are easy to set too optimistically. Planners tend to use the efficiency they are asked to hit and the absence they would like to see. Use what the last few months show, and keep the cell next to it in view. If the plan is only right in the best cell, say so when you present it.

A new hire is not a whole person in month one

The plan says 8. If you have 7 experienced people and hire the eighth at the start of the month, the plan is short in month one, because a new operator takes weeks to reach standard. The ramp-up plan and learning curve guide shows how to get a learning rate from your own data and turn it into a weekly plan. Here the only question is how much of a person the newcomer is each week.

Illustrative inputs: the new hire reaches 50, 70, 85 and 100 percent of an experienced operator's output in weeks 1 to 4. These are planning inputs, not a benchmark: use the shares from your last few hires on this kind of work, or the weekly plan from your learning curve. The average over the month is 76.25 percent, so the eighth person gives 0.7625 x 140.8 = 107.4 hours.

Illustrative: weekly hours against weekly need in month one, seven experienced people plus one new hire
WeekNew hire outputHours availableHours neededGap
150%264.0279.4minus 15.4
270%271.0279.4minus 8.4
385%276.3279.4minus 3.1
4100%281.6279.4plus 2.2

Weekly need is 1,117.6 / 4 = 279.4 hours. Weekly capacity is (7 + the new hire's share) x 140.8 / 4. Month total: 1,093.0 hours available, 24.7 short.

Month one with a new eighth person

Example numbers
  • Week 1: new hire at 50%264.0 h
  • Week 2: new hire at 70%271.0 h
  • Week 3: new hire at 85%276.3 h
  • Week 4: new hire at 100%281.6 h

Red line: weekly need, 279.4 hours (1,117.6 / 4)

Weekly need is 279.4 hours. Seven experienced people and a new hire working at 50, 70, 85 and 100 percent give 264.0, 271.0, 276.3, 281.6 hours in weeks 1 to 4. Only week 4 covers the need.

Eight names on the roster is 7.76 people of output in month one. The shortfall is 24.7 hours over the month, about 3.5 hours of overtime for each of the seven experienced people. The new hire's shares are inputs from your own ramp-up records.

The roster has 8 names and the month has 7.76 people of output. The 24.7 hour gap is about 3.5 hours of overtime for each of the seven experienced people, and the trainer's time, which is not in these numbers, comes out of the experienced people's productive hours as well. Plan the hire early enough that the ramp finishes before the demand does. From month two the eight people give 1,126.4 hours and the gap closes.

Overtime, a hire or a temporary: compare the hours

Put the gap in hours and the choice gets simple. Seven people give 7 x 140.8 = 985.6 hours. The plan needs 1,117.6, so the gap is 132.0 hours a month: 18.9 hours of overtime each, 4.7 a week. That is a permanent hire. A gap of 24.7 hours for one month is overtime.

  • A gap that lasts a season: overtime or a temporary worker, with the ramp-up of the temporary counted the same way as above.
  • A gap that lasts all year: a hire. Overtime that never ends is a hire you have not made yet, paid at the overtime rate.
  • Overtime is not free hours: the efficiency assumed in step 1 usually falls on long days, so check it before you rely on it. This is general practice, not a rule: test it on your own records.
  • Overtime rules, limits and consent differ by country, state and agreement. Check yours before you plan on it.

The gap in hours, two ways to close it

Example numbers

Seven people and overtime

  • 7 x 140.8 = 985.6 h
  • Short 132.0 h
  • 18.9 h each, 4.7 h a week

No ramp-up, but overtime on top of the efficiency already assumed. Fine for a peak, wrong for a permanent gap.

Eight people

  • 8 x 140.8 = 1,126.4 h
  • Spare 8.8 h
  • Month one: short 24.7 h

Covers the load from month two. Almost no slack, so one extra absence puts you back on overtime.

Seven people give 985.6 hours against 1,117.6 needed: 132.0 hours short, 18.9 hours of overtime each. Eight people give 1,126.4 hours, 8.8 spare, but 24.7 short in the first month while the new hire learns.

Compare in hours, not heads. A permanent gap of 132 hours a month is a hire. A gap that lasts one season is overtime or a temporary.

Shifts, weeks and minimum crews

Headcount from hours is a floor. The roster then has to cover the shifts, and two things hold it up. The first is the minimum crew: if the area needs 4 people to run at all, then two shifts need 8 present every day, so with 7 percent absence you need more than 8 on the payroll. The second is the days: 8 people with 7 percent absence is 8 x 0.93 = 7.44 present on an average day, but any one day can be 6 or 8.

For round the clock cover, the arithmetic is a fixed one: a week has 168 hours, a 40 hour contract gives 40, so 168 / 40 = 4.2 people for every position that must be filled all week, before absence. Then add absence on top. Use the shift schedule planner to test a pattern, and cross-train, so that when the plan is short on one day another person can cover the gap. A cross-training plan is what turns 7.44 present into a line that still runs.

How to build the plan, step by step

  1. 1

    Get demand by product for the period

    Use the order book and the forecast for the month or the quarter you are staffing. Say which one, and when it was last updated.

  2. 2

    Multiply by standard minutes and add up

    Units x standard minutes for each product, summed, divided by 60. Check that every standard is current and includes its allowances.

  3. 3

    Divide by planned efficiency

    Use the efficiency you actually achieved in the same area recently. The result is the hours you will pay for.

  4. 4

    Work out productive hours per person

    Scheduled hours, less planned absence, less training and meetings. Take each number from a record, and do not deduct breaks.

  5. 5

    Divide, round with a stated rule, then test

    Headcount = hours on the clock / productive hours. Round up, or round down and plan overtime in hours. Then run the efficiency and absence one step either way, and add the ramp-up of any new hire.

What the plan must not hide

  • Skills. Eight people can have the hours and still be unable to run the one process that only two of them are trained on. Check the plan against the skills matrix, not only the hours.
  • Stations. Headcount does not fix a bottleneck. If one station limits the line, extra people elsewhere add cost and no output. See production capacity calculation.
  • Mix. A month with more of product C needs more hours per unit. Rerun the plan when the mix changes, not only when the volume does.
  • Old standards. If a time was set years ago and the method has changed, the plan is wrong in a direction that looks like a labour problem.
  • The assumptions themselves. Show the efficiency, the absence rate, the training hours and the rounding rule beside the answer, so that anyone can see which one to question.
  • The case for people. A plan that cannot be followed from demand to headcount is a plan that is hard to defend when you ask for more. How to ask for more headcount uses this arithmetic as the evidence.

When this method is the wrong tool

It needs standard times and repeating work. A job shop with one-off orders, or maintenance with no standards, has to plan from history or from work sampling instead. It also treats people as hours. People are not interchangeable minutes: a plan that is right on paper still has to be talked through with the supervisors and the people who will do the work, and the people side matters. Staffing numbers feel personal. Say that the plan is a calculation from the work and not a verdict on anyone's speed, show the inputs, and let the team correct the ones they know better. Once a plan has been built, use it for what-if questions as well, such as what a faster changeover is worth in people. It cannot tell you what is legal or reasonable for your site, and it is not legal advice.

Where software helps

The plan is only as good as the standard times behind it. LeanSuite's Time and Motion Study drafts element times from a video of the station, on a timeline that links back to the footage, for you to check and certify. The operator staffing calculator is a free workbook for the line-level sums, and the standard time calculator turns observed times into the minutes this plan multiplies.

FAQ

Questions about manpower planning from standard time

  1. Multiply each product's units by its standard minutes, add them up and divide by 60 to get standard hours. Divide by your planned efficiency to get hours on the clock. Divide again by the productive hours one person gives in the period, after absence and training, and round up. In the example here, 950 standard hours becomes 8 people.

  2. Headcount equals required hours divided by productive hours per person. Required hours are units times standard minutes, divided by 60 and by planned efficiency. Productive hours are scheduled hours less absence, training and meetings. With 1,117.6 required hours and 140.8 productive hours per person, the result is 7.94, rounded up to 8 people.

  3. Required labor hours equal total standard hours divided by planned efficiency. Standard hours are the sum of units times standard minutes per unit, divided by 60. At 85 percent efficiency, 950 standard hours needs 950 divided by 0.85, which is 1,117.6 hours on the clock. Use the efficiency your own area achieved recently, not the target.

  4. There is no standard rate. Use your own absence record for the same area and season, covering leave, sickness and other time off, and say which period you averaged. Productive hours per person are scheduled hours times one minus the absence rate, less training and meetings. In this guide's example, a rise from 7 to 12 percent adds about half a person.

  5. Compare the gap in hours. A gap that lasts a month or a season is usually overtime or a temporary worker. A gap that lasts all year is a hire, because permanent overtime is a hire at overtime rates. Remember a new hire is not a full person for the first weeks, and check the overtime rules that apply to your site.

  6. Count the new hire as a share of an experienced operator's output each week, taken from your own ramp-up records or learning curve. In the example, shares of 50, 70, 85 and 100 percent average 76 percent, so eight people give 7.76 people of output in month one and the plan is 24.7 hours short.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?