Practical guide · Standard work, SOPs and training
Standard WIP: how to calculate standard work in process for a cell
Short answer
Standard WIP is the smallest number of pieces that must be in a process for the operator to repeat the work sequence without waiting. For each step, divide the time one piece stays there by takt time and round up. Add the steps. That is the number.
Standard work in process, also called SWIP or standard in-process stock, is the third element of standard work. To calculate it for a cell, list every step where a piece sits without the operator: each machine, and each timed wait such as curing or cooling. Divide the time a piece stays at the step by takt time and round up. A machine that finishes inside one takt time needs 1 piece. A 300 second cure at a 72 second takt time needs 5. Add the steps together. If the operator walks against the flow of parts, add one piece between each pair of machines. In the example on this page the answer is 9 pieces.
Last reviewed:
What is standard WIP?
Standard WIP for one cell: 9 pieces, each with a reason
Example numbersTakt time 72 s: one piece leaves, and one enters, every 72 s
- 1
Press
8 s load, 20 s machine
28 / 72 = 0.39, so 1 piece
- 2
Dispense
6 s load, 30 s machine
36 / 72 = 0.50, so 1 piece
- 3
Cure rack
300 s cure, nobody there
300 / 72 = 4.17, so 5 pieces
- 4
Tester
8 s load, 100 s test
108 / 72 = 1.50, so 2 pieces
9
pieces of standard WIP: 1 + 1 + 5 + 2. A piece takes 9 x 72 = 648 s, or 10.8 minutes, to cross the cell.
Four steps in a row with a takt time of 72 seconds. The press holds 1 piece, the dispenser 1 piece, the cure rack 5 pieces and the two-nest tester 2 pieces. Total 9 pieces.
Standard WIP is the number of pieces a process needs inside it to keep going. The Lean Enterprise Institute's Lean Lexicon gives it as the third element of standardized work: the standard inventory, including units in machines, required to keep the process operating smoothly. Taiichi Ohno called it standard inventory and described it as the minimum work in process needed for operations to proceed. Plants also say standard in-process stock, SWIP or SIPS. They all mean the same number.
It exists because of a simple fact about cells. When an operator arrives at a machine, there has to be a finished piece in it to take out, or the operator stands and waits for the cycle. So each machine holds a piece while the operator is somewhere else. Those pieces are not waste. They are what lets one person run several machines.
It is a minimum and a maximum at once. One piece fewer and somebody waits. One piece more and it sits on a bench, hiding whatever went wrong. That makes it the easiest of the three elements of standard work to check: stand in the aisle and count.
How to calculate standard WIP
Work step by step through the cell, in the order the part flows. At each step ask one question: how long does one piece stay here with nobody holding it? Then divide by takt time and round up.
Pieces at a step = time one piece stays at the step / takt time, rounded up to a whole piece. Standard WIP for the cell is the sum over all the steps. The reasoning is that one piece enters the step every takt time and one leaves, so a piece that stays for four and a bit takt times has four more behind it.
| Kind of step | Pieces to count | Why |
|---|---|---|
| Machine that holds one piece and finishes inside takt time | 1 | The ratio is under 1 and rounds up to 1. The piece waits in the machine until the operator comes back. |
| Machine whose load plus cycle time is longer than takt time | Time / takt time, rounded up | One nest cannot keep up. A tester that needs 108 seconds at a 72 second takt time needs 2 nests and holds 2 pieces. |
| Timed wait with no machine: cure, cool, dry, soak | Time / takt time, rounded up | The pieces queue in a first in, first out lane. One goes in and one comes out every takt time. |
| Manual step with no machine | 0 | The piece is in the operator's hands and moves with them. Some plants count 1 per operator instead. Pick one convention and note it. |
| Operator walks against the flow of parts | Add 1 between each pair of machines | Each machine is unloaded before the part it needs next has arrived, so one has to be waiting. This is Ohno's rule. |
| Batch step: oven, washer, outside process | At least one full batch in the step, plus the pieces building up for the next | A batch step cannot take one piece each takt time. Gemba Academy teaches doubling the rounded ratio for these steps. |
Raw material waiting at the start and finished goods at the end are not standard WIP. They are set separately, usually by container size or a kanban.
A quick estimate you will see quoted is the sum of all the cycle times divided by takt time. It is a useful first guess for the size of the answer. It comes out low, because it does not round up at each step, and it says nothing about where the pieces go. Use the step by step count for the number you post.
Worked example: a cell with a cure rack
Illustrative numbers. A cell bonds a sensor into a housing. The shift has 450 minutes of working time, 27,000 seconds, and the customer needs 375 pieces: takt time is 27,000 / 375 = 72 seconds. The part goes through a press, an adhesive dispenser, a cure rack and a tester. The operator walks with the flow.
| Step | Time one piece stays | Divided by takt time | Pieces |
|---|---|---|---|
| Press | 8 s load + 20 s machine = 28 s | 28 / 72 = 0.39 | 1 |
| Dispenser | 6 s load + 30 s machine = 36 s | 36 / 72 = 0.50 | 1 |
| Cure rack | 300 s cure | 300 / 72 = 4.17 | 5 |
| Tester | 8 s load + 100 s test = 108 s | 108 / 72 = 1.50 | 2 |
Standard WIP: 1 + 1 + 5 + 2 = 9 pieces. The tester needs two nests, loaded on alternate cycles.
The sum, step by step
Example numbersPieces at a step = time one piece stays at the step ÷ takt time, rounded up
Takt time is 72 s. Time at a step is load time plus machine time, or the full cure, cool or dry time.
- Press =28 ÷ 72 = 0.39, rounded up= 1
- Dispense =36 ÷ 72 = 0.50, rounded up= 1
- Cure rack =300 ÷ 72 = 4.17, rounded up= 5
- Tester =108 ÷ 72 = 1.50, rounded up= 2
Two rows deserve a second look. The cure rack needs 5 places, not 4: a piece that has been in for four takt times, 288 seconds, has not finished its 300 second cure, so a fifth is behind it. And the tester is slower than takt time. One nest would pass a piece every 108 seconds when the cell needs one every 72. Two nests, loaded turn about, each have 144 seconds between loads, which covers the 108.
Standard WIP also tells you how long a part takes to cross the cell. One piece leaves every takt time, so 9 pieces is 9 x 72 = 648 seconds, about 10.8 minutes from the press to the end of test. If a defect is found at the tester, that is how old the cause is, and 9 is how many suspect pieces are behind it.
Walking with the flow or against it
The count depends on which way the operator walks. Ohno put it this way in Toyota Production System: if the work is done in the order of the machining processes, only the items mounted on the machines are needed and nothing has to be held between machines. If the operator proceeds in the reverse order, one item's worth of inventory is needed between machines.
The reason is easy to see at one machine. Walking with the flow, the operator arrives carrying the part from the machine before, swaps it for the finished one and carries that forward. Walking against the flow, the operator arrives empty-handed from downstream. The part to load must already be waiting there, and the part just unloaded is put down for the next lap. Three machines need 3 pieces one way and 5 the other.
Same three machines, two walking directions
Example numbersWith the flow
3 pieces
The operator carries each part forward to the next machine, so nothing waits between machines.
Against the flow
5 pieces
Each machine is unloaded into the gap behind the operator, and loaded from the gap ahead.
Two drawings of three machines in a row, with parts flowing from machine 1 to machine 3. When the operator walks in the same direction as the parts, standard WIP is 3 pieces, one in each machine. When the operator walks against the flow, one more piece is needed between each pair of machines, so standard WIP is 5 pieces.
Plants do sometimes walk against the flow on purpose, for example to bring the operator back to the start of a U-shaped cell beside the finish. It is a fair trade as long as the extra pieces are counted, marked and on the chart.
One short, one over
Standard WIP is only useful if a different count is visible and means something. In the example, 8 pieces means a step is starved and the cell will miss a cycle. 10 means a piece is waiting somewhere it has no place, which usually means a machine was late on an earlier cycle and nobody said so.
One piece short, standard, one piece over
Example numbersOne short
8 pieces
The operator reaches the tester and the rack has nothing cured to load. The tester misses a cycle, and so does the customer.
What you see
An empty nest or an empty rack slot
Standard
9 pieces
Every machine has its piece and every rack slot is full. One piece leaves and one enters each takt time.
What you see
Nothing waiting, nothing missing
One over
10 pieces
The extra piece sits on a bench between steps. It hides a late machine for one cycle, and it ages if the next step finds a defect.
What you see
A part on a bench with no marked place
Three states of the same cell. With 8 pieces the tester is starved. With 9 pieces the cell flows. With 10 pieces one part waits on a bench.
- Give every piece a marked place: a nest, a numbered rack slot, a painted square. No place, no piece.
- Put the number on the standard work chart and mark each piece on the layout.
- Make the count part of the team leader's walk. It takes ten seconds.
- When the count is wrong, ask what happened on the last few cycles before putting it right.
- At the end of a shift, leave the cell with its standard WIP in place so the next shift starts in flow.
How to bring the number down
Standard WIP is the right amount for the cell as it is today. Change the cell and the right amount changes. In the example the cure rack holds 5 of the 9 pieces, so that is where to look. A faster-curing adhesive at 140 seconds gives 140 / 72 = 1.94, which rounds up to 2. The total falls from 9 to 6, and time through the cell from 648 seconds to 6 x 72 = 432.
Shorten the longest stay and the standard WIP falls
Example numbersBefore
300 s cure: 9 pieces
9 x 72 = 648 s through the cell.
- 1
Press
8 s load, 20 s machine
28 / 72 = 0.39, so 1 piece
- 2
Dispense
6 s load, 30 s machine
36 / 72 = 0.50, so 1 piece
- 3
Cure rack
300 s cure, nobody there
300 / 72 = 4.17, so 5 pieces
- 4
Tester
8 s load, 100 s test
108 / 72 = 1.50, so 2 pieces
After
140 s cure: 6 pieces
6 x 72 = 432 s through the cell.
- 1
Press
8 s load, 20 s machine
28 / 72 = 0.39, so 1 piece
- 2
Dispense
6 s load, 30 s machine
36 / 72 = 0.50, so 1 piece
- 3
Cure rack
140 s cure, nobody there
140 / 72 = 1.94, so 2 pieces
- 4
Tester
8 s load, 100 s test
108 / 72 = 1.50, so 2 pieces
Before, the adhesive cures for 300 seconds, the rack holds 5 pieces and standard WIP is 9. After a change to a 140 second cure the rack holds 2 pieces and standard WIP is 6. Time through the cell falls from 648 to 432 seconds.
- Shorten the longest stay. Cure, cooling and test times usually hold the most pieces.
- Bring a slow machine under takt time, so it needs one nest and not two.
- Change the walking direction to follow the flow, if the layout allows.
- Replace a batch step with one that takes single pieces.
- Do not cut the number without changing the process. Taking a piece out of a cell that needs it only moves the waiting to the operator.
Takt time moves the number too. A shorter takt time means more pieces, because the same stay now spans more cycles. If demand rises and takt time falls from 72 to 60 seconds, the 300 second cure needs 300 / 60 = 5 places and the tester still needs 2, so the cell still needs 9. At a 50 second takt time the rack needs 6 and the tester 3, and the cell needs 11. Recalculate whenever takt time changes. Updating standard work after an improvement covers reissuing the chart.
Common mistakes
- Rounding the total and not each step. The pieces cannot be shared between steps.
- Counting raw material and finished goods. Standard WIP is what sits inside the process.
- Treating it as a target to minimise. Below the standard, the operator waits.
- Treating it as a limit only. Above the standard is as wrong as below.
- Forgetting the walking direction. A cell walked against the flow needs more, and the chart must show where.
- Leaving it as a number on a sheet. Without a marked place for each piece nobody can see a wrong count.
- Using it outside repeating work. A job shop or a maintenance bench has no takt time to divide by. Cap the work in process there another way, such as a limit on open jobs.
Where software helps
The calculation needs honest times for each step: load time, machine time and how long a piece really sits in the rack. LeanSuite's Time and Motion Study drafts element times from a video of the cell on a timeline that links back to the footage, for you to check and certify. The count and the chart are then yours to draw: the standard work sheet is a free template with a place for the standard in-process stock.
Standardized work software
Keep standard work current in LeanSuite
LeanSuite covers most of the cycle in one platform: working out the standard with Vision AI, keeping it current with SOPs and work instructions, and training and auditing it.
Go deeper
This page is the short version. These guides cover each part in full.
- The Three Elements of Standard Work: Takt Time, Work Sequence, Standard WIPStandard WIP next to the other two elements it depends on.
- Standard Work Tools: Combination Sheet, Standardized Work Chart, Job BreakdownThe chart the number is posted on, and the other forms.
- Standard Work in Manufacturing: The Complete GuideWhere standard WIP fits in rolling standard work out across a plant.
All our articles on this subject are in the standard work, sops and training topic.
Free templates and tools
- Standard work sheet templateTakt time, each element's manual, machine and walk time on a time chart, key points and standard WIP.
- Standard work combination tableOne operator's manual, machine, walk and wait time on a time chart against takt, with machine cycles and a process capacity sheet.
- Process capacity sheet templateEach machine in a part's routing with manual, auto and tool change time, its capacity per shift, and the step that limits the cell against demand.
- Standard work audit checklist24 checks of a job against its written standard, ten timed cycles, and each gap sorted by cause before anyone acts.
- Takt time calculatorThe pace a line must hit to meet customer demand, from shift time, breaks and daily demand.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
- Lead time calculatorManufacturing lead time from WIP and throughput (Little's Law), and the share of it that adds value.
Doing this in LeanSuite
Time and Motion Study
Film the station and the AI times every element on a timeline that links to the video. You check it and certify it.
See Time and Motion StudyStandardized work software
Working out the standard with Vision AI, keeping it current with SOPs and work instructions, and training and auditing it.
See Standardized work software
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about standard WIP
Standard WIP, or standard work in process, is the smallest number of pieces that must be inside a process for the operator to repeat the work sequence without waiting. It includes the pieces in machines. It is one of the three elements of standard work, with takt time and work sequence, and it is marked on the standard work chart.
For each step where a piece sits without the operator, divide the time the piece stays there by takt time and round up. Add the results. A machine that finishes within one takt time needs 1 piece. A 300 second cure at a 72 second takt time needs 5. If the operator walks against the flow, add one piece between each pair of machines.
Pieces at a step equal the time one piece stays at the step divided by takt time, rounded up. Standard WIP is the sum across the steps. A quick estimate is the sum of all cycle times divided by takt time, but it comes out low because it does not round up at each step.
Not quite. A WIP limit is a ceiling: do not exceed this many. Standard WIP is an exact amount: the cell needs this many to run, and more or fewer both signal a problem. Standard WIP also needs a takt time and a repeating sequence. A WIP limit can be used anywhere.
Walking with the flow, the operator carries each part to the next machine. Walking against it, the operator reaches each machine before the part it needs, so one has to be waiting there from the previous lap. Taiichi Ohno gives the rule: in the order of the processes only the pieces on the machines are needed, in reverse order one more between machines.
No. It counts the pieces inside the process: in machines, in cure or cooling lanes and, where the operator walks against the flow, between machines. Raw material at the start and finished goods at the end are set separately, usually by container size or kanban.
Related guides and tools
- Standard work: the three elements, of which this is the third
- From time study to standard work: where the count goes on the chart
- Standard work combination table: checking each machine is done before the operator returns
- Takt time: the number every step is divided by
- Kanban: setting the stock between processes, outside the cell
- Cycle time vs lead time: why work in process sets how long a part takes
- Standard work sheet: the chart with a place for standard in-process stock
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk
Or browse the topics, the full library and the lean glossary.
Rather see it on your own problem?
Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.