Skip to content
LeanSuite

Standard WIP: how to calculate standard work in process for a cell

Short answer

Standard WIP is the smallest number of pieces that must be in a process for the operator to repeat the work sequence without waiting. For each step, divide the time one piece stays there by takt time and round up. Add the steps. That is the number.

Standard work in process, also called SWIP or standard in-process stock, is the third element of standard work. To calculate it for a cell, list every step where a piece sits without the operator: each machine, and each timed wait such as curing or cooling. Divide the time a piece stays at the step by takt time and round up. A machine that finishes inside one takt time needs 1 piece. A 300 second cure at a 72 second takt time needs 5. Add the steps together. If the operator walks against the flow of parts, add one piece between each pair of machines. In the example on this page the answer is 9 pieces.

Last reviewed:

What is standard WIP?

Standard WIP for one cell: 9 pieces, each with a reason

Example numbers

Takt time 72 s: one piece leaves, and one enters, every 72 s

  1. 1

    Press

    8 s load, 20 s machine

    28 / 72 = 0.39, so 1 piece

  2. 2

    Dispense

    6 s load, 30 s machine

    36 / 72 = 0.50, so 1 piece

  3. 3

    Cure rack

    300 s cure, nobody there

    300 / 72 = 4.17, so 5 pieces

  4. 4

    Tester

    8 s load, 100 s test

    108 / 72 = 1.50, so 2 pieces

9

pieces of standard WIP: 1 + 1 + 5 + 2. A piece takes 9 x 72 = 648 s, or 10.8 minutes, to cross the cell.

Four steps in a row with a takt time of 72 seconds. The press holds 1 piece, the dispenser 1 piece, the cure rack 5 pieces and the two-nest tester 2 pieces. Total 9 pieces.

Each yellow dot is a piece that must be in the cell when the operator starts a cycle. A step that holds a piece for less than one takt time needs 1. The cure rack holds each piece for 300 s, more than four takt times, so it needs 5. Add them up: 9.

Standard WIP is the number of pieces a process needs inside it to keep going. The Lean Enterprise Institute's Lean Lexicon gives it as the third element of standardized work: the standard inventory, including units in machines, required to keep the process operating smoothly. Taiichi Ohno called it standard inventory and described it as the minimum work in process needed for operations to proceed. Plants also say standard in-process stock, SWIP or SIPS. They all mean the same number.

It exists because of a simple fact about cells. When an operator arrives at a machine, there has to be a finished piece in it to take out, or the operator stands and waits for the cycle. So each machine holds a piece while the operator is somewhere else. Those pieces are not waste. They are what lets one person run several machines.

It is a minimum and a maximum at once. One piece fewer and somebody waits. One piece more and it sits on a bench, hiding whatever went wrong. That makes it the easiest of the three elements of standard work to check: stand in the aisle and count.

How to calculate standard WIP

Work step by step through the cell, in the order the part flows. At each step ask one question: how long does one piece stay here with nobody holding it? Then divide by takt time and round up.

Pieces at a step = time one piece stays at the step / takt time, rounded up to a whole piece. Standard WIP for the cell is the sum over all the steps. The reasoning is that one piece enters the step every takt time and one leaves, so a piece that stays for four and a bit takt times has four more behind it.

The rule for each kind of step
Kind of stepPieces to countWhy
Machine that holds one piece and finishes inside takt time1The ratio is under 1 and rounds up to 1. The piece waits in the machine until the operator comes back.
Machine whose load plus cycle time is longer than takt timeTime / takt time, rounded upOne nest cannot keep up. A tester that needs 108 seconds at a 72 second takt time needs 2 nests and holds 2 pieces.
Timed wait with no machine: cure, cool, dry, soakTime / takt time, rounded upThe pieces queue in a first in, first out lane. One goes in and one comes out every takt time.
Manual step with no machine0The piece is in the operator's hands and moves with them. Some plants count 1 per operator instead. Pick one convention and note it.
Operator walks against the flow of partsAdd 1 between each pair of machinesEach machine is unloaded before the part it needs next has arrived, so one has to be waiting. This is Ohno's rule.
Batch step: oven, washer, outside processAt least one full batch in the step, plus the pieces building up for the nextA batch step cannot take one piece each takt time. Gemba Academy teaches doubling the rounded ratio for these steps.

Raw material waiting at the start and finished goods at the end are not standard WIP. They are set separately, usually by container size or a kanban.

A quick estimate you will see quoted is the sum of all the cycle times divided by takt time. It is a useful first guess for the size of the answer. It comes out low, because it does not round up at each step, and it says nothing about where the pieces go. Use the step by step count for the number you post.

Worked example: a cell with a cure rack

Illustrative numbers. A cell bonds a sensor into a housing. The shift has 450 minutes of working time, 27,000 seconds, and the customer needs 375 pieces: takt time is 27,000 / 375 = 72 seconds. The part goes through a press, an adhesive dispenser, a cure rack and a tester. The operator walks with the flow.

Illustrative: standard WIP for the sensor housing cell, takt time 72 seconds
StepTime one piece staysDivided by takt timePieces
Press8 s load + 20 s machine = 28 s28 / 72 = 0.391
Dispenser6 s load + 30 s machine = 36 s36 / 72 = 0.501
Cure rack300 s cure300 / 72 = 4.175
Tester8 s load + 100 s test = 108 s108 / 72 = 1.502

Standard WIP: 1 + 1 + 5 + 2 = 9 pieces. The tester needs two nests, loaded on alternate cycles.

The sum, step by step

Example numbers

Pieces at a step = time one piece stays at the step ÷ takt time, rounded up

Takt time is 72 s. Time at a step is load time plus machine time, or the full cure, cool or dry time.

  1. Press =28 ÷ 72 = 0.39, rounded up= 1
  2. Dispense =36 ÷ 72 = 0.50, rounded up= 1
  3. Cure rack =300 ÷ 72 = 4.17, rounded up= 5
  4. Tester =108 ÷ 72 = 1.50, rounded up= 2
Standard WIP for the cell9 pieces
Round each step up on its own, then add. Adding the four ratios first and rounding the total would give 7 pieces, which is not enough to keep every step fed.

Two rows deserve a second look. The cure rack needs 5 places, not 4: a piece that has been in for four takt times, 288 seconds, has not finished its 300 second cure, so a fifth is behind it. And the tester is slower than takt time. One nest would pass a piece every 108 seconds when the cell needs one every 72. Two nests, loaded turn about, each have 144 seconds between loads, which covers the 108.

Standard WIP also tells you how long a part takes to cross the cell. One piece leaves every takt time, so 9 pieces is 9 x 72 = 648 seconds, about 10.8 minutes from the press to the end of test. If a defect is found at the tester, that is how old the cause is, and 9 is how many suspect pieces are behind it.

Walking with the flow or against it

The count depends on which way the operator walks. Ohno put it this way in Toyota Production System: if the work is done in the order of the machining processes, only the items mounted on the machines are needed and nothing has to be held between machines. If the operator proceeds in the reverse order, one item's worth of inventory is needed between machines.

The reason is easy to see at one machine. Walking with the flow, the operator arrives carrying the part from the machine before, swaps it for the finished one and carries that forward. Walking against the flow, the operator arrives empty-handed from downstream. The part to load must already be waiting there, and the part just unloaded is put down for the next lap. Three machines need 3 pieces one way and 5 the other.

Same three machines, two walking directions

Example numbers

With the flow

3 pieces

The operator carries each part forward to the next machine, so nothing waits between machines.

M1
M2
M3

Against the flow

5 pieces

Each machine is unloaded into the gap behind the operator, and loaded from the gap ahead.

M1
between
M2
between
M3

Two drawings of three machines in a row, with parts flowing from machine 1 to machine 3. When the operator walks in the same direction as the parts, standard WIP is 3 pieces, one in each machine. When the operator walks against the flow, one more piece is needed between each pair of machines, so standard WIP is 5 pieces.

Walking against the flow, the operator unloads a machine before the part it needs next has arrived, so a finished piece has to be waiting between each pair of machines. That is 2 extra pieces here. Taiichi Ohno gives this as the rule for standard inventory.

Plants do sometimes walk against the flow on purpose, for example to bring the operator back to the start of a U-shaped cell beside the finish. It is a fair trade as long as the extra pieces are counted, marked and on the chart.

One short, one over

Standard WIP is only useful if a different count is visible and means something. In the example, 8 pieces means a step is starved and the cell will miss a cycle. 10 means a piece is waiting somewhere it has no place, which usually means a machine was late on an earlier cycle and nobody said so.

One piece short, standard, one piece over

Example numbers
  • One short

    8 pieces

    The operator reaches the tester and the rack has nothing cured to load. The tester misses a cycle, and so does the customer.

    What you see

    An empty nest or an empty rack slot

  • Standard

    9 pieces

    Every machine has its piece and every rack slot is full. One piece leaves and one enters each takt time.

    What you see

    Nothing waiting, nothing missing

  • One over

    10 pieces

    The extra piece sits on a bench between steps. It hides a late machine for one cycle, and it ages if the next step finds a defect.

    What you see

    A part on a bench with no marked place

Three states of the same cell. With 8 pieces the tester is starved. With 9 pieces the cell flows. With 10 pieces one part waits on a bench.

Standard WIP is a number you can audit from the aisle. Count the pieces. A different count means the cell is not running to its standard, whatever the output board says.
  • Give every piece a marked place: a nest, a numbered rack slot, a painted square. No place, no piece.
  • Put the number on the standard work chart and mark each piece on the layout.
  • Make the count part of the team leader's walk. It takes ten seconds.
  • When the count is wrong, ask what happened on the last few cycles before putting it right.
  • At the end of a shift, leave the cell with its standard WIP in place so the next shift starts in flow.

How to bring the number down

Standard WIP is the right amount for the cell as it is today. Change the cell and the right amount changes. In the example the cure rack holds 5 of the 9 pieces, so that is where to look. A faster-curing adhesive at 140 seconds gives 140 / 72 = 1.94, which rounds up to 2. The total falls from 9 to 6, and time through the cell from 648 seconds to 6 x 72 = 432.

Shorten the longest stay and the standard WIP falls

Example numbers

Before

300 s cure: 9 pieces

9 x 72 = 648 s through the cell.

  1. 1

    Press

    8 s load, 20 s machine

    28 / 72 = 0.39, so 1 piece

  2. 2

    Dispense

    6 s load, 30 s machine

    36 / 72 = 0.50, so 1 piece

  3. 3

    Cure rack

    300 s cure, nobody there

    300 / 72 = 4.17, so 5 pieces

  4. 4

    Tester

    8 s load, 100 s test

    108 / 72 = 1.50, so 2 pieces

After

140 s cure: 6 pieces

6 x 72 = 432 s through the cell.

  1. 1

    Press

    8 s load, 20 s machine

    28 / 72 = 0.39, so 1 piece

  2. 2

    Dispense

    6 s load, 30 s machine

    36 / 72 = 0.50, so 1 piece

  3. 3

    Cure rack

    140 s cure, nobody there

    140 / 72 = 1.94, so 2 pieces

  4. 4

    Tester

    8 s load, 100 s test

    108 / 72 = 1.50, so 2 pieces

Before, the adhesive cures for 300 seconds, the rack holds 5 pieces and standard WIP is 9. After a change to a 140 second cure the rack holds 2 pieces and standard WIP is 6. Time through the cell falls from 648 to 432 seconds.

The cure rack held more than half the pieces in the cell. A faster-curing adhesive takes the rack from 5 pieces to 2, standard WIP from 9 to 6, and the time a part spends in the cell from 10.8 to 7.2 minutes. The standard work chart has to be reissued with the new number.
  • Shorten the longest stay. Cure, cooling and test times usually hold the most pieces.
  • Bring a slow machine under takt time, so it needs one nest and not two.
  • Change the walking direction to follow the flow, if the layout allows.
  • Replace a batch step with one that takes single pieces.
  • Do not cut the number without changing the process. Taking a piece out of a cell that needs it only moves the waiting to the operator.

Takt time moves the number too. A shorter takt time means more pieces, because the same stay now spans more cycles. If demand rises and takt time falls from 72 to 60 seconds, the 300 second cure needs 300 / 60 = 5 places and the tester still needs 2, so the cell still needs 9. At a 50 second takt time the rack needs 6 and the tester 3, and the cell needs 11. Recalculate whenever takt time changes. Updating standard work after an improvement covers reissuing the chart.

Common mistakes

  • Rounding the total and not each step. The pieces cannot be shared between steps.
  • Counting raw material and finished goods. Standard WIP is what sits inside the process.
  • Treating it as a target to minimise. Below the standard, the operator waits.
  • Treating it as a limit only. Above the standard is as wrong as below.
  • Forgetting the walking direction. A cell walked against the flow needs more, and the chart must show where.
  • Leaving it as a number on a sheet. Without a marked place for each piece nobody can see a wrong count.
  • Using it outside repeating work. A job shop or a maintenance bench has no takt time to divide by. Cap the work in process there another way, such as a limit on open jobs.

Where software helps

The calculation needs honest times for each step: load time, machine time and how long a piece really sits in the rack. LeanSuite's Time and Motion Study drafts element times from a video of the cell on a timeline that links back to the footage, for you to check and certify. The count and the chart are then yours to draw: the standard work sheet is a free template with a place for the standard in-process stock.

Standardized work software

Keep standard work current in LeanSuite

LeanSuite covers most of the cycle in one platform: working out the standard with Vision AI, keeping it current with SOPs and work instructions, and training and auditing it.

FAQ

Questions about standard WIP

  1. Standard WIP, or standard work in process, is the smallest number of pieces that must be inside a process for the operator to repeat the work sequence without waiting. It includes the pieces in machines. It is one of the three elements of standard work, with takt time and work sequence, and it is marked on the standard work chart.

  2. For each step where a piece sits without the operator, divide the time the piece stays there by takt time and round up. Add the results. A machine that finishes within one takt time needs 1 piece. A 300 second cure at a 72 second takt time needs 5. If the operator walks against the flow, add one piece between each pair of machines.

  3. Pieces at a step equal the time one piece stays at the step divided by takt time, rounded up. Standard WIP is the sum across the steps. A quick estimate is the sum of all cycle times divided by takt time, but it comes out low because it does not round up at each step.

  4. Not quite. A WIP limit is a ceiling: do not exceed this many. Standard WIP is an exact amount: the cell needs this many to run, and more or fewer both signal a problem. Standard WIP also needs a takt time and a repeating sequence. A WIP limit can be used anywhere.

  5. Walking with the flow, the operator carries each part to the next machine. Walking against it, the operator reaches each machine before the part it needs, so one has to be waiting there from the previous lap. Taiichi Ohno gives the rule: in the order of the processes only the pieces on the machines are needed, in reverse order one more between machines.

  6. No. It counts the pieces inside the process: in machines, in cure or cooling lanes and, where the operator walks against the flow, between machines. Raw material at the start and finished goods at the end are set separately, usually by container size or kanban.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.