Methods-Time Measurement (MTM) is a predetermined motion time system. It breaks manual work into basic motions such as reach, grasp, move, position and release and gives each a time in TMU. One TMU is 0.00001 hour, which is 0.036 seconds.

MTM sets the time for a manual job from its method. In MTM-1, the original system, you list every basic motion of each hand, code it by its conditions (distance, how exact the placement is, how easy the grasp), read the time for that code from the MTM data card and add the times. The total is the normal time in TMU: multiply by 0.036 for seconds or 0.0006 for minutes, then add allowances for standard time. MTM-2 and MTM-UAS use bigger building blocks, so they are quicker to apply and suit longer cycles and batch work. The data tables are licensed by the MTM associations, which also train and certify analysts.

Last reviewed:

What is Methods-Time Measurement?

One hand, five basic motions, 34 TMU

Example numbers
1
2
3
4
5
  1. 1Reach to bracket R10B12 TMU
  2. 2Grasp bracket G1A2 TMU
  3. 3Move bracket to pin M10C12 TMU
  4. 4Position on pin P1SE6 TMU
  5. 5Release RL12 TMU

12 + 2 + 12 + 6 + 2 = 34 TMU x 0.036 = 1.224 s

The right hand takes a bracket and seats it on a pin: Reach to bracket, code R10B, 12 TMU; Grasp bracket, code G1A, 2 TMU; Move bracket to pin, code M10C, 12 TMU; Position on pin, code P1SE, 6 TMU; Release, code RL1, 2 TMU. Total 34 TMU, which is 1.224 seconds. The values are illustrative.

Illustrative teaching values in whole TMU, not the MTM-1 data card. Each motion has a code, each code has a time, and the cycle is their sum.

In manufacturing, MTM means Methods-Time Measurement. (The same three letters are also a transport company, a watch brand and made to measure clothing, which is why searches for it are a mess.) It is the best known predetermined motion time system: a way to work out how long a manual job should take by describing the motions, not by timing a person.

Its authors described a procedure in two parts. First, break a manual operation down into the basic motions it needs. Second, give every motion a time that was fixed in advance and depends only on what kind of motion it is and the conditions it is made under. Both halves of the name matter. The time comes out of the method, so the only way to get a shorter time is a better method.

MTM was built by Harold B. Maynard, Gustave J. Stegemerten and John L. Schwab of the Methods Engineering Council in the 1940s, during work for Westinghouse. They filmed shop operations at 16 frames a second, counted the frames each motion took, and levelled the times to a normal pace with the Westinghouse rating system. The book, Methods-Time Measurement, came out in 1948, and the tables were printed in it for anyone to use. That openness is why MTM became the common reference and why later systems, including MOST and MODAPTS, were built on it or checked against it.

What is a TMU, and how do you convert it to seconds?

TMU stands for time measurement unit. One TMU is one hundred-thousandth of an hour: 0.00001 hour, 0.0006 minute, 0.036 second. The unit is that small because the motions are that short. A simple grasp is about 2 TMU, seven hundredths of a second. Writing that in seconds would fill the tables with zeros, so the authors picked a unit small enough to work in whole numbers and one decimal.

How small a TMU is: the five motions against one second

Example numbers
The five motions on a TMU rulerA bar of 34 TMU drawn on a scale from 0 to 40 TMU, with a marker at 27.8 TMU for one second.341 second = 27.8 TMU010203040TMU

1 TMU

= 0.036 s

27.8 TMU

= 1 second

1,666.7 TMU

= 1 minute

100,000 TMU

= 1 hour

A ruler in TMU. One second is 27.8 TMU. The five motions of the example total 34 TMU, 1.22 seconds. One TMU is 0.036 second, one minute is 1,666.7 TMU and one hour is 100,000 TMU.

A whole reach, grasp, move, position and release takes about a second and a quarter. Seconds are too coarse a unit for work this short.
TMU conversions
To convertDo thisExample
TMU to secondsTMU x 0.03634 TMU x 0.036 = 1.224 s
TMU to minutesTMU x 0.0006380 TMU x 0.0006 = 0.228 min
TMU to hoursTMU / 100,000380 TMU = 0.0038 h
Seconds to TMUSeconds x 27.810 s = 277.8 TMU
Minutes to TMUMinutes x 1,666.71 min = 1,666.7 TMU
Hours to TMUHours x 100,0001 h = 100,000 TMU

27.8 is 1 / 0.036 and 1,666.7 is 60 / 0.036, both rounded to one decimal.

Two things to remember when you convert. First, a TMU total is a normal time: it has no allowance in it. Second, the hour form is handy for costing, because standard hours per 100 pieces is simply TMU per piece divided by 1,000. A job of 380 TMU is 0.38 standard hours per 100 before allowances. MOST uses the same TMU. MODAPTS does not: its unit is the MOD, 0.129 second.

The MTM-1 basic motions

MTM-1 is the original, most detailed system. Everything a person does with their hands, eyes and body at a workstation is written as a string of the motions below. For each one, the data card has a table, and the columns of that table are the conditions that change the time.

The MTM-1 basic motions, by the part of the body that makes them

Arm

Reach (R)Move (M)Turn (T)Crank (C)

Hand and fingers

Grasp (G)Release (RL)Position (P)Disengage (D)Apply pressure (AP)

Eyes

Eye travel (ET)Eye focus (EF)

Body, legs and feet

Foot and leg motionSidestepTurn bodyBend, stoop, kneelSit and standWalk
Most bench work is written with the first two groups. Eye and body motions are added only when they limit the cycle.
The MTM-1 basic motions and what changes their time
MotionSymbolWhat it isWhat the time depends on
ReachRMoving the empty hand to a destinationDistance, and the case: how well defined the destination is
MoveMMoving an object with the handDistance, the case (to the other hand or a stop, to an approximate place, to an exact place) and weight
TurnTRotating the hand and forearm about the forearm's long axisDegrees turned and weight
Apply pressureAPA short push or squeeze with no real movementWhether the grip has to be reset first
GraspGGetting control of an object with the fingersThe type: pick-up, regrasp, transfer, select from a jumble, contact
PositionPAligning and engaging one object with anotherClass of fit (loose, close, exact), symmetry and ease of handling
ReleaseRLLetting goOpening the fingers, or simply breaking contact
DisengageDPulling two objects apart against resistanceClass of fit and ease of handling
CrankCMoving the hand in a circle to turn a handleDiameter, number of turns and resistance
Eye travel and eye focusET, EFShifting the eyes to a new place, and looking long enough to seeDistance between the points and from the eye; focus is a fixed time
Body, leg and foot motionsFoot and leg motion, sidestep, turn body, bend, stoop, kneel, sit, stand, walkThe motion, and for walking the number of paces

Structure only. The time values belong to the MTM associations and are on the licensed MTM-1 data card.

The cases are where the method shows. Take reach. Reaching to a part that always sits in the same nest is one case. Reaching to a part that lies alone but in a slightly different spot each cycle is another. Reaching into a bin of jumbled parts, where the hand has to search and select, is a third, and it takes longer for the same distance. So when a methods engineer puts a part in a fixed nest, the saving is visible in the code before anything is built.

MTM-1 also has rules for motions made at the same time. If both hands reach together, the cycle is charged only the longer of the two. And the card has a table that says which pairs of motions a practised person can truly do together, which ones need practice and which cannot be combined, such as two exact positions outside the area of normal vision.

How a motion code and the data card are read

An MTM-1 code is a short sentence. The first letter says which motion. The number says how far or how much. The letters after it say which case. R10B reads: reach, 10 inches, case B, an object in a location that may vary a little from cycle to cycle. P1SE reads: position, class 1 fit (loose, no pressure needed), symmetrical part, easy to handle. Metric cards give distances in centimetres, so check which card a study used.

How to read an MTM-1 code

R10B

Rthe motion: reach
10the distance, in inches
Bthe case: how well defined the target is

Reach 10 inches to a single object whose place varies a little from cycle to cycle.

P1SE

Pthe motion: position
1class of fit: 1 is loose
Ssymmetry of the part
Eease of handling

Position with a loose fit, a symmetrical part, easy to handle.

R10B reads reach, 10 inches, case B: an object whose location varies slightly. P1SE reads position, class 1 loose fit, symmetrical, easy to handle.

The letter names the table. The number picks the row. The case letters pick the column. The time is where they meet.

To read the time, open the table for that motion, find the row for the distance and the column for the case, and take the figure where they meet. Distances that fall between rows go to the next row or are interpolated, by the card's own rule. A weight above the table's light limit adds a factor and a constant to a move. That is all the look-up there is. The judgement is in choosing the case, and it is the part that takes training.

This page does not print the tables. They are copyrighted, and a table copied from a web page with no training behind it produces standards nobody can defend. For real analysis use the current data card from your MTM association.

A worked example: one hand, five motions

Illustrative example. An operator's right hand takes a bracket that lies alone on the bench 10 inches away and places it on a locating pin 10 inches from there. The TMU values are whole numbers chosen for teaching. They are close to the scale of the real ones and are not the MTM-1 card values.

  1. 1

    Describe the motion in order

    Reach to the bracket. Close the fingers on it. Carry it to the pin. Line it up and seat it. Let go. Five motions, one hand.

  2. 2

    Measure the distances

    Hand to bracket: 10 inches. Bracket to pin: 10 inches. Measure the path the hand travels, not the straight line on the drawing.

  3. 3

    Choose the case for each motion

    The bracket lies alone but not in a nest, so the reach is case B. It is easy to pick up: a simple pick-up grasp. The move ends at an exact place, the pin. The fit is loose, the hole is round and the part is easy to handle.

  4. 4

    Write the codes

    R10B, G1A, M10C, P1SE, RL1.

  5. 5

    Read and add the times

    With the illustrative values: 12 + 2 + 12 + 6 + 2 = 34 TMU.

  6. 6

    Convert

    34 x 0.036 = 1.224 seconds, or 34 x 0.0006 = 0.0204 minutes. This is normal time for one hand's part of the cycle, before allowances.

Illustrative: the five motions with teaching values, not MTM-1 card values
MotionCodeWhy this caseTMU (illustrative)
Reach to bracketR10BSingle object, position varies slightly12
Grasp bracketG1AEasy pick-up of an object by itself2
Move bracket to pinM10CTo an exact location12
Position on pinP1SELoose fit, symmetrical, easy to handle6
ReleaseRL1Open the fingers2
Total34 TMU = 1.224 s

Use the licensed MTM-1 data card for real values. They are printed to one decimal and differ from these.

Now change the method on paper. Put the brackets in a nest so the hand always finds one in the same place and the reach becomes the easiest case. Chamfer the pin so the position needs less care. Each change swaps one code for a cheaper one, and you can add up the saving before anyone cuts metal. That is what the system was built for: the M in MTM stands for methods.

MTM-2, MTM-UAS and MTM-MEK: bigger blocks for longer work

MTM-1 is precise and slow to apply. For a ten second cycle made a million times a year that effort pays. For a four minute assembly made in batches of fifty it does not. The later MTM systems combine the basic motions into bigger blocks, so one line of analysis covers what took three or five lines in MTM-1.

The MTM systems by level of detail
SystemBuilding blocksTypical use
MTM-1Single basic motions: reach, grasp, move, position, release and the restShort cycles in mass production, where a fraction of a second is worth analysing
MTM-2 (International MTM Directorate, 1965)Eleven categories. GET combines reach, grasp and release. PUT combines move and position. The others are get weight, put weight, regrasp, apply pressure, eye action, crank, step, foot motion, and bend and ariseCycles of roughly a minute or more that still repeat often
MTM-UAS (German, Swiss and Austrian associations, mid-1970s)Basic operations: get and place, place, handle tool, operate, motion cycles, body motions, visual controlBatch production. The MTM Association calls it the most used MTM system
MTM-MEKLarger operations again, built for work that seldom repeats exactlyOne-off and small-batch production

MTM-3 (1970) simplified MTM-2 further and is no longer maintained. Newer systems from the MTM associations, such as MTM-HWD, describe the motion and the posture together.

The same pick and place at three levels of detail

MTM-1

5 lines

R
G
M
P
RL

Reach, grasp, move, position, release: each coded on its own.

MTM-2

2 lines

GET
PUT

GET combines reach, grasp and release. PUT combines move and position.

MTM-UAS

1 line

Get and place

One basic operation, chosen by distance band, weight and how exact the placing is.

MTM-1 writes the pick and place as five lines: reach, grasp, move, position, release. MTM-2 writes it as two: GET, which combines reach, grasp and release, and PUT, which combines move and position. MTM-UAS writes it as one line: get and place.

Fewer lines means faster analysis. It also means you can no longer see which motion inside the block is worth improving.

The coarser systems also simplify the choices. MTM-2 has only three cases of GET and three of PUT, and it sorts distance into five bands in place of a row for every inch. A whole-body motion is a single figure: bend and arise is 61 TMU in MTM-2. Fewer choices means faster analysis and fewer places for two analysts to differ.

What you give up is resolution. A block that covers reach, grasp and release as one line cannot tell you which of the three to improve, and on a very short cycle the rounding inside each block is a visible share of the total. The rule of thumb is to match the system to the cycle: MTM-1 for the short, high-volume cycle, MTM-2 in the middle, MTM-UAS for batch work and MTM-MEK when each job is nearly a one-off. Never mix levels inside one standard without saying so on the sheet.

Training and certification

MTM is taught and licensed by the MTM associations: national bodies that work under an international umbrella and own the data. The routes differ a little by country, but the pattern is the same everywhere.

  • A course for each system, taught by a licensed instructor, with an exam at the end. The MTM-1 course is the longest because it covers every motion and case. MTM-2 and MTM-UAS courses are shorter and usually assume the basics.
  • A certificate that names the system and the level, often with an expiry date and a refresher to renew it. Many customers and works councils ask to see it before they accept a standard.
  • Further levels for people who will build standard data, train others or audit analyses.
  • Licensed data cards and software. The tables and the building blocks may not be copied into a home-made spreadsheet and shared.

If you are choosing, ask what your customers and your sister plants use. Some customers, particularly in automotive supply chains, ask for a specific MTM system by name. A certificate in the system your customer audits against is worth more than a deeper one in a system nobody around you reads.

Limits, and the people side

  • MTM covers manual motion. Machine time, process time and waiting are added from other sources.
  • It describes a trained operator who knows the job. A learner takes longer, and MTM does not say how much longer.
  • It gives one clean cycle. Fumbles, sticking parts and variation between pieces are not in the total, so compare it with a few timed or filmed cycles once the job runs.
  • The analysis is only as good as the method description. A wrong distance or a wrong case is easy to write and hard to spot later.
  • MTM-1 on long cycles costs more analyst time than the standard is worth. Use a coarser system or a time study.

To the person at the station, an MTM standard can look like a number invented in an office. Show the analysis line by line at the workplace, let the operator try the method it describes, and correct the analysis where the real job differs. People accept a time they can check far more readily than one they are told. Where a works council or union agreement governs work measurement, it may say which system can be used and how a standard is disputed. This is general practice, not legal advice.

Related tools and next steps

Once a job is running, the quickest check on an MTM standard is to film it. LeanSuite's Time and Motion Study times every element from one phone video and links each time to its video frame, so you can put the measured elements next to the analysed ones and see where they part.

FAQ

Questions about mTM (Methods-Time Measurement)

  1. MTM is Methods-Time Measurement, a predetermined motion time system published in 1948 by Maynard, Stegemerten and Schwab. It sets the time for a manual job by breaking it into basic motions such as reach, grasp, move, position and release and adding a published time for each. The times are in TMU, where 1 TMU is 0.036 seconds. It is used to set standards, plan new jobs and improve methods.

  2. Methods-Time Measurement is a way to time manual work from its method. The job is broken into basic motions, and each motion gets a time that was fixed in advance for that kind of motion under those conditions: the distance, the fit, the weight. The analyst describes the method, codes the motions, reads the times from the MTM data card and adds them. No stopwatch and no performance rating are involved.

  3. A TMU is a time measurement unit, the unit used by MTM and MOST. One TMU is 0.00001 hour, 0.0006 minute or 0.036 second, so there are 100,000 TMU in an hour, about 1,666.7 in a minute and about 27.8 in a second. To convert TMU to seconds, multiply by 0.036. A motion sequence of 34 TMU takes 1.224 seconds.

  4. Multiply TMU by 0.036 for seconds and by 0.0006 for minutes. For example, 380 TMU x 0.036 = 13.68 seconds, and 380 x 0.0006 = 0.228 minutes. Going the other way, multiply seconds by 27.8 or minutes by 1,666.7 to get TMU. Divide TMU by 100,000 for hours. The result is a normal time, so add allowances before you use it as a standard.

  5. The size of the building block. MTM-1 uses single basic motions and suits short cycles in mass production. MTM-2, from 1965, combines them into eleven categories such as GET and PUT and suits cycles of about a minute or more. MTM-UAS, from the mid-1970s, uses basic operations such as get and place and handle tool and was built for batch production. Each step is faster to apply and less detailed.

  6. Reach, move, turn, apply pressure, grasp, position, release, disengage and crank for the hands and arms, eye travel and eye focus for the eyes, and a set of body, leg and foot motions such as step, sidestep, bend, stoop, kneel, sit, stand and walk. Each has its own table on the MTM-1 data card, with the time set by conditions such as distance, case, fit and weight.

  7. You should not. The tables are copyrighted by the MTM associations and licensed with their training, and the hard part of MTM is not the look-up but choosing the right case for each motion. An untrained analysis produces a precise-looking number that nobody can defend. Take the association's course for the system you need and use its current data card or software.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.