Method guide · Standard work, SOPs and training
MTM (Methods-Time Measurement): MTM-1, MTM-2, MTM-UAS and what a TMU is
Short answer
Methods-Time Measurement (MTM) is a predetermined motion time system. It breaks manual work into basic motions such as reach, grasp, move, position and release and gives each a time in TMU. One TMU is 0.00001 hour, which is 0.036 seconds.
MTM sets the time for a manual job from its method. In MTM-1, the original system, you list every basic motion of each hand, code it by its conditions (distance, how exact the placement is, how easy the grasp), read the time for that code from the MTM data card and add the times. The total is the normal time in TMU: multiply by 0.036 for seconds or 0.0006 for minutes, then add allowances for standard time. MTM-2 and MTM-UAS use bigger building blocks, so they are quicker to apply and suit longer cycles and batch work. The data tables are licensed by the MTM associations, which also train and certify analysts.
Last reviewed:
What is Methods-Time Measurement?
One hand, five basic motions, 34 TMU
Example numbers- 1Reach to bracket R10B12 TMU
- 2Grasp bracket G1A2 TMU
- 3Move bracket to pin M10C12 TMU
- 4Position on pin P1SE6 TMU
- 5Release RL12 TMU
12 + 2 + 12 + 6 + 2 = 34 TMU x 0.036 = 1.224 s
The right hand takes a bracket and seats it on a pin: Reach to bracket, code R10B, 12 TMU; Grasp bracket, code G1A, 2 TMU; Move bracket to pin, code M10C, 12 TMU; Position on pin, code P1SE, 6 TMU; Release, code RL1, 2 TMU. Total 34 TMU, which is 1.224 seconds. The values are illustrative.
In manufacturing, MTM means Methods-Time Measurement. (The same three letters are also a transport company, a watch brand and made to measure clothing, which is why searches for it are a mess.) It is the best known predetermined motion time system: a way to work out how long a manual job should take by describing the motions, not by timing a person.
Its authors described a procedure in two parts. First, break a manual operation down into the basic motions it needs. Second, give every motion a time that was fixed in advance and depends only on what kind of motion it is and the conditions it is made under. Both halves of the name matter. The time comes out of the method, so the only way to get a shorter time is a better method.
MTM was built by Harold B. Maynard, Gustave J. Stegemerten and John L. Schwab of the Methods Engineering Council in the 1940s, during work for Westinghouse. They filmed shop operations at 16 frames a second, counted the frames each motion took, and levelled the times to a normal pace with the Westinghouse rating system. The book, Methods-Time Measurement, came out in 1948, and the tables were printed in it for anyone to use. That openness is why MTM became the common reference and why later systems, including MOST and MODAPTS, were built on it or checked against it.
What is a TMU, and how do you convert it to seconds?
TMU stands for time measurement unit. One TMU is one hundred-thousandth of an hour: 0.00001 hour, 0.0006 minute, 0.036 second. The unit is that small because the motions are that short. A simple grasp is about 2 TMU, seven hundredths of a second. Writing that in seconds would fill the tables with zeros, so the authors picked a unit small enough to work in whole numbers and one decimal.
How small a TMU is: the five motions against one second
Example numbers1 TMU
= 0.036 s
27.8 TMU
= 1 second
1,666.7 TMU
= 1 minute
100,000 TMU
= 1 hour
A ruler in TMU. One second is 27.8 TMU. The five motions of the example total 34 TMU, 1.22 seconds. One TMU is 0.036 second, one minute is 1,666.7 TMU and one hour is 100,000 TMU.
| To convert | Do this | Example |
|---|---|---|
| TMU to seconds | TMU x 0.036 | 34 TMU x 0.036 = 1.224 s |
| TMU to minutes | TMU x 0.0006 | 380 TMU x 0.0006 = 0.228 min |
| TMU to hours | TMU / 100,000 | 380 TMU = 0.0038 h |
| Seconds to TMU | Seconds x 27.8 | 10 s = 277.8 TMU |
| Minutes to TMU | Minutes x 1,666.7 | 1 min = 1,666.7 TMU |
| Hours to TMU | Hours x 100,000 | 1 h = 100,000 TMU |
27.8 is 1 / 0.036 and 1,666.7 is 60 / 0.036, both rounded to one decimal.
Two things to remember when you convert. First, a TMU total is a normal time: it has no allowance in it. Second, the hour form is handy for costing, because standard hours per 100 pieces is simply TMU per piece divided by 1,000. A job of 380 TMU is 0.38 standard hours per 100 before allowances. MOST uses the same TMU. MODAPTS does not: its unit is the MOD, 0.129 second.
The MTM-1 basic motions
MTM-1 is the original, most detailed system. Everything a person does with their hands, eyes and body at a workstation is written as a string of the motions below. For each one, the data card has a table, and the columns of that table are the conditions that change the time.
The MTM-1 basic motions, by the part of the body that makes them
Arm
Hand and fingers
Eyes
Body, legs and feet
| Motion | Symbol | What it is | What the time depends on |
|---|---|---|---|
| Reach | R | Moving the empty hand to a destination | Distance, and the case: how well defined the destination is |
| Move | M | Moving an object with the hand | Distance, the case (to the other hand or a stop, to an approximate place, to an exact place) and weight |
| Turn | T | Rotating the hand and forearm about the forearm's long axis | Degrees turned and weight |
| Apply pressure | AP | A short push or squeeze with no real movement | Whether the grip has to be reset first |
| Grasp | G | Getting control of an object with the fingers | The type: pick-up, regrasp, transfer, select from a jumble, contact |
| Position | P | Aligning and engaging one object with another | Class of fit (loose, close, exact), symmetry and ease of handling |
| Release | RL | Letting go | Opening the fingers, or simply breaking contact |
| Disengage | D | Pulling two objects apart against resistance | Class of fit and ease of handling |
| Crank | C | Moving the hand in a circle to turn a handle | Diameter, number of turns and resistance |
| Eye travel and eye focus | ET, EF | Shifting the eyes to a new place, and looking long enough to see | Distance between the points and from the eye; focus is a fixed time |
| Body, leg and foot motions | Foot and leg motion, sidestep, turn body, bend, stoop, kneel, sit, stand, walk | The motion, and for walking the number of paces |
Structure only. The time values belong to the MTM associations and are on the licensed MTM-1 data card.
The cases are where the method shows. Take reach. Reaching to a part that always sits in the same nest is one case. Reaching to a part that lies alone but in a slightly different spot each cycle is another. Reaching into a bin of jumbled parts, where the hand has to search and select, is a third, and it takes longer for the same distance. So when a methods engineer puts a part in a fixed nest, the saving is visible in the code before anything is built.
MTM-1 also has rules for motions made at the same time. If both hands reach together, the cycle is charged only the longer of the two. And the card has a table that says which pairs of motions a practised person can truly do together, which ones need practice and which cannot be combined, such as two exact positions outside the area of normal vision.
How a motion code and the data card are read
An MTM-1 code is a short sentence. The first letter says which motion. The number says how far or how much. The letters after it say which case. R10B reads: reach, 10 inches, case B, an object in a location that may vary a little from cycle to cycle. P1SE reads: position, class 1 fit (loose, no pressure needed), symmetrical part, easy to handle. Metric cards give distances in centimetres, so check which card a study used.
How to read an MTM-1 code
R10B
Reach 10 inches to a single object whose place varies a little from cycle to cycle.
P1SE
Position with a loose fit, a symmetrical part, easy to handle.
R10B reads reach, 10 inches, case B: an object whose location varies slightly. P1SE reads position, class 1 loose fit, symmetrical, easy to handle.
To read the time, open the table for that motion, find the row for the distance and the column for the case, and take the figure where they meet. Distances that fall between rows go to the next row or are interpolated, by the card's own rule. A weight above the table's light limit adds a factor and a constant to a move. That is all the look-up there is. The judgement is in choosing the case, and it is the part that takes training.
This page does not print the tables. They are copyrighted, and a table copied from a web page with no training behind it produces standards nobody can defend. For real analysis use the current data card from your MTM association.
A worked example: one hand, five motions
Illustrative example. An operator's right hand takes a bracket that lies alone on the bench 10 inches away and places it on a locating pin 10 inches from there. The TMU values are whole numbers chosen for teaching. They are close to the scale of the real ones and are not the MTM-1 card values.
- 1
Describe the motion in order
Reach to the bracket. Close the fingers on it. Carry it to the pin. Line it up and seat it. Let go. Five motions, one hand.
- 2
Measure the distances
Hand to bracket: 10 inches. Bracket to pin: 10 inches. Measure the path the hand travels, not the straight line on the drawing.
- 3
Choose the case for each motion
The bracket lies alone but not in a nest, so the reach is case B. It is easy to pick up: a simple pick-up grasp. The move ends at an exact place, the pin. The fit is loose, the hole is round and the part is easy to handle.
- 4
Write the codes
R10B, G1A, M10C, P1SE, RL1.
- 5
Read and add the times
With the illustrative values: 12 + 2 + 12 + 6 + 2 = 34 TMU.
- 6
Convert
34 x 0.036 = 1.224 seconds, or 34 x 0.0006 = 0.0204 minutes. This is normal time for one hand's part of the cycle, before allowances.
| Motion | Code | Why this case | TMU (illustrative) |
|---|---|---|---|
| Reach to bracket | R10B | Single object, position varies slightly | 12 |
| Grasp bracket | G1A | Easy pick-up of an object by itself | 2 |
| Move bracket to pin | M10C | To an exact location | 12 |
| Position on pin | P1SE | Loose fit, symmetrical, easy to handle | 6 |
| Release | RL1 | Open the fingers | 2 |
| Total | 34 TMU = 1.224 s |
Use the licensed MTM-1 data card for real values. They are printed to one decimal and differ from these.
Now change the method on paper. Put the brackets in a nest so the hand always finds one in the same place and the reach becomes the easiest case. Chamfer the pin so the position needs less care. Each change swaps one code for a cheaper one, and you can add up the saving before anyone cuts metal. That is what the system was built for: the M in MTM stands for methods.
MTM-2, MTM-UAS and MTM-MEK: bigger blocks for longer work
MTM-1 is precise and slow to apply. For a ten second cycle made a million times a year that effort pays. For a four minute assembly made in batches of fifty it does not. The later MTM systems combine the basic motions into bigger blocks, so one line of analysis covers what took three or five lines in MTM-1.
| System | Building blocks | Typical use |
|---|---|---|
| MTM-1 | Single basic motions: reach, grasp, move, position, release and the rest | Short cycles in mass production, where a fraction of a second is worth analysing |
| MTM-2 (International MTM Directorate, 1965) | Eleven categories. GET combines reach, grasp and release. PUT combines move and position. The others are get weight, put weight, regrasp, apply pressure, eye action, crank, step, foot motion, and bend and arise | Cycles of roughly a minute or more that still repeat often |
| MTM-UAS (German, Swiss and Austrian associations, mid-1970s) | Basic operations: get and place, place, handle tool, operate, motion cycles, body motions, visual control | Batch production. The MTM Association calls it the most used MTM system |
| MTM-MEK | Larger operations again, built for work that seldom repeats exactly | One-off and small-batch production |
MTM-3 (1970) simplified MTM-2 further and is no longer maintained. Newer systems from the MTM associations, such as MTM-HWD, describe the motion and the posture together.
The same pick and place at three levels of detail
MTM-1
5 lines
Reach, grasp, move, position, release: each coded on its own.
MTM-2
2 lines
GET combines reach, grasp and release. PUT combines move and position.
MTM-UAS
1 line
One basic operation, chosen by distance band, weight and how exact the placing is.
MTM-1 writes the pick and place as five lines: reach, grasp, move, position, release. MTM-2 writes it as two: GET, which combines reach, grasp and release, and PUT, which combines move and position. MTM-UAS writes it as one line: get and place.
The coarser systems also simplify the choices. MTM-2 has only three cases of GET and three of PUT, and it sorts distance into five bands in place of a row for every inch. A whole-body motion is a single figure: bend and arise is 61 TMU in MTM-2. Fewer choices means faster analysis and fewer places for two analysts to differ.
What you give up is resolution. A block that covers reach, grasp and release as one line cannot tell you which of the three to improve, and on a very short cycle the rounding inside each block is a visible share of the total. The rule of thumb is to match the system to the cycle: MTM-1 for the short, high-volume cycle, MTM-2 in the middle, MTM-UAS for batch work and MTM-MEK when each job is nearly a one-off. Never mix levels inside one standard without saying so on the sheet.
Training and certification
MTM is taught and licensed by the MTM associations: national bodies that work under an international umbrella and own the data. The routes differ a little by country, but the pattern is the same everywhere.
- A course for each system, taught by a licensed instructor, with an exam at the end. The MTM-1 course is the longest because it covers every motion and case. MTM-2 and MTM-UAS courses are shorter and usually assume the basics.
- A certificate that names the system and the level, often with an expiry date and a refresher to renew it. Many customers and works councils ask to see it before they accept a standard.
- Further levels for people who will build standard data, train others or audit analyses.
- Licensed data cards and software. The tables and the building blocks may not be copied into a home-made spreadsheet and shared.
If you are choosing, ask what your customers and your sister plants use. Some customers, particularly in automotive supply chains, ask for a specific MTM system by name. A certificate in the system your customer audits against is worth more than a deeper one in a system nobody around you reads.
Limits, and the people side
- MTM covers manual motion. Machine time, process time and waiting are added from other sources.
- It describes a trained operator who knows the job. A learner takes longer, and MTM does not say how much longer.
- It gives one clean cycle. Fumbles, sticking parts and variation between pieces are not in the total, so compare it with a few timed or filmed cycles once the job runs.
- The analysis is only as good as the method description. A wrong distance or a wrong case is easy to write and hard to spot later.
- MTM-1 on long cycles costs more analyst time than the standard is worth. Use a coarser system or a time study.
To the person at the station, an MTM standard can look like a number invented in an office. Show the analysis line by line at the workplace, let the operator try the method it describes, and correct the analysis where the real job differs. People accept a time they can check far more readily than one they are told. Where a works council or union agreement governs work measurement, it may say which system can be used and how a standard is disputed. This is general practice, not legal advice.
Related tools and next steps
- Standard time calculator: add rating and allowances to a normal time and get units per hour.
- Standard time: the allowance step that turns an MTM total into a standard.
- MOST and MODAPTS: two faster systems, one of them in TMU.
- Therbligs and motion economy: the motion vocabulary MTM grew out of, and the rules for a workplace that needs fewer motions.
- Workstation design: where to put parts and tools so the reach and move distances are short.
Once a job is running, the quickest check on an MTM standard is to film it. LeanSuite's Time and Motion Study times every element from one phone video and links each time to its video frame, so you can put the measured elements next to the analysed ones and see where they part.
Go deeper
This page is the short version. These guides cover each part in full.
- Standard Work in Manufacturing: A Complete GuideWriting down and holding the method that an MTM analysis describes.
- Standard Work Tools: Combination Sheet, Standardized Work Chart, Job BreakdownThe sheets that carry manual, walk and machine times to the station.
- The Three Elements of Standard Work: Takt Time, Work Sequence, Standard WIPHow element times are compared with takt and arranged into a work sequence.
- Yamazumi Chart: What It Is and How to Make One in 7 StepsStacking each operator's element times against takt to balance a line.
All our articles on this subject are in the standard work, sops and training topic.
Free templates and tools
- Time study sheetTime each element over 10 cycles and work out the average, lowest repeatable and standard time. Excel does the sums.
- Standard work combination tableOne operator's manual, machine, walk and wait time on a time chart against takt, with machine cycles and a process capacity sheet.
- Standard time calculatorObserved times, a rating and an allowance in; normal time, standard time, units per hour, pieces per shift and labour cost per unit out, with the working.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
- Line balancing calculatorLine efficiency, balance delay and the minimum number of stations from station times and takt.
Doing this in LeanSuite
Time and Motion Study
Times every element from one phone video of the process and reports cycle time, standard time, takt and units per hour, each linked to its video frame.
See Time and Motion StudyLine Balancing
Drop in a video of your line and get a Yamazumi chart, a takt comparison and rebalancing recommendations.
See Line Balancing
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about mTM (Methods-Time Measurement)
MTM is Methods-Time Measurement, a predetermined motion time system published in 1948 by Maynard, Stegemerten and Schwab. It sets the time for a manual job by breaking it into basic motions such as reach, grasp, move, position and release and adding a published time for each. The times are in TMU, where 1 TMU is 0.036 seconds. It is used to set standards, plan new jobs and improve methods.
Methods-Time Measurement is a way to time manual work from its method. The job is broken into basic motions, and each motion gets a time that was fixed in advance for that kind of motion under those conditions: the distance, the fit, the weight. The analyst describes the method, codes the motions, reads the times from the MTM data card and adds them. No stopwatch and no performance rating are involved.
A TMU is a time measurement unit, the unit used by MTM and MOST. One TMU is 0.00001 hour, 0.0006 minute or 0.036 second, so there are 100,000 TMU in an hour, about 1,666.7 in a minute and about 27.8 in a second. To convert TMU to seconds, multiply by 0.036. A motion sequence of 34 TMU takes 1.224 seconds.
Multiply TMU by 0.036 for seconds and by 0.0006 for minutes. For example, 380 TMU x 0.036 = 13.68 seconds, and 380 x 0.0006 = 0.228 minutes. Going the other way, multiply seconds by 27.8 or minutes by 1,666.7 to get TMU. Divide TMU by 100,000 for hours. The result is a normal time, so add allowances before you use it as a standard.
The size of the building block. MTM-1 uses single basic motions and suits short cycles in mass production. MTM-2, from 1965, combines them into eleven categories such as GET and PUT and suits cycles of about a minute or more. MTM-UAS, from the mid-1970s, uses basic operations such as get and place and handle tool and was built for batch production. Each step is faster to apply and less detailed.
Reach, move, turn, apply pressure, grasp, position, release, disengage and crank for the hands and arms, eye travel and eye focus for the eyes, and a set of body, leg and foot motions such as step, sidestep, bend, stoop, kneel, sit, stand and walk. Each has its own table on the MTM-1 data card, with the time set by conditions such as distance, case, fit and weight.
You should not. The tables are copyrighted by the MTM associations and licensed with their training, and the hard part of MTM is not the look-up but choosing the right case for each motion. An untrained analysis produces a precise-looking number that nobody can defend. Take the association's course for the system you need and use its current data card or software.
Related guides and tools
- Predetermined motion time systems: the whole family and when to use one
- MOST and MODAPTS: sequence models, index values and MODs
- Therbligs and the principles of motion economy
- Standard time: rating, allowances and both allowance formulas
- How to conduct a time study once the job is running
- Workstation design: shorter reaches by layout
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk
Or browse the topics, the full library and the lean glossary.
Rather see it on your own problem?
Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.