Linking a time study to the PFMEA, control plan and work instructions
Short answer
A time study already names every step of the job, in order, and shows where the work is unstable. That is the raw material for the process flow, the PFMEA, the control plan and the work instruction. Build them from one breakdown and they stay consistent.
Use the element breakdown from the time study as the single source. Each element becomes a step in the process flow and a process step in the PFMEA, where the failure modes and causes are rated. The controls that survive the PFMEA go into the control plan with a method, a sample size and a reaction plan. The key points go into the work instruction at the element they belong to. Elements with a wide spread in the timed cycles are a signal to look for causes there first. When any one of the four changes, check the other three.
Last reviewed:
One process, four documents
One element breakdown, four documents
Example numbersTime study element breakdown
- E1 Pick housing, place in fixture
- E2 Fit O-ring on cover
- E3 Grease the seal lip
- E4 Press seal into housing
- E5 Check seal depth with gauge
- E6 Fit cover, drive four screws
Process flow
In what order, and where are the checks?
Takes: Element order and names grouped into operations
Op 30: press shaft seal, then gauge check
PFMEA
How could each step go wrong?
Takes: Steps, work elements, film notes and the spread of times
Seal seated crooked: leak at the shaft
Control plan
How is each characteristic kept in control?
Takes: Where the check sits in the cycle and how long it takes
Depth gauge on every part, red bin if it fails
Work instruction
What does the operator do, and what must not go wrong?
Takes: Element names, order, time and key points
Seal must slide onto the guide by hand, else stop
A time study element list feeds four documents in order: the process flow, the PFMEA, the control plan and the work instruction. Each card says what the document asks, what it takes from the study, and the example entry for element 4, pressing the seal.
Most plants write four documents about the same job, and four different people write them. The process engineer draws the process flow. The quality engineer leads the PFMEA. A different quality engineer fills in the control plan. A supervisor or trainer writes the work instruction. Each is correct on the day it is signed, and then they drift apart: the PFMEA names a check that is not in the control plan, the control plan asks for a gauge the work instruction never mentions, and the work instruction describes a sequence nobody follows.
A time study cures most of this, because it is the one piece of work that looked at the real job, step by step, with a clock. Its element breakdown gives every step a name, a place in the order and a measured time. If all four documents start from that list, they use the same names, the same order and the same numbers. Where they disagree, you see it straight away.
This page is about the links, not the documents. For how to rate severity, occurrence and detection, read the FMEA guide. For the quality planning around launch, read APQP. For the work instruction and how it differs from standard work, read standard work vs SOP vs work instruction.
What each document takes from the study
| Document | The question it answers | What it takes from the time study |
|---|---|---|
| Process flow diagram | In what order do the operations happen, and where do the checks sit? | The sequence of work, and which elements belong together as one operation |
| PFMEA | How could each step go wrong, and what would that do? | The list of steps and what each is meant to achieve, the elements that vary most, the notes from the film (rework, reaching, hesitation) |
| Control plan | How do we keep each characteristic under control, and what happens if it is not? | Where in the cycle each check happens, how long the check takes, which operations are manual |
| Work instruction | What does the operator do, in what order, and what must they not get wrong? | The element names and order, the time each takes, the key points seen in the best cycles |
Notice what the study does not give. It does not rate severity, it does not choose a sample size and it does not decide what is a special characteristic. Those come from the product, the customer and the team. The study supplies the structure and the evidence they work from.
What the element breakdown hands over
The AIAG and VDA FMEA Handbook of 2019 builds a process FMEA in seven steps: planning and preparation, structure analysis, function analysis, failure analysis, risk analysis, optimization and results documentation. The first of the analysis steps asks the team to lay out the process as a structure of process steps and the work elements that make each one, such as the machine, the person and the material. The element breakdown is that structure, already measured.
| The time study has | The PFMEA needs | How to use it |
|---|---|---|
| A named, numbered element | A process step and its function | Copy the name. State the function as what the element must achieve, in a few words, for example "seal seated square and to depth". |
| Who or what does the element: operator, press, fixture | The work elements of the step | Take them from the sheet's resource column. Do not invent a different list. |
| The spread of the timed cycles | Evidence for causes and for the occurrence rating | A wide spread means the element is not being done the same way each time. Ask why, on the film. |
| Cycles marked abnormal, with a note | Failure modes that have actually happened | A note like "seal crooked, pressed again" is a failure mode and a cause, seen on the floor, not guessed. |
| Walk and reach before an element | Human factor causes | Long reaches, awkward parts and bins out of reach cause wrong parts and skipped steps. |
The spread is the part most teams miss. A time study usually reports the average, and the average hides the trouble. If six cycles of an element take 8 to 9 seconds and two take 14 and 15, the average of about 10 seconds describes none of them. The two slow cycles are something going wrong and being put right by the operator, which is exactly what the PFMEA is meant to find.
How to carry the study through the four documents
- 1
Freeze the element breakdown
Agree the element names, order and numbers with the operator and the supervisor. Give each element an ID. From here on every document uses these IDs.
- 2
Draw the process flow from it
Group elements into operations and give each operation a number and a name. Mark where parts are checked, moved, stored or waiting. Use the same operation numbers in all four documents.
- 3
Seed the PFMEA with the steps and the film
Each operation becomes a process step with its functions and work elements. Add every failure mode you saw on the film or in the abnormal cycle notes before the team brainstorms new ones. Then rate and act as in the FMEA guide.
- 4
Write the control plan from the controls the PFMEA keeps
Every prevention and detection control that the PFMEA relies on gets a row: the characteristic, the method, the size and frequency of the check, and the reaction plan. If the PFMEA relies on a control that has no row, the plan is incomplete.
- 5
Write the work instruction from the same elements
One instruction per operation, steps in the element order, a key point and its reason wherever the PFMEA says a mistake costs something, and the checks the control plan assigns to the operator. Add the time of each element so the operator can see the target.
- 6
Time it again and compare
After any control or method change, time the job again with the new sequence. The check you added takes time, and the cycle must still fit takt. Then update every document the change touched.
A worked row, carried through all four documents
This example is illustrative. Station 3 of a small gear pump line assembles the pump housing in six elements. A time study timed eight cycles, in seconds. Element 4, pressing the shaft seal into the housing, is the one we follow.
| Element | Cycles 1 to 8 | Mean | Range |
|---|---|---|---|
| 1. Pick housing, place in fixture | 6, 6, 7, 6, 6, 7, 6, 6 | 6.25 | 1 |
| 2. Fit O-ring on cover | 5, 5, 5, 6, 5, 5, 5, 5 | 5.13 | 1 |
| 3. Grease the seal lip | 4, 4, 4, 4, 5, 4, 4, 4 | 4.13 | 1 |
| 4. Press seal into housing | 9, 8, 14, 9, 8, 9, 15, 9 | 10.13 | 7 |
| 5. Check seal depth with go/no-go gauge | 5, 5, 5, 6, 5, 5, 5, 5 | 5.13 | 1 |
| 6. Fit cover, drive four screws | 18, 17, 18, 19, 18, 18, 17, 18 | 17.88 | 2 |
The six means add up to 48.6 s a cycle. Means are rounded to two decimal places; the sum is worked from the unrounded means.
Five elements have a range of 1 or 2 seconds. Element 4 has a range of 7. On the film, cycles 3 and 7 show the same thing: the seal started crooked in the bore, the operator pulled it back and pressed again. That is 2 of 8 cycles, so we cannot say how often it happens over a month, only that it happens and that the operator puts it right without telling anyone. The average, 10.1 s, would never have shown it.
Eight timed cycles of each element: the spread shows the trouble
Example numbersE1 Pick housing, place in fixtureMean 6.25 s, range 1 s
E2 Fit O-ring on coverMean 5.13 s, range 1 s
E3 Grease the seal lipMean 4.13 s, range 1 s
E4 Press seal into housingMean 10.13 s, range 7 s
E5 Check seal depth with gaugeMean 5.13 s, range 1 s
E6 Fit cover, drive four screwsMean 17.88 s, range 2 s
Dashed line: the mean. Yellow dots: cycles where the film shows a re-press.
A dot for each of eight timed cycles on a 0 to 20 second scale. Elements 1, 2, 3, 5 and 6 are tight, with a range of 1 or 2 seconds. Element 4 has a range of 7 seconds, with two cycles at 14 and 15 seconds, while its mean is 10.1 seconds.
In the process flow
Elements 3 to 5 become one operation, "Op 30: press shaft seal", with the depth check built in. The flow shows the gauge check after the press and before the cover goes on, so a bad seal is found before it is trapped under the cover.
In the PFMEA
| Field | Before | After |
|---|---|---|
| Process step and function | Op 30 press seal: seal seated square, flush to the stated depth | Same |
| Work elements | Press 3, operator, shaft seal, housing bore | Press 3 with guide sleeve and stop, operator, shaft seal, housing bore |
| Failure mode | Seal seated crooked or not to depth | Same |
| Effect | Leak at the shaft, returned pump | Same |
| Cause | Seal starts crooked because nothing guides it into the bore | Same, now guided |
| Prevention control | None | Guide sleeve on the press, hard stop at the depth |
| Detection control | Go/no-go depth gauge, element 5 | Same |
| Severity, occurrence, detection (illustrative) | 8, 5, 5 | 8, 2, 5 |
| Action priority | Look it up in the handbook table for 8, 5, 5 | Look it up for 8, 2, 5 |
The ratings are made up for the example. We do not reproduce the action priority tables here: they are in the AIAG and VDA handbook, and the team should read the result from there, not from a rule of thumb.
Look at what moved. The guide sleeve is a prevention control, so only the occurrence rating falls. Severity stays at 8, because a leaking pump is just as bad as before. Detection stays at 5, because the gauge is the same gauge.
In the control plan
| Column | Entry |
|---|---|
| Operation | 30, press shaft seal (same number as the flow and the PFMEA) |
| Machine and tool | Press 3, guide sleeve, depth stop |
| Product characteristic | Seal depth, to the drawing's tolerance |
| Process characteristic | Guide sleeve fitted, stop height set |
| Evaluation method | Go/no-go depth gauge |
| Size and frequency | Every part, by the operator, at element 5 |
| Reaction plan | Stop, put the part in the red bin, call the supervisor, check the stop height before restarting |
The columns follow the usual layout of the control plan forms. Use the form your customer asks for. Whether the stop height needs a periodic check, and how often, is a decision for the team.
In the work instruction
- Step 4, press the seal. Set the seal on the guide sleeve and press to the stop.
- Key point: the seal must slide onto the guide by hand. If it does not, stop and do not press.
- Reason: a crooked seal leaks at the customer.
- Step 5, check the depth. Use the go/no-go gauge on every part. If it does not pass, use the red bin and call the supervisor.
- Target time: step 4, 9 s. Step 5, 5 s.
The same step, Op 30, in all four documents
Example numbersProcess flow
Operation: 30, press shaft seal
Next: Gauge check, then fit cover
PFMEA
Failure mode: Seal crooked or not to depth
Effect: Leak at the shaft
Cause: Nothing guides the seal in
S, O, D: 8, 5, 5 then 8, 2, 5
Control plan
Characteristic: Seal depth
Method: Go/no-go gauge, every part
Reaction: Stop, red bin, call supervisor
Work instruction
Step: Set seal on the guide, press to the stop
Key point: Must slide on by hand, else stop
Time: 9 s
Operation 30, press shaft seal, written four ways. In the flow it is one operation followed by a gauge check. In the PFMEA the failure mode is a crooked seal with severity 8, occurrence 5 falling to 2 and detection 5. In the control plan the depth gauge checks every part. In the work instruction the key point is that the seal must slide onto the guide by hand.
Time it again
With the guide sleeve fitted, eight new cycles of element 4 were 9, 9, 10, 9, 9, 10, 9 and 9 seconds. The mean is 9.25 s and the range is 1. The mean fell by only 0.88 s, so cycle time went from 48.6 s to 47.75 s. The real gain is the spread: the 14 and 15 second cycles are gone, and the operator no longer has to hide a mistake. The work instruction now carries 9 s as the target, because that is what the new method takes.
Element 4 timed again after the guide sleeve
Example numbersBefore no guideMean 10.13 s, range 7 s
After guide sleeve and stopMean 9.25 s, range 1 s
Station cycle before48.63 s
Station cycle after47.75 s
Eight cycles of element 4 before and after the change. Before: range 7 seconds, mean 10.13. After: 9 or 10 seconds, range 1, mean 9.25. The cycle time of the station falls from 48.63 to 47.75 seconds.
When one changes, check the other three
| If this changes | Check this |
|---|---|
| The method or the element order (found in a new time study) | Process flow numbers, PFMEA steps, control plan row, work instruction steps and times |
| A PFMEA action adds a prevention or detection control | Control plan row, work instruction key point, and a new timing for the element |
| A customer complaint or a defect found in production | PFMEA failure mode and ratings, then control plan, then the work instruction |
| The control plan changes a check or its frequency | PFMEA detection control, and the operator's time if the check is manual |
| A new fixture, machine or material | All four, and a fresh time study of the affected elements |
IATF 16949 clause 8.5.1.1, as it is reported in published summaries, lists changes to the process, to the product and to the FMEA among the events that call for a control plan review. Read the wording in your own copy of the standard.
What a change in one document asks of the other three
| If this changes | Process flow | PFMEA | Control plan | Work instruction |
|---|---|---|---|---|
| New method or element order | Edit | Edit | Edit | Edit |
| PFMEA adds a control | Check | Edit | Edit | Edit |
| Customer complaint or defect | No | Edit | Edit | Check |
| Control plan changes a check | Check | Check | Edit | Check |
| New fixture, machine or material | Edit | Edit | Edit | Edit |
A table of five kinds of change against the four documents. Edit means the document almost always changes, Check means look and change it if needed, No means it is not normally affected. A new method, or a new fixture, machine or material, means editing all four.
One person should own the chain for a given line, even if several people write the pages. That person checks the four documents together each time one of them is revised, using the operation numbers as the thread. Two documents that disagree on a number are the first thing an auditor finds, and the first thing a new operator trips over.
Limits, and the people side
- A time study only sees what happens while it is running. Rare failures, such as a bad lot of seals, will not turn up in eight cycles. The PFMEA team still needs the quality history, the customer returns and the people who know the process.
- Do not treat a slow cycle as proof of a defect, or a clean cycle as proof of none. The spread is a pointer, not a measurement of risk.
- The customer's forms and rules win. Ford's published customer-specific requirements, for example, ask for the FMEAs to be aligned with the control plan and the work instructions. Check what each customer you supply requires. This page is general practice, not advice for your audit.
- Operators fear time studies, and they will see a study that finds the places where they correct a fault as an inspection of them. Say plainly that the study looks at the method, and that a long cycle caused by a fixture that does not guide the part is the fixture's fault. Show the operator the film, and put their fix, not just yours, on the work instruction.
- This page is about repeated work. For one-off or maintenance work, a plan and a checklist fit better than a cycle time.
Tools and templates
- Time study sheet: the element list and the timed cycles that feed everything here.
- PFMEA template: the failure chain, ratings and actions.
- Control plan template: one row per characteristic and control.
- Work instruction template: steps, key points and reasons at the station.
Go deeper
This page is the short version. These guides cover each part in full.
- FMEA in Manufacturing: Failure Mode and Effects Analysis GuideThe ratings, the ranking and the team method that the PFMEA step on this page relies on.
- Standard Work vs SOPs vs Work InstructionsWhere the work instruction sits among the three documents and when each one fits.
- Visual Work Instructions: Effective DocumentationHow to lay out the instruction so the key points are read, not skipped.
- Standard Work Tools: Combination Sheet, Chart and Job BreakdownThe job breakdown that the element list on this page starts from.
All our articles on this subject are in the standard work, sops and training topic.
Free templates and tools
- Time study sheetTime each element over 10 cycles and work out the average, lowest repeatable and standard time. Excel does the sums.
- PFMEA template (process FMEA)Failure modes, effects and causes rated for severity, occurrence and detection, with RPN before and after action.
- Control plan templateWhat is checked at each step, against which limits, how, how often, and what to do when a result is out.
- Work instruction templateA one-page work instruction with key points and step times, and an Excel training record that flags re-checks.
Doing this in LeanSuite
Time and Motion Study
Film the station and the AI times every element on a timeline that links to the video, split into value-added, necessary and waste.
See Time and Motion StudyStandardized work software
Working out the standard with Vision AI, keeping it current with SOPs and work instructions, and training and auditing it.
See Standardized work softwareDigital work instructions
Puts the current work instruction in front of the operator at the station.
See Digital work instructions
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about time study, PFMEA, control plan and work instructions
PFMEA stands for process failure mode and effects analysis. It lists each step of a manufacturing process, how the step could fail to make the part to the drawing, what each failure would do and what causes it. The team rates the risks, adds controls and acts on the highest ones before production starts, and again after any process change.
The control plan turns the controls the PFMEA relies on into rows a person can follow. Each prevention or detection control gets a characteristic, a method, a sample size and frequency, and a reaction plan. Both documents use the same operation numbers, so a reader can go from a risk to its control and back.
A control plan says what is checked, how, how often and what to do if it fails. It is written for quality and audit. A work instruction says how the operator does each step, with key points and the reason for each. The checks assigned to the operator in the control plan should appear as steps in the work instruction.
Yes. The element breakdown gives the PFMEA its process steps in the order they happen, and the film shows failure modes that actually occur, such as a part pressed twice. A wide spread in an element's timed cycles points at a cause worth looking at. It does not replace the team's knowledge or the quality history, and it does not rate severity.
There is no single rule, and the customer's requirements come first. In many plants the process or quality engineer leads the PFMEA and the control plan, and a supervisor or trainer writes the work instruction. What matters is that one named person checks the three together, and the operators who do the job take part in writing them.
Update them when the process, the product, the measurement method or the supply source changes, when a defect reaches a customer, and when a new time study finds a different method. Published summaries of IATF 16949 list shipped nonconforming product and changes to the FMEA among the triggers for a control plan review. Update the work instruction in the same pass.
Related guides and tools
- FMEA: the types, the ratings and a worked PFMEA example
- APQP: the quality planning that sits around these four documents
- Flowchart: the symbols and layout for the process flow
- Standard work: the three elements the work instruction supports
- How to break a job into elements: where the list starts
- From time study to standard work: the same study, written as standard work
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk
Or browse the topics, the full library and the lean glossary.
Rather see it on your own problem?
Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.