Skip to content
LeanSuite

Linking a time study to the PFMEA, control plan and work instructions

Short answer

A time study already names every step of the job, in order, and shows where the work is unstable. That is the raw material for the process flow, the PFMEA, the control plan and the work instruction. Build them from one breakdown and they stay consistent.

Use the element breakdown from the time study as the single source. Each element becomes a step in the process flow and a process step in the PFMEA, where the failure modes and causes are rated. The controls that survive the PFMEA go into the control plan with a method, a sample size and a reaction plan. The key points go into the work instruction at the element they belong to. Elements with a wide spread in the timed cycles are a signal to look for causes there first. When any one of the four changes, check the other three.

Last reviewed:

One process, four documents

One element breakdown, four documents

Example numbers

Time study element breakdown

  1. E1 Pick housing, place in fixture
  2. E2 Fit O-ring on cover
  3. E3 Grease the seal lip
  4. E4 Press seal into housing
  5. E5 Check seal depth with gauge
  6. E6 Fit cover, drive four screws

Process flow

In what order, and where are the checks?

Takes: Element order and names grouped into operations

Op 30: press shaft seal, then gauge check

PFMEA

How could each step go wrong?

Takes: Steps, work elements, film notes and the spread of times

Seal seated crooked: leak at the shaft

Control plan

How is each characteristic kept in control?

Takes: Where the check sits in the cycle and how long it takes

Depth gauge on every part, red bin if it fails

Work instruction

What does the operator do, and what must not go wrong?

Takes: Element names, order, time and key points

Seal must slide onto the guide by hand, else stop

A time study element list feeds four documents in order: the process flow, the PFMEA, the control plan and the work instruction. Each card says what the document asks, what it takes from the study, and the example entry for element 4, pressing the seal.

All four start from the same element names and the same operation numbers. Where they disagree, you see it.

Most plants write four documents about the same job, and four different people write them. The process engineer draws the process flow. The quality engineer leads the PFMEA. A different quality engineer fills in the control plan. A supervisor or trainer writes the work instruction. Each is correct on the day it is signed, and then they drift apart: the PFMEA names a check that is not in the control plan, the control plan asks for a gauge the work instruction never mentions, and the work instruction describes a sequence nobody follows.

A time study cures most of this, because it is the one piece of work that looked at the real job, step by step, with a clock. Its element breakdown gives every step a name, a place in the order and a measured time. If all four documents start from that list, they use the same names, the same order and the same numbers. Where they disagree, you see it straight away.

This page is about the links, not the documents. For how to rate severity, occurrence and detection, read the FMEA guide. For the quality planning around launch, read APQP. For the work instruction and how it differs from standard work, read standard work vs SOP vs work instruction.

What each document takes from the study

The four documents and what the time study gives each
DocumentThe question it answersWhat it takes from the time study
Process flow diagramIn what order do the operations happen, and where do the checks sit?The sequence of work, and which elements belong together as one operation
PFMEAHow could each step go wrong, and what would that do?The list of steps and what each is meant to achieve, the elements that vary most, the notes from the film (rework, reaching, hesitation)
Control planHow do we keep each characteristic under control, and what happens if it is not?Where in the cycle each check happens, how long the check takes, which operations are manual
Work instructionWhat does the operator do, in what order, and what must they not get wrong?The element names and order, the time each takes, the key points seen in the best cycles

Notice what the study does not give. It does not rate severity, it does not choose a sample size and it does not decide what is a special characteristic. Those come from the product, the customer and the team. The study supplies the structure and the evidence they work from.

What the element breakdown hands over

The AIAG and VDA FMEA Handbook of 2019 builds a process FMEA in seven steps: planning and preparation, structure analysis, function analysis, failure analysis, risk analysis, optimization and results documentation. The first of the analysis steps asks the team to lay out the process as a structure of process steps and the work elements that make each one, such as the machine, the person and the material. The element breakdown is that structure, already measured.

From the study sheet to the PFMEA structure
The time study hasThe PFMEA needsHow to use it
A named, numbered elementA process step and its functionCopy the name. State the function as what the element must achieve, in a few words, for example "seal seated square and to depth".
Who or what does the element: operator, press, fixtureThe work elements of the stepTake them from the sheet's resource column. Do not invent a different list.
The spread of the timed cyclesEvidence for causes and for the occurrence ratingA wide spread means the element is not being done the same way each time. Ask why, on the film.
Cycles marked abnormal, with a noteFailure modes that have actually happenedA note like "seal crooked, pressed again" is a failure mode and a cause, seen on the floor, not guessed.
Walk and reach before an elementHuman factor causesLong reaches, awkward parts and bins out of reach cause wrong parts and skipped steps.

The spread is the part most teams miss. A time study usually reports the average, and the average hides the trouble. If six cycles of an element take 8 to 9 seconds and two take 14 and 15, the average of about 10 seconds describes none of them. The two slow cycles are something going wrong and being put right by the operator, which is exactly what the PFMEA is meant to find.

How to carry the study through the four documents

  1. 1

    Freeze the element breakdown

    Agree the element names, order and numbers with the operator and the supervisor. Give each element an ID. From here on every document uses these IDs.

  2. 2

    Draw the process flow from it

    Group elements into operations and give each operation a number and a name. Mark where parts are checked, moved, stored or waiting. Use the same operation numbers in all four documents.

  3. 3

    Seed the PFMEA with the steps and the film

    Each operation becomes a process step with its functions and work elements. Add every failure mode you saw on the film or in the abnormal cycle notes before the team brainstorms new ones. Then rate and act as in the FMEA guide.

  4. 4

    Write the control plan from the controls the PFMEA keeps

    Every prevention and detection control that the PFMEA relies on gets a row: the characteristic, the method, the size and frequency of the check, and the reaction plan. If the PFMEA relies on a control that has no row, the plan is incomplete.

  5. 5

    Write the work instruction from the same elements

    One instruction per operation, steps in the element order, a key point and its reason wherever the PFMEA says a mistake costs something, and the checks the control plan assigns to the operator. Add the time of each element so the operator can see the target.

  6. 6

    Time it again and compare

    After any control or method change, time the job again with the new sequence. The check you added takes time, and the cycle must still fit takt. Then update every document the change touched.

A worked row, carried through all four documents

This example is illustrative. Station 3 of a small gear pump line assembles the pump housing in six elements. A time study timed eight cycles, in seconds. Element 4, pressing the shaft seal into the housing, is the one we follow.

Illustrative: eight timed cycles at station 3, in seconds
ElementCycles 1 to 8MeanRange
1. Pick housing, place in fixture6, 6, 7, 6, 6, 7, 6, 66.251
2. Fit O-ring on cover5, 5, 5, 6, 5, 5, 5, 55.131
3. Grease the seal lip4, 4, 4, 4, 5, 4, 4, 44.131
4. Press seal into housing9, 8, 14, 9, 8, 9, 15, 910.137
5. Check seal depth with go/no-go gauge5, 5, 5, 6, 5, 5, 5, 55.131
6. Fit cover, drive four screws18, 17, 18, 19, 18, 18, 17, 1817.882

The six means add up to 48.6 s a cycle. Means are rounded to two decimal places; the sum is worked from the unrounded means.

Five elements have a range of 1 or 2 seconds. Element 4 has a range of 7. On the film, cycles 3 and 7 show the same thing: the seal started crooked in the bore, the operator pulled it back and pressed again. That is 2 of 8 cycles, so we cannot say how often it happens over a month, only that it happens and that the operator puts it right without telling anyone. The average, 10.1 s, would never have shown it.

Eight timed cycles of each element: the spread shows the trouble

Example numbers

E1 Pick housing, place in fixtureMean 6.25 s, range 1 s

E2 Fit O-ring on coverMean 5.13 s, range 1 s

E3 Grease the seal lipMean 4.13 s, range 1 s

E4 Press seal into housingMean 10.13 s, range 7 s

E5 Check seal depth with gaugeMean 5.13 s, range 1 s

E6 Fit cover, drive four screwsMean 17.88 s, range 2 s

Dashed line: the mean. Yellow dots: cycles where the film shows a re-press.

A dot for each of eight timed cycles on a 0 to 20 second scale. Elements 1, 2, 3, 5 and 6 are tight, with a range of 1 or 2 seconds. Element 4 has a range of 7 seconds, with two cycles at 14 and 15 seconds, while its mean is 10.1 seconds.

Five elements are tight. Element 4 is not, and its average of 10.1 s describes none of its cycles. The two slow dots are where the seal went in crooked and was pressed again.

In the process flow

Elements 3 to 5 become one operation, "Op 30: press shaft seal", with the depth check built in. The flow shows the gauge check after the press and before the cover goes on, so a bad seal is found before it is trapped under the cover.

In the PFMEA

Illustrative PFMEA line for Op 30, before and after the change
FieldBeforeAfter
Process step and functionOp 30 press seal: seal seated square, flush to the stated depthSame
Work elementsPress 3, operator, shaft seal, housing borePress 3 with guide sleeve and stop, operator, shaft seal, housing bore
Failure modeSeal seated crooked or not to depthSame
EffectLeak at the shaft, returned pumpSame
CauseSeal starts crooked because nothing guides it into the boreSame, now guided
Prevention controlNoneGuide sleeve on the press, hard stop at the depth
Detection controlGo/no-go depth gauge, element 5Same
Severity, occurrence, detection (illustrative)8, 5, 58, 2, 5
Action priorityLook it up in the handbook table for 8, 5, 5Look it up for 8, 2, 5

The ratings are made up for the example. We do not reproduce the action priority tables here: they are in the AIAG and VDA handbook, and the team should read the result from there, not from a rule of thumb.

Look at what moved. The guide sleeve is a prevention control, so only the occurrence rating falls. Severity stays at 8, because a leaking pump is just as bad as before. Detection stays at 5, because the gauge is the same gauge.

In the control plan

Illustrative control plan row for Op 30
ColumnEntry
Operation30, press shaft seal (same number as the flow and the PFMEA)
Machine and toolPress 3, guide sleeve, depth stop
Product characteristicSeal depth, to the drawing's tolerance
Process characteristicGuide sleeve fitted, stop height set
Evaluation methodGo/no-go depth gauge
Size and frequencyEvery part, by the operator, at element 5
Reaction planStop, put the part in the red bin, call the supervisor, check the stop height before restarting

The columns follow the usual layout of the control plan forms. Use the form your customer asks for. Whether the stop height needs a periodic check, and how often, is a decision for the team.

In the work instruction

  • Step 4, press the seal. Set the seal on the guide sleeve and press to the stop.
  • Key point: the seal must slide onto the guide by hand. If it does not, stop and do not press.
  • Reason: a crooked seal leaks at the customer.
  • Step 5, check the depth. Use the go/no-go gauge on every part. If it does not pass, use the red bin and call the supervisor.
  • Target time: step 4, 9 s. Step 5, 5 s.

The same step, Op 30, in all four documents

Example numbers

Process flow

Operation: 30, press shaft seal

Next: Gauge check, then fit cover

PFMEA

Failure mode: Seal crooked or not to depth

Effect: Leak at the shaft

Cause: Nothing guides the seal in

S, O, D: 8, 5, 5 then 8, 2, 5

Control plan

Characteristic: Seal depth

Method: Go/no-go gauge, every part

Reaction: Stop, red bin, call supervisor

Work instruction

Step: Set seal on the guide, press to the stop

Key point: Must slide on by hand, else stop

Time: 9 s

Operation 30, press shaft seal, written four ways. In the flow it is one operation followed by a gauge check. In the PFMEA the failure mode is a crooked seal with severity 8, occurrence 5 falling to 2 and detection 5. In the control plan the depth gauge checks every part. In the work instruction the key point is that the seal must slide onto the guide by hand.

Each document answers its own question, and every entry traces to element 4. The operation number is the thread.

Time it again

With the guide sleeve fitted, eight new cycles of element 4 were 9, 9, 10, 9, 9, 10, 9 and 9 seconds. The mean is 9.25 s and the range is 1. The mean fell by only 0.88 s, so cycle time went from 48.6 s to 47.75 s. The real gain is the spread: the 14 and 15 second cycles are gone, and the operator no longer has to hide a mistake. The work instruction now carries 9 s as the target, because that is what the new method takes.

Element 4 timed again after the guide sleeve

Example numbers

Before no guideMean 10.13 s, range 7 s

After guide sleeve and stopMean 9.25 s, range 1 s

Station cycle before48.63 s

Station cycle after47.75 s

Eight cycles of element 4 before and after the change. Before: range 7 seconds, mean 10.13. After: 9 or 10 seconds, range 1, mean 9.25. The cycle time of the station falls from 48.63 to 47.75 seconds.

The mean moves by under a second. The range falls from 7 s to 1 s, and the station cycle goes from 48.63 s to 47.75 s.

When one changes, check the other three

What a change in one document asks of the others
If this changesCheck this
The method or the element order (found in a new time study)Process flow numbers, PFMEA steps, control plan row, work instruction steps and times
A PFMEA action adds a prevention or detection controlControl plan row, work instruction key point, and a new timing for the element
A customer complaint or a defect found in productionPFMEA failure mode and ratings, then control plan, then the work instruction
The control plan changes a check or its frequencyPFMEA detection control, and the operator's time if the check is manual
A new fixture, machine or materialAll four, and a fresh time study of the affected elements

IATF 16949 clause 8.5.1.1, as it is reported in published summaries, lists changes to the process, to the product and to the FMEA among the events that call for a control plan review. Read the wording in your own copy of the standard.

What a change in one document asks of the other three

If this changesProcess flowPFMEAControl planWork instruction
New method or element orderEditEditEditEdit
PFMEA adds a controlCheckEditEditEdit
Customer complaint or defectNoEditEditCheck
Control plan changes a checkCheckCheckEditCheck
New fixture, machine or materialEditEditEditEdit

A table of five kinds of change against the four documents. Edit means the document almost always changes, Check means look and change it if needed, No means it is not normally affected. A new method, or a new fixture, machine or material, means editing all four.

Edit means the document changes. Check means look, and change it if needed. A change to the method or the equipment touches all four, and the affected elements need a fresh timing.

One person should own the chain for a given line, even if several people write the pages. That person checks the four documents together each time one of them is revised, using the operation numbers as the thread. Two documents that disagree on a number are the first thing an auditor finds, and the first thing a new operator trips over.

Limits, and the people side

  • A time study only sees what happens while it is running. Rare failures, such as a bad lot of seals, will not turn up in eight cycles. The PFMEA team still needs the quality history, the customer returns and the people who know the process.
  • Do not treat a slow cycle as proof of a defect, or a clean cycle as proof of none. The spread is a pointer, not a measurement of risk.
  • The customer's forms and rules win. Ford's published customer-specific requirements, for example, ask for the FMEAs to be aligned with the control plan and the work instructions. Check what each customer you supply requires. This page is general practice, not advice for your audit.
  • Operators fear time studies, and they will see a study that finds the places where they correct a fault as an inspection of them. Say plainly that the study looks at the method, and that a long cycle caused by a fixture that does not guide the part is the fixture's fault. Show the operator the film, and put their fix, not just yours, on the work instruction.
  • This page is about repeated work. For one-off or maintenance work, a plan and a checklist fit better than a cycle time.

Tools and templates

FAQ

Questions about time study, PFMEA, control plan and work instructions

  1. PFMEA stands for process failure mode and effects analysis. It lists each step of a manufacturing process, how the step could fail to make the part to the drawing, what each failure would do and what causes it. The team rates the risks, adds controls and acts on the highest ones before production starts, and again after any process change.

  2. The control plan turns the controls the PFMEA relies on into rows a person can follow. Each prevention or detection control gets a characteristic, a method, a sample size and frequency, and a reaction plan. Both documents use the same operation numbers, so a reader can go from a risk to its control and back.

  3. A control plan says what is checked, how, how often and what to do if it fails. It is written for quality and audit. A work instruction says how the operator does each step, with key points and the reason for each. The checks assigned to the operator in the control plan should appear as steps in the work instruction.

  4. Yes. The element breakdown gives the PFMEA its process steps in the order they happen, and the film shows failure modes that actually occur, such as a part pressed twice. A wide spread in an element's timed cycles points at a cause worth looking at. It does not replace the team's knowledge or the quality history, and it does not rate severity.

  5. There is no single rule, and the customer's requirements come first. In many plants the process or quality engineer leads the PFMEA and the control plan, and a supervisor or trainer writes the work instruction. What matters is that one named person checks the three together, and the operators who do the job take part in writing them.

  6. Update them when the process, the product, the measurement method or the supply source changes, when a defect reaches a customer, and when a new time study finds a different method. Published summaries of IATF 16949 list shipped nonconforming product and changes to the FMEA among the triggers for a control plan review. Update the work instruction in the same pass.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.