Time study in automotive assembly: takt, mixed models and the moving line

Short answer

On an automotive assembly line the time study answers one question: does the work at this station fit inside takt, for every variant, with the operator walking a moving line? Time each variant, compare the weighted average and the heaviest one with takt, and check the sequence.

An assembly line runs to takt, the time between one vehicle and the next, so a station is not measured by how many pieces it makes. It is measured by whether its work content fits inside takt. On a mixed-model line the work content changes from car to car, so you time each variant, weight the times by the build mix and check two things: the weighted average must sit under takt, and the heaviest variant must be absorbed by the lighter cars around it before the operator drifts out of the station. Planning uses a predetermined time system on the drawing; the running line is checked with video.

Last reviewed:

What makes assembly different

In most plants a time study sets a standard, and the operator's output is compared with it. On a paced assembly line that comparison means little. The line moves at one speed, every station gets the same takt time, and an operator cannot make more than the line brings. The study is there to design the station: how much work it can hold, for which variants, and where the operator stands while doing it.

Three things follow from the moving line, and each one changes how you study the job.

  • Time is distance. If the line moves at 6 metres a minute, a job of 47 seconds carries the operator 4.7 metres downstream. The work has to finish inside the station, and the walk back to the next car is part of the cycle.
  • The work content changes with the car. A base trim and a premium trim come down the same line, and the premium may hold 20 seconds more work. One time is not enough. You need one per variant, and the build mix.
  • There is no buffer inside the cycle. A station that runs over cannot catch up by working faster later in the hour. It drifts into the next station, pulls the cord, or lets a defect through. So the heaviest variant matters as much as the average.

This guide covers final assembly and the paced sub-assembly lines that feed it. Body, paint and powertrain machining are machine-paced and are studied differently: see time study in CNC machining for the machining side and time study in metal fabrication and welding for weld cells.

What gets timed on an assembly line

A station cycle is short, usually well under two minutes, and made of the same few kinds of element. Split them this way, because each kind is fixed by something different.

The element types in an assembly station cycle and what fixes each one
Element typeExamplesWhat fixes the timeHow to shorten it
GetWalk to the rack, pick the part, pick the toolWhere the part and the tool sit relative to the carLine-side presentation: part at the point of use, in reach, in the order of build
PlacePosition the panel, seat clips, route a harnessThe part design and how blind the fit isLocating features, fewer clips, a fixture or an assist
FastenDrive screws, torque bolts, press a connectorThe tool cycle and the number of fastenersFewer fasteners, multi-spindle tools, a tool on a balancer
ConfirmRead the torque light, scan a label, push-pull-push on a connectorThe quality planError proofing that confirms without an operator action
Walk backReturn upstream to the next carLine speed and how far the job carried the operatorLess work content, or work done riding with the car
Option workExtra connector, extra screws, a different partThe variantMove it to a sub-assembly, or sequence the heavy cars apart

Fasten and confirm elements are partly paced by the tool. Take the tool cycle from the tool controller and do not rate it.

The general method for splitting a job and timing it is in how to conduct a time study. What is specific to assembly is the last two rows. A stopwatch study of a bench job has no walk back and no option work, and those two are where most assembly stations go wrong.

The right method for each phase

An assembly station is studied several times in its life, and the best method changes each time, because what exists to be observed changes.

Which work measurement method fits each phase of an assembly line's life
PhaseWhat existsMethodWhat you get
Planning, before the line is builtDrawings, a process sheet, maybe a digital modelA predetermined time system such as MTM-UAS or MOSTPlanned times per variant, good enough to balance the line and count operators
Pre-series buildsReal parts and tools, slow and irregular cyclesVideo of each build, timed element by elementA check of the planned times, and the fit and reach problems the model missed
Launch and ramp-upThe real line, operators still learningVideo time study, repeated weeklyHow fast actual times approach the plan, station by station
Running productionA stable line and a changing mixVideo time study on change, with tool and line dataUpdated variant times after each engineering or mix change
Off-line workRepair bays, logistics, team leadersWork samplingWhere the time of the people who do not work to takt goes

One station, five studies over its life

  1. Phase 1

    Planning

    Drawings, a process sheet

    Predetermined time system

    Planned times per variant

  2. Phase 2

    Pre-series

    Real parts, slow cycles

    Video, element by element

    Plan checked, fit problems found

  3. Phase 3

    Launch

    The line, operators learning

    Video, repeated weekly

    Actual against plan, by station

  4. Phase 4

    Running

    Stable line, changing mix

    Video on every change

    Variant times kept current

  5. Alongside

    Off-line work

    Repair, logistics, team leaders

    Work sampling

    Where unpaced time goes

Five phases of an assembly line and the method that fits each: Planning, Predetermined time system; Pre-series, Video, element by element; Launch, Video, repeated weekly; Running, Video on every change; Off-line work, Work sampling.

The method changes because what exists to observe changes. Plan with a predetermined system, check with video, and keep checking.

Planning comes first because the line has to be balanced before it exists. A predetermined motion time system builds a time from the motions on the process sheet, with no operator to observe and no pace rating. MTM-UAS is one such system with a long record in car plants, and it is often paired with an ergonomic worksheet so that a station is checked for time and for physical load in one pass.

Once the line runs, a planned time is a claim to be checked. Video is the practical way on a moving line. A stopwatch observer has to walk with the car, in the operator's way, for a cycle that is over in a minute. A fixed camera sees every car that passes, and the footage settles the argument about what the operator does on the premium trim. The guide to time study from video covers camera position and analysis.

Work sampling is the wrong tool for a paced station, because the answer is already known: the operator is at the car. It is the right tool for everyone around the line who is not paced.

What IATF 16949 asks for, and what it does not

Suppliers to the car industry work under IATF 16949, and people often ask whether it requires time studies. It does not name any work measurement method. What it requires is the thing a time study feeds.

  • Clause 8.5.1.2 is titled standardised work: operator instructions and visual standards. It requires standardised work documents that are communicated to and understood by the people doing the work, legible, in a language those people understand and accessible at the work area, and it asks for operator safety rules to be included.
  • Clause 8.5.1.3 covers verification of job set-ups, which is where a changeover study ends up.
  • Customer-specific requirements often go further than the standard. Several car makers publish their own on top of it. Read yours: that is where a required format or a required capacity check will be, if there is one.

So the audit question is not whether you ran a time study. It is whether the standardised work at the station matches what the operator does, and whether it is kept current when the job changes. A time study is how the times on that sheet were set, and a dated study with its footage is good evidence that they were. The guide to standard work covers the documents.

This is a plain reading of the standard for orientation, not audit advice. Check the current text and your customers' requirements.

A worked example: a door trim station

Illustrative example. A trim line builds 450 vehicles in a shift with 450 minutes of running time. One station fits the front door trim panel. The panel comes in three variants: base, mid with a door speaker, and premium with the speaker, an ambient light strip and an armrest fixed by two more screws. The build mix is 60, 30 and 10 percent.

  1. 1

    Work out takt and the line speed

    Takt is running time divided by demand: 27,000 seconds over 450 vehicles is 60 seconds. With a vehicle pitch of 6 metres the line moves 6 metres every 60 seconds, which is 0.1 metres a second. Every second of work is 10 centimetres of floor.

  2. 2

    Film each variant and split the job into elements

    Film enough cars to catch at least ten cycles of the rarest variant. Split the cycle at clear break points: hand touches part, tool leaves the last screw, foot leaves the car.

  3. 3

    Time the base job and rate the manual elements

    Average each element over the cycles, rate the manual ones against normal pace, and leave tool-paced time as it is. The sum is the normal time for the base variant.

  4. 4

    Time the option work as its own elements

    Do not time the premium job as one long cycle. Time only what it adds to the base. Then each variant is the base plus its options, and a new variant next year is a sum, not a new study.

  5. 5

    Add allowances and compare each variant with takt

    Apply your plant's allowance for personal needs, fatigue and delays to get the standard time per variant. Then weight the variants by the mix.

  6. 6

    Check the sequence

    Walk a real build sequence through the station and track how far the operator drifts. Set a rule for how heavy cars may follow each other.

The base job

Illustrative: the base door trim job, element by element (seconds)
ElementObservedRatingNormal time
Pick the trim panel from the rack5.51005.5
Position the panel and seat eight clips10.011011.0
Connect the window switch5.01005.0
Drive four screws with the DC tool12.0Tool-paced12.0
Fit two screw covers4.01054.2
Read the torque result on the display1.51001.5
Walk back to the next car3.81003.8
Total41.843.0

Normal time is observed time x rating / 100. The rating scale and the allowance below are conventions: use the ones your plant has agreed.

The base door trim job against takt

Example numbers
  • Pick the panel5.5 s (5.5 x 100%)
  • Position, seat eight clips11.0 s (10.0 x 110%)
  • Connect the window switch5.0 s (5.0 x 100%)
  • Drive four screws (tool)12.0 s (tool)
  • Fit two screw covers4.2 s (4.0 x 105%)
  • Read the torque result1.5 s (1.5 x 100%)
  • Walk back to the next car3.8 s (3.8 x 100%)

Observed total 41.8 s, normal total 43.0 s.

The base door trim job has 7 elements and 43.0 normal seconds of work against a 60 second takt. The walk back is 3.8 seconds. The four screws are tool-paced and not rated.

43.0 normal seconds of a 60 second takt. The walk back is part of the cycle, and the screw time (hatched) comes from the tool and is not rated.

The three variants against takt

Illustrative: standard time per variant with a 10 percent allowance, against a 60 second takt
VariantMixOption work addedNormal timeStandard timeAgainst takt
Base60%None43.0 s47.3 s12.7 s under
Mid30%Speaker connector 4.0 s, harness clip 4.0 s51.0 s56.1 s3.9 s under
Premium10%Mid options, light strip 7.0 s, two armrest screws 6.0 s64.0 s70.4 s10.4 s over
Weighted average100%52.25 s87.1% of takt

Weighted average = 0.60 x 47.3 + 0.30 x 56.1 + 0.10 x 70.4 = 52.25 seconds. The 10 percent allowance is illustrative.

Standard time per variant against takt

Example numbers

Base (60% of cars)

Mid (30% of cars)

Premium (10% of cars)

Weighted average (0.6 x 47.3 + 0.3 x 56.1 + 0.1 x 70.4)

52.25 s

Standard times with a 10 percent allowance: base 47.3 seconds, mid 56.1, premium 70.4, against a takt of 60 seconds. The premium car runs 10.4 seconds over takt. The weighted average is 52.25 seconds, 87.1% of takt. The operator can drift 15 seconds into the next station.

The weighted average sits at 87.1% of takt, so the station looks fine. Only the premium car goes over, by 10.4 seconds, and that is inside the 15 second limit as long as it arrives alone.

The station passes the first test: on average it is loaded to 87 percent of takt. It fails a naive second test, because the premium car needs 70.4 seconds and takt is 60. Whether that matters depends on what comes before and after the premium car, which is the next section.

Mixed-model lines: drift and the sequence rule

On a moving line, running over takt does not stop anything at first. The operator finishes the premium car 10.4 seconds late, which is 1.04 metres further downstream than the station boundary. The next car is already 10.4 seconds into the station when the operator gets back to it. That lateness is called drift.

A light car pays the drift back. The base car needs 47.3 seconds, so it gives back 12.7 seconds, and the operator is on time again one car later. Two rules decide whether a station survives its heavy variant.

  • There is a limit to drift. In this example the operator can work 1.5 metres, which is 15 seconds, into the next station before getting in that operator's way or running out of tool reach. Past the limit the line stops or the car leaves unfinished.
  • Drift adds up only when heavy cars come together. One premium car causes 10.4 seconds of drift and is recovered. Two in a row cause 20.8 seconds, which is past the limit.
Illustrative: operator drift over two ten-car sequences at the door trim station (seconds late at the end of each car)
Car12345678910
Planned mix (one premium in ten)BMBPBMBBMB
Drift00010.4000000
Bad day (three premium, two together)BMPPBMBPBB
Drift0010.420.88.14.2010.400

B is base, M is mid, P is premium. Drift after a car = the drift before it + its standard time minus takt, and never less than zero. The limit at this station is 15 seconds.

Drift at the door trim station, two sequences

Example numbers

Planned mix, one premium in ten (peak 10.4 s)

Bad day, three premium, two together (peak 20.8 s, over the limit)

Dashed line: the 15 second limit at this station. Numbers are seconds late at the end of each car.

Seconds the operator is late at the end of each of ten cars. Planned mix, one premium car: peak 10.4 seconds, recovered. Bad day, three premium cars with two together: peak 20.8 seconds on car 4, over the 15 second limit, and the station takes until car 7 to recover.

B is base, M is mid, P is premium. One premium car is absorbed by the light cars after it. Two in a row push the operator past the limit, and it takes three cars to recover.

The second sequence breaks the station at car 4, and it takes until car 7 to recover. The fix is a sequence rule, agreed with production control: never two premium cars in a row at this station, or at least one base car after each premium. Car plants set rules like this for every option that loads a station heavily, and smoothing the mix this way is part of heijunka.

When the rule cannot be kept, because the premium share has grown, the options are the usual ones: move the option work to a sub-assembly off the line, split it with the next station, add a floating operator who helps on heavy cars, or lengthen the station.

Balancing the line on two numbers per station

A single-model line is balanced on one number per station. A mixed-model line needs two: the weighted average, which decides how many operators the line needs, and the heaviest variant, which decides whether each station survives its worst car.

Illustrative: five trim stations on a 60 second takt (standard seconds)
StationWeighted averageHeaviest variantVerdict
1. Door trim52.2570.4Average fine. Heaviest needs the sequence rule.
2. Seal and weatherstrip55.058.0Fine on both.
3. Mirror and harness49.566.0Room on average. Heaviest drifts 6.0 s and recovers.
4. Speaker and window regulator57.261.5Tight. 95% loaded with little recovery.
5. Door check and adjust46.046.0No variants. 14.0 s spare.
Line259.954.33 operators of work for 5 operators: 86.7% balanced

Operators needed = total weighted work content / takt = 259.95 / 60 = 4.33, so five. Balance efficiency = 259.95 / (5 x 60) = 86.7 percent.

Five trim stations, two numbers each

Example numbers

1. Door trim

52.3 s
70.4 s

2. Seal and weatherstrip

55.0 s
58.0 s

3. Mirror and harness

49.5 s
66.0 s

4. Speaker and window regulator

57.2 s
61.5 s

5. Door check and adjust

46.0 s
  • Weighted average
  • Heaviest variant, inside takt
  • Heaviest variant, over takt

Dashed line: takt, 60 s. Operators of work = 259.95 / 60 = 4.33, so five operators at 86.7% balance efficiency.

Weighted average and heaviest variant per station against a 60 second takt. 1. Door trim: average 52.25, heaviest 70.4. 2. Seal and weatherstrip: average 55.00, heaviest 58.0. 3. Mirror and harness: average 49.50, heaviest 66.0. 4. Speaker and window regulator: average 57.20, heaviest 61.5. 5. Door check and adjust: average 46.00, heaviest 46.0. Total weighted work 259.95 seconds is 4.33 operators of work for 5 operators, 86.7% balanced.

Station 4 is the risk: 95% loaded on average with almost nothing to give back after a heavy car. Station 5 has 14 seconds spare and no variants, so it is where work should move.

Read the table the way a line engineer would. Station 4 is the risk, not station 1, although station 1 has the heaviest single car: it is loaded to 95 percent on average and its light cars give back almost nothing. Station 5 has 14 seconds spare and no variants, so it is where work from station 4 should go if the build order allows. The method for moving elements between stations is in line balancing, and the chart that shows it is the yamazumi chart.

Plants also track the whole line with one figure, labor hours per vehicle: all the paid hours in the shop divided by the vehicles built. It moves when the balance improves, and it hides which station changed. Keep the station table as the working document.

Ergonomics: the same motion 450 times a shift

A posture that looks harmless once is a different thing at 450 cycles a shift. Assembly has a short list of loads that come up again and again: arms above the shoulder under the body and in the roof, a bent or twisted trunk inside the cabin, push forces from clips and connectors on the fingers and thumb, and the weight of tools held away from the body.

  • Assess every variant. The premium trim in the example adds two screws driven at arm's length inside the door, which is the worst posture of the cycle and does not appear on the base car.
  • Look at the time study footage twice. The same video that gives element times shows the postures, so one filming session covers both.
  • Use a screening method your plant has agreed. REBA and RULA score a posture. The EAWS worksheet, published by the MTM association and built for cycle work, scores postures, forces, loads and repetition together, and is often paired with MTM-UAS at the planning stage.
  • Treat a balance change as an ergonomics change. Moving 8 seconds of work to another station also moves its posture and its force there.

The guide to ergonomic assessment in manufacturing covers the methods, and workstation design covers reach zones and part presentation. This is general practice and not medical or legal advice.

The people side on a paced line

Operators on a paced line cannot be asked for more output, and most know it. What they fear from a study is different: more work loaded into the same takt, or a team member taken off the line. Say what the study is for before the camera goes up, and mean it.

  • Study the station, not the person. Film several operators and shifts, and report times by variant, never by name.
  • Show the footage to the team first. The operator knows why the premium car takes longer, and usually knows the fix.
  • Be honest about what happens to saved time. If the plan is to rebalance and free a position, say how the person is redeployed.
  • Follow the agreements in force. Where a union agreement or works council covers work measurement or filming, it decides how the study is run.

Mistakes specific to assembly lines

Assembly line time study mistakes and what to do in their place
MistakeWhat goes wrongDo this
Timing only the common variantThe station is balanced for the base car and stops on every premium one.Time each variant's option work and check the heaviest car against takt and the drift limit.
Balancing on the average aloneA station at 95 percent on average has no recovery and drifts all shift.Carry two numbers per station: weighted average and heaviest variant.
Leaving out the walk backThe cycle looks 4 seconds shorter than it is, on every car.Start and end the cycle at the same point: the operator's first touch of the car.
Rating tool-paced timeA screw cycle rated at 110 gives a normal time the tool cannot deliver.Take tool time from the controller and rate only the manual elements.
Studying at launch and never againTimes from week two of ramp-up stay on the sheet for years while the mix shifts.Restudy on every engineering change, mix change and takt change.
Treating planned times as measuredThe predetermined times assumed a part presentation the line does not have.Check planned times against video once real parts and racks are in place.
Ignoring the sequenceThe balance holds on paper and fails whenever heavy cars arrive together.Agree a sequence rule for each heavy option and test it against real build orders.

Templates, tools and related guides

LeanSuite's time and motion study times each element from a phone video of the station, and line balancing turns the station videos into a yamazumi chart against takt. The ergonomic study scores REBA and RULA from the same kind of footage. For how plants in the sector use the platform, see LeanSuite for automotive.

FAQ

Questions about time study in automotive assembly

  1. Work out takt first, then film the station for enough cars to see every variant. Split the cycle into elements, time each one, rate the manual elements and add allowances to get a standard time per variant. Compare the weighted average with takt, check the heaviest variant against the drift the station can absorb, and restudy whenever the job, the mix or takt changes.

  2. Mixed-model line balancing assigns work to stations on a line that builds several variants in one stream. Each station's work content is weighted by the build mix, and the weighted average must fit inside takt. Because some variants exceed takt at some stations, the balance also has to check the heaviest variant and set sequence rules so that heavy units do not arrive together.

  3. No. IATF 16949 does not name a work measurement method. Clause 8.5.1.2 requires standardised work documents that are communicated, understood, legible, in a language the operators understand and accessible at the work area. A time study is the usual way the times on those documents are set, and customer-specific requirements may add capacity checks of their own.

  4. Takt time is set by demand: running time divided by the number of vehicles required, so every station on the line shares it. Cycle time is what a station takes to finish its work on one vehicle. A station works when its cycle time, for every variant and with allowances, fits inside takt. Takt is a target and cycle time is a measurement.

  5. They do different jobs. A predetermined system such as MTM-UAS builds a time from the motions on a process sheet, so it works before the line exists and needs no pace rating. A stopwatch or video study measures what the real station takes. Plants plan with a predetermined system and check the running line with video.

  6. Drift is how far behind the operator is when a car's work takes longer than takt. On a line moving at 0.1 metres a second, a job that runs 10 seconds over carries the operator one metre past the station boundary. A lighter car afterwards recovers the time. Drift becomes a line stop when heavy cars follow each other and it passes the station's limit.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.