Time study in warehouse operations: how to build engineered labor standards

Short answer

A warehouse time study does not time a cycle, because no two orders are alike. It times what every order is made of: a fixed start and finish, travel per metre, a stop per line and handling per unit. An engineered labor standard adds those up for each assignment.

In a factory the job repeats, so one standard time fits every cycle. In a warehouse each pick assignment has its own number of lines, units and metres to travel, so a single average rate is wrong for most of them. The answer is an engineered labor standard: time the building blocks once (start and finish, travel per metre by equipment, the stop at a location, handling per case by size and slot height), add personal, fatigue and delay allowances, and let the system calculate a goal time for every assignment from its own lines, units and route. Performance is goal time divided by actual time. Use time study or video for the building blocks, predetermined times such as Master Standard Data or MOST for manual handling, and work sampling for indirect time.

Last reviewed:

Why a warehouse time study is different from a factory one

A warehouse standard is a formula, not a single time

Example numbers
  • per assignment

    Start and finish

    75 s

    Take the work, fetch a cart, drop the load, confirm.

  • per metre

    Travel

    0.80 s

    Set by the route and the equipment, not by the picker.

  • per line

    Stop at a location

    10 s

    Park, find the slot, scan, read the quantity.

  • per unit

    Handle a unit

    4 s

    Reach, grasp, place. Plus 2 s from a low or high slot.

Goal time for one assignment

(fixed + metres x time per metre + lines x time per line + units x time per unit) x (1 + allowance)

Four building blocks are timed once: start and finish at 75 seconds per assignment, travel at 0.8 seconds per metre, a stop at a location at 10 seconds per line and handling at 4 seconds per unit. The goal time for any assignment is the sum of each block times its count, times one plus the allowance.

Time each block once. Then every assignment gets its own goal time from its own metres, lines and units.

A time study on an assembly line times one job that repeats. Thirty cycles, a rating, allowances, and you have a standard time that holds for every unit. Try that on an order picker and it falls apart on the second order. One assignment is 4 lines from two aisles. The next is 14 lines spread over six. Neither is the cycle.

So warehouse work is measured one level down. You don't time the order. You time the things every order is built from, and then you count how many of each thing a given order has. The standard becomes a small formula in place of a single number.

  • Fixed time per assignment: get the work, pick up a cart or pallet, drop the finished load, sign off. It is the same whether the order has 2 lines or 20.
  • Travel: time per metre, which depends on the equipment (on foot, with a cart, on a pallet jack, on a lift truck) and on the route the system sends you.
  • Time per line: stop at the location, find the slot, scan, read the quantity. One per location visited.
  • Time per unit: reach, grasp, move and place one case or one each. It changes with the size and weight of the item and the height of the slot.

Travel deserves its own line because there is so much of it. A long-quoted estimate from Tompkins and colleagues' Facilities Planning, repeated in de Koster, Le-Duc and Roodbergen's 2007 review of order picking research, puts travel at about half of an order picker's time, and puts order picking at as much as 55 percent of a warehouse's operating cost. Your own split will differ. But any standard that ignores distance is ignoring the biggest piece.

The work in a warehouse, and what each job's time depends on

Before timing anything, write down what drives the time of each job. These drivers are what you will count per assignment, so they have to be things the warehouse management system (WMS) already records or can calculate.

Warehouse jobs, what drives their time and the unit the standard is built on
JobWhat the time depends onBuild the standard per
Unloading and receivingFloor-loaded or palletized, cases per pallet, mixed or single item, checks and labels requiredTrailer, pallet and case
PutawayDistance from dock to slot, slot height, single or double deep rack, lift truck typePallet, metre travelled and metre lifted
ReplenishmentDistance from reserve to pick face, slot height, whether cases are cut open or decantedPallet or case, and metre travelled
Order pickingRoute length, number of locations visited, units per line, case size and weight, slot heightAssignment, metre, line and unit
PackingItems per order, carton choice, dunnage, labels and paperwork, special customer requirementsOrder, item and carton
Loading and shippingPallets or loose cartons, wrap and label, distance from staging to door, load checksPallet or carton, and trailer

Packing at a fixed bench is the one job here that behaves like factory work. It can be timed, balanced and laid out like any workstation.

Packing benches are worth a separate look. The operator stands in one place, so the levers are reach distances and bench layout, covered in workstation design, and where several packers feed one conveyor the split of work between them is a line balancing question.

What engineered labor standards are

An engineered labor standard is the time a trained person, working at a normal pace by the defined method, should take for one specific assignment, calculated from measured element times and the content of that assignment. Three words in that sentence do the work: measured, method and specific.

That sets it apart from the two cheaper kinds of warehouse labor standards you will meet.

Three kinds of warehouse labor standards

  • Historical average

    How it is set
    Last quarter's units or lines divided by hours
    What it is good for
    Budgets and headcount for a whole building
    Where it fails
    It bakes in whatever waste was there, and it is wrong for any one order or person.
  • Simple rate from a study

    How it is set
    A time study of a few typical assignments, turned into cases or lines per hour
    What it is good for
    A stable operation with one order profile
    Where it fails
    It breaks when the order mix, the slotting or the season changes.
  • Engineered (discrete) standard

    How it is set
    Element times for travel, lines and units, applied to each assignment's own content
    What it is good for
    Goal times for individual assignments, fair comparison between people, costing a change before making it
    Where it fails
    It costs real engineering time to build and must be maintained.
Read left to right: each kind costs more to build than the one before and holds up under more change.

The formula for a pick assignment looks like this. Goal time = (fixed time + metres travelled x time per metre + lines x time per line + units x time per unit) x (1 + allowance). Real standards add more terms: a different time per unit for each case size class, an extra for slots below the knee or above the shoulder, a time for building a stable pallet. The structure stays the same.

The element times come from two places. Travel and anything done on a machine is timed on site, because trucks, floors and aisles differ. Manual handling is often built from a predetermined time system, which gives a time for each basic motion without a stopwatch. In warehousing the usual ones are Master Standard Data (MSD), set out by Crossan and Nance in the book of the same name, and MOST. Both work in larger motion blocks than MTM, which makes them quicker to apply to long handling tasks. The guide to predetermined motion time systems explains how they work.

Be honest about the cost. A Logistics Viewpoints series on warehouse labor standards quotes one rule of thumb from practitioners: fully discrete standards are often not worth building for a site with fewer than about 70 people on a shift. Below that, a careful time study and a few rates by order type may be the right size of answer.

Which measurement method fits which warehouse job

No single method covers a warehouse. Each sees one part of the work well and is blind to another.

Measurement methods for warehouse work: what each is good for and what it misses

  • Stopwatch time study

    Use it for
    Travel speed by equipment over a measured distance, lift and lower times, dock work, anything with a machine in it
    What it misses
    It needs a rating of pace, it follows one person, and an observer walking behind a picker changes how they work.
  • Video study

    Use it for
    Fixed stations such as packing, receiving desks and the pick face itself. The footage can be replayed and the method argued over.
    What it misses
    A fixed camera can't follow a picker down six aisles. Consent and clear rules are needed first.
  • Predetermined times (MSD, MOST, MTM)

    Use it for
    Manual handling: reach, grasp, lift, place, by case size and slot height. Also planning a job or layout that does not exist yet.
    What it misses
    Machine time and travel on trucks. It also needs a trained analyst, and it describes the method on paper, not the one people use.
  • Work sampling

    Use it for
    Indirect work and delays: waiting at the dock, battery changes, looking for a pallet, congestion. Also the delay allowance.
    What it misses
    It gives shares of time, not element times, and says nothing about the method.
  • WMS and scan data

    Use it for
    Volumes, order profiles, distances from the location map, and actual time per assignment across every person and shift
    What it misses
    The time between two scans holds everything: walking, picking, waiting, talking. It shows how long, never why.
Each method sees one part of the work well. A sound standard uses at least three of these: site time study for travel, predetermined times or video for handling, and sampling for the allowance. Scan data then tests the result.

The work sampling guide covers the number of observations and the random schedule. For fixed stations, time study from video covers filming and analysis. Lift truck tasks with long, irregular cycles follow the approach in timing long-cycle and team work.

How to run a warehouse time study, step by step

This is the sequence for one job, such as case picking in one zone. Repeat it for each job that needs a standard.

From the method to a maintained standard

  1. 1

    Fix the method first

  2. 2

    List the drivers and check the system has them

  3. 3

    Time the building blocks

  4. 4

    Time travel by equipment

  5. 5

    Add allowances

  6. 6

    Calculate goal times for real assignments

  7. 7

    Test, explain and maintain

Steps 3 and 4 are the time study itself. The steps around them decide whether anyone trusts the result.
  1. 1

    Fix the method first

    Watch the job and agree the best current way to do it: where the cart is parked at a location, scan before or after the pick, how a pallet is built. A standard for a method nobody follows is worthless. Fix obvious waste now, not after.

  2. 2

    List the drivers and check the system has them

    Write down what makes one assignment longer than another: metres, lines, units, case size, slot height. Confirm the WMS holds each one, or can calculate it from the location map. A driver you can't count can't be in the formula.

  3. 3

    Time the building blocks

    Time each element over enough repeats to be stable: the start and finish of an assignment, the stop at a location, the handling of one case in each size class and at each slot level. Rate the pace and convert to normal time as in any time study.

  4. 4

    Time travel by equipment

    Mark a measured distance in a real aisle and time people and trucks over it, loaded and empty, including the slow-down at aisle ends and crossings. Express it as seconds per metre. Do not use a catalog top speed for a truck. It rarely reaches it.

  5. 5

    Add allowances

    Add personal, fatigue and delay allowances to the normal time. Take the delay part from a work sampling study of the zone, not from a guess. Heavy cases and cold stores justify more fatigue allowance than a light each-pick zone.

  6. 6

    Calculate goal times for real assignments

    Apply the formula to a few hundred past assignments from the WMS. Each one gets its own goal time from its own metres, lines and units.

  7. 7

    Test, explain and maintain

    Compare goal times with actual times. Where they disagree badly, walk the assignment and find out why before blaming the picker. Show the people who do the job how the number is built. Then set a rule: any change to slotting, layout, equipment or method triggers a review of the standard.

The timing technique itself, including continuous and snap-back timing, rating and how many repeats to take, is in how to conduct a time study. The time study sample size calculator gives the number of readings for a target accuracy.

A worked example: the goal time for one pick assignment

Illustrative example. A pick zone has six aisles, each 30 m long, with 5 m between aisle centers. The pack station where assignments start and finish is 10 m from the front of aisle 1. Pickers walk with a cart and follow a serpentine route: up one aisle, down the next. An assignment of 14 lines and 24 units has picks in all six aisles.

The element times

The site's studies gave these normal times. Travel with a cart was timed at 0.80 seconds a metre, which is 4.5 km/h. That is a little slower than the 3 miles an hour (4.83 km/h, or 0.75 seconds a metre) that time study textbooks use as a benchmark of normal walking pace with no load, which is what you would expect with a cart and aisle ends to turn at.

Illustrative: element times for cart picking in this zone (normal time)
ElementNormal timeCounted per
Start the assignment: take it on the scanner, fetch a cart and totes40 sAssignment
Finish: drop the cart at the pack station and confirm35 sAssignment
Travel with a cart0.80 sMetre
Stop at a location: park, find the slot, scan, read the quantity10 sLine
Pick one unit and place it in the tote4 sUnit
Extra for a unit from a slot below the knee or above the shoulder2 sUnit from those slots

The route

The distance comes from the location map, not from pacing it out. From the pack station to aisle 1 is 10 m. Six aisles at 30 m each is 180 m. Five moves across to the next aisle at 5 m each is 25 m. The route ends at the front of aisle 6, which is 25 m along the front from aisle 1, so the walk back is 25 + 10 = 35 m. Total: 10 + 180 + 25 + 35 = 250 m.

The pick path for assignment A: 14 locations, 250 m

Example numbers
Pick path through six aislesTop view of a pick zone with 6 aisles. The route leaves the pack station, runs 10 metres to aisle 1, goes up and down 6 aisles of 30 metres with 5 metres between them, visits 14 pick locations and returns 35 metres along the front. Total 250 metres.123456AislePack station10 m5 m30 m each aisle35 m back
Pack station to aisle 1
10 m
6 aisles6 x 30 m
180 m
5 moves to the next aisle5 x 5 m
25 m
Back to the pack station25 + 10 m
35 m
Route length
250 m

At 0.80 s a metre: 250 x 0.80 = 200 s of travel.

The route for the 14-line assignment: 10 metres to aisle 1, six aisles of 30 metres, five moves of 5 metres to the next aisle and 35 metres back, 250 metres in all, which is 200 seconds of travel at 0.8 seconds a metre.

The yellow dots are the 14 pick locations. The distance comes from the location map and the routing rule, so the system can calculate it for every assignment. Aisle spacing is not drawn to scale.

The goal time

Illustrative: building the goal time for the 14-line assignment
Part of the standardWorkingTime
Fixed: start and finish40 s + 35 s75 s
Travel250 m x 0.80 s200 s
Lines14 lines x 10 s140 s
Units24 units x 4 s96 s
Units from low or high slots8 units x 2 s16 s
Normal time75 + 200 + 140 + 96 + 16527 s
Allowance at 15 percent of normal time527 x 0.1579 s
Goal time (standard time for this assignment)527 x 1.15606 s, or 10.1 min

The 15 percent allowance is an example figure for personal needs, fatigue and delays. Set your own from a sampling study and your site's rules. Travel is the largest single part: 200 of 527 seconds, or 38 percent.

Building the goal time, part by part

Example numbers
  • Start and finish75 s
  • Travel, 250 m200 s
  • 14 stops at locations140 s
  • 24 units handled, 8 from low or high slots112 s
  • Allowance, 15% of normal time79 s
  • Goal time606 s
  • Actual time taken690 s

Start and finish 75 seconds, travel 200, stops 140, handling 112, which is 527 seconds of normal time. A 15 percent allowance adds 79 seconds for a goal time of 606 seconds. The picker took 690 seconds, so performance is 87.8%.

Normal time is 527 s, and travel is 38% of it. Performance = goal time / actual time = 606 / 690 = 87.8%.

Performance

The picker finished this assignment in 11 minutes 30 seconds, which is 690 seconds. Performance = goal time / actual time = 606 / 690 = 87.8 percent. Over one assignment that number means little: a blocked aisle or an empty pick face explains it. Over a shift of forty assignments it is a fair measure, because every assignment was judged against its own content.

Why pick rate and lines per hour mislead

Most warehouses manage picking by a rate: lines per hour, cases per hour, units per hour. A warehouse pick rate is easy to calculate. Divide lines or units picked by the hours spent picking. The trouble is what the number hides.

Take a second assignment in the same zone, worked with the same element times. It has 4 lines and 40 units, all in aisles 1 and 2, with no awkward slots. The route is 10 + 30 + 5 + 30 + 15 = 90 m.

Illustrative: two assignments at exactly 100 percent of standard
Assignment AAssignment B
Lines144
Units2440
Distance250 m90 m
Normal time527 s347 s
Goal time with 15 percent allowance606 s (10.1 min)399 s (6.65 min)
Lines per hour at goal time8336
Units per hour at goal time143361

Goal time for B: 75 + 72 + 40 + 160 = 347 s normal, x 1.15 = 399 s. Rates are lines or units divided by goal time, x 3,600.

Same pace, very different rates

Example numbers
  • Start and finish
  • Travel
  • Stops at locations
  • Handling units
  • Allowance
  • Assignment A

    14 lines, 24 units, 250 m through six aisles

    Goal time 10.1 min, worked at 100% of standard

    Lines per hour

    83

    Units per hour

    143

  • Assignment B

    4 lines, 40 units, 90 m through two aisles

    Goal time 6.65 min, worked at 100% of standard

    Lines per hour

    36

    Units per hour

    361

Assignment A, 14 lines and 24 units over 250 metres, has a goal time of 10.1 min and comes out at 83 lines per hour and 143 units per hour. Assignment B, 4 lines and 40 units over 90 metres, has a goal time of 6.65 min and comes out at 36 lines per hour and 361 units per hour. Both are worked at exactly the standard pace.

Both bars are drawn to one time scale. Neither rate says who worked harder. Each one mostly describes the order.

Both pickers worked at exactly the standard pace. Judged on lines per hour, the one who drew assignment B looks less than half as productive. Judged on units per hour, it is the other way round by a factor of two and a half. Neither rate measured effort. Both measured the order.

This is why a flat target such as 80 lines an hour produces arguments. People learn which assignments flatter the number and which ruin it. A goal time per assignment removes the argument, since the 14-line order is expected to take 10.1 minutes and the 4-line order 6.65. If you must report a rate, report performance against standard next to it.

Pick path and slotting: where the travel time is decided

The picker does not choose how far to walk. The slotting plan and the routing rule choose. Since travel is the largest element, the biggest gains in a pick zone usually come from changing where things are kept, and the engineered standard lets you price that change before you move a single case.

Suppose the zone is re-slotted so the fastest-moving items sit in the aisles nearest the pack station. The same 14 lines now fall in aisles 1 to 4. The route becomes 10 + 120 + 15 + 25 = 170 m in place of 250 m.

Illustrative: the same 14-line assignment before and after re-slotting
BeforeAfter
Aisles visited64
Distance250 m170 m
Travel time200 s136 s
Normal time527 s463 s
Goal time606 s532 s

Goal time falls by 74 seconds, or 12 percent, with no change in how fast anyone works.

Re-slotting changes the route, so it changes the standard

Example numbers
  • Before: picks in six aisles

    Before: picks in six aisles: pick path through 6 aislesTop view of a pick zone with 6 aisles. The route leaves the pack station, runs 10 metres to aisle 1, goes up and down 6 aisles of 30 metres with 5 metres between them, visits 14 pick locations and returns 35 metres along the front. Total 250 metres.123456AislePack station10 m5 m30 m each aisle35 m back
    Distance
    250 m
    Travel
    200 s
    Goal time
    606 s
  • After: picks in four aisles

    After: picks in four aisles: pick path through 4 aislesTop view of a pick zone with 6 aisles. The route leaves the pack station, runs 10 metres to aisle 1, goes up and down 4 aisles of 30 metres with 5 metres between them, visits 14 pick locations and returns 25 metres along the front. Total 170 metres.123456AislePack station10 m5 m30 m each aisle25 m back
    Distance
    170 m
    Travel
    136 s
    Goal time
    532 s

Before re-slotting the 14 lines are spread over six aisles: 250 metres, 200 seconds of travel and a goal time of 606 seconds. After the fast movers are moved to the nearest aisles the same 14 lines sit in four aisles: 170 metres, 136 seconds of travel and a goal time of 532 seconds.

The same 14 lines and 24 units. The goal time drops by 74 s, or 12%, with nobody working faster. A flat rate set before the move is now too easy by the same amount.

Two things follow. First, a spaghetti diagram of real pick routes is a cheap way to see the wasted travel before any calculation. Second, the standard has to move with the slots. If the building is re-slotted and the old flat rate stays, the rate is now 12 percent too easy. If the change goes the other way and the rate stays, people are being held to a number the layout no longer allows.

Slot height matters too, for time and for backs. The 2 second extra for low and high slots in the example is the time cost. The injury risk is a separate question, and the methods for it are in ergonomic assessment. Putting heavy and fast-moving items between knee and shoulder height wins on both counts.

What a warehouse labor management system does with the standards

A warehouse labor management system (LMS) is the software that applies the standards. It takes each assignment from the WMS, calculates the goal time from the element times and the location map, takes the actual time from the scans, and reports performance by person, job and shift. It also tracks the time between assignments, which is where indirect work and delays show up.

  • The LMS does not create standards. Someone still has to study the work and supply the element times. Software filled with guessed times produces precise-looking wrong answers.
  • It needs clean master data: case dimensions and weights, slot coordinates, travel paths. Errors there become errors in every goal time.
  • It measures time between scans. A picker who waits two minutes for a replenishment looks slow unless the delay is recorded as a delay.
  • It is as fair as its upkeep. New racking, a changed route rule or a new tote size all change the work.

A small site can get most of the benefit without an LMS: a spreadsheet with the element times, a weekly export of assignments and their lines, units and zones, and goal time calculated per assignment.

Mistakes that are specific to warehouse standards

Warehouse labor standard mistakes and what to do in their place

  • Mistake

    Using last year's average as the standard

    What goes wrong: The average includes every delay and bad habit of last year, and nobody can say what part of it is work.

    Do this

    Keep the average for budgets. Build goal times from measured elements.

  • Mistake

    One rate for every order

    What goes wrong: Lines per hour swings with units per line and distance, so people are ranked by the orders they drew.

    Do this

    Calculate a goal time per assignment and manage on performance against it.

  • Mistake

    Leaving travel out, or using one average distance

    What goes wrong: The largest element is treated as a constant when it varies more than any other.

    Do this

    Take the distance for each assignment from the location map and the routing rule.

  • Mistake

    Timing the best picker on the best day

    What goes wrong: The times are right for one person and one hour, and too tight for everyone else.

    Do this

    Time several trained people, rate the pace, and study at different times of the shift and week.

  • Mistake

    No update after a re-slot or layout change

    What goes wrong: The standard describes a building that no longer exists. It drifts too loose or too tight.

    Do this

    Tie a standards review to every slotting, layout, equipment and method change.

  • Mistake

    Counting every gap between scans as picking

    What goes wrong: Waiting for replenishment, congestion and battery changes land on the picker's performance.

    Do this

    Record delays as delays, measure them by work sampling and fix the causes.

  • Mistake

    Setting the rate with no allowance for the load

    What goes wrong: A pace that is fine for small cartons is not sustainable for 20 kg cases over a shift.

    Do this

    Set fatigue allowances by weight and conditions, and check the heavy jobs with an ergonomic assessment.

Most of these are one mistake: treating a number that describes the order as a number that describes the person.

The people side: rates, quotas and trust

Warehouse standards have a harder reputation than factory ones, and it is earned. A number that follows each person through every scan of every shift is felt differently from a line rate shared by a team. A standard that people believe is fair is useful. One they believe is a trap gets gamed, and it pushes people to skip breaks and safe lifting to protect the number.

  • Show the working. Walk a picker through one assignment: this is the distance, these are the lines, this is the allowance, this is the goal time. A standard nobody can explain will not be trusted.
  • Build breaks, safety steps and reasonable delays into the standard, and say so. Time spent on a safety check or a rest break should never count against anyone.
  • Use performance to find problems before you use it to judge people. A zone where everyone is at 80 percent has a process problem.
  • Judge on a week, not on an assignment. Single assignments are noisy.
  • Watch injury data next to performance data. Rising strain reports in a zone are a signal about the standard, the slotting or both. The warehouse safety guide covers the hazards.
  • Involve the people who do the job in the study. They know which locations are awkward and which scans double up.

Several US states now regulate warehouse quotas by law. California's AB 701, in force since 1 January 2022, requires large warehouse employers to give each worker a written description of every quota they are held to, and bars quotas that prevent meal and rest breaks or use of the bathroom. It applies to employers with 100 or more employees at one distribution center or 1,000 or more across the state. New York, Minnesota, Washington and Oregon have passed laws along similar lines. The details differ and they change, so check the current rules where you operate. This is general practice, not legal advice. Where a union agreement covers work measurement, follow it.

Templates, tools and related guides

For fixed stations such as packing benches and receiving desks, LeanSuite's time and motion study works from a phone video: film the station and the AI times every element on a timeline that links back to the footage, for an engineer to review and certify. It suits the station work in a warehouse, not a picker travelling through the aisles.

FAQ

Questions about time study in warehouse operations

  1. Engineered labor standards are goal times calculated for each assignment from measured element times and the content of that assignment. For a pick assignment that means a fixed start and finish time, travel time for the route, a time per line and a time per unit by case size and slot height, plus personal, fatigue and delay allowances. They differ from historical averages, which only divide past volume by past hours.

  2. Fix the method first, then time the building blocks instead of whole orders: starting and finishing an assignment, travel per metre for each type of equipment, the stop at a location and the handling of one unit by size and slot height. Rate the pace, add allowances, and calculate a goal time for each assignment from its own distance, lines and units. Check the goal times against real assignments before using them.

  3. Pick rate is the number of lines, cases or units picked divided by the hours spent picking. A picker who completes 640 lines in 8 hours has a rate of 80 lines per hour. The rate depends heavily on units per line and travel distance, so compare people on performance against a goal time for each assignment, not on the raw rate.

  4. There is no single good figure. Lines per hour depends on the distance between picks, the units per line, the size of the items, the equipment and the slotting. In the worked example on this page, two assignments at the same standard pace come out at 83 and 36 lines per hour. Set the expectation from an engineered standard for your own layout and order profile.

  5. A warehouse labor management system, or LMS, is software that calculates a goal time for each assignment from labor standards and the location map, compares it with the actual time from scans, and reports performance by person, job and shift. It also tracks indirect time between assignments. It applies standards but does not create them: the element times still come from time studies and predetermined time systems.

  6. Master Standard Data, or MSD, is a predetermined time system set out by Richard Crossan and Harold Nance in their book of the same name. It gives standard times for basic manual motions such as reaching, grasping and placing, so an analyst can build the time for a handling task without a stopwatch. It is widely used for warehouse labor standards, usually with on-site time studies for travel and lift trucks.

  7. Travel is usually the largest part of a picker's time. A widely quoted estimate from Tompkins and colleagues puts it at about half. It is also the part that varies most between assignments, and it is set by slotting and routing, not by how hard the picker works. A standard that leaves travel out, or treats it as a constant, is wrong for most assignments.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.