Bottleneck analysis from a time study: find the constraint, then check it on the floor
Short answer
The bottleneck is the station that limits what the whole line can make. Time each station, divide the shift by each time, and the smallest result is the constraint. Then prove it on the floor: the station that never waits is the one.
To find a bottleneck from a time study, take the time per piece at every station and compare it with takt time. The station with the longest time has the lowest capacity, shift time divided by station time, and sets the output of the line. Confirm it by watching: stations before it are blocked, stations after it are starved, and it never waits. A study times good cycles, so check stations that sit within about 5 percent of each other against the floor. Fix the constraint, then look again: the next slowest station takes its place.
Last reviewed:
What is a bottleneck, and is it the same as a constraint?
Five stations against takt time: one is over
Example numbersCut435 per shift
Wind275 per shift
Assemble321 per shift
Test355 per shift
Pack465 per shift
275
pieces a shift from the line, set by wind alone: 27,000 s / 98 s. The customer needs 300, so the line is 25 short.
Station times in seconds per piece: cut 62, wind 98, assemble 84, test 76, pack 58. Takt time is 90 seconds. Only wind is over takt, at 98 seconds, so it is the constraint and the line can make 275 pieces a shift against a demand of 300.
A bottleneck is a step whose capacity is lower than the demand placed on it, so it limits the output of everything around it. An hour lost there is an hour lost for the whole line. An hour gained anywhere else is worth nothing until the bottleneck can use it. That idea comes from Eliyahu Goldratt and Jeff Cox's novel The Goal (1984), and it is the core of the theory of constraints.
The two words are used loosely, but they are not quite the same. A bottleneck is a resource, usually a machine or a station. A constraint is whatever stops the system doing more: it can be a station, but it can also be a rule, a shift pattern, a supplier or the market. Goldratt made the point that a policy can be the constraint as well as a machine. A time study can only find the first kind. This page is about that kind, the station you can time.
A time study is a good place to start because it already gives you what you need: an honest time per piece at each station. What it does not give you is how the stations behave next to each other over a whole shift. That is why the method below has two halves, the arithmetic and the check on the floor.
How to find the bottleneck from station times
- 1
Get one time per piece for each station
Use the standard time or the selected cycle time from the study, not a single lucky cycle. For a machine, use load, run and unload together, the time before the next piece can start. For a station with two machines or two people sharing a job, divide by the number working in parallel.
- 2
Work out takt time
Available time in the shift divided by customer demand in the shift. Takt time is the pace the customer sets. Station times are compared with it, not with each other.
- 3
Compare each station with takt
Station time divided by takt time is the load. Over 100 percent means the station cannot keep up. Under 100 means it can, with room to spare.
- 4
Turn each time into capacity
Shift time divided by station time, rounded down, is the most pieces that station can pass in a shift. The smallest figure on the line is the line's capacity, and the station it belongs to is the bottleneck.
- 5
Check the pattern on the floor
Walk the line for an hour with a clipboard. Note who waits and why. The bottleneck never waits for work and never waits for room. Stations before it are blocked, stations after it are starved.
- 6
Look for a close second
If a second station is within about 5 percent of the first, treat both as constraints until the floor says otherwise. A study times normal cycles, and the losses it misses fall unevenly.
Steps 1 to 4 are arithmetic you can do from a time study sheet in ten minutes. Steps 5 and 6 are the reason the answer can be trusted. The free bottleneck calculator does steps 1 to 4 for a line of any length and shows the gap to demand.
Worked example: a five-station line
Illustrative numbers. A line assembles small motor sub-assemblies through five stations. The shift has 450 minutes, 27,000 seconds, and the customer needs 300 a shift, so takt time is 27,000 / 300 = 90 seconds. The time study gives the times in the table. Nobody has stated where the problem is. The table does.
| Station | Time per piece | Load against takt (90 s) | Capacity per shift |
|---|---|---|---|
| Cut | 62 s | 62 / 90 = 68.9 percent | 27,000 / 62 = 435 |
| Wind | 98 s | 98 / 90 = 108.9 percent | 27,000 / 98 = 275 |
| Assemble | 84 s | 84 / 90 = 93.3 percent | 27,000 / 84 = 321 |
| Test | 76 s | 76 / 90 = 84.4 percent | 27,000 / 76 = 355 |
| Pack | 58 s | 58 / 90 = 64.4 percent | 27,000 / 58 = 465 |
Capacity is rounded down to whole pieces. Wind is the only station over 100 percent, and its 275 is the line's capacity.
Wind is the constraint. The line makes 275 a shift against a need for 300, which is 25 short. Making cut faster, or pack, or test, changes nothing in that number. Assemble deserves a note: at 93.3 percent it is not the problem, but it is the next one, and it will matter in a moment.
The same times drawn as a yamazumi chart show the shape better than the table: stacked work content for each station against the takt line. The yamazumi is also the tool to use when you start moving work between stations. For a whole line with machines and people mixed, the process capacity sheet lays out the same arithmetic.
Confirming it on the floor: blocked and starved
Arithmetic says which station should be the constraint. The floor says whether it is. In a line with limited space between stations, the constraint sets the pace and everyone else adjusts to it. A station that is waiting is waiting for someone, and who that someone is points straight at the bottleneck.
If wind sets the pace at 98 seconds a piece, cut can only work as fast as wind takes pieces away. Once the space in front of wind is full, cut stops: it is blocked. Assemble, test and pack can only work when wind sends a piece. They finish it faster than wind makes the next one, and wait: they are starved. Wind itself always has a piece in front of it and always has room after it. Work through the hour for this line and the waiting falls out of the times.
One hour at the line's pace: who waits for whom
Example numbersCut: works 38.0 min, blocked 22.0 min
Wind: works 60.0 min, never waits
Assemble: works 51.4 min, starved 8.6 min
Test: works 46.5 min, starved 13.5 min
Pack: works 35.5 min, starved 24.5 min
- Working
- Blocked: next place is full
- Starved: no piece to work on
The line runs at the pace of wind, one piece every 98 seconds. In an hour, cut works 38.0 minutes and is blocked for 22.0. Wind works all 60 minutes and never waits. Assemble, test and pack work 51.4, 46.5 and 35.5 minutes and are starved for the rest.
| Station | Working | Waiting | Kind of waiting |
|---|---|---|---|
| Cut | 62 / 98 x 60 = 38.0 min | 22.0 min | Blocked: wind has no room for another piece |
| Wind | 98 / 98 x 60 = 60.0 min | 0 min | None: this is the constraint |
| Assemble | 84 / 98 x 60 = 51.4 min | 8.6 min | Starved: waiting for a wound part |
| Test | 76 / 98 x 60 = 46.5 min | 13.5 min | Starved |
| Pack | 58 / 98 x 60 = 35.5 min | 24.5 min | Starved |
The line as a whole works 378 / (5 x 98) = 77.1 percent of the time. The 22.9 percent that is left is not a loss to chase everywhere. Most of it is the price of a constraint.
Real floors are noisier than this, but the pattern holds: blocked before, starved after, and one station that never waits. That is the clearest sign you can get without instruments. Record it with a tally sheet, a mark each time you see a station idle and the reason. A work sampling round across all five stations gives you the same answer with a sample size you can defend, and it tells you how much of each station's time is waiting versus working.
- A buffer that is always full in front of a station is a sign that station is the constraint.
- A buffer that is always empty in front of a station means the station is starved. Look upstream.
- If the buffer sizes jump around, the constraint is moving, or there is more than one.
- A station that waits for an operator, a forklift or a tool is waiting for a shared resource, and that resource may be the real constraint.
A station that looks hurried is not necessarily the constraint. It may be fed from a full buffer and have little to do between pieces. Look at who waits, not at who looks busy.
When the study and the floor disagree
Sometimes the arithmetic says one station and the floor says another. The usual reason is that a time study is built from good, normal cycles, and a shift is not made of those alone. Anything that stretches the real time per piece without being in the study moves the constraint.
| What the study misses | What it does to the station | How to see it |
|---|---|---|
| Variability from cycle to cycle | A station that averages 84 s but swings between 70 and 100 holds up the stations around it more than its average suggests | The spread of the timed cycles, not only the mean. A control chart of the last 30 cycles. |
| Jams, micro-stops and short breakdowns | Time lost that never shows in a normal cycle | Downtime log, or OEE availability and performance for the machine |
| Changeovers and setup | Whole blocks of the shift with no output | Changeover log by product, times per shift |
| Shared resources | One tester, crane, operator or forklift serving two stations, each looking fine alone | Watch who waits for the shared item, and when |
| Rework and scrap loops | Pieces visit a station twice, or good output is less than parts made | First pass yield at each station, rework flow on the layout |
| Mixed products | Each product has a different bottleneck, and the mix sets which wins | A table of station times for every product and the shift mix |
The simplest correction is effective time per piece: the study time divided by the share of the clock the station actually produces. If wind loses 5 percent of the clock to jams and restarts, an 80 second cycle is 80 / 0.95 = 84.2 seconds per piece in practice. Assemble is 84 seconds and loses nothing that anyone has seen. A study that stopped at the timed cycle would call assemble the constraint. On the floor, the two are level, to within a second.
Two stations, one number apart: the study alone cannot say which is slower
Example numbersWind: 80 s timed, 84.2 s with jams
Assemble: 84 s timed, no loss seen
- Time in the study
- Time added by jams, 5 percent of the clock
84.2
s per piece for wind in practice: 80 s / (1 minus 0.05). Assemble is 84 s. The gap is 0.2 s, which is smaller than the error in any stopwatch study.
Timed in the study, wind takes 80 seconds and assemble 84, so assemble looks like the constraint. Wind loses 5 percent of its time to jams and restarts, which is 84.2 seconds per piece on average. That makes the two stations equal within a second, at about 321 pieces a shift each.
That is not a failure of the study. It is the reason step 6 says to look for a close second. When two stations are inside 5 percent of each other, improving one only moves the problem to the other. Work on both, or choose the one where the gain is cheaper, and be clear that the line is limited by a pair.
The other direction happens too: the floor says a station is the bottleneck, but the study shows it as comfortably fast. Then the time it is losing is outside the cycle, in waiting for material, changeovers or breaks. A man and machine chart of the station shows where an operator waits on a machine, or a machine on an operator.
What to do once you have found it: the five focusing steps
Goldratt's answer is five steps, in order, repeated. In his order they are: identify the constraint, decide how to exploit it, subordinate everything else to that decision, elevate the constraint, and then, if the constraint has moved, go back to step one without letting inertia build a new one. The wording varies a little between books, and the order does not.
- Identify. This page so far: the station that sets the output of the line.
- Exploit. Get the most from the constraint as it is, before spending money. Never let it wait for a part, a tool, an operator or a break. Load the next piece while it runs. Keep quality checks upstream, so it never works on a bad piece.
- Subordinate. Make everything else serve the constraint. Upstream stations release work at the constraint's pace, not their own. A cut station that runs flat out only builds a pile in front of wind. Its idle time is correct, not a loss to recover.
- Elevate. If exploiting is not enough, add capacity: a second fixture, a second machine, a person, overtime. This step costs money, which is why it comes after exploit.
- Go back to step 1. When the constraint is no longer the slowest, a different station is. The rules and buffers you set for the old one now protect nothing, and may hold the new one back.
On the example line the steps look like this. Identify: wind at 98 seconds, 275 a shift. Exploit: load the next part while the winder runs, and cover breaks. That takes the time from 98 to 86 seconds, which is 27,000 / 86 = 313 a shift, over the 300 needed, for no spend. Subordinate: cut is held to the winder's pace with two pieces of buffer. Then demand rises to 330 a shift, takt time falls to 27,000 / 330 = 81.8 seconds, and exploit is not enough. A second fixture takes wind to 80 seconds, 337 a shift. That is elevate.
The five focusing steps, with this line's numbers
Example numbers- 1
Identify. Wind is the only station over takt: 98 s against 90 s. 275 a shift, 300 needed.
- 2
Exploit. Load the next part while the winder runs, cover breaks. 98 s becomes 86 s: 313 a shift. No money spent.
- 3
Subordinate. Cut releases a piece only when wind takes one. Two pieces of buffer ahead of wind, no more. Cut's idle time is not a problem to fix.
- 4
Elevate. Demand rises to 330, takt 81.8 s. A second fixture takes wind to 80 s: 337 a shift. Now it costs money.
- 5
Go back to 1. Assemble, at 84 s, is now the slowest: 321 a shift, short of 330. Start again, and drop the old buffer rules.
Five steps in a loop. Identify wind as the constraint. Exploit it by loading while it runs, 98 to 86 seconds. Subordinate cut to wind's pace. Elevate with a second fixture, 80 seconds. Go back to step 1: assemble at 84 seconds is the new constraint.
Where the constraint goes next
The result of step 4 is not the end. At 80 seconds, wind is no longer the slowest station: assemble is, at 84 seconds. At a takt time of 81.8 seconds assemble is over, at 84 / 81.8 = 102.7 percent, and the line can make 321 a shift against 330. The bottleneck has moved one station downstream. The gain from fixing wind was real, from 275 to 321, but it stopped at the gap between the two: 84 minus 80 is 4 seconds.
Say the next fix moves a 5 second element from assemble to pack, using a yamazumi to pick the element. Assemble becomes 79 seconds and pack 63. Now the slowest is wind again, at 80 seconds, and the line makes 337 a shift. The constraint is back where it started, in a stronger position, and still holds up the line. That is the normal course of a line balancing job: each fix moves the constraint, and the job ends when the constraint sits where you want it, or when the line meets demand with room to spare.
The constraint moves when you fix it
Example numbers1. Start: constraint Wind, 275 a shift
Cut435 per shift
Wind275 per shift
Assemble321 per shift
Test355 per shift
Pack465 per shift
2. Wind to 80 s, demand 330: constraint Assemble, 321 a shift
Cut435 per shift
Wind337 per shift
Assemble321 per shift
Test355 per shift
Pack465 per shift
3. Move 5 s from assemble to pack: constraint Wind, 337 a shift
Cut435 per shift
Wind337 per shift
Assemble341 per shift
Test355 per shift
Pack428 per shift
Three states of the same line. Start, takt 90 seconds: wind 98 is the constraint, 275 a shift. After wind goes to 80 and demand rises to 330, takt 81.8: assemble at 84 is the constraint, 321 a shift. After moving 5 seconds from assemble to pack: wind at 80 is the constraint again, 337 a shift, enough for 330.
- The gain from any fix is capped by the next slowest station. Look at it before you spend.
- Reset the buffer and release rules every time the constraint moves. They were written for a different station.
- Choose where the constraint should live. A constraint on the cheapest, most reliable, easiest to staff station is a good place for it. A planned constraint is better than a surprise one.
- Keep the time study up to date. After a change, retime the stations that moved, and the one now closest to the constraint. From time study to standard work covers keeping the documents in step.
Where this method is the wrong tool
- Job shops and mixed-model work. Each job has its own route and times, and the constraint depends on the mix of the week. Use production capacity by work centre against the load, not a single line view.
- Long, irregular cycles. A study of five cycles cannot show a constraint that appears one shift in ten. Use logs of output by hour, or work sampling over several shifts.
- Constraints that are not stations: a supplier that delivers late, a policy that releases work in batches, a limit on overtime, a market that buys less than the line can make. Timing stations will not find these. If every station is under takt time and the line still misses output, look here.
- Lines where speed is not the issue, such as quality: when the station that limits good output is the one with the highest scrap, count good pieces, not pieces.
The people side is simple to state. When a station is called the bottleneck, the person working there often hears blame. Explain that the line's output is limited by the design of the work, not by the effort of whoever is at that station, and bring the operator into the fix. They know what makes the cycle stretch.
Common mistakes
- Choosing the station that looks busiest. Look for the one that never waits.
- Improving a station that is not the constraint, and calling the extra work in process a result.
- Comparing station times with each other and not with takt time. A line can have a slowest station and still meet demand.
- Using one timed cycle, or the best one. Use the standard time and look at the spread.
- Ignoring a close second. Within 5 percent, both are the constraint.
- Forcing upstream stations to run flat out. It builds stock in front of the constraint and hides every problem.
- Not checking again after a fix. The constraint moves, and so does the right buffer.
- Treating the answer as permanent. A new product, a new shift pattern or a changed takt time can move it.
Where software helps
The arithmetic is small. The hard part is getting honest station times for every station and every product. LeanSuite's Time and Motion Study times each element from a video of the station, on a timeline you check against the footage. Line Balancing takes the times from a video of the line and draws the yamazumi against takt time. For a quick check, the bottleneck calculator is free.
Go deeper
This page is the short version. These guides cover each part in full.
- Manufacturing Bottleneck Elimination: 5 Proven StrategiesWays to raise the capacity of a constraint once you have found it.
- The Theory of Constraints: A Framework for Operational ExcellenceThe five focusing steps and the thinking behind them.
- Yamazumi Chart: Workload Balancing for JIT Production LinesThe chart to use when moving work off the constraint.
- Throughput Time: How to Calculate and Improve ItWhy work in front of the constraint stretches the time a part takes.
All our articles on this subject are in the value stream mapping and flow topic.
Free templates and tools
- Yamazumi chart template (operator balance)Stack each operator's element times against takt time on one board, so the station that rises above the line is easy to see.
- Bottleneck analysis worksheetEffective capacity per station from cycle time, parallel units, availability and yield, the bottleneck, takt and utilization, a queue cross-check and the five focusing steps.
- Process capacity sheet templateEach machine in a part's routing with manual, auto and tool change time, its capacity per shift, and the step that limits the cell against demand.
- Time study sheetTime each element over 10 cycles and work out the average, lowest repeatable and standard time. Excel does the sums.
- Bottleneck calculatorThe step that limits your line, from each step's cycle time, machines and uptime, with daily capacity and the gap to demand.
- Takt time calculatorThe pace a line must hit to meet customer demand, from shift time, breaks and daily demand.
- Line balancing calculatorLine efficiency, balance delay and the minimum number of stations from station times and takt.
Doing this in LeanSuite
Time and Motion Study
Film the station and the AI times every element on a timeline that links to the video. You check it and certify it.
See Time and Motion StudyLine Balancing
Drop in a video of your line and get a Yamazumi chart, a takt comparison and rebalancing recommendations.
See Line Balancing
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about bottleneck analysis from a time study
Time every station, divide the shift time by each station time, and find the smallest result. That station has the lowest capacity and is the bottleneck. Confirm on the floor: stations before it are blocked, stations after it are starved, and it never waits. If a second station is within about 5 percent, treat both as constraints.
A bottleneck is a resource, usually a machine or station, whose capacity is below the demand placed on it. A constraint is anything that limits what the whole system can do. It can be a station, but it can also be a policy, a supplier or the market. Every bottleneck is a constraint, but not every constraint is a bottleneck.
Compare each station's cycle time with takt time. A station whose time is longer than takt time cannot keep up with demand. The station with the longest time per piece is the bottleneck, and its capacity, shift time divided by cycle time, is the capacity of the line. Cycle times from a time study show good cycles, so confirm with observation.
Identify the constraint, exploit it, subordinate everything else to that decision, elevate the constraint, and then go back to step one if the constraint has moved, without letting inertia build a new one. Exploit comes before elevate because it costs nothing: get the most from the constraint before adding money to it.
Because every line has a slowest station, and when you speed one up the next slowest takes over. The gain from a fix is limited to the gap between the two. In the example on this page, wind went from 98 to 80 seconds, but assemble at 84 seconds became the constraint, so the line gained 46 pieces, not 62.
It can point to one. A study gives the time per piece at each station, which is enough to call the likely constraint. It misses jams, changeovers, shared resources and variability between cycles, so confirm the result by watching who waits for whom. Where two stations are within about 5 percent of each other, the floor decides.
Related guides and tools
- Line balancing: what to do after the constraint is found
- Yamazumi chart: station times stacked against takt time
- Takt time: the line every station is compared with
- Production capacity: from station times to pieces per shift
- Man and machine chart: where an operator or machine waits
- Time and motion study: where the station times come from
- OEE: the losses a time study does not see
- Work sampling: counting who waits, and why
- Bottleneck calculator: capacity and gap to demand
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk
Or browse the topics, the full library and the lean glossary.
Rather see it on your own problem?
Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.