Skip to content
LeanSuite

Bottleneck analysis from a time study: find the constraint, then check it on the floor

Short answer

The bottleneck is the station that limits what the whole line can make. Time each station, divide the shift by each time, and the smallest result is the constraint. Then prove it on the floor: the station that never waits is the one.

To find a bottleneck from a time study, take the time per piece at every station and compare it with takt time. The station with the longest time has the lowest capacity, shift time divided by station time, and sets the output of the line. Confirm it by watching: stations before it are blocked, stations after it are starved, and it never waits. A study times good cycles, so check stations that sit within about 5 percent of each other against the floor. Fix the constraint, then look again: the next slowest station takes its place.

Last reviewed:

What is a bottleneck, and is it the same as a constraint?

Five stations against takt time: one is over

Example numbers
  • Cut435 per shift

  • Wind275 per shift

  • Assemble321 per shift

  • Test355 per shift

  • Pack465 per shift

275

pieces a shift from the line, set by wind alone: 27,000 s / 98 s. The customer needs 300, so the line is 25 short.

Station times in seconds per piece: cut 62, wind 98, assemble 84, test 76, pack 58. Takt time is 90 seconds. Only wind is over takt, at 98 seconds, so it is the constraint and the line can make 275 pieces a shift against a demand of 300.

The bar that crosses the red line is the constraint. Assemble is close but under it. The other three could run faster than the line ever needs them to.

A bottleneck is a step whose capacity is lower than the demand placed on it, so it limits the output of everything around it. An hour lost there is an hour lost for the whole line. An hour gained anywhere else is worth nothing until the bottleneck can use it. That idea comes from Eliyahu Goldratt and Jeff Cox's novel The Goal (1984), and it is the core of the theory of constraints.

The two words are used loosely, but they are not quite the same. A bottleneck is a resource, usually a machine or a station. A constraint is whatever stops the system doing more: it can be a station, but it can also be a rule, a shift pattern, a supplier or the market. Goldratt made the point that a policy can be the constraint as well as a machine. A time study can only find the first kind. This page is about that kind, the station you can time.

A time study is a good place to start because it already gives you what you need: an honest time per piece at each station. What it does not give you is how the stations behave next to each other over a whole shift. That is why the method below has two halves, the arithmetic and the check on the floor.

How to find the bottleneck from station times

  1. 1

    Get one time per piece for each station

    Use the standard time or the selected cycle time from the study, not a single lucky cycle. For a machine, use load, run and unload together, the time before the next piece can start. For a station with two machines or two people sharing a job, divide by the number working in parallel.

  2. 2

    Work out takt time

    Available time in the shift divided by customer demand in the shift. Takt time is the pace the customer sets. Station times are compared with it, not with each other.

  3. 3

    Compare each station with takt

    Station time divided by takt time is the load. Over 100 percent means the station cannot keep up. Under 100 means it can, with room to spare.

  4. 4

    Turn each time into capacity

    Shift time divided by station time, rounded down, is the most pieces that station can pass in a shift. The smallest figure on the line is the line's capacity, and the station it belongs to is the bottleneck.

  5. 5

    Check the pattern on the floor

    Walk the line for an hour with a clipboard. Note who waits and why. The bottleneck never waits for work and never waits for room. Stations before it are blocked, stations after it are starved.

  6. 6

    Look for a close second

    If a second station is within about 5 percent of the first, treat both as constraints until the floor says otherwise. A study times normal cycles, and the losses it misses fall unevenly.

Steps 1 to 4 are arithmetic you can do from a time study sheet in ten minutes. Steps 5 and 6 are the reason the answer can be trusted. The free bottleneck calculator does steps 1 to 4 for a line of any length and shows the gap to demand.

Worked example: a five-station line

Illustrative numbers. A line assembles small motor sub-assemblies through five stations. The shift has 450 minutes, 27,000 seconds, and the customer needs 300 a shift, so takt time is 27,000 / 300 = 90 seconds. The time study gives the times in the table. Nobody has stated where the problem is. The table does.

Illustrative: station times, load against takt time and capacity per shift
StationTime per pieceLoad against takt (90 s)Capacity per shift
Cut62 s62 / 90 = 68.9 percent27,000 / 62 = 435
Wind98 s98 / 90 = 108.9 percent27,000 / 98 = 275
Assemble84 s84 / 90 = 93.3 percent27,000 / 84 = 321
Test76 s76 / 90 = 84.4 percent27,000 / 76 = 355
Pack58 s58 / 90 = 64.4 percent27,000 / 58 = 465

Capacity is rounded down to whole pieces. Wind is the only station over 100 percent, and its 275 is the line's capacity.

Wind is the constraint. The line makes 275 a shift against a need for 300, which is 25 short. Making cut faster, or pack, or test, changes nothing in that number. Assemble deserves a note: at 93.3 percent it is not the problem, but it is the next one, and it will matter in a moment.

The same times drawn as a yamazumi chart show the shape better than the table: stacked work content for each station against the takt line. The yamazumi is also the tool to use when you start moving work between stations. For a whole line with machines and people mixed, the process capacity sheet lays out the same arithmetic.

Confirming it on the floor: blocked and starved

Arithmetic says which station should be the constraint. The floor says whether it is. In a line with limited space between stations, the constraint sets the pace and everyone else adjusts to it. A station that is waiting is waiting for someone, and who that someone is points straight at the bottleneck.

If wind sets the pace at 98 seconds a piece, cut can only work as fast as wind takes pieces away. Once the space in front of wind is full, cut stops: it is blocked. Assemble, test and pack can only work when wind sends a piece. They finish it faster than wind makes the next one, and wait: they are starved. Wind itself always has a piece in front of it and always has room after it. Work through the hour for this line and the waiting falls out of the times.

One hour at the line's pace: who waits for whom

Example numbers
  • Cut: works 38.0 min, blocked 22.0 min

  • Wind: works 60.0 min, never waits

  • Assemble: works 51.4 min, starved 8.6 min

  • Test: works 46.5 min, starved 13.5 min

  • Pack: works 35.5 min, starved 24.5 min

  • Working
  • Blocked: next place is full
  • Starved: no piece to work on

The line runs at the pace of wind, one piece every 98 seconds. In an hour, cut works 38.0 minutes and is blocked for 22.0. Wind works all 60 minutes and never waits. Assemble, test and pack work 51.4, 46.5 and 35.5 minutes and are starved for the rest.

Upstream of the constraint, stations are blocked: the buffer in front of wind is full. Downstream, they are starved: wind has not sent them a piece. The station that never waits is the constraint.
Illustrative: one hour at the line's pace of one piece every 98 s
StationWorkingWaitingKind of waiting
Cut62 / 98 x 60 = 38.0 min22.0 minBlocked: wind has no room for another piece
Wind98 / 98 x 60 = 60.0 min0 minNone: this is the constraint
Assemble84 / 98 x 60 = 51.4 min8.6 minStarved: waiting for a wound part
Test76 / 98 x 60 = 46.5 min13.5 minStarved
Pack58 / 98 x 60 = 35.5 min24.5 minStarved

The line as a whole works 378 / (5 x 98) = 77.1 percent of the time. The 22.9 percent that is left is not a loss to chase everywhere. Most of it is the price of a constraint.

Real floors are noisier than this, but the pattern holds: blocked before, starved after, and one station that never waits. That is the clearest sign you can get without instruments. Record it with a tally sheet, a mark each time you see a station idle and the reason. A work sampling round across all five stations gives you the same answer with a sample size you can defend, and it tells you how much of each station's time is waiting versus working.

  • A buffer that is always full in front of a station is a sign that station is the constraint.
  • A buffer that is always empty in front of a station means the station is starved. Look upstream.
  • If the buffer sizes jump around, the constraint is moving, or there is more than one.
  • A station that waits for an operator, a forklift or a tool is waiting for a shared resource, and that resource may be the real constraint.

A station that looks hurried is not necessarily the constraint. It may be fed from a full buffer and have little to do between pieces. Look at who waits, not at who looks busy.

When the study and the floor disagree

Sometimes the arithmetic says one station and the floor says another. The usual reason is that a time study is built from good, normal cycles, and a shift is not made of those alone. Anything that stretches the real time per piece without being in the study moves the constraint.

What a study leaves out, and how to find it
What the study missesWhat it does to the stationHow to see it
Variability from cycle to cycleA station that averages 84 s but swings between 70 and 100 holds up the stations around it more than its average suggestsThe spread of the timed cycles, not only the mean. A control chart of the last 30 cycles.
Jams, micro-stops and short breakdownsTime lost that never shows in a normal cycleDowntime log, or OEE availability and performance for the machine
Changeovers and setupWhole blocks of the shift with no outputChangeover log by product, times per shift
Shared resourcesOne tester, crane, operator or forklift serving two stations, each looking fine aloneWatch who waits for the shared item, and when
Rework and scrap loopsPieces visit a station twice, or good output is less than parts madeFirst pass yield at each station, rework flow on the layout
Mixed productsEach product has a different bottleneck, and the mix sets which winsA table of station times for every product and the shift mix

The simplest correction is effective time per piece: the study time divided by the share of the clock the station actually produces. If wind loses 5 percent of the clock to jams and restarts, an 80 second cycle is 80 / 0.95 = 84.2 seconds per piece in practice. Assemble is 84 seconds and loses nothing that anyone has seen. A study that stopped at the timed cycle would call assemble the constraint. On the floor, the two are level, to within a second.

Two stations, one number apart: the study alone cannot say which is slower

Example numbers
  • Wind: 80 s timed, 84.2 s with jams

  • Assemble: 84 s timed, no loss seen

  • Time in the study
  • Time added by jams, 5 percent of the clock

84.2

s per piece for wind in practice: 80 s / (1 minus 0.05). Assemble is 84 s. The gap is 0.2 s, which is smaller than the error in any stopwatch study.

Timed in the study, wind takes 80 seconds and assemble 84, so assemble looks like the constraint. Wind loses 5 percent of its time to jams and restarts, which is 84.2 seconds per piece on average. That makes the two stations equal within a second, at about 321 pieces a shift each.

The study timed good cycles. The winder's jams add 4.2 s to every piece on average, so the line has two constraints in practice. Fix both, or the constraint will keep swapping.

That is not a failure of the study. It is the reason step 6 says to look for a close second. When two stations are inside 5 percent of each other, improving one only moves the problem to the other. Work on both, or choose the one where the gain is cheaper, and be clear that the line is limited by a pair.

The other direction happens too: the floor says a station is the bottleneck, but the study shows it as comfortably fast. Then the time it is losing is outside the cycle, in waiting for material, changeovers or breaks. A man and machine chart of the station shows where an operator waits on a machine, or a machine on an operator.

What to do once you have found it: the five focusing steps

Goldratt's answer is five steps, in order, repeated. In his order they are: identify the constraint, decide how to exploit it, subordinate everything else to that decision, elevate the constraint, and then, if the constraint has moved, go back to step one without letting inertia build a new one. The wording varies a little between books, and the order does not.

  • Identify. This page so far: the station that sets the output of the line.
  • Exploit. Get the most from the constraint as it is, before spending money. Never let it wait for a part, a tool, an operator or a break. Load the next piece while it runs. Keep quality checks upstream, so it never works on a bad piece.
  • Subordinate. Make everything else serve the constraint. Upstream stations release work at the constraint's pace, not their own. A cut station that runs flat out only builds a pile in front of wind. Its idle time is correct, not a loss to recover.
  • Elevate. If exploiting is not enough, add capacity: a second fixture, a second machine, a person, overtime. This step costs money, which is why it comes after exploit.
  • Go back to step 1. When the constraint is no longer the slowest, a different station is. The rules and buffers you set for the old one now protect nothing, and may hold the new one back.

On the example line the steps look like this. Identify: wind at 98 seconds, 275 a shift. Exploit: load the next part while the winder runs, and cover breaks. That takes the time from 98 to 86 seconds, which is 27,000 / 86 = 313 a shift, over the 300 needed, for no spend. Subordinate: cut is held to the winder's pace with two pieces of buffer. Then demand rises to 330 a shift, takt time falls to 27,000 / 330 = 81.8 seconds, and exploit is not enough. A second fixture takes wind to 80 seconds, 337 a shift. That is elevate.

The five focusing steps, with this line's numbers

Example numbers
  1. 1

    Identify. Wind is the only station over takt: 98 s against 90 s. 275 a shift, 300 needed.

  2. 2

    Exploit. Load the next part while the winder runs, cover breaks. 98 s becomes 86 s: 313 a shift. No money spent.

  3. 3

    Subordinate. Cut releases a piece only when wind takes one. Two pieces of buffer ahead of wind, no more. Cut's idle time is not a problem to fix.

  4. 4

    Elevate. Demand rises to 330, takt 81.8 s. A second fixture takes wind to 80 s: 337 a shift. Now it costs money.

  5. 5

    Go back to 1. Assemble, at 84 s, is now the slowest: 321 a shift, short of 330. Start again, and drop the old buffer rules.

Five steps in a loop. Identify wind as the constraint. Exploit it by loading while it runs, 98 to 86 seconds. Subordinate cut to wind's pace. Elevate with a second fixture, 80 seconds. Go back to step 1: assemble at 84 seconds is the new constraint.

Exploit comes before elevate on purpose: it costs nothing, and it may be all the line needs. Step 5 is the one people skip.

Where the constraint goes next

The result of step 4 is not the end. At 80 seconds, wind is no longer the slowest station: assemble is, at 84 seconds. At a takt time of 81.8 seconds assemble is over, at 84 / 81.8 = 102.7 percent, and the line can make 321 a shift against 330. The bottleneck has moved one station downstream. The gain from fixing wind was real, from 275 to 321, but it stopped at the gap between the two: 84 minus 80 is 4 seconds.

Say the next fix moves a 5 second element from assemble to pack, using a yamazumi to pick the element. Assemble becomes 79 seconds and pack 63. Now the slowest is wind again, at 80 seconds, and the line makes 337 a shift. The constraint is back where it started, in a stronger position, and still holds up the line. That is the normal course of a line balancing job: each fix moves the constraint, and the job ends when the constraint sits where you want it, or when the line meets demand with room to spare.

The constraint moves when you fix it

Example numbers

1. Start: constraint Wind, 275 a shift

  • Cut435 per shift

  • Wind275 per shift

  • Assemble321 per shift

  • Test355 per shift

  • Pack465 per shift

2. Wind to 80 s, demand 330: constraint Assemble, 321 a shift

  • Cut435 per shift

  • Wind337 per shift

  • Assemble321 per shift

  • Test355 per shift

  • Pack465 per shift

3. Move 5 s from assemble to pack: constraint Wind, 337 a shift

  • Cut435 per shift

  • Wind337 per shift

  • Assemble341 per shift

  • Test355 per shift

  • Pack428 per shift

Three states of the same line. Start, takt 90 seconds: wind 98 is the constraint, 275 a shift. After wind goes to 80 and demand rises to 330, takt 81.8: assemble at 84 is the constraint, 321 a shift. After moving 5 seconds from assemble to pack: wind at 80 is the constraint again, 337 a shift, enough for 330.

The yellow bar is the constraint in each panel. Fixing one station does not finish the job. It hands the constraint to the next slowest, and the line gains only the gap between the two.
  • The gain from any fix is capped by the next slowest station. Look at it before you spend.
  • Reset the buffer and release rules every time the constraint moves. They were written for a different station.
  • Choose where the constraint should live. A constraint on the cheapest, most reliable, easiest to staff station is a good place for it. A planned constraint is better than a surprise one.
  • Keep the time study up to date. After a change, retime the stations that moved, and the one now closest to the constraint. From time study to standard work covers keeping the documents in step.

Where this method is the wrong tool

  • Job shops and mixed-model work. Each job has its own route and times, and the constraint depends on the mix of the week. Use production capacity by work centre against the load, not a single line view.
  • Long, irregular cycles. A study of five cycles cannot show a constraint that appears one shift in ten. Use logs of output by hour, or work sampling over several shifts.
  • Constraints that are not stations: a supplier that delivers late, a policy that releases work in batches, a limit on overtime, a market that buys less than the line can make. Timing stations will not find these. If every station is under takt time and the line still misses output, look here.
  • Lines where speed is not the issue, such as quality: when the station that limits good output is the one with the highest scrap, count good pieces, not pieces.

The people side is simple to state. When a station is called the bottleneck, the person working there often hears blame. Explain that the line's output is limited by the design of the work, not by the effort of whoever is at that station, and bring the operator into the fix. They know what makes the cycle stretch.

Common mistakes

  • Choosing the station that looks busiest. Look for the one that never waits.
  • Improving a station that is not the constraint, and calling the extra work in process a result.
  • Comparing station times with each other and not with takt time. A line can have a slowest station and still meet demand.
  • Using one timed cycle, or the best one. Use the standard time and look at the spread.
  • Ignoring a close second. Within 5 percent, both are the constraint.
  • Forcing upstream stations to run flat out. It builds stock in front of the constraint and hides every problem.
  • Not checking again after a fix. The constraint moves, and so does the right buffer.
  • Treating the answer as permanent. A new product, a new shift pattern or a changed takt time can move it.

Where software helps

The arithmetic is small. The hard part is getting honest station times for every station and every product. LeanSuite's Time and Motion Study times each element from a video of the station, on a timeline you check against the footage. Line Balancing takes the times from a video of the line and draws the yamazumi against takt time. For a quick check, the bottleneck calculator is free.

FAQ

Questions about bottleneck analysis from a time study

  1. Time every station, divide the shift time by each station time, and find the smallest result. That station has the lowest capacity and is the bottleneck. Confirm on the floor: stations before it are blocked, stations after it are starved, and it never waits. If a second station is within about 5 percent, treat both as constraints.

  2. A bottleneck is a resource, usually a machine or station, whose capacity is below the demand placed on it. A constraint is anything that limits what the whole system can do. It can be a station, but it can also be a policy, a supplier or the market. Every bottleneck is a constraint, but not every constraint is a bottleneck.

  3. Compare each station's cycle time with takt time. A station whose time is longer than takt time cannot keep up with demand. The station with the longest time per piece is the bottleneck, and its capacity, shift time divided by cycle time, is the capacity of the line. Cycle times from a time study show good cycles, so confirm with observation.

  4. Identify the constraint, exploit it, subordinate everything else to that decision, elevate the constraint, and then go back to step one if the constraint has moved, without letting inertia build a new one. Exploit comes before elevate because it costs nothing: get the most from the constraint before adding money to it.

  5. Because every line has a slowest station, and when you speed one up the next slowest takes over. The gain from a fix is limited to the gap between the two. In the example on this page, wind went from 98 to 80 seconds, but assemble at 84 seconds became the constraint, so the line gained 46 pieces, not 62.

  6. It can point to one. A study gives the time per piece at each station, which is enough to call the likely constraint. It misses jams, changeovers, shared resources and variability between cycles, so confirm the result by watching who waits for whom. Where two stations are within about 5 percent of each other, the floor decides.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.