Skip to content
LeanSuite

Why do a time study? The eight decisions it feeds

Short answer

A time study tells you how long a job should take when a qualified person does it by the agreed method at a normal pace. That number, the standard time, is the input to eight decisions: cost, staffing, line balance, capacity, layout, ergonomics, pay and improvement.

The purpose of a time study is to replace opinion about how long a job takes with a measured standard time, and to see where the time inside the job goes. Every plan that involves labour starts from that number. Cost per unit is standard time x the labour rate. Operators needed is demand x standard time / minutes per shift. Capacity is minutes available / standard time. The element breakdown behind the standard shows the walking, waiting and awkward reaches to remove. Without a study, each of those decisions runs on a guess or on last year's average, which already contains last year's losses.

Last reviewed:

What is the purpose of a time study?

One standard time, eight decisions

Example numbers

Standard time

1.40 min

a valve: 1.25 x 1.00 x 1.12

1

Costing and quoting

1.40 / 60 x 30.00

0.70 of labour a valve

2

Staffing

1,200 x 1.40 / 480

3.5, so 4 operators

3

Line balance

75 s / 4 operators

18.75 s each, takt 22.5 s

4

Capacity

4 x 480 / 1.40

1,371 valves a shift

5

Layout

0.15 min walking x 1,200

180 minutes of walking a shift

6

Ergonomics

1 floor-level lift a cycle

1,200 lifts a shift

7

Incentives and performance

1,680 / 1,920 minutes

87.5 percent of standard

8

Continuous improvement

Rack to the bench: 0.168 min x 1,200

3.4 labour hours a shift saved

A hub. In the centre, a standard time of 1.40 minutes a valve. Around it, eight decisions, each with the sum that uses the standard and its answer: Costing and quoting: 0.70 of labour a valve; Staffing: 3.5, so 4 operators; Line balance: 18.75 s each, takt 22.5 s; Capacity: 1,371 valves a shift; Layout: 180 minutes of walking a shift; Ergonomics: 1,200 lifts a shift; Incentives and performance: 87.5 percent of standard; Continuous improvement: 3.4 labour hours a shift saved.

The numbers are the valve cell worked through below: 1.25 minutes observed, rating 100, allowance 12 percent, 1,200 valves a shift, 4 operators on 480 paid minutes. Eight people use this figure. It should be the same figure.

The purpose of a time study is to find out how long a job should take, in a way that other people can check. Not how long it took last Tuesday, and not how long the supervisor thinks it takes. How long it takes a trained person, following the agreed method, at a pace they can keep up all shift, with fair time added for personal needs, fatigue and small delays. That figure is the standard time.

A study gives you four things, and the standard is only the first.

  • The standard time: one number per unit, in minutes, that planning and costing can use.
  • The element breakdown: the job split into steps, each with its own time. This is where you see that 12 percent of the cycle is walking.
  • The method, written down: a standard is only valid for the method that was timed, so the study records that method.
  • A list of losses: the waits, searches, rework and awkward motions the observer saw. These are the improvement ideas.

Most of the value sits in what the number is then used for. The same standard time turns up in eight different decisions, usually made by eight different people who each wonder where the others got their figure.

The eight decisions a time study feeds

The eight decisions and what the time study supplies to each
DecisionThe questionWhat the study suppliesThe sum
1. Costing and quotingWhat does the labour in one unit cost? What do we quote?Standard time per unitStandard time x labour rate
2. StaffingHow many operators does this demand need?Standard time per unitDemand x standard time / paid minutes per operator
3. Line balanceWho does which elements so nobody is over takt?Element timesGroup elements so each operator's total is at or under takt
4. CapacityHow many can we make per shift? Can we take the order?Standard time per unitOperators x minutes per shift / standard time
5. LayoutWhere should parts, tools and people be?Time spent walking, reaching and fetching, by elementSeconds of movement x cycles per shift
6. ErgonomicsWhich motions will hurt someone if repeated all shift?How often and for how long each posture occursRepetitions per shift = units per shift x times per cycle
7. Incentives and performanceWhat is a fair day's work?Standard time per unit, agreed with the people it applies toStandard minutes earned / minutes worked
8. Continuous improvementWhat do we fix first, and did the fix work?Value-added and wasted time by element, before and afterSeconds removed x units per year

A note on each.

  • Costing and quoting. Labour cost per unit is the standard time multiplied by the labour rate. A quote built on a guess either loses the order or wins a job that loses money. The standard also sets the labour hours a budget should allow, which is what a labour variance is measured against.
  • Staffing. Demand multiplied by standard time gives the labour minutes a shift needs. Divide by the paid minutes of one operator and round up. The guide to how many operators you need works this through with takt.
  • Line balance. The element times, not the total, are what let you share work between stations. Line balancing and the yamazumi chart both start from a time study.
  • Capacity. Minutes available divided by standard time is the output a cell can promise. It answers whether an order fits before anyone commits to a date.
  • Layout. The breakdown shows how much of each cycle is walking and fetching. That tells you what a new layout is worth before you move a bench, and a spaghetti diagram shows where the steps go.
  • Ergonomics. A posture that scores badly matters more when it happens 1,200 times a shift than when it happens twice. The study supplies the frequency and duration that an ergonomic assessment needs, and the fatigue allowance in the standard depends on the same facts.
  • Incentives and performance. Where pay or a performance figure depends on output, the standard is the definition of 100 percent. This is the most sensitive use, and the reason a standard has to be accurate, agreed and open to challenge.
  • Continuous improvement. Elements sorted into value added and non value added show which labour losses are biggest. A second study after the change proves the gain in seconds instead of in opinion.

One standard, eight answers: a worked example

Illustrative example. A cell assembles a small valve. A time study of 30 cycles gives an average observed time of 1.25 minutes a unit. The operators were working at a normal pace, so the rating is 100 and the normal time is also 1.25 minutes. With an allowance of 12 percent, the standard time is 1.25 x 1.12 = 1.40 minutes a unit. The breakdown shows that 0.15 minutes of each cycle is walking to a parts rack.

The cell runs one shift of 480 paid minutes. Demand is 1,200 valves a shift. The loaded labour rate is 30.00 an hour.

Illustrative: one standard time of 1.40 minutes carried through the eight decisions
DecisionWorkingAnswer
Costing1.40 / 60 x 30.000.70 of labour in each valve
Quoting an order of 5,0005,000 x 1.40 / 60116.7 labour hours
Staffing1,200 x 1.40 = 1,680 standard minutes; 1,680 / 4803.5, so 4 operators
Line balance75 s of work content / 4 operators, against a takt of 22.5 s18.75 s each, 83 percent of takt
Capacity4 x 480 / 1.401,371 valves a shift at standard
Layout0.15 min of walking x 1,200 valves180 minutes of walking a shift, 12 percent of the work content
ErgonomicsOne lift of the valve body from a floor tote in every cycle1,200 lifts a shift, 300 for each operator if shared equally
Performance1,680 standard minutes earned / 1,920 minutes paid87.5 percent
ImprovementMove the rack to the bench: 1.10 x 1.12 = 1.232 min; saving 0.168 min x 1,200201.6 minutes, or 3.4 labour hours, a shift

Takt here is the 450 running minutes left after 30 minutes of breaks, divided by 1,200: 22.5 seconds. Staffing divides standard minutes by the full 480 paid minutes because the standard time already contains the allowances. Take breaks out of the time available as well and you count them twice.

What the standard shows about the cell: the load today, and the standard after the fix

Example numbers

Load today

Labour minutes

1,680 of 1,920 paid minutes

1,200 x 1.40 standard minutes earned, 4 x 480 paid.

Output

1,200 of 1,371 valves of capacity

Room for 171 more valves a shift with the same 4 people.

Before and after moving the rack

Before

standard 1.40 min

  • Working
  • Walking to the rack
  • Allowance, 12%

After

standard 1.232 min

  • Working
  • Allowance, 12%

Saving: 0.168 min x 1,200 = 201.6 minutes a shift

Two panels. First, load: the cell earns 1,680 standard minutes against 1,920 paid minutes, 87.5 percent, and makes 1,200 valves against a capacity of 1,371. Second, before and after moving the rack: the standard falls from 1.40 to 1.232 minutes because 0.15 minutes of walking is removed.

Both load bars read 87.5 percent because they are the same fact seen twice. The 171 valves of headroom and the 3.4 hours a shift from moving the rack are both invisible without the standard.

Read down the last column and the one study has answered the cost accountant, the planner, the supervisor, the layout engineer, the safety lead and the CI manager. It has also shown that the cell is loaded to 87.5 percent, so another 171 valves a shift fit without another person.

What you get wrong without one

A plant with no time standards still makes all eight decisions. It just makes them with whatever number is to hand, usually last year's output divided by last year's hours. That figure is real, but it is an average of good days and bad days, and it has every wait, search and rework of the old method inside it.

What each decision runs on when there is no time study, and what goes wrong
DecisionWhat gets used insteadWhat goes wrong
Costing and quotingA guess, or the time from a similar partQuotes that are too high lose work. Quotes that are too low win work that loses money, and nobody can say which jobs those are.
StaffingLast year's headcount, plus or minus oneOvertime in one cell and idle time in the next. Requests for people become arguments, because neither side has a number.
Line balanceWhoever is free does what is leftOne station is always behind and the rest wait for it. The line runs at the pace of its slowest station.
CapacityThe best shift anyone remembersDelivery dates promised on output the cell reaches once a month.
LayoutWhere the bench has always beenMoney spent on a new layout with no way to say what it was worth.
ErgonomicsA posture check on one cycleA risk score with no idea how many times a shift the posture occurs.
Incentives and performanceOutput against a target somebody choseTargets people see as arbitrary, because they are. Trust goes first.
Continuous improvementThe loudest complaintEffort spent on what annoys people, not on what costs the most time. No baseline to prove a gain.

What a small error costs

Take the valve cell again and suppose the standard in use is 5 percent too generous: 1.47 minutes where the job needs 1.40. The difference is 0.07 minutes a valve. At 1,200 valves a shift over 240 working days, that is 0.07 x 1,200 x 240 = 20,160 minutes, or 336 labour hours a year, planned and paid for and not needed. A standard that is 5 percent too tight is no better: the cell misses its plan by the same 336 hours and somebody is blamed for it.

A few hours of study against a year of a wrong standard

Example numbers

One careful study

5 hours, once

A standard 5 percent out

336 hours, every year

Two bars on one scale. The study: about 5 analyst hours, once. A standard that is 5 percent out: 336 labour hours every year.

0.07 min x 1,200 valves x 240 days = 20,160 minutes, or 336 hours a year. The 5 hours is the stopwatch study in the cost table below. On a job that runs twice a year the bars swap, and an estimate is the right tool.

The study that would have found the error takes a few hours. That ratio, a few hours against a few hundred, is the whole business case for measuring a high-volume job properly.

When a time study is the wrong tool

A time study suits one kind of work: a manual job that exists today, repeats, and has a cycle short enough to watch a good number of times. Outside that, another method is cheaper, more accurate or the only one possible.

Which way to measure: six questions before you reach for a stopwatch

  1. 1

    Does the job exist today?

    No
    Predetermined time system (MTM, MOST), standard data from similar jobs, or a timed mock-up
    Yes
  2. 2

    Will it ever repeat?

    No
    An estimate by someone who knows the work
    Yes
  3. 3

    Does a machine set the pace?

    Yes
    Machine data for the automatic cycle. Time study only for the load and unload
    No
  4. 4

    Is the work long, irregular or spread over many people?

    Yes
    Work sampling
    No
  5. 5

    Is the cycle only a few seconds, at very high volume?

    Yes
    Predetermined time system, or frame-by-frame video
    No
  6. 6

    Is it one of a family of parts you have already studied?

    Yes
    Standard data from your own element times
    No
  7. Time study: time the job directly, by stopwatch or from video

A decision flow of six questions asked in order. Does the job exist today? If no: Predetermined time system (MTM, MOST), standard data from similar jobs, or a timed mock-up. Will it ever repeat? If no: An estimate by someone who knows the work. Does a machine set the pace? If yes: Machine data for the automatic cycle. Time study only for the load and unload. Is the work long, irregular or spread over many people? If yes: Work sampling. Is the cycle only a few seconds, at very high volume? If yes: Predetermined time system, or frame-by-frame video. Is it one of a family of parts you have already studied? If yes: Standard data from your own element times. If none of the exits apply, use a time study.

Ask the questions from the top. The first exit you hit is the method. A time study is what is left: a manual job that exists, repeats, and has a cycle you can watch many times.
When to use something other than a time study
The situationWhy a time study strugglesUse this
The job does not exist yet: a new product, a quote, a line being designedThere is nothing to timeA predetermined time system such as MTM or MOST, standard data from similar jobs, or a timed mock-up
The work is long and irregular: maintenance, material handling, setters, team leadersNo short cycle. Weeks of watching to see every task onceWork sampling
The question is where a department's time goes, not how long one job takesOne observer can time one job, not forty peopleWork sampling
The machine sets the pace: an automatic cycle with the operator loading and watchingThe cycle is whatever the machine does. A stopwatch adds nothing to the counterMachine and system data for the cycle, with a time study only for the load and unload
Very short cycles at very high volume, a few seconds eachToo fast to read by eye, and a rating error is multiplied by millionsA predetermined time system, or frame-by-frame video
A family of similar parts that differ in size or countStudying each one repeats the same elementsStandard data built once from your own studies
A one-off job that will never repeatThe study costs more than the jobAn estimate by someone who knows the work
The method is still changing every weekThe standard is out of date before it is issuedFix the method first. Time it roughly as a baseline if you need one.

The guide to [time study vs work sampling](/learn/time-study-vs-work-sampling) goes through that one choice in detail.

Two more cases are about people, not technique. Do not run a study to build a case against one person. That is a performance conversation, and a stopwatch makes it worse. And do not run one in secret. A standard nobody was told about will not be accepted, and where there is a union agreement it may not be allowed. How to plan a time study covers what to say and to whom.

What a time study costs: by stopwatch and from video

A time study costs analyst hours, and a little of the operator's goodwill. No equipment to speak of. So the honest way to compare ways of doing one is to ask where the hours go. The table below does that for the valve job: a 1.25 minute cycle, 30 cycles, so 37.5 minutes of running work to capture.

Illustrative: where an analyst's hours go in one study (assumed hours, not measurements)
TaskStopwatch on the floorVideo, marked by handVideo, marked by software
Plan the study, brief the team, set up1.5 h1.5 h1.5 h
Capture 30 cycles, with stops and waiting1.0 h at the station0.75 h filming0.75 h filming
Turn the capture into element times1.5 h working up the readings2.5 h replaying to mark every break point1.0 h reviewing and correcting
Rate, add allowances, check outliersIncluded above0.5 hIncluded above
Write up the method and the report1.0 h1.0 h0.5 h
Total5.0 h6.25 h3.75 h

Assumptions for a simple job. Marking by hand is taken as four times the running length of the footage (37.5 minutes x 4 = 2.5 hours). Put your own hours in. The pattern matters more than the totals.

Where the analyst's hours go in one study

Example numbers
  • Plan and brief
  • Capture the cycles
  • Turn into element times
  • Rate and add allowances
  • Write up

Stopwatch on the floor

5 hours

Plan and brief: 1.5 hours
Capture the cycles: 1 hours
Turn into element times: 1.5 hours
Write up: 1 hours

Video, marked by hand

6.25 hours

Plan and brief: 1.5 hours
Capture the cycles: 0.75 hours
Turn into element times: 2.5 hours
Rate and add allowances: 0.5 hours
Write up: 1 hours

Video, marked by software

3.75 hours

Plan and brief: 1.5 hours
Capture the cycles: 0.75 hours
Turn into element times: 1 hours
Write up: 0.5 hours

Three stacked bars on one scale. Stopwatch on the floor: 5 hours. Video, marked by hand: 6.25 hours. Video, marked by software: 3.75 hours. Planning and briefing is 1.5 hours in all three. The largest difference is the step that turns the capture into element times: 1.5, 2.5 and 1.0 hours.

Assumed hours for a 1.25 minute job timed over 30 cycles, the same as the table above. The left block never shrinks. The dark block is where the three ways differ. Where rating is not shown, it is inside the dark block.

Three things stand out, whatever hours you use.

  • Planning and briefing do not shrink. The talk with the operators and the check that the method is stable take the same time with a watch or a camera. Skip them and the rest is wasted.
  • Video marked by hand is slower than a stopwatch, not faster. What you buy with the extra time is evidence: every reading can be replayed, checked by someone else, and shown to the operator.
  • The saving from software is in the middle of the job, turning footage into element times. It moves the engineer from marking break points to checking them.

The costs that are not in the table

  • A second use of the same capture. A stopwatch study gives element times and nothing else. Footage of the same cycles can also feed a line balance, a posture score and a work instruction, with no second visit to the station.
  • The re-study. When the method changes, the stopwatch study starts again from nothing. With video you film the changed job and compare.
  • The dispute. If an operator challenges a stopwatch reading, it is one person's word against another's. If they challenge a video study, you watch the clip together.
  • The standard you never set. The real cost in most plants is the jobs nobody has time to study, which run for years on an estimate.

Whether five hours is a lot depends on what the standard governs. Spread over the 336 labour hours a year that a 5 percent error costs on the valve cell, it is small. For a job that runs twice a year, it is too much, and an estimate will do.

Where in a plant time studies are used

Where time studies are used on a plant, and what they feed
AreaWhat gets timedWhat it is used forWatch for
Manual assemblyEach operator's elements, station by stationLine balance, staffing, cost per unitModel mix: time the high runner and the hardest variant
Machining and mouldingLoad, unload, inspect, deburr and walk between machines. The automatic cycle comes from the machineHow many machines one operator can run; the standard work combination tableDo not rate a machine. Only the manual elements get a pace rating
Packing and end of lineCarton build, fill, label, palletizeStaffing against line speed, pack costWaiting for product is a line problem. Record it as a delay, not as packing
Warehouse and kittingPick, travel, scan, put away, per line or per totePick rates, route design, headcount by volumeTravel dominates and varies. Sampling may suit the whole area better
ChangeoversEvery step from last good part to first good partSMED: splitting internal from external workIt is one long cycle, not a repeating one. Film it
Inspection and testHandling, measuring and recording, per part or per sampleInspection cost and staffingSearch and paperwork time is often larger than measuring
Material handlingRoutes for a tugger or water spider, stop by stopRoute timing and frequencyIrregular work. Time the route, sample the rest
MaintenanceRepeating planned tasks such as a lubrication routePlanned hours on a job planRepairs do not repeat. Use estimates or sampling

The people side of the purpose

Operators have good reason to ask why a study is being done. For a century the answer was often to cut the rate or the headcount, and people remember. An operator who suspects that will, quite sensibly, not show you their normal pace. So the purpose has to be said out loud, before the study, by someone they believe.

  • Name the decision. Say we are quoting a new part and need the real time, or we want to move the rack and need to know what the walk costs. A vague purpose sounds like a hidden one.
  • Say what it will not be used for, and only if that is true. If the study will not affect pay or headcount, say so plainly. If it might, do not pretend.
  • Study the job, not the person. The standard is for a qualified worker at a normal pace, not a judgement of whoever happened to be on shift.
  • Share the result with the people who were timed, first. Show them the element breakdown and ask what is wrong with it. They will know.

The script for that talk, and what never to say, is in how to plan a time study. The wider skill is in the guides to resistance to change on the shop floor and difficult conversations at work.

Doing more of them

The limit on time studies in most plants is not belief in them. It is engineer hours. That is why the jobs with standards are the ones studied years ago, and the new ones run on estimates.

LeanSuite's time and motion study works from a video you record and upload. It times every element on a timeline linked to the footage and splits the time into value-added, necessary and waste, for an engineer to review and certify. The same recording can feed a line balance and an ergonomic study, which is several of the eight decisions from one visit to the station.

Templates and tools

Time and motion study software

Run a time study in LeanSuite

Time and motion study software that works from phone video: LeanSuite times every element, gives cycle and standard time, and draws a Yamazumi chart.

FAQ

Questions about why do a time study

  1. The purpose of a time study is to set how long a job should take a qualified worker at a normal pace, as a measured standard time, and to see where the time inside the job goes. The standard feeds costing, staffing, line balancing and capacity planning. The element breakdown shows the walking, waiting and awkward motions to remove.

  2. A time study is watching a job being done, timing each step over a number of cycles, and working out how long the whole job should take. The observer adjusts for whether the person was working faster or slower than normal and adds time for breaks and small delays. The result is one number, the standard time per unit.

  3. Eight decisions: costing and quoting, staffing, line balancing, capacity planning, workstation layout, ergonomic reviews, incentive or performance schemes, and continuous improvement. Each one needs either the standard time per unit or the times of the elements inside it. A plant without studies still makes all eight decisions, using estimates or last year's averages.

  4. When the job does not exist yet, use a predetermined time system or data from similar jobs. When the work is long and irregular, such as maintenance, use work sampling. When a machine sets the pace, use machine data for the cycle. When a job will never repeat, use an estimate. And never run one in secret or to build a case against one person.

  5. It depends on the cycle length and the number of cycles, but for a short repeating job most of the time is not the timing. Planning and briefing the team, working up the readings and writing up the method usually take longer than the observation. In the illustrative study on this page, 37.5 minutes of running work takes about 5 analyst hours in all.

  6. An engineer films an assembly operator for 30 cycles, splits the job into elements and finds an average of 1.25 minutes a unit, of which 0.15 minutes is walking to a parts rack. With a 12 percent allowance the standard is 1.40 minutes. Moving the rack to the bench cuts it to 1.232 minutes, which at 1,200 units a shift saves 3.4 labour hours.

  7. Decide what the result will be used for, fix and write down the method first, pick a trained operator working at a normal pace, tell them and their supervisor why, break the job into elements, time enough cycles, rate the pace, add allowances, and share the result with the people who were timed before it is used.

  8. No. Work study is the wider field. It covers method study, which improves the way a job is done, and work measurement, which sets how long it should take. Time study is one technique of work measurement, alongside work sampling and predetermined time systems. A time study on its own measures a method without improving it.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.