Why do a time study? The eight decisions it feeds
Short answer
A time study tells you how long a job should take when a qualified person does it by the agreed method at a normal pace. That number, the standard time, is the input to eight decisions: cost, staffing, line balance, capacity, layout, ergonomics, pay and improvement.
The purpose of a time study is to replace opinion about how long a job takes with a measured standard time, and to see where the time inside the job goes. Every plan that involves labour starts from that number. Cost per unit is standard time x the labour rate. Operators needed is demand x standard time / minutes per shift. Capacity is minutes available / standard time. The element breakdown behind the standard shows the walking, waiting and awkward reaches to remove. Without a study, each of those decisions runs on a guess or on last year's average, which already contains last year's losses.
Last reviewed:
What is the purpose of a time study?
One standard time, eight decisions
Example numbersStandard time
1.40 min
a valve: 1.25 x 1.00 x 1.12
Costing and quoting
1.40 / 60 x 30.00
0.70 of labour a valve
Staffing
1,200 x 1.40 / 480
3.5, so 4 operators
Line balance
75 s / 4 operators
18.75 s each, takt 22.5 s
Capacity
4 x 480 / 1.40
1,371 valves a shift
Layout
0.15 min walking x 1,200
180 minutes of walking a shift
Ergonomics
1 floor-level lift a cycle
1,200 lifts a shift
Incentives and performance
1,680 / 1,920 minutes
87.5 percent of standard
Continuous improvement
Rack to the bench: 0.168 min x 1,200
3.4 labour hours a shift saved
A hub. In the centre, a standard time of 1.40 minutes a valve. Around it, eight decisions, each with the sum that uses the standard and its answer: Costing and quoting: 0.70 of labour a valve; Staffing: 3.5, so 4 operators; Line balance: 18.75 s each, takt 22.5 s; Capacity: 1,371 valves a shift; Layout: 180 minutes of walking a shift; Ergonomics: 1,200 lifts a shift; Incentives and performance: 87.5 percent of standard; Continuous improvement: 3.4 labour hours a shift saved.
The purpose of a time study is to find out how long a job should take, in a way that other people can check. Not how long it took last Tuesday, and not how long the supervisor thinks it takes. How long it takes a trained person, following the agreed method, at a pace they can keep up all shift, with fair time added for personal needs, fatigue and small delays. That figure is the standard time.
A study gives you four things, and the standard is only the first.
- The standard time: one number per unit, in minutes, that planning and costing can use.
- The element breakdown: the job split into steps, each with its own time. This is where you see that 12 percent of the cycle is walking.
- The method, written down: a standard is only valid for the method that was timed, so the study records that method.
- A list of losses: the waits, searches, rework and awkward motions the observer saw. These are the improvement ideas.
Most of the value sits in what the number is then used for. The same standard time turns up in eight different decisions, usually made by eight different people who each wonder where the others got their figure.
The eight decisions a time study feeds
| Decision | The question | What the study supplies | The sum |
|---|---|---|---|
| 1. Costing and quoting | What does the labour in one unit cost? What do we quote? | Standard time per unit | Standard time x labour rate |
| 2. Staffing | How many operators does this demand need? | Standard time per unit | Demand x standard time / paid minutes per operator |
| 3. Line balance | Who does which elements so nobody is over takt? | Element times | Group elements so each operator's total is at or under takt |
| 4. Capacity | How many can we make per shift? Can we take the order? | Standard time per unit | Operators x minutes per shift / standard time |
| 5. Layout | Where should parts, tools and people be? | Time spent walking, reaching and fetching, by element | Seconds of movement x cycles per shift |
| 6. Ergonomics | Which motions will hurt someone if repeated all shift? | How often and for how long each posture occurs | Repetitions per shift = units per shift x times per cycle |
| 7. Incentives and performance | What is a fair day's work? | Standard time per unit, agreed with the people it applies to | Standard minutes earned / minutes worked |
| 8. Continuous improvement | What do we fix first, and did the fix work? | Value-added and wasted time by element, before and after | Seconds removed x units per year |
A note on each.
- Costing and quoting. Labour cost per unit is the standard time multiplied by the labour rate. A quote built on a guess either loses the order or wins a job that loses money. The standard also sets the labour hours a budget should allow, which is what a labour variance is measured against.
- Staffing. Demand multiplied by standard time gives the labour minutes a shift needs. Divide by the paid minutes of one operator and round up. The guide to how many operators you need works this through with takt.
- Line balance. The element times, not the total, are what let you share work between stations. Line balancing and the yamazumi chart both start from a time study.
- Capacity. Minutes available divided by standard time is the output a cell can promise. It answers whether an order fits before anyone commits to a date.
- Layout. The breakdown shows how much of each cycle is walking and fetching. That tells you what a new layout is worth before you move a bench, and a spaghetti diagram shows where the steps go.
- Ergonomics. A posture that scores badly matters more when it happens 1,200 times a shift than when it happens twice. The study supplies the frequency and duration that an ergonomic assessment needs, and the fatigue allowance in the standard depends on the same facts.
- Incentives and performance. Where pay or a performance figure depends on output, the standard is the definition of 100 percent. This is the most sensitive use, and the reason a standard has to be accurate, agreed and open to challenge.
- Continuous improvement. Elements sorted into value added and non value added show which labour losses are biggest. A second study after the change proves the gain in seconds instead of in opinion.
One standard, eight answers: a worked example
Illustrative example. A cell assembles a small valve. A time study of 30 cycles gives an average observed time of 1.25 minutes a unit. The operators were working at a normal pace, so the rating is 100 and the normal time is also 1.25 minutes. With an allowance of 12 percent, the standard time is 1.25 x 1.12 = 1.40 minutes a unit. The breakdown shows that 0.15 minutes of each cycle is walking to a parts rack.
The cell runs one shift of 480 paid minutes. Demand is 1,200 valves a shift. The loaded labour rate is 30.00 an hour.
| Decision | Working | Answer |
|---|---|---|
| Costing | 1.40 / 60 x 30.00 | 0.70 of labour in each valve |
| Quoting an order of 5,000 | 5,000 x 1.40 / 60 | 116.7 labour hours |
| Staffing | 1,200 x 1.40 = 1,680 standard minutes; 1,680 / 480 | 3.5, so 4 operators |
| Line balance | 75 s of work content / 4 operators, against a takt of 22.5 s | 18.75 s each, 83 percent of takt |
| Capacity | 4 x 480 / 1.40 | 1,371 valves a shift at standard |
| Layout | 0.15 min of walking x 1,200 valves | 180 minutes of walking a shift, 12 percent of the work content |
| Ergonomics | One lift of the valve body from a floor tote in every cycle | 1,200 lifts a shift, 300 for each operator if shared equally |
| Performance | 1,680 standard minutes earned / 1,920 minutes paid | 87.5 percent |
| Improvement | Move the rack to the bench: 1.10 x 1.12 = 1.232 min; saving 0.168 min x 1,200 | 201.6 minutes, or 3.4 labour hours, a shift |
Takt here is the 450 running minutes left after 30 minutes of breaks, divided by 1,200: 22.5 seconds. Staffing divides standard minutes by the full 480 paid minutes because the standard time already contains the allowances. Take breaks out of the time available as well and you count them twice.
What the standard shows about the cell: the load today, and the standard after the fix
Example numbersLoad today
Labour minutes
1,680 of 1,920 paid minutes
1,200 x 1.40 standard minutes earned, 4 x 480 paid.
Output
1,200 of 1,371 valves of capacity
Room for 171 more valves a shift with the same 4 people.
Before and after moving the rack
Before
standard 1.40 min
- Working
- Walking to the rack
- Allowance, 12%
After
standard 1.232 min
- Working
- Allowance, 12%
Saving: 0.168 min x 1,200 = 201.6 minutes a shift
Two panels. First, load: the cell earns 1,680 standard minutes against 1,920 paid minutes, 87.5 percent, and makes 1,200 valves against a capacity of 1,371. Second, before and after moving the rack: the standard falls from 1.40 to 1.232 minutes because 0.15 minutes of walking is removed.
Read down the last column and the one study has answered the cost accountant, the planner, the supervisor, the layout engineer, the safety lead and the CI manager. It has also shown that the cell is loaded to 87.5 percent, so another 171 valves a shift fit without another person.
What you get wrong without one
A plant with no time standards still makes all eight decisions. It just makes them with whatever number is to hand, usually last year's output divided by last year's hours. That figure is real, but it is an average of good days and bad days, and it has every wait, search and rework of the old method inside it.
| Decision | What gets used instead | What goes wrong |
|---|---|---|
| Costing and quoting | A guess, or the time from a similar part | Quotes that are too high lose work. Quotes that are too low win work that loses money, and nobody can say which jobs those are. |
| Staffing | Last year's headcount, plus or minus one | Overtime in one cell and idle time in the next. Requests for people become arguments, because neither side has a number. |
| Line balance | Whoever is free does what is left | One station is always behind and the rest wait for it. The line runs at the pace of its slowest station. |
| Capacity | The best shift anyone remembers | Delivery dates promised on output the cell reaches once a month. |
| Layout | Where the bench has always been | Money spent on a new layout with no way to say what it was worth. |
| Ergonomics | A posture check on one cycle | A risk score with no idea how many times a shift the posture occurs. |
| Incentives and performance | Output against a target somebody chose | Targets people see as arbitrary, because they are. Trust goes first. |
| Continuous improvement | The loudest complaint | Effort spent on what annoys people, not on what costs the most time. No baseline to prove a gain. |
What a small error costs
Take the valve cell again and suppose the standard in use is 5 percent too generous: 1.47 minutes where the job needs 1.40. The difference is 0.07 minutes a valve. At 1,200 valves a shift over 240 working days, that is 0.07 x 1,200 x 240 = 20,160 minutes, or 336 labour hours a year, planned and paid for and not needed. A standard that is 5 percent too tight is no better: the cell misses its plan by the same 336 hours and somebody is blamed for it.
A few hours of study against a year of a wrong standard
Example numbersOne careful study
5 hours, once
A standard 5 percent out
336 hours, every year
Two bars on one scale. The study: about 5 analyst hours, once. A standard that is 5 percent out: 336 labour hours every year.
The study that would have found the error takes a few hours. That ratio, a few hours against a few hundred, is the whole business case for measuring a high-volume job properly.
When a time study is the wrong tool
A time study suits one kind of work: a manual job that exists today, repeats, and has a cycle short enough to watch a good number of times. Outside that, another method is cheaper, more accurate or the only one possible.
Which way to measure: six questions before you reach for a stopwatch
- 1
Does the job exist today?
NoPredetermined time system (MTM, MOST), standard data from similar jobs, or a timed mock-upYes - 2
Will it ever repeat?
NoAn estimate by someone who knows the workYes - 3
Does a machine set the pace?
YesMachine data for the automatic cycle. Time study only for the load and unloadNo - 4
Is the work long, irregular or spread over many people?
YesWork samplingNo - 5
Is the cycle only a few seconds, at very high volume?
YesPredetermined time system, or frame-by-frame videoNo - 6
Is it one of a family of parts you have already studied?
YesStandard data from your own element timesNo Time study: time the job directly, by stopwatch or from video
A decision flow of six questions asked in order. Does the job exist today? If no: Predetermined time system (MTM, MOST), standard data from similar jobs, or a timed mock-up. Will it ever repeat? If no: An estimate by someone who knows the work. Does a machine set the pace? If yes: Machine data for the automatic cycle. Time study only for the load and unload. Is the work long, irregular or spread over many people? If yes: Work sampling. Is the cycle only a few seconds, at very high volume? If yes: Predetermined time system, or frame-by-frame video. Is it one of a family of parts you have already studied? If yes: Standard data from your own element times. If none of the exits apply, use a time study.
| The situation | Why a time study struggles | Use this |
|---|---|---|
| The job does not exist yet: a new product, a quote, a line being designed | There is nothing to time | A predetermined time system such as MTM or MOST, standard data from similar jobs, or a timed mock-up |
| The work is long and irregular: maintenance, material handling, setters, team leaders | No short cycle. Weeks of watching to see every task once | Work sampling |
| The question is where a department's time goes, not how long one job takes | One observer can time one job, not forty people | Work sampling |
| The machine sets the pace: an automatic cycle with the operator loading and watching | The cycle is whatever the machine does. A stopwatch adds nothing to the counter | Machine and system data for the cycle, with a time study only for the load and unload |
| Very short cycles at very high volume, a few seconds each | Too fast to read by eye, and a rating error is multiplied by millions | A predetermined time system, or frame-by-frame video |
| A family of similar parts that differ in size or count | Studying each one repeats the same elements | Standard data built once from your own studies |
| A one-off job that will never repeat | The study costs more than the job | An estimate by someone who knows the work |
| The method is still changing every week | The standard is out of date before it is issued | Fix the method first. Time it roughly as a baseline if you need one. |
The guide to [time study vs work sampling](/learn/time-study-vs-work-sampling) goes through that one choice in detail.
Two more cases are about people, not technique. Do not run a study to build a case against one person. That is a performance conversation, and a stopwatch makes it worse. And do not run one in secret. A standard nobody was told about will not be accepted, and where there is a union agreement it may not be allowed. How to plan a time study covers what to say and to whom.
What a time study costs: by stopwatch and from video
A time study costs analyst hours, and a little of the operator's goodwill. No equipment to speak of. So the honest way to compare ways of doing one is to ask where the hours go. The table below does that for the valve job: a 1.25 minute cycle, 30 cycles, so 37.5 minutes of running work to capture.
| Task | Stopwatch on the floor | Video, marked by hand | Video, marked by software |
|---|---|---|---|
| Plan the study, brief the team, set up | 1.5 h | 1.5 h | 1.5 h |
| Capture 30 cycles, with stops and waiting | 1.0 h at the station | 0.75 h filming | 0.75 h filming |
| Turn the capture into element times | 1.5 h working up the readings | 2.5 h replaying to mark every break point | 1.0 h reviewing and correcting |
| Rate, add allowances, check outliers | Included above | 0.5 h | Included above |
| Write up the method and the report | 1.0 h | 1.0 h | 0.5 h |
| Total | 5.0 h | 6.25 h | 3.75 h |
Assumptions for a simple job. Marking by hand is taken as four times the running length of the footage (37.5 minutes x 4 = 2.5 hours). Put your own hours in. The pattern matters more than the totals.
Where the analyst's hours go in one study
Example numbers- Plan and brief
- Capture the cycles
- Turn into element times
- Rate and add allowances
- Write up
Stopwatch on the floor
5 hours
Video, marked by hand
6.25 hours
Video, marked by software
3.75 hours
Three stacked bars on one scale. Stopwatch on the floor: 5 hours. Video, marked by hand: 6.25 hours. Video, marked by software: 3.75 hours. Planning and briefing is 1.5 hours in all three. The largest difference is the step that turns the capture into element times: 1.5, 2.5 and 1.0 hours.
Three things stand out, whatever hours you use.
- Planning and briefing do not shrink. The talk with the operators and the check that the method is stable take the same time with a watch or a camera. Skip them and the rest is wasted.
- Video marked by hand is slower than a stopwatch, not faster. What you buy with the extra time is evidence: every reading can be replayed, checked by someone else, and shown to the operator.
- The saving from software is in the middle of the job, turning footage into element times. It moves the engineer from marking break points to checking them.
The costs that are not in the table
- A second use of the same capture. A stopwatch study gives element times and nothing else. Footage of the same cycles can also feed a line balance, a posture score and a work instruction, with no second visit to the station.
- The re-study. When the method changes, the stopwatch study starts again from nothing. With video you film the changed job and compare.
- The dispute. If an operator challenges a stopwatch reading, it is one person's word against another's. If they challenge a video study, you watch the clip together.
- The standard you never set. The real cost in most plants is the jobs nobody has time to study, which run for years on an estimate.
Whether five hours is a lot depends on what the standard governs. Spread over the 336 labour hours a year that a 5 percent error costs on the valve cell, it is small. For a job that runs twice a year, it is too much, and an estimate will do.
Where in a plant time studies are used
| Area | What gets timed | What it is used for | Watch for |
|---|---|---|---|
| Manual assembly | Each operator's elements, station by station | Line balance, staffing, cost per unit | Model mix: time the high runner and the hardest variant |
| Machining and moulding | Load, unload, inspect, deburr and walk between machines. The automatic cycle comes from the machine | How many machines one operator can run; the standard work combination table | Do not rate a machine. Only the manual elements get a pace rating |
| Packing and end of line | Carton build, fill, label, palletize | Staffing against line speed, pack cost | Waiting for product is a line problem. Record it as a delay, not as packing |
| Warehouse and kitting | Pick, travel, scan, put away, per line or per tote | Pick rates, route design, headcount by volume | Travel dominates and varies. Sampling may suit the whole area better |
| Changeovers | Every step from last good part to first good part | SMED: splitting internal from external work | It is one long cycle, not a repeating one. Film it |
| Inspection and test | Handling, measuring and recording, per part or per sample | Inspection cost and staffing | Search and paperwork time is often larger than measuring |
| Material handling | Routes for a tugger or water spider, stop by stop | Route timing and frequency | Irregular work. Time the route, sample the rest |
| Maintenance | Repeating planned tasks such as a lubrication route | Planned hours on a job plan | Repairs do not repeat. Use estimates or sampling |
The people side of the purpose
Operators have good reason to ask why a study is being done. For a century the answer was often to cut the rate or the headcount, and people remember. An operator who suspects that will, quite sensibly, not show you their normal pace. So the purpose has to be said out loud, before the study, by someone they believe.
- Name the decision. Say we are quoting a new part and need the real time, or we want to move the rack and need to know what the walk costs. A vague purpose sounds like a hidden one.
- Say what it will not be used for, and only if that is true. If the study will not affect pay or headcount, say so plainly. If it might, do not pretend.
- Study the job, not the person. The standard is for a qualified worker at a normal pace, not a judgement of whoever happened to be on shift.
- Share the result with the people who were timed, first. Show them the element breakdown and ask what is wrong with it. They will know.
The script for that talk, and what never to say, is in how to plan a time study. The wider skill is in the guides to resistance to change on the shop floor and difficult conversations at work.
Doing more of them
The limit on time studies in most plants is not belief in them. It is engineer hours. That is why the jobs with standards are the ones studied years ago, and the new ones run on estimates.
LeanSuite's time and motion study works from a video you record and upload. It times every element on a timeline linked to the footage and splits the time into value-added, necessary and waste, for an engineer to review and certify. The same recording can feed a line balance and an ergonomic study, which is several of the eight decisions from one visit to the station.
Templates and tools
- Time study sheet: elements, cycles, rating and allowances on one page.
- Operator staffing calculator: from demand and work content to headcount.
- Process capacity sheet: what each process can make in a shift.
- Yamazumi operator balance chart: element times stacked against takt.
- Time study sample size calculator: how many cycles to time.
- Takt time calculator and line balancing calculator.
Time and motion study software
Run a time study in LeanSuite
Time and motion study software that works from phone video: LeanSuite times every element, gives cycle and standard time, and draws a Yamazumi chart.
Go deeper
This page is the short version. These guides cover each part in full.
- How to Improve Shop Floor ProductivityWhat to do about the losses once a study has put a time on them.
- How to Improve Production Efficiency: 7 Practical WaysThe other levers on output, next to labour time.
- The Three Elements of Standard Work: Takt Time, Sequence and WIPWhere the element times go next: the work sequence loaded against takt.
- Manufacturing Bottleneck Elimination StrategiesUsing measured times to find and relieve the station that limits output.
All our articles on this subject are in the standard work, sops and training topic.
Free templates and tools
- Time study sheetTime each element over 10 cycles and work out the average, lowest repeatable and standard time. Excel does the sums.
- Operator staffing calculatorTakt, work content, the operators a line needs, a check of your station plan and the roster with absence cover, from your own demand and element times.
- Process capacity sheet templateEach machine in a part's routing with manual, auto and tool change time, its capacity per shift, and the step that limits the cell against demand.
- Standard work combination tableOne operator's manual, machine, walk and wait time on a time chart against takt, with machine cycles and a process capacity sheet.
- Time study sample size calculatorHow many cycles of an element to time, from your first readings, with the t formula, the ILO formula and the range method.
- Takt time calculatorThe pace a line must hit to meet customer demand, from shift time, breaks and daily demand.
- Line balancing calculatorLine efficiency, balance delay and the minimum number of stations from station times and takt.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
Doing this in LeanSuite
Time and Motion Study
Film the station and the AI times every element on a timeline that links to the video, split into value-added, necessary and waste.
See Time and Motion StudyLine Balancing
Drop in a video of your line and get a Yamazumi chart, a takt comparison and rebalancing recommendations.
See Line BalancingErgonomic Study
Maps 18 body joints from video, scores REBA and RULA automatically and flags the postures that need a fix.
See Ergonomic Study
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about why do a time study
The purpose of a time study is to set how long a job should take a qualified worker at a normal pace, as a measured standard time, and to see where the time inside the job goes. The standard feeds costing, staffing, line balancing and capacity planning. The element breakdown shows the walking, waiting and awkward motions to remove.
A time study is watching a job being done, timing each step over a number of cycles, and working out how long the whole job should take. The observer adjusts for whether the person was working faster or slower than normal and adds time for breaks and small delays. The result is one number, the standard time per unit.
Eight decisions: costing and quoting, staffing, line balancing, capacity planning, workstation layout, ergonomic reviews, incentive or performance schemes, and continuous improvement. Each one needs either the standard time per unit or the times of the elements inside it. A plant without studies still makes all eight decisions, using estimates or last year's averages.
When the job does not exist yet, use a predetermined time system or data from similar jobs. When the work is long and irregular, such as maintenance, use work sampling. When a machine sets the pace, use machine data for the cycle. When a job will never repeat, use an estimate. And never run one in secret or to build a case against one person.
It depends on the cycle length and the number of cycles, but for a short repeating job most of the time is not the timing. Planning and briefing the team, working up the readings and writing up the method usually take longer than the observation. In the illustrative study on this page, 37.5 minutes of running work takes about 5 analyst hours in all.
An engineer films an assembly operator for 30 cycles, splits the job into elements and finds an average of 1.25 minutes a unit, of which 0.15 minutes is walking to a parts rack. With a 12 percent allowance the standard is 1.40 minutes. Moving the rack to the bench cuts it to 1.232 minutes, which at 1,200 units a shift saves 3.4 labour hours.
Decide what the result will be used for, fix and write down the method first, pick a trained operator working at a normal pace, tell them and their supervisor why, break the job into elements, time enough cycles, rate the pace, add allowances, and share the result with the people who were timed before it is used.
No. Work study is the wider field. It covers method study, which improves the way a job is done, and work measurement, which sets how long it should take. Time study is one technique of work measurement, alongside work sampling and predetermined time systems. A time study on its own measures a method without improving it.
Related guides and tools
- Time and motion study: what it is, the steps and a worked example
- How to plan a time study: scope, operator, shift and the talk before it
- How to conduct a time study: the procedure step by step
- Standard time: observed, normal and standard time with the formula
- Time study vs work sampling: which to use
- How many operators do you need: work content divided by takt
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk
Or browse the topics, the full library and the lean glossary.
Rather see it on your own problem?
Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.