Permit to work (PTW): how the system works, types of permit and a worked example

Short answer

A permit to work is a written authorization for one job, in one place, for a limited time. It says the plant has been made safe and the precautions are in place, and it is issued before the work and closed after it.

A permit to work (PTW) is a documented procedure that lets named people do a specific job, within a set time, once the area has been made safe. The issuer goes to the job, checks that every energy source is isolated and proved, and signs. The permit holder accepts it, briefs the crew and works inside its limits. When the work ends the holder hands back, the issuer tests the plant, and the permit is cancelled. A permit does not describe the method. That is the job of the JSA or method statement it points to. General guidance, not legal advice: the rules differ by country and by type of work.

Last reviewed:

What is a permit to work?

A permit to work, PTW for short, is a controlled piece of paper (or screen) that sits between a plan and the start of the work. HSE in Great Britain describes it as a documented procedure that authorises certain people to carry out specific work within a specified time frame. It sets out the precautions, based on a risk assessment, and it can include a method statement.

It exists because some jobs are dangerous for a reason the crew cannot see: stored energy, a line that still holds product, another team working above. A permit forces one person who knows the plant to go to the job and confirm those things, and forces the people doing the work to say they understand the limits. It is also how an area stays aware of what is happening in it. HSE's human factors page makes the same point: a permit is communication between site management, supervisors, operators and the people doing the work, and it helps stop two jobs clashing.

Think of it as a gate. Planning documents describe how the work will be done. The permit decides whether it may start today, here, with these people, and it records who took the plant back when it ended.

A permit compared with the documents around it
DocumentQuestion it answersWhat the permit adds
JSA or SOPHow is this task done safely?The permit does not describe the method. It points to the JSA and checks the plant is ready for it.
SWMS or method statementHow will this high-risk job be done, step by step?The permit confirms the area is safe and is live only for a set period. See the safe work method statement guide.
Lockout tagout procedureHow is this machine's energy isolated?The permit lists the isolations for this job and requires proof that each worked. See lockout tagout.
Pre-task planWhat is different today?The pre-task plan is the crew's own briefing after the permit is accepted.
Stop work authorityCan anyone stop the job?A permit says what stops it. Stop work authority says nobody needs permission to do so.

A permit is a check that the precautions are in place. It does not replace the risk assessment, the JSA or the lockout procedure.

Which document works at which moment of a job

DocumentPlanning, days beforeStart of the jobDuring the workHand-back
JSA or SOPHow is this kind of task done safely?Write onceRead
SWMS or method statementHow will this high-risk job be done?Write for the jobBrief and signCheck the work against it
Permit to workIs the plant safe, and may the job start?RequestIssue at the jobHold, suspend, hand overHand back and cancel
Pre-task planWhat is different today?Brief the crew
Field level risk assessmentIs this step safe right now?Before each step

A table of five safety documents against four moments: planning, the start of the job, during the work and hand-back. The job safety analysis and the method statement are written in planning. The permit is requested in planning, issued at the start, held during the work and handed back at the end. The pre-task plan is a briefing at the start. The field level risk assessment is a check before each step.

The permit is the only document that spans the whole job: requested in planning, issued at the start, held while the work goes on and handed back at the end.

When a permit is needed, and the types of permit

HSE says permits are for work that needs extra care: hot work such as welding, entering vessels, cutting into pipework that has carried hazardous substances, and work needing electrical or mechanical isolation. The test is the same in any plant. Use a permit when the job is non-routine, needs isolations, involves more than one group, or is handed from one shift to the next.

  • Non-routine work: maintenance, repair, cleaning inside equipment, modification, testing, dismantling.
  • Work that needs isolations, or that two or more groups have to coordinate to do safely.
  • Work handed from one group or shift to another.
  • Not routine production work and not every small job. When everything needs a permit, people stop reading them.
Common types of work permit and what the rules say where we checked
PermitUsed forWhat it adds to a general permitWhat the US rule says
General work (cold work)Maintenance, repair, cleaning, anything needing isolation or coordinationIsolations, precautions, handover, handbackWe found no general permit-to-work requirement in the OSHA pages we read. The site sets its own system.
Hot workWelding, cutting, grinding, anything producing sparks or flameArea cleared and inspected, fire precautions, limited time29 CFR 1910.252(a)(2)(iv): the person responsible for authorizing cutting and welding inspects the area and designates the precautions, preferably in a written permit.
Confined space entryTanks, vessels, pits, silosAtmosphere tests, an attendant, a rescue arrangement29 CFR 1910.146: an entry permit is required for a permit-required confined space. The entry supervisor signs it before entry and cancels it when the work ends or a condition arises that it does not allow.
Work at heightRoofs, scaffolds, lifts, edgesAccess, edge protection, rescue, drop zoneSet by your fall protection rules and site policy.
ElectricalWork on or near energised or recently de-energised equipmentIsolation, proving dead, authorised persons onlySet by your electrical safety rules and site policy.
ExcavationDigging, trenches, trial holesBuried services located, edges and access controlledSet by your excavation rules and site policy.

OSHA regulations quoted from osha.gov on 28 November 2026. Other countries and states differ, and many sites also require a permit where the law does not. Read the rule that applies to your site.

Hot work and confined space permits do not replace the general permit when a job needs isolations as well. Link them: the general permit lists the numbers of the other permits for the same job, and each says it is not the whole story. See the hot work permit template and the confined space entry permit template.

Who does what

A permit needs at least two people who are not the same person. HSE's human factors page asks that roles and responsibilities are clear, with no important gaps or overlaps. Sites use different titles. These are the five roles that matter, whatever they are called.

The five roles in a permit system
RoleWhat they do
RequesterDescribes the work and its limits and attaches the JSA or SWMS.
IssuerKnows the plant. Goes to the job, checks isolations and precautions, issues the permit, visits during the work and takes the handback. Never issues a permit to themself.
Permit holderIn charge of the work. Briefs the crew, keeps to the limits, stops if anything changes, and hands back.
IsolatorMakes each isolation, locks or tags it and proves it. Signs the row.
EveryoneWorks only inside the permit, and stops the job if it cannot be done that way.

Roles follow the form in the permit-to-work template. Some sites use "issuing authority" and "performing authority" for the first two.

The figure maps those roles onto the six stages. The pattern to notice is that the issuer is the only person who is both at the start and at the end. That is what stops a permit being opened by one team and closed by whoever is left.

Who does what, stage by stage

Role1Request2Prepare3Issue4Work5Hand back6Cancel
Issuer (knows the plant)Goes to the job, checks isolations and precautionsSigns the issue at the jobVisits the job, may suspendTakes the handback, tests the plantCancels and updates the register
Permit holder (leads the work)Asks, with the JSA or SWMS attachedWalks the job with the issuerSigns acceptance, briefs the crewKeeps to the limits, stops if it changesClears the area, signs the handback
Isolator and crewIsolates, locks, tags and proves each sourceEach person fits a personal lockWorks only inside the permitEach removes their own lock

A grid of three roles against six stages of a permit: request, prepare, issue, work, hand back and cancel. The issuer prepares, issues, visits, takes the handback and cancels. The permit holder requests, accepts, works within limits and hands back. The isolator and crew isolate, fit locks and remove their own locks.

Two different people sign the issue and the acceptance. If one person fills both roles, the permit has checked nothing.

How a permit works, step by step

The same ten steps hold for a general permit, a hot work permit and a confined space permit. What changes is the checks inside steps 3 and 4.

Ten steps from request to cancellation

  1. 1

    Request and scope

  2. 2

    Check for clashes

  3. 3

    Isolate and prove

  4. 4

    Go to the job

  5. 5

    Issue

  6. 6

    Accept and brief

  7. 7

    Work, and suspend if it stops

  8. 8

    Hand over at a shift change or extension

  9. 9

    Hand back

  10. 10

    Test, cancel and return to service

Steps 3 and 4 are the ones a permit exists for: isolate and prove, then go and look. Steps 9 and 10 are separate on purpose.
  1. 1

    Request and scope

    The requester writes the work exactly, and the limits: what this permit does not cover. They attach the JSA or SWMS. Words like "maintenance on tank 3" are too wide. "Replace the agitator gearbox on T-3, no entry into the tank" is a permit.

  2. 2

    Check for clashes

    Look at the permit register and the board. Is anyone working above, below or on the same line? Is a hot work permit live nearby? A clash found here costs a phone call. Found on the day, it costs a stopped job.

  3. 3

    Isolate and prove

    The isolator isolates every energy source on the permit, locks or tags it and then tries it. A start button pressed with no result, a gauge read at zero, a valve cracked open and found dry. The result goes on the permit.

  4. 4

    Go to the job

    The issuer walks the job with the permit holder: the place, the equipment, the isolations on the plant, the precautions. This is the step that gets skipped when the issuer is busy, and it is the one a permit exists for.

  5. 5

    Issue

    The issuer signs that the isolations are made and tried, the precautions are in place and the work may start within the limits and times written. For work your site ranks as high hazard, a second authorizer signs first.

  6. 6

    Accept and brief

    The permit holder signs that they understand the work, the hazards and the limits, reads the permit to the crew at the job, and each person signs. Each person fits their own lock to the lock box. A copy is displayed at the job and a copy is kept where permits are issued.

  7. 7

    Work, and suspend if it stops

    The crew works inside the permit. If the job stops (wrong part, break, weather, an alarm), the holder writes the state the plant was left in and the permit is suspended. A suspended permit is still live: its isolations stay on, and it stays on the board.

  8. 8

    Hand over at a shift change or extension

    Work past the end time or across a shift needs a new declaration. Outgoing and incoming holders and the issuer check the isolations together on the plant. The incoming person locks on before the outgoing person's lock comes off.

  9. 9

    Hand back

    The holder says the work is complete or what is left, and in what state. Tools and waste are out, guards are back, everyone is clear and told the job is over, and each lock has been removed by the person who fitted it. The issuer signs the handback.

  10. 10

    Test, cancel and return to service

    The issuer, with the person taking the plant back, tests it: a test run, a leak check, a function test. Only then is the permit cancelled and the register updated. Handback and cancellation are two steps on purpose.

Isolation: the part that cannot be skipped

Illustrative example, used from here to the end of the guide. A maintenance crew replaces the agitator gearbox on mixing tank T-3. The gearbox weighs 85 kg (187 lb) and comes out on a chain hoist. The permit is PTW-0457, and it points to JSA-112.

Four energy sources are on the permit: the agitator motor, the steam jacket, the product inlet and the stored motion in the agitator shaft. Each gets four moves: isolate it, lock it, tag it, then try it. The fourth move is the one that matters. A line that reads "lock L-031" and nothing in the last column has been switched off, not proved. HSE's human factors page notes that failures during isolation and reinstatement of process plant are one of the main causes of loss-of-containment incidents. The lockout tagout guide goes through the machine side in more detail.

Isolation: four moves for every energy source, and the proof

Example numbers
1. Isolate2. Lock3. Tag4. Try
EnergyIsolation pointHow isolatedLock or tagZero-energy check: what was tried, and the result
ElectricalBreaker Q14 in MCC-2Opened, locked, taggedL-031Start button pressed: no start. Dead at the motor terminals.
SteamJacket supply valve V-12; bleed V-13V-12 closed and chained, V-13 openL-032Gauge reads 0. Bleed open, nothing flowing.
ProductTank inlet valve V-7Closed and lockedL-033Level gauge empty. Inlet drain open, nothing flowing.
Stored motionAgitator shaftShaft clamp fittedTag T-118Shaft pushed by hand: does not turn.

Four steps, isolate, lock, tag and try, then four rows from the example permit PTW-0457 listing each energy source on the tank agitator with its isolation point, how it was isolated, the lock or tag number and the zero-energy check that was tried.

The last column is the one to read first. A row with a lock number and no result in that column has not been isolated, only switched off.

Worked example: one permit across a suspension and a shift handover

The gearbox job did not go to plan. A hot work permit was needed for two seized bolts, a wrong part stopped the job at midday, and the shift changed in the middle. The table is what the permit and its register recorded. All names, numbers and times are made up.

PTW-0457: what happened and who signed (illustrative)
TimeWhat happenedWhoWhere it was written
07:00Issued at the job after the issuer saw the four isolations made and tried. Valid to 15:00.N. Osei, issuerIssue block
07:05Accepted. Crew of three briefed, each person's lock on lock box LB-2.K. Brandt, permit holderAcceptance block
08:00Hot work permit HW-0098 issued to cut two seized coupling bolts. Cancelled 09:45.N. Osei issues, K. Brandt holdsLinked permits line
12:15Suspended. The new coupling has the wrong bore. Gearbox out, shaft clamped and supported, opening covered, area barriered. All isolations left on.K. BrandtSuspension block
15:00Shift handover. Incoming holder and incoming issuer check every isolation on the plant. The incoming holder locks on to LB-2 before the outgoing locks come off. New end time 23:00.B. Mwangi, F. LindqvistHandover block
15:40Restart allowed after the issuer checked every isolation and the job. The correct coupling arrived at 15:25.F. LindqvistSuspension block
18:30Work complete. Tools out, guard fitted, locks removed by the people who fitted them. Issuer signs the handback at 18:50.B. Mwangi, F. LindqvistHandback block
19:10Test run for 15 minutes: no leaks, no unusual noise or vibration. Permit cancelled, register updated.F. LindqvistCancellation block

Times and names are from the worked example in the permit-to-work template.

One permit across a day: suspension, handover, handback

Example numbers
07:0009:0011:0013:0015:0017:0019:00
PTW-0457 gearbox
HW-0098 hot work
  • 07:05 Accepted, crew briefed
  • 09:45 Hot work cancelled
  • 12:15 Suspended: wrong coupling
  • 15:00 Shift handover, both at the plant
  • 15:40 Restart allowed
  • 18:30 Handback
  • 19:10 Cancelled after test run

Solid bar: permit live and work under way. Dashed bar: suspended, isolations still on.

Timeline from 07:00 to 19:30. Permit PTW-0457 runs from 07:00, is suspended from 12:15 to 15:40 with its isolations left on, then runs again until handback at 18:30. A hot work permit HW-0098 runs inside it from 08:00 to 09:45. The shift handover is at 15:00 during the suspension and the permit is cancelled at 19:10 after a test run.

The permit stayed live while suspended: every lock stayed on. The hot work permit was a separate permit that ended before the main job did.

Three things in this record are the permit doing its job. The suspension kept the isolations on for three and a half hours while nobody was working, so the next person to look at the tank was not surprised. The handover was done at the plant, not over the phone, and the order of the locks left nobody unprotected at any moment. And the hot work was a separate permit, issued to a different standard of check and ended before the main job did.

Keeping the system honest: the register, the board and the rules

A permit system is one sheet of paper repeated, so its quality is decided by the habits around the sheet. A register with one line per permit, kept where permits are issued and updated at every change, lets the issuer see every live and suspended permit on the site together. Six rules do most of the work.

  • The permit is issued at the job, not from a desk.
  • One job, one place, one shift at most. Longer work is handed over in writing, with both sides at the plant.
  • A suspended permit is still live. Its isolations stay on, and it stays on the register and the board.
  • A copy is displayed at the job and a copy is where permits are issued.
  • Handback and cancellation are two steps: the holder says the work is done, then the plant is tested and taken back.
  • Nobody issues a permit to themself, and nobody signs a permit for work they have not seen.

Read the register for two flags. A permit that is suspended and past its end time is a lock still on a machine that nobody is watching. A permit that is open and past its end time is a job nobody has handed back. Both are visible from the register in seconds, and neither is visible from the plant.

Why permit systems fail

  • Permits for everything. When a permit is needed to change a light bulb, nobody reads any of them, and the one for the tank gets signed like the rest.
  • Issued from a desk. The signature says the issuer has seen the job. If they have not, the permit has checked nothing.
  • Isolation by switch. A lock number with no result in the check column. The plant has been switched off, not proved dead.
  • One person plays both roles. The same person issues, holds and hands back. There is no second look.
  • Signed in advance. Permits filled in and signed the day before, for the crew to pick up. Conditions on the day are not the conditions on the paper.
  • The suspended permit forgotten. A lock stays on a machine after the crew has gone, and the next shift has no record of why.
  • Handback means cancellation. The crew leaves, the permit is torn up and the plant goes back into service untested.
  • The permit stands in for the plan. A permit with no JSA or method statement behind it tells the crew they may start, and nothing about how.

What a permit cannot do

A permit is an administrative control. It does not hold a load, drain a line or stop a motor. What it does is make sure that the controls that do those things are in place and checked by someone who has no stake in the job running on time. It works only as well as the people who issue it: the fastest way to ruin a system is to measure issuers on how quickly they turn permits around.

The wider process for outside crews, from prequalification to the review after the job, is in the guide to contractor safety management. LeanSuite is not a permit-to-work system. Its safety improvement tools run inspections and lockout checks from templates and raise a safety tag when an item fails, which is useful around a permit system but is not one.

This guide is general practice. It is not legal advice and it does not tell you whether a particular form satisfies a regulation. Check the rules that apply to your site and your type of work.

Templates and related guides

Doing this in LeanSuite

See it on your own lines

Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.

FAQ

Questions about permit to work (PTW)

  1. A permit to work is a documented procedure that authorises named people to do a specific job within a set time, once the area has been made safe. It records the work and its limits, the isolations that were made and proved, the precautions, and who issued, accepted and handed back. HSE describes it in these terms. It controls the start and the end of the job, not the method.

  2. PTW stands for permit to work. In safety documents you may also see it written as permit-to-work or work permit. It refers to the same system: a controlled authorization for one job in one place for a limited time. In plant safety the three letters nearly always mean this permit.

  3. The common types are general or cold work, hot work, confined space entry, work at height, electrical work and excavation. A general permit covers isolation and coordination. The specialised ones add their own checks, such as atmosphere tests for confined spaces or fire precautions for hot work. One job can need several, and each lists the others' numbers. Which you need depends on the work and the rules that apply to your site.

  4. A JSA describes how a task is done safely: its steps, the hazards at each and the controls. A permit to work decides whether a particular job may start now, in this place, and records that the plant has been made safe. The permit points to the JSA but does not replace it. A job can have a good JSA and no permit, or a signed permit and no plan, and both are weak.

  5. A person who knows the plant and has been trained and authorised by the site, such as a shift supervisor or area owner. They must go to the job, check the isolations and precautions, and not issue a permit to themself. Who counts as competent is set in your own procedure and by the rules that apply to you. The person doing the work is the permit holder, not the issuer.

  6. No. Lockout tagout is the method for isolating a machine's energy with locks and tags. A permit to work is the authorization that lists those isolations for a job, requires proof that each worked, and covers the rest: precautions, clashes with other work, handover and handback. A permit often relies on lockout, and a simple lockout on a routine task may need no permit.

  7. We found no general permit-to-work requirement on the OSHA pages we read. OSHA does require permits for particular work. Under 29 CFR 1910.146 a permit-required confined space needs an entry permit signed by the entry supervisor before entry. Under 29 CFR 1910.252 the person authorizing cutting and welding inspects the area and designates precautions, preferably in a written permit. Check the standard for your work.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.