Practical guide · Safety management
Permit to work (PTW): how the system works, types of permit and a worked example
Short answer
A permit to work is a written authorization for one job, in one place, for a limited time. It says the plant has been made safe and the precautions are in place, and it is issued before the work and closed after it.
A permit to work (PTW) is a documented procedure that lets named people do a specific job, within a set time, once the area has been made safe. The issuer goes to the job, checks that every energy source is isolated and proved, and signs. The permit holder accepts it, briefs the crew and works inside its limits. When the work ends the holder hands back, the issuer tests the plant, and the permit is cancelled. A permit does not describe the method. That is the job of the JSA or method statement it points to. General guidance, not legal advice: the rules differ by country and by type of work.
Last reviewed:
What is a permit to work?
A permit to work, PTW for short, is a controlled piece of paper (or screen) that sits between a plan and the start of the work. HSE in Great Britain describes it as a documented procedure that authorises certain people to carry out specific work within a specified time frame. It sets out the precautions, based on a risk assessment, and it can include a method statement.
It exists because some jobs are dangerous for a reason the crew cannot see: stored energy, a line that still holds product, another team working above. A permit forces one person who knows the plant to go to the job and confirm those things, and forces the people doing the work to say they understand the limits. It is also how an area stays aware of what is happening in it. HSE's human factors page makes the same point: a permit is communication between site management, supervisors, operators and the people doing the work, and it helps stop two jobs clashing.
Think of it as a gate. Planning documents describe how the work will be done. The permit decides whether it may start today, here, with these people, and it records who took the plant back when it ended.
| Document | Question it answers | What the permit adds |
|---|---|---|
| JSA or SOP | How is this task done safely? | The permit does not describe the method. It points to the JSA and checks the plant is ready for it. |
| SWMS or method statement | How will this high-risk job be done, step by step? | The permit confirms the area is safe and is live only for a set period. See the safe work method statement guide. |
| Lockout tagout procedure | How is this machine's energy isolated? | The permit lists the isolations for this job and requires proof that each worked. See lockout tagout. |
| Pre-task plan | What is different today? | The pre-task plan is the crew's own briefing after the permit is accepted. |
| Stop work authority | Can anyone stop the job? | A permit says what stops it. Stop work authority says nobody needs permission to do so. |
A permit is a check that the precautions are in place. It does not replace the risk assessment, the JSA or the lockout procedure.
Which document works at which moment of a job
| Document | Planning, days before | Start of the job | During the work | Hand-back |
|---|---|---|---|---|
| JSA or SOPHow is this kind of task done safely? | Write once | Read | ||
| SWMS or method statementHow will this high-risk job be done? | Write for the job | Brief and sign | Check the work against it | |
| Permit to workIs the plant safe, and may the job start? | Request | Issue at the job | Hold, suspend, hand over | Hand back and cancel |
| Pre-task planWhat is different today? | Brief the crew | |||
| Field level risk assessmentIs this step safe right now? | Before each step |
A table of five safety documents against four moments: planning, the start of the job, during the work and hand-back. The job safety analysis and the method statement are written in planning. The permit is requested in planning, issued at the start, held during the work and handed back at the end. The pre-task plan is a briefing at the start. The field level risk assessment is a check before each step.
When a permit is needed, and the types of permit
HSE says permits are for work that needs extra care: hot work such as welding, entering vessels, cutting into pipework that has carried hazardous substances, and work needing electrical or mechanical isolation. The test is the same in any plant. Use a permit when the job is non-routine, needs isolations, involves more than one group, or is handed from one shift to the next.
- Non-routine work: maintenance, repair, cleaning inside equipment, modification, testing, dismantling.
- Work that needs isolations, or that two or more groups have to coordinate to do safely.
- Work handed from one group or shift to another.
- Not routine production work and not every small job. When everything needs a permit, people stop reading them.
| Permit | Used for | What it adds to a general permit | What the US rule says |
|---|---|---|---|
| General work (cold work) | Maintenance, repair, cleaning, anything needing isolation or coordination | Isolations, precautions, handover, handback | We found no general permit-to-work requirement in the OSHA pages we read. The site sets its own system. |
| Hot work | Welding, cutting, grinding, anything producing sparks or flame | Area cleared and inspected, fire precautions, limited time | 29 CFR 1910.252(a)(2)(iv): the person responsible for authorizing cutting and welding inspects the area and designates the precautions, preferably in a written permit. |
| Confined space entry | Tanks, vessels, pits, silos | Atmosphere tests, an attendant, a rescue arrangement | 29 CFR 1910.146: an entry permit is required for a permit-required confined space. The entry supervisor signs it before entry and cancels it when the work ends or a condition arises that it does not allow. |
| Work at height | Roofs, scaffolds, lifts, edges | Access, edge protection, rescue, drop zone | Set by your fall protection rules and site policy. |
| Electrical | Work on or near energised or recently de-energised equipment | Isolation, proving dead, authorised persons only | Set by your electrical safety rules and site policy. |
| Excavation | Digging, trenches, trial holes | Buried services located, edges and access controlled | Set by your excavation rules and site policy. |
OSHA regulations quoted from osha.gov on 28 November 2026. Other countries and states differ, and many sites also require a permit where the law does not. Read the rule that applies to your site.
Hot work and confined space permits do not replace the general permit when a job needs isolations as well. Link them: the general permit lists the numbers of the other permits for the same job, and each says it is not the whole story. See the hot work permit template and the confined space entry permit template.
Who does what
A permit needs at least two people who are not the same person. HSE's human factors page asks that roles and responsibilities are clear, with no important gaps or overlaps. Sites use different titles. These are the five roles that matter, whatever they are called.
| Role | What they do |
|---|---|
| Requester | Describes the work and its limits and attaches the JSA or SWMS. |
| Issuer | Knows the plant. Goes to the job, checks isolations and precautions, issues the permit, visits during the work and takes the handback. Never issues a permit to themself. |
| Permit holder | In charge of the work. Briefs the crew, keeps to the limits, stops if anything changes, and hands back. |
| Isolator | Makes each isolation, locks or tags it and proves it. Signs the row. |
| Everyone | Works only inside the permit, and stops the job if it cannot be done that way. |
Roles follow the form in the permit-to-work template. Some sites use "issuing authority" and "performing authority" for the first two.
The figure maps those roles onto the six stages. The pattern to notice is that the issuer is the only person who is both at the start and at the end. That is what stops a permit being opened by one team and closed by whoever is left.
Who does what, stage by stage
| Role | 1Request | 2Prepare | 3Issue | 4Work | 5Hand back | 6Cancel |
|---|---|---|---|---|---|---|
| Issuer (knows the plant) | Goes to the job, checks isolations and precautions | Signs the issue at the job | Visits the job, may suspend | Takes the handback, tests the plant | Cancels and updates the register | |
| Permit holder (leads the work) | Asks, with the JSA or SWMS attached | Walks the job with the issuer | Signs acceptance, briefs the crew | Keeps to the limits, stops if it changes | Clears the area, signs the handback | |
| Isolator and crew | Isolates, locks, tags and proves each source | Each person fits a personal lock | Works only inside the permit | Each removes their own lock |
A grid of three roles against six stages of a permit: request, prepare, issue, work, hand back and cancel. The issuer prepares, issues, visits, takes the handback and cancels. The permit holder requests, accepts, works within limits and hands back. The isolator and crew isolate, fit locks and remove their own locks.
How a permit works, step by step
The same ten steps hold for a general permit, a hot work permit and a confined space permit. What changes is the checks inside steps 3 and 4.
Ten steps from request to cancellation
- 1
Request and scope
- 2
Check for clashes
- 3
Isolate and prove
- 4
Go to the job
- 5
Issue
- 6
Accept and brief
- 7
Work, and suspend if it stops
- 8
Hand over at a shift change or extension
- 9
Hand back
- 10
Test, cancel and return to service
- 1
Request and scope
The requester writes the work exactly, and the limits: what this permit does not cover. They attach the JSA or SWMS. Words like "maintenance on tank 3" are too wide. "Replace the agitator gearbox on T-3, no entry into the tank" is a permit.
- 2
Check for clashes
Look at the permit register and the board. Is anyone working above, below or on the same line? Is a hot work permit live nearby? A clash found here costs a phone call. Found on the day, it costs a stopped job.
- 3
Isolate and prove
The isolator isolates every energy source on the permit, locks or tags it and then tries it. A start button pressed with no result, a gauge read at zero, a valve cracked open and found dry. The result goes on the permit.
- 4
Go to the job
The issuer walks the job with the permit holder: the place, the equipment, the isolations on the plant, the precautions. This is the step that gets skipped when the issuer is busy, and it is the one a permit exists for.
- 5
Issue
The issuer signs that the isolations are made and tried, the precautions are in place and the work may start within the limits and times written. For work your site ranks as high hazard, a second authorizer signs first.
- 6
Accept and brief
The permit holder signs that they understand the work, the hazards and the limits, reads the permit to the crew at the job, and each person signs. Each person fits their own lock to the lock box. A copy is displayed at the job and a copy is kept where permits are issued.
- 7
Work, and suspend if it stops
The crew works inside the permit. If the job stops (wrong part, break, weather, an alarm), the holder writes the state the plant was left in and the permit is suspended. A suspended permit is still live: its isolations stay on, and it stays on the board.
- 8
Hand over at a shift change or extension
Work past the end time or across a shift needs a new declaration. Outgoing and incoming holders and the issuer check the isolations together on the plant. The incoming person locks on before the outgoing person's lock comes off.
- 9
Hand back
The holder says the work is complete or what is left, and in what state. Tools and waste are out, guards are back, everyone is clear and told the job is over, and each lock has been removed by the person who fitted it. The issuer signs the handback.
- 10
Test, cancel and return to service
The issuer, with the person taking the plant back, tests it: a test run, a leak check, a function test. Only then is the permit cancelled and the register updated. Handback and cancellation are two steps on purpose.
Isolation: the part that cannot be skipped
Illustrative example, used from here to the end of the guide. A maintenance crew replaces the agitator gearbox on mixing tank T-3. The gearbox weighs 85 kg (187 lb) and comes out on a chain hoist. The permit is PTW-0457, and it points to JSA-112.
Four energy sources are on the permit: the agitator motor, the steam jacket, the product inlet and the stored motion in the agitator shaft. Each gets four moves: isolate it, lock it, tag it, then try it. The fourth move is the one that matters. A line that reads "lock L-031" and nothing in the last column has been switched off, not proved. HSE's human factors page notes that failures during isolation and reinstatement of process plant are one of the main causes of loss-of-containment incidents. The lockout tagout guide goes through the machine side in more detail.
Isolation: four moves for every energy source, and the proof
Example numbers| Energy | Isolation point | How isolated | Lock or tag | Zero-energy check: what was tried, and the result |
|---|---|---|---|---|
| Electrical | Breaker Q14 in MCC-2 | Opened, locked, tagged | L-031 | Start button pressed: no start. Dead at the motor terminals. |
| Steam | Jacket supply valve V-12; bleed V-13 | V-12 closed and chained, V-13 open | L-032 | Gauge reads 0. Bleed open, nothing flowing. |
| Product | Tank inlet valve V-7 | Closed and locked | L-033 | Level gauge empty. Inlet drain open, nothing flowing. |
| Stored motion | Agitator shaft | Shaft clamp fitted | Tag T-118 | Shaft pushed by hand: does not turn. |
Four steps, isolate, lock, tag and try, then four rows from the example permit PTW-0457 listing each energy source on the tank agitator with its isolation point, how it was isolated, the lock or tag number and the zero-energy check that was tried.
Worked example: one permit across a suspension and a shift handover
The gearbox job did not go to plan. A hot work permit was needed for two seized bolts, a wrong part stopped the job at midday, and the shift changed in the middle. The table is what the permit and its register recorded. All names, numbers and times are made up.
| Time | What happened | Who | Where it was written |
|---|---|---|---|
| 07:00 | Issued at the job after the issuer saw the four isolations made and tried. Valid to 15:00. | N. Osei, issuer | Issue block |
| 07:05 | Accepted. Crew of three briefed, each person's lock on lock box LB-2. | K. Brandt, permit holder | Acceptance block |
| 08:00 | Hot work permit HW-0098 issued to cut two seized coupling bolts. Cancelled 09:45. | N. Osei issues, K. Brandt holds | Linked permits line |
| 12:15 | Suspended. The new coupling has the wrong bore. Gearbox out, shaft clamped and supported, opening covered, area barriered. All isolations left on. | K. Brandt | Suspension block |
| 15:00 | Shift handover. Incoming holder and incoming issuer check every isolation on the plant. The incoming holder locks on to LB-2 before the outgoing locks come off. New end time 23:00. | B. Mwangi, F. Lindqvist | Handover block |
| 15:40 | Restart allowed after the issuer checked every isolation and the job. The correct coupling arrived at 15:25. | F. Lindqvist | Suspension block |
| 18:30 | Work complete. Tools out, guard fitted, locks removed by the people who fitted them. Issuer signs the handback at 18:50. | B. Mwangi, F. Lindqvist | Handback block |
| 19:10 | Test run for 15 minutes: no leaks, no unusual noise or vibration. Permit cancelled, register updated. | F. Lindqvist | Cancellation block |
Times and names are from the worked example in the permit-to-work template.
One permit across a day: suspension, handover, handback
Example numbers- 07:05 Accepted, crew briefed
- 09:45 Hot work cancelled
- 12:15 Suspended: wrong coupling
- 15:00 Shift handover, both at the plant
- 15:40 Restart allowed
- 18:30 Handback
- 19:10 Cancelled after test run
Solid bar: permit live and work under way. Dashed bar: suspended, isolations still on.
Timeline from 07:00 to 19:30. Permit PTW-0457 runs from 07:00, is suspended from 12:15 to 15:40 with its isolations left on, then runs again until handback at 18:30. A hot work permit HW-0098 runs inside it from 08:00 to 09:45. The shift handover is at 15:00 during the suspension and the permit is cancelled at 19:10 after a test run.
Three things in this record are the permit doing its job. The suspension kept the isolations on for three and a half hours while nobody was working, so the next person to look at the tank was not surprised. The handover was done at the plant, not over the phone, and the order of the locks left nobody unprotected at any moment. And the hot work was a separate permit, issued to a different standard of check and ended before the main job did.
Keeping the system honest: the register, the board and the rules
A permit system is one sheet of paper repeated, so its quality is decided by the habits around the sheet. A register with one line per permit, kept where permits are issued and updated at every change, lets the issuer see every live and suspended permit on the site together. Six rules do most of the work.
- The permit is issued at the job, not from a desk.
- One job, one place, one shift at most. Longer work is handed over in writing, with both sides at the plant.
- A suspended permit is still live. Its isolations stay on, and it stays on the register and the board.
- A copy is displayed at the job and a copy is where permits are issued.
- Handback and cancellation are two steps: the holder says the work is done, then the plant is tested and taken back.
- Nobody issues a permit to themself, and nobody signs a permit for work they have not seen.
Read the register for two flags. A permit that is suspended and past its end time is a lock still on a machine that nobody is watching. A permit that is open and past its end time is a job nobody has handed back. Both are visible from the register in seconds, and neither is visible from the plant.
Why permit systems fail
- Permits for everything. When a permit is needed to change a light bulb, nobody reads any of them, and the one for the tank gets signed like the rest.
- Issued from a desk. The signature says the issuer has seen the job. If they have not, the permit has checked nothing.
- Isolation by switch. A lock number with no result in the check column. The plant has been switched off, not proved dead.
- One person plays both roles. The same person issues, holds and hands back. There is no second look.
- Signed in advance. Permits filled in and signed the day before, for the crew to pick up. Conditions on the day are not the conditions on the paper.
- The suspended permit forgotten. A lock stays on a machine after the crew has gone, and the next shift has no record of why.
- Handback means cancellation. The crew leaves, the permit is torn up and the plant goes back into service untested.
- The permit stands in for the plan. A permit with no JSA or method statement behind it tells the crew they may start, and nothing about how.
What a permit cannot do
A permit is an administrative control. It does not hold a load, drain a line or stop a motor. What it does is make sure that the controls that do those things are in place and checked by someone who has no stake in the job running on time. It works only as well as the people who issue it: the fastest way to ruin a system is to measure issuers on how quickly they turn permits around.
The wider process for outside crews, from prequalification to the review after the job, is in the guide to contractor safety management. LeanSuite is not a permit-to-work system. Its safety improvement tools run inspections and lockout checks from templates and raise a safety tag when an item fails, which is useful around a permit system but is not one.
This guide is general practice. It is not legal advice and it does not tell you whether a particular form satisfies a regulation. Check the rules that apply to your site and your type of work.
Templates and related guides
- Hot work permit template and confined space entry permit template: the two specialised permits.
- Lockout tagout procedure template: the isolation steps for the equipment in the job.
- Job safety analysis template: the task steps and controls the permit points to.
- Contractor safety checklist: what to check before, during and after an outside crew works on site.
- Safe work method statement and pre-task plan: the written method before the permit and the crew's briefing after it.
Go deeper
This page is the short version. These guides cover each part in full.
- 7 Preventable Shop Floor Incidents Most Plants MissThe kind of incident a permit's isolation check is meant to stop.
- Top Five Common Manufacturing HazardsThe energy and hazard families to look for when you fill in the hazards block.
- Safety Vigilance Gaps Costing Manufacturers MillionsWhat happens between the paper and the work when nobody checks.
- Near-Miss Reporting Prevents Future IncidentsWhy a stopped permit job is a report to learn from, not a delay to hide.
All our articles on this subject are in the safety management topic.
Free templates and tools
- Hot work permit templateA hot work permit with a precautions checklist, fire watch record and close-out, plus an Excel permit log.
- Confined space entry permit templateA confined space entry permit with checks, an air test log, an entry log and cancellation, plus an Excel register.
- Lockout/tagout (LOTO) procedure templateA machine-specific LOTO procedure: energy sources and isolation points, the steps from shutdown to restart, and the annual review.
- Job safety analysis (JSA) templateJob steps, hazards, risk scored before and after the controls, the hierarchy of controls, PPE and sign-off.
- Contractor safety checklist28 checks for one contractor job, from planning and prequalification to permits, orientation, on-site checks and the review afterwards.
- Risk matrix calculatorSeverity times likelihood on a 3 x 3, 4 x 4 or 5 x 5 risk matrix, the band and its action, editable banding, and the score after further controls.
Doing this in LeanSuite
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about permit to work (PTW)
A permit to work is a documented procedure that authorises named people to do a specific job within a set time, once the area has been made safe. It records the work and its limits, the isolations that were made and proved, the precautions, and who issued, accepted and handed back. HSE describes it in these terms. It controls the start and the end of the job, not the method.
PTW stands for permit to work. In safety documents you may also see it written as permit-to-work or work permit. It refers to the same system: a controlled authorization for one job in one place for a limited time. In plant safety the three letters nearly always mean this permit.
The common types are general or cold work, hot work, confined space entry, work at height, electrical work and excavation. A general permit covers isolation and coordination. The specialised ones add their own checks, such as atmosphere tests for confined spaces or fire precautions for hot work. One job can need several, and each lists the others' numbers. Which you need depends on the work and the rules that apply to your site.
A JSA describes how a task is done safely: its steps, the hazards at each and the controls. A permit to work decides whether a particular job may start now, in this place, and records that the plant has been made safe. The permit points to the JSA but does not replace it. A job can have a good JSA and no permit, or a signed permit and no plan, and both are weak.
A person who knows the plant and has been trained and authorised by the site, such as a shift supervisor or area owner. They must go to the job, check the isolations and precautions, and not issue a permit to themself. Who counts as competent is set in your own procedure and by the rules that apply to you. The person doing the work is the permit holder, not the issuer.
No. Lockout tagout is the method for isolating a machine's energy with locks and tags. A permit to work is the authorization that lists those isolations for a job, requires proof that each worked, and covers the rest: precautions, clashes with other work, handover and handback. A permit often relies on lockout, and a simple lockout on a routine task may need no permit.
We found no general permit-to-work requirement on the OSHA pages we read. OSHA does require permits for particular work. Under 29 CFR 1910.146 a permit-required confined space needs an entry permit signed by the entry supervisor before entry. Under 29 CFR 1910.252 the person authorizing cutting and welding inspects the area and designates precautions, preferably in a written permit. Check the standard for your work.
Related guides and tools
- Safe work method statement: the written method the permit points to
- Pre-task plan: the crew's briefing after the permit is accepted
- Job safety analysis: the task steps and controls behind a permit
- Lockout tagout: isolating a machine's energy
- Stop work authority: anyone can stop the job
- Contractor safety management: the stages around a permit
- Management of change: when the job changes the plant
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk
Or browse the topics, the full library and the lean glossary.
Rather see it on your own problem?
Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.