Time study vs motion study vs method study vs work study
Short answer
Work study is the umbrella. It has two halves: method study, which finds a better way to do a job, and work measurement, which sets how long the job should take. Motion study is method study at the scale of the hands. Time study is one work measurement technique.
Method study asks how the job should be done. It records the present way, questions every step and designs a better one. Motion study is the fine-grained end of method study: it looks at the movements of hands, eyes and body inside one workstation. Work measurement asks how long the job should take a qualified worker at a normal pace. Time study is the best-known way to answer that, by timing the job directly, rating the pace and adding allowances. Work study is the British and ILO name for method study and work measurement together. The American name for much the same field is motion and time study, or methods engineering. Fix the method first, then measure it.
Last reviewed:
The five terms, and the question each one answers
How the five terms fit together
Work study
Get more from the same people, machines and material
Method study
How should the job be done? Record the present way, question every step, design a better one.
Motion study
Method study at the scale of the hands: every reach, grasp, move and release inside one workstation.
- Process chart
- Flow diagram
- Two-handed chart
- Eliminate, combine, rearrange, simplify
Work measurement
How long should the job take? The time for a qualified worker at a normal pace.
Time study
Time the job directly, rate the pace, add allowances
Work sampling
Random instant observations give shares of time
Predetermined time systems
Add up table times for basic motions: MTM, MOST
Standard data
Reuse element times from your own earlier studies
Structured estimating
An experienced estimate against benchmark jobs
A tree. Work study at the top splits into two branches. Branch one, method study, asks how the job should be done and contains motion study. Branch two, work measurement, asks how long the job should take and contains time study, work sampling, predetermined time systems, standard data and structured estimating. A band underneath says the order of work is method first, then measurement.
The terms get mixed up because they overlap and because two countries named the same field twice. Sort them by the question each one answers and the overlap stops being a problem. There are only two questions: how should this job be done, and how long should it take?
| Term | The question it answers | What you look at | What you end up with |
|---|---|---|---|
| Work study | How do we get more from the same people, machines and material? | The whole job: its method and its time | A better method and a time standard for it. It is the umbrella over the next two terms. |
| Method study | How should this job be done? | The sequence of operations, the movement of material and people, the layout, the tools | A new method, written down, cheaper and easier than the old one |
| Motion study | Which movements does the job need, and which can go? | Hands, eyes and body inside one workstation, often from film | A workstation and a motion pattern with the wasted movements taken out |
| Work measurement | How long should this job take a qualified worker at a normal pace? | The work content of a defined method | A time standard. Time study, work sampling and predetermined time systems are all ways to get one. |
| Time study | How long does this job take when we time it directly? | A run of cycles, element by element, with a stopwatch or from video | Observed time, then normal time after rating, then standard time after allowances |
Definitions follow the ILO's Introduction to Work Study and the British Standard glossary of work study terms (BS 3138).
So the short version is two pairs. Work study is method study plus work measurement. Motion study is a part of method study, and time study is a part of work measurement. The phrase time and motion study is the everyday name for the whole thing.
Two vocabularies for one field
A good half of the confusion is geography. British practice, and the International Labour Organization textbook that carried it around the world, speaks of work study. American practice grew from Taylor's time study and the Gilbreths' motion study and joined the two names together. If your textbook is by Kanawaty or Currie you learned the left column. If it is by Barnes, Niebel or Maynard you learned the right one.
| British and ILO term | American term | Meaning |
|---|---|---|
| Work study | Motion and time study; methods engineering; work design | The whole field: improve the method, then set the time |
| Method study | Methods analysis; methods engineering; motion study | Recording and questioning the way a job is done to find a better way |
| Work measurement | Work measurement; time study, used loosely | Setting the time for a qualified worker to do a defined job |
| Basic time | Normal time | Observed time adjusted by the pace rating |
| Relaxation allowance | Personal and fatigue allowances | Time added for personal needs and recovery from effort |
| Standard time; standard minute value (SMV) | Standard time; standard allowed minutes (SAM) | Normal time plus allowances |
| Activity sampling | Work sampling | Estimating shares of time from random instant observations |
| Predetermined time standards (PTS) | Predetermined motion time systems (PMTS) | Building a time from tables of basic motions, such as MTM and MOST |
In American plants, time study is often used as a loose name for all work measurement. In this guide it means direct timing only.
Method study: how should the job be done?
Method study is the systematic recording and critical examination of the way work is done, so as to make it easier and cheaper. It exists because the way a job is done today is rarely the way anyone designed it. It grew: a bench was moved, a part changed, someone left. Method study writes down what really happens and asks of each step whether it needs to exist.
The ILO text lists eight steps: select, record, examine, develop, evaluate, define, install and maintain. Older British texts shorten them to six and the acronym SREDIM.
- 1
Select
Pick the job worth studying: the bottleneck, the one with the most labour hours, the one people complain about.
- 2
Record
Write down the present method by watching it, not by reading the procedure. Use a process chart, a flow diagram, a two-handed chart or video.
- 3
Examine
Question every step: what is done and why, where, when, by whom and how. Ask each time whether it could be eliminated, combined, rearranged or simplified.
- 4
Develop
Design the new method with the people who do the job.
- 5
Evaluate
Compare the new method with the old: time, cost, quality, safety, effort.
- 6
Define
Write the new method down so that it can be taught and checked.
- 7
Install
Train people, change the layout and tools, and run it.
- 8
Maintain
Check that the new method is still in use and has not drifted back.
The recording tools are the ones a lean team already knows under other names. A flow process chart lists every operation, move, delay, inspection and storage. A flow diagram or spaghetti diagram draws the path on a floor plan. A multiple activity chart puts an operator and a machine on one time scale. The examine step, with its eliminate, combine, rearrange and simplify, is what lean calls ECRS. Sorting each step by value added and non value added is the same examination with a different label.
Motion study: which movements does the job need?
Motion study is method study with a magnifying glass. Method study looks at the flow of a job across a department. Motion study looks at what two hands do in the space of one bench: every reach, grasp, move and release. Frank and Lillian Gilbreth built it, first by watching bricklayers and then by filming work against a clock that read to fractions of a second.
Therbligs
The Gilbreths broke manual work into basic elements and named them therbligs, their own name spelled backwards with the th kept together. A paper of 1915 lists 16. Later lists run to 17 and then 18, with plan and hold added. Niebel and Freivalds sort them into two groups: effective therbligs that move the work forward, and ineffective ones that a better method should shrink or remove. The grouping is what makes the list useful on the floor. You do not need to code a job in therbligs to ask why the left hand is holding a part for eight seconds when a fixture could.
The therbligs, sorted by what a better method does with them
Effective: 8
Move the work forward. Make them shorter and easier.
- Reach (transport empty)
- Move (transport loaded)
- Grasp
- Release load
- Pre-position
- Use
- Assemble
- Disassemble
Ineffective: 9
Add time and no progress. Shrink or remove them.
- SearchFix: a fixed place for every part
- SelectFix: one part type per bin
- PositionFix: guides, chamfers, stops
- HoldFix: a fixture or clamp
- InspectFix: gauges built into the step
- PlanFix: a fixed, taught sequence
- Unavoidable delayFix: balance the two hands
- Avoidable delayFix: remove the cause
- RestFix: lower the effort of the job
Two groups. Eight effective therbligs move the work forward: reach, move, grasp, release load, pre-position, use, assemble and disassemble. Nine ineffective therbligs are the ones to shrink or remove, each with a typical fix: search, select, position, hold, inspect, plan, unavoidable delay, avoidable delay and rest.
The principles of motion economy
Ralph Barnes turned the Gilbreths' findings into 22 principles of motion economy, in three groups: the use of the human body, the arrangement of the workplace, and the design of tools and equipment. A few carry most of the benefit.
- Both hands should start and finish their motions together, and should not be idle at the same time except during rest.
- Arm motions should be symmetrical and in opposite directions.
- Use the smallest body movement that does the job: fingers before wrists, wrists before forearms, forearms before shoulders.
- Give every tool and part a fixed place, inside the normal reach of the hands.
- Feed parts by gravity to the point of use, and let finished parts drop away.
- Free the hands from holding. A hand is a poor vice. Use a fixture or a foot pedal.
Motion study is where method study meets ergonomics. The same film that shows a wasted reach shows a raised shoulder. An ergonomic assessment scores the posture, and motion study removes the reason for it.
Work measurement: how long should the job take?
Work measurement is the application of techniques to establish the time for a qualified worker to carry out a task at a defined rate of working. Each part of that sentence matters. Qualified means trained and able, not the fastest person on the shift. A defined rate means a normal pace that can be kept up all day. And task means a defined method. A time with no method attached is not a standard.
Time study is one of five techniques the ILO lists. They differ in whether you watch the job, how much detail you get and how much effort it takes.
| Technique | How the time is found | Best for |
|---|---|---|
| Time study | Time a run of cycles directly, rate the pace, add allowances | Short, repeating manual jobs that exist today |
| Work sampling (activity sampling) | Tally what is happening at random instants; shares of tallies estimate shares of time | Long, irregular or shared work; finding where time goes across a department |
| Predetermined time systems (MTM, MOST, MODAPTS) | Break the job into basic motions and add up their times from published tables | Jobs that do not exist yet; very short cycles at high volume; no pace rating needed |
| Standard data | Build the time from your own library of element times taken in earlier studies | Families of similar jobs, where a new part differs only in size or count |
| Structured estimating | An experienced person estimates the time, job by job or by comparing with benchmark jobs | One-off and long-cycle work such as maintenance and toolroom jobs |
The five are the ILO's list. Machine and system data, such as cycle counters, are a sixth source for machine-paced work, though they record what happened, not what should happen.
The guide to time study vs work sampling goes through that one choice in detail, and work sampling has the method and the formula.
Time study: the direct way to measure
A time study records the times of a specific job, element by element, under stated conditions, and works them up into the time the job should take at a defined pace. It is the technique people mean when they picture someone with a stopwatch and a clipboard, though a camera has replaced both in many plants.
- Break the job into elements with clear break points. See how to break a job into elements.
- Time enough cycles for the accuracy you need. See how many cycles to time.
- Average the readings for each element. That is the observed time.
- Rate the operator's pace against normal and adjust. Observed time x rating = normal time, which British texts call basic time.
- Add allowances for personal needs, fatigue and unavoidable delays. Normal time x (1 + allowance) = standard time.
What a time study produces: three times, each built on the one before
Example numbersObserved time
42 s
The average of the timed cycles
- x rating 100%
Normal time
42 s
British texts: basic time
- x (1 + 12% allowance)
Standard time
47.0 s
76.5 cartons an hour
Three steps rising left to right. Observed time 42 seconds, multiplied by a rating of 100 percent, gives a normal time of 42 seconds. Normal time multiplied by 1 plus a 12 percent allowance gives a standard time of 47.0 seconds, which is 76.5 cartons an hour.
The full procedure is in how to conduct a time study. What matters here is where it sits. A time study measures a method. It does not judge whether the method is any good. Point a stopwatch at a job with a 14 second walk in every cycle and you get an accurate standard that includes the walk.
Where Taylor and the Gilbreths fit
The two halves of the field have different parents, and the parents did not get on. That history is why there are two names.
Two beginnings, one field: time study and motion study from 1878 to 1957
- 1878Time studyTaylor joins Midvale Steel. In the early 1880s he starts timing machine-shop work with a stopwatch, element by element.
- 1898Time studyBethlehem Steel, to 1901: the shovelling and pig iron studies.
- 1903Time studyTaylor publishes Shop Management.
- 1909Motion studyFrank Gilbreth's Bricklaying System: by his account, 18 motions a brick cut to about 5.
- 1911Time studyThe Principles of Scientific Management. Moulders walk out at Watertown Arsenal when a time study starts unannounced.
- 1911Motion studyGilbreth publishes Motion Study.
- 1914Motion studyLillian Gilbreth publishes The Psychology of Management.
- 1915Time studyTaylor dies. Congress bars stopwatch timing in army arsenals and navy yards.
- 1915Motion studyA Gilbreth paper lists 16 basic elements of motion, later named therbligs.
- 1921Motion studyThe Gilbreths' paper An Indictment of Stop-Watch Time Study.
- 1924Motion studyFrank Gilbreth dies. Lillian carries the work on for decades.
- 1937JoinedBarnes publishes Motion and Time Study: one subject, one textbook.
- 1948JoinedMethods-Time Measurement (MTM) gives each basic motion a time.
- 1957JoinedThe ILO's Introduction to Work Study spreads the British vocabulary worldwide.
A timeline with two lanes. The time study lane follows Frederick Taylor from Midvale Steel in 1878 to his death in 1915. The motion study lane follows Frank and Lillian Gilbreth from 1909 to 1924. The lanes join in 1937 with Barnes's Motion and Time Study, then MTM in 1948 and the ILO's Introduction to Work Study in 1957.
Frederick Winslow Taylor is usually called the father of time study. He joined the Midvale Steel Company in Philadelphia in 1878, became a foreman, and in the early 1880s began timing machine-shop work with a stopwatch, splitting each job into elements so that a fair day's work could be set from data instead of argument. He carried the work on at Bethlehem Steel from 1898 to 1901, with the shovelling and pig iron studies that became famous. He published Shop Management in 1903 and The Principles of Scientific Management in 1911.
Frank Gilbreth came at the same problem from the other side. As a bricklaying contractor he noticed that no two bricklayers worked the same way, and set out to find the best way. By his own account he cut the motions to lay a brick from 18 to about 5 and raised output from 120 to 350 bricks an hour, with an adjustable scaffold and a better arrangement of bricks and mortar. He published Bricklaying System in 1909 and Motion Study in 1911. Lillian Gilbreth, a psychologist, was his partner in all of it. Her book The Psychology of Management appeared in 1914, and she carried the work on for decades after his death in 1924. Together they filmed work against a fast clock, which they called micromotion study, and traced the path of a hand with a small lamp on a long-exposure photograph.
The Gilbreths thought the stopwatch was the wrong instrument. Their argument was that timing a poor method only made the poor method official, and that a watch read by eye was too coarse to study motions. In 1921 they put it in writing in a paper to the Taylor Society titled An Indictment of Stop-Watch Time Study. Taylor's followers answered that motion study without a time was no basis for planning or pay.
Both were right, and practice joined the two. By the 1930s American textbooks treated them as one subject. Barnes's Motion and Time Study came out in 1937. In 1948 Maynard, Stegemerten and Schwab published Methods-Time Measurement, which gave each basic motion a time and so merged the Gilbreths' elements with Taylor's clock. British practice arrived at the same place under the name work study, and the ILO's Introduction to Work Study, first published in 1957, spread that vocabulary across much of the world.
One more piece of the history still matters on the floor. In 1911 moulders at the US Army's Watertown Arsenal walked out when a time study began without the workforce being prepared for it. A House committee held hearings, and from 1915 Congress wrote a bar on stopwatch timing and bonus pay into the appropriation acts for army arsenals and navy yards, where it stayed for decades. The lesson is older than any modern plant: how a study is introduced decides whether it can be done at all. The guide to planning a time study covers what to say first.
Which comes first: method before measurement
Method study comes first. A time standard is a promise that a defined method takes a defined time. If the method still has waste in it, the standard has waste in it, and from then on the waste is protected: it is in the cost, the staffing plan and perhaps the pay. If the method changes afterwards, the standard is void and the study has to be done again.
Illustrative example. A packer builds a carton, fills it, labels it and puts it on a pallet. Each cycle takes 60 seconds: 38 seconds at the bench, 14 seconds walking to a pallet of flat cartons behind her, and 8 seconds looking for the right label roll.
| Time study first | Method study first | |
|---|---|---|
| Work at the bench | 38 s | 38 s |
| Walking for cartons | 14 s | 3 s (cartons on a rack at the bench) |
| Looking for labels | 8 s | 1 s (one roll per product, on a marked peg) |
| Normal time per carton (rating 100) | 60 s | 42 s |
| Standard time (allowance 12 percent) | 60 x 1.12 = 67.2 s | 42 x 1.12 = 47.0 s |
| Output at standard | 3,600 / 67.2 = 53.6 cartons an hour | 3,600 / 47.04 = 76.5 cartons an hour |
The 12 percent allowance and the rating of 100 are example figures. Both standards are equally accurate. Only one of them is worth having.
Before and after: the same job, measured with equal care
Example numbersBefore: time study first
60 s a carton
- Work at the bench: 38 s
- Walking for cartons: 14 s
- Looking for labels: 8 s
Standard: 60 x 1.12 = 67.2 s, or 53.6 cartons an hour
After: method study first
42 s a carton
- Work at the bench: 38 s
- Walking for cartons: 3 s
- Looking for labels: 1 s
Standard: 42 x 1.12 = 47.0 s, or 76.5 cartons an hour
Two bars on the same scale. Before the method study the cycle is 60 seconds: 38 at the bench, 14 walking and 8 looking for labels, giving a standard of 67.2 seconds. After it the cycle is 42 seconds: 38 at the bench, 3 walking and 1 looking, giving a standard of 47.0 seconds.
The first study is not wrong. It is a faithful measurement of 22 seconds of walking and searching in every cycle. It would price the product, staff the line and judge the packer on a method nobody chose.
Where timing comes first anyway
- As a baseline. Rough timing of the present method tells you how big each loss is, so you know which to attack and can prove the gain afterwards. This is measurement in the service of method study, and it sets no standard.
- To choose where to look. A work sampling study across a department finds the area that loses the most time. Method study then goes there.
- When the decision cannot wait. A quote is due on Friday and the job runs today. Time it as it is, mark the standard as temporary and note the losses you saw.
So the order in practice is a loop: time the present method roughly, improve the method, write it down, measure it properly, set the standard, and study it again when the method changes.
One job seen through each study
The differences are easiest to see when all four are pointed at the same packing bench.
| Study | What the engineer does | What comes back |
|---|---|---|
| Method study | Charts every step from flat carton to pallet, and draws the packer's path on a floor plan | The walk for cartons and the search for labels can go. New layout: cartons on a rack at the bench, one label roll per product. |
| Motion study | Films both hands filling and taping one carton | The left hand holds the flaps shut for 5 seconds while the right hand reaches for the tape gun. A flap guide and a hanging tape gun free it. |
| Time study | Times 20 cycles of the new method, element by element, rates the pace and adds allowances | A standard time of 47 seconds a carton, and the output per hour that follows from it |
| Work sampling | Looks at the whole packing area at random times for a week | The share of the area's time that goes on packing, waiting for product, walking and rework |
Method study and motion study change the job. Time study and work sampling describe it. A plant that only does the second pair knows its losses to the second and still has them.
Mix-ups worth avoiding
- Time study and time and motion study. A time study only measures. A time and motion study, as the phrase is used today, improves the method and then measures it.
- Method study and methods engineering. Same thing. Methods engineering is the American name, usually credited to H.B. Maynard.
- Work study and work measurement. Work measurement is half of work study. The other half is method study.
- Cycle time and standard time. Cycle time is what the job took. Standard time is what it should take a qualified worker at a normal pace, with allowances. The cycle time vs lead time guide has the first.
- Time study and work sampling. Time study watches one job continuously. Work sampling glances at many jobs at random moments. They are both work measurement.
- Motion study and ergonomics. Motion study removes wasted movement to save time and effort. Ergonomics scores the risk of injury. They use the same film and often reach the same fix.
- Work study and jobs for students. In the United States, work-study is also a college funding programme. It has nothing to do with this.
What video changes
The Gilbreths needed a hand-cranked camera and a special clock to do motion study, and Taylor's engineers needed a trained eye and a watch. One recording now serves both. A phone on a tripod captures the method, the motions and the times in a single pass, and it can be replayed, which a stopwatch reading cannot.
That removes the old reason for doing the two halves apart. LeanSuite's time and motion study takes video of a station and times every element on a timeline linked to the footage, split into value-added, necessary and waste, so the same study that sets the time also shows what to take out. An engineer still reviews it, decides the method and certifies the result.
Templates and tools
- Time study sheet: elements down, cycles across, with rating and allowances.
- Process flow diagram template: to record the present method before you question it.
- Spaghetti diagram template: the path a person walks, drawn on the floor plan.
- Standard work sheet: to define the new method once it is agreed.
- Time study sample size calculator: how many cycles to time.
Go deeper
This page is the short version. These guides cover each part in full.
- Standard Work in Manufacturing: A Complete GuideWhat the define and maintain steps look like on the floor once the new method is agreed.
- How to Improve Shop Floor ProductivityThe wider set of losses a method study goes looking for.
- Standard Work Tools: Combination Sheet, Chart and Job BreakdownThe documents that hold the method and the times after the study.
- Yamazumi Chart: What It Is and How to Make One in 7 StepsStacking the element times from a study against takt to balance a line.
All our articles on this subject are in the standard work, sops and training topic.
Free templates and tools
- Time study sheetTime each element over 10 cycles and work out the average, lowest repeatable and standard time. Excel does the sums.
- Process flow diagram templateA squared sheet to draw the flow with a symbol key, and a step table that counts operations, moves, checks, waits and storage.
- Spaghetti diagram templateSquared paper to trace every trip, a trip log that turns grid squares into feet, meters and walking time, and a before and after comparison.
- Standard work sheet templateTakt time, each element's manual, machine and walk time on a time chart, key points and standard WIP.
- Time study sample size calculatorHow many cycles of an element to time, from your first readings, with the t formula, the ILO formula and the range method.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
- Takt time calculatorThe pace a line must hit to meet customer demand, from shift time, breaks and daily demand.
Doing this in LeanSuite
Time and Motion Study
Film the station and the AI times every element on a timeline that links to the video, split into value-added, necessary and waste.
See Time and Motion StudyAI Video Analysis
Turns video of real work into time studies, line balance charts, changeover splits and other studies you review and certify.
See AI Video Analysis
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about time study vs motion study vs method study
Work study is the whole field: it improves the way a job is done and then sets how long it should take. It has two parts, method study and work measurement. Time study is one technique inside work measurement, in which the job is timed directly, the pace is rated and allowances are added. So time study is a part of work study, not a rival to it.
Time study measures how long a job takes and turns that into a standard time. Motion study examines the movements the job is made of, to remove the wasted ones and make the rest easier. Time study comes from Frederick Taylor and uses a stopwatch or video. Motion study comes from Frank and Lillian Gilbreth and uses film. Used together they are a time and motion study.
Method study asks how a job should be done: it records the present method, questions each step and develops a better one. Work measurement asks how long the job should take a qualified worker at a normal pace, using time study, work sampling or predetermined time systems. Method study comes first, because a time set on a poor method builds the waste into the standard.
Two sets of people. Frederick Winslow Taylor developed stopwatch time study at Midvale Steel in the 1880s and is called the father of time study. Frank and Lillian Gilbreth developed motion study in the early 1900s, starting with bricklaying. The two approaches were rivals at first and were joined into one subject, motion and time study, by the 1930s.
A time and motion study examines a job in two ways: the motions it is made of, to find a better method, and the time it takes, to set a standard for that method. The result is a written method with wasted steps removed and a standard time used for costing, staffing, line balancing and capacity planning.
Originally to set a fair day's work and piece rates from measurement instead of argument, and to find the least tiring way to do manual jobs. Today the same studies feed product costing and quotes, staffing, line balancing, capacity plans, workstation layout, ergonomic reviews and improvement projects. Setting pay is only one use among several.
Method study. A time standard belongs to one defined method, so the method should be improved and written down before it is measured. Timing first gives an accurate standard for a job that still contains walking, searching and waiting. The one exception is a rough timing of the present method as a baseline, which sets no standard.
Therbligs are the basic elements of manual work defined by Frank and Lillian Gilbreth, such as search, select, grasp, transport loaded, position, assemble, use and release load. The name is Gilbreth spelled backwards with the th kept together. The Gilbreths' 1915 list had 16 and modern lists have 18. They are used in motion study to find movements a better method can remove.
Related guides and tools
- Time and motion study: what it is, the steps and a worked example
- How to conduct a time study: the procedure step by step
- Standard time: observed, normal and standard time with the formula
- Work sampling: the other common way to measure work
- Why do a time study: the eight decisions it feeds
- How to plan a time study: scope, operator, shift and the talk before it
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk
Or browse the topics, the full library and the lean glossary.
Rather see it on your own problem?
Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.