Time study vs motion study vs method study vs work study

Short answer

Work study is the umbrella. It has two halves: method study, which finds a better way to do a job, and work measurement, which sets how long the job should take. Motion study is method study at the scale of the hands. Time study is one work measurement technique.

Method study asks how the job should be done. It records the present way, questions every step and designs a better one. Motion study is the fine-grained end of method study: it looks at the movements of hands, eyes and body inside one workstation. Work measurement asks how long the job should take a qualified worker at a normal pace. Time study is the best-known way to answer that, by timing the job directly, rating the pace and adding allowances. Work study is the British and ILO name for method study and work measurement together. The American name for much the same field is motion and time study, or methods engineering. Fix the method first, then measure it.

Last reviewed:

The five terms, and the question each one answers

How the five terms fit together

Work study

Get more from the same people, machines and material

1

Method study

How should the job be done? Record the present way, question every step, design a better one.

Motion study

Method study at the scale of the hands: every reach, grasp, move and release inside one workstation.

  • Process chart
  • Flow diagram
  • Two-handed chart
  • Eliminate, combine, rearrange, simplify
2

Work measurement

How long should the job take? The time for a qualified worker at a normal pace.

  • Time study

    Time the job directly, rate the pace, add allowances

  • Work sampling

    Random instant observations give shares of time

  • Predetermined time systems

    Add up table times for basic motions: MTM, MOST

  • Standard data

    Reuse element times from your own earlier studies

  • Structured estimating

    An experienced estimate against benchmark jobs

Order of work:1 fix the method2 measure it

A tree. Work study at the top splits into two branches. Branch one, method study, asks how the job should be done and contains motion study. Branch two, work measurement, asks how long the job should take and contains time study, work sampling, predetermined time systems, standard data and structured estimating. A band underneath says the order of work is method first, then measurement.

Two questions, two branches. Motion study sits inside method study, and time study sits inside work measurement. Time and motion study is the everyday name for the whole tree.

The terms get mixed up because they overlap and because two countries named the same field twice. Sort them by the question each one answers and the overlap stops being a problem. There are only two questions: how should this job be done, and how long should it take?

Time study, motion study, method study, work measurement and work study compared
TermThe question it answersWhat you look atWhat you end up with
Work studyHow do we get more from the same people, machines and material?The whole job: its method and its timeA better method and a time standard for it. It is the umbrella over the next two terms.
Method studyHow should this job be done?The sequence of operations, the movement of material and people, the layout, the toolsA new method, written down, cheaper and easier than the old one
Motion studyWhich movements does the job need, and which can go?Hands, eyes and body inside one workstation, often from filmA workstation and a motion pattern with the wasted movements taken out
Work measurementHow long should this job take a qualified worker at a normal pace?The work content of a defined methodA time standard. Time study, work sampling and predetermined time systems are all ways to get one.
Time studyHow long does this job take when we time it directly?A run of cycles, element by element, with a stopwatch or from videoObserved time, then normal time after rating, then standard time after allowances

Definitions follow the ILO's Introduction to Work Study and the British Standard glossary of work study terms (BS 3138).

So the short version is two pairs. Work study is method study plus work measurement. Motion study is a part of method study, and time study is a part of work measurement. The phrase time and motion study is the everyday name for the whole thing.

Two vocabularies for one field

A good half of the confusion is geography. British practice, and the International Labour Organization textbook that carried it around the world, speaks of work study. American practice grew from Taylor's time study and the Gilbreths' motion study and joined the two names together. If your textbook is by Kanawaty or Currie you learned the left column. If it is by Barnes, Niebel or Maynard you learned the right one.

British and ILO terms next to the American terms for the same thing
British and ILO termAmerican termMeaning
Work studyMotion and time study; methods engineering; work designThe whole field: improve the method, then set the time
Method studyMethods analysis; methods engineering; motion studyRecording and questioning the way a job is done to find a better way
Work measurementWork measurement; time study, used looselySetting the time for a qualified worker to do a defined job
Basic timeNormal timeObserved time adjusted by the pace rating
Relaxation allowancePersonal and fatigue allowancesTime added for personal needs and recovery from effort
Standard time; standard minute value (SMV)Standard time; standard allowed minutes (SAM)Normal time plus allowances
Activity samplingWork samplingEstimating shares of time from random instant observations
Predetermined time standards (PTS)Predetermined motion time systems (PMTS)Building a time from tables of basic motions, such as MTM and MOST

In American plants, time study is often used as a loose name for all work measurement. In this guide it means direct timing only.

Method study: how should the job be done?

Method study is the systematic recording and critical examination of the way work is done, so as to make it easier and cheaper. It exists because the way a job is done today is rarely the way anyone designed it. It grew: a bench was moved, a part changed, someone left. Method study writes down what really happens and asks of each step whether it needs to exist.

The ILO text lists eight steps: select, record, examine, develop, evaluate, define, install and maintain. Older British texts shorten them to six and the acronym SREDIM.

  1. 1

    Select

    Pick the job worth studying: the bottleneck, the one with the most labour hours, the one people complain about.

  2. 2

    Record

    Write down the present method by watching it, not by reading the procedure. Use a process chart, a flow diagram, a two-handed chart or video.

  3. 3

    Examine

    Question every step: what is done and why, where, when, by whom and how. Ask each time whether it could be eliminated, combined, rearranged or simplified.

  4. 4

    Develop

    Design the new method with the people who do the job.

  5. 5

    Evaluate

    Compare the new method with the old: time, cost, quality, safety, effort.

  6. 6

    Define

    Write the new method down so that it can be taught and checked.

  7. 7

    Install

    Train people, change the layout and tools, and run it.

  8. 8

    Maintain

    Check that the new method is still in use and has not drifted back.

The recording tools are the ones a lean team already knows under other names. A flow process chart lists every operation, move, delay, inspection and storage. A flow diagram or spaghetti diagram draws the path on a floor plan. A multiple activity chart puts an operator and a machine on one time scale. The examine step, with its eliminate, combine, rearrange and simplify, is what lean calls ECRS. Sorting each step by value added and non value added is the same examination with a different label.

Motion study: which movements does the job need?

Motion study is method study with a magnifying glass. Method study looks at the flow of a job across a department. Motion study looks at what two hands do in the space of one bench: every reach, grasp, move and release. Frank and Lillian Gilbreth built it, first by watching bricklayers and then by filming work against a clock that read to fractions of a second.

Therbligs

The Gilbreths broke manual work into basic elements and named them therbligs, their own name spelled backwards with the th kept together. A paper of 1915 lists 16. Later lists run to 17 and then 18, with plan and hold added. Niebel and Freivalds sort them into two groups: effective therbligs that move the work forward, and ineffective ones that a better method should shrink or remove. The grouping is what makes the list useful on the floor. You do not need to code a job in therbligs to ask why the left hand is holding a part for eight seconds when a fixture could.

The therbligs, sorted by what a better method does with them

Effective: 8

Move the work forward. Make them shorter and easier.

  • Reach (transport empty)
  • Move (transport loaded)
  • Grasp
  • Release load
  • Pre-position
  • Use
  • Assemble
  • Disassemble

Ineffective: 9

Add time and no progress. Shrink or remove them.

  • SearchFix: a fixed place for every part
  • SelectFix: one part type per bin
  • PositionFix: guides, chamfers, stops
  • HoldFix: a fixture or clamp
  • InspectFix: gauges built into the step
  • PlanFix: a fixed, taught sequence
  • Unavoidable delayFix: balance the two hands
  • Avoidable delayFix: remove the cause
  • RestFix: lower the effort of the job

Two groups. Eight effective therbligs move the work forward: reach, move, grasp, release load, pre-position, use, assemble and disassemble. Nine ineffective therbligs are the ones to shrink or remove, each with a typical fix: search, select, position, hold, inspect, plan, unavoidable delay, avoidable delay and rest.

Grouping after Niebel and Freivalds, who list 17. The 18th in most modern lists, find, is the instant a search ends and is usually folded into search. Motion study keeps the left column short and tries to delete the right one.

The principles of motion economy

Ralph Barnes turned the Gilbreths' findings into 22 principles of motion economy, in three groups: the use of the human body, the arrangement of the workplace, and the design of tools and equipment. A few carry most of the benefit.

  • Both hands should start and finish their motions together, and should not be idle at the same time except during rest.
  • Arm motions should be symmetrical and in opposite directions.
  • Use the smallest body movement that does the job: fingers before wrists, wrists before forearms, forearms before shoulders.
  • Give every tool and part a fixed place, inside the normal reach of the hands.
  • Feed parts by gravity to the point of use, and let finished parts drop away.
  • Free the hands from holding. A hand is a poor vice. Use a fixture or a foot pedal.

Motion study is where method study meets ergonomics. The same film that shows a wasted reach shows a raised shoulder. An ergonomic assessment scores the posture, and motion study removes the reason for it.

Work measurement: how long should the job take?

Work measurement is the application of techniques to establish the time for a qualified worker to carry out a task at a defined rate of working. Each part of that sentence matters. Qualified means trained and able, not the fastest person on the shift. A defined rate means a normal pace that can be kept up all day. And task means a defined method. A time with no method attached is not a standard.

Time study is one of five techniques the ILO lists. They differ in whether you watch the job, how much detail you get and how much effort it takes.

The work measurement techniques and what each is for
TechniqueHow the time is foundBest for
Time studyTime a run of cycles directly, rate the pace, add allowancesShort, repeating manual jobs that exist today
Work sampling (activity sampling)Tally what is happening at random instants; shares of tallies estimate shares of timeLong, irregular or shared work; finding where time goes across a department
Predetermined time systems (MTM, MOST, MODAPTS)Break the job into basic motions and add up their times from published tablesJobs that do not exist yet; very short cycles at high volume; no pace rating needed
Standard dataBuild the time from your own library of element times taken in earlier studiesFamilies of similar jobs, where a new part differs only in size or count
Structured estimatingAn experienced person estimates the time, job by job or by comparing with benchmark jobsOne-off and long-cycle work such as maintenance and toolroom jobs

The five are the ILO's list. Machine and system data, such as cycle counters, are a sixth source for machine-paced work, though they record what happened, not what should happen.

The guide to time study vs work sampling goes through that one choice in detail, and work sampling has the method and the formula.

Time study: the direct way to measure

A time study records the times of a specific job, element by element, under stated conditions, and works them up into the time the job should take at a defined pace. It is the technique people mean when they picture someone with a stopwatch and a clipboard, though a camera has replaced both in many plants.

  • Break the job into elements with clear break points. See how to break a job into elements.
  • Time enough cycles for the accuracy you need. See how many cycles to time.
  • Average the readings for each element. That is the observed time.
  • Rate the operator's pace against normal and adjust. Observed time x rating = normal time, which British texts call basic time.
  • Add allowances for personal needs, fatigue and unavoidable delays. Normal time x (1 + allowance) = standard time.

What a time study produces: three times, each built on the one before

Example numbers
  1. Observed time

    42 s

    The average of the timed cycles

  2. x rating 100%
  3. Normal time

    42 s

    British texts: basic time

  4. x (1 + 12% allowance)
  5. Standard time

    47.0 s

    76.5 cartons an hour

Three steps rising left to right. Observed time 42 seconds, multiplied by a rating of 100 percent, gives a normal time of 42 seconds. Normal time multiplied by 1 plus a 12 percent allowance gives a standard time of 47.0 seconds, which is 76.5 cartons an hour.

The packing job from the example further down, after its method was improved. The rating adjusts for the pace of the person timed. The allowance adds personal, fatigue and delay time. Neither step looks at whether the method is a good one.

The full procedure is in how to conduct a time study. What matters here is where it sits. A time study measures a method. It does not judge whether the method is any good. Point a stopwatch at a job with a 14 second walk in every cycle and you get an accurate standard that includes the walk.

Where Taylor and the Gilbreths fit

The two halves of the field have different parents, and the parents did not get on. That history is why there are two names.

Two beginnings, one field: time study and motion study from 1878 to 1957

  1. 1878
    Time studyTaylor joins Midvale Steel. In the early 1880s he starts timing machine-shop work with a stopwatch, element by element.
  2. 1898
    Time studyBethlehem Steel, to 1901: the shovelling and pig iron studies.
  3. 1903
    Time studyTaylor publishes Shop Management.
  4. 1909
    Motion studyFrank Gilbreth's Bricklaying System: by his account, 18 motions a brick cut to about 5.
  5. 1911
    Time studyThe Principles of Scientific Management. Moulders walk out at Watertown Arsenal when a time study starts unannounced.
  6. 1911
    Motion studyGilbreth publishes Motion Study.
  7. 1914
    Motion studyLillian Gilbreth publishes The Psychology of Management.
  8. 1915
    Time studyTaylor dies. Congress bars stopwatch timing in army arsenals and navy yards.
  9. 1915
    Motion studyA Gilbreth paper lists 16 basic elements of motion, later named therbligs.
  10. 1921
    Motion studyThe Gilbreths' paper An Indictment of Stop-Watch Time Study.
  11. 1924
    Motion studyFrank Gilbreth dies. Lillian carries the work on for decades.
  12. 1937
    JoinedBarnes publishes Motion and Time Study: one subject, one textbook.
  13. 1948
    JoinedMethods-Time Measurement (MTM) gives each basic motion a time.
  14. 1957
    JoinedThe ILO's Introduction to Work Study spreads the British vocabulary worldwide.

A timeline with two lanes. The time study lane follows Frederick Taylor from Midvale Steel in 1878 to his death in 1915. The motion study lane follows Frank and Lillian Gilbreth from 1909 to 1924. The lanes join in 1937 with Barnes's Motion and Time Study, then MTM in 1948 and the ILO's Introduction to Work Study in 1957.

Taylor's side is on the left and the Gilbreths' on the right. They argued for a decade, and the textbooks of the 1930s joined them.

Frederick Winslow Taylor is usually called the father of time study. He joined the Midvale Steel Company in Philadelphia in 1878, became a foreman, and in the early 1880s began timing machine-shop work with a stopwatch, splitting each job into elements so that a fair day's work could be set from data instead of argument. He carried the work on at Bethlehem Steel from 1898 to 1901, with the shovelling and pig iron studies that became famous. He published Shop Management in 1903 and The Principles of Scientific Management in 1911.

Frank Gilbreth came at the same problem from the other side. As a bricklaying contractor he noticed that no two bricklayers worked the same way, and set out to find the best way. By his own account he cut the motions to lay a brick from 18 to about 5 and raised output from 120 to 350 bricks an hour, with an adjustable scaffold and a better arrangement of bricks and mortar. He published Bricklaying System in 1909 and Motion Study in 1911. Lillian Gilbreth, a psychologist, was his partner in all of it. Her book The Psychology of Management appeared in 1914, and she carried the work on for decades after his death in 1924. Together they filmed work against a fast clock, which they called micromotion study, and traced the path of a hand with a small lamp on a long-exposure photograph.

The Gilbreths thought the stopwatch was the wrong instrument. Their argument was that timing a poor method only made the poor method official, and that a watch read by eye was too coarse to study motions. In 1921 they put it in writing in a paper to the Taylor Society titled An Indictment of Stop-Watch Time Study. Taylor's followers answered that motion study without a time was no basis for planning or pay.

Both were right, and practice joined the two. By the 1930s American textbooks treated them as one subject. Barnes's Motion and Time Study came out in 1937. In 1948 Maynard, Stegemerten and Schwab published Methods-Time Measurement, which gave each basic motion a time and so merged the Gilbreths' elements with Taylor's clock. British practice arrived at the same place under the name work study, and the ILO's Introduction to Work Study, first published in 1957, spread that vocabulary across much of the world.

One more piece of the history still matters on the floor. In 1911 moulders at the US Army's Watertown Arsenal walked out when a time study began without the workforce being prepared for it. A House committee held hearings, and from 1915 Congress wrote a bar on stopwatch timing and bonus pay into the appropriation acts for army arsenals and navy yards, where it stayed for decades. The lesson is older than any modern plant: how a study is introduced decides whether it can be done at all. The guide to planning a time study covers what to say first.

Which comes first: method before measurement

Method study comes first. A time standard is a promise that a defined method takes a defined time. If the method still has waste in it, the standard has waste in it, and from then on the waste is protected: it is in the cost, the staffing plan and perhaps the pay. If the method changes afterwards, the standard is void and the study has to be done again.

Illustrative example. A packer builds a carton, fills it, labels it and puts it on a pallet. Each cycle takes 60 seconds: 38 seconds at the bench, 14 seconds walking to a pallet of flat cartons behind her, and 8 seconds looking for the right label roll.

Illustrative: the same packing job measured before and after a method study
Time study firstMethod study first
Work at the bench38 s38 s
Walking for cartons14 s3 s (cartons on a rack at the bench)
Looking for labels8 s1 s (one roll per product, on a marked peg)
Normal time per carton (rating 100)60 s42 s
Standard time (allowance 12 percent)60 x 1.12 = 67.2 s42 x 1.12 = 47.0 s
Output at standard3,600 / 67.2 = 53.6 cartons an hour3,600 / 47.04 = 76.5 cartons an hour

The 12 percent allowance and the rating of 100 are example figures. Both standards are equally accurate. Only one of them is worth having.

Before and after: the same job, measured with equal care

Example numbers

Before: time study first

60 s a carton

  • Work at the bench: 38 s
  • Walking for cartons: 14 s
  • Looking for labels: 8 s

Standard: 60 x 1.12 = 67.2 s, or 53.6 cartons an hour

After: method study first

42 s a carton

  • Work at the bench: 38 s
  • Walking for cartons: 3 s
  • Looking for labels: 1 s

Standard: 42 x 1.12 = 47.0 s, or 76.5 cartons an hour

Two bars on the same scale. Before the method study the cycle is 60 seconds: 38 at the bench, 14 walking and 8 looking for labels, giving a standard of 67.2 seconds. After it the cycle is 42 seconds: 38 at the bench, 3 walking and 1 looking, giving a standard of 47.0 seconds.

The 38 seconds of real work never changed. The 22 seconds of walking and looking fell to 4. Time the job first and those 22 seconds become part of the standard.

The first study is not wrong. It is a faithful measurement of 22 seconds of walking and searching in every cycle. It would price the product, staff the line and judge the packer on a method nobody chose.

Where timing comes first anyway

  • As a baseline. Rough timing of the present method tells you how big each loss is, so you know which to attack and can prove the gain afterwards. This is measurement in the service of method study, and it sets no standard.
  • To choose where to look. A work sampling study across a department finds the area that loses the most time. Method study then goes there.
  • When the decision cannot wait. A quote is due on Friday and the job runs today. Time it as it is, mark the standard as temporary and note the losses you saw.

So the order in practice is a loop: time the present method roughly, improve the method, write it down, measure it properly, set the standard, and study it again when the method changes.

One job seen through each study

The differences are easiest to see when all four are pointed at the same packing bench.

Illustrative: what each study would do at the same packing bench
StudyWhat the engineer doesWhat comes back
Method studyCharts every step from flat carton to pallet, and draws the packer's path on a floor planThe walk for cartons and the search for labels can go. New layout: cartons on a rack at the bench, one label roll per product.
Motion studyFilms both hands filling and taping one cartonThe left hand holds the flaps shut for 5 seconds while the right hand reaches for the tape gun. A flap guide and a hanging tape gun free it.
Time studyTimes 20 cycles of the new method, element by element, rates the pace and adds allowancesA standard time of 47 seconds a carton, and the output per hour that follows from it
Work samplingLooks at the whole packing area at random times for a weekThe share of the area's time that goes on packing, waiting for product, walking and rework

Method study and motion study change the job. Time study and work sampling describe it. A plant that only does the second pair knows its losses to the second and still has them.

Mix-ups worth avoiding

  • Time study and time and motion study. A time study only measures. A time and motion study, as the phrase is used today, improves the method and then measures it.
  • Method study and methods engineering. Same thing. Methods engineering is the American name, usually credited to H.B. Maynard.
  • Work study and work measurement. Work measurement is half of work study. The other half is method study.
  • Cycle time and standard time. Cycle time is what the job took. Standard time is what it should take a qualified worker at a normal pace, with allowances. The cycle time vs lead time guide has the first.
  • Time study and work sampling. Time study watches one job continuously. Work sampling glances at many jobs at random moments. They are both work measurement.
  • Motion study and ergonomics. Motion study removes wasted movement to save time and effort. Ergonomics scores the risk of injury. They use the same film and often reach the same fix.
  • Work study and jobs for students. In the United States, work-study is also a college funding programme. It has nothing to do with this.

What video changes

The Gilbreths needed a hand-cranked camera and a special clock to do motion study, and Taylor's engineers needed a trained eye and a watch. One recording now serves both. A phone on a tripod captures the method, the motions and the times in a single pass, and it can be replayed, which a stopwatch reading cannot.

That removes the old reason for doing the two halves apart. LeanSuite's time and motion study takes video of a station and times every element on a timeline linked to the footage, split into value-added, necessary and waste, so the same study that sets the time also shows what to take out. An engineer still reviews it, decides the method and certifies the result.

Templates and tools

FAQ

Questions about time study vs motion study vs method study

  1. Work study is the whole field: it improves the way a job is done and then sets how long it should take. It has two parts, method study and work measurement. Time study is one technique inside work measurement, in which the job is timed directly, the pace is rated and allowances are added. So time study is a part of work study, not a rival to it.

  2. Time study measures how long a job takes and turns that into a standard time. Motion study examines the movements the job is made of, to remove the wasted ones and make the rest easier. Time study comes from Frederick Taylor and uses a stopwatch or video. Motion study comes from Frank and Lillian Gilbreth and uses film. Used together they are a time and motion study.

  3. Method study asks how a job should be done: it records the present method, questions each step and develops a better one. Work measurement asks how long the job should take a qualified worker at a normal pace, using time study, work sampling or predetermined time systems. Method study comes first, because a time set on a poor method builds the waste into the standard.

  4. Two sets of people. Frederick Winslow Taylor developed stopwatch time study at Midvale Steel in the 1880s and is called the father of time study. Frank and Lillian Gilbreth developed motion study in the early 1900s, starting with bricklaying. The two approaches were rivals at first and were joined into one subject, motion and time study, by the 1930s.

  5. A time and motion study examines a job in two ways: the motions it is made of, to find a better method, and the time it takes, to set a standard for that method. The result is a written method with wasted steps removed and a standard time used for costing, staffing, line balancing and capacity planning.

  6. Originally to set a fair day's work and piece rates from measurement instead of argument, and to find the least tiring way to do manual jobs. Today the same studies feed product costing and quotes, staffing, line balancing, capacity plans, workstation layout, ergonomic reviews and improvement projects. Setting pay is only one use among several.

  7. Method study. A time standard belongs to one defined method, so the method should be improved and written down before it is measured. Timing first gives an accurate standard for a job that still contains walking, searching and waiting. The one exception is a rough timing of the present method as a baseline, which sets no standard.

  8. Therbligs are the basic elements of manual work defined by Frank and Lillian Gilbreth, such as search, select, grasp, transport loaded, position, assemble, use and release load. The name is Gilbreth spelled backwards with the th kept together. The Gilbreths' 1915 list had 16 and modern lists have 18. They are used in motion study to find movements a better method can remove.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.