Practical guide · Standard work, SOPs and training
Time study in food and beverage manufacturing: crews, changeovers and wash-downs
Short answer
In a food or beverage plant the line sets the pace, so a time study rarely means a stopwatch standard for one operator. Three studies pay back: how many people the line needs at each rate, how long each changeover and wash-down takes and why, and where the shift goes.
On a filling or packing line the machine sets the rate and people tend, feed, check, clear jams and pack off. So study the crew, not a single cycle: time the manual jobs per case, multiply by the line rate and you have the people needed at each speed. Then film a changeover from the last good unit of one product to the first good unit of the next and sort every minute into strip, clean, verify, reassemble and start-up. Leave the cleaning and verification steps in the food safety plan exactly as written, and take out the fetching, waiting and searching around them. In the worked example here that takes an allergen changeover from 135 minutes to 92 with no change to the clean.
Last reviewed:
Why a food line is not an assembly line
One line, two kinds of work
Example numbersMachine-paced: 60 tubs a minute
1 operator tending
Station 1
Filler
Top up hopper, clear jams
Station 2
Lidder and sealer
Load lids and film
Station 3
Checkweigher, metal detector
Hourly checks, rejects
Station 4
Date coder
Code check at start-up
Study with work sampling or full-shift video. There is no cycle to time.
Pack-off: paced by the line, 5 cases a minute
Station 5
Case packing
18.4 s of work per case
Station 6
Palletizing
7.5 s of work per case
Study with a time study per case, then multiply by the line rate.
A tub filling line at 60 tubs a minute. Stations 1 to 4 (filler, lidder and sealer, checkweigher and metal detector, date coder) are machine-paced and tended by one operator. Stations 5 and 6 (case packing by two people, palletizing by one) are manual work paced by the line at 5 cases a minute.
The classic time study assumes one person repeating one cycle at their own pace. Time the cycle, rate it, add allowances, and you have a standard time. Most food and beverage work does not look like that.
A filler, a wrapper or a canning line runs at a set speed. The people around it do not make the product one unit at a time. They keep the machine fed and running, check what comes off it, and pack it away. Timing the line tells you the machine's rate, which the display already shows. The question worth an engineer's week is a different one: how much human work does this line need per minute at this rate, and who is doing it?
- Paced work. The line decides how often a case, a tray or a pallet is due. People keep up or the line backs up.
- Tending work. Loading film, lids and cartons, topping up a hopper, clearing a jam, doing the hourly weight and seal checks. It comes at irregular intervals.
- Self-paced manual work. Hand packing, tray loading, weighing, kitting ingredients, decorating. Here the ordinary time study fits.
- Not running at all. Product changeovers, allergen cleans, wash-down, clean in place (CIP), start-up and line clearance. In many plants this is the biggest block of time nobody has measured.
Each kind of work needs its own way of measuring. The rest of this page takes them in turn, using one illustrative line throughout: a tub filling line for hummus running 60 tubs a minute, 12 tubs to a case, with a crew of four.
Where the time goes in a food plant
Before choosing a method, sort the plant's work into the kinds below. The right study follows from the kind of work, and most lines have all of them.
| Kind of work | Examples | What sets the time | What a study can change |
|---|---|---|---|
| Machine-paced running | Filling, sealing, wrapping, baking, cooking, cooling | The process and the machine: fill rate, bake time, cooling curve | Very little. Speed belongs to process and quality engineering, not to a stopwatch. |
| Paced manual work | Case packing, tray loading, palletizing off the end of the line | Line rate x the manual work per case | Method, layout, crew size at each rate |
| Tending | Film and lid changes, hopper top-ups, jam clearing, in-process checks | How often the event comes and how long it takes | Reach and walking, frequency of jams, who covers what |
| Self-paced manual work | Hand packing, weighing and batching, decorating, kitting | The operator and the method | Method, workstation, standard time |
| Changeover and cleaning | Product change, allergen clean, wash-down, CIP, start-up, line clearance | The cleaning procedure, plus everything around it | The fetching, waiting, searching and adjusting around the clean. Not the clean itself. |
| Stops | Jams, short stops, waiting for materials or for a check | Causes upstream of the people | Finding the cause; see where a full shift on video goes |
A picture of one day makes the priorities plain. The illustrative line below is staffed for two shifts, 960 minutes. It has one allergen changeover, two short label changes and an end of day sanitation. Add breaks and short stops and it fills tubs for 520 of those minutes: 54.2 percent. Nobody on the crew is slow. The time is in the changeovers and the cleaning, so that is where the first study should point.
Where 960 staffed minutes go
Example numbers- Running at rate520 min (54.2%)
- Allergen changeover with wash-down (1)135 min (14.1%)
- End of day sanitation120 min (12.5%)
- Short stops and jams75 min (7.8%)
- Breaks60 min (6.3%)
- Label changes (2 x 25 min)50 min (5.2%)
Of 960 staffed minutes the line runs for 520, 54.2%. Allergen changeover with wash-down (1): 135 minutes. End of day sanitation: 120 minutes. Short stops and jams: 75 minutes. Breaks: 60 minutes. Label changes (2 x 25 min): 50 minutes.
Get this split from a downtime log if the plant keeps an honest one, from work sampling of the line state over two weeks, or from video of whole shifts. A 30 minute stopwatch study of the packers would have missed all of it.
Which study answers which question
Start from the decision you need to make, not from the method you know. The family of methods is laid out in the guide to time and motion study; in a food plant the choice usually comes down to these.
Match the study to the kind of work
If the work is
People paced by the line
Case packing, tray loading, palletizing
Use
Crew loading study
Time the work per case, multiply by line rate
If the work is
People tending a machine
Filler and wrapper operators
Use
Work sampling or full-shift video
Random observations: what share of time on each task
If the work is
People working at their own pace
Hand packing, weighing, batching
Use
Time study and standard time
Elements, rating, allowances
If the work is
The line stopped
Changeover, allergen clean, wash-down, start-up
Use
Changeover study from video
Buckets, then fixed, internal and external
People paced by the line (Case packing, tray loading, palletizing): use a Crew loading study. People tending a machine (Filler and wrapper operators): use a Work sampling or full-shift video. People working at their own pace (Hand packing, weighing, batching): use a Time study and standard time. The line stopped (Changeover, allergen clean, wash-down, start-up): use a Changeover study from video.
| You need to know | Use | Why |
|---|---|---|
| How many people the line needs at each rate | Crew loading study: a time study of each manual job per case, multiplied by line rate | The line sets how often the work comes. The study sets how long each piece takes. |
| What the filler or wrapper operator does all shift | Work sampling, or video of whole shifts | Tending is irregular. No single cycle exists to time. |
| The standard for hand packing, weighing or batching | Stopwatch or video time study, then standard time | Self-paced, repeating, one station: the textbook case. |
| Why a changeover takes two hours | Changeover study from video, sorted into buckets and into internal and external work | The job is long, done by several people at once, and happens a few times a week. Video catches all of them together. |
| Where the shift goes | Downtime log with reason codes, line-state sampling, or OEE | The loss is spread across the day in pieces too small to notice. |
| Whether the packing job is hurting people | Ergonomic assessment of the station | Repetitive reaching and lifting at line rate is a risk a time standard does not show. |
Two methods are a poor fit almost everywhere in this industry. Predetermined time systems are slow to apply to work that changes with every product format, and a stopwatch standard on the filler operator measures somebody watching a machine. Long jobs worked by a team, such as a full sanitation shift, need the approach in the guide to timing long cycle and team work.
Crew loading on a paced line
Crew loading asks one thing: at this line rate, how many minutes of human work arrive each minute? If the answer is 2.2, the pack-off needs three people, and each will be busy about 72 percent of the time. The sum is the same one used in line balancing, with the line rate standing in for takt.
From a time per case to a crew
- 1
List the manual jobs and what triggers each
- 2
Time each job per trigger
- 3
Turn the line rate into triggers per minute
- 4
Multiply and add
- 5
Round up, then look at the load
- 6
Repeat for every rate and format you run
- 1
List the manual jobs and what triggers each
Per case: erect, load, close. Per pallet: change the pallet, wrap, label. Per reel or per hour: film change, weight check. Write the trigger next to each job, because the trigger is what turns a time into a load.
- 2
Time each job per trigger
Film the station or use a stopwatch, and time the elements over enough cycles. Rate the pace and add allowances as in any time study. The result is a standard time per case, per pallet or per event.
- 3
Turn the line rate into triggers per minute
Units per minute divided by units per case gives cases per minute. Cases per minute divided by cases per pallet gives pallets per minute.
- 4
Multiply and add
Work per minute for a job = triggers per minute x standard time per trigger. Divide by 60 seconds to express it in people. Add the jobs that one crew shares.
- 5
Round up, then look at the load
Crew = the load in people, rounded up. Load per person = load divided by crew. A crew loaded close to 100 percent has no time to deal with a jammed case, so the line will stop.
- 6
Repeat for every rate and format you run
A crew that fits 60 a minute may not fit 80, and a 6 pack loads the packers differently from a 12 pack. Build the table once and the supervisor can staff from it.
Worked example: case packing and palletizing at three line rates
Illustrative example. On the hummus line, tubs leave the checkweigher and metal detector at 60 a minute and are packed by hand, 12 to a case. A video time study of the case packing job gives the elements below.
| Element | Normal time (s) |
|---|---|
| Erect case and set it on the stand | 4.0 |
| Load 12 tubs in two layers | 8.5 |
| Check the date code and close the flaps | 2.0 |
| Push the case to the taper | 1.5 |
| Normal time per case | 16.0 |
| Standard time per case with a 15 percent allowance | 18.4 |
16.0 x 1.15 = 18.4 seconds. The 15 percent allowance is illustrative; use your own plant's allowance policy.
Palletizing was timed the same way: 6.0 seconds to place each case, plus 90 seconds to change and wrap a pallet of 60 cases, which is 1.5 seconds a case. That makes 7.5 seconds per case. At 60 tubs a minute the line makes 5 cases a minute, so case packing needs 5 x 18.4 = 92 seconds of work every minute, or 1.53 people, and palletizing needs 5 x 7.5 = 37.5 seconds, or 0.63 of a person.
| Line rate (tubs/min) | Cases/min | Case packing (people) | Palletizing (people) | Total load | Crew | Load per person |
|---|---|---|---|---|---|---|
| 40 | 3.33 | 1.02 | 0.42 | 1.44 | 2 | 72% |
| 60 | 5.00 | 1.53 | 0.63 | 2.16 | 3 | 72% |
| 80 | 6.67 | 2.04 | 0.83 | 2.88 | 3 | 96% |
| 80, with a fourth person | 6.67 | 2.04 | 0.83 | 2.88 | 4 | 72% |
Load in people = cases per minute x standard seconds per case / 60. Crew members share case packing and palletizing.
Pack-off load at three line rates
Example numbers40 tubs a minute (3.33 cases)
1.44 people of work, crew of 2: 72%
60 tubs a minute (5.00 cases)
2.16 people of work, crew of 3: 72%
80 tubs a minute (6.67 cases)
2.88 people of work, crew of 3: 96%
- Case packing, 18.4 s per case
- Palletizing, 7.5 s per case
- Crew on the line
At 40 tubs a minute the pack-off needs 1.44 people of work; a crew of 2 is loaded to 72%. At 60 tubs a minute the pack-off needs 2.16 people of work; a crew of 3 is loaded to 72%. At 80 tubs a minute the pack-off needs 2.88 people of work; a crew of 3 is loaded to 96%.
Read the 80 row twice. Three people can do it on paper at 96 percent, which means that one crushed case or one late pallet stops the line. The honest choices are a fourth person, or taking seconds out of the job first: a case erector, tubs presented in rows of six, a stand at the right height. Each second off the case cycle is worth 0.11 of a person at this rate. The fourth crew member, the filler operator, is a tending job: a sampling study of 200 random observations found the operator busy in 154, or 77 percent, so there is little spare there to lend to the pack-off.
The changeover and wash-down study
A changeover in a food plant is a SMED problem with one extra rule: part of it is cleaning that protects the consumer, and that part is not yours to shorten. The study exists to find everything else. Measure from the last good unit of the old product to the first good unit of the new one, at rate and released by quality.
- 1
Agree the scope with quality and sanitation first
Sit down with the food safety lead and the sanitation supervisor. Mark which steps are fixed by the cleaning procedure and the food safety plan. Say out loud that those steps are outside the study's reach.
- 2
Film the whole changeover, every person
One camera wide on the machine, a second on the wash bay or the parts table if work happens there. Start before the last good unit and stop after the first good one. Tell the crew why, and follow the plant's rules on filming.
- 3
List every task with a start, an end and a name
Go through the footage and write one line per task per person, including the walks and the waits. A wait is a task with nobody in the frame.
- 4
Sort each task into a bucket
Strip and prepare, clean and sanitize, wait and verify, reassemble and materials, start-up. The buckets show where the time sits before anyone argues about a single task.
- 5
Mark each task fixed, internal or external
Fixed: set by the cleaning procedure or a verification test. Internal: needs the line stopped. External: could be done while the line still runs or after it restarts. Fetching the cleaning cart is external. Foam contact time is fixed.
- 6
Move, remove and shorten, in that order
Move external work out of the stop. Remove waits by calling people before they are needed. Shorten what is left with pre-kitted change parts, a second pair of hands and written settings. Leave the fixed tasks alone.
- 7
Write the new sequence and film it again
Put the sequence on a checklist with who does what, in what order. Run it, film it, and compare bucket by bucket. Have quality sign off that the clean was done to the procedure both times.
Worked example: an allergen changeover with wash-down
Illustrative example. The hummus line changes from a recipe that contains sesame to one that does not. The procedure calls for a full wet clean and an allergen swab before restart. Filmed from last good tub to first good tub, the changeover took 135 minutes. The team listed twelve tasks, marked each one, and ran the new sequence two weeks later.
| Task | Type | Before | After | What changed |
|---|---|---|---|---|
| Run out product and empty the hopper | Internal | 6 | 6 | Nothing |
| Fetch tools, hoses, chemicals and the parts cart | External | 9 | 0 | Cart stocked and parked at the line before the last tub |
| Strip the filler: nozzles, hopper, guards | Internal | 14 | 9 | A packer strips the guards while the operator takes the nozzles |
| Dry pick-up and pre-rinse | Internal | 10 | 8 | Hose and squeegee already at the line |
| Apply foam and hold for the contact time | Fixed | 15 | 15 | Nothing. Set by the cleaning procedure. |
| Scrub and rinse | Fixed | 12 | 12 | Nothing. Set by the cleaning procedure. |
| Sanitize and drain | Fixed | 8 | 8 | Nothing. Set by the cleaning procedure. |
| Wait for quality to arrive | Wait | 11 | 0 | Quality is called when sanitizing starts |
| Visual inspection, allergen swab and result | Fixed | 12 | 12 | Nothing. The test takes as long as it takes. |
| Reassemble with the next product's parts | Internal | 16 | 10 | Clean parts kitted in order on a board; no searching |
| Bring lids, film and labels; line clearance | Part external | 8 | 3 | Packers stage materials during the clean; the 3 minute clearance check stays |
| Start-up: prime, set weights and seal, first good tub | Internal | 14 | 9 | Settings sheet with last run's weights and sealer settings |
| Total | 135 | 92 | 43 minutes shorter, 31.9 percent |
Fixed tasks total 47 minutes before and after. Everything else fell from 88 minutes to 45.
The tasks grouped into buckets show where the gain came from.
The changeover by bucket: 135 minutes to 92
Example numbersBefore: 135 min
After: 92 min
- Strip and prepare29 to 15
- Clean and sanitize45 to 43
- Wait and verify23 to 12
- Reassemble and materials24 to 13
- Start-up14 to 9
Before, 135 minutes: Strip and prepare 29, Clean and sanitize 45, Wait and verify 23, Reassemble and materials 24, Start-up 14. After, 92 minutes: Strip and prepare 15, Clean and sanitize 43, Wait and verify 12, Reassemble and materials 13, Start-up 9.
| Bucket | Before | After | Saved |
|---|---|---|---|
| Strip and prepare | 29 | 15 | 14 |
| Clean and sanitize | 45 | 43 | 2 |
| Wait and verify | 23 | 12 | 11 |
| Reassemble and materials | 24 | 13 | 11 |
| Start-up | 14 | 9 | 5 |
| Total | 135 | 92 | 43 |
The 2 minutes saved in the clean bucket are from the pre-rinse set-up. Foam, scrub, rinse and sanitize are unchanged at 35 minutes.
At 60 tubs a minute, 43 minutes is 2,580 tubs, or 215 cases, each time this changeover runs. On the illustrative day it lifts running time from 520 to 563 minutes, 54.2 to 58.6 percent. No cleaning step was touched and nobody worked faster. The crew stopped fetching, waiting and searching.
What the study must not touch
Fixed by the food safety plan, and everything around it
Example numbersBefore
After
47 min
Cleaning and verification, unchanged
88 to 45 min
Fetching, stripping, waiting, reassembly, start-up
2,580 tubs
Extra output per changeover at 60 a minute
Cleaning and verification take 47 minutes before and after. The work around them falls from 88 minutes to 45, a cut of 48.9%.
A time study in a food plant has a boundary that one in a machine shop does not. Cleaning works through four things together: time, mechanical action, chemical concentration and temperature. Cut the time and one of the other three has to rise to make up for it. That is a decision for the people who own the cleaning procedure, backed by their own testing. It is never a by-product of a changeover project.
In the United States, sanitation controls and food allergen controls are among the preventive controls a facility writes into its food safety plan under 21 CFR Part 117, and many plants also validate their allergen cleans with allergen-specific tests. Other countries and customer standards have their own rules. The point for the engineer is simple: these steps are written down for a reason you may not see from the floor.
- Mark fixed tasks on the task list before anyone discusses savings, and have quality confirm the marking.
- Do not shorten contact times, rinse steps, drying, swab counts or test read times. Do not skip a verification because the last twenty passed.
- Do not reassemble or load materials ahead of release if the procedure says release comes first.
- If the study suggests the clean itself could change, for example a different sequence or a tool-less design that cleans faster, hand that to quality and sanitation as a proposal. They decide and re-verify.
- Record that the clean was done to procedure in both the before and after films. A faster changeover that fails a swab is a slower changeover.
This is general practice for studying work. It is not food safety or regulatory advice, and your food safety plan and the people responsible for it have the final word.
Measures to agree before you start
Food plants argue about definitions more than about numbers. Settle these before the first film, write them on the study sheet, and keep them the same for the after study.
- Changeover time. Last good unit of the old product to first good unit of the new one, at rate and released. A changeover that ends when the machine is reassembled hides the start-up.
- What counts as planned. OEE is availability x performance x quality, and plants differ on whether scheduled sanitation sits inside or outside planned production time. Either works. Pick one and say which.
- Start-up loss. Count the tubs rejected for weight, seal or code before the first good one, and the minutes they took. It belongs to the changeover.
- Giveaway. Product filled above the declared weight. A crew that restarts fast by setting the filler heavy has moved the loss, not removed it.
- Crew, not headcount. Record who was on the line during the study, including the people borrowed from next door during the changeover.
- Format. Record the product, pack size and case count. A standard for a 12 pack says little about a 6 pack.
Mistakes that are specific to food and beverage
Food and beverage time study mistakes and what to do in their place
Mistake
Timing the line and calling it a time study
What goes wrong: You have measured the filler's speed. The crew size and the lost time are still unknown.
Do this
Time the manual work per case and multiply by the line rate. Sample or film the tending jobs.
Mistake
Treating cleaning time as waste to cut
What goes wrong: A shorter contact time or a skipped swab puts consumers at risk and can bring a recall.
Do this
Mark cleaning and verification as fixed. Take the minutes out of the work around them.
Mistake
Stopping the clock at reassembly
What goes wrong: The start-up, with its rejects and adjustments, vanishes from the study.
Do this
Measure to the first good unit at rate, released by quality.
Mistake
Studying one product
What goes wrong: The standard fits the easy SKU. The sticky one, the small pack and the allergen change behave differently.
Do this
Study the formats that make up most of the volume, and each type of changeover in the matrix.
Mistake
Studying the best crew on day shift
What goes wrong: Seasonal and agency crews with two weeks on the line cannot hit the number.
Do this
Study experienced operators for the standard, and plan a learning period for new starters.
Mistake
Loading the crew to 100 percent
What goes wrong: Every jam becomes a line stop because nobody has a free second.
Do this
Leave room in the load, or remove seconds from the job before removing a person.
Mistake
Ignoring where people stand and walk
What goes wrong: A packer who walks six steps for every stack of cases loses the time the study was looking for.
Do this
Draw the walk on a spaghetti diagram and move the materials.
The people side
Packing crews have heard that a study means fewer people on the line. Sanitation crews have heard that it means less time to do a job they are personally signed against. Both fears are reasonable, and both distort the study if they are left alone.
- Say what the study is for before the camera comes out, and say what it is not for. If the aim is changeover time, say that crew numbers are not in scope.
- Tell the sanitation team, in front of their supervisor, that cleaning steps are fixed and the study is looking at what holds them up.
- Many crews are seasonal or from an agency, and several languages may be spoken on one line. Explain the study in the languages the crew uses, with a picture of the result you expect.
- Cold rooms, wet floors, gloves, sleeves and hearing protection all slow work down for good reasons. Time the job as it is really done in that gear, and let the allowance reflect the conditions.
- Packing at line rate is repetitive work. If the study shows a job at 90 percent load with a reach above shoulder height, treat that as a finding and run an ergonomic assessment before anyone talks about rate.
- Show the crew the film and the task list first. They will spot the missing tool and the pointless walk faster than the engineer will.
This is general practice, not legal or labor relations advice. Where a union agreement or works council covers work measurement or filming, follow it.
Templates, tools and related guides
LeanSuite's SMED module runs each changeover as a timed checklist, and its AI splits a filmed changeover into internal and external tasks. Time and motion study does the same for a packing station: film it and the AI times every element on a timeline that links back to the video, for an engineer to review. Both sit on AI video analysis. See how plants in food and beverage and packaging and converting use them.
- SMED: the changeover method in full, with internal and external work and a worked study.
- Time study from video: how to film and break down a job without a stopwatch.
- Line balancing and the line balancing product page: sharing work across a crew.
- Work sampling: for tending jobs and for the state of the line across two weeks.
- Spaghetti diagram and workstation design: where people walk and reach at the pack-off.
- Ergonomic study: posture and lifting risk at the packing station.
- SMED changeover worksheet, changeover checklist, changeover matrix and line clearance checklist.
- SMED changeover calculator and OEE calculator: what the minutes are worth.
Go deeper
This page is the short version. These guides cover each part in full.
- How to Reduce Changeover Time in ManufacturingThe wider set of changeover techniques once the study has shown where the minutes are.
- SMED and JIT: Single-Minute Exchange of DieWhy short changeovers let a plant run smaller batches and more products per day.
- How to Reduce Manufacturing DowntimeThe stops between changeovers: finding and removing their causes.
- What Is Planned Downtime?How scheduled cleaning and changeovers are counted, and what that does to the numbers.
- Top Ergonomic Practices for Manufacturing TeamsReducing the strain of repetitive packing and lifting work.
All our articles on this subject are in the standard work, sops and training topic.
Free templates and tools
- SMED changeover worksheetChangeover steps with times, internal or external, what can move, ideas and before/after totals.
- Changeover checklist25 checks for every changeover, a record of planned and actual times, and a log of changeover time against target.
- Changeover matrix templateA from-to matrix of changeover minutes with the clean each transition needs (allergen, color, format), and a weekly planner that totals the order and suggests a shorter one.
- Line clearance checklist28 line clearance checks in six sections (area, equipment, materials, printed materials, documents, coder and vision settings), cleared by the operator and verified by a second person, with a printed-materials reconciliation and a worked example that does not balance.
- Time study sheetTime each element over 10 cycles and work out the average, lowest repeatable and standard time. Excel does the sums.
- SMED changeover calculatorTime saved by moving changeover steps from internal to external, capacity freed per week and the smaller batch it allows.
- OEE calculatorOverall equipment effectiveness from shift time, downtime, ideal cycle time and part counts.
- Line balancing calculatorLine efficiency, balance delay and the minimum number of stations from station times and takt.
- Standard time calculatorObserved times, a rating and an allowance in; normal time, standard time, units per hour, pieces per shift and labour cost per unit out, with the working.
Doing this in LeanSuite
SMED
Runs each changeover as a timed checklist, and AI splits a filmed changeover into internal and external tasks.
See SMEDTime and Motion Study
Film the station and the AI times every element on a timeline that links to the video, split into value-added, necessary and waste.
See Time and Motion StudyAI Video Analysis
Turns video of real work into time studies, line balance charts, changeover splits and other studies you review and certify.
See AI Video AnalysisLine Balancing
Drop in a video of your line and get a Yamazumi chart, a takt comparison and rebalancing recommendations.
See Line Balancing
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about time study in food and beverage manufacturing
Do not time the machine. List the manual jobs around it, such as case packing and palletizing, and time each one per case or per pallet. Multiply by the line rate to get the seconds of work arriving each minute, divide by 60 to get people, and round up. Study tending jobs like the filler operator with work sampling or full-shift video, because they have no fixed cycle.
Work it out from the load. Cases per minute x standard seconds of manual work per case, divided by 60, gives the load in people. At 5 cases a minute and 18.4 seconds per case, case packing needs 1.53 people, so two. Add the other shared jobs, round up, and check the load per person. A crew loaded near 100 percent cannot absorb a jam.
You can reduce the time around the clean, not the clean itself. Contact times, rinses and verification tests are set by the cleaning procedure and the food safety plan and are outside a time study's reach. The study finds the fetching, waiting for quality, searching for parts and slow start-ups that surround them. In the example on this page those fell from 88 minutes to 45 while the 47 minutes of cleaning and verification stayed the same.
From the last good unit of the outgoing product to the first good unit of the next product, running at rate and released by quality. That includes run-out, stripping the machine, cleaning, inspection and any allergen test, reassembly, line clearance and start-up. Stopping the clock when the machine is back together hides the start-up, which is often one of the longest parts.
Yes, with one added rule. SMED separates work that needs the line stopped from work that does not, and moves the second kind out of the stop. In a food plant a third kind is added: cleaning and verification steps that are fixed. Mark those first and leave them alone. The rest, such as staging the cleaning cart, kitting clean parts and calling quality early, responds to SMED as it does anywhere.
Use work sampling or video of whole shifts. A machine operator's work arrives at irregular moments: a film change, a jam, an hourly check. There is no repeating cycle to time, so a stopwatch study mostly records someone watching the machine. Random observations over two weeks, or footage of full shifts, show what share of time goes on tending, clearing jams, checks and waiting.
Related guides and tools
- Time and motion study: the family of methods and when to use each
- How to conduct a time study: the method step by step
- Standard time: observed time, rating and allowances
- SMED: how to cut changeover time with a study from video
- Work sampling: random observations for tending work and line state
- Line balancing: sharing work across stations and crews
- Timing long cycle and team work: sanitation shifts and crew jobs
- Time study from video: filming and breaking down a job
- Ergonomic assessment: checking repetitive packing work
- Workstation design: reach, height and layout at the pack-off
- Spaghetti diagram: drawing where the crew walks
- LeanSuite for food and beverage plants
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk
Or browse the topics, the full library and the lean glossary.