Skip to content
LeanSuite

Time study in food and beverage manufacturing: crews, changeovers and wash-downs

Short answer

In a food or beverage plant the line sets the pace, so a time study rarely means a stopwatch standard for one operator. Three studies pay back: how many people the line needs at each rate, how long each changeover and wash-down takes and why, and where the shift goes.

On a filling or packing line the machine sets the rate and people tend, feed, check, clear jams and pack off. So study the crew, not a single cycle: time the manual jobs per case, multiply by the line rate and you have the people needed at each speed. Then film a changeover from the last good unit of one product to the first good unit of the next and sort every minute into strip, clean, verify, reassemble and start-up. Leave the cleaning and verification steps in the food safety plan exactly as written, and take out the fetching, waiting and searching around them. In the worked example here that takes an allergen changeover from 135 minutes to 92 with no change to the clean.

Last reviewed:

Why a food line is not an assembly line

One line, two kinds of work

Example numbers

Machine-paced: 60 tubs a minute

1 operator tending

  • Station 1

    Filler

    Top up hopper, clear jams

  • Station 2

    Lidder and sealer

    Load lids and film

  • Station 3

    Checkweigher, metal detector

    Hourly checks, rejects

  • Station 4

    Date coder

    Code check at start-up

Study with work sampling or full-shift video. There is no cycle to time.

Pack-off: paced by the line, 5 cases a minute

  • Station 5

    Case packing

    18.4 s of work per case

  • Station 6

    Palletizing

    7.5 s of work per case

Study with a time study per case, then multiply by the line rate.

A tub filling line at 60 tubs a minute. Stations 1 to 4 (filler, lidder and sealer, checkweigher and metal detector, date coder) are machine-paced and tended by one operator. Stations 5 and 6 (case packing by two people, palletizing by one) are manual work paced by the line at 5 cases a minute.

The machine half sets the rate. The study is about the people: what the one operator tends, and how much work the line sends the three at the pack-off every minute.

The classic time study assumes one person repeating one cycle at their own pace. Time the cycle, rate it, add allowances, and you have a standard time. Most food and beverage work does not look like that.

A filler, a wrapper or a canning line runs at a set speed. The people around it do not make the product one unit at a time. They keep the machine fed and running, check what comes off it, and pack it away. Timing the line tells you the machine's rate, which the display already shows. The question worth an engineer's week is a different one: how much human work does this line need per minute at this rate, and who is doing it?

  • Paced work. The line decides how often a case, a tray or a pallet is due. People keep up or the line backs up.
  • Tending work. Loading film, lids and cartons, topping up a hopper, clearing a jam, doing the hourly weight and seal checks. It comes at irregular intervals.
  • Self-paced manual work. Hand packing, tray loading, weighing, kitting ingredients, decorating. Here the ordinary time study fits.
  • Not running at all. Product changeovers, allergen cleans, wash-down, clean in place (CIP), start-up and line clearance. In many plants this is the biggest block of time nobody has measured.

Each kind of work needs its own way of measuring. The rest of this page takes them in turn, using one illustrative line throughout: a tub filling line for hummus running 60 tubs a minute, 12 tubs to a case, with a crew of four.

Where the time goes in a food plant

Before choosing a method, sort the plant's work into the kinds below. The right study follows from the kind of work, and most lines have all of them.

Kinds of work on a food or beverage line and what sets their time
Kind of workExamplesWhat sets the timeWhat a study can change
Machine-paced runningFilling, sealing, wrapping, baking, cooking, coolingThe process and the machine: fill rate, bake time, cooling curveVery little. Speed belongs to process and quality engineering, not to a stopwatch.
Paced manual workCase packing, tray loading, palletizing off the end of the lineLine rate x the manual work per caseMethod, layout, crew size at each rate
TendingFilm and lid changes, hopper top-ups, jam clearing, in-process checksHow often the event comes and how long it takesReach and walking, frequency of jams, who covers what
Self-paced manual workHand packing, weighing and batching, decorating, kittingThe operator and the methodMethod, workstation, standard time
Changeover and cleaningProduct change, allergen clean, wash-down, CIP, start-up, line clearanceThe cleaning procedure, plus everything around itThe fetching, waiting, searching and adjusting around the clean. Not the clean itself.
StopsJams, short stops, waiting for materials or for a checkCauses upstream of the peopleFinding the cause; see where a full shift on video goes

A picture of one day makes the priorities plain. The illustrative line below is staffed for two shifts, 960 minutes. It has one allergen changeover, two short label changes and an end of day sanitation. Add breaks and short stops and it fills tubs for 520 of those minutes: 54.2 percent. Nobody on the crew is slow. The time is in the changeovers and the cleaning, so that is where the first study should point.

Where 960 staffed minutes go

Example numbers
  • Running at rate520 min (54.2%)
  • Allergen changeover with wash-down (1)135 min (14.1%)
  • End of day sanitation120 min (12.5%)
  • Short stops and jams75 min (7.8%)
  • Breaks60 min (6.3%)
  • Label changes (2 x 25 min)50 min (5.2%)

Of 960 staffed minutes the line runs for 520, 54.2%. Allergen changeover with wash-down (1): 135 minutes. End of day sanitation: 120 minutes. Short stops and jams: 75 minutes. Breaks: 60 minutes. Label changes (2 x 25 min): 50 minutes.

The line fills tubs for 520 of 960 minutes, 54.2%. The largest single block after that is one changeover, so study it first.

Get this split from a downtime log if the plant keeps an honest one, from work sampling of the line state over two weeks, or from video of whole shifts. A 30 minute stopwatch study of the packers would have missed all of it.

Which study answers which question

Start from the decision you need to make, not from the method you know. The family of methods is laid out in the guide to time and motion study; in a food plant the choice usually comes down to these.

Match the study to the kind of work

  • If the work is

    People paced by the line

    Case packing, tray loading, palletizing

    Use

    Crew loading study

    Time the work per case, multiply by line rate

  • If the work is

    People tending a machine

    Filler and wrapper operators

    Use

    Work sampling or full-shift video

    Random observations: what share of time on each task

  • If the work is

    People working at their own pace

    Hand packing, weighing, batching

    Use

    Time study and standard time

    Elements, rating, allowances

  • If the work is

    The line stopped

    Changeover, allergen clean, wash-down, start-up

    Use

    Changeover study from video

    Buckets, then fixed, internal and external

People paced by the line (Case packing, tray loading, palletizing): use a Crew loading study. People tending a machine (Filler and wrapper operators): use a Work sampling or full-shift video. People working at their own pace (Hand packing, weighing, batching): use a Time study and standard time. The line stopped (Changeover, allergen clean, wash-down, start-up): use a Changeover study from video.

Ask first what sets the time: the line, the machine's needs, the operator, or the cleaning procedure. The method follows.
The question, the method and why it fits food and beverage work
You need to knowUseWhy
How many people the line needs at each rateCrew loading study: a time study of each manual job per case, multiplied by line rateThe line sets how often the work comes. The study sets how long each piece takes.
What the filler or wrapper operator does all shiftWork sampling, or video of whole shiftsTending is irregular. No single cycle exists to time.
The standard for hand packing, weighing or batchingStopwatch or video time study, then standard timeSelf-paced, repeating, one station: the textbook case.
Why a changeover takes two hoursChangeover study from video, sorted into buckets and into internal and external workThe job is long, done by several people at once, and happens a few times a week. Video catches all of them together.
Where the shift goesDowntime log with reason codes, line-state sampling, or OEEThe loss is spread across the day in pieces too small to notice.
Whether the packing job is hurting peopleErgonomic assessment of the stationRepetitive reaching and lifting at line rate is a risk a time standard does not show.

Two methods are a poor fit almost everywhere in this industry. Predetermined time systems are slow to apply to work that changes with every product format, and a stopwatch standard on the filler operator measures somebody watching a machine. Long jobs worked by a team, such as a full sanitation shift, need the approach in the guide to timing long cycle and team work.

Crew loading on a paced line

Crew loading asks one thing: at this line rate, how many minutes of human work arrive each minute? If the answer is 2.2, the pack-off needs three people, and each will be busy about 72 percent of the time. The sum is the same one used in line balancing, with the line rate standing in for takt.

From a time per case to a crew

  1. 1

    List the manual jobs and what triggers each

  2. 2

    Time each job per trigger

  3. 3

    Turn the line rate into triggers per minute

  4. 4

    Multiply and add

  5. 5

    Round up, then look at the load

  6. 6

    Repeat for every rate and format you run

The time study gives seconds per case. The line rate turns that into people.
  1. 1

    List the manual jobs and what triggers each

    Per case: erect, load, close. Per pallet: change the pallet, wrap, label. Per reel or per hour: film change, weight check. Write the trigger next to each job, because the trigger is what turns a time into a load.

  2. 2

    Time each job per trigger

    Film the station or use a stopwatch, and time the elements over enough cycles. Rate the pace and add allowances as in any time study. The result is a standard time per case, per pallet or per event.

  3. 3

    Turn the line rate into triggers per minute

    Units per minute divided by units per case gives cases per minute. Cases per minute divided by cases per pallet gives pallets per minute.

  4. 4

    Multiply and add

    Work per minute for a job = triggers per minute x standard time per trigger. Divide by 60 seconds to express it in people. Add the jobs that one crew shares.

  5. 5

    Round up, then look at the load

    Crew = the load in people, rounded up. Load per person = load divided by crew. A crew loaded close to 100 percent has no time to deal with a jammed case, so the line will stop.

  6. 6

    Repeat for every rate and format you run

    A crew that fits 60 a minute may not fit 80, and a 6 pack loads the packers differently from a 12 pack. Build the table once and the supervisor can staff from it.

Worked example: case packing and palletizing at three line rates

Illustrative example. On the hummus line, tubs leave the checkweigher and metal detector at 60 a minute and are packed by hand, 12 to a case. A video time study of the case packing job gives the elements below.

Illustrative: case packing elements, seconds per case at normal pace
ElementNormal time (s)
Erect case and set it on the stand4.0
Load 12 tubs in two layers8.5
Check the date code and close the flaps2.0
Push the case to the taper1.5
Normal time per case16.0
Standard time per case with a 15 percent allowance18.4

16.0 x 1.15 = 18.4 seconds. The 15 percent allowance is illustrative; use your own plant's allowance policy.

Palletizing was timed the same way: 6.0 seconds to place each case, plus 90 seconds to change and wrap a pallet of 60 cases, which is 1.5 seconds a case. That makes 7.5 seconds per case. At 60 tubs a minute the line makes 5 cases a minute, so case packing needs 5 x 18.4 = 92 seconds of work every minute, or 1.53 people, and palletizing needs 5 x 7.5 = 37.5 seconds, or 0.63 of a person.

Illustrative: pack-off crew at three line rates
Line rate (tubs/min)Cases/minCase packing (people)Palletizing (people)Total loadCrewLoad per person
403.331.020.421.44272%
605.001.530.632.16372%
806.672.040.832.88396%
80, with a fourth person6.672.040.832.88472%

Load in people = cases per minute x standard seconds per case / 60. Crew members share case packing and palletizing.

Pack-off load at three line rates

Example numbers
  • 40 tubs a minute (3.33 cases)

    1.44 people of work, crew of 2: 72%

  • 60 tubs a minute (5.00 cases)

    2.16 people of work, crew of 3: 72%

  • 80 tubs a minute (6.67 cases)

    2.88 people of work, crew of 3: 96%

  • Case packing, 18.4 s per case
  • Palletizing, 7.5 s per case
  • Crew on the line

At 40 tubs a minute the pack-off needs 1.44 people of work; a crew of 2 is loaded to 72%. At 60 tubs a minute the pack-off needs 2.16 people of work; a crew of 3 is loaded to 72%. At 80 tubs a minute the pack-off needs 2.88 people of work; a crew of 3 is loaded to 96%.

Load in people = cases a minute x standard seconds per case / 60. At 80 a minute three people are 96% loaded: add a fourth or take seconds out of the case cycle.

Read the 80 row twice. Three people can do it on paper at 96 percent, which means that one crushed case or one late pallet stops the line. The honest choices are a fourth person, or taking seconds out of the job first: a case erector, tubs presented in rows of six, a stand at the right height. Each second off the case cycle is worth 0.11 of a person at this rate. The fourth crew member, the filler operator, is a tending job: a sampling study of 200 random observations found the operator busy in 154, or 77 percent, so there is little spare there to lend to the pack-off.

The changeover and wash-down study

A changeover in a food plant is a SMED problem with one extra rule: part of it is cleaning that protects the consumer, and that part is not yours to shorten. The study exists to find everything else. Measure from the last good unit of the old product to the first good unit of the new one, at rate and released by quality.

  1. 1

    Agree the scope with quality and sanitation first

    Sit down with the food safety lead and the sanitation supervisor. Mark which steps are fixed by the cleaning procedure and the food safety plan. Say out loud that those steps are outside the study's reach.

  2. 2

    Film the whole changeover, every person

    One camera wide on the machine, a second on the wash bay or the parts table if work happens there. Start before the last good unit and stop after the first good one. Tell the crew why, and follow the plant's rules on filming.

  3. 3

    List every task with a start, an end and a name

    Go through the footage and write one line per task per person, including the walks and the waits. A wait is a task with nobody in the frame.

  4. 4

    Sort each task into a bucket

    Strip and prepare, clean and sanitize, wait and verify, reassemble and materials, start-up. The buckets show where the time sits before anyone argues about a single task.

  5. 5

    Mark each task fixed, internal or external

    Fixed: set by the cleaning procedure or a verification test. Internal: needs the line stopped. External: could be done while the line still runs or after it restarts. Fetching the cleaning cart is external. Foam contact time is fixed.

  6. 6

    Move, remove and shorten, in that order

    Move external work out of the stop. Remove waits by calling people before they are needed. Shorten what is left with pre-kitted change parts, a second pair of hands and written settings. Leave the fixed tasks alone.

  7. 7

    Write the new sequence and film it again

    Put the sequence on a checklist with who does what, in what order. Run it, film it, and compare bucket by bucket. Have quality sign off that the clean was done to the procedure both times.

Worked example: an allergen changeover with wash-down

Illustrative example. The hummus line changes from a recipe that contains sesame to one that does not. The procedure calls for a full wet clean and an allergen swab before restart. Filmed from last good tub to first good tub, the changeover took 135 minutes. The team listed twelve tasks, marked each one, and ran the new sequence two weeks later.

Illustrative: the allergen changeover task by task, before and after (minutes)
TaskTypeBeforeAfterWhat changed
Run out product and empty the hopperInternal66Nothing
Fetch tools, hoses, chemicals and the parts cartExternal90Cart stocked and parked at the line before the last tub
Strip the filler: nozzles, hopper, guardsInternal149A packer strips the guards while the operator takes the nozzles
Dry pick-up and pre-rinseInternal108Hose and squeegee already at the line
Apply foam and hold for the contact timeFixed1515Nothing. Set by the cleaning procedure.
Scrub and rinseFixed1212Nothing. Set by the cleaning procedure.
Sanitize and drainFixed88Nothing. Set by the cleaning procedure.
Wait for quality to arriveWait110Quality is called when sanitizing starts
Visual inspection, allergen swab and resultFixed1212Nothing. The test takes as long as it takes.
Reassemble with the next product's partsInternal1610Clean parts kitted in order on a board; no searching
Bring lids, film and labels; line clearancePart external83Packers stage materials during the clean; the 3 minute clearance check stays
Start-up: prime, set weights and seal, first good tubInternal149Settings sheet with last run's weights and sealer settings
Total1359243 minutes shorter, 31.9 percent

Fixed tasks total 47 minutes before and after. Everything else fell from 88 minutes to 45.

The tasks grouped into buckets show where the gain came from.

The changeover by bucket: 135 minutes to 92

Example numbers

Before: 135 min

After: 92 min

  • Strip and prepare29 to 15
  • Clean and sanitize45 to 43
  • Wait and verify23 to 12
  • Reassemble and materials24 to 13
  • Start-up14 to 9

Before, 135 minutes: Strip and prepare 29, Clean and sanitize 45, Wait and verify 23, Reassemble and materials 24, Start-up 14. After, 92 minutes: Strip and prepare 15, Clean and sanitize 43, Wait and verify 12, Reassemble and materials 13, Start-up 9.

Both bars are on the same scale, last good tub to first good tub. The dark clean block barely moves. The buckets on either side of it shrink.
Illustrative: the same changeover by bucket (minutes)
BucketBeforeAfterSaved
Strip and prepare291514
Clean and sanitize45432
Wait and verify231211
Reassemble and materials241311
Start-up1495
Total1359243

The 2 minutes saved in the clean bucket are from the pre-rinse set-up. Foam, scrub, rinse and sanitize are unchanged at 35 minutes.

At 60 tubs a minute, 43 minutes is 2,580 tubs, or 215 cases, each time this changeover runs. On the illustrative day it lifts running time from 520 to 563 minutes, 54.2 to 58.6 percent. No cleaning step was touched and nobody worked faster. The crew stopped fetching, waiting and searching.

What the study must not touch

Fixed by the food safety plan, and everything around it

Example numbers

Before

After

  • 47 min

    Cleaning and verification, unchanged

  • 88 to 45 min

    Fetching, stripping, waiting, reassembly, start-up

  • 2,580 tubs

    Extra output per changeover at 60 a minute

Cleaning and verification take 47 minutes before and after. The work around them falls from 88 minutes to 45, a cut of 48.9%.

The study took 43 minutes out of the changeover and none of them came from the 47 minutes of foam, scrub, rinse, sanitize, inspection and swab.

A time study in a food plant has a boundary that one in a machine shop does not. Cleaning works through four things together: time, mechanical action, chemical concentration and temperature. Cut the time and one of the other three has to rise to make up for it. That is a decision for the people who own the cleaning procedure, backed by their own testing. It is never a by-product of a changeover project.

In the United States, sanitation controls and food allergen controls are among the preventive controls a facility writes into its food safety plan under 21 CFR Part 117, and many plants also validate their allergen cleans with allergen-specific tests. Other countries and customer standards have their own rules. The point for the engineer is simple: these steps are written down for a reason you may not see from the floor.

  • Mark fixed tasks on the task list before anyone discusses savings, and have quality confirm the marking.
  • Do not shorten contact times, rinse steps, drying, swab counts or test read times. Do not skip a verification because the last twenty passed.
  • Do not reassemble or load materials ahead of release if the procedure says release comes first.
  • If the study suggests the clean itself could change, for example a different sequence or a tool-less design that cleans faster, hand that to quality and sanitation as a proposal. They decide and re-verify.
  • Record that the clean was done to procedure in both the before and after films. A faster changeover that fails a swab is a slower changeover.

This is general practice for studying work. It is not food safety or regulatory advice, and your food safety plan and the people responsible for it have the final word.

Measures to agree before you start

Food plants argue about definitions more than about numbers. Settle these before the first film, write them on the study sheet, and keep them the same for the after study.

  • Changeover time. Last good unit of the old product to first good unit of the new one, at rate and released. A changeover that ends when the machine is reassembled hides the start-up.
  • What counts as planned. OEE is availability x performance x quality, and plants differ on whether scheduled sanitation sits inside or outside planned production time. Either works. Pick one and say which.
  • Start-up loss. Count the tubs rejected for weight, seal or code before the first good one, and the minutes they took. It belongs to the changeover.
  • Giveaway. Product filled above the declared weight. A crew that restarts fast by setting the filler heavy has moved the loss, not removed it.
  • Crew, not headcount. Record who was on the line during the study, including the people borrowed from next door during the changeover.
  • Format. Record the product, pack size and case count. A standard for a 12 pack says little about a 6 pack.

Mistakes that are specific to food and beverage

Food and beverage time study mistakes and what to do in their place

  • Mistake

    Timing the line and calling it a time study

    What goes wrong: You have measured the filler's speed. The crew size and the lost time are still unknown.

    Do this

    Time the manual work per case and multiply by the line rate. Sample or film the tending jobs.

  • Mistake

    Treating cleaning time as waste to cut

    What goes wrong: A shorter contact time or a skipped swab puts consumers at risk and can bring a recall.

    Do this

    Mark cleaning and verification as fixed. Take the minutes out of the work around them.

  • Mistake

    Stopping the clock at reassembly

    What goes wrong: The start-up, with its rejects and adjustments, vanishes from the study.

    Do this

    Measure to the first good unit at rate, released by quality.

  • Mistake

    Studying one product

    What goes wrong: The standard fits the easy SKU. The sticky one, the small pack and the allergen change behave differently.

    Do this

    Study the formats that make up most of the volume, and each type of changeover in the matrix.

  • Mistake

    Studying the best crew on day shift

    What goes wrong: Seasonal and agency crews with two weeks on the line cannot hit the number.

    Do this

    Study experienced operators for the standard, and plan a learning period for new starters.

  • Mistake

    Loading the crew to 100 percent

    What goes wrong: Every jam becomes a line stop because nobody has a free second.

    Do this

    Leave room in the load, or remove seconds from the job before removing a person.

  • Mistake

    Ignoring where people stand and walk

    What goes wrong: A packer who walks six steps for every stack of cases loses the time the study was looking for.

    Do this

    Draw the walk on a spaghetti diagram and move the materials.

Most of these come from treating a paced, cleaned line like a bench assembly job.

The people side

Packing crews have heard that a study means fewer people on the line. Sanitation crews have heard that it means less time to do a job they are personally signed against. Both fears are reasonable, and both distort the study if they are left alone.

  • Say what the study is for before the camera comes out, and say what it is not for. If the aim is changeover time, say that crew numbers are not in scope.
  • Tell the sanitation team, in front of their supervisor, that cleaning steps are fixed and the study is looking at what holds them up.
  • Many crews are seasonal or from an agency, and several languages may be spoken on one line. Explain the study in the languages the crew uses, with a picture of the result you expect.
  • Cold rooms, wet floors, gloves, sleeves and hearing protection all slow work down for good reasons. Time the job as it is really done in that gear, and let the allowance reflect the conditions.
  • Packing at line rate is repetitive work. If the study shows a job at 90 percent load with a reach above shoulder height, treat that as a finding and run an ergonomic assessment before anyone talks about rate.
  • Show the crew the film and the task list first. They will spot the missing tool and the pointless walk faster than the engineer will.

This is general practice, not legal or labor relations advice. Where a union agreement or works council covers work measurement or filming, follow it.

Templates, tools and related guides

LeanSuite's SMED module runs each changeover as a timed checklist, and its AI splits a filmed changeover into internal and external tasks. Time and motion study does the same for a packing station: film it and the AI times every element on a timeline that links back to the video, for an engineer to review. Both sit on AI video analysis. See how plants in food and beverage and packaging and converting use them.

FAQ

Questions about time study in food and beverage manufacturing

  1. Do not time the machine. List the manual jobs around it, such as case packing and palletizing, and time each one per case or per pallet. Multiply by the line rate to get the seconds of work arriving each minute, divide by 60 to get people, and round up. Study tending jobs like the filler operator with work sampling or full-shift video, because they have no fixed cycle.

  2. Work it out from the load. Cases per minute x standard seconds of manual work per case, divided by 60, gives the load in people. At 5 cases a minute and 18.4 seconds per case, case packing needs 1.53 people, so two. Add the other shared jobs, round up, and check the load per person. A crew loaded near 100 percent cannot absorb a jam.

  3. You can reduce the time around the clean, not the clean itself. Contact times, rinses and verification tests are set by the cleaning procedure and the food safety plan and are outside a time study's reach. The study finds the fetching, waiting for quality, searching for parts and slow start-ups that surround them. In the example on this page those fell from 88 minutes to 45 while the 47 minutes of cleaning and verification stayed the same.

  4. From the last good unit of the outgoing product to the first good unit of the next product, running at rate and released by quality. That includes run-out, stripping the machine, cleaning, inspection and any allergen test, reassembly, line clearance and start-up. Stopping the clock when the machine is back together hides the start-up, which is often one of the longest parts.

  5. Yes, with one added rule. SMED separates work that needs the line stopped from work that does not, and moves the second kind out of the stop. In a food plant a third kind is added: cleaning and verification steps that are fixed. Mark those first and leave them alone. The rest, such as staging the cleaning cart, kitting clean parts and calling quality early, responds to SMED as it does anywhere.

  6. Use work sampling or video of whole shifts. A machine operator's work arrives at irregular moments: a film change, a jam, an hourly check. There is no repeating cycle to time, so a stopwatch study mostly records someone watching the machine. Random observations over two weeks, or footage of full shifts, show what share of time goes on tending, clearing jams, checks and waiting.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.