HIRA: hazard identification and risk assessment, with the register format
Short answer
HIRA stands for hazard identification and risk assessment. In a plant it usually means one document: a register that lists every activity in a department, the hazards in each, the controls in place, a risk score, the extra controls planned and the risk that remains, with an owner and a review date.
The full form of HIRA is hazard identification and risk assessment. A HIRA register has one line for each hazard of each activity, with these columns: activity, routine or non-routine, hazard, consequence, existing controls, severity, likelihood, risk level, additional controls, residual risk, owner and review date. To build one, list every activity in the department including maintenance, cleaning and contractor work, walk each one with the people who do it, score the risk with today's controls, decide extra controls from the top of the hierarchy of controls, and score again. A HIRA covers a whole department at activity level. A JSA covers one job step by step and feeds the HIRA. ISO 45001 clause 6.1.2 asks for hazard identification and risk assessment but never uses the word HIRA. This is general guidance, and the rules that apply to your site may ask for more.
Last reviewed:
What is HIRA, and what does it stand for?
HIRA is short for hazard identification and risk assessment. The words describe a process: find what could harm people, then judge how bad and how likely the harm is, so you know what to control first. In daily plant language, though, "the HIRA" is a thing you can open: a register, usually a spreadsheet, with a line for every hazard in every activity of a department.
It is the same process our risk assessment guide teaches, under a different name. That guide covers the method: hazard against risk, the six steps, the 5x5 matrix and its limits. This page covers the document: what goes in each column, how to build the register for a whole department, what a filled one looks like and how it relates to a JSA.
The term is searched most in India, where it is a common name for a plant's risk assessment register. Elsewhere the same document is called a risk register, a risk assessment register or a hazard register. You may also meet HIRAC or HIRARC, where the added letters stand for control or for risk control. The content is the same.
A register exists so that three questions have one answer in one place. What can hurt people here? What are we relying on to stop it? What have we promised to do next, and who owns it? If you cannot answer those for a department in five minutes, you do not yet have a HIRA, however many forms are on file.
The HIRA format: the register column by column
No standard fixes the format, so registers differ from company to company. The twelve columns below are the ones most plants end up with, and they follow the order of the thinking: what is done, what could go wrong, what stops it today, how big the risk is, what more will be done, and what is left.
The twelve HIRA columns follow the order of the thinking
Find it
What is done and what could go wrong
- 1 Activity
- 2 Routine or non-routine
- 3 Hazard
- 4 Consequence
Judge it today
What stops it now, and how big is it
- 5 Existing controls
- 6 Severity
- 7 Likelihood
- 8 Risk level
Act on it
What more will be done, and what is left
- 9 Additional controls
- 10 Residual risk
Keep it alive
Who answers for it, and when it is looked at again
- 11 Owner
- 12 Review date
Twelve register columns in four groups: find it (activity, routine or non-routine, hazard, consequence), judge it today (existing controls, severity, likelihood, risk level), act on it (additional controls, residual risk), keep it alive (owner, review date).
| Column | What goes in it | Common mistake |
|---|---|---|
| 1. Activity | One task or operation in plain words, with where it is done: "Load bar stock into the lathe bar feeder" | Writing a department or a machine ("CNC area") in place of something people do |
| 2. Routine or non-routine | R for work in the normal cycle or done every shift. NR for setups, cleaning, maintenance, breakdowns, start-up, contractor jobs | Listing only routine work. Non-routine tasks are the ones the daily controls were not designed for |
| 3. Hazard | The thing with the potential to cause harm: a rotating chuck, a 28 kg bar, coolant mist, a forklift crossing | Writing the harm ("injury") or the missing control ("no guard") as the hazard |
| 4. Consequence | The credible worst harm and who suffers it: "hand drawn in, amputation, operator or setter" | "Injury" with no detail, so severity cannot be judged |
| 5. Existing controls | What is in place and working today: guards, interlocks, procedures, training, PPE | Listing controls that exist on paper. If the interlock is bypassed, it is not a control |
| 6. Severity (S) | A number on your scale for that consequence, such as 1 (first aid) to 5 (fatality or permanent disability) | Lowering severity because the event is unlikely. That is the next column's job |
| 7. Likelihood (L) | A number on your scale for how likely the consequence is with the existing controls | Scoring as if every control always works |
| 8. Risk level | S times L, and the band it falls in (low, medium, high, very high on your own banding) | A colour with no number, so nobody can see how it was reached |
| 9. Additional controls | What will be added, chosen from the top of the hierarchy of controls first | "Training" and "be careful" on every line |
| 10. Residual risk | S times L again, as it will be once the additional controls are in and working | Dropping severity when only likelihood changed. PPE and procedures rarely change how bad the worst outcome is |
| 11. Owner | One named person or role answerable for the additional controls | "Safety department" or "all" |
| 12. Review date | When this line will be looked at again, plus the date each action is due | One date for the whole register, set a year away |
Add a line number, the date and the names of the team in the header. Some registers add columns for legal requirements, the persons exposed or an action status. Keep the twelve in this order whatever you add.
Two columns do most of the work and get the least attention. "Existing controls" is the list of things that must keep working for the score to be true, which makes it the checklist for your inspections and audits. "Additional controls" with an owner and a date is an action plan. A register where every line reads "training" and "PPE" in both is a list of hazards with nothing done about them.
How to build a HIRA register for a department
Build it one department at a time, on the floor, with the people who do the work. A register written in an office from a list of machines misses the activities between the machines, which is where a lot of the handling, cleaning and unjamming happens.
Eight steps from a list of activities to a signed register
- 1
Set the boundary and the team
- 2
List every activity, routine and non-routine
- 3
Walk each activity and name the hazards
- 4
Write the consequence and who is exposed
- 5
Record the existing controls, and check them
- 6
Score severity and likelihood with today's controls
- 7
Decide additional controls, an owner and a date
- 8
Approve it, share it, and keep it alive
- 1
Set the boundary and the team
Name the department, what is inside it and what is not (the aisle, the stores, the compressor room). Put together a small team: the supervisor, an operator, a maintenance technician and the safety lead. Add a setter or a contractor representative when their work is on the list.
- 2
List every activity, routine and non-routine
Start from the process flow, the standard work or work instructions, and any time study element lists. Then add what those leave out: setups, cleaning, maintenance, material deliveries, waste removal, breakdowns, start-up after a stop, work by contractors and visitors. Ask the night shift what they do that the day shift does not.
- 3
Walk each activity and name the hazards
Watch the activity, or have the person walk you through it. For each one go through the hazard families: mechanical, electrical, handling and posture, slips, trips and falls, vehicles, chemicals, noise, heat, fire, pressure and stored energy. Write one line for each hazard.
- 4
Write the consequence and who is exposed
The credible worst harm, and to whom: the operator, the setter, a cleaner, a passing forklift driver, a visitor. This is what the severity score will rest on.
- 5
Record the existing controls, and check them
List what is in place. Then test the important ones on the spot: open the interlocked door, look for the guard, ask to see the procedure. A control that does not work goes in the additional controls column as a repair.
- 6
Score severity and likelihood with today's controls
Use one written scale for the whole site. Score as a team, out loud, and note why when you disagree. Multiply for the risk level and mark the band.
- 7
Decide additional controls, an owner and a date
Start with the high lines and anything at the top severity. Work down the hierarchy of controls: eliminate, substitute, engineer, then administrative controls and PPE. Give each action one owner and a due date, then score the residual risk.
- 8
Approve it, share it, and keep it alive
The department manager signs. Brief every shift on the high lines and post them at the area. Set review dates line by line, and review at once after an incident, a near miss or any change to the people, machines, materials or methods.
Expect a first register for one department to take a few sessions on the floor. The value is in the walking and the arguing about scores. Copying a register from another site skips both, and gives you their hazards with your signature on them.
A word on the scoring
This page uses severity 1 to 5 times likelihood 1 to 5, with scores of 1 to 4 low, 5 to 9 medium, 10 to 16 high and 20 to 25 very high. That is our convention, the one on the risk matrix calculator and the risk assessment matrix template, and no standard sets it. Use your site's scale and write it on the register. The reasoning behind the matrix, and its known weaknesses, are in the risk assessment guide.
A filled HIRA register: extract for a machining department
Illustrative example. A job shop runs a machining department with CNC lathes fed by bar feeders, two machining centres, a pedestal grinder for deburring and a forklift that takes finished pallets out through the main aisle. Ten lines from its register are below. To fit the page, the hazard and consequence share a column, and so do the owner and review date.
| # | Activity (R or NR) | Hazard and consequence | Existing controls | S x L = risk | Additional controls | Residual S x L | Owner, review |
|---|---|---|---|---|---|---|---|
| 1 | Load 28 kg bar stock into the lathe bar feeder (R) | Manual lift of a 3 m bar: back strain, crushed fingers | Two-person lift rule, gloves | 3 x 4 = 12 High | Bar rack at feeder height so bars roll across (engineering) | 3 x 2 = 6 Medium | Production supervisor, May 2027 |
| 2 | Run the CNC lathe in automatic cycle (R) | Rotating chuck and workpiece: part or jaw thrown, entanglement | Interlocked door, chuck pressure monitor | 5 x 1 = 5 Medium | Monthly interlock test added to the maintenance plan | 5 x 1 = 5 Medium | Maintenance lead, Feb 2027 |
| 3 | Clear swarf from the chuck and chip conveyor (R) | Sharp swarf, spindle that can start: deep cuts, hand caught | Swarf hook and brush provided, gloves | 3 x 4 = 12 High | Door interlock holds the spindle stopped; guard over the conveyor inlet; hook only, no hands | 3 x 2 = 6 Medium | Production supervisor, Feb 2027 |
| 4 | Change chuck jaws and milling fixtures (NR, setup) | 9 kg jaws and 22 kg fixtures handled over the table: crushed hand or foot | Safety shoes | 3 x 3 = 9 Medium | Lifting eye and jib hoist for fixtures over 15 kg | 3 x 1 = 3 Low | Tooling engineer, May 2027 |
| 5 | Mix and top up metalworking coolant (R, weekly) | Skin contact with concentrate: dermatitis | Gloves, safety data sheet at the sump | 2 x 4 = 8 Medium | Dosing pump mixes at the tap; weekly concentration check | 2 x 2 = 4 Low | Maintenance lead, Nov 2027 |
| 6 | Deburr parts on the pedestal grinder (R) | Wheel burst, sparks and grit: eye injury | Wheel guards, eye shields, tool rest, glasses | 4 x 2 = 8 Medium | Wheel and tool rest gap check added to the weekly inspection | 4 x 1 = 4 Low | Production supervisor, Nov 2027 |
| 7 | Move finished pallets across the main aisle by forklift (R) | Forklift and pedestrians share the cell exit: person struck | Marked aisle, horn at the exit | 5 x 2 = 10 High | Barrier rail at the cell exit with one marked crossing | 5 x 1 = 5 Medium | Logistics lead, Feb 2027 |
| 8 | Clean out the coolant sump and chip conveyor (NR, twice a year) | Conveyor that can start, slippery sump: limb caught, fall | General lockout procedure | 4 x 3 = 12 High | Task lockout steps posted at the machine; sump vacuum in place of hand bailing | 4 x 1 = 4 Low | Maintenance lead, before next clean |
| 9 | Replace light fittings above the machines from a mobile platform (NR, contractor) | Work at height over running machines: fall, dropped object | Contractor induction | 5 x 2 = 10 High | Permit to work, machines below stopped, exclusion zone | 5 x 1 = 5 Medium | Facilities manager, each job |
| 10 | Blow chips off parts and fixtures with an air gun (R) | Noise across the cell: hearing loss over years | Hearing protection zone | 3 x 4 = 12 High | Quiet nozzles, noise survey, machine doors kept shut | 3 x 2 = 6 Medium | Safety lead, May 2027 |
Severity 1 to 5 times likelihood 1 to 5. Bands: 1 to 4 low, 5 to 9 medium, 10 to 16 high, 20 to 25 very high. Our own scales: use your site's.
Ten register lines: risk before and after the additional controls
Example numbers1. Load bar stock
12 to 6
2. Run the lathe
5 to 5
3. Clear swarf
12 to 6
4. Change jaws and fixtures (NR)
9 to 3
5. Mix coolant
8 to 4
6. Pedestal grinder
8 to 4
7. Forklift at the exit
10 to 5
8. Clean the sump (NR)
12 to 4
9. Replace lights (NR)
10 to 5
10. Air gun, noise
12 to 6
Ten lines of a machining department register. Before: 6 high and 4 medium, total 98. After: 6 medium and 4 low, total 48.
Now read it as a manager would. Before the additional controls the ten lines add up to 98 points: six high and four medium. After them the total is 48: six medium and four low, with nothing left in the high band. Three of the ten lines are non-routine work, and two of those three were high.
- Line 2 does not move: 5 x 1 before and 5 x 1 after. The lathe can kill, the interlock makes that very unlikely, and nothing on the list changes the severity. The additional control is there to keep the likelihood at 1. A line like this belongs on a short list the manager sees, whatever its score.
- Lines 7 and 9 keep severity 5 as well. A barrier and a permit make the event less likely. They do not make a forklift or a fall gentler.
- Line 8 happens twice a year and scored as high as anything done every shift. Rare is not the same as low risk: the general lockout procedure had never been written for this task.
- Line 10 is a health hazard with no accident to point to. Registers built from accident records miss lines like it.
- Lines 1, 3 and 4 use engineering controls and drop the furthest. Line 6 improves with an inspection, an administrative control, so its residual score depends on that check being done every week.
The residual column is a promise, not a fact. Line 1 is still a 12 until the bar rack is installed. Many plants show the current score and the target score side by side for that reason, and only move the line when the owner closes the action.
HIRA and ISO 45001 clause 6.1.2
ISO 45001:2018, the international standard for occupational health and safety management systems, does not contain the acronym HIRA. What it has is clause 6.1.2, titled hazard identification and assessment of risks and opportunities. The HIRA register is the way many plants show they meet that clause. In our own words, with the standard itself as the authority:
| Clause | What it asks for, in plain words | Where it shows in a HIRA |
|---|---|---|
| 6.1.2.1 Hazard identification | An ongoing, proactive process that takes into account, among other things, how work is organised, routine and non-routine activities, past incidents, potential emergencies, everyone with access to the workplace including contractors and visitors, and actual or proposed changes | The activity column with its R and NR lines, lines for contractor work, lines added after incidents and changes |
| 6.1.2.2 Assessment of OH&S risks | Assess the risks from the identified hazards, taking the effectiveness of existing controls into account, with a methodology and criteria that are defined, proactive and kept as documented information | The existing controls column, the written severity and likelihood scales, the risk level |
| 6.1.2.3 Assessment of opportunities | Look for chances to improve safety and health performance, such as adapting work to workers | Additional controls that redesign the job, not only guard it |
| 6.1.4 Planning action | Plan actions to address the risks and check they work | Additional controls, owner, date and residual risk |
| 8.1.2 Eliminating hazards and reducing risks | Use the hierarchy of controls | The order in which additional controls are chosen |
| 8.1.3 Management of change | Control planned changes and review the consequences of unintended ones | A register line reviewed whenever its activity changes |
A paraphrase for orientation. Read the standard for the exact requirements. The standard asks for a defined method and records, and does not prescribe a register layout.
Two practical points follow. First, the standard asks for workers to take part in identifying hazards and assessing risks (clause 5.4), so a register with no operator's name on it is weak evidence. Second, it asks for an ongoing process. An auditor will pick a recent change, a new machine or a moved line, and ask to see the register line that changed with it. That link is covered in management of change, and the standard as a whole in our ISO 45001 guide.
National law is a separate question. Many countries have their own rules on risk assessment, on particular hazards and on who must be consulted, and a customer or corporate standard may add more. Check the rules that apply to your site: a register that fits this page may not cover everything they ask for.
HIRA vs JSA vs HAZOP
These are not rivals. They look at risk from different heights, and a plant with hazardous processes uses all of them.
| Document | Looks at | Level of detail | Who writes it, and when |
|---|---|---|---|
| HAZOP (hazard and operability study) | A process design: what happens if flow, pressure, temperature or level deviates from intent | Each section of pipe and vessel, guide word by guide word | A multi-discipline team led by a trained facilitator, at design and at major process changes |
| HIRA | A whole department or site: every activity and its hazards | One line for each hazard of each activity | The department team with safety. Built once, then kept current |
| JSA or JHA (job safety or job hazard analysis) | One job | Step by step: each step, its hazards, its controls | The supervisor and the people who do the job, before a job is standardised and when it changes |
| Point-of-work check | Today's task, in today's conditions | A few questions on a card, minutes before starting | The person doing the work, every time |
The difference between a HIRA and a JSA in one line: the HIRA says which jobs carry the most risk, and the JSA says how to do one of those jobs safely.
Four documents, four heights
HAZOP
A process design: what if flow, pressure or temperature deviates
Multi-discipline team, at design and major process change
HIRA
A whole department: every activity and its hazards
Department team with safety. Built once, kept current
JSA or JHA
One job, step by step
Supervisor and the people who do it
Point-of-work check
Today's task in today's conditions
The person doing it, every time
HAZOP covers a process design, HIRA a whole department, a JSA one job and the point-of-work check today's task. Each narrows the view.
They feed each other. The HIRA's high lines tell you which jobs need a JSA first. Each finished JSA sends its worst scores back to the register. A HAZOP's findings arrive in the register as lines about process upsets. And a point-of-work check that keeps finding the same problem is telling you a register line is wrong. The full set of look-alike documents, JSRA and task risk assessment included, is sorted out in JSA vs JHA vs JSRA.
How a time study or JSA element list feeds the activity column
The hardest column to fill well is the first. Ask a room what activities happen in a department and you get machine names. The detail you need already exists somewhere else: in the element lists that industrial engineers write for time studies, and in the step lists of any JSAs already done. Each one is a list of what people really do at a station, in order, with break points you can see.
Take the trim press job from our guide to job safety analysis from video. The time study broke one 48 second cycle into eight elements, and the JSA scored a hazard at each. The register does not need all eight rows. It takes the job as one activity and one line for each distinct hazard, carrying the highest score the JSA found for it.
| Register line for "Trim and stack housings, trim press cell" (R) | From JSA elements | S x L carried over |
|---|---|---|
| Hands in the trim die: caught in | 2 (load the die), 5 (clear flash by hand) | 5 x 3 = 15 High |
| Twisted lift to a floor pallet: back strain | 7 (turn, bend and stack) | 3 x 4 = 12 High |
| Ejected flash and noise at the press | 3 (press trims) | 3 x 3 = 9 Medium |
| Sharp flash edges: cuts | 4 (unload), 5 and 6 (sharp scrap and edges) | 2 x 4 = 8 Medium |
| Warm housing from the conveyor: burn | 1 (pick the housing) | 2 x 3 = 6 Medium |
| Repeated filing: wrist strain | 6 (deburr two edges) | 2 x 3 = 6 Medium |
| Flash on the floor: trip | 8 (walk back) | 2 x 3 = 6 Medium |
Where two elements share a hazard, the line carries the higher score: loading the die is 5 x 2 = 10 and clearing flash is 5 x 3 = 15, so the line reads 15. The JSA number goes in the existing controls column as a reference.
Eight element rows become seven register lines
Example numbers- Hands in the trim die: caught infrom5 x 3 = 15
- Twisted lift to a floor pallet: back strainfrom3 x 4 = 12
- Ejected flash and noise at the pressfrom3 x 3 = 9
- Sharp flash edges: cutsfrom2 x 4 = 8
- Warm housing from the conveyor: burnfrom2 x 3 = 6
- Repeated filing: wrist strainfrom2 x 3 = 6
- Flash on the floor: tripfrom2 x 3 = 6
Seven HIRA lines for the trim press job, each listing the JSA elements it comes from and the severity times likelihood it carries over.
The irregular elements a time study records, such as freeing a jammed part, swapping a pallet or changing a die, become the non-routine lines for the same station. That is useful twice over, because non-routine work is exactly what a register built from machine lists leaves out.
The link runs the other way too. When a time study leads to a new method, the element list changes, so the JSA changes, so the register line changes. In the trim press example an air blast removes the hand-clearing element, and the top register line falls from 15 to 10. If your industrial engineers and your safety team keep one shared element list for each job, the register updates itself from the work they already do.
Common HIRA mistakes
- A register of machines. "Lathe: mechanical hazard" tells nobody what to do. Lines start with an activity.
- Routine work only. Cleaning, setups, breakdowns and contractor jobs are missing, and they are where the daily controls do not reach.
- Written by one person at a desk. The scores look tidy and nobody on the floor recognises them.
- Scoring with imaginary controls. The procedure nobody follows and the interlock with a magnet on it still get full credit.
- Residual risk that always lands in the low band. If every line drops to 2 after "training", the scoring is being used to close the page.
- Lower severity after PPE. Gloves change the likelihood of a cut. They do not change what a press does to a hand.
- No owners and no dates, so the additional controls column is a wish list.
- Built for the audit, then filed. The new machine, the moved line and last month's near miss never reach it.
- One enormous register for the whole site that nobody can read. Keep one for each department, and a one-page summary of the high lines for the plant manager.
- Treating a low score as proof of safety. The number is a way to rank lines for attention. It is not a measurement.
Controls decay between reviews, so the register needs a routine that checks them. In LeanSuite, workplace safety runs safety inspections, gemba walks and LOTO checks from ready-made templates on a phone, and a failed item raises a safety tag for someone to fix. Use the existing controls column as the source for those checklists and the register stays tied to what is true on the floor.
Templates and related guides
- Risk register template: a register with owners and review dates to adapt to the twelve columns.
- Risk assessment matrix: the 5x5 grid and its bands, in Excel and PDF.
- Risk matrix calculator: score severity times likelihood on your own banding.
- Job safety analysis template: for the jobs your high lines point to.
- Risk assessment: the method behind the register, with a fabrication cell worked on a 5x5 matrix.
- Hierarchy of controls: choosing additional controls that change the score for real.
- Permit to work: the control for the non-routine, high severity lines.
Go deeper
This page is the short version. These guides cover each part in full.
- Top Five Common Manufacturing HazardsThe hazard families that fill most of the lines in a manufacturing register.
- 7 Preventable Shop Floor Incidents Most Plants MissIncidents that trace back to activities a register never listed.
- OSHA Audit Preparation: Reducing 40 Hours to 4 HoursKeeping assessments, inspections and actions where an auditor can see them.
- Building a Proactive Safety Culture in ManufacturingGetting operators to take part in finding hazards, which a register depends on.
All our articles on this subject are in the safety management topic.
Free templates and tools
- Risk register templateOne scored list of operational risks with owners, actions and dates, a heat map and a review log.
- Risk assessment matrix template (5×5)A color-coded 5 × 5 severity and likelihood matrix, a scoring guide and a risk register.
- Job safety analysis (JSA) templateJob steps, hazards, risk scored before and after the controls, the hierarchy of controls, PPE and sign-off.
- Preliminary hazard analysis (PHA) worksheetFind and score the hazards of a new line, machine or process before design is fixed, then choose controls and re-score.
- Risk matrix calculatorSeverity times likelihood on a 3 x 3, 4 x 4 or 5 x 5 risk matrix, the band and its action, editable banding, and the score after further controls.
Doing this in LeanSuite
Workplace Safety
Safety inspections, gemba walks and LOTO checks from ready-made templates; a failed item raises a safety tag.
See Workplace SafetyAudit Management
Runs scheduled audits and tracks the findings to closure.
See Audit ManagementTime and Motion Study
Film a station on a phone and get element times, cycle time, standard time and a Yamazumi chart.
See Time and Motion Study
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about hIRA (hazard identification and risk assessment)
HIRA stands for hazard identification and risk assessment. It is the process of finding what could harm people at work, judging how severe and how likely that harm is, and deciding what controls are needed. In most plants the word also names the document that records it: a register with a line for each hazard of each activity in a department.
A HIRA covers a whole department or site at activity level, with one line for each hazard, and shows which jobs carry the most risk. A JSA, or job safety analysis, covers one job step by step and shows how to do it safely. The HIRA tells you which jobs need a JSA first, and each JSA sends its highest risk scores back to the HIRA.
There is no fixed format, but most registers have twelve columns in this order: activity, routine or non-routine, hazard, consequence, existing controls, severity, likelihood, risk level, additional controls, residual risk, owner and review date. The header carries the department, the date and the names of the team that did the assessment. Each hazard of each activity gets its own line.
ISO 45001 does not use the word HIRA and does not prescribe a register layout. Clause 6.1.2 asks for an ongoing, proactive process to identify hazards and assess risks, covering routine and non-routine work, with a defined method and criteria kept as documented information. A HIRA register is a common way to show that. Read the standard for the exact wording, and check your national rules as well.
Review each line by its own date, with the high lines most often, and the whole register at least once a year. Review at once after an incident or near miss in the area, and before any change to the people, machines, materials, methods or layout. A register that was last opened for the audit is describing a department that no longer exists.
A small team from the department, not one person at a desk: the supervisor, at least one operator who does the work, a maintenance technician and the safety lead, with a setter or contractor added when their tasks are on the list. The department manager approves it. Worker participation is also what ISO 45001 clause 5.4 asks for when hazards are identified and risks assessed.
Residual risk is the risk that remains once the additional controls are in place and working. You score severity and likelihood a second time and multiply them. Severity rarely changes unless the hazard is removed or reduced at source, so most of the drop comes from likelihood. Until the action is closed, the residual score is a target and the line still carries its original risk.
Related guides and tools
- Risk assessment: the method, the six steps and the 5x5 matrix
- Job safety analysis: one job, step by step
- JSA vs JHA vs JSRA vs HIRA: which document when
- ISO 45001: the clauses in plain words
- Management of change: when a register line must be reviewed
- Job safety analysis from video: the element list behind the activity column
- Risk register template: every risk, its owner and its review date
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk
Or browse the topics, the full library and the lean glossary.
Rather see it on your own problem?
Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.