Skip to content
LeanSuite

Practical guide · Safety management

HIRA: hazard identification and risk assessment, with the register format

Short answer

HIRA stands for hazard identification and risk assessment. In a plant it usually means one document: a register that lists every activity in a department, the hazards in each, the controls in place, a risk score, the extra controls planned and the risk that remains, with an owner and a review date.

The full form of HIRA is hazard identification and risk assessment. A HIRA register has one line for each hazard of each activity, with these columns: activity, routine or non-routine, hazard, consequence, existing controls, severity, likelihood, risk level, additional controls, residual risk, owner and review date. To build one, list every activity in the department including maintenance, cleaning and contractor work, walk each one with the people who do it, score the risk with today's controls, decide extra controls from the top of the hierarchy of controls, and score again. A HIRA covers a whole department at activity level. A JSA covers one job step by step and feeds the HIRA. ISO 45001 clause 6.1.2 asks for hazard identification and risk assessment but never uses the word HIRA. This is general guidance, and the rules that apply to your site may ask for more.

Last reviewed:

What is HIRA, and what does it stand for?

HIRA is short for hazard identification and risk assessment. The words describe a process: find what could harm people, then judge how bad and how likely the harm is, so you know what to control first. In daily plant language, though, "the HIRA" is a thing you can open: a register, usually a spreadsheet, with a line for every hazard in every activity of a department.

It is the same process our risk assessment guide teaches, under a different name. That guide covers the method: hazard against risk, the six steps, the 5x5 matrix and its limits. This page covers the document: what goes in each column, how to build the register for a whole department, what a filled one looks like and how it relates to a JSA.

The term is searched most in India, where it is a common name for a plant's risk assessment register. Elsewhere the same document is called a risk register, a risk assessment register or a hazard register. You may also meet HIRAC or HIRARC, where the added letters stand for control or for risk control. The content is the same.

A register exists so that three questions have one answer in one place. What can hurt people here? What are we relying on to stop it? What have we promised to do next, and who owns it? If you cannot answer those for a department in five minutes, you do not yet have a HIRA, however many forms are on file.

The HIRA format: the register column by column

No standard fixes the format, so registers differ from company to company. The twelve columns below are the ones most plants end up with, and they follow the order of the thinking: what is done, what could go wrong, what stops it today, how big the risk is, what more will be done, and what is left.

The twelve HIRA columns follow the order of the thinking

Find it

What is done and what could go wrong

  • 1 Activity
  • 2 Routine or non-routine
  • 3 Hazard
  • 4 Consequence

Judge it today

What stops it now, and how big is it

  • 5 Existing controls
  • 6 Severity
  • 7 Likelihood
  • 8 Risk level

Act on it

What more will be done, and what is left

  • 9 Additional controls
  • 10 Residual risk

Keep it alive

Who answers for it, and when it is looked at again

  • 11 Owner
  • 12 Review date

Twelve register columns in four groups: find it (activity, routine or non-routine, hazard, consequence), judge it today (existing controls, severity, likelihood, risk level), act on it (additional controls, residual risk), keep it alive (owner, review date).

Read left to right: find the hazard, judge it with today's controls, act on it, then keep it alive. Add columns if you must, but keep these twelve in this order.
The twelve columns of a HIRA register
ColumnWhat goes in itCommon mistake
1. ActivityOne task or operation in plain words, with where it is done: "Load bar stock into the lathe bar feeder"Writing a department or a machine ("CNC area") in place of something people do
2. Routine or non-routineR for work in the normal cycle or done every shift. NR for setups, cleaning, maintenance, breakdowns, start-up, contractor jobsListing only routine work. Non-routine tasks are the ones the daily controls were not designed for
3. HazardThe thing with the potential to cause harm: a rotating chuck, a 28 kg bar, coolant mist, a forklift crossingWriting the harm ("injury") or the missing control ("no guard") as the hazard
4. ConsequenceThe credible worst harm and who suffers it: "hand drawn in, amputation, operator or setter""Injury" with no detail, so severity cannot be judged
5. Existing controlsWhat is in place and working today: guards, interlocks, procedures, training, PPEListing controls that exist on paper. If the interlock is bypassed, it is not a control
6. Severity (S)A number on your scale for that consequence, such as 1 (first aid) to 5 (fatality or permanent disability)Lowering severity because the event is unlikely. That is the next column's job
7. Likelihood (L)A number on your scale for how likely the consequence is with the existing controlsScoring as if every control always works
8. Risk levelS times L, and the band it falls in (low, medium, high, very high on your own banding)A colour with no number, so nobody can see how it was reached
9. Additional controlsWhat will be added, chosen from the top of the hierarchy of controls first"Training" and "be careful" on every line
10. Residual riskS times L again, as it will be once the additional controls are in and workingDropping severity when only likelihood changed. PPE and procedures rarely change how bad the worst outcome is
11. OwnerOne named person or role answerable for the additional controls"Safety department" or "all"
12. Review dateWhen this line will be looked at again, plus the date each action is dueOne date for the whole register, set a year away

Add a line number, the date and the names of the team in the header. Some registers add columns for legal requirements, the persons exposed or an action status. Keep the twelve in this order whatever you add.

Two columns do most of the work and get the least attention. "Existing controls" is the list of things that must keep working for the score to be true, which makes it the checklist for your inspections and audits. "Additional controls" with an owner and a date is an action plan. A register where every line reads "training" and "PPE" in both is a list of hazards with nothing done about them.

How to build a HIRA register for a department

Build it one department at a time, on the floor, with the people who do the work. A register written in an office from a list of machines misses the activities between the machines, which is where a lot of the handling, cleaning and unjamming happens.

Eight steps from a list of activities to a signed register

  1. 1

    Set the boundary and the team

  2. 2

    List every activity, routine and non-routine

  3. 3

    Walk each activity and name the hazards

  4. 4

    Write the consequence and who is exposed

  5. 5

    Record the existing controls, and check them

  6. 6

    Score severity and likelihood with today's controls

  7. 7

    Decide additional controls, an owner and a date

  8. 8

    Approve it, share it, and keep it alive

Steps 2 to 5 happen on the floor with the people who do the work. Checking that the existing controls really work is the step most registers skip.
  1. 1

    Set the boundary and the team

    Name the department, what is inside it and what is not (the aisle, the stores, the compressor room). Put together a small team: the supervisor, an operator, a maintenance technician and the safety lead. Add a setter or a contractor representative when their work is on the list.

  2. 2

    List every activity, routine and non-routine

    Start from the process flow, the standard work or work instructions, and any time study element lists. Then add what those leave out: setups, cleaning, maintenance, material deliveries, waste removal, breakdowns, start-up after a stop, work by contractors and visitors. Ask the night shift what they do that the day shift does not.

  3. 3

    Walk each activity and name the hazards

    Watch the activity, or have the person walk you through it. For each one go through the hazard families: mechanical, electrical, handling and posture, slips, trips and falls, vehicles, chemicals, noise, heat, fire, pressure and stored energy. Write one line for each hazard.

  4. 4

    Write the consequence and who is exposed

    The credible worst harm, and to whom: the operator, the setter, a cleaner, a passing forklift driver, a visitor. This is what the severity score will rest on.

  5. 5

    Record the existing controls, and check them

    List what is in place. Then test the important ones on the spot: open the interlocked door, look for the guard, ask to see the procedure. A control that does not work goes in the additional controls column as a repair.

  6. 6

    Score severity and likelihood with today's controls

    Use one written scale for the whole site. Score as a team, out loud, and note why when you disagree. Multiply for the risk level and mark the band.

  7. 7

    Decide additional controls, an owner and a date

    Start with the high lines and anything at the top severity. Work down the hierarchy of controls: eliminate, substitute, engineer, then administrative controls and PPE. Give each action one owner and a due date, then score the residual risk.

  8. 8

    Approve it, share it, and keep it alive

    The department manager signs. Brief every shift on the high lines and post them at the area. Set review dates line by line, and review at once after an incident, a near miss or any change to the people, machines, materials or methods.

Expect a first register for one department to take a few sessions on the floor. The value is in the walking and the arguing about scores. Copying a register from another site skips both, and gives you their hazards with your signature on them.

A word on the scoring

This page uses severity 1 to 5 times likelihood 1 to 5, with scores of 1 to 4 low, 5 to 9 medium, 10 to 16 high and 20 to 25 very high. That is our convention, the one on the risk matrix calculator and the risk assessment matrix template, and no standard sets it. Use your site's scale and write it on the register. The reasoning behind the matrix, and its known weaknesses, are in the risk assessment guide.

A filled HIRA register: extract for a machining department

Illustrative example. A job shop runs a machining department with CNC lathes fed by bar feeders, two machining centres, a pedestal grinder for deburring and a forklift that takes finished pallets out through the main aisle. Ten lines from its register are below. To fit the page, the hazard and consequence share a column, and so do the owner and review date.

HIRA register extract, machining department (illustrative)
#Activity (R or NR)Hazard and consequenceExisting controlsS x L = riskAdditional controlsResidual S x LOwner, review
1Load 28 kg bar stock into the lathe bar feeder (R)Manual lift of a 3 m bar: back strain, crushed fingersTwo-person lift rule, gloves3 x 4 = 12 HighBar rack at feeder height so bars roll across (engineering)3 x 2 = 6 MediumProduction supervisor, May 2027
2Run the CNC lathe in automatic cycle (R)Rotating chuck and workpiece: part or jaw thrown, entanglementInterlocked door, chuck pressure monitor5 x 1 = 5 MediumMonthly interlock test added to the maintenance plan5 x 1 = 5 MediumMaintenance lead, Feb 2027
3Clear swarf from the chuck and chip conveyor (R)Sharp swarf, spindle that can start: deep cuts, hand caughtSwarf hook and brush provided, gloves3 x 4 = 12 HighDoor interlock holds the spindle stopped; guard over the conveyor inlet; hook only, no hands3 x 2 = 6 MediumProduction supervisor, Feb 2027
4Change chuck jaws and milling fixtures (NR, setup)9 kg jaws and 22 kg fixtures handled over the table: crushed hand or footSafety shoes3 x 3 = 9 MediumLifting eye and jib hoist for fixtures over 15 kg3 x 1 = 3 LowTooling engineer, May 2027
5Mix and top up metalworking coolant (R, weekly)Skin contact with concentrate: dermatitisGloves, safety data sheet at the sump2 x 4 = 8 MediumDosing pump mixes at the tap; weekly concentration check2 x 2 = 4 LowMaintenance lead, Nov 2027
6Deburr parts on the pedestal grinder (R)Wheel burst, sparks and grit: eye injuryWheel guards, eye shields, tool rest, glasses4 x 2 = 8 MediumWheel and tool rest gap check added to the weekly inspection4 x 1 = 4 LowProduction supervisor, Nov 2027
7Move finished pallets across the main aisle by forklift (R)Forklift and pedestrians share the cell exit: person struckMarked aisle, horn at the exit5 x 2 = 10 HighBarrier rail at the cell exit with one marked crossing5 x 1 = 5 MediumLogistics lead, Feb 2027
8Clean out the coolant sump and chip conveyor (NR, twice a year)Conveyor that can start, slippery sump: limb caught, fallGeneral lockout procedure4 x 3 = 12 HighTask lockout steps posted at the machine; sump vacuum in place of hand bailing4 x 1 = 4 LowMaintenance lead, before next clean
9Replace light fittings above the machines from a mobile platform (NR, contractor)Work at height over running machines: fall, dropped objectContractor induction5 x 2 = 10 HighPermit to work, machines below stopped, exclusion zone5 x 1 = 5 MediumFacilities manager, each job
10Blow chips off parts and fixtures with an air gun (R)Noise across the cell: hearing loss over yearsHearing protection zone3 x 4 = 12 HighQuiet nozzles, noise survey, machine doors kept shut3 x 2 = 6 MediumSafety lead, May 2027

Severity 1 to 5 times likelihood 1 to 5. Bands: 1 to 4 low, 5 to 9 medium, 10 to 16 high, 20 to 25 very high. Our own scales: use your site's.

Ten register lines: risk before and after the additional controls

Example numbers

1. Load bar stock

12 to 6

2. Run the lathe

5 to 5

3. Clear swarf

12 to 6

4. Change jaws and fixtures (NR)

9 to 3

5. Mix coolant

8 to 4

6. Pedestal grinder

8 to 4

7. Forklift at the exit

10 to 5

8. Clean the sump (NR)

12 to 4

9. Replace lights (NR)

10 to 5

10. Air gun, noise

12 to 6

Before: 98 points, 6 high, 4 mediumAfter: 48 points, 6 medium, 4 low

Ten lines of a machining department register. Before: 6 high and 4 medium, total 98. After: 6 medium and 4 low, total 48.

Lavender dot: today. Yellow dot: planned residual. The total falls from 98 to 48; high lines go from 6 to 0. Line 2 does not move: severity 5 cannot fall, the control only holds likelihood at 1.

Now read it as a manager would. Before the additional controls the ten lines add up to 98 points: six high and four medium. After them the total is 48: six medium and four low, with nothing left in the high band. Three of the ten lines are non-routine work, and two of those three were high.

  • Line 2 does not move: 5 x 1 before and 5 x 1 after. The lathe can kill, the interlock makes that very unlikely, and nothing on the list changes the severity. The additional control is there to keep the likelihood at 1. A line like this belongs on a short list the manager sees, whatever its score.
  • Lines 7 and 9 keep severity 5 as well. A barrier and a permit make the event less likely. They do not make a forklift or a fall gentler.
  • Line 8 happens twice a year and scored as high as anything done every shift. Rare is not the same as low risk: the general lockout procedure had never been written for this task.
  • Line 10 is a health hazard with no accident to point to. Registers built from accident records miss lines like it.
  • Lines 1, 3 and 4 use engineering controls and drop the furthest. Line 6 improves with an inspection, an administrative control, so its residual score depends on that check being done every week.

The residual column is a promise, not a fact. Line 1 is still a 12 until the bar rack is installed. Many plants show the current score and the target score side by side for that reason, and only move the line when the owner closes the action.

HIRA and ISO 45001 clause 6.1.2

ISO 45001:2018, the international standard for occupational health and safety management systems, does not contain the acronym HIRA. What it has is clause 6.1.2, titled hazard identification and assessment of risks and opportunities. The HIRA register is the way many plants show they meet that clause. In our own words, with the standard itself as the authority:

ISO 45001:2018 clause 6.1.2 and what it means for the register (our summary)
ClauseWhat it asks for, in plain wordsWhere it shows in a HIRA
6.1.2.1 Hazard identificationAn ongoing, proactive process that takes into account, among other things, how work is organised, routine and non-routine activities, past incidents, potential emergencies, everyone with access to the workplace including contractors and visitors, and actual or proposed changesThe activity column with its R and NR lines, lines for contractor work, lines added after incidents and changes
6.1.2.2 Assessment of OH&S risksAssess the risks from the identified hazards, taking the effectiveness of existing controls into account, with a methodology and criteria that are defined, proactive and kept as documented informationThe existing controls column, the written severity and likelihood scales, the risk level
6.1.2.3 Assessment of opportunitiesLook for chances to improve safety and health performance, such as adapting work to workersAdditional controls that redesign the job, not only guard it
6.1.4 Planning actionPlan actions to address the risks and check they workAdditional controls, owner, date and residual risk
8.1.2 Eliminating hazards and reducing risksUse the hierarchy of controlsThe order in which additional controls are chosen
8.1.3 Management of changeControl planned changes and review the consequences of unintended onesA register line reviewed whenever its activity changes

A paraphrase for orientation. Read the standard for the exact requirements. The standard asks for a defined method and records, and does not prescribe a register layout.

Two practical points follow. First, the standard asks for workers to take part in identifying hazards and assessing risks (clause 5.4), so a register with no operator's name on it is weak evidence. Second, it asks for an ongoing process. An auditor will pick a recent change, a new machine or a moved line, and ask to see the register line that changed with it. That link is covered in management of change, and the standard as a whole in our ISO 45001 guide.

National law is a separate question. Many countries have their own rules on risk assessment, on particular hazards and on who must be consulted, and a customer or corporate standard may add more. Check the rules that apply to your site: a register that fits this page may not cover everything they ask for.

HIRA vs JSA vs HAZOP

These are not rivals. They look at risk from different heights, and a plant with hazardous processes uses all of them.

HIRA, JSA, HAZOP and the point-of-work check on one line each
DocumentLooks atLevel of detailWho writes it, and when
HAZOP (hazard and operability study)A process design: what happens if flow, pressure, temperature or level deviates from intentEach section of pipe and vessel, guide word by guide wordA multi-discipline team led by a trained facilitator, at design and at major process changes
HIRAA whole department or site: every activity and its hazardsOne line for each hazard of each activityThe department team with safety. Built once, then kept current
JSA or JHA (job safety or job hazard analysis)One jobStep by step: each step, its hazards, its controlsThe supervisor and the people who do the job, before a job is standardised and when it changes
Point-of-work checkToday's task, in today's conditionsA few questions on a card, minutes before startingThe person doing the work, every time

The difference between a HIRA and a JSA in one line: the HIRA says which jobs carry the most risk, and the JSA says how to do one of those jobs safely.

Four documents, four heights

HAZOP

A process design: what if flow, pressure or temperature deviates

Multi-discipline team, at design and major process change

HIRA

A whole department: every activity and its hazards

Department team with safety. Built once, kept current

JSA or JHA

One job, step by step

Supervisor and the people who do it

Point-of-work check

Today's task in today's conditions

The person doing it, every time

HAZOP covers a process design, HIRA a whole department, a JSA one job and the point-of-work check today's task. Each narrows the view.

The HIRA says which jobs carry the most risk. The JSA says how to do one of them safely. The point-of-work check catches what changed since.

They feed each other. The HIRA's high lines tell you which jobs need a JSA first. Each finished JSA sends its worst scores back to the register. A HAZOP's findings arrive in the register as lines about process upsets. And a point-of-work check that keeps finding the same problem is telling you a register line is wrong. The full set of look-alike documents, JSRA and task risk assessment included, is sorted out in JSA vs JHA vs JSRA.

How a time study or JSA element list feeds the activity column

The hardest column to fill well is the first. Ask a room what activities happen in a department and you get machine names. The detail you need already exists somewhere else: in the element lists that industrial engineers write for time studies, and in the step lists of any JSAs already done. Each one is a list of what people really do at a station, in order, with break points you can see.

Take the trim press job from our guide to job safety analysis from video. The time study broke one 48 second cycle into eight elements, and the JSA scored a hazard at each. The register does not need all eight rows. It takes the job as one activity and one line for each distinct hazard, carrying the highest score the JSA found for it.

From eight JSA rows to seven register lines: the trim press job (illustrative)
Register line for "Trim and stack housings, trim press cell" (R)From JSA elementsS x L carried over
Hands in the trim die: caught in2 (load the die), 5 (clear flash by hand)5 x 3 = 15 High
Twisted lift to a floor pallet: back strain7 (turn, bend and stack)3 x 4 = 12 High
Ejected flash and noise at the press3 (press trims)3 x 3 = 9 Medium
Sharp flash edges: cuts4 (unload), 5 and 6 (sharp scrap and edges)2 x 4 = 8 Medium
Warm housing from the conveyor: burn1 (pick the housing)2 x 3 = 6 Medium
Repeated filing: wrist strain6 (deburr two edges)2 x 3 = 6 Medium
Flash on the floor: trip8 (walk back)2 x 3 = 6 Medium

Where two elements share a hazard, the line carries the higher score: loading the die is 5 x 2 = 10 and clearing flash is 5 x 3 = 15, so the line reads 15. The JSA number goes in the existing controls column as a reference.

Eight element rows become seven register lines

Example numbers
  • Hands in the trim die: caught infrom5 x 3 = 15
  • Twisted lift to a floor pallet: back strainfrom3 x 4 = 12
  • Ejected flash and noise at the pressfrom3 x 3 = 9
  • Sharp flash edges: cutsfrom2 x 4 = 8
  • Warm housing from the conveyor: burnfrom2 x 3 = 6
  • Repeated filing: wrist strainfrom2 x 3 = 6
  • Flash on the floor: tripfrom2 x 3 = 6

Seven HIRA lines for the trim press job, each listing the JSA elements it comes from and the severity times likelihood it carries over.

The element list is the activity column's raw material. Where two elements share a hazard the line keeps the higher score: loading the die is 10, clearing flash is 15, so the line reads 15.

The irregular elements a time study records, such as freeing a jammed part, swapping a pallet or changing a die, become the non-routine lines for the same station. That is useful twice over, because non-routine work is exactly what a register built from machine lists leaves out.

The link runs the other way too. When a time study leads to a new method, the element list changes, so the JSA changes, so the register line changes. In the trim press example an air blast removes the hand-clearing element, and the top register line falls from 15 to 10. If your industrial engineers and your safety team keep one shared element list for each job, the register updates itself from the work they already do.

Common HIRA mistakes

  • A register of machines. "Lathe: mechanical hazard" tells nobody what to do. Lines start with an activity.
  • Routine work only. Cleaning, setups, breakdowns and contractor jobs are missing, and they are where the daily controls do not reach.
  • Written by one person at a desk. The scores look tidy and nobody on the floor recognises them.
  • Scoring with imaginary controls. The procedure nobody follows and the interlock with a magnet on it still get full credit.
  • Residual risk that always lands in the low band. If every line drops to 2 after "training", the scoring is being used to close the page.
  • Lower severity after PPE. Gloves change the likelihood of a cut. They do not change what a press does to a hand.
  • No owners and no dates, so the additional controls column is a wish list.
  • Built for the audit, then filed. The new machine, the moved line and last month's near miss never reach it.
  • One enormous register for the whole site that nobody can read. Keep one for each department, and a one-page summary of the high lines for the plant manager.
  • Treating a low score as proof of safety. The number is a way to rank lines for attention. It is not a measurement.

Controls decay between reviews, so the register needs a routine that checks them. In LeanSuite, workplace safety runs safety inspections, gemba walks and LOTO checks from ready-made templates on a phone, and a failed item raises a safety tag for someone to fix. Use the existing controls column as the source for those checklists and the register stays tied to what is true on the floor.

Templates and related guides

FAQ

Questions about hIRA (hazard identification and risk assessment)

  1. HIRA stands for hazard identification and risk assessment. It is the process of finding what could harm people at work, judging how severe and how likely that harm is, and deciding what controls are needed. In most plants the word also names the document that records it: a register with a line for each hazard of each activity in a department.

  2. A HIRA covers a whole department or site at activity level, with one line for each hazard, and shows which jobs carry the most risk. A JSA, or job safety analysis, covers one job step by step and shows how to do it safely. The HIRA tells you which jobs need a JSA first, and each JSA sends its highest risk scores back to the HIRA.

  3. There is no fixed format, but most registers have twelve columns in this order: activity, routine or non-routine, hazard, consequence, existing controls, severity, likelihood, risk level, additional controls, residual risk, owner and review date. The header carries the department, the date and the names of the team that did the assessment. Each hazard of each activity gets its own line.

  4. ISO 45001 does not use the word HIRA and does not prescribe a register layout. Clause 6.1.2 asks for an ongoing, proactive process to identify hazards and assess risks, covering routine and non-routine work, with a defined method and criteria kept as documented information. A HIRA register is a common way to show that. Read the standard for the exact wording, and check your national rules as well.

  5. Review each line by its own date, with the high lines most often, and the whole register at least once a year. Review at once after an incident or near miss in the area, and before any change to the people, machines, materials, methods or layout. A register that was last opened for the audit is describing a department that no longer exists.

  6. A small team from the department, not one person at a desk: the supervisor, at least one operator who does the work, a maintenance technician and the safety lead, with a setter or contractor added when their tasks are on the list. The department manager approves it. Worker participation is also what ISO 45001 clause 5.4 asks for when hazards are identified and risks assessed.

  7. Residual risk is the risk that remains once the additional controls are in place and working. You score severity and likelihood a second time and multiply them. Severity rarely changes unless the hazard is removed or reduced at source, so most of the drop comes from likelihood. Until the action is closed, the residual score is a target and the line still carries its original risk.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.