Time study in garment manufacturing: cycle studies, capacity studies and the operation bulletin

Short answer

A garment factory times each sewing operation to set its standard minute value (SMV), then uses a capacity study to check what each operator can really make in an hour. The operation bulletin puts the two together: operations, machines, SMVs, hourly target and operators needed.

In a sewing factory a time study does three jobs. A cycle time study at the machine, by stopwatch or video, measures one operation element by element and gives its SMV once the pace is rated and allowances are added. A capacity study times a few cycles of each operator on the line and converts them to pieces per hour, to find the operation that holds the line back. The operation bulletin lists every operation of the style with its machine, SMV, hourly capacity and operators needed, so the line can be set and balanced. Factories that own General Sewing Data build SMVs from motion codes before the style reaches the floor, and use the stopwatch to check them.

Last reviewed:

What the work study department does in a sewing factory

Sewing is labor paced. The machine runs only while an operator feeds it, so almost every plan in the factory is built from minutes of labor: the price quoted to the buyer, the delivery date, the number of machines on the line and, in many factories, the operator's pay. Somebody has to produce those minutes. That is the work study or industrial engineering (IE) department, and its officers spend most of the day on the sewing floor with a stopwatch, a phone or a tablet.

  • Method: decide how each operation is done, with which machine, attachment, folder or guide, and how the parts are picked up and put down.
  • Standard time: set the SMV of every operation, from a time study or from synthetic data.
  • Operation bulletin: list the operations of the style in sequence with machines, SMVs, targets and the operators needed.
  • Line layout: place the machines so work moves forward in short hand-offs. A spaghetti diagram of the bundles shows where it does not.
  • Capacity study: check what each operator can make per hour on the operation they have been given.
  • Line balancing: move people and work so no operation starves the next. The general method is in line balancing.
  • Follow-up: read the hourly output against the target, find the reason for each gap and report efficiency.

The parent subject is time and motion study. This guide covers what is particular to sewing: the shape of the cycle, the trade's own documents and the numbers a line is run by.

A sewing operation is handling with bursts of sewing in it

Watch one operator for a minute and the pattern is always the same. She picks up the parts, matches the edges, places them under the presser foot, sews a short burst, stops to realign, sews again, cuts the thread and puts the piece aside. The needle runs for part of the cycle. The hands work for all of it.

One side seam cycle: the needle runs in four short bursts

Example numbers
  • Needle running
  • Handling
  • Realign inside the seam
  1. 1Pick up front and back, match edges6 s
  2. 2Place under the presser foot3 s
  3. 3Sew first side, burst 15 s
  4. 4Realign2 s
  5. 5Sew first side, burst 24 s
  6. 6Turn garment, place second side4 s
  7. 7Sew second side, burst 15 s
  8. 8Realign2 s
  9. 9Sew second side, burst 24 s
  10. 10Cut the thread chain2 s
  11. 11Put aside on the bundle3 s

Needle running

18 s

45% of the cycle

Hands

22 s

55% of the cycle

Cycle

40 s

90 pieces an hour at this pace

A 40 second cycle drawn as a bar of 11 elements. The needle runs in four bursts that add up to 18 seconds. Picking up, placing, realigning, cutting and putting aside take the other 22 seconds.

Time from pick up to pick up. A study that starts the watch when the machine starts and stops it when the machine stops has measured less than half of this job.
Illustrative: one cycle of a T-shirt side seam on a 4-thread overlock, 40 seconds
ElementSecondsKind
Pick up front and back from the bundle, match the edges6Handling
Place under the presser foot3Handling
Sew first side: burst, realign, burst5 + 2 + 4Sewing, with one realign
Turn the garment and place the second side4Handling
Sew second side: burst, realign, burst5 + 2 + 4Sewing, with one realign
Cut the thread chain2Handling
Put the piece aside on the bundle3Handling

The needle runs for 18 of the 40 seconds (45 percent). The other 22 seconds are hands. On a shorter seam the needle's share is smaller, because the pick up and the put aside take about as long whatever the seam length.

Three things follow for anyone timing the job. First, the machine part of the cycle depends on seam length, stitch density and machine speed, so it can be calculated. The handling part depends on the method, so it has to be observed or built from motion data. Second, most of the improvement is in the handling: where the bundle sits, which hand picks up, whether a guide or folder removes a realign. That is workstation design, and it comes before timing. Third, some work does not happen every cycle. Untying and retying a bundle, signing the bundle ticket, changing a bobbin or a thread cone and fixing a thread break happen once per bundle or once in many pieces. They belong in the standard, spread over the pieces they serve.

Stopwatch, video, GSD or a capacity study: which one when

Four measurement methods are in daily use on sewing floors. They answer different questions, and a well run IE department uses all four.

The four measurement methods used in a sewing factory

  • Cycle time study

    Question it answers
    What should this operation take?
    How it works
    Time each element over a run of cycles, rate the pace, add allowances
    What you get
    An SMV for the operation
    When it is used
    Styles already running; checking a disputed SMV
    Main limit
    Needs a trained operator already doing the job, and depends on the rating
  • Video study

    Question it answers
    What should it take, and how is it being done?
    How it works
    Film the operator, then mark the elements on the footage
    What you get
    An SMV, plus footage of the method to replay and teach from
    When it is used
    Method improvement, training, short cycles that are hard to split by eye
    Main limit
    One camera sees one workstation
  • General Sewing Data

    Question it answers
    What will it take, before anyone has sewn it?
    How it works
    Build the operation from coded motions with fixed times, plus calculated sewing time
    What you get
    An SMV and a written method, with no rating needed
    When it is used
    Costing and pre-production, before the line is set
    Main limit
    Needs a license and trained analysts; only as good as the method that was coded
  • Capacity study

    Question it answers
    What can this operator make per hour today?
    How it works
    Time a few cycles of each operator and convert to pieces per hour
    What you get
    Capacity per operator and per operation, and the bottleneck
    When it is used
    Line setting, and whenever output is short of target
    Main limit
    Not a standard: it measures a person, not the job
Read each card top to bottom. The first row decides the choice: each method answers a different question.

What General Sewing Data is

General Sewing Data (GSD) is a predetermined motion time system written for sewn products. It was devised by Methods Workshop Limited in the United Kingdom and published in 1978, and it is built on MTM core data. The analyst describes an operation as a sequence of coded motions, such as getting and matching parts, aligning, sewing, trimming and putting aside. Each code carries a fixed time, and the sewing time is calculated from the seam and the machine. Today it is sold as part of GSDCost by Coats Digital. Because the times come from the method and not from watching a person, a GSD value needs no performance rating and can be set before the style reaches the floor. The wider family is covered in predetermined motion time systems.

The two approaches check each other. A factory with GSD still times operations on the floor, because a coded method that nobody follows gives a standard nobody meets. A factory without it relies on time studies and on its own records of similar operations. For long jobs that do not repeat, such as sample making, spreading and cutting, see timing long cycle and team work. For where the time of helpers, checkers and feeders goes, use work sampling.

How to do a cycle time study on a sewing operation

The method is the standard one in how to conduct a time study. These are the points where sewing differs.

A cycle time study at the sewing machine

  1. 1

    Fix the method first

  2. 2

    Choose a trained operator who agrees to it

  3. 3

    Break the cycle into elements with clear break points

  4. 4

    Time enough cycles

  5. 5

    Record what does not happen every cycle

  6. 6

    Rate the pace

  7. 7

    Add the allowances and state the SMV

The first step and the fifth are the two that sewing floor studies most often skip.
  1. 1

    Fix the method first

    Check the machine, the needle and thread, the stitches per inch, the attachment and where the bundle sits. Timing a poor method gives an accurate standard for the wrong job.

  2. 2

    Choose a trained operator who agrees to it

    Pick someone who has done this operation long enough to be past the learning stage and who works at a steady pace. Tell her what the study is for and what will be done with it.

  3. 3

    Break the cycle into elements with clear break points

    Pick up and match, position, sew, realign, sew, trim, put aside. Use break points you can see or hear, such as the hand touching the part or the machine starting. Keep sewing bursts apart from handling.

  4. 4

    Time enough cycles

    A quick check uses a handful of cycles. A study that sets an SMV needs more, and how many depends on how much the cycle varies: the time study sample size calculator gives the number. Sewing cycles are short, so filming twenty cycles and timing from the video is often easier than splitting a 3 second element by eye. See time study from video.

  5. 5

    Record what does not happen every cycle

    Note the bundle size and time the untie, the ticket and the retie. Time a bobbin change, a thread cone change and a thread break when they happen, and count how many pieces pass between them.

  6. 6

    Rate the pace

    Judge the operator's speed and effort against your scale's normal pace while you time, not afterwards. The rating turns observed time into basic time. Standard time explains the scales.

  7. 7

    Add the allowances and state the SMV

    Basic time plus allowances for personal needs and fatigue, for the machine and for bundle handling gives the SMV. The formula, the usual allowance conventions and a worked derivation are in SMV and SAM in garment manufacturing.

Write the method on the same sheet as the time: machine, attachment, stitches per inch, seam length, bundle size. An SMV without its method cannot be checked later, and it cannot be defended when the fabric or the machine changes.

The capacity study: what each operator can make in an hour

A capacity study is the quick tool of the sewing floor. The IE officer stands at each operator in turn, times a few consecutive cycles from pick up to pick up, averages them and converts the average to pieces per hour. Many factories use five cycles and leave out any cycle with an abnormal stop, such as a thread break. That is a trade habit and not a rule: if the five cycles disagree a lot, time more.

The capacity study calculation
StepWorkingResult
Average cycle timeSum of the timed cycles / number of cyclesSeconds per piece
Capacity per hour3,600 / average cycle time in secondsPieces per hour for one operator
Operation capacityAdd the capacities of every operator on the operationPieces per hour for the operation
Line capacityThe lowest operation capacity on the linePieces per hour the line can pass

Some factories reduce the result by their allowance percentage, or apply a rating, before comparing it with the target. Say which you do on the sheet. The example below uses the plain figure.

Read the result for what it is. It is potential: the output if the operator held that pace all hour with work always waiting and no stops. Real hourly output is lower, and the gap between the two is useful. If an operator's capacity is 124 an hour and she is making 95, the loss is not her speed. Look for waiting, bundle handling, machine trouble or rework. If her capacity is itself below the target, the fix is method, training or a second pair of hands.

Reading a capacity study: three cases against a target of 144 an hour

Example numbers
  • Capacity and output both above target

    Target144
    Capacity170
    Output146

    The operation is not holding the line back.

    Leave it. Look elsewhere.

  • Capacity above target, output below

    Target144
    Capacity164
    Output120

    The operator is fast enough. Time is being lost between cycles.

    Look for waiting, bundle handling, machine stops and rework.

  • Capacity itself below target

    Target144
    Capacity124
    Output118

    Even with no stops this operation cannot make the target.

    Improve the method, train, or add a second operator.

Three cards compare an operation's capacity and its actual hourly output with a target of 144. Capacity 170 and output 146: no problem. Capacity 164 and output 120: time is lost between cycles. Capacity 124 and output 118: the operation cannot reach the target at all.

Capacity is what the timed cycles say is possible. Output is what the hourly count says happened. Which of the two is short tells you what kind of problem you have.

A capacity study is also not a standard. It measures one person on one day, at whatever pace she chose while being watched. Do not set an SMV or a piece rate from it.

The operation bulletin: the line on one page

The operation bulletin is the planning document of a sewing line. It lists every operation of the style in sewing order with the machine and attachment, the SMV, the hourly capacity at standard pace and the number of operators the target calls for. Supervisors set the line from it, mechanics pull machines from it, and planning and costing take the total SMV from it. Some factories call it an operation breakdown or a line plan.

The four sums in an operation bulletin
NumberFormulaWhat it tells you
Garment SMVSum of the operation SMVsStandard minutes of sewing in one garment
Daily line targetOperators x working minutes x planned efficiency / garment SMVPieces the line should make in a day
Capacity per operator at standard60 / operation SMVPieces per hour from one operator working at 100 percent
Operators needed on an operationHourly target x operation SMV / (60 x planned efficiency)How many people to put there, as a decimal

Planned efficiency is the factory's own figure for this line and this kind of style, taken from its records. It is not a standard, and it is lower in the first days of a new style.

The operators needed figure never comes out in whole people. An operation that needs 1.4 operators gets one or two, and that rounding is where balancing starts. The trade's usual answers are to give a fast operator the operation that needs 1.2, to pair two small operations on one person where the machine type allows, and to keep a multi-skilled floater who covers the fractions. A skills matrix shows who can sew what.

Line efficiency

The line is judged by efficiency: minutes produced divided by minutes attended. Minutes produced are pieces out x garment SMV. Minutes attended are operators x minutes worked. A line of 12 operators that works 480 minutes and makes 944 garments of 3.50 SMV has produced 3,304 minutes from 5,760 attended, which is 57.4 percent. Count helpers in the operators only if their work is in the SMV. The general version of this measure is in labor efficiency.

Worked example: a T-shirt line that is short of target

Illustrative example. A line of 12 operators sews a basic crew neck T-shirt in eight operations. The SMVs are given: they came from the factory's time studies and are inputs here. The line works 480 minutes a day and is planned at 70 percent efficiency.

Step 1: the operation bulletin

Garment SMV is 3.50 minutes. The daily target is 12 x 480 x 0.70 / 3.50 = 1,152 pieces, which is 144 an hour.

Operation bulletin for the T-shirt line

Example numbers
Style
Crew neck T-shirt
Operators
12
Minutes per day
480
Planned efficiency
70%
Garment SMV
3.50
Target
1,152 a day, 144 an hour
No.OperationMachineSMVCapacity per operator at 100%Operators neededOperators setShort or spare
1Shoulder join4-thread overlock0.302001.0310.03 short
2Neck rib attach4-thread overlock0.501201.7120.29 spare
3Neck topstitchFlatlock0.401501.3710.37 short
4Label attachSingle needle lockstitch0.252400.8610.14 spare
5Sleeve hemFlatlock0.351711.2010.20 short
6Sleeve attach4-thread overlock0.601002.0620.06 short
7Side seam4-thread overlock0.70862.4020.40 short
8Bottom hemFlatlock0.401501.3720.63 spare
Total3.5012.0012

Operators needed = 144 x SMV / (60 x 0.70). Capacity per operator at 100% = 60 / SMV.

An operation bulletin sheet. Header: 12 operators, 480 minutes, 70 percent planned efficiency, garment SMV 3.50, target 144 an hour. Eight rows give each operation's machine, SMV, capacity per operator at 100 percent, operators needed and operators set. Neck topstitch needs 1.37 and has 1. Bottom hem needs 1.37 and has 2.

The last column is the one to read. Every operation is a little short or a little spare, because people come in whole numbers. The two flatlock rows marked in yellow are where this line will go wrong.

Step 2: the hourly count says something is wrong

After the first days on the style the line averages 118 pieces an hour against the 144 planned. Over the day that is 944 pieces and an efficiency of 57.4 percent. Part-sewn pieces are piling up in front of the neck topstitch.

Step 3: the capacity study

The IE officer times five consecutive cycles of every operator and converts each average to pieces per hour.

Illustrative: capacity study of the 12 operators, five cycles each
OperatorOperationCycles timed (seconds)AverageCapacity per hourOperation capacity
A1 Shoulder join16, 15, 17, 16, 1616.0225225
B2 Neck rib attach27, 28, 29, 28, 2828.0129238
C2 Neck rib attach32, 34, 33, 35, 3133.0109
D3 Neck topstitch28, 30, 29, 31, 2729.0124124
E4 Label attach18, 17, 19, 18, 1818.0200200
F5 Sleeve hem21, 22, 23, 22, 2222.0164164
G6 Sleeve attach33, 35, 34, 34, 3434.0106196
H6 Sleeve attach39, 41, 40, 42, 3840.090
I7 Side seam40, 39, 41, 40, 4040.090170
J7 Side seam44, 46, 45, 47, 4345.080
K8 Bottom hem23, 22, 24, 23, 2323.0157295
L8 Bottom hem25, 27, 26, 26, 2626.0138

Capacity per hour = 3,600 / average cycle. Operation capacities are added before rounding, so 128.6 + 109.1 shows as 238.

Capacity of each operation against the target, as first set

Example numbers
  • 1 Shoulder join225 an hour
  • 2 Neck rib attach238 an hour
  • 3 Neck topstitch: lowest on the line124 an hour
  • 4 Label attach200 an hour
  • 5 Sleeve hem164 an hour
  • 6 Sleeve attach196 an hour
  • 7 Side seam170 an hour
  • 8 Bottom hem295 an hour
  • One operator's capacity (letter and pieces an hour)
  • The operation with the lowest capacity

Eight bars show the capacity per hour of each operation, split by operator, against a dashed target mark at 144. Seven operations are above the target. Neck topstitch, with one operator at 124 an hour, is below it. Bottom hem has two operators and 295 an hour.

A line passes what its slowest operation passes. Here that is 124 an hour at the neck topstitch, while the bottom hem two steps later could sew 295.

Seven operations can pass more than the 144 target. One cannot. The neck topstitch has one operator with a capacity of 124 an hour, so the line can never make more than 124, and with ordinary stops it makes 118. Two operations later, the bottom hem has a capacity of 295, about twice what the line can feed it. Operators K and L spend a good part of each hour waiting.

Step 4: rebalance

Both operations run on flatlock machines, and the skills matrix shows operator L has sewn neck topstitch before. The supervisor moves L and her machine up the line to join D. A check after an hour of practice puts L's cycle on the new operation at 27 seconds, which is 133 an hour.

Illustrative: the two flatlock operations and the line before and after moving operator L
BeforeAfter
Neck topstitch: operatorsDD and L
Neck topstitch: capacity per hour124257
Bottom hem: operatorsK and LK
Bottom hem: capacity per hour295157
Lowest operation capacity on the line124 (neck topstitch)157 (bottom hem)
Hourly output, averaged over the day118138
Line efficiency57.4%67.1%

No one was added and no SMV changed. Efficiency = pieces per day x 3.50 / (12 x 480): 944 pieces before, 1,104 after.

After moving operator L from the bottom hem to the neck topstitch

Example numbers
  • 1 Shoulder join225 an hour
  • 2 Neck rib attach238 an hour
  • 3 Neck topstitch257 an hour
  • 4 Label attach200 an hour
  • 5 Sleeve hem164 an hour
  • 6 Sleeve attach196 an hour
  • 7 Side seam170 an hour
  • 8 Bottom hem: lowest on the line157 an hour

Lowest operation capacity

124 to 157

Neck topstitch, then bottom hem

Hourly output

118 to 138

Target 144

Line efficiency

57.4% to 67.1%

Same 12 operators, same SMVs

The same eight bars after the move. Neck topstitch now has operators D and L and 257 an hour. Bottom hem has operator K alone and 157 an hour, which is now the lowest on the line and above the target of 144. Hourly output rises from 118 to 138 and line efficiency from 57.4 to 67.1 percent.

Every bar now reaches past the dashed target mark. The bottom hem and the sleeve hem have the least margin, so they are the next two workstations to study.

The line is still six pieces an hour under its target, and the capacity study says where to look next. The bottom hem at 157 and the sleeve hem at 164 are now the tightest operations, each with one operator and little margin over 144. The side seam has 170. The next gains come from the hem methods and from keeping work in front of K, not from another move.

Bundle lines, overhead lines and teams: how the system changes the study

How work travels between operators changes what a cycle contains, so name the system on every study.

Three ways work moves through a sewing room, and what each means for the study

  • Progressive bundle

    How work moves
    Tied bundles of cut parts pass from operation to operation. Each operator sews the whole bundle before passing it on.
    What it means for the time study
    Bundle handling is real work that happens once per bundle. Time it and spread it over the bundle size. A capacity study taken mid-bundle misses it.
  • Overhead or unit production

    How work moves
    A hanger on a rail brings one garment to the operator and takes it away.
    What it means for the time study
    Pick up and put aside are shorter and the same every cycle, so cycles vary less. The line stops quickly at a bottleneck, so balance matters more.
  • Modular or team

    How work moves
    A small cross-trained team passes single pieces hand to hand, with members moving between machines.
    What it means for the time study
    One person does several operations and walks between them. Study the team's cycle and each person's loop, as in a cell, and include the walking.
Name the system on the study sheet. The same operation has a different cycle in each.

Standing and moving teams and seated bundle lines also load the body differently. Sewing is hours of repeated reaching with the neck bent and the wrists working, so pair the time study with an ergonomic assessment of the workstation. A faster method that hurts does not last.

New styles: the changeover and the learning curve

A sewing line changes product more often than most assembly lines, and each change costs twice. First the line stops or slows while machines are moved, attachments fitted, threads changed and the first pieces approved. That is a changeover, and the SMED method applies: prepare machines, folders and trims while the old style is still running, so the stop itself is short. Then the operators learn the new operations, and output climbs over days towards the planned efficiency.

  • Do not time a new style on day one and call it the standard. The operator is still learning, and a standard set then will be loose within a week.
  • Do not judge the line against full efficiency on day one either. Plan a ramp and write it into the target, using the factory's own record of how similar styles ramped.
  • Short orders never leave the learning stage. For those, the changeover and the first days are most of the job, so that is where to study.

Mistakes made in sewing floor time studies

Sewing floor time study mistakes and what to do in their place

  • Mistake

    Timing only the needle

    What goes wrong: The standard covers the sewing bursts and misses pick up, matching, realigning and putting aside, which can be most of the cycle.

    Do this

    Time from pick up to pick up, and keep sewing and handling as separate elements.

  • Mistake

    Leaving out bundle handling

    What goes wrong: Untying, the ticket and retying happen once per bundle and never show in a five cycle check.

    Do this

    Time them once and divide by the bundle size. Restudy when the bundle size changes.

  • Mistake

    Ignoring bobbin, thread and needle stops

    What goes wrong: A lockstitch operator who changes a bobbin every so many pieces can never hit a standard that assumes she does not.

    Do this

    Time the stop, count the pieces between stops and include it, or cover it with a stated machine allowance. Not both.

  • Mistake

    Studying the fastest operator only

    What goes wrong: The SMV fits one person. Everyone else is under target from the first hour.

    Do this

    Study a trained operator at a steady pace and rate her. Check the result on a second operator.

  • Mistake

    Skipping the rating, or always writing 100

    What goes wrong: Observed time becomes the standard, so a fast operator sets a tight standard and a slow one a loose standard.

    Do this

    Rate every study. Practice rating as a team against the same footage so officers agree.

  • Mistake

    Using a capacity study as a standard

    What goes wrong: One person's pace on one afternoon becomes the price of the job.

    Do this

    Use capacity studies to set and balance the line. Use a full time study or synthetic data for the SMV.

  • Mistake

    Setting the standard during the learning days

    What goes wrong: The time includes hesitation that will be gone in a week.

    Do this

    Wait until the operator is past the learning stage, or use synthetic data for the first standard and check it later.

  • Mistake

    Keeping the SMV when the method changes

    What goes wrong: A new folder, a different fabric or a larger bundle changes the work, and the old number is wrong.

    Do this

    Tie each SMV to its written method and restudy when the method changes.

Most of these come from timing the machine when the job is the hands.

The people side: piece rates, trust and who holds the stopwatch

In many garment factories the time study touches pay directly. Where operators are paid by the piece or earn a bonus on efficiency, the SMV sets how hard a day's wage is to earn. That changes how people behave when the watch comes out. An operator who believes a fast study will cut her rate has every reason to work slowly while she is timed, and an officer who knows that has a reason to rate hard. Both distort the number.

There is also a plain imbalance of power on the floor. The officer with a stopwatch or a phone has authority over the operator being timed, and both know it. A study done carelessly feels like surveillance, and it will be resisted quietly.

  • Say what the study is for before you start, to the operator and to the line, in the language they speak at home.
  • Agree the rule for standards in advance: a standard changes when the method, machine or material changes, and not because someone beat it.
  • Ask before filming. Frame the hands, the parts and the machine, and say who will see the footage and how long it is kept.
  • Show the operator her own study and let her say what was unusual about those cycles.
  • Never use a capacity study to rank or discipline people. Its job is to find where the line needs help.
  • Train operators as work study officers and line leaders where you can. It changes who is willing to speak.

This is general practice and not legal or labor relations advice. Wage systems, filming at work and work measurement are regulated differently by country, and many factories are bound by buyer codes of conduct and union agreements. Follow those.

Templates, tools and where video fits

Sewing cycles are short and the elements inside them shorter, which is why video suits this work. LeanSuite's time and motion study takes a phone video of the workstation and the AI times every element on a timeline that links back to the footage, split into value-added, necessary and waste, for an engineer to review and certify. Line balancing turns a video of the line into a Yamazumi chart with a takt comparison and rebalancing recommendations. Both run on AI video analysis, which also covers ergonomic studies and changeovers.

FAQ

Questions about time study in garment manufacturing

  1. Time study in the garment industry is the measurement of how long each sewing, cutting or finishing operation takes, in order to set its standard minute value (SMV). An industrial engineer times a trained operator over a number of cycles, element by element, rates her pace and adds allowances. The SMVs are then used for costing, line targets, line balancing and, in many factories, incentive pay.

  2. Work study is the department and the discipline that sets methods and times in a garment factory. It has two halves: method study, which decides how each operation should be done, and work measurement, which sets the standard time for it. In practice work study officers write operation bulletins, set SMVs, run capacity studies, balance lines and follow up hourly output against target.

  3. An operation bulletin is the planning sheet for one style on one sewing line. It lists every operation in sewing order with its machine type, attachments and SMV, then calculates the hourly target, the capacity per operator and the number of operators and machines each operation needs. Supervisors use it to set the line, and planning and costing take the garment SMV from it.

  4. Stand at each operator in turn and time a few consecutive cycles, commonly five, from one pick up to the next. Leave out any cycle with an abnormal stop. Average the cycles and divide 3,600 by the average in seconds to get pieces per hour. Add the operators on each operation, then compare each operation's capacity with the hourly target. The lowest one is the bottleneck.

  5. Line efficiency is minutes produced divided by minutes attended, as a percentage. Minutes produced are the pieces made multiplied by the garment SMV. Minutes attended are the number of operators multiplied by the minutes they worked. A line of 12 operators working 480 minutes that makes 944 garments of 3.50 SMV produces 3,304 standard minutes from 5,760 attended, an efficiency of 57.4 percent.

  6. GSD stands for General Sewing Data. It is a predetermined motion time system for sewn products, devised by Methods Workshop Limited and published in 1978 on MTM core data. An analyst builds an operation from coded motions with fixed times plus calculated sewing time, which gives an SMV without a stopwatch or a rating. It is sold today within GSDCost by Coats Digital.

  7. Work it out from the operation bulletin. For each operation, operators needed = hourly target x operation SMV / (60 x planned efficiency). Add the results for the line total. A 3.50 SMV garment at 144 pieces an hour and 70 percent planned efficiency needs 144 x 3.50 / 42 = 12 operators. Each operation's share comes out as a decimal, and rounding those to whole people is the balancing problem.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?