Method guide · Standard work, SOPs and training
MOST and MODAPTS: sequence models, index values and MODs explained
Short answer
MOST and MODAPTS are fast predetermined motion time systems. MOST describes a task as fixed sequences of lettered steps with index numbers: add the indexes and multiply by 10 for TMU. MODAPTS codes each movement by the body part that moves, in MODs of 0.129 second.
Both systems set the time for manual work from the method, with no stopwatch. In BasicMOST almost everything is one of three sequence models. The general move is A B G A B P A: walk or reach, bend, gain control, move, bend, place, return. Each letter gets an index from a short scale (0, 1, 3, 6, 10, 16), and the sum times 10 is the time in TMU, at 0.036 second each. MiniMOST multiplies by 1 for very short cycles and MaxiMOST by 100 for long ones. In MODAPTS every code carries its own time: M4 is a whole-arm move of 4 MODs, G1 a simple grasp of 1. Add the numbers and multiply by 0.129 for seconds.
Last reviewed:
What are MOST and MODAPTS?
BasicMOST in one picture: a pick and place is one sentence
Example numbers- A1 B0 G1 reach within arm's length, no bend, grasp a light part
- A1 B0 P1 move it within reach, no bend, place with a loose fit
- A0 no return: the hand stays for the next cycle
Add the indexes
1 + 0 + 1 + 1 + 0 + 1 + 0 = 4
x 10
40 TMU
x 0.036
1.44 s
The general move sequence A B G A B P A for a pick and place within reach: A1 B0 G1, A1 B0 P1, A0. The indexes add to 4; times 10 is 40 TMU, which is 1.44 seconds.
MOST is the Maynard Operation Sequence Technique. (In this field it is always an acronym, written in capitals.) MODAPTS is the Modular Arrangement of Predetermined Time Standards. Both are predetermined motion time systems: you describe how a job is done, code the description, and the codes give you the time.
Both were invented for the same reason. MTM-1, the original system, describes work one basic motion at a time and takes hours to apply to a minute of work. In the late 1960s Kjell Zandin, working in the Swedish division of H. B. Maynard and Company, noticed that the MTM motions kept turning up in the same order whenever a person handled an object: reach, grasp, move, position, release, again and again. So why code five motions when you could code one sequence? BasicMOST was released in Sweden in 1972 and in the United States in 1974.
Chris Heyde in Australia had taken a different shortcut a few years earlier, in 1966. His observation was that the time for a movement depends mostly on which part of the body makes it. A finger moves faster than a hand, a hand faster than a forearm. Take the finger movement as the unit and every other movement is a small whole number of those units. That is MODAPTS.
The three BasicMOST sequence models
BasicMOST says that nearly all manual work is one of three things: moving an object freely through the air, moving an object that stays in contact with a surface or is attached to something, or using a hand tool. Each has a fixed sentence of letters, called a sequence model. You never add or drop a letter. You only fill in the index under each one.
| Model | Sequence | Use it when | Example |
|---|---|---|---|
| General move | A B G A B P A | An object is picked up and moved freely through space | Take a part from a tote and put it on a fixture |
| Controlled move | A B G M X I A | The object stays in contact with a surface or is attached to something as it moves | Push a clamp lever, slide a box along a bench, press a button |
| Tool use | A B G A B P * A B P A | A hand tool is fetched, put to the work, used and put back. The * is the tool action | Tighten a screw with a driver, cut with a knife, check with a gauge |
A manual crane sequence also exists for moving loads with a jib crane. Tool actions include fasten or loosen, cut, surface treat, measure, record and think.
Three sentences cover most manual work
General move
An object moved freely through the air
Controlled move
An object that stays in contact or attached
Tool use
Fetch a tool, use it, put it back
General move: A B G, A B P, A. Controlled move: A B G, M X I, A. Tool use: A B G to get the tool, A B P to put it to the work, the tool action, A B P to put it aside, A to return.
| Letter | Parameter | What it covers |
|---|---|---|
| A | Action distance | Movement of the hands, fingers or feet through space, loaded or empty: from a short reach to several steps |
| B | Body motion | Vertical movement of the body: bending, sitting, standing, or getting past an obstruction such as a door |
| G | Gain control | Everything the hand does to get hold of the object |
| P | Placement | Aligning, orienting and engaging the object before letting go |
| M | Move controlled | Guiding the object along a controlled path |
| X | Process time | Time the machine or device takes, not the person |
| I | Alignment | Lining the object up at the end of a controlled move or after process time |
Read the general move as three phases. A B G is the get: go to the object, bend if you must, take hold. A B P is the put: carry it, bend if you must, place it. The last A is the return: go back to where the next cycle starts. A person who has learned that one sentence can describe most of what happens at an assembly bench.
Index values: how the letters get their times
Under each letter you write an index. The index is not a free choice of any number: it comes from a short scale, 0, 1, 3, 6, 10, 16 and then 24, 32, 42 and 54 for the rarer long ones. Each step on the scale stands for a band of time, and the system's data card says which everyday description belongs to which index. To get the time, add the indexes in the sequence and multiply by 10. The answer is in TMU, and 1 TMU is 0.036 second.
- Action distance: 0 means two inches or less, 1 means within reach, 3 means one or two steps, and the index climbs with the number of steps.
- Body motion: 0 means none, 6 means bend and arise, and higher values cover sitting down, standing up and passing through a door.
- Gain control: 1 means a light object picked up simply, 3 covers the harder grasps: heavy or bulky, obstructed, tangled with others, or several objects gathered.
- Placement: 0 means no placement at all, such as a toss; 1 means lay aside or a loose fit; 3 means adjustments or light pressure; 6 means care, precision or heavy pressure.
Because the scale has gaps, no single index is exact. A real motion might be worth 4 and gets a 3 or a 6. Zandin's point was that this does not matter over a whole operation: the roundings up and the roundings down cancel as the sequences add up. It is also why MOST is not meant for timing one short motion in isolation, and why the system comes in three sizes.
The descriptions above are the publicly described core. The full tables, with every index and the rules for frequencies and simultaneous motions, are on the licensed BasicMOST data card.
A worked BasicMOST example
Illustrative example. An operator stands at a fixture. A tote of light brackets sits on the floor two steps away. The task: fetch one bracket, seat it on the fixture, and push the clamp lever shut.
- 1
Split the task into activities and pick the model for each
Fetching the bracket and seating it is an object moved freely: a general move. Pushing the lever is an object that stays attached as it moves: a controlled move.
- 2
Write the sequence letters
General move: A B G A B P A. Controlled move: A B G M X I A.
- 3
Index the general move
Two steps to the tote: A3. Bend and arise to reach the floor: B6. Light bracket, simple grasp: G1. Two steps back: A3. No bend at the fixture: B0. Seat it with a small adjustment: P3. No return, the operator stays put: A0.
- 4
Index the controlled move
Lever within reach: A1. No body motion: B0. Grasp the handle: G1. One short push: M1. No process time and no alignment: X0, I0. No return: A0.
- 5
Add the indexes and multiply by 10
General move: 3 + 6 + 1 + 3 + 0 + 3 + 0 = 16, so 160 TMU. Controlled move: 1 + 0 + 1 + 1 + 0 + 0 + 0 = 3, so 30 TMU. Together 190 TMU.
- 6
Convert, then add allowances
190 x 0.036 = 6.84 seconds, or 190 x 0.0006 = 0.114 minutes. That is normal time. Add your allowance for the standard, as the standard time guide shows.
| Activity | Sequence with indexes | Index total | TMU | Seconds |
|---|---|---|---|---|
| Fetch bracket from floor tote, seat on fixture | A3 B6 G1 A3 B0 P3 A0 | 16 | 160 | 5.76 |
| Push clamp lever shut | A1 B0 G1 M1 X0 I0 A0 | 3 | 30 | 1.08 |
| Task total | 19 | 190 | 6.84 |
TMU = index total x 10. Seconds = TMU x 0.036. Index meanings as publicly described; use the licensed data card for real work.
Now read the first line as a methods engineer. Twelve of its sixteen index points are the two walks and the bend: A3, B6, A3. Put the tote on a stand at the operator's side and they become A1, B0, A1, and the sequence drops to A1 B0 G1 A1 B0 P3 A0: 6 index points, 60 TMU. The task falls from 190 to 90 TMU, from 6.84 to 3.24 seconds, and you found it without a stopwatch.
Move the tote and read the saving off the sequence
Example numbersBefore: tote on the floor, two steps away
Fetch and seat: 16 x 10 = 160 TMU. Lever: 30 TMU.
190 TMU = 6.84 s
After: tote on a stand within reach
Fetch and seat: 6 x 10 = 60 TMU. Lever: 30 TMU.
90 TMU = 3.24 s
Task time
Before, with the tote on the floor two steps away: A3 B6 G1 A3 B0 P3 A0 plus the lever, 190 TMU, 6.84 seconds. After, with the tote on a stand within reach: A1 B0 G1 A1 B0 P3 A0 plus the lever, 90 TMU, 3.24 seconds.
MiniMOST and MaxiMOST
BasicMOST works in steps of 10 TMU, about a third of a second. That is too coarse for a five second cycle and needlessly fine for a forty minute machine set-up. So in 1980 two more versions were released, built the same way with a different multiplier.
| Version | Multiply the index total by | Smallest step | Meant for | How often the job repeats (Maynard's guide) |
|---|---|---|---|---|
| MiniMOST | 1 | 1 TMU (0.036 s) | Short, identical cycles at one workplace, where each reach is measured in inches | More than 1,500 times a week |
| BasicMOST | 10 | 10 TMU (0.36 s) | Most assembly and machine tending, with cycles from under a minute to about ten minutes | 150 to 1,500 times a week |
| MaxiMOST | 100 | 100 TMU (3.6 s) | Long, varied work: set-ups, maintenance, heavy assembly, material handling | Fewer than 150 times a week |
The frequency bands are Maynard's published guidance for choosing a level, not a law. Cycle length and how much the method varies matter as much.
Three sizes of MOST: same sentences, different multiplier
MiniMOST
x 1
Smallest step: 1 TMU = 0.036 s
Short, identical cycles
More than 1,500 times a week
BasicMOST
x 10
Smallest step: 10 TMU = 0.36 s
Most assembly and machine tending
150 to 1,500 times a week
MaxiMOST
x 100
Smallest step: 100 TMU = 3.6 s
Set-ups, maintenance, long varied jobs
Fewer than 150 times a week
MiniMOST multiplies the index total by 1, so its smallest step is 1 TMU or 0.036 second. BasicMOST multiplies by 10: 0.36 second. MaxiMOST multiplies by 100: 3.6 seconds.
There is also AdminMOST for office work, at the same level as BasicMOST. Whichever level you use, the rule from the last section holds: the system is accurate over a whole operation, not over a single line. Maynard's guidance for picking a level is built around an accuracy target of plus or minus 5 percent at 95 percent confidence for the total.
MODAPTS: timing by the body part that moves
MODAPTS has one unit, the MOD. One MOD is 0.129 second, which is 0.00215 minute: about the time to move a finger. Every element in the system is a whole number of MODs, and the number is written into the code. M2 takes 2 MODs. G3 takes 3. You never open a table to find a time, because the code is the time.
The system has 21 elements in three classes.
| Class | What it describes | How the codes run |
|---|---|---|
| Movement | Moving a finger, hand or arm through space. The class is chosen by the body part that has to move, not by measuring the distance | M1 finger, M2 hand, M3 forearm, M4 whole arm, M5 arm at full stretch |
| Terminal | What ends the movement: a get or a put | Get: G0 contact, G1 simple grasp, G3 a grasp that needs more than one finger action. Put: P0 no attention needed, P2 with one check or correction, P5 with more than one |
| Auxiliary | Everything else: load factor, eye use, regrasp, decide, foot action, apply pressure, crank, walk, bend and arise, sit and stand | One letter and its MOD value. Walking is W5, 5 MODs a pace; bend and arise is B17; sit and stand is S30 |
Described from the published outline of the system. The full definitions and rules are in the MODAPTS manual from the International MODAPTS Association.
MODAPTS movement classes: the more of the arm that moves, the more MODs
M1 is a finger move of 1 MOD, 0.129 second. M2 is a hand move from the wrist, 2 MODs. M3 is a forearm move from the elbow, 3 MODs. M4 is a whole-arm move from the shoulder, 4 MODs. M5 is the arm at full stretch, 5 MODs.
A movement and the terminal activity that ends it are written as a pair. M3G1 is a forearm move that ends in a simple grasp: 3 + 1 = 4 MODs. M4P2 is a whole-arm move that ends in a placement needing one check: 4 + 2 = 6 MODs. An analyst watching a job, or a video of it, writes these pairs down almost as fast as the hands move, which is the system's selling point.
A worked MODAPTS example
Illustrative example. The same hand motion as on the MTM page: the right hand takes a bracket lying on the bench and places it on a locating pin. Both movements use the whole arm.
| Activity | Code | MODs | Seconds |
|---|---|---|---|
| Reach to the bracket and grasp it | M4G1 | 4 + 1 = 5 | 0.645 |
| Carry it to the pin and place it with one check | M4P2 | 4 + 2 = 6 | 0.774 |
| Total | 11 | 1.419 |
Seconds = MODs x 0.129. Normal time, before allowances.
A get and a put in MODAPTS: 11 MODs
Example numbersGet: M4G1
4 + 1 = 5 MODs = 0.645 s
Put: M4P2
4 + 2 = 6 MODs = 0.774 s
Add the MODs
5 + 6 = 11 MODs
x 0.129
1.419 s
M4G1 is a whole-arm move of 4 MODs ending in a simple grasp of 1 MOD. M4P2 is a whole-arm move of 4 MODs ending in a placement with one check, 2 MODs. Total 11 MODs, 1.419 seconds.
Two lines, eleven MODs, 1.42 seconds. To convert the other way, a second is about 7.75 MODs and a minute is about 465. MODAPTS is used by large manufacturers and also by organisations that employ people with disabilities, where a simple system that everyone can follow matters.
MOST, MODAPTS and MTM-1 compared
| MTM-1 | BasicMOST | MODAPTS | |
|---|---|---|---|
| Building block | One basic motion | A whole sequence of motions | A movement plus what ends it |
| Time unit | TMU (0.036 s) | TMU, in steps of 10 | MOD (0.129 s) |
| What you must measure | Each distance, to the inch or centimetre | Distance in bands: within reach, steps | Nothing: which body part moves |
| Where the time comes from | A table per motion | An index per letter, from the data card | The number in the code |
| Speed of analysis | Slowest | Fast | Fast, and the quickest to learn |
| Detail on a short cycle | Highest | Low; MiniMOST exists for this | Moderate |
| Best fit | Short cycles in very high volume | General assembly, machine tending, walking work | Seated or standing bench work with the hands |
| The same pick and place (illustrative) | 34 TMU = 1.22 s | 40 TMU = 1.44 s | 11 MOD = 1.42 s |
Last row: MTM-1 with teaching values (12 + 2 + 12 + 6 + 2), BasicMOST A1 B0 G1 A1 B0 P1 A0 = 4 x 10, MODAPTS M4G1 M4P2. Illustrative, not a benchmark of the systems.
One pick and place, written three ways
Example numbersMTM-1 5 lines
34 TMU = 1.22 s
R10B G1A M10C P1SE RL1
BasicMOST 1 line
40 TMU = 1.44 s
A1 B0 G1 A1 B0 P1 A0
MODAPTS 2 lines
11 MOD = 1.42 s
M4G1 M4P2
Bars drawn on one scale, 0 to 1.6 seconds.
MTM-1: R10B G1A M10C P1SE RL1, 34 TMU, 1.22 seconds. BasicMOST: A1 B0 G1 A1 B0 P1 A0, 40 TMU, 1.44 seconds. MODAPTS: M4G1 M4P2, 11 MOD, 1.42 seconds.
The last row is worth a moment. Three systems, one small task, three answers within about a fifth of a second of each other. They will never agree exactly on one motion, because each rounds at a different place. Over a full operation of fifty or a hundred lines they converge, which is all a standard needs. What you must not do is mix them: a standard that is half MOST and half MODAPTS cannot be audited by anyone trained in either.
How to choose between them
- Start with what your company or your customer already uses. A shared system is worth more than a slightly better fit.
- If people walk, bend, fetch and use tools, MOST describes that naturally: the walking and the body motions are built into every sequence.
- If the work is done by the hands at one bench, and you want supervisors and team leaders to read the analysis, MODAPTS is the easier language.
- If the cycle is a few seconds long and runs all year, use a detailed system: MTM-1 or MiniMOST.
- If the job is already running and you need a number this week, time it. The time study guide shows how, and the page on therbligs and motion economy has a decision table that includes stopwatch and video.
Limits, training and the people side
- Both systems time manual work by a trained person at normal pace. Machine time, waiting, learning and variation come from somewhere else.
- Both are owned. MOST belongs to Accenture, which acquired H. B. Maynard and Company, and MODAPTS to the International MODAPTS Association. Each trains and certifies analysts, and certificates usually have to be renewed.
- Both depend on the method being written correctly. One wrong index or one missed movement is small, but a habit of them is not.
- Neither is a design rule for a healthy job. A sequence can be fast on paper and still ask for a bend to the floor four hundred times a shift. Check posture and force separately.
- Neither replaces looking. Once the job runs, compare the analysis with a few filmed cycles.
The people side is the same as for any standard that is built away from the station. Take the analysis to the workplace, go through it line by line with the person who does the job, and change it where the job differs. An operator who has seen that A3 B6 means two steps and a bend to the floor will also be the first to suggest moving the tote. Where an agreement with a union or works council covers work measurement, follow it. This is general practice, not legal advice.
For jobs that already run, LeanSuite's Time and Motion Study times every element from one phone video, with each time linked to its video frame. It gives you measured element times to put beside a MOST or MODAPTS analysis, and a recording everyone can watch when the two differ.
Go deeper
This page is the short version. These guides cover each part in full.
- Standard Work in Manufacturing: A Complete GuideHolding the method that a MOST or MODAPTS analysis describes.
- Standard Work Tools: Combination Sheet, Standardized Work Chart, Job BreakdownThe sheets that show manual, walking and machine time together.
- The Three Elements of Standard Work: Takt Time, Work Sequence, Standard WIPComparing element times with takt and fixing the work sequence.
- Yamazumi Chart: What It Is and How to Make One in 7 StepsBalancing operators with element times, whichever system they came from.
All our articles on this subject are in the standard work, sops and training topic.
Free templates and tools
- Time study sheetTime each element over 10 cycles and work out the average, lowest repeatable and standard time. Excel does the sums.
- Standard work combination tableOne operator's manual, machine, walk and wait time on a time chart against takt, with machine cycles and a process capacity sheet.
- Standard time calculatorObserved times, a rating and an allowance in; normal time, standard time, units per hour, pieces per shift and labour cost per unit out, with the working.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
- Line balancing calculatorLine efficiency, balance delay and the minimum number of stations from station times and takt.
Doing this in LeanSuite
Time and Motion Study
Times every element from one phone video of the process and reports cycle time, standard time, takt and units per hour, each linked to its video frame.
See Time and Motion StudyAI Video Analysis
One process video becomes a time and motion study, an ergonomic study, line balancing and more.
See AI Video Analysis
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about mOST and MODAPTS
Both are predetermined motion time systems: they set the time for manual work from the method, without a stopwatch. MTM (Methods-Time Measurement, 1948) codes every basic motion, such as reach, grasp and move. MOST (Maynard Operation Sequence Technique, 1972) grew out of MTM and codes whole sequences of motions with index numbers, so it is much faster to apply. Both count time in TMU, where 1 TMU is 0.036 second.
TMU is the time measurement unit, the same unit MTM uses: 0.00001 hour, or 0.036 second. In BasicMOST you add the index values in a sequence and multiply by 10 to get TMU. A sequence of A1 B0 G1 A1 B0 P1 A0 adds to 4, which is 40 TMU or 1.44 seconds. MiniMOST multiplies the index total by 1 and MaxiMOST by 100.
There are three main ones. The general move, A B G A B P A, covers an object moved freely through space. The controlled move, A B G M X I A, covers an object that stays in contact with a surface or attached to something. The tool use sequence, A B G A B P then a tool action then A B P A, covers fetching a hand tool, using it and putting it back.
The multiplier and the kind of work. MiniMOST multiplies the index total by 1 and suits short, identical cycles repeated more than about 1,500 times a week. BasicMOST multiplies by 10 and suits most assembly work, repeated 150 to 1,500 times a week. MaxiMOST multiplies by 100 and suits long, varied jobs such as set-ups and maintenance, done fewer than 150 times a week.
MODAPTS, the Modular Arrangement of Predetermined Time Standards, is a predetermined time system created by Chris Heyde in Australia in 1966. It codes each movement by the body part that makes it: M1 for a finger, M2 a hand, M3 a forearm, M4 the whole arm. The number in each code is its time in MODs, and one MOD is 0.129 second. It has 21 elements.
One MOD is 0.129 second, or 0.00215 minute. To convert a MODAPTS total, multiply the MODs by 0.129. A get coded M4G1 (5 MODs) and a put coded M4P2 (6 MODs) total 11 MODs, which is 1.419 seconds. Going the other way, one second is about 7.75 MODs and one minute is about 465. These are normal times, before allowances.
Not on a single motion. MTM-1 describes each motion in more detail, so it is the more exact tool for a short cycle. MOST uses a stepped index scale, so each line is rounded, but over a whole operation the roundings up and down largely cancel. MOST's advantage is speed: an analysis takes far less time, which is why it is used for longer cycles and general assembly.
Related guides and tools
- Predetermined motion time systems: the family and when to use one
- MTM: the basic motions, the TMU and MTM-UAS
- Therbligs and motion economy, with a which-system decision table
- Standard time: adding allowances to a MOST or MODAPTS total
- Workstation design: layouts that remove walks and bends
- Estimating cycle time for a product that does not exist yet
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk
Or browse the topics, the full library and the lean glossary.
Rather see it on your own problem?
Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.