Worked examples · Value stream mapping and flow
Line balancing examples: three lines worked before and after
Short answer
Three lines, balanced with every number on the page. An assembly line that needs a fifth station when takt drops, a packing line with one element longer than takt, and a cell that gives up an operator when demand falls. Each is shown before and after against the takt line.
Line balancing means sharing the work of a line so every station finishes inside takt time. The fewest stations you can hope for is total work divided by takt, rounded up. In the examples here: 142 seconds of assembly work at a 36 second takt needs 5 stations, not the 4 the sum suggests, because the order of the work does not allow a better split. A packing element of 24 seconds on a 20 second takt has to be split, which takes the line from 5 stations to 4. A cell with 104 seconds of work goes from 3 operators at a 40 second takt to 2 at a 60 second takt.
Last reviewed:
The three lines at a glance
Three lines, three different problems
Example numbersAssembly line
4 to 5 stations
Demand up 25%: takt 45 s to 36 s
- Longest station 40 s to 33 s
- Paid time per unit 180 s, unchanged
Packing line
5 to 4 stations
One element longer than takt (24 s against 20 s)
- Longest station 24 s to 19 s
- Output 1,125 to 1,421 a day, demand 1,350
Machining cell
3 to 2 operators
Demand down a third: takt 40 s to 60 s
- Longest share 38 s to 58 s
- Paid time per piece 120 s, unchanged
Assembly line: takt falls from 45 to 36 seconds, stations go from 4 to 5. Packing line: one 24 second element on a 20 second takt, stations go from 5 to 4. Machining cell: takt rises from 40 to 60 seconds, operators go from 3 to 2.
The main line balancing guide teaches the method on one drill line. This page is the gallery. Each line below has a different problem, so you can find the one that looks like yours. All numbers are illustrative, and each one was recomputed by script before it went on the page.
| Assembly line | Packing line | Machining cell | |
|---|---|---|---|
| What changed | Demand up from 600 to 750 a day | Nothing: one element is longer than takt | Demand down from 675 to 450 a day |
| Work per unit | 142 s, 10 elements | 66 s, 7 elements | 104 s, 7 elements |
| Takt | 45 s to 36 s | 20 s | 40 s to 60 s |
| Crew | 4 to 5 stations | 5 to 4 stations | 3 to 2 operators |
| Longest station | 40 s to 33 s | 24 s to 19 s | 38 s to 58 s |
| Efficiency at takt | 78.9% to 78.9% | 55.0% at its 24 s pace to 82.5% | 86.7% to 86.7% |
| The lesson | The sum says 4. The order of the work says 5. | Move nothing: split the long element. | Rebalance on the way down, or pay 50% more per piece. |
The sums and the rules used here
Every line uses the same few sums. Available time is 450 minutes a shift, which is 27,000 seconds, in all three. Efficiency here is divided by takt, the cycle time each line is balanced to. Some textbooks, including Groover's and Niebel's, divide by the longest station instead because that is the pace the line really runs at. The line balancing guide shows both on one line. Whichever you use, compare like with like.
| What | Formula | Example from the assembly line |
|---|---|---|
| Takt time | Available time / demand | 27,000 / 750 = 36 s |
| Theoretical minimum stations | Total work / takt, rounded up | 142 / 36 = 3.94, so 4 |
| Balance efficiency | Total work / (stations x takt) | 142 / (5 x 36) = 78.9% |
| Idle time per unit | Stations x takt minus total work | 180 minus 142 = 38 s |
| Balance delay | 1 minus balance efficiency | 38 / 180 = 21.1% |
| Output of the line | Available time / longest station, rounded down | 27,000 / 33 = 818 a day |
[Takt time](/learn/takt-time) is the pace the customer sets. The longest station is the pace the line can actually run.
To fill the stations I use ranked positional weight, published by Helgeson and Birnie in 1961: an element's weight is its own time plus the time of everything that has to follow it, and you fill each station from the heaviest free element down. It is one convention among several, and a good hand rule, not a guarantee. Where a line was small enough (ten elements in four stations is about a million possible assignments), I also had a script try every split that respects the order, to see what the best possible answer was. Where the two disagree, the page says so.
Example 1: assembly line, demand rises
Illustrative. A line assembles a room thermostat. Today the customer takes 600 a day, so takt is 27,000 / 600 = 45 seconds and the line runs with four stations. Ten work elements make up 142 seconds. Next quarter the customer asks for 750 a day, so takt becomes 27,000 / 750 = 36 seconds.
| Element | Work | Time (s) | Must come after |
|---|---|---|---|
| A | Load base | 5 | None |
| B | Fit circuit board | 18 | A |
| C | Fit display | 14 | A |
| D | Connect wires to board | 22 | B |
| E | Fit relay | 10 | B |
| F | Fit knob | 8 | C |
| G | Fit back cover | 12 | D, E, F |
| H | Snap and screw cover | 20 | G |
| I | Functional test | 24 | H |
| J | Label and bag | 9 | I |
| Total | 142 |
Read the precedence diagram before you move anything. Everything from G on is a single chain, 12 + 20 + 24 + 9 = 65 seconds, that can only be cut between elements. The test, I, cannot start until H is done, and H cannot be done until the cover goes on. That chain is what limits the answer.
What must come before what, and where each element went
Example numbers- Station 1: A, B, E = 33 s
- Station 2: C, F = 22 s
- Station 3: D = 22 s
- Station 4: G, H = 32 s
- Station 5: I, J = 33 s
Precedence diagram of ten elements. A leads to B and C. B leads to D and E, C leads to F. D, E and F all lead to G. Then G, H, I and J follow in a chain. Station 1 holds A, B and E, station 2 C and F, station 3 D, station 4 G and H, station 5 I and J.
Today the four stations are 37, 40, 32 and 33 seconds. All are under the 45 second takt, so the line meets 600 a day, with the longest station making 27,000 / 40 = 675. Efficiency at takt is 142 / (4 x 45) = 78.9%. At the 40 second pace it is 142 / 160 = 88.8%, which is why the two conventions must not be mixed.
Now takt is 36. The sum says 142 / 36 = 3.94, so four stations should do. They cannot. Trying every split of the ten elements that respects the order, the best four-station balance still has a 40 second station, four seconds over takt. The reason is simple arithmetic. Four stations at 36 seconds hold 144 seconds, and there are 142 seconds of work. That leaves 2 seconds of slack in total, and elements this size do not pack that tightly: the test and the cover step cannot share a station (24 + 20 = 44), for one. Ranked positional weight also finds five stations, 33, 36, 20, 20 and 33 seconds. It meets takt, but station 2 has no margin and two stations are half empty. A full search of five-station splits gives a better one.
Assembly line: four stations at takt 45, five at takt 36
Example numbersTakt timeWork elements, in seconds
Before: 600 a day, takt 45 s
4 stations, longest 40 s, efficiency 142 / (4 x 45) = 78.9%
After: 750 a day, takt 36 s
5 stations, longest 33 s, efficiency 142 / (5 x 36) = 78.9%
Left: four stations of 37, 40, 32 and 33 seconds against a 45 second takt. Right: demand rises, takt falls to 36 seconds, and five stations of 33, 22, 22, 32 and 33 seconds hold it. Four stations cannot, because the best possible four station split has a 40 second station.
| Before, takt 45 s | After, takt 36 s | |
|---|---|---|
| Stations and their elements | S1 A B C, S2 D E F, S3 G H, S4 I J | S1 A B E, S2 C F, S3 D, S4 G H, S5 I J |
| Station times (s) | 37, 40, 32, 33 | 33, 22, 22, 32, 33 |
| Longest station | 40 s | 33 s |
| Spare time on the longest | 5 s against takt | 3 s against takt |
| Output at the longest station | 675 a day | 818 a day |
| Efficiency at takt | 78.9% | 78.9% |
| Paid time per unit | 4 x 27,000 / 600 = 180 s | 5 x 27,000 / 750 = 180 s |
The fifth station is a fact about this product's order of work, not a mistake in the balance.
Demand rose by a quarter and the crew rose by a quarter, so paid time per unit did not move: 180 seconds both ways. That is the right result for a line that stays balanced. Stations 2 and 3 carry only 22 seconds each, 14 under takt. That spare time is the next place to look, and the room you will want when times vary. See the yamazumi chart guide for how to read the picture.
Example 2: packing line, one element longer than takt
Illustrative. A line packs pouches into cartons for a customer who takes 1,350 cartons a day, so takt is 27,000 / 1,350 = 20 seconds. Seven elements make up 66 seconds, so the minimum is 66 / 20 = 3.3, which means 4 stations. Today it runs with five, and the output is short.
| Element | Work | Time (s) | Must come after |
|---|---|---|---|
| A | Open carton and place on belt | 7 | None |
| B | Load 24 pouches by hand | 24 | A |
| C | Insert leaflet | 5 | B |
| D | Close and tape | 10 | C |
| E | Label | 6 | D |
| F | Check weight | 6 | D |
| G | Stack on pallet | 8 | E, F |
| Total | 66 |
Today's stations are A on its own (7 s), B on its own (24 s), C and D (15 s), E and F (12 s) and G (8 s). Station 2 takes 24 seconds on a 20 second takt. The line runs at the pace of that station: 27,000 / 24 = 1,125 cartons a day, 225 short. Efficiency at that pace is 66 / (5 x 24) = 55.0%, with 54 seconds of waiting in every carton.
Look at the element and not at the neighbors. B is longer than takt all by itself, so shuffling A, C and D changes nothing. One element cannot be shared between two people unless you break it up. Loading 24 pouches can be shared: one person loads 12, a second loads the other 12, 12 s each. With B split into B1 and B2, filling by ranked positional weight gives four stations.
Packing line: one element longer than takt
Example numbersTakt timeWork elements, in seconds
Before: 1,350 a day, takt 20 s
5 stations, longest 24 s: output 1,125 a day
After: loading split in two
4 stations, longest 19 s: output 1,421 a day
Left: five stations of 7, 24, 15, 12 and 8 seconds against a 20 second takt. The 24 second station is over takt. Right: the 24 second loading element is split in two halves of 12 seconds, and four stations of 19, 17, 16 and 14 seconds hold takt.
| Before | After | |
|---|---|---|
| Stations and their elements | S1 A, S2 B, S3 C D, S4 E F, S5 G | S1 A B1, S2 B2 C, S3 D E, S4 F G |
| Station times (s) | 7, 24, 15, 12, 8 | 19, 17, 16, 14 |
| Longest station | 24 s, 4 s over takt | 19 s, 1 s under takt |
| Output a day | 1,125, short by 225 | 1,421, over demand by 71 |
| Efficiency | 55.0% at its 24 s pace | 66 / (4 x 20) = 82.5% at takt |
| Idle time per carton | 54 s | 14 s |
Station 1 has 1 s of spare time, which is very little. See the caution below.
A line with one fewer person that now makes more is a good result, but treat the 1 second margin as a warning. A carton that jams or a slow loader puts station 1 over takt, and there is no slack to catch it. Two ways to widen it: shorten the loading itself with a pouch fixture, or keep a floating helper at the first station until the line has been timed over several shifts.
Splitting an element only works if two people can physically do it without getting in each other's way and without a quality risk. Two people loading one carton at 12 pouches each is easy to see. Splitting a weld between two welders is not. Check the split with the operators, and if you cannot split an element, the other choices are a faster method, or a second parallel station that takes every other carton.
Example 3: a machining cell, demand falls
Illustrative. A cell machines a shaft on a lathe, a mill and a drill, then deburrs, gauges, cleans and packs it. The operators walk a loop and each does a share of seven elements, 104 seconds of work per shaft including walking. At 675 a day takt is 40 seconds. Next year the product moves to a new customer program and demand falls to 450 a day, so takt becomes 60 seconds.
| Element | Work | Time (s) |
|---|---|---|
| a | Load lathe, start | 10 |
| b | Unload lathe, load mill, start | 14 |
| c | Unload mill, load drill, start | 14 |
| d | Unload drill, deburr | 20 |
| e | Gauge two dimensions | 18 |
| f | Clean and oil | 16 |
| g | Pack and log | 12 |
| Total | 104 |
Before anything is shared, check the machines. A cell balance only works if each machine can make one piece per takt. The mill runs for 24 seconds on its own and needs 14 seconds of the operator at the load, 24 + 14 = 38 seconds, which is under the tightest takt, 40. The lathe and the drill have more room. If the mill needed 44, no split of the manual work could save you, and the bottleneck calculator is the next stop.
At a 40 second takt: 104 / 40 = 2.6, so three operators. In loop order the work splits as a, b, c (38 s), d, e (38 s) and f, g (28 s). At a 60 second takt: 104 / 60 = 1.73, so two operators. The only cut that fits is a, b, c, d (58 s) and e, f, g (46 s). The other possible cut, after c, gives 38 and 66, and 66 is over takt.
Machining cell: three operators at takt 40, two at takt 60
Example numbersTakt timeWork elements, in seconds
Before: 675 a day, takt 40 s
3 operators, efficiency 104 / (3 x 40) = 86.7%
After: 450 a day, takt 60 s
2 operators, efficiency 104 / (2 x 60) = 86.7%
Left: three operators with 38, 38 and 28 seconds of work against a 40 second takt. Right: demand falls, takt becomes 60 seconds, and two operators with 58 and 46 seconds hold it. Total work is 104 seconds in both.
| 675 a day, takt 40 s | 450 a day, takt 60 s | 450 a day, crew left at 3 | |
|---|---|---|---|
| Operators | 3 | 2 | 3 |
| Operator shares (s) | 38, 38, 28 | 58, 46 | 38, 38, 28 |
| Longest share | 38 s | 58 s | 38 s |
| Efficiency at takt | 104 / 120 = 86.7% | 104 / 120 = 86.7% | 104 / 180 = 57.8% |
| Idle time per piece | 16 s | 16 s | 76 s |
| Paid time per piece | 3 x 27,000 / 675 = 120 s | 2 x 27,000 / 450 = 120 s | 3 x 27,000 / 450 = 180 s |
Output of two operators is 27,000 / 58 = 465 a day against a demand of 450.
The third column is the one to remember. With the crew unchanged and demand down a third, each piece carries 180 seconds of paid time instead of 120, half as much again. Nothing broke on the line. The balance just went stale, which is the usual way lines drift.
The two-operator split has 2 seconds of spare time on operator 1, about 3%. That is less than most plants allow. Before committing, time the operator's share over a dozen or more cycles. If the deburr, d, sometimes takes 22 s, operator 1 is over takt and the cell cannot make 450. The options are to speed up d with a better tool, or to let operator 2 take the first part of the deburr when operator 1 is behind. The latter works in a cell and rarely works on a fixed line, which is one reason cells are easy to resize. Whatever you do, the combination table for each operator's loop has to be redrawn.
What the three examples teach
- The sum gives a target, not an answer. Total work divided by takt is the fewest stations the line could have. The order of the work decides whether you reach it. On the assembly line you could not.
- Look for an element longer than takt first. No move of other work fixes it. Split it, shorten it, or run it in parallel.
- A crew that fits yesterday's takt is the most common imbalance. Paid time per unit rose 50% on the cell with no change on the shop floor except demand.
- Efficiency is not the goal alone. Both the assembly line and the cell finished near 79% and 87% respectively and were right. What mattered was that every station fit inside takt with some margin.
- Check the margin before you commit. 1 second on the packing line and 2 seconds on the cell are enough on paper and risky on the floor.
- A good rule is not the best answer. Ranked positional weight found the right number of stations each time. It took a full search to find the 33 second split on the assembly line.
How to balance your own line
- 1
List the elements and time them
Use a time and motion study so the times are repeatable all shift, not the best cycle you saw. Break the work where it could be handed over, and keep walking and waiting as their own elements.
- 2
Write what must come before what
Only real reasons count: physical order and quality. Draw the precedence diagram and walk it with an operator.
- 3
Work out takt and the minimum
Takt is available time divided by demand. The minimum number of stations is total work divided by takt, rounded up. That is your target.
- 4
Find any element longer than takt
These come first. Decide to split, shorten or duplicate each one before you fill any station.
- 5
Fill the stations with a rule
Use ranked positional weight or the largest candidate rule from the line balancing guide. Run two rules and keep the better one. For a line of about twelve elements, a line balancing calculator will try more.
- 6
Check the margin and the machines
Look at the longest station, not the average. Leave a few seconds of spare time where times vary. Check that every machine can make one piece per takt. See how many operators for the crew number.
- 7
Try it, then rewrite the standard
Run the new split with the operators for a shift, time it again, adjust, and only then update the standard work at each station.
Where these examples stop being true
- The numbers are illustrative. Your elements, your skills and your tools set your own answer.
- Mixed-model lines, where variants differ in work content, need more than one table. Balance on the weighted average and test against the heaviest variant.
- Skills, certified jobs, fixed equipment and ergonomics rule out some splits that look fine on paper. Check each station with the person who does it.
- A balance that loads every operator to the last second leaves nobody room for a dropped screw. A few seconds of planned slack is not waste.
- Operators will read a rebalance as a speed-up. Say what the study is for, show the chart first and make clear it is about the work and not the person. A balance built with the people who do the job gets tried properly.
LeanSuite's Line Balancing takes a video of the line, times each operator's elements and draws every station against takt, so you can move an element and see the chart redraw before anything changes on the floor. You check the result and decide. The free yamazumi operator balance template draws the same bars by hand.
Line balancing software
Balance a line in LeanSuite
One video of the line goes in. A Yamazumi chart against takt, and rebalancing scenarios you can test, come out.
Go deeper
This page is the short version. These guides cover each part in full.
- Yamazumi Chart: What It Is and How to Make One in 7 StepsThe stacked bar chart used for every before and after in this guide.
- Manufacturing Bottleneck Elimination: 5 Proven StrategiesWhat to do when the limit is a machine and not the split of manual work.
- Cell Design in JIT: Flow Layout PlanningLaying out a cell so operators can share elements as demand changes.
All our articles on this subject are in the value stream mapping and flow topic.
Free templates and tools
- Yamazumi chart template (operator balance)A printable grid for up to eight operators with the takt line, a task table per operator, and an Excel version that works out each total against takt.
- Time study sheetTime each element over 10 cycles and work out the average, lowest repeatable and standard time. Excel does the sums.
- Operator staffing calculatorTakt, work content, the operators a line needs, a check of your station plan and the roster with absence cover, from your own demand and element times.
- Standard work combination tableOne operator's manual, machine, walk and wait time on a time chart against takt, with machine cycles and a process capacity sheet.
- Line balancing calculatorLine efficiency, balance delay and the minimum number of stations from station times and takt.
- Bottleneck calculatorThe step that limits your line, from each step's cycle time, machines and uptime, with daily capacity and the gap to demand.
- Takt time calculatorThe pace a line must hit to meet customer demand, from shift time, breaks and daily demand.
Doing this in LeanSuite
Line Balancing
Drop in a video of your line and get a Yamazumi chart, a takt comparison and rebalancing recommendations.
See Line BalancingTime and Motion Study
Film the station and the AI times every element on a timeline that links to the video, split into value-added, necessary and waste.
See Time and Motion Study
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about line balancing examples
A ten-element thermostat line with 142 seconds of work and a 36 second takt. The sum says 4 stations, but the order of the work makes the best four-station split 40 seconds, so the line needs 5 stations of 33, 22, 22, 32 and 33 seconds. Every station fits inside takt and the longest has 3 seconds to spare.
Balance efficiency is total work content divided by the number of stations times the cycle time the line is balanced to. With 142 seconds of work, 5 stations and a 36 second takt, it is 142 / 180 = 78.9%. Some textbooks divide by the longest station instead. Either is valid, but use the same one throughout.
Because work comes in lumps and has an order. Total work divided by takt assumes you can cut work into any size and give it to any station. Elements cannot be cut, and some must follow others, so a long chain of dependent elements can force a station over takt even when the sum says there is room.
No rearranging of other elements helps, so change the element. Split it between two people if the work can be shared, shorten it with a fixture or a better method, or run two stations in parallel that each take every other unit. In the packing example, splitting a 24 second loading element in two cut a five-station line to four.
Divide the work per piece, walking included, by the new takt time and round up. A cell with 104 seconds of work needs 3 operators at a 40 second takt and 2 at a 60 second takt. Then check that each share fits inside takt with some margin, and that every machine can still make one piece per takt.
List the work elements, time each one and write down what must come before what. Then work out takt time and the minimum number of stations. Look for any element longer than takt before you fill a single station, because those need a different fix. Only then assign elements to stations with a rule and check the result.
Related guides and tools
- Line balancing: the method, the formulas and the drill line worked in full
- Yamazumi chart: how to build and read the bars
- Precedence diagram: drawing what must come before what
- Takt time: the line every station is balanced to
- How many operators: from work content and takt to a crew
- Standard work combination table: each operator's loop after a rebalance
- Time and motion study: where the element times come from
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk
Or browse the topics, the full library and the lean glossary.
Rather see it on your own problem?
Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.