Skip to content
LeanSuite

Line balancing examples: three lines worked before and after

Short answer

Three lines, balanced with every number on the page. An assembly line that needs a fifth station when takt drops, a packing line with one element longer than takt, and a cell that gives up an operator when demand falls. Each is shown before and after against the takt line.

Line balancing means sharing the work of a line so every station finishes inside takt time. The fewest stations you can hope for is total work divided by takt, rounded up. In the examples here: 142 seconds of assembly work at a 36 second takt needs 5 stations, not the 4 the sum suggests, because the order of the work does not allow a better split. A packing element of 24 seconds on a 20 second takt has to be split, which takes the line from 5 stations to 4. A cell with 104 seconds of work goes from 3 operators at a 40 second takt to 2 at a 60 second takt.

Last reviewed:

The three lines at a glance

Three lines, three different problems

Example numbers

Assembly line

4 to 5 stations

Demand up 25%: takt 45 s to 36 s

  • Longest station 40 s to 33 s
  • Paid time per unit 180 s, unchanged

Packing line

5 to 4 stations

One element longer than takt (24 s against 20 s)

  • Longest station 24 s to 19 s
  • Output 1,125 to 1,421 a day, demand 1,350

Machining cell

3 to 2 operators

Demand down a third: takt 40 s to 60 s

  • Longest share 38 s to 58 s
  • Paid time per piece 120 s, unchanged

Assembly line: takt falls from 45 to 36 seconds, stations go from 4 to 5. Packing line: one 24 second element on a 20 second takt, stations go from 5 to 4. Machining cell: takt rises from 40 to 60 seconds, operators go from 3 to 2.

Same method each time: sum the work, divide by takt, fill the stations, check the longest one. Each line is worked below.

The main line balancing guide teaches the method on one drill line. This page is the gallery. Each line below has a different problem, so you can find the one that looks like yours. All numbers are illustrative, and each one was recomputed by script before it went on the page.

Illustrative: the three lines, before and after
Assembly linePacking lineMachining cell
What changedDemand up from 600 to 750 a dayNothing: one element is longer than taktDemand down from 675 to 450 a day
Work per unit142 s, 10 elements66 s, 7 elements104 s, 7 elements
Takt45 s to 36 s20 s40 s to 60 s
Crew4 to 5 stations5 to 4 stations3 to 2 operators
Longest station40 s to 33 s24 s to 19 s38 s to 58 s
Efficiency at takt78.9% to 78.9%55.0% at its 24 s pace to 82.5%86.7% to 86.7%
The lessonThe sum says 4. The order of the work says 5.Move nothing: split the long element.Rebalance on the way down, or pay 50% more per piece.

The sums and the rules used here

Every line uses the same few sums. Available time is 450 minutes a shift, which is 27,000 seconds, in all three. Efficiency here is divided by takt, the cycle time each line is balanced to. Some textbooks, including Groover's and Niebel's, divide by the longest station instead because that is the pace the line really runs at. The line balancing guide shows both on one line. Whichever you use, compare like with like.

The sums used on this page
WhatFormulaExample from the assembly line
Takt timeAvailable time / demand27,000 / 750 = 36 s
Theoretical minimum stationsTotal work / takt, rounded up142 / 36 = 3.94, so 4
Balance efficiencyTotal work / (stations x takt)142 / (5 x 36) = 78.9%
Idle time per unitStations x takt minus total work180 minus 142 = 38 s
Balance delay1 minus balance efficiency38 / 180 = 21.1%
Output of the lineAvailable time / longest station, rounded down27,000 / 33 = 818 a day

[Takt time](/learn/takt-time) is the pace the customer sets. The longest station is the pace the line can actually run.

To fill the stations I use ranked positional weight, published by Helgeson and Birnie in 1961: an element's weight is its own time plus the time of everything that has to follow it, and you fill each station from the heaviest free element down. It is one convention among several, and a good hand rule, not a guarantee. Where a line was small enough (ten elements in four stations is about a million possible assignments), I also had a script try every split that respects the order, to see what the best possible answer was. Where the two disagree, the page says so.

Example 1: assembly line, demand rises

Illustrative. A line assembles a room thermostat. Today the customer takes 600 a day, so takt is 27,000 / 600 = 45 seconds and the line runs with four stations. Ten work elements make up 142 seconds. Next quarter the customer asks for 750 a day, so takt becomes 27,000 / 750 = 36 seconds.

Illustrative: the thermostat line's elements and what each one must follow
ElementWorkTime (s)Must come after
ALoad base5None
BFit circuit board18A
CFit display14A
DConnect wires to board22B
EFit relay10B
FFit knob8C
GFit back cover12D, E, F
HSnap and screw cover20G
IFunctional test24H
JLabel and bag9I
Total142

Read the precedence diagram before you move anything. Everything from G on is a single chain, 12 + 20 + 24 + 9 = 65 seconds, that can only be cut between elements. The test, I, cannot start until H is done, and H cannot be done until the cover goes on. That chain is what limits the answer.

What must come before what, and where each element went

Example numbers
A 5 sB 18 sC 14 sD 22 sE 10 sF 8 sG 12 sH 20 sI 24 sJ 9 s
  • Station 1: A, B, E = 33 s
  • Station 2: C, F = 22 s
  • Station 3: D = 22 s
  • Station 4: G, H = 32 s
  • Station 5: I, J = 33 s

Precedence diagram of ten elements. A leads to B and C. B leads to D and E, C leads to F. D, E and F all lead to G. Then G, H, I and J follow in a chain. Station 1 holds A, B and E, station 2 C and F, station 3 D, station 4 G and H, station 5 I and J.

From G to J the work is one chain of 65 s (12 + 20 + 24 + 9) that can only be cut between elements. B has to come before both D and E, so B goes early.

Today the four stations are 37, 40, 32 and 33 seconds. All are under the 45 second takt, so the line meets 600 a day, with the longest station making 27,000 / 40 = 675. Efficiency at takt is 142 / (4 x 45) = 78.9%. At the 40 second pace it is 142 / 160 = 88.8%, which is why the two conventions must not be mixed.

Now takt is 36. The sum says 142 / 36 = 3.94, so four stations should do. They cannot. Trying every split of the ten elements that respects the order, the best four-station balance still has a 40 second station, four seconds over takt. The reason is simple arithmetic. Four stations at 36 seconds hold 144 seconds, and there are 142 seconds of work. That leaves 2 seconds of slack in total, and elements this size do not pack that tightly: the test and the cover step cannot share a station (24 + 20 = 44), for one. Ranked positional weight also finds five stations, 33, 36, 20, 20 and 33 seconds. It meets takt, but station 2 has no margin and two stations are half empty. A full search of five-station splits gives a better one.

Assembly line: four stations at takt 45, five at takt 36

Example numbers

Takt timeWork elements, in seconds

Before: 600 a day, takt 45 s

4 stations, longest 40 s, efficiency 142 / (4 x 45) = 78.9%

Assembly line before: four stations against a 45 second taktS1 37 seconds, S2 40 seconds, S3 32 seconds, S4 33 seconds. Takt 45 seconds.01020304050ABCS1DEFS2GHS3IJS437403233

After: 750 a day, takt 36 s

5 stations, longest 33 s, efficiency 142 / (5 x 36) = 78.9%

Assembly line after: five stations against a 36 second taktS1 33 seconds, S2 22 seconds, S3 22 seconds, S4 32 seconds, S5 33 seconds. Takt 36 seconds.01020304050ABES1CFS2DS3GHS4IJS53322223233

Left: four stations of 37, 40, 32 and 33 seconds against a 45 second takt. Right: demand rises, takt falls to 36 seconds, and five stations of 33, 22, 22, 32 and 33 seconds hold it. Four stations cannot, because the best possible four station split has a 40 second station.

Four stations is the theoretical minimum at takt 36 (142 / 36 = 3.94), but no split of these elements gets under 40 s on four. The fifth station is not a failure of the method: it is what the precedence chain allows.
Illustrative: the assembly line before and after demand rises
Before, takt 45 sAfter, takt 36 s
Stations and their elementsS1 A B C, S2 D E F, S3 G H, S4 I JS1 A B E, S2 C F, S3 D, S4 G H, S5 I J
Station times (s)37, 40, 32, 3333, 22, 22, 32, 33
Longest station40 s33 s
Spare time on the longest5 s against takt3 s against takt
Output at the longest station675 a day818 a day
Efficiency at takt78.9%78.9%
Paid time per unit4 x 27,000 / 600 = 180 s5 x 27,000 / 750 = 180 s

The fifth station is a fact about this product's order of work, not a mistake in the balance.

Demand rose by a quarter and the crew rose by a quarter, so paid time per unit did not move: 180 seconds both ways. That is the right result for a line that stays balanced. Stations 2 and 3 carry only 22 seconds each, 14 under takt. That spare time is the next place to look, and the room you will want when times vary. See the yamazumi chart guide for how to read the picture.

Example 2: packing line, one element longer than takt

Illustrative. A line packs pouches into cartons for a customer who takes 1,350 cartons a day, so takt is 27,000 / 1,350 = 20 seconds. Seven elements make up 66 seconds, so the minimum is 66 / 20 = 3.3, which means 4 stations. Today it runs with five, and the output is short.

Illustrative: the packing line's elements, in the order they happen
ElementWorkTime (s)Must come after
AOpen carton and place on belt7None
BLoad 24 pouches by hand24A
CInsert leaflet5B
DClose and tape10C
ELabel6D
FCheck weight6D
GStack on pallet8E, F
Total66

Today's stations are A on its own (7 s), B on its own (24 s), C and D (15 s), E and F (12 s) and G (8 s). Station 2 takes 24 seconds on a 20 second takt. The line runs at the pace of that station: 27,000 / 24 = 1,125 cartons a day, 225 short. Efficiency at that pace is 66 / (5 x 24) = 55.0%, with 54 seconds of waiting in every carton.

Look at the element and not at the neighbors. B is longer than takt all by itself, so shuffling A, C and D changes nothing. One element cannot be shared between two people unless you break it up. Loading 24 pouches can be shared: one person loads 12, a second loads the other 12, 12 s each. With B split into B1 and B2, filling by ranked positional weight gives four stations.

Packing line: one element longer than takt

Example numbers

Takt timeWork elements, in seconds

Before: 1,350 a day, takt 20 s

5 stations, longest 24 s: output 1,125 a day

Packing line before: five stations, one over a 20 second taktS1 7 seconds, S2 24 seconds, S3 15 seconds, S4 12 seconds, S5 8 seconds. Takt 20 seconds.0102030AS1BS2CDS3EFS4GS572415128

After: loading split in two

4 stations, longest 19 s: output 1,421 a day

Packing line after: four stations against a 20 second taktS1 19 seconds, S2 17 seconds, S3 16 seconds, S4 14 seconds. Takt 20 seconds.0102030AB1S1B2CS2DES3FGS419171614

Left: five stations of 7, 24, 15, 12 and 8 seconds against a 20 second takt. The 24 second station is over takt. Right: the 24 second loading element is split in two halves of 12 seconds, and four stations of 19, 17, 16 and 14 seconds hold takt.

No amount of moving other elements fixes station 2: the element itself is longer than takt. Split it, shorten it or run two loaders in parallel. The red number is the only station over takt.
Illustrative: the packing line before and after splitting the loading
BeforeAfter
Stations and their elementsS1 A, S2 B, S3 C D, S4 E F, S5 GS1 A B1, S2 B2 C, S3 D E, S4 F G
Station times (s)7, 24, 15, 12, 819, 17, 16, 14
Longest station24 s, 4 s over takt19 s, 1 s under takt
Output a day1,125, short by 2251,421, over demand by 71
Efficiency55.0% at its 24 s pace66 / (4 x 20) = 82.5% at takt
Idle time per carton54 s14 s

Station 1 has 1 s of spare time, which is very little. See the caution below.

A line with one fewer person that now makes more is a good result, but treat the 1 second margin as a warning. A carton that jams or a slow loader puts station 1 over takt, and there is no slack to catch it. Two ways to widen it: shorten the loading itself with a pouch fixture, or keep a floating helper at the first station until the line has been timed over several shifts.

Splitting an element only works if two people can physically do it without getting in each other's way and without a quality risk. Two people loading one carton at 12 pouches each is easy to see. Splitting a weld between two welders is not. Check the split with the operators, and if you cannot split an element, the other choices are a faster method, or a second parallel station that takes every other carton.

Example 3: a machining cell, demand falls

Illustrative. A cell machines a shaft on a lathe, a mill and a drill, then deburrs, gauges, cleans and packs it. The operators walk a loop and each does a share of seven elements, 104 seconds of work per shaft including walking. At 675 a day takt is 40 seconds. Next year the product moves to a new customer program and demand falls to 450 a day, so takt becomes 60 seconds.

Illustrative: the shaft cell's elements, in loop order
ElementWorkTime (s)
aLoad lathe, start10
bUnload lathe, load mill, start14
cUnload mill, load drill, start14
dUnload drill, deburr20
eGauge two dimensions18
fClean and oil16
gPack and log12
Total104

Before anything is shared, check the machines. A cell balance only works if each machine can make one piece per takt. The mill runs for 24 seconds on its own and needs 14 seconds of the operator at the load, 24 + 14 = 38 seconds, which is under the tightest takt, 40. The lathe and the drill have more room. If the mill needed 44, no split of the manual work could save you, and the bottleneck calculator is the next stop.

At a 40 second takt: 104 / 40 = 2.6, so three operators. In loop order the work splits as a, b, c (38 s), d, e (38 s) and f, g (28 s). At a 60 second takt: 104 / 60 = 1.73, so two operators. The only cut that fits is a, b, c, d (58 s) and e, f, g (46 s). The other possible cut, after c, gives 38 and 66, and 66 is over takt.

Machining cell: three operators at takt 40, two at takt 60

Example numbers

Takt timeWork elements, in seconds

Before: 675 a day, takt 40 s

3 operators, efficiency 104 / (3 x 40) = 86.7%

Cell before: three operators against a 40 second taktOp 1 38 seconds, Op 2 38 seconds, Op 3 28 seconds. Takt 40 seconds.010203040506070abcOp 1deOp 2fgOp 3383828

After: 450 a day, takt 60 s

2 operators, efficiency 104 / (2 x 60) = 86.7%

Cell after: two operators against a 60 second taktOp 1 58 seconds, Op 2 46 seconds. Takt 60 seconds.010203040506070abcdOp 1efgOp 25846

Left: three operators with 38, 38 and 28 seconds of work against a 40 second takt. Right: demand falls, takt becomes 60 seconds, and two operators with 58 and 46 seconds hold it. Total work is 104 seconds in both.

Both crews run at 86.7% of paid time. Keeping three operators at takt 60 would drop that to 57.8% and raise labor per piece from 120 s to 180 s. The 2 s left on operator 1 is thin: time that share over many cycles before you commit.
Illustrative: the shaft cell at two levels of demand, and if the crew had not changed
675 a day, takt 40 s450 a day, takt 60 s450 a day, crew left at 3
Operators323
Operator shares (s)38, 38, 2858, 4638, 38, 28
Longest share38 s58 s38 s
Efficiency at takt104 / 120 = 86.7%104 / 120 = 86.7%104 / 180 = 57.8%
Idle time per piece16 s16 s76 s
Paid time per piece3 x 27,000 / 675 = 120 s2 x 27,000 / 450 = 120 s3 x 27,000 / 450 = 180 s

Output of two operators is 27,000 / 58 = 465 a day against a demand of 450.

The third column is the one to remember. With the crew unchanged and demand down a third, each piece carries 180 seconds of paid time instead of 120, half as much again. Nothing broke on the line. The balance just went stale, which is the usual way lines drift.

The two-operator split has 2 seconds of spare time on operator 1, about 3%. That is less than most plants allow. Before committing, time the operator's share over a dozen or more cycles. If the deburr, d, sometimes takes 22 s, operator 1 is over takt and the cell cannot make 450. The options are to speed up d with a better tool, or to let operator 2 take the first part of the deburr when operator 1 is behind. The latter works in a cell and rarely works on a fixed line, which is one reason cells are easy to resize. Whatever you do, the combination table for each operator's loop has to be redrawn.

What the three examples teach

  • The sum gives a target, not an answer. Total work divided by takt is the fewest stations the line could have. The order of the work decides whether you reach it. On the assembly line you could not.
  • Look for an element longer than takt first. No move of other work fixes it. Split it, shorten it, or run it in parallel.
  • A crew that fits yesterday's takt is the most common imbalance. Paid time per unit rose 50% on the cell with no change on the shop floor except demand.
  • Efficiency is not the goal alone. Both the assembly line and the cell finished near 79% and 87% respectively and were right. What mattered was that every station fit inside takt with some margin.
  • Check the margin before you commit. 1 second on the packing line and 2 seconds on the cell are enough on paper and risky on the floor.
  • A good rule is not the best answer. Ranked positional weight found the right number of stations each time. It took a full search to find the 33 second split on the assembly line.

How to balance your own line

  1. 1

    List the elements and time them

    Use a time and motion study so the times are repeatable all shift, not the best cycle you saw. Break the work where it could be handed over, and keep walking and waiting as their own elements.

  2. 2

    Write what must come before what

    Only real reasons count: physical order and quality. Draw the precedence diagram and walk it with an operator.

  3. 3

    Work out takt and the minimum

    Takt is available time divided by demand. The minimum number of stations is total work divided by takt, rounded up. That is your target.

  4. 4

    Find any element longer than takt

    These come first. Decide to split, shorten or duplicate each one before you fill any station.

  5. 5

    Fill the stations with a rule

    Use ranked positional weight or the largest candidate rule from the line balancing guide. Run two rules and keep the better one. For a line of about twelve elements, a line balancing calculator will try more.

  6. 6

    Check the margin and the machines

    Look at the longest station, not the average. Leave a few seconds of spare time where times vary. Check that every machine can make one piece per takt. See how many operators for the crew number.

  7. 7

    Try it, then rewrite the standard

    Run the new split with the operators for a shift, time it again, adjust, and only then update the standard work at each station.

Where these examples stop being true

  • The numbers are illustrative. Your elements, your skills and your tools set your own answer.
  • Mixed-model lines, where variants differ in work content, need more than one table. Balance on the weighted average and test against the heaviest variant.
  • Skills, certified jobs, fixed equipment and ergonomics rule out some splits that look fine on paper. Check each station with the person who does it.
  • A balance that loads every operator to the last second leaves nobody room for a dropped screw. A few seconds of planned slack is not waste.
  • Operators will read a rebalance as a speed-up. Say what the study is for, show the chart first and make clear it is about the work and not the person. A balance built with the people who do the job gets tried properly.

LeanSuite's Line Balancing takes a video of the line, times each operator's elements and draws every station against takt, so you can move an element and see the chart redraw before anything changes on the floor. You check the result and decide. The free yamazumi operator balance template draws the same bars by hand.

Line balancing software

Balance a line in LeanSuite

One video of the line goes in. A Yamazumi chart against takt, and rebalancing scenarios you can test, come out.

FAQ

Questions about line balancing examples

  1. A ten-element thermostat line with 142 seconds of work and a 36 second takt. The sum says 4 stations, but the order of the work makes the best four-station split 40 seconds, so the line needs 5 stations of 33, 22, 22, 32 and 33 seconds. Every station fits inside takt and the longest has 3 seconds to spare.

  2. Balance efficiency is total work content divided by the number of stations times the cycle time the line is balanced to. With 142 seconds of work, 5 stations and a 36 second takt, it is 142 / 180 = 78.9%. Some textbooks divide by the longest station instead. Either is valid, but use the same one throughout.

  3. Because work comes in lumps and has an order. Total work divided by takt assumes you can cut work into any size and give it to any station. Elements cannot be cut, and some must follow others, so a long chain of dependent elements can force a station over takt even when the sum says there is room.

  4. No rearranging of other elements helps, so change the element. Split it between two people if the work can be shared, shorten it with a fixture or a better method, or run two stations in parallel that each take every other unit. In the packing example, splitting a 24 second loading element in two cut a five-station line to four.

  5. Divide the work per piece, walking included, by the new takt time and round up. A cell with 104 seconds of work needs 3 operators at a 40 second takt and 2 at a 60 second takt. Then check that each share fits inside takt with some margin, and that every machine can still make one piece per takt.

  6. List the work elements, time each one and write down what must come before what. Then work out takt time and the minimum number of stations. Look for any element longer than takt before you fill a single station, because those need a different fix. Only then assign elements to stations with a rule and check the result.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.