Practical guide · Value stream mapping and flow
Labor efficiency and labor variance: the formulas, a worked month and what to do about a bad number
Short answer
Labor efficiency is standard hours earned divided by actual hours worked. The labor efficiency variance puts that gap in money: (actual hours minus standard hours allowed) x standard rate. The labor rate variance is (actual rate minus standard rate) x actual hours.
Standard hours allowed, also called earned hours, are good units made x standard hours per unit. Labor efficiency = earned hours / actual hours worked. Labor efficiency variance = (actual hours minus standard hours allowed) x standard rate. Labor rate variance = (actual rate minus standard rate) x actual hours. A department that makes 4,000 units at a standard of 0.50 hours earns 2,000 hours. If it worked 2,150 hours at $24.80 against a standard rate of $24.00, efficiency is 2,000 / 2,150 = 93.0%, the efficiency variance is 150 x $24.00 = $3,600 unfavorable and the rate variance is $0.80 x 2,150 = $1,720 unfavorable. Together they are the $5,320 by which actual labor cost came in above standard.
Last reviewed:
What labor efficiency and labor variance measure
Labor variance in one picture: hours across, rate up
Example numbers- Standard cost = 2,000 earned hours x $24.00 = $48,000
- Labor efficiency variance = (2,150 minus 2,000) x $24.00 = $3,600 unfavorable
- Labor rate variance = ($24.80 minus $24.00) x 2,150 = $1,720 unfavorable
- Actual cost = 2,150 x $24.80 = $53,320, which is $5,320 above standard
Both answer one question: did the work take the labor we said it would? Labor efficiency answers in hours, as a percentage. Labor variance answers in money, and splits the answer in two: how much of the gap came from using more or fewer hours than standard, and how much from paying a different rate than standard.
They exist because a plant quotes, budgets and staffs on a standard time per unit. If the real hours drift away from that standard, prices are wrong, the schedule is wrong and the headcount plan is wrong. The variance is the alarm. It tells you that something differs from the plan and roughly how much it costs. It does not tell you why. That part is your job, and most of this page is about doing it well.
The engineer and the accountant use the same data and different words. Engineers talk about earned hours and efficiency percent. Accountants talk about standard hours allowed and the efficiency variance in dollars. Earned hours and standard hours allowed are the same number.
Labor efficiency, utilization and productivity
Three ratios get used as if they were one. They split the paid day in different places, so each points at a different kind of problem.
| Ratio | Formula | What a low number points to | In the example month |
|---|---|---|---|
| Labor utilization | Direct hours worked / paid hours | People are paid and present but not on the job: waiting for material, machine down, meetings, training, cleaning | 2,150 / 2,400 = 89.6% |
| Labor efficiency | Earned hours / direct hours worked | The job took longer than standard while people were on it: rework, learning, method drift, small stops, or a wrong standard | 2,000 / 2,150 = 93.0% |
| Labor productivity against standard | Earned hours / paid hours | The two above combined. It equals utilization x efficiency | 2,000 / 2,400 = 83.3% |
Efficiency follows the management accounting definition: standard hours of actual output over actual hours worked. Utilization follows the APICS definition: hours worked over hours available.
Three kinds of hours, three ratios
Example numbersEveryone clocked in, all month
250 hours were waiting, meetings, training and downtime
4,000 good units x 0.50 standard hours. 150 hours on the job earned nothing
Utilization
89.6%
2,150 / 2,400
Efficiency
93.0%
2,000 / 2,150
Productivity against standard
83.3%
2,000 / 2,400
Paid hours 2,400, direct hours worked 2,150, earned hours 2,000. Utilization 89.6%, efficiency 93.0%, productivity against standard 83.3%.
Labor productivity in its plainest form is output divided by labor hours, such as units per paid hour. The example department makes 4,000 units in 2,400 paid hours: 1.67 units per hour. That number is fine for tracking one product over time. It stops working when the mix changes, because a month of harder products looks like a bad month. Earned hours fix that by weighting every unit with its own standard.
Check which hours your reports divide by. Many plants report an efficiency that is really earned hours over paid hours, and then argue about whether 83% is good. Split it. Utilization losses are mostly a supply and planning problem. Efficiency losses are mostly a method, training and quality problem. Some plants add quality and call the three-way product overall labor effectiveness, which the OLE calculator works out.
Earned hours against actual hours
Earned hours are the hours the standard says the period's good output should have taken. You earn them by making good units. You spend actual hours whether or not anything was made.
| Term | Also called | What it is | Source |
|---|---|---|---|
| Earned hours | Standard hours allowed, standard hours produced | Good units made x standard hours per unit, added up over all products | Production count and the standards file |
| Actual hours worked | Direct hours, hours on standard | Hours people spent on the jobs that have a standard | Job bookings or the MES |
| Paid hours | Clocked hours, attendance hours | All hours paid for direct employees, including time not on the job | Time and attendance |
| Indirect or idle hours | Off-standard time, downtime bookings | Paid hours minus actual hours worked | Downtime and indirect bookings |
- Count good units only. A unit that is scrapped earned nothing, and the hours spent on it stay in the actual hours.
- Earn rework at zero unless the rework has its own standard. The original standard already paid for making the unit once.
- Use the standard that was in force when the work was done. Changing standards mid-month without a record makes the trend meaningless.
- Include set-up if set-up has a standard: earned set-up hours = set-ups done x standard hours per set-up.
The booking rules decide the answer as much as the floor does. If a line waits 40 minutes for material and those minutes stay booked to the job, efficiency falls. If they are booked to a waiting code, utilization falls. The cost is the same. Write the rule down and keep it the same every month, or people will learn to move time between the two.
The same 60 hours of waiting, booked two ways
Example numbersLeft on the job
The wait hides inside the job. Efficiency takes the hit.
Utilization
89.6%
2,150 / 2,400
Efficiency
93.0%
2,000 / 2,150
Booked to a waiting code
The wait is visible as lost time. Utilization takes the hit.
Utilization
87.1%
2,090 / 2,400
Efficiency
95.7%
2,000 / 2,090
If 60 hours of waiting for material stay booked to the job, utilization is 89.6% and efficiency 93.0%. If they are booked to a waiting code, utilization is 87.1% and efficiency 95.7%. Productivity against standard is 83.3% either way.
Labor efficiency variance and labor rate variance
Standard costing compares what labor cost with what it should have cost for the units actually made, then splits the difference into an hours part and a rate part.
| Variance | Formula | What it isolates |
|---|---|---|
| Total direct labor variance | (Actual hours x actual rate) minus (standard hours allowed x standard rate) | Everything: actual labor cost against standard labor cost for the output |
| Labor efficiency variance | (Actual hours minus standard hours allowed) x standard rate | The cost of using more or fewer hours than standard, priced at the standard rate so pay changes do not blur it |
| Labor rate variance | (Actual rate minus standard rate) x actual hours | The cost of paying more or less per hour than standard, on the hours actually worked |
| Check | Efficiency variance + rate variance = total variance | The two parts must add back to the total |
AH = actual hours, SH = standard hours allowed for actual output, AR = actual rate, SR = standard rate. Some textbooks call the efficiency variance the labor time, usage or quantity variance.
Written this way round, a positive result means cost above standard: unfavorable. A negative result is favorable. Some texts subtract in the other order so that favorable is positive. Do not rely on the sign. Label every variance with the word favorable or unfavorable, or F and U.
Standard hours allowed are always for the actual output, not the budgeted output. If you planned 4,500 units and made 4,000, the standard hours are 4,000 x the standard, and the missing 500 units are a volume question, not a labor efficiency one.
Where paid hours and worked hours differ, some systems add a third piece. The idle time variance is idle hours x standard rate, the rate variance is then worked on paid hours, and the efficiency variance on hours worked. It is the money version of splitting utilization from efficiency.
How to calculate them, step by step
From the month's output to the two variances
- 1
Count the good output by product
- 2
Work out earned hours
- 3
Get actual hours and actual labor cost
- 4
Work out the ratios
- 5
Work out the two variances
- 6
Split the hours by cause
- 1
Count the good output by product
Good units completed in the period, from the production record. Leave out scrap, and count rework once.
- 2
Work out earned hours
Multiply each product's good units by its standard hours per unit and add them up. This is standard hours allowed.
- 3
Get actual hours and actual labor cost
Hours booked to those jobs, and what was paid for them including overtime premium. Actual rate = actual labor cost / actual hours.
- 4
Work out the ratios
Efficiency = earned hours / actual hours. If you also have paid hours, utilization = actual hours / paid hours.
- 5
Work out the two variances
Efficiency variance = (actual hours minus earned hours) x standard rate. Rate variance = (actual rate minus standard rate) x actual hours. Check that they add up to actual cost minus standard cost.
- 6
Split the hours by cause
Use the loss records for the period to account for the extra hours: rework, learning, stops, method. A variance with no causes attached is only a number.
Worked example: one month in a gearbox assembly department
Illustrative example. A department assembles one gearbox. The standard is 30 minutes of direct labor per unit, which is 0.50 standard hours, and the standard labor rate is $24.00 an hour, so the standard labor cost is $12.00 a unit.
| Input | Value | Where it comes from |
|---|---|---|
| Good units made | 4,000 | Production record |
| Standard hours per unit | 0.50 | The time standard |
| Standard rate | $24.00 an hour | The costing standard |
| Actual hours worked on the job | 2,150 | Job bookings |
| Actual rate | $24.80 an hour | Payroll for those hours, including overtime premium, divided by the hours |
| Paid hours | 2,400 | Time and attendance |
| Step | Sum | Result |
|---|---|---|
| Earned hours | 4,000 x 0.50 | 2,000 hours |
| Labor efficiency | 2,000 / 2,150 | 93.0% |
| Labor utilization | 2,150 / 2,400 | 89.6% |
| Productivity against standard | 2,000 / 2,400 | 83.3% |
| Standard labor cost | 2,000 x $24.00 | $48,000 |
| Actual labor cost | 2,150 x $24.80 | $53,320 |
| Total labor variance | $53,320 minus $48,000 | $5,320 unfavorable |
| Labor efficiency variance | (2,150 minus 2,000) x $24.00 | $3,600 unfavorable |
| Labor rate variance | ($24.80 minus $24.00) x 2,150 | $1,720 unfavorable |
| Check | $3,600 + $1,720 | $5,320 |
Actual labor cost per unit is $53,320 / 4,000 = $13.33 against a standard of $12.00.
From standard cost to actual cost
Example numbersActual labor cost for the month: $53,320
- Standard cost for 4,000 units: $48,000
- Total variance, unfavorable: $5,320
The $5,320 split in two
- Efficiency variance: 150 hours x $24.00: $3,600
- Rate variance: $0.80 x 2,150 hours: $1,720
Standard labor cost $48,000 plus an efficiency variance of $3,600 and a rate variance of $1,720 gives the actual cost of $53,320.
Read it in order. The department earned 2,000 hours and used 2,150, so 150 hours more than standard went into the same output. At the standard rate those hours cost $3,600. On top of that, every hour worked cost 80 cents more than planned, mostly overtime premium, which adds $1,720. Two different problems with two different owners.
The 250 paid hours that were not on the job do not appear in either variance here, because this plant books them to overhead. At the standard rate they are another 250 x $24.00 = $6,000. A plant that reported only the efficiency of 93% would miss the bigger loss.
How the time standard feeds every number
Every figure on this page hangs on one input: standard hours per unit. It comes from a time and motion study, or from an estimate, or from last year's average. If it is wrong, the variance measures the error in the standard and not the performance of the floor.
| Standard per unit | Earned hours | Efficiency | Efficiency variance | What the report says |
|---|---|---|---|---|
| 0.45 hours (10% tight) | 1,800 | 83.7% | $8,400 unfavorable | The department is failing |
| 0.50 hours (as studied) | 2,000 | 93.0% | $3,600 unfavorable | There is a gap worth finding |
| 0.55 hours (10% loose) | 2,200 | 102.3% | $1,200 favorable | Everything is fine |
Same 4,000 units, same 2,150 hours, same people. Only the standard changed.
One month of work, measured against three standards
Example numbers100%: hours used equal hours earned
Standard 0.45 h, 10% tight: efficiency 83.7%, variance $8,400 unfavorable. Standard 0.50 h, as studied: efficiency 93.0%, variance $3,600 unfavorable. Standard 0.55 h, 10% loose: efficiency 102.3%, variance $1,200 favorable
- A standard is only valid for the method it was set on. A fixture change, a new part, a layout move or a different batch size all call for a new study.
- Know what is inside it. A standard includes a normal pace and allowances for personal needs, fatigue and small delays. If the allowance already covers minor stops, booking them as downtime too counts them twice.
- Standards set from history carry history's waste. Last year's average hours per unit make last year's rework and waiting look like standard performance.
- Keep a change record: what changed, when, by how much. Then a jump in efficiency can be traced to the floor or to the file.
- For new products, expect to miss the standard at first and plan for it. People get faster with repetition, and the labor losses guide covers how to keep learning apart from other losses.
This is where measurement tools earn their keep. With LeanSuite's Time and Motion Study, the standard is built from video with each element timed on a timeline, so when someone says the standard is wrong you can open the footage and look together.
What to do when the variance is bad
An unfavorable efficiency variance has four possible sources, and only one of them is people working slowly. Rule them out in this order.
- 1
Check the count and the bookings
Were all good units counted? Were hours from another job, or waiting time, booked here? A surprising variance is a data error more often than a floor problem.
- 2
Check the standard
Has the product, method, tooling or batch size changed since it was set? If so, restudy before you judge anyone.
- 3
Check the conditions
Material quality, machine stops, missing tools, new starters, a different crew size. These make trained people at normal pace take longer than standard.
- 4
Watch the work
Go and see the job, or film it, and compare with the documented method. Look for steps that have crept in and steps that are skipped.
- 5
Account for the hours
Put a number of hours against each cause until most of the gap is explained. Then act on the largest one.
| Cause | Hours | At $24.00 | Action |
|---|---|---|---|
| Rework on the housing seal | 45 | $1,080 | Fix the seal seating fixture, the source of the leaks |
| Two new starters still learning | 40 | $960 | Planned and temporary. Track their curve and keep it out of the trend |
| Short stops and waiting not booked off | 35 | $840 | Book stops over 5 minutes to a code, then work on the top reason |
| Method drift at station 3 | 30 | $720 | Retrain to the standard work and audit it weekly |
| Total | 150 | $3,600 |
Where the 150 extra hours went
Example numbersRework on the housing seal: 45 hours, $1,080. Two new starters still learning: 40 hours, $960. Short stops and waiting not booked off: 35 hours, $840. Method drift at station 3: 30 hours, $720
The rate variance has its own short list: overtime premium, a higher-graded person doing lower-graded work, agency rates, or a pay rise the standard rate has not caught up with. Overtime is the one to look at with the efficiency variance. Extra hours often cause the overtime, so fixing the first can remove part of the second.
A favorable variance deserves a look too. It can mean a real improvement that should become the new standard. It can also mean a loose standard, skipped checks, or a department building units nobody ordered because making more earns more hours.
Where these measures mislead, and the people side
- They reward output, wanted or not. A department judged on efficiency alone will run long batches and build stock. Pair the measure with schedule attainment and quality.
- They are late. A monthly variance tells you about work done up to five weeks ago. Hour-by-hour output against target on the floor catches the same problems the same day.
- They are averages. One bad job can hide among twenty good ones. Look at efficiency by product and by shift before drawing conclusions.
- They say nothing about the bottleneck. An efficient hour at a step that is not the constraint ships nothing extra. See production capacity.
- They shrink in meaning as direct labor shrinks. Where labor is a small share of cost, chasing its variance can cost more than it saves.
- They are not a measure of a person. The standard assumes a trained operator, the stated method and normal conditions. Most of a variance comes from conditions the operator does not control.
That last point decides whether the numbers stay honest. If efficiency is used to rank or discipline individuals, people will protect themselves: bookings get adjusted, problems get hidden, and the standard gets fought at every restudy. Use the variance to find problems in the process, share it with the team that produced it, and fix causes in the open. Pay and disciplinary matters have their own rules, agreements and, in many plants, a union contract. This page does not cover those.
Tools and templates
- Cost variance workbook: standard against actual cost with the variances split out.
- Standard time calculator: observed time, rating and allowance in, standard time out.
- OLE calculator: labor availability, performance and quality in one number.
- Time study sheet: record timed cycles when a standard needs checking.
- Manufacturing cost per unit worksheet: see what the labor gap does to unit cost.
Go deeper
This page is the short version. These guides cover each part in full.
- How to Improve Shop Floor ProductivityPractical ways to raise output per labor hour once you know where the hours go.
- How to Improve Production Efficiency: 7 Practical WaysSeven levers on the losses that sit behind an unfavorable efficiency variance.
- Ways to Reduce Manufacturing CostsWhere labor sits among the other costs of making a unit, and what to cut first.
- Loss Prioritization Framework for ManufacturingHow to rank the causes of lost hours so the first fix is the biggest one.
All our articles on this subject are in the value stream mapping and flow topic.
Free templates and tools
- Standard cost variance workbookEight standard cost variances from your standards and actuals, favorable or unfavorable, proved against actual cost, with the questions to ask on the floor.
- Time study sheetTime each element over 10 cycles and work out the average, lowest repeatable and standard time. Excel does the sums.
- Cost per unit worksheet (manufacturing cost per good unit)One product's cost per good unit by materials, labor, machine and overhead, the gap to target, and which cost lever is worth most a year.
- Standard time calculatorObserved times, a rating and an allowance in; normal time, standard time, units per hour, pieces per shift and labour cost per unit out, with the working.
- Overall labor effectiveness (OLE) calculatorHow well paid labor hours turn into good output: availability, performance and quality of the crew.
Doing this in LeanSuite
Time and Motion Study
Film the station and the AI times every element on a timeline that links to the video, split into value-added, necessary and waste.
See Time and Motion StudyLoss & Cost Management
Shows where your plant loses money, puts a cost on each loss and gives you the tools to remove it.
See Loss & Cost Management
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about labor efficiency and labor variance
Labor efficiency variance = (actual hours worked minus standard hours allowed for actual output) x standard rate. If a department used 2,150 hours to make output that should have taken 2,000 hours, at a standard rate of $24.00, the variance is 150 x $24.00 = $3,600 unfavorable. Fewer hours than standard gives a favorable variance.
Labor efficiency = standard hours earned / actual hours worked x 100. Standard hours earned are good units made x standard hours per unit. A team that makes 4,000 units at a standard of 0.50 hours earns 2,000 hours. If it worked 2,150 hours, labor efficiency is 2,000 / 2,150 = 93.0%.
The rate variance is about the price of an hour: (actual rate minus standard rate) x actual hours. The efficiency variance is about the number of hours: (actual hours minus standard hours allowed) x standard rate. Overtime premium and pay grades drive the first. Rework, learning, stops, method drift and wrong standards drive the second. Added together they equal the total labor variance.
More hours were used than the standard allows for the output. Common causes are rework and scrap, new or untrained operators, poor material, machine stops and waiting booked to the job, drift from the standard method, and a standard that is out of date or was set too tight. Check the data and the standard before assuming the floor was slow.
Utilization is the share of paid hours spent on direct work: direct hours / paid hours. Efficiency is how those direct hours compare with the standard: earned hours / direct hours. A team paid for 2,400 hours that works 2,150 on the job and earns 2,000 has 89.6% utilization and 93.0% efficiency. Multiplied together they give 83.3%.
Earned hours are the standard hours for the good output actually produced: units made x standard hours per unit, added up across products. Accountants call them standard hours allowed. They let you compare output across products of different sizes, and dividing them by actual hours gives labor efficiency.
No. It can come from a real improvement in the method. It can also come from a loose standard, skipped inspections, or building more units than the schedule needs because output earns hours. Check quality, schedule attainment and the age of the standard before treating a favorable variance as a saving.
Related guides and tools
- Standard time: how the hours per unit behind every variance are set
- Labor losses: where paid hours go when they are not making product
- Labor cost and quoting: turning a standard into a cost per unit and a price
- Production capacity: what efficiency and utilization do to what you can ship
- How many operators a line needs: work content, takt, losses and the roster
- Time and motion study: checking a standard that people doubt
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk
Or browse the topics, the full library and the lean glossary.
Rather see it on your own problem?
Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.