Labor efficiency and labor variance: the formulas, a worked month and what to do about a bad number

Short answer

Labor efficiency is standard hours earned divided by actual hours worked. The labor efficiency variance puts that gap in money: (actual hours minus standard hours allowed) x standard rate. The labor rate variance is (actual rate minus standard rate) x actual hours.

Standard hours allowed, also called earned hours, are good units made x standard hours per unit. Labor efficiency = earned hours / actual hours worked. Labor efficiency variance = (actual hours minus standard hours allowed) x standard rate. Labor rate variance = (actual rate minus standard rate) x actual hours. A department that makes 4,000 units at a standard of 0.50 hours earns 2,000 hours. If it worked 2,150 hours at $24.80 against a standard rate of $24.00, efficiency is 2,000 / 2,150 = 93.0%, the efficiency variance is 150 x $24.00 = $3,600 unfavorable and the rate variance is $0.80 x 2,150 = $1,720 unfavorable. Together they are the $5,320 by which actual labor cost came in above standard.

Last reviewed:

What labor efficiency and labor variance measure

Labor variance in one picture: hours across, rate up

Example numbers
Labor cost as a rectangle of hours times rateStandard cost is 2,000 hours times $24.00, $48,000. The efficiency variance is the strip to its right, 150 extra hours at the standard rate, $3,600. The rate variance is the strip across the top, 80 cents on all 2,150 actual hours, $1,720. Not drawn to scale.Standard cost$48,000Efficiency$3,600 URate variance $1,720 U$24.00$24.802,0002,1500Hours (not to scale)Rate per hour
  • Standard cost = 2,000 earned hours x $24.00 = $48,000
  • Labor efficiency variance = (2,150 minus 2,000) x $24.00 = $3,600 unfavorable
  • Labor rate variance = ($24.80 minus $24.00) x 2,150 = $1,720 unfavorable
  • Actual cost = 2,150 x $24.80 = $53,320, which is $5,320 above standard
The sand block is what the output should have cost. Extra hours add the yellow strip at the standard rate. A higher rate adds the lavender strip across every hour actually worked. U means unfavorable.

Both answer one question: did the work take the labor we said it would? Labor efficiency answers in hours, as a percentage. Labor variance answers in money, and splits the answer in two: how much of the gap came from using more or fewer hours than standard, and how much from paying a different rate than standard.

They exist because a plant quotes, budgets and staffs on a standard time per unit. If the real hours drift away from that standard, prices are wrong, the schedule is wrong and the headcount plan is wrong. The variance is the alarm. It tells you that something differs from the plan and roughly how much it costs. It does not tell you why. That part is your job, and most of this page is about doing it well.

The engineer and the accountant use the same data and different words. Engineers talk about earned hours and efficiency percent. Accountants talk about standard hours allowed and the efficiency variance in dollars. Earned hours and standard hours allowed are the same number.

Labor efficiency, utilization and productivity

Three ratios get used as if they were one. They split the paid day in different places, so each points at a different kind of problem.

The three labor ratios (example values are illustrative)
RatioFormulaWhat a low number points toIn the example month
Labor utilizationDirect hours worked / paid hoursPeople are paid and present but not on the job: waiting for material, machine down, meetings, training, cleaning2,150 / 2,400 = 89.6%
Labor efficiencyEarned hours / direct hours workedThe job took longer than standard while people were on it: rework, learning, method drift, small stops, or a wrong standard2,000 / 2,150 = 93.0%
Labor productivity against standardEarned hours / paid hoursThe two above combined. It equals utilization x efficiency2,000 / 2,400 = 83.3%

Efficiency follows the management accounting definition: standard hours of actual output over actual hours worked. Utilization follows the APICS definition: hours worked over hours available.

Three kinds of hours, three ratios

Example numbers
Paid hours2,400 h

Everyone clocked in, all month

Direct hours worked2,150 h

250 hours were waiting, meetings, training and downtime

Earned hours2,000 h

4,000 good units x 0.50 standard hours. 150 hours on the job earned nothing

Utilization

89.6%

2,150 / 2,400

Efficiency

93.0%

2,000 / 2,150

Productivity against standard

83.3%

2,000 / 2,400

Paid hours 2,400, direct hours worked 2,150, earned hours 2,000. Utilization 89.6%, efficiency 93.0%, productivity against standard 83.3%.

The step from the first bar to the second is time people were paid but not on the job. The step from the second to the third is time on the job beyond the standard. Different causes, different fixes.

Labor productivity in its plainest form is output divided by labor hours, such as units per paid hour. The example department makes 4,000 units in 2,400 paid hours: 1.67 units per hour. That number is fine for tracking one product over time. It stops working when the mix changes, because a month of harder products looks like a bad month. Earned hours fix that by weighting every unit with its own standard.

Check which hours your reports divide by. Many plants report an efficiency that is really earned hours over paid hours, and then argue about whether 83% is good. Split it. Utilization losses are mostly a supply and planning problem. Efficiency losses are mostly a method, training and quality problem. Some plants add quality and call the three-way product overall labor effectiveness, which the OLE calculator works out.

Earned hours against actual hours

Earned hours are the hours the standard says the period's good output should have taken. You earn them by making good units. You spend actual hours whether or not anything was made.

The hour terms and where each comes from
TermAlso calledWhat it isSource
Earned hoursStandard hours allowed, standard hours producedGood units made x standard hours per unit, added up over all productsProduction count and the standards file
Actual hours workedDirect hours, hours on standardHours people spent on the jobs that have a standardJob bookings or the MES
Paid hoursClocked hours, attendance hoursAll hours paid for direct employees, including time not on the jobTime and attendance
Indirect or idle hoursOff-standard time, downtime bookingsPaid hours minus actual hours workedDowntime and indirect bookings
  • Count good units only. A unit that is scrapped earned nothing, and the hours spent on it stay in the actual hours.
  • Earn rework at zero unless the rework has its own standard. The original standard already paid for making the unit once.
  • Use the standard that was in force when the work was done. Changing standards mid-month without a record makes the trend meaningless.
  • Include set-up if set-up has a standard: earned set-up hours = set-ups done x standard hours per set-up.

The booking rules decide the answer as much as the floor does. If a line waits 40 minutes for material and those minutes stay booked to the job, efficiency falls. If they are booked to a waiting code, utilization falls. The cost is the same. Write the rule down and keep it the same every month, or people will learn to move time between the two.

The same 60 hours of waiting, booked two ways

Example numbers

Left on the job

The wait hides inside the job. Efficiency takes the hit.

Paid2,400 h
Booked to the job2,150 h
Earned2,000 h

Utilization

89.6%

2,150 / 2,400

Efficiency

93.0%

2,000 / 2,150

Booked to a waiting code

The wait is visible as lost time. Utilization takes the hit.

Paid2,400 h
Booked to the job2,090 h
Earned2,000 h

Utilization

87.1%

2,090 / 2,400

Efficiency

95.7%

2,000 / 2,090

If 60 hours of waiting for material stay booked to the job, utilization is 89.6% and efficiency 93.0%. If they are booked to a waiting code, utilization is 87.1% and efficiency 95.7%. Productivity against standard is 83.3% either way.

Nothing changed on the floor. Moving the booking lifts one ratio and drops the other, and the product stays at 83.3%. Fix the rule, then read the trend.

Labor efficiency variance and labor rate variance

Standard costing compares what labor cost with what it should have cost for the units actually made, then splits the difference into an hours part and a rate part.

The direct labor variance formulas
VarianceFormulaWhat it isolates
Total direct labor variance(Actual hours x actual rate) minus (standard hours allowed x standard rate)Everything: actual labor cost against standard labor cost for the output
Labor efficiency variance(Actual hours minus standard hours allowed) x standard rateThe cost of using more or fewer hours than standard, priced at the standard rate so pay changes do not blur it
Labor rate variance(Actual rate minus standard rate) x actual hoursThe cost of paying more or less per hour than standard, on the hours actually worked
CheckEfficiency variance + rate variance = total varianceThe two parts must add back to the total

AH = actual hours, SH = standard hours allowed for actual output, AR = actual rate, SR = standard rate. Some textbooks call the efficiency variance the labor time, usage or quantity variance.

Written this way round, a positive result means cost above standard: unfavorable. A negative result is favorable. Some texts subtract in the other order so that favorable is positive. Do not rely on the sign. Label every variance with the word favorable or unfavorable, or F and U.

Standard hours allowed are always for the actual output, not the budgeted output. If you planned 4,500 units and made 4,000, the standard hours are 4,000 x the standard, and the missing 500 units are a volume question, not a labor efficiency one.

Where paid hours and worked hours differ, some systems add a third piece. The idle time variance is idle hours x standard rate, the rate variance is then worked on paid hours, and the efficiency variance on hours worked. It is the money version of splitting utilization from efficiency.

How to calculate them, step by step

From the month's output to the two variances

  1. 1

    Count the good output by product

  2. 2

    Work out earned hours

  3. 3

    Get actual hours and actual labor cost

  4. 4

    Work out the ratios

  5. 5

    Work out the two variances

  6. 6

    Split the hours by cause

Steps 1 to 3 are data. Steps 4 and 5 are arithmetic. Step 6 is the one that changes anything.
  1. 1

    Count the good output by product

    Good units completed in the period, from the production record. Leave out scrap, and count rework once.

  2. 2

    Work out earned hours

    Multiply each product's good units by its standard hours per unit and add them up. This is standard hours allowed.

  3. 3

    Get actual hours and actual labor cost

    Hours booked to those jobs, and what was paid for them including overtime premium. Actual rate = actual labor cost / actual hours.

  4. 4

    Work out the ratios

    Efficiency = earned hours / actual hours. If you also have paid hours, utilization = actual hours / paid hours.

  5. 5

    Work out the two variances

    Efficiency variance = (actual hours minus earned hours) x standard rate. Rate variance = (actual rate minus standard rate) x actual hours. Check that they add up to actual cost minus standard cost.

  6. 6

    Split the hours by cause

    Use the loss records for the period to account for the extra hours: rework, learning, stops, method. A variance with no causes attached is only a number.

Worked example: one month in a gearbox assembly department

Illustrative example. A department assembles one gearbox. The standard is 30 minutes of direct labor per unit, which is 0.50 standard hours, and the standard labor rate is $24.00 an hour, so the standard labor cost is $12.00 a unit.

Illustrative: the month's inputs for the gearbox department
InputValueWhere it comes from
Good units made4,000Production record
Standard hours per unit0.50The time standard
Standard rate$24.00 an hourThe costing standard
Actual hours worked on the job2,150Job bookings
Actual rate$24.80 an hourPayroll for those hours, including overtime premium, divided by the hours
Paid hours2,400Time and attendance
Illustrative: the gearbox department's ratios and variances for the month
StepSumResult
Earned hours4,000 x 0.502,000 hours
Labor efficiency2,000 / 2,15093.0%
Labor utilization2,150 / 2,40089.6%
Productivity against standard2,000 / 2,40083.3%
Standard labor cost2,000 x $24.00$48,000
Actual labor cost2,150 x $24.80$53,320
Total labor variance$53,320 minus $48,000$5,320 unfavorable
Labor efficiency variance(2,150 minus 2,000) x $24.00$3,600 unfavorable
Labor rate variance($24.80 minus $24.00) x 2,150$1,720 unfavorable
Check$3,600 + $1,720$5,320

Actual labor cost per unit is $53,320 / 4,000 = $13.33 against a standard of $12.00.

From standard cost to actual cost

Example numbers

Actual labor cost for the month: $53,320

$48,000
  • Standard cost for 4,000 units: $48,000
  • Total variance, unfavorable: $5,320

The $5,320 split in two

$3,600
$1,720
  • Efficiency variance: 150 hours x $24.00: $3,600
  • Rate variance: $0.80 x 2,150 hours: $1,720

Standard labor cost $48,000 plus an efficiency variance of $3,600 and a rate variance of $1,720 gives the actual cost of $53,320.

The variance is about a tenth of the labor bill. Two thirds of it is hours and one third is rate, which tells you where to start. Per unit, labor cost $13.33 against a standard of $12.00.

Read it in order. The department earned 2,000 hours and used 2,150, so 150 hours more than standard went into the same output. At the standard rate those hours cost $3,600. On top of that, every hour worked cost 80 cents more than planned, mostly overtime premium, which adds $1,720. Two different problems with two different owners.

The 250 paid hours that were not on the job do not appear in either variance here, because this plant books them to overhead. At the standard rate they are another 250 x $24.00 = $6,000. A plant that reported only the efficiency of 93% would miss the bigger loss.

How the time standard feeds every number

Every figure on this page hangs on one input: standard hours per unit. It comes from a time and motion study, or from an estimate, or from last year's average. If it is wrong, the variance measures the error in the standard and not the performance of the floor.

Illustrative: the same month measured against three different standards
Standard per unitEarned hoursEfficiencyEfficiency varianceWhat the report says
0.45 hours (10% tight)1,80083.7%$8,400 unfavorableThe department is failing
0.50 hours (as studied)2,00093.0%$3,600 unfavorableThere is a gap worth finding
0.55 hours (10% loose)2,200102.3%$1,200 favorableEverything is fine

Same 4,000 units, same 2,150 hours, same people. Only the standard changed.

One month of work, measured against three standards

Example numbers
Standard 0.45 h, 10% tight83.7%, $8,400 unfavorable
Standard 0.50 h, as studied93.0%, $3,600 unfavorable
Standard 0.55 h, 10% loose102.3%, $1,200 favorable

100%: hours used equal hours earned

Standard 0.45 h, 10% tight: efficiency 83.7%, variance $8,400 unfavorable. Standard 0.50 h, as studied: efficiency 93.0%, variance $3,600 unfavorable. Standard 0.55 h, 10% loose: efficiency 102.3%, variance $1,200 favorable

The floor did exactly the same thing in all three rows. A standard that is 10% out moves the verdict from failing to fine, so check the standard before you judge the department.
  • A standard is only valid for the method it was set on. A fixture change, a new part, a layout move or a different batch size all call for a new study.
  • Know what is inside it. A standard includes a normal pace and allowances for personal needs, fatigue and small delays. If the allowance already covers minor stops, booking them as downtime too counts them twice.
  • Standards set from history carry history's waste. Last year's average hours per unit make last year's rework and waiting look like standard performance.
  • Keep a change record: what changed, when, by how much. Then a jump in efficiency can be traced to the floor or to the file.
  • For new products, expect to miss the standard at first and plan for it. People get faster with repetition, and the labor losses guide covers how to keep learning apart from other losses.

This is where measurement tools earn their keep. With LeanSuite's Time and Motion Study, the standard is built from video with each element timed on a timeline, so when someone says the standard is wrong you can open the footage and look together.

What to do when the variance is bad

An unfavorable efficiency variance has four possible sources, and only one of them is people working slowly. Rule them out in this order.

  1. 1

    Check the count and the bookings

    Were all good units counted? Were hours from another job, or waiting time, booked here? A surprising variance is a data error more often than a floor problem.

  2. 2

    Check the standard

    Has the product, method, tooling or batch size changed since it was set? If so, restudy before you judge anyone.

  3. 3

    Check the conditions

    Material quality, machine stops, missing tools, new starters, a different crew size. These make trained people at normal pace take longer than standard.

  4. 4

    Watch the work

    Go and see the job, or film it, and compare with the documented method. Look for steps that have crept in and steps that are skipped.

  5. 5

    Account for the hours

    Put a number of hours against each cause until most of the gap is explained. Then act on the largest one.

Illustrative: where the gearbox department's 150 extra hours went
CauseHoursAt $24.00Action
Rework on the housing seal45$1,080Fix the seal seating fixture, the source of the leaks
Two new starters still learning40$960Planned and temporary. Track their curve and keep it out of the trend
Short stops and waiting not booked off35$840Book stops over 5 minutes to a code, then work on the top reason
Method drift at station 330$720Retrain to the standard work and audit it weekly
Total150$3,600

Where the 150 extra hours went

Example numbers
Rework on the housing seal45 h, $1,080
Two new starters still learning40 h, $960
Short stops and waiting not booked off35 h, $840
Method drift at station 330 h, $720

Rework on the housing seal: 45 hours, $1,080. Two new starters still learning: 40 hours, $960. Short stops and waiting not booked off: 35 hours, $840. Method drift at station 3: 30 hours, $720

A variance of $3,600 becomes four jobs with owners. Only the last is about how people work, and the fix there is training and an audit, not pressure.

The rate variance has its own short list: overtime premium, a higher-graded person doing lower-graded work, agency rates, or a pay rise the standard rate has not caught up with. Overtime is the one to look at with the efficiency variance. Extra hours often cause the overtime, so fixing the first can remove part of the second.

A favorable variance deserves a look too. It can mean a real improvement that should become the new standard. It can also mean a loose standard, skipped checks, or a department building units nobody ordered because making more earns more hours.

Where these measures mislead, and the people side

  • They reward output, wanted or not. A department judged on efficiency alone will run long batches and build stock. Pair the measure with schedule attainment and quality.
  • They are late. A monthly variance tells you about work done up to five weeks ago. Hour-by-hour output against target on the floor catches the same problems the same day.
  • They are averages. One bad job can hide among twenty good ones. Look at efficiency by product and by shift before drawing conclusions.
  • They say nothing about the bottleneck. An efficient hour at a step that is not the constraint ships nothing extra. See production capacity.
  • They shrink in meaning as direct labor shrinks. Where labor is a small share of cost, chasing its variance can cost more than it saves.
  • They are not a measure of a person. The standard assumes a trained operator, the stated method and normal conditions. Most of a variance comes from conditions the operator does not control.

That last point decides whether the numbers stay honest. If efficiency is used to rank or discipline individuals, people will protect themselves: bookings get adjusted, problems get hidden, and the standard gets fought at every restudy. Use the variance to find problems in the process, share it with the team that produced it, and fix causes in the open. Pay and disciplinary matters have their own rules, agreements and, in many plants, a union contract. This page does not cover those.

Tools and templates

FAQ

Questions about labor efficiency and labor variance

  1. Labor efficiency variance = (actual hours worked minus standard hours allowed for actual output) x standard rate. If a department used 2,150 hours to make output that should have taken 2,000 hours, at a standard rate of $24.00, the variance is 150 x $24.00 = $3,600 unfavorable. Fewer hours than standard gives a favorable variance.

  2. Labor efficiency = standard hours earned / actual hours worked x 100. Standard hours earned are good units made x standard hours per unit. A team that makes 4,000 units at a standard of 0.50 hours earns 2,000 hours. If it worked 2,150 hours, labor efficiency is 2,000 / 2,150 = 93.0%.

  3. The rate variance is about the price of an hour: (actual rate minus standard rate) x actual hours. The efficiency variance is about the number of hours: (actual hours minus standard hours allowed) x standard rate. Overtime premium and pay grades drive the first. Rework, learning, stops, method drift and wrong standards drive the second. Added together they equal the total labor variance.

  4. More hours were used than the standard allows for the output. Common causes are rework and scrap, new or untrained operators, poor material, machine stops and waiting booked to the job, drift from the standard method, and a standard that is out of date or was set too tight. Check the data and the standard before assuming the floor was slow.

  5. Utilization is the share of paid hours spent on direct work: direct hours / paid hours. Efficiency is how those direct hours compare with the standard: earned hours / direct hours. A team paid for 2,400 hours that works 2,150 on the job and earns 2,000 has 89.6% utilization and 93.0% efficiency. Multiplied together they give 83.3%.

  6. Earned hours are the standard hours for the good output actually produced: units made x standard hours per unit, added up across products. Accountants call them standard hours allowed. They let you compare output across products of different sizes, and dividing them by actual hours gives labor efficiency.

  7. No. It can come from a real improvement in the method. It can also come from a loose standard, skipped inspections, or building more units than the schedule needs because output earns hours. Check quality, schedule attainment and the age of the standard before treating a favorable variance as a saving.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.