Time study in electronics assembly: PCB, box build and cable harness

Short answer

In electronics assembly the machines set their own times, so the study belongs on the hand work: insertion, soldering, inspection, box build and harness. With hundreds of part numbers, time the repeating actions once, build standard data, and calculate each product's time from its counts.

An electronics plant has two kinds of work. The surface mount line is machine-paced: its times come from the placement program and the oven, and people affect it through changeovers and stops. Everything after it is hand-paced: manual insertion, hand soldering, inspection, test, box build and cable harness assembly. Most plants build too many part numbers to study each one, so the method is standard data. Time the actions that repeat across products, such as inserting a terminal or driving a screw, then calculate a product's time from how many of each it has, and check the formula against video of a real build.

Last reviewed:

What makes electronics assembly different

Walk an electronics plant from front to back and the pacing changes halfway. At the front, a surface mount line prints paste, places components and reflows the board with nobody touching it. At the back, people insert the parts the machines cannot place, solder by hand, inspect under magnification, build boards into enclosures and lay cable harnesses on a board. A time study means something different in each half.

  • The mix is high and the lots are small. A contract manufacturer may build hundreds of part numbers a year, many in lots of 20 or 50. There are never enough cycles of one product to study it the textbook way before the lot is finished.
  • The elements are tiny. Placing a component or pushing a terminal home takes a second or two, under the 0.04 minute that textbooks give as the floor for a stopwatch. Individual actions have to be timed in groups, from video frame by frame, or from a predetermined time system.
  • The time is in the counts. Two harnesses differ in how many wires, terminals and ties they have, not in what the operator does. That makes the work ideal for a formula.
  • Labor is quoted before it is built. The time estimate goes into a price weeks before the first unit exists, so the estimating method matters as much as the measuring one.
  • Quality gates are part of the job. Inspection, test and rework are real elements with real times, and how much of them a product needs depends on the workmanship class the customer specified.

What gets timed, stage by stage

An electronics plant has two kinds of work

Machine-paced

  • Surface mount line

    Placement program and oven set the seconds per board

  • Wave or selective solder

    Conveyor or program sets the pace

Method: machine data, plus a changeover study.

Hand-paced

  • Manual insertion

    Seconds per component

  • Hand soldering

    Seconds per joint

  • Inspection and test

    Handling by video, run time from the tester

  • Box build

    Seconds per screw, connector, label

  • Cable harness

    Seconds per wire, terminal, tie

  • Rework

    Share of time by sampling

Method: standard data from video or a predetermined time system.

Stage by stage, what paces the work. Surface mount and wave or selective solder are machine-paced, and their times come from the program or the log. Manual insertion, hand soldering, inspection and test, box build, cable harness and rework are hand-paced and are where standard data is built.

Take machine time as it is and never rate it. Build standard data for the hand half, where the part numbers and the labor are.
Electronics assembly stages: what paces each one and how to measure it
StagePaced byWhat to measureMethod
Surface mount lineThe slowest machine, usually placementSeconds per board from the program, changeover time, stopsMachine data. Study the changeover and the feeder loading by video.
Manual insertionHandsSeconds per component by type: axial, radial, connectorStandard data per component, from video or a predetermined system
Wave or selective solderThe conveyor or the programLoad and unload time, pallets per hourMachine data plus a short study of loading
Hand soldering and touch-upHandsSeconds per joint by joint type and accessStandard data per joint, from video
Inspection and testHands and the testerFixture load and unload, test run time, inspection per boardTester log for the run time, video for the handling
Box buildHandsSeconds per screw, per connector, per label, per cable routedStandard data, or a direct study when volume is steady
Cable harnessHands and the formboardSeconds per wire routed, terminal inserted, tie, tape wrap, testStandard data from video of a few harnesses
ReworkHandsMinutes per defect type, and how often each occursWork sampling for the share of time, a study for the common repairs

The split matters for the standard. Machine time is taken as it is and never rated. Hand time is rated and carries allowances. A board that takes 38 seconds to place and 6 seconds to load does not have a 44 second manual standard: it has 6 seconds of labor and 38 seconds in which the operator can do something else. The guide to man-machine charts shows how to draw that.

One board: 44 seconds of machine, 6 of labor

Example numbers

Machine

Operator

  • Operator loads the board6 s
  • Machine places, not rated38 s
  • Machine waits while the board is loaded6 s
  • Operator free: capacity for another machine or task

A board takes 6 seconds to load and 38 seconds to place, 44 seconds in all. The operator is needed for the 6 second load only and is free for the other 38 seconds.

The manual standard for this board is 6 seconds, not 44. The other 38 are machine time, and the operator can do something else in them.

On the surface mount line, the study with the best return is usually the changeover, because small lots mean many of them. Film one from the last good board of the old job to the first good board of the new one and split it with SMED.

The right method: study it once or build a formula

Two properties of the job decide the method: how many units of the same product you will build, and how short the repeating actions are.

Choosing a work measurement method in electronics assembly
SituationMethodWhy
One product runs for months at steady volumeDirect time study from videoEnough cycles to observe, and the standard pays back the study.
Hundreds of part numbers in small lotsStandard data and a time formulaStudy the repeating actions once and reuse them on every product.
Actions shorter than two or three secondsA predetermined time system, or video timed in groupsToo short to time one by one with a watch.
A new product is being quotedThe formula, from the bill of materials and the drawingNothing exists to observe yet.
Rework, kitting, material handling, supervisionWork samplingIrregular work spread over many people.
Machine stagesMachine dataThe program or the log already holds the time.

A predetermined motion time system suits fine bench work well, because the motions are small, repeatable and mostly reach, grasp, position and insert. Its weakness in electronics is the cost of analysis when the mix is high, which is the same problem a direct study has. Standard data solves it either way: whether the unit times come from video or from a predetermined system, you set them once per action and not once per product.

Video has one more use here. Bench work is seated and close, so a stopwatch observer has to lean over the operator's shoulder to see a connector click home. A small camera above the bench sees the hands and nothing else, and the time study from video guide covers the setup.

Building standard data, with a worked cable harness

Standard data is a table of times for the actions that repeat across your products, plus a rule for adding them up. It turns one careful study into a time for every product that uses the same actions.

  1. 1

    List the actions and what each one is counted by

    For a harness: wires routed, terminals inserted, cable ties, tape wraps, labels, one test and one fixed block of getting the kit and bagging the harness. The count is the driver.

  2. 2

    Film a few different products

    Choose three or four harnesses that differ in size, and film five to ten builds of each. Variety matters more than volume, because you are measuring the action and not the product.

  3. 3

    Time each action in groups and divide by the count

    Do not try to time one terminal. Time the run of 28 and divide. Rate the pace and average across the products to get a normal time per action.

  4. 4

    Check that the unit time holds across products

    If routing a wire takes 7 seconds on a small harness and 12 on a large one, the action has a second driver, such as wire length. Split it or add the driver.

  5. 5

    Write the formula and add allowances

    Normal time = the sum of count x unit time, plus the fixed block. Standard time = normal time x (1 + allowance).

  6. 6

    Check the formula against a product it has not seen

    Calculate the time for a harness that was not in the study, then film it and compare. Agree in advance what gap is acceptable.

The worked example

Illustrative example. A plant builds a harness with 14 wires and three connector housings. The wires arrive cut, stripped and crimped from an automatic machine, so the bench job is to route them on the formboard, insert the 28 terminals, tie and tape the bundle, label it and test it.

Illustrative: the time formula for a 14 wire harness (normal seconds)
ActionUnit timeCountTime
Route one wire on the formboard7 s1498 s
Insert one terminal and tug-test it5 s28140 s
Fit and trim one cable tie6 s1060 s
One spot wrap of tape4 s624 s
Apply one label9 s218 s
Load the tester, run the continuity test, unload35 s135 s
Get the kit, remove the harness from the board, bag it50 s150 s
Normal time425 s

Standard time = 425 x 1.12 = 476 seconds, or 7.93 minutes, with an illustrative 12 percent allowance. The unit times are examples: measure your own.

A 14 wire harness is a sum of counts

Example numbers
  • Route a wire14 x 7 s

    98 s
  • Insert and tug-test a terminal28 x 5 s

    140 s
  • Fit and trim a cable tie10 x 6 s

    60 s
  • Spot wrap of tape6 x 4 s

    24 s
  • Apply a label2 x 9 s

    18 s
  • Test: load, run, unload1 x 35 s

    35 s
  • Get the kit, bag the harness1 x 50 s

    50 s

Normal 425 s, x 1.12 allowance = 476 s standard (7.93 min)

Normal time is the sum of count times unit time: Route a wire 14 times 7 seconds is 98, Insert and tug-test a terminal 28 times 5 seconds is 140, Fit and trim a cable tie 10 times 6 seconds is 60, Spot wrap of tape 6 times 4 seconds is 24, Apply a label 2 times 9 seconds is 18, Test: load, run, unload 1 times 35 seconds is 35, Get the kit, bag the harness 1 times 50 seconds is 50. The total is 425 normal seconds, 476 seconds standard with a 12 percent allowance, 7.93 minutes. Terminal insertion is the largest line at 140 seconds.

Terminal insertion is a third of the harness (33%) and depends only on the count. Twice the terminals is not a little longer: it is 140 seconds longer.

A third of the time is terminal insertion, and it is driven purely by the count. That is the first thing the formula tells an estimator: a harness with twice the terminals is not a little longer, it is 140 seconds longer.

Checking the formula against video

The team films ten builds of this harness, which was not one of the products used to set the unit times. The average observed time is 452 seconds and the observer rates the pace at 95. Normal time from the video is 452 x 0.95 = 429.4 seconds. The formula said 425. The gap is 4.4 seconds, about 1 percent, well inside the 5 percent the team agreed beforehand, so the formula stands.

Checking the formula against video

Example numbers

Formula

425 s

Video (452 x 0.95)

429.4 s

The formula gives 425 normal seconds. Ten filmed builds average 452 seconds observed at a rating of 95, which is 429.4 normal seconds. The gap is 4.4 seconds, 1.0%, inside the agreed 5 percent.

The gap is 4.4 seconds, 1.0%. The dashed lines are the 5 percent the team agreed before filming. If it had been 15 percent, go back to the footage and find the action that ran long.

Had the gap been 15 percent, the answer would not be to adjust the total. It would be to go back to the footage and find which action ran long, because that points to a missing driver.

Small lots: the time that is not in the cycle

The standard above is the time per harness once the job is running. In a high-mix plant a large part of the labor is spent getting it running: fetching the formboard, pulling the kit, reading the drawing, building and checking the first piece. That time is paid once per lot, so its cost per unit depends on the lot size.

Illustrative: time per harness including a 25 minute lot setup, by lot size
Lot sizeSetup per unitRun time per unitTotal per unitSetup share
10150 s476 s626 s24.0%
2075 s476 s551 s13.6%
5030 s476 s506 s5.9%
10015 s476 s491 s3.1%

Setup per unit = 1,500 seconds / lot size. A lot of 10 costs 27.5 percent more labor per harness than a lot of 100.

Setup spread over the lot

Example numbers

Lot 10

626 s

Lot 20

551 s

Lot 50

506 s

Lot 100

491 s

  • Run time per harness476 s
  • Lot setup per harness (1,500 s / lot)150, 75, 30, 15 s

Labor per harness is 476 seconds of run time plus a 25 minute lot setup divided by the lot. A lot of 10: 150 seconds of setup, 24.0% of the total 626. A lot of 20: 75 seconds of setup, 13.6% of the total 551. A lot of 50: 30 seconds of setup, 5.9% of the total 506. A lot of 100: 15 seconds of setup, 3.1% of the total 491.

A lot of 10 costs 27.5 percent more labor per harness than a lot of 100. Quote setup per lot and run time per unit as separate lines.

Two points for the estimator. Quote setup and run time as separate lines, so a change in lot size changes the price correctly. And study the setup itself: it is a changeover, and the same SMED questions apply to a formboard and a kit as to a press.

Small lots have a second cost, which is learning. The first units of an unfamiliar product take longer than the standard, and a lot of 10 may end before the operator reaches it. The size of that effect varies by product and by person, so measure it on your own first lots before building it into a quote.

Where the workmanship standards touch the times

Electronics assembly is built and inspected to published workmanship standards, and they change the work content.

  • IPC-A-610 sets the acceptance criteria for electronic assemblies: what a finished board has to look like.
  • J-STD-001 sets the requirements for soldered electrical and electronic assemblies: the materials and the process.
  • IPC/WHMA-A-620 does the same for cable and wire harness assemblies, covering crimped, mechanically secured and soldered connections.
  • All three use three product classes. Class 1 is general electronic products, class 2 is products where continued service matters, and class 3 is high-reliability products where failure cannot be tolerated. The criteria tighten as the class rises.

The class is a time study input, because it changes how much inspection, how much touch-up and how much documentation a unit carries. Two rules follow. Record the class on the study, since a time set on class 2 work does not transfer to class 3. And never shorten an inspection or test element to hit a time without quality agreeing: those elements exist because the customer's drawing calls for them.

Static control adds elements too. Checking a wrist strap, handling boards by the edges and using shielded bags and trays all take seconds that belong in the standard. This is orientation, not a statement of what any standard requires of your product: read the current revision and the customer's drawing.

Ergonomics of fine, seated work

Electronics work is light, and it still injures people. The loads are small forces repeated thousands of times and postures held still for hours.

  • Neck and upper back: a head held forward over a microscope, a magnifier or a low board.
  • Fingers and thumb: pushing terminals into housings and pressing connectors home. On the example harness that is 28 pushes per unit, and about 1,600 in a 450 minute shift at the standard rate of 56 or 57 harnesses.
  • Wrist and forearm: cutters, crimp tools and screwdrivers used with a bent wrist. Harness taping adds a twisting motion.
  • Shoulders: reaching across a wide formboard, often with the arm raised and unsupported.
  • Eyes: fine inspection under poor or glaring light.

The fixes are usually cheap: a tilted, height-adjustable formboard, insertion tools for stiff terminals, a power driver on a balancer, an eyepiece-free microscope and job rotation across different hand motions. Score the job from the same video used for the time study. The guides to ergonomic assessment in manufacturing and workstation design cover the methods and the reach zones. This is general practice and not medical advice.

Balancing a line of benches

Where volume justifies a line, such as box build for one product family, the standard data feeds the balance directly. Work out takt time from the order, list the elements with their formula times, and assign them to benches so that each bench sits under takt. Because every time came from a count, rebalancing for the next product is arithmetic and not a new study. The method is in line balancing, and the picture of the result is a yamazumi chart.

Balance around the testers. A functional test has a fixed run time that no operator can shorten, so it is often the true bottleneck of a box build line. Put the handling for it on a person who has other work to do while it runs.

The people side

  • Explain that the study measures actions and not people. Unit times come from several operators and several products, so no one person sets the standard.
  • Film hands and the work surface only, and say so. Bench cameras make that easy.
  • Involve the experienced assemblers in splitting the job. They know which connector is hard to seat and why, and that is your missing driver.
  • Do not turn a quoting formula into a personal target overnight. A time built for estimating has not been tested as a daily standard until it has been checked against a run.
  • Follow any agreement that covers work measurement or filming.

Mistakes specific to electronics assembly

Electronics assembly time study mistakes and what to do in their place
MistakeWhat goes wrongDo this
Studying each product from scratchThe study finishes after the lot does, and the next product starts again from nothing.Build standard data for the repeating actions and calculate products from counts.
Timing single short actions with a stopwatchReaction time is as large as the action, so the times are noise.Time a run of the action and divide by the count, or use video or a predetermined system.
Adding machine time into the labor standardA board looks like 44 seconds of labor when 38 of them are the machine's.Keep machine time and hand time in separate columns.
Leaving setup out of the unit timeQuotes for small lots lose money on every order.Quote setup per lot and run time per unit as separate lines.
Ignoring the workmanship classA class 2 time is used to quote class 3 work with more inspection.Record the class on every study and keep separate inspection data per class.
Treating rework as zeroThe standard assumes every unit passes test the first time.Measure the rework share by sampling and show it as its own line, so it can be reduced.
Trusting the formula without a checkA missing driver, such as wire length, hides until a large product is quoted.Test the formula against video of a product that was not in the study.

Templates, tools and related guides

LeanSuite's time and motion study times the elements of a bench job from a phone video, which is a quick way to collect the footage for a set of unit times, and AI video analysis covers the related studies such as changeovers. The ergonomic study scores postures from video. For how plants in the sector use the platform, see LeanSuite for electronics and PCB assembly.

FAQ

Questions about time study in electronics assembly

  1. Use standard data. List the actions the product needs, such as components inserted, joints soldered, wires routed, terminals inserted and ties fitted. Multiply each count by a unit time measured in your own plant, add a fixed block for getting and bagging the unit, and add allowances. Add setup time per lot as a separate line, then check the result against video of a real build.

  2. Standard data is a table of normal times for actions that repeat across many jobs, each tied to a driver such as a count or a length. A job's time is calculated by adding the unit times for the actions it contains. It lets a plant with hundreds of products set a consistent time for each one, and quote new products, without studying every job.

  3. The machine cycle does not need a time study, because the placement program and the line log already give seconds per board. What does need a study is the human work around the line: changeovers, feeder loading, paste and stencil handling, first board checks and the response to stops. In high-mix plants the changeover is usually the study with the largest return.

  4. Three reasons. Individual actions are often shorter than the two or three seconds an observer can time reliably with a watch. Lots are small, so there are few cycles of any one product to observe. And the work is seated and close, so the observer cannot see the hands without leaning over the operator. Video and standard data deal with all three.

  5. Setup time is paid once per lot, so its share per unit rises as the lot shrinks. With 25 minutes of setup and a run time of 476 seconds, a lot of 100 costs 491 seconds per unit and a lot of 10 costs 626 seconds, which is 27.5 percent more. Quote setup and run time separately so the price follows the lot size.

  6. Yes. IPC-A-610, J-STD-001 and IPC/WHMA-A-620 each define three product classes, and the acceptance criteria tighten from class 1 to class 3. A higher class usually means more inspection, more touch-up and more records per unit. Record the class on every time study and do not reuse a time set on one class to quote another.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.