Cycle counters and PLC timers can give you the machine's part of a time standard, and for a machine-paced job they are often enough. They show how long the work took, not how long it should take. Split by product, set the stops aside, then average.

Historical and machine data are enough for the machine's part of a time standard when the machine sets the pace, one product runs at a time and stops are recorded or visible. Take the gaps between counted parts, split them by product, set aside the gaps that are stops, and use the average of what is left as the cycle. Keep the stops as their own line. The data cannot tell you the operator's work, pace or allowances, so time that part of the job. In the example on this page the raw mean of 391 gaps was 69.05 seconds, 32% above the real 52.2 second cycle.

Last reviewed:

What historical and machine data can and cannot tell you

One shift of counter data: 391 gaps, four kinds of time

Example numbers
50 to 59 sProduct A running50 to 59 s: 300 gaps
60 to 69 s60 to 69 s: 0 gaps
70 to 79 sProduct B running70 to 79 s: 60 gaps
80 to 99 sShort stops80 to 99 s: 10 gaps
100 to 119 s100 to 119 s: 5 gaps
120 to 139 s120 to 139 s: 5 gaps
140 to 159 s140 to 159 s: 5 gaps
300 s and overStarved, blocked, changeover300 s and over: 6 gaps

Bar length uses a square root scale so the small groups stay visible. The counts are exact.

69.05 s

Mean of all 391 gaps (27,000 s / 391)

52.2 s

Product A cycle, 300 clean gaps

71.0 s

Product B cycle, 60 clean gaps

A cycle counter recorded 391 gaps between parts in one 450 minute shift. 300 are product A running at about 52 seconds, 60 are product B at about 71 seconds, 25 are short stops of 88 to 150 seconds, and 6 are gaps of 300 seconds or more. The mean of all gaps is 69.05 seconds, which matches neither product.

The raw mean (69.05 s) falls in the empty space between the two products. It describes no cycle that ever happened. Clean first, then average.

Historical data is any record of how long past work took: an ERP routing time, hours booked to a job, timestamps from an MES, a cycle counter on a machine, a PLC timer, a downtime log. Machine data is the part that comes straight from the equipment, with no one writing it down. It is cheap, it covers every shift including nights, and a month of it holds thousands of cycles where a stopwatch study holds twenty.

The catch is in what it records. A standard time is the time a job should take: in the ILO's method, the observed time is adjusted to standard pace with a rating, and allowances are added. Data records how long the work did take, with the stops, the slow shift and the bad batch included. Nobody rated it. That is why raw history makes a poor standard, and why cleaned history can make a good one for the part of the job a machine controls.

A machine has no pace to rate. If the automatic cycle takes 38 seconds, it takes 38 seconds whether the operator is brisk or slow, so the rating question does not arise for machine time. It still arises for everything a person does, and that is where the line falls: machine data for the machine, a study for the person. The rest of this page is how to do the first well and how to join the two.

What each source holds

Before you trust a number, know which kind of source it came from. They answer different questions, and the same word, cycle time, means something different in each.

The usual sources of time data and where each one misleads
SourceWhat it holdsGood forMisleads when
ERP routing or standard timeThe time someone set, usually in minutes per piece, often years agoA starting point, and what the system currently believesNobody updated it after a method, tool or product change. It is a plan, not a measurement, and may hide allowances nobody can name.
Booked labor hoursHours charged to an order or a job ticketWhole-job totals over many ordersHours are booked to fit the routing, and a person's day is split across jobs by estimate.
Cycle counter or MES countsA timestamp each time a part is countedThe gap between parts, rate by product, stops visible as long gapsIt counts parts, not good parts. It cannot say why a gap was long, and where it sits on the line changes what the gap means.
PLC cycle timerThe exact time of the automatic cycle, sometimes of each machine stateThe machine's own run time to a tenth of a secondIt leaves out loading, unloading and waiting for the operator. The PLC may say 38 s while parts leave every 52.
Downtime log or reason codesStart, end and cause of stops that people enteredWhy a long gap was longShort stops are rarely entered, and the categories are the ones the person typing chose.
A time studyOperator elements timed over several cycles, rated, with allowancesThe operator's work, the method and the allowancesIt costs observer time and covers only the cycles watched.

Use these to cross-check each other. When the ERP says 45 seconds and the counter says 52.2, one of them is wrong, and finding out which is worth the afternoon.

When the data is enough, and when to time the job

Data is enough more often than people think for machine time, and less often than IT systems claim for people time. Four conditions decide it.

  • The machine sets the pace. A press, a molding machine, a CNC cycle, a filler or a packaging machine running its own cycle.
  • One product runs at a time, or every count can be tied to a product or part number.
  • Stops are coded, or at least show up as gaps you can recognize and look up.
  • The count agrees with a short timing of the same machine. Twenty cycles with a stopwatch is enough for this check.
  • Time the job instead when a person sets the pace: manual assembly, packing by hand, picking, most maintenance. No counter records effort.
  • Time it when the product is new and there is no history, or when the method has just changed. History describes the old way.
  • Time it when the number will set pay, staffing or a quote and may be challenged. A study with ratings on record is the stronger document. If you work under a union agreement, read time study in a union plant first.
  • Use work sampling when what you need is how the day divides between activities, not how long one cycle takes.

Put the four conditions in order and you have a decision flow. The first question that fails tells you what to do next.

Is machine data enough for this job?

  1. Does the machine, not the person, set the pace of the cycle?

    If no

    Data will not give the operator's time or effort. Time and rate the job: a stopwatch study or a video study.

  2. Can every count be tied to one product or part number?

    If no

    Split by product first. One average over mixed products fits none of them.

  3. Are stops coded, or at least visible as long gaps?

    If no

    Watch one shift and write down every stop before you trust any average.

  4. Is the count within your tolerance of 20 timed cycles?

    If no

    Find out why first: clock, counter position, a speed setting, or counts of bad parts.

  5. Every answer right

    Use the cleaned cycle as machine time, add operator work from a short study, and keep stops as their own line.

Four questions in order. If a person sets the pace, time the job. If counts cannot be tied to one product, split them first. If stops are neither coded nor visible, watch a shift first. If the count disagrees with 20 timed cycles beyond a tolerance you set in advance, find out why before you use it.

The tolerance is yours to set before you look. A common choice is a few percent, written on the sheet.

How to clean machine data: a worked example

Cleaning means deciding, with written rules, which gaps are cycles and which are something else, before anyone looks at an average. The rules below are one reasonable set. The 1.25 times and the 300 second line are conventions of this page, not standards: pick your own, write them on the sheet, and apply them the same way every time.

  1. 1

    Choose whole shifts

    Take complete shifts and remove breaks, planned downtime and the time before the first part of the run. One shift is shown here. For a real standard, use ten or more and compare them.

  2. 2

    Split by product

    Sort the counts by part number before you do anything else. A machine that makes two products has two cycles.

  3. 3

    Compute the gap between counts

    Subtract each timestamp from the next. Check that the stamps are in seconds. A clock that stamps whole minutes cannot show a 52 second cycle.

  4. 4

    Write the rule for what is a cycle

    Here: a gap more than 1.25 times the product's median gap is not a cycle. Of those, a gap under 300 seconds is a short stop, and a gap of 300 seconds or more is looked up in the log: starved, blocked, changeover or breakdown.

  5. 5

    Average what is left, by product

    Report the median and the mean. If they differ by more than a percent or two, look at the gaps again before you choose one.

  6. 6

    Keep the stops, as their own line

    Add up the stop time and divide by the good parts. Do not fold it into the cycle. It is a loss to be reduced, not a property of the machine.

  7. 7

    Check against a short timing

    Time twenty cycles of the machine at the floor. If it disagrees with the cleaned figure by more than the tolerance you set, find out why.

Worked example: one machine, one shift

Illustrative numbers. A machine makes two products. The cycle counter stamped 391 parts over one 450 minute shift, 27,000 seconds. The counter gaps sort into five groups.

Illustrative: what the counter recorded in one 450 minute shift
GroupGapsGap valuesTotal secondsMean gap
Product A running30051 to 54 s15,66052.2 s
Product B running6070 to 72 s4,26071.0 s
Short stops, all on product A2588 to 150 s2,865114.6 s
Starved or blocked, from the log5360 to 780 s2,700540 s
Changeover A to B11,515 s1,5151,515 s
All gaps39127,00069.05 s

Product A runs 76.7% of the counted gaps. That is why the raw median, 52 s, looks right and the raw mean does not.

Take the mean of all 391 gaps and you get 69.05 seconds, which is 32% above product A's real cycle and below product B's. Set aside the six long gaps and it is 22,785 / 385 = 59.18 seconds. Set aside the 25 short-stop gaps and it is 19,920 / 360 = 55.33 seconds. Still wrong, because the two products are mixed. Split them and the answers are 52.2 seconds for A and 71.0 seconds for B.

Cleaning the gaps, one rule at a time

Example numbers
  1. 1. All 391 gaps

    69.05 s

    27,000 s over 391 gaps

  2. 2. Set aside 6 gaps of 300 s or more

    59.18 s

    Removes 4,215 s: 5 starved or blocked, 1 changeover

  3. 3. Set aside 25 short-stop gaps

    55.33 s

    Removes 2,865 s, 10.6% of the shift. Both products still mixed

  4. 4a. Product A only

    52.20 s

    300 gaps, 15,660 s

  5. 4b. Product B only

    71.00 s

    60 gaps, 4,260 s

The mean gap falls from 69.05 seconds on all gaps, to 59.18 after removing gaps of 300 seconds or more, to 55.33 after removing short stops, then splits into 52.2 seconds for product A and 71.0 for product B.

Each step has a written rule. The last step is the one that matters: the right cycle depends on the product.

Now the stops. The 25 short-stop gaps hold 25 x 52 = 1,300 seconds of cycle and 1,565 seconds of stopped machine, 62.6 seconds a stop. Spread over the 300 A parts that is 5.22 seconds a part, 10.0% on top of the cycle. It belongs in the loss analysis, next to the 45 minutes starved or blocked and the 25 minute changeover. It does not belong in the cycle. Suppose the ERP routing for A says 45 seconds. That is 16% under the demonstrated 52.2, and without the counter nobody would have known.

Where the 450 minutes went

Example numbers
  • Product A cycles
    261.0 min, 58.0%
  • Product B cycles
    71.0 min, 15.8%
  • Short-stop gaps
    47.75 min, 10.6%
  • Starved or blocked
    45.0 min, 10.0%
  • Changeover A to B
    25.25 min, 5.6%

Inside the short-stop gaps: 21.67 min of cycles (25 x 52 s) and 26.08 min of stops (1,565 s).

Of 450 minutes: product A cycles 261.0, product B cycles 71.0, short-stop gaps 47.75 (of which 21.67 are the cycles inside them and 26.08 the stops), starved or blocked 45.0, changeover 25.25.

Only the first two bars, and the 21.7 minutes of cycles inside the short-stop gaps, are cycle time. The rest is loss: it goes on the loss and OEE sheets, not into the cycle.

Where machine data misleads

Most bad time standards from machine data come from one of the problems below. Each one leaves a signature in the gaps, and that is how you spot it.

Problems in machine data, how each one looks, and what to do
ProblemWhat it looks likeWhat to do
Starved: nothing arriving to work onA long gap with the machine ready and no part waitingNot the machine's cycle. Record it as a supply loss and look at the feed.
Blocked: nowhere to put the partA long gap with a finished part waitingNot the machine's cycle. Look at the next process and the buffer.
Short stopsGaps well over the cycle (88 to 150 s here), seldom coded, 10% of the cycle in totalCount them as their own line. Micro-stops are often the biggest hidden loss.
Mixed productsTwo or more humps in the gaps, and a mean that sits between themSplit by part number. If there is no part number, split by schedule.
Counter in the wrong placeGaps follow a downstream buffer or a pack-off, not the machineCount at the machine, or use the PLC cycle timer.
Run below design speedTight gaps, all long, no stopsCompare with the machine's design cycle. If the plant has set an ideal cycle time for OEE, check it too.
Bad parts countedThe count is high against good outputUse the good-part count, or subtract scrap and rework.
Clock resolutionGaps in whole minutes, or repeated stampsFix the stamp to seconds before using any of it.
Operator-dependent cycleGap includes the machine waiting for the loadNot machine time. Use the PLC auto time and time the operator separately.

In OEE the ideal cycle time is the most common source of error. Performance over 100% usually means it is set too high, not that the machine got faster (oee.com).

Two points on averages. The median resists a few long gaps, which is why it is the usual first choice, but it hides a second product: in this example it reads 52 seconds with B's 60 gaps in the data. And the mean is only meaningful after cleaning. Quote both, and say what you removed.

Combining the data with a short study

The two sources split the work neatly. The counter or PLC gives the machine's cycle and the stops. A short study gives what the operator does, with a rating and allowances: how to conduct a time study covers it, time study from video is the lighter route, and how many cycles to time sets the number. The same twenty timed cycles of the machine double as the check on the counter.

Put side by side, the two give a machine-tending answer a counter alone cannot. Product A has a 52.2 second machine cycle. The study finds 25 seconds of operator work a part: load 9, unload 6, gauge the bore 8, walk 2. Divide 52.2 by 25 and you get 2.09, so one operator can tend two machines on paper, using 50 of every 52.2 seconds. That is 96% of the operator before a single stop, and each short stop pulls the operator away, so the second machine will wait now and then. Man-machine charts draw this properly, and production capacity calculation turns it into units per shift.

Machine time from the counter, operator time from a short study

Example numbers

From the counter

Machine, product A

Clean cycle, 300 gaps52.2 s
Short stops per part5.22 s
Stops as share of cycle10.0%

From the study

Operator, per part

Load the machine9 s
Unload6 s
Gauge the bore8 s
Walk between machines2 s
Operator work25 s

52.2 s / 25 s = 2.09: two machines per operator, on paper

Two machines use 50 of every 52.2 s, 96% of the operator. A short stop on either machine pulls the operator in, so expect the second machine to wait now and then.

Check: 20 timed cycles averaged 52.25 s against 52.20 s from the counter, 0.1% apart.

The counter gives product A a clean machine cycle of 52.2 seconds and stops of 5.22 seconds per part. A short study gives the operator 25 seconds per part: load 9, unload 6, gauge 8, walk 2. 52.2 divided by 25 is 2.09, so two machines per operator on paper, using 50 of 52.2 seconds, which is 96% of the operator before any stop. Twenty timed cycles averaged 52.25 seconds, within 0.1% of the counter.

Each source does what it is good at. The same 20 timed cycles also check the counter.

Use the stop line on its own. At 5.22 seconds a part it is the figure the loss work needs, and the one to reduce. See labor losses in manufacturing and how to calculate OEE for where it goes. For a part with no history at all, how to estimate cycle time for a new product is the route, not data.

The people side

Machine data feels neutral, and that is exactly when it gets used badly. Operators know when a counter is watching, and if the cleaned cycle turns into a personal quota, the next set of data will be worse. General practice, not legal advice.

  • Tell the team what you are pulling and why before you pull it. Show the cleaned cycle and the stop list to the people who run the machine first. They usually know the cause of the long gaps.
  • Use the cleaned cycle as a figure for the machine, not as a rate for a person. A machine cycle is not a measure of effort.
  • Do not charge a stop to the operator. Starved, blocked and short stops are mostly process problems.
  • Keep the written cleaning rules next to the number. If someone challenges the standard, you can show exactly what was set aside and why.

Common mistakes

  • Averaging all the gaps. The mean of a mixed, stopped machine is a number that never happened.
  • Folding the stops into the cycle. It hides the biggest chance to improve and overstates the machine.
  • Using the ERP routing as the truth. It is what someone set, not what was measured.
  • Using the PLC time for the whole cycle. It leaves out the operator's load and unload.
  • Cleaning without writing the rules down. The next person cannot repeat it, and you cannot defend it.
  • Skipping the check against a timed cycle. Twenty cycles is half an hour and catches a wrong counter.
  • Using history for a changed method or a new product. The data describes the old way.

Where software helps

Your MES and counters already supply the machine side. For the operator side, LeanSuite's Time and Motion Study drafts element times from a video of the station on a timeline that links back to the footage, and you check and certify them. The time study sheet is a free template if you would rather time it by hand, and the process capacity sheet holds the machine and operator times together.

Doing this in LeanSuite

See it on your own lines

Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.

FAQ

Questions about historical and machine data as time standards

  1. Partly. Historical data records how long work took, with stops and slow shifts included, not how long it should take. For a machine-paced job, cleaned counter or PLC data can set the machine's cycle well. It cannot set the operator's work, which needs timing, a rating and allowances. Split by product, set stops aside and check against a short timing.

  2. You need a timestamp for every counted part, in seconds, and a part number for each count. Take the gap between consecutive counts, set aside the gaps that are stops or waits, and average the rest by product. A stop log or reason codes help explain the long gaps. A stopwatch check of twenty cycles confirms the counter.

  3. Use whole shifts, split by product and compute the gap between counts. Then apply a written rule for what is not a cycle, such as a gap over 1.25 times the product's median. Gaps under a set limit are short stops, longer ones are looked up in the log. Average the rest and report the stops as a separate line.

  4. Ideal cycle time is the fastest a machine runs steadily when nothing goes wrong, used in OEE to judge performance. Actual cycle time is what the counter shows, including slow running and short stops. Performance equals ideal cycle time times total count divided by run time. If it exceeds 100%, the ideal is usually set too high.

  5. Because the average usually mixes things that are not cycles: stops, waits for supply, changeovers and several products at different speeds. In the example on this page the mean of 391 gaps was 69.05 seconds while the real cycle was 52.2. Clean the gaps first, split by product, then average.

  6. No. A micro-stop is a brief pause where the machine is not producing, so it belongs in the loss analysis and not in the cycle. Sources set the limit differently, from under one minute to under five, so choose a threshold, write it down and report the stops as their own line.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.