Practical guide · Safety management
Management of change (MOC): the process, PSSR and a worked example
Short answer
Management of change, MOC, is a written process that makes sure a change to equipment, materials, methods, layout or people is assessed for safety and approved before it is made, and that documents and training are updated before the changed work starts. A pre-startup safety review is its last check.
MOC stands for management of change. Before anything is changed, someone writes down what will change and why, a team that includes the people who do the work assesses what the change could do to safety and health, the actions needed are listed, and a named person approves. After the change is made and before it runs, procedures, risk assessments and standard work are updated, the people affected are trained, and a pre-startup safety review (PSSR) confirms the change was built as approved. A like-for-like replacement to the same specification is not a change. Temporary and emergency changes are, and they need an end date. A new method from a time study, a line rebalance or a new layout is a change too: the job safety analysis, the ergonomic score and the standard work must be redone before it runs. This is general guidance. The rules that apply to your site may ask for more.
Last reviewed:
What is management of change in safety?
Every control in a plant was designed for the plant as it was on some particular day. The guard fits that machine. The procedure describes that sequence. The risk assessment scored that layout. Change the machine, the sequence or the layout and the controls can stop matching the work without anyone noticing. Management of change, MOC for short, is the routine that closes that gap: no change goes in until someone has asked what it does to safety, and no changed process starts until the paperwork and the people have caught up.
The idea was learned the hard way. On 1 June 1974 a chemical plant at Flixborough in England exploded, killing 28 people on the site. A leaking reactor had been taken out of a series of reactors, and a temporary bypass pipe was fitted across the gap to keep production going. The UK Health and Safety Executive's summary of the case puts it in one sentence: "A plant modification occurred without a full assessment of the potential consequences." No drawing of the bypass was made, only limited calculations were done, and the installed pipework was not pressure tested.
Most changes in a factory are far smaller than that, and the lesson is the same size at every scale. The people who make a change are thinking about the problem it solves. MOC makes somebody think, for a few minutes or a few days, about the problems it could cause.
A note on the name. In safety, management of change is about changes to plant, process and work. It is a different thing from change management in the organisational sense, which is about bringing people along with a new way of working, and different again from an engineering change request, which controls changes to a product's design. A good MOC does borrow from both.
What counts as a change?
The hardest part of MOC is not the form. It is noticing that something is a change at all. A useful test: if the answer to "is it exactly what was there before, to the same specification?" is no, treat it as a change until a screening says otherwise.
Screening: is it a change, and which route
Ask whether the replacement is exactly what was there to the same specification. If yes, log it as maintenance. If no, it is a change: permanent changes take the full process, temporary ones carry an end date, emergency ones get duty manager approval and a full review the next working day.
| What changes | Examples | Why it matters for safety |
|---|---|---|
| Equipment and tooling | A new machine, a different guard switch, a lift table, a faster drive, a modified fixture | New pinch points and energy sources; guards and interlocks designed for the old set-up |
| Materials and chemicals | A new coolant, adhesive or cleaning agent; a heavier part; a different supplier's grade | New exposure, fire or reaction hazards; handling loads that no longer match the lift aids |
| Method and sequence | An element removed, combined or re-ordered after a time study; a new work instruction | Hands in new places; a control skipped because its step is gone |
| Layout | A moved machine, a new aisle, a relocated pallet position, a blocked exit route | Traffic, reach, lighting, escape routes and emergency equipment |
| Operating limits and software | Line speed, pressure, temperature or cycle settings outside the approved range; edited PLC or robot programs | Safeguards and alarms set for the old limits; safety logic changed by accident |
| People and organisation | One operator now runs two machines; a shift pattern change; work moved to contractors; fewer trained setters | Workload, fatigue, supervision and competence |
| Procedures and safety systems | A revised lockout procedure, a changed inspection interval, an alarm switched off | The control itself is what changed |
Your own list should be written into the MOC procedure, with examples from your plant. People recognise examples faster than definitions.
Replacement in kind: the one thing that is not a change
OSHA's process safety rule exempts "replacements in kind" from its MOC paragraph and defines the term: "Replacement in kind means a replacement which satisfies the design specification." A worn bearing swapped for the same bearing is a replacement in kind. So is a hose replaced with the same type, rating and length. The same valve from a different maker, a seal in a different material or a guard switch of a different type is not, even when the catalogue calls it equivalent. If someone had to decide it was near enough, it is a change.
Temporary changes
A temporary change is still a change. The Flixborough bypass was temporary. Bypassed interlocks, jumpers, rented equipment, a trial of a new method for one week, a clamp on a leaking pipe: each goes through MOC with one extra field, the date it ends. On that date the change is removed and the original condition checked, or it is extended by the same person who approved it, or it goes through MOC again as a permanent change. A temporary change with no end date becomes how the plant runs.
Emergency changes
Sometimes a change cannot wait for a meeting, at two in the morning with a line down. A workable convention, which you should write into your own procedure, is a short form: the duty manager approves by name, a minimum risk review is done at the job with whoever is there, the change is logged, and the full MOC review happens on the next working day. The emergency route exists to keep an urgent repair inside the system. It must not turn into the usual way of avoiding the paperwork, so count how often it is used.
What OSHA and ISO 45001 say about MOC
Two documents are behind most MOC procedures. This is a plain summary to help you find your way. Read the sources themselves for the requirements, and check which rules apply where you operate, because they differ by country and by industry.
| Source | Who it applies to | What it asks for |
|---|---|---|
| 29 CFR 1910.119(l), management of change | United States employers with a process covered by OSHA's standard on process safety management of highly hazardous chemicals: broadly, a process holding a listed chemical at or above its threshold quantity, or 10,000 pounds or more of certain flammable gases and liquids, with exceptions | Written procedures to manage changes, except replacements in kind, to process chemicals, technology, equipment and procedures, and changes to facilities that affect a covered process. Before any change the procedure must address: the technical basis, the impact on safety and health, modifications to operating procedures, the necessary time period for the change, and the authorization requirements. Affected employees and contract employees are informed and trained before start-up, and process safety information and operating procedures are updated |
| 29 CFR 1910.119(i), pre-startup safety review | The same covered processes: new facilities, and modified facilities when the modification is significant enough to require a change in the process safety information | Before highly hazardous chemicals are introduced, confirm that construction and equipment match the design specifications; that safety, operating, maintenance and emergency procedures are in place and adequate; that a process hazard analysis has been done for a new facility and its recommendations resolved, and that a modified facility has been through management of change; and that training of each employee involved in operating the process is complete |
| ISO 45001:2018 clause 8.1.3, management of change | Any organisation that has chosen to work to the standard, in any industry | A process to implement and control planned changes, temporary and permanent, that affect health and safety performance: new or changed products, services and processes (including locations, work organisation, working conditions, equipment and workforce), changes to legal and other requirements, changes in knowledge about hazards and risks, and developments in knowledge and technology. Review the consequences of unintended changes and act to reduce any adverse effects |
A paraphrase, not the legal text. The OSHA paragraphs apply to covered processes only. A machining cell, an assembly line or a trim press is not a covered process, so MOC there is good practice, a customer or corporate requirement, or part of an ISO 45001 system.
So for most discrete manufacturing no regulation names an MOC form. The reason to have one is practical: other duties, such as keeping risk assessments current and training people on the hazards of their work, are hard to meet if changes slip through unassessed. The OSHA paragraph is still the best short checklist there is. Its five considerations (technical basis, safety and health impact, procedures, time period, authorization) fit a change to a packing bench as well as a change to a reactor.
The MOC process, step by step
Ten steps, and three places where the work stops until someone signs. Scale the effort to the change: a moved pallet position might take one page and twenty minutes, a new machine several meetings. What must not scale down is the order.
Ten steps, three stop points
Before the change
- Raise the request
- Screen it
- Write the technical basis
- Assess safety and health
- List and sort the actions
- Approve
Stop 1: no approval, no work starts
Make it and catch up
- Make the change
- Update documents, train people
Prove it
- Pre-startup safety review
- Start up, watch, close out
Stops 2 and 3: no sign-off, no start-up; the MOC stays open until the actions are closed
Steps 1 to 6 happen before the change and end at the approval stop. Steps 7 and 8 make the change and update documents and training. Steps 9 and 10 are the pre-startup safety review and close-out, which carry the second and third stops.
- 1
Raise the change request
Before anything is bought, built or moved. Say what will change, where, why, who is asking, and whether it is permanent, temporary (with an end date) or an emergency.
- 2
Screen it: change or replacement in kind?
A like-for-like replacement to the same specification is logged as maintenance and goes no further. Anything else carries on. When in doubt, it is a change.
- 3
Write down the technical basis
What the change is meant to achieve and how it works: drawings, specifications, the supplier's manual, the study that led to it. If the change came from a time study, attach the before sheet and the proposed method.
- 4
Assess the effect on safety and health
With the people who run, maintain and clean the equipment. Walk the change through every task: normal running, loading and unloading, jams, cleaning, setup, maintenance and emergencies. Redo the job safety analysis for the new method and look for hazards the change adds as well as the ones it removes.
- 5
List the actions and sort them
Guards, isolation points, procedures, training, signs, inspections. Mark each one as required before start-up or allowed after it, with an owner and a date.
- 6
Approve
The named approver signs that the assessment is complete and the actions are right. Stop point one: no approval, no work starts.
- 7
Make the change
Under the normal controls for the work itself: lockout, permits and contractor rules. Build what was approved. If the design has to change on the day, go back to step 4.
- 8
Update the documents and train the people
Standard work, work instructions, the lockout procedure, the maintenance plan, drawings, the risk register. Train every shift and every contractor whose task is affected, before they meet the change.
- 9
Hold the pre-startup safety review
Walk the finished change with the checklist: built as approved, before-start-up actions closed, safeguards tested, documents updated, people trained. Stop point two: no sign-off, no start-up.
- 10
Start up, watch, and close out
Watch the first runs with the operator. Finish the after-start-up actions. For a temporary change, remove it or renew it on its end date. Stop point three: the MOC stays open until every action is closed and the documents match the floor.
Who approves?
The person who wants the change should not be the only one who approves it. Beyond that, match the level of approval to the size of the risk. The table is a starting convention, not a rule from any standard. Set your own and write it into the procedure.
| Kind of change | Reviewed by | Approved by |
|---|---|---|
| Replacement in kind | The maintenance planner confirms the specification | No MOC. Logged in the maintenance record |
| Minor change with no new hazard found at screening, such as a relabelled rack or a moved workbench | Area supervisor and safety lead | Area manager |
| Change to equipment, guarding, energy sources, chemicals, layout, staffing or method | Engineering, maintenance, safety and an operator from the area | Department manager |
| Change that alters a safety system, or carries a severe potential consequence | The same team plus a specialist: machinery safety, electrical, process or occupational health | Plant manager |
| Temporary change | As for its kind, with an end date | As for its kind. Extension only by the same approver |
| Emergency change | Whoever is competent and on site, at the job | Duty manager by name. Full review on the next working day |
PSSR: the pre-startup safety review
PSSR stands for pre-startup safety review. It is the last check between a finished change and a running process, done at the equipment and not in a meeting room. The term comes from OSHA's process safety rule, where it applies to covered chemical processes. The habit is worth having anywhere, because the commonest MOC failure is a good assessment followed by a change that was not built as assessed.
The OSHA paragraph asks the review to confirm four things, and they translate directly to any plant.
| Confirm that | On the floor, check |
|---|---|
| It was built to the design | The installed equipment matches the approved drawing and specification: the guard that was drawn, the nozzle that was specified, the rated load on the plate. Anything changed on the day has been back through assessment |
| Procedures are in place and adequate | Standard work, work instruction, lockout procedure with any new isolation point, maintenance plan, emergency steps. Read them at the machine and see if they describe what is there |
| The hazard review is done and its actions are closed | Every before-start-up action from the MOC is finished and seen. Safeguards have been tested, not assumed: trip the light curtain, open the interlocked door, press the emergency stop |
| People are trained | Every shift, relief operators, setters, maintenance and contractors whose task is affected, with a record. Ask one of them to show you the new method |
A PSSR is a go or no-go decision with a signature. A list of open items "to be finished next week" is a no-go, unless each was marked as allowed after start-up when the change was approved.
Keep the checklist short enough to be done properly and specific to the change. Twenty generic questions answered "N/A" teach people to tick. Eight questions written from the MOC's own action list get read.
A worked example: two changes at a trim press cell
Illustrative example. A study of a trim press cell put the time study, the job safety analysis and the REBA posture scores for one job on a single sheet. The full study is in job safety analysis from video. It found two elements that were slow, risky and awkward at once, and the team proposed two changes.
| Change | What it is meant to fix | Expected result |
|---|---|---|
| A. An air blast and a scrap chute at the trim die | The operator clears trimmed flash from the die by hand every cycle: 5 seconds of waste, risk 5 x 3 = 15, REBA 7 | The element disappears. The chute also keeps flash off the floor, so the trip risk on the walk back falls from 2 x 3 = 6 to 2 x 1 = 2 |
| B. A spring lift table with a turntable under the pallet | The operator turns, bends and stacks 9 kg housings on a pallet on the floor: 8 seconds, risk 3 x 4 = 12, REBA 10 | Stacking takes 6 seconds at waist height, risk 3 x 2 = 6, REBA 3 |
With cut-resistant gloves and sleeves at unload as well, the study expects the cycle to fall from 48 to 41 seconds, the highest risk score from 15 to 10 and the highest REBA from 10 to 5.
Both changes are improvements, and both came from a safety study. That is exactly when MOC gets skipped: who would hold up a safety fix? But each one adds equipment, energy and tasks that were not there before. Here are the questions the review team raised when they walked the two changes through every task at the cell.
| # | Change | Question | Decision | When |
|---|---|---|---|---|
| 1 | A | Compressed air is noisy. Does the blast raise the noise at the operator's ear? | Fit a low-noise nozzle and time the blast to a short pulse. Measure at the operator's position on the first run and compare with the reading before | Before start-up |
| 2 | A | Where does the blown flash go? | Aim the blast away from the operator into a hooded chute. Eye protection stays | Before start-up |
| 3 | A | Does the chute opening give a hand a way into the die from behind? | Enclose the chute so the die cannot be reached through it, and check the opening against the site's guarding standard | Before start-up |
| 4 | A | The press now has a second energy source. Is the air in the lockout procedure? | Add a lockable air isolation valve with a bleed, label it, and add the step to the press lockout procedure | Before start-up |
| 5 | A | The blast is wired into the press controls. Do the light curtain and two-hand start still work as before? | Test both safety functions after the wiring change and record the test | Before start-up |
| 6 | A | Who empties the scrap bin under the chute, and how heavy does it get? | A wheeled bin with a fill line, and a row for the task in the job safety analysis | Before start-up |
| 7 | B | The table rises and falls as the load changes. Is there a crush point under it or at its edge? | A skirt guard around the mechanism and toe clearance at the base | Before start-up |
| 8 | B | Can the table carry a full pallet? | A full pallet is 40 housings at 9 kg, 360 kg, plus a 25 kg pallet: 385 kg. Confirm the rating plate and the spring setting cover it | Before start-up |
| 9 | B | The turntable spins freely. Can it trap a foot or swing while the forklift loads it? | A rotation lock for loading, and a marked standing position for the operator | Before start-up |
| 10 | B | The forklift now places the pallet on a table instead of the floor. Does the pallet swap change? | Revise the standard work for the pallet swap with the driver and brief every driver | Before start-up |
| 11 | B | Who inspects the springs, bearings and skirt? | Add the table to the preventive maintenance plan | Within 30 days |
Eleven questions from two changes: ten actions before start-up and one after. None of them stopped the project. Three of them (4, 5 and 7) would have been new hazards running from day one.
Eleven questions from two safety fixes
Example numbersChange A: air blast and scrap chute
Change B: spring lift table with turntable
Eleven MOC questions: six for change A and five for change B. Ten are before start-up actions and one is after. Questions 4, 5 and 7 would have been new hazards from the first day.
The documents that had to change
- Job safety analysis: redone for the seven remaining elements, with a new row for emptying the scrap bin. Highest score 10, sum of scores 43, down from 15 and 72.
- Ergonomic score: stacking re-scored at REBA 3 on the lift table. The highest score on the job is now 5, at loading and unloading the die.
- Standard work and the time standard: element 5 removed, element 7 at 6 seconds, cycle 41 seconds. At 48 seconds the cell made 75 housings an hour of running time, and at 41 seconds it can make about 88, so the pallet swap now comes round sooner and the downstream process has to be able to take the parts.
- Lockout procedure for the press: the air isolation step added.
- Maintenance plan: the lift table, the nozzle and the chute guard.
- Risk register: the top line for the cell falls from 15 to 10, with the date and the MOC number.
- Training record: both shifts and the relief operators, signed before their first run on the new method.
The pre-startup safety review took half an hour at the cell. It found one thing: the air valve was fitted and labelled, but the lockout procedure posted on the press was still the old revision. Start-up waited forty minutes for a printout. That is a PSSR doing its job.
Then the team filmed the new method and filled in the same sheet again. The numbers above are predictions until that second study confirms them. A measured cycle of 43 seconds, or a posture nobody expected at the turntable, would send the team back to step 4.
A new method from a time study is a change
Industrial engineers change how work is done for a living. A time study removes an element. A line rebalance moves work from station 4 to station 5. A new layout halves the walking. Each of these is a change to the method, and method is one of the things a safety assessment was written around. The awkward truth is that most of these changes never see an MOC form, because they look like productivity work and no equipment was bought.
The fix is one rule: when the element list changes, the documents built on it are redone before the new method runs. The table shows which ones, for the changes that come out of time and motion work.
What to redo when the method changes
| Change | Job safety analysis | Ergonomic score | Standard work | Time standard | Risk register line |
|---|---|---|---|---|---|
| An element removed or automated | Redo | Redo | Redo | Redo | Redo |
| Work moved between stations in a line rebalance | Redo | Redo | Redo | Redo | Check |
| Takt time or line speed changed, same method | Check | Redo | Redo | Check | Check |
| New layout or moved equipment | Redo | Redo | Redo | Redo | Redo |
| New fixture, tool or lift aid | Redo | Redo | Redo | Redo | Check |
| New part number or heavier variant on the station | Check | Redo | Check | Redo | Check |
| One operator now runs two machines | Redo | Redo | Redo | Redo | Redo |
| Like-for-like replacement of a worn part | No | No | No | No | No |
A matrix of eight kinds of method change against five documents: job safety analysis, ergonomic score, standard work, time standard and risk register line. Each cell says redo, check or no.
- A rebalance is the easiest one to miss. The element being moved was assessed at the station it left. At the new station it sits next to different equipment, is done by a person already carrying other work, and may push a posture that was fine for 20 seconds a cycle to 35.
- A faster cycle changes likelihood. The hazard and its severity are the same, but a hand that passes a pinch point 75 times an hour now passes it about 88 times.
- A new method needs the old controls checked. If the step that included "check the clamp" was removed as waste, something else must now make sure the clamp is closed.
- The time standard waits for the safety review. Set the standard on the method that passed the MOC, not on the method the engineer first proposed.
Two tools sit either side of the MOC. Before the change, the study that proposes it. After the change, change point management: the shift-level habit of logging every change to man, machine, material and method and checking the product more closely until the change is proven. The 4M change management sheet is the log for that. It is a quality tool and it does not replace an MOC, but the two work well together: the MOC approves a planned change, and the 4M sheet records the day it went live and the extra checks that followed.
The re-study is quick if the first study was filmed. In LeanSuite you upload the film of the new method, and the time and motion study compares two studies side by side with their value-added percentages. The ergonomic study lets you re-score the job after a layout or tooling change. Both analyse uploaded files and give you drafts to review. The MOC decision, the job safety analysis and the sign-off stay with your team.
The traps
- The form arrives after the change. If the MOC is written the week after installation, it is a record, not a control. Tie the purchase order or the work order to an approved MOC number.
- "It's like for like." Most uncontrolled changes are replacements that were nearly the same. Make someone check the specification, not the description.
- Improvements get waved through. A safety fix or a kaizen is still a change, and good intentions do not guard a pinch point.
- Temporary changes with no end date. Keep a register of them and review it every week.
- The assessment only covers normal running. Ask about jams, cleaning, setup and maintenance for the changed equipment, every time.
- No operator in the review. The people who will live with the change see problems a drawing does not show.
- Start-up before training. The night shift meets the new method with nobody there to explain it.
- Documents never catch up. Six months later the work instruction, the lockout procedure and the risk register describe a cell that no longer exists.
- Emergency approval as the normal route. If a third of your changes are emergencies, the plan is the problem.
- So heavy that people avoid it. A forty-page form for a moved bin teaches everyone to stop asking. Keep a one-page version for small changes, and make the screening step fast.
- Many small changes, each harmless. Ten approved tweaks to one cell in a year can add up to a different process. Re-study the whole job now and then, not only the last change.
Templates and related guides
- 4M change management sheet: the shift log of change points and the extra checks after each.
- Job safety analysis template: for the assessment in step 4.
- Risk register template: where the changed line is recorded.
- Lockout tagout procedure template: for a new isolation point.
- Risk matrix calculator: score the hazards a change adds and the ones it removes.
- Job safety analysis from video: the study behind the worked example.
- HIRA: the register a change must update.
- ISO 45001: where clause 8.1.3 sits in the standard.
- Permit to work: the control for the installation work itself.
Go deeper
This page is the short version. These guides cover each part in full.
- 7 Preventable Shop Floor Incidents Most Plants MissIncidents that follow a change nobody assessed.
- Top Five Common Manufacturing HazardsThe hazards to ask about when a change is walked through every task.
- Building a Proactive Safety Culture in ManufacturingWhy people raise a change request early in some plants and hide the change in others.
- OSHA Audit Preparation: Reducing 40 Hours to 4 HoursKeeping the records of changes, training and reviews where an auditor can find them.
All our articles on this subject are in the safety management topic.
Free templates and tools
- 4M change management sheet (change point)A shift log of every change to Man, Machine, Material, Method or Design, the extra checks after it and when normal checks resume, with a change point board.
- Job safety analysis (JSA) templateJob steps, hazards, risk scored before and after the controls, the hierarchy of controls, PPE and sign-off.
- Risk register templateOne scored list of operational risks with owners, actions and dates, a heat map and a review log.
- Lockout/tagout (LOTO) procedure templateA machine-specific LOTO procedure: energy sources and isolation points, the steps from shutdown to restart, and the annual review.
- Risk matrix calculatorSeverity times likelihood on a 3 x 3, 4 x 4 or 5 x 5 risk matrix, the band and its action, editable banding, and the score after further controls.
Doing this in LeanSuite
Time and Motion Study
Film a station on a phone and get element times, cycle time, standard time and a Yamazumi chart.
See Time and Motion StudyErgonomic Study
Maps 18 body joints from video, scores REBA and RULA automatically and flags the postures that need a fix.
See Ergonomic StudyWorkplace Safety
Safety inspections, gemba walks and LOTO checks from ready-made templates; a failed item raises a safety tag.
See Workplace Safety
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about management of change (MOC)
MOC stands for management of change. It is the written process a site uses to make sure a change to equipment, materials, methods, layout, procedures or staffing is assessed for its effect on safety and health and approved before it is made, and that documents and training are updated before the changed work starts.
Raise a change request, screen it as a change or a replacement in kind, record the technical basis, assess the effect on safety and health with the people who do the work, list the actions, get approval, make the change, update documents and train people, hold a pre-startup safety review, then start up and close out. Work stops at approval and at the pre-startup review until someone signs.
PSSR stands for pre-startup safety review. It is the final check on a new or modified process before it runs: that it was built to the approved design, that procedures are in place, that the hazard review's actions are closed and that the people involved are trained. The term comes from OSHA's process safety management rule, 29 CFR 1910.119(i), which applies to covered chemical processes.
For processes covered by OSHA's process safety management standard, yes: 29 CFR 1910.119(l) requires written procedures to manage changes other than replacements in kind. That standard covers processes with highly hazardous chemicals above set quantities. Most discrete manufacturing is outside it, so there MOC is good practice or a requirement of a system such as ISO 45001 clause 8.1.3. Check which rules apply to your site.
A replacement that satisfies the design specification, in the words of OSHA's process safety rule. Swapping a worn part for an identical one is a replacement in kind and does not need an MOC. A part from a different maker, in a different material or of a different type is a change, even if it is sold as equivalent, and should be screened before it is fitted.
Yes. Removing, combining or re-ordering elements changes where hands go, which postures are held and which checks get done, even when no equipment is bought. Before the new method runs, redo the job safety analysis and the ergonomic score, update the standard work and train the operators. Set the new time standard on the method that passed that review.
In safety, management of change controls technical and operational changes: equipment, chemicals, methods, layout and staffing are assessed for hazards before they change. Change management, in the organisational sense, is about helping people adopt a new way of working. An MOC needs some of the second to succeed, because a change nobody was told about is a hazard however well it was assessed.
Related guides and tools
- Job safety analysis from video: the trim press study that proposed these changes
- HIRA: the risk register a change must update
- ISO 45001: clause 8.1.3 in the context of the whole standard
- Lockout tagout: isolating every energy source, new ones included
- Permit to work: controlling the installation work itself
- 4M change management sheet: logging change points shift by shift
- Line balancing: the rebalance that moves work, and its hazards, between stations
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk