Management of change (MOC): the process, PSSR and a worked example

Short answer

Management of change, MOC, is a written process that makes sure a change to equipment, materials, methods, layout or people is assessed for safety and approved before it is made, and that documents and training are updated before the changed work starts. A pre-startup safety review is its last check.

MOC stands for management of change. Before anything is changed, someone writes down what will change and why, a team that includes the people who do the work assesses what the change could do to safety and health, the actions needed are listed, and a named person approves. After the change is made and before it runs, procedures, risk assessments and standard work are updated, the people affected are trained, and a pre-startup safety review (PSSR) confirms the change was built as approved. A like-for-like replacement to the same specification is not a change. Temporary and emergency changes are, and they need an end date. A new method from a time study, a line rebalance or a new layout is a change too: the job safety analysis, the ergonomic score and the standard work must be redone before it runs. This is general guidance. The rules that apply to your site may ask for more.

Last reviewed:

What is management of change in safety?

Every control in a plant was designed for the plant as it was on some particular day. The guard fits that machine. The procedure describes that sequence. The risk assessment scored that layout. Change the machine, the sequence or the layout and the controls can stop matching the work without anyone noticing. Management of change, MOC for short, is the routine that closes that gap: no change goes in until someone has asked what it does to safety, and no changed process starts until the paperwork and the people have caught up.

The idea was learned the hard way. On 1 June 1974 a chemical plant at Flixborough in England exploded, killing 28 people on the site. A leaking reactor had been taken out of a series of reactors, and a temporary bypass pipe was fitted across the gap to keep production going. The UK Health and Safety Executive's summary of the case puts it in one sentence: "A plant modification occurred without a full assessment of the potential consequences." No drawing of the bypass was made, only limited calculations were done, and the installed pipework was not pressure tested.

Most changes in a factory are far smaller than that, and the lesson is the same size at every scale. The people who make a change are thinking about the problem it solves. MOC makes somebody think, for a few minutes or a few days, about the problems it could cause.

A note on the name. In safety, management of change is about changes to plant, process and work. It is a different thing from change management in the organisational sense, which is about bringing people along with a new way of working, and different again from an engineering change request, which controls changes to a product's design. A good MOC does borrow from both.

What counts as a change?

The hardest part of MOC is not the form. It is noticing that something is a change at all. A useful test: if the answer to "is it exactly what was there before, to the same specification?" is no, treat it as a change until a screening says otherwise.

Screening: is it a change, and which route

Is it exactly what was there, to the same design specification?
Yes
Replacement in kind. Log it in the maintenance record. No MOC.
No, or someone had to decide it was near enough
It is a change. How long will it last?
Permanent. Full MOC process, ten steps.
Temporary. Full MOC plus an end date. Remove it, or the same approver renews it.
Emergency. Duty manager approves by name, minimum risk review at the job, full review next working day.

Ask whether the replacement is exactly what was there to the same specification. If yes, log it as maintenance. If no, it is a change: permanent changes take the full process, temporary ones carry an end date, emergency ones get duty manager approval and a full review the next working day.

When in doubt it is a change. Temporary and emergency changes still go through MOC: they only differ in the end date and the speed of the first review.
Kinds of change, with examples from a manufacturing plant
What changesExamplesWhy it matters for safety
Equipment and toolingA new machine, a different guard switch, a lift table, a faster drive, a modified fixtureNew pinch points and energy sources; guards and interlocks designed for the old set-up
Materials and chemicalsA new coolant, adhesive or cleaning agent; a heavier part; a different supplier's gradeNew exposure, fire or reaction hazards; handling loads that no longer match the lift aids
Method and sequenceAn element removed, combined or re-ordered after a time study; a new work instructionHands in new places; a control skipped because its step is gone
LayoutA moved machine, a new aisle, a relocated pallet position, a blocked exit routeTraffic, reach, lighting, escape routes and emergency equipment
Operating limits and softwareLine speed, pressure, temperature or cycle settings outside the approved range; edited PLC or robot programsSafeguards and alarms set for the old limits; safety logic changed by accident
People and organisationOne operator now runs two machines; a shift pattern change; work moved to contractors; fewer trained settersWorkload, fatigue, supervision and competence
Procedures and safety systemsA revised lockout procedure, a changed inspection interval, an alarm switched offThe control itself is what changed

Your own list should be written into the MOC procedure, with examples from your plant. People recognise examples faster than definitions.

Replacement in kind: the one thing that is not a change

OSHA's process safety rule exempts "replacements in kind" from its MOC paragraph and defines the term: "Replacement in kind means a replacement which satisfies the design specification." A worn bearing swapped for the same bearing is a replacement in kind. So is a hose replaced with the same type, rating and length. The same valve from a different maker, a seal in a different material or a guard switch of a different type is not, even when the catalogue calls it equivalent. If someone had to decide it was near enough, it is a change.

Temporary changes

A temporary change is still a change. The Flixborough bypass was temporary. Bypassed interlocks, jumpers, rented equipment, a trial of a new method for one week, a clamp on a leaking pipe: each goes through MOC with one extra field, the date it ends. On that date the change is removed and the original condition checked, or it is extended by the same person who approved it, or it goes through MOC again as a permanent change. A temporary change with no end date becomes how the plant runs.

Emergency changes

Sometimes a change cannot wait for a meeting, at two in the morning with a line down. A workable convention, which you should write into your own procedure, is a short form: the duty manager approves by name, a minimum risk review is done at the job with whoever is there, the change is logged, and the full MOC review happens on the next working day. The emergency route exists to keep an urgent repair inside the system. It must not turn into the usual way of avoiding the paperwork, so count how often it is used.

What OSHA and ISO 45001 say about MOC

Two documents are behind most MOC procedures. This is a plain summary to help you find your way. Read the sources themselves for the requirements, and check which rules apply where you operate, because they differ by country and by industry.

MOC and PSSR in OSHA's process safety rule and in ISO 45001 (our summary)
SourceWho it applies toWhat it asks for
29 CFR 1910.119(l), management of changeUnited States employers with a process covered by OSHA's standard on process safety management of highly hazardous chemicals: broadly, a process holding a listed chemical at or above its threshold quantity, or 10,000 pounds or more of certain flammable gases and liquids, with exceptionsWritten procedures to manage changes, except replacements in kind, to process chemicals, technology, equipment and procedures, and changes to facilities that affect a covered process. Before any change the procedure must address: the technical basis, the impact on safety and health, modifications to operating procedures, the necessary time period for the change, and the authorization requirements. Affected employees and contract employees are informed and trained before start-up, and process safety information and operating procedures are updated
29 CFR 1910.119(i), pre-startup safety reviewThe same covered processes: new facilities, and modified facilities when the modification is significant enough to require a change in the process safety informationBefore highly hazardous chemicals are introduced, confirm that construction and equipment match the design specifications; that safety, operating, maintenance and emergency procedures are in place and adequate; that a process hazard analysis has been done for a new facility and its recommendations resolved, and that a modified facility has been through management of change; and that training of each employee involved in operating the process is complete
ISO 45001:2018 clause 8.1.3, management of changeAny organisation that has chosen to work to the standard, in any industryA process to implement and control planned changes, temporary and permanent, that affect health and safety performance: new or changed products, services and processes (including locations, work organisation, working conditions, equipment and workforce), changes to legal and other requirements, changes in knowledge about hazards and risks, and developments in knowledge and technology. Review the consequences of unintended changes and act to reduce any adverse effects

A paraphrase, not the legal text. The OSHA paragraphs apply to covered processes only. A machining cell, an assembly line or a trim press is not a covered process, so MOC there is good practice, a customer or corporate requirement, or part of an ISO 45001 system.

So for most discrete manufacturing no regulation names an MOC form. The reason to have one is practical: other duties, such as keeping risk assessments current and training people on the hazards of their work, are hard to meet if changes slip through unassessed. The OSHA paragraph is still the best short checklist there is. Its five considerations (technical basis, safety and health impact, procedures, time period, authorization) fit a change to a packing bench as well as a change to a reactor.

The MOC process, step by step

Ten steps, and three places where the work stops until someone signs. Scale the effort to the change: a moved pallet position might take one page and twenty minutes, a new machine several meetings. What must not scale down is the order.

Ten steps, three stop points

Before the change

  1. Raise the request
  2. Screen it
  3. Write the technical basis
  4. Assess safety and health
  5. List and sort the actions
  6. Approve

Stop 1: no approval, no work starts

Make it and catch up

  1. Make the change
  2. Update documents, train people

Prove it

  1. Pre-startup safety review
  2. Start up, watch, close out

Stops 2 and 3: no sign-off, no start-up; the MOC stays open until the actions are closed

Steps 1 to 6 happen before the change and end at the approval stop. Steps 7 and 8 make the change and update documents and training. Steps 9 and 10 are the pre-startup safety review and close-out, which carry the second and third stops.

Scale the effort to the change, never the order. The stop points are where the work waits for a signature.
  1. 1

    Raise the change request

    Before anything is bought, built or moved. Say what will change, where, why, who is asking, and whether it is permanent, temporary (with an end date) or an emergency.

  2. 2

    Screen it: change or replacement in kind?

    A like-for-like replacement to the same specification is logged as maintenance and goes no further. Anything else carries on. When in doubt, it is a change.

  3. 3

    Write down the technical basis

    What the change is meant to achieve and how it works: drawings, specifications, the supplier's manual, the study that led to it. If the change came from a time study, attach the before sheet and the proposed method.

  4. 4

    Assess the effect on safety and health

    With the people who run, maintain and clean the equipment. Walk the change through every task: normal running, loading and unloading, jams, cleaning, setup, maintenance and emergencies. Redo the job safety analysis for the new method and look for hazards the change adds as well as the ones it removes.

  5. 5

    List the actions and sort them

    Guards, isolation points, procedures, training, signs, inspections. Mark each one as required before start-up or allowed after it, with an owner and a date.

  6. 6

    Approve

    The named approver signs that the assessment is complete and the actions are right. Stop point one: no approval, no work starts.

  7. 7

    Make the change

    Under the normal controls for the work itself: lockout, permits and contractor rules. Build what was approved. If the design has to change on the day, go back to step 4.

  8. 8

    Update the documents and train the people

    Standard work, work instructions, the lockout procedure, the maintenance plan, drawings, the risk register. Train every shift and every contractor whose task is affected, before they meet the change.

  9. 9

    Hold the pre-startup safety review

    Walk the finished change with the checklist: built as approved, before-start-up actions closed, safeguards tested, documents updated, people trained. Stop point two: no sign-off, no start-up.

  10. 10

    Start up, watch, and close out

    Watch the first runs with the operator. Finish the after-start-up actions. For a temporary change, remove it or renew it on its end date. Stop point three: the MOC stays open until every action is closed and the documents match the floor.

Who approves?

The person who wants the change should not be the only one who approves it. Beyond that, match the level of approval to the size of the risk. The table is a starting convention, not a rule from any standard. Set your own and write it into the procedure.

A starting convention for MOC approval levels
Kind of changeReviewed byApproved by
Replacement in kindThe maintenance planner confirms the specificationNo MOC. Logged in the maintenance record
Minor change with no new hazard found at screening, such as a relabelled rack or a moved workbenchArea supervisor and safety leadArea manager
Change to equipment, guarding, energy sources, chemicals, layout, staffing or methodEngineering, maintenance, safety and an operator from the areaDepartment manager
Change that alters a safety system, or carries a severe potential consequenceThe same team plus a specialist: machinery safety, electrical, process or occupational healthPlant manager
Temporary changeAs for its kind, with an end dateAs for its kind. Extension only by the same approver
Emergency changeWhoever is competent and on site, at the jobDuty manager by name. Full review on the next working day

PSSR: the pre-startup safety review

PSSR stands for pre-startup safety review. It is the last check between a finished change and a running process, done at the equipment and not in a meeting room. The term comes from OSHA's process safety rule, where it applies to covered chemical processes. The habit is worth having anywhere, because the commonest MOC failure is a good assessment followed by a change that was not built as assessed.

The OSHA paragraph asks the review to confirm four things, and they translate directly to any plant.

The four PSSR confirmations and what to check on a manufacturing change
Confirm thatOn the floor, check
It was built to the designThe installed equipment matches the approved drawing and specification: the guard that was drawn, the nozzle that was specified, the rated load on the plate. Anything changed on the day has been back through assessment
Procedures are in place and adequateStandard work, work instruction, lockout procedure with any new isolation point, maintenance plan, emergency steps. Read them at the machine and see if they describe what is there
The hazard review is done and its actions are closedEvery before-start-up action from the MOC is finished and seen. Safeguards have been tested, not assumed: trip the light curtain, open the interlocked door, press the emergency stop
People are trainedEvery shift, relief operators, setters, maintenance and contractors whose task is affected, with a record. Ask one of them to show you the new method

A PSSR is a go or no-go decision with a signature. A list of open items "to be finished next week" is a no-go, unless each was marked as allowed after start-up when the change was approved.

Keep the checklist short enough to be done properly and specific to the change. Twenty generic questions answered "N/A" teach people to tick. Eight questions written from the MOC's own action list get read.

A worked example: two changes at a trim press cell

Illustrative example. A study of a trim press cell put the time study, the job safety analysis and the REBA posture scores for one job on a single sheet. The full study is in job safety analysis from video. It found two elements that were slow, risky and awkward at once, and the team proposed two changes.

The two proposed changes and what the study expects from them (illustrative)
ChangeWhat it is meant to fixExpected result
A. An air blast and a scrap chute at the trim dieThe operator clears trimmed flash from the die by hand every cycle: 5 seconds of waste, risk 5 x 3 = 15, REBA 7The element disappears. The chute also keeps flash off the floor, so the trip risk on the walk back falls from 2 x 3 = 6 to 2 x 1 = 2
B. A spring lift table with a turntable under the palletThe operator turns, bends and stacks 9 kg housings on a pallet on the floor: 8 seconds, risk 3 x 4 = 12, REBA 10Stacking takes 6 seconds at waist height, risk 3 x 2 = 6, REBA 3

With cut-resistant gloves and sleeves at unload as well, the study expects the cycle to fall from 48 to 41 seconds, the highest risk score from 15 to 10 and the highest REBA from 10 to 5.

Both changes are improvements, and both came from a safety study. That is exactly when MOC gets skipped: who would hold up a safety fix? But each one adds equipment, energy and tasks that were not there before. Here are the questions the review team raised when they walked the two changes through every task at the cell.

The MOC questions the two changes raised, and what was decided (illustrative)
#ChangeQuestionDecisionWhen
1ACompressed air is noisy. Does the blast raise the noise at the operator's ear?Fit a low-noise nozzle and time the blast to a short pulse. Measure at the operator's position on the first run and compare with the reading beforeBefore start-up
2AWhere does the blown flash go?Aim the blast away from the operator into a hooded chute. Eye protection staysBefore start-up
3ADoes the chute opening give a hand a way into the die from behind?Enclose the chute so the die cannot be reached through it, and check the opening against the site's guarding standardBefore start-up
4AThe press now has a second energy source. Is the air in the lockout procedure?Add a lockable air isolation valve with a bleed, label it, and add the step to the press lockout procedureBefore start-up
5AThe blast is wired into the press controls. Do the light curtain and two-hand start still work as before?Test both safety functions after the wiring change and record the testBefore start-up
6AWho empties the scrap bin under the chute, and how heavy does it get?A wheeled bin with a fill line, and a row for the task in the job safety analysisBefore start-up
7BThe table rises and falls as the load changes. Is there a crush point under it or at its edge?A skirt guard around the mechanism and toe clearance at the baseBefore start-up
8BCan the table carry a full pallet?A full pallet is 40 housings at 9 kg, 360 kg, plus a 25 kg pallet: 385 kg. Confirm the rating plate and the spring setting cover itBefore start-up
9BThe turntable spins freely. Can it trap a foot or swing while the forklift loads it?A rotation lock for loading, and a marked standing position for the operatorBefore start-up
10BThe forklift now places the pallet on a table instead of the floor. Does the pallet swap change?Revise the standard work for the pallet swap with the driver and brief every driverBefore start-up
11BWho inspects the springs, bearings and skirt?Add the table to the preventive maintenance planWithin 30 days

Eleven questions from two changes: ten actions before start-up and one after. None of them stopped the project. Three of them (4, 5 and 7) would have been new hazards running from day one.

Eleven questions from two safety fixes

Example numbers

Change A: air blast and scrap chute

1Noise at the ear
2Where the flash goes
3Chute opening
4Air in the lockout
5Safety circuits retested
6Emptying the scrap bin

Change B: spring lift table with turntable

7Crush point at the table
8Load rating, 385 kg
9Turntable spin
10Pallet swap changes
11Springs and bearings inspected
Before start-upWithin 30 days

Eleven MOC questions: six for change A and five for change B. Ten are before start-up actions and one is after. Questions 4, 5 and 7 would have been new hazards from the first day.

10 actions were needed before start-up, 1 could wait 30 days. Ringed tiles (4, 5 and 7) would have been new hazards running from day one. Change A is the air blast and chute, change B the lift table.

The documents that had to change

  • Job safety analysis: redone for the seven remaining elements, with a new row for emptying the scrap bin. Highest score 10, sum of scores 43, down from 15 and 72.
  • Ergonomic score: stacking re-scored at REBA 3 on the lift table. The highest score on the job is now 5, at loading and unloading the die.
  • Standard work and the time standard: element 5 removed, element 7 at 6 seconds, cycle 41 seconds. At 48 seconds the cell made 75 housings an hour of running time, and at 41 seconds it can make about 88, so the pallet swap now comes round sooner and the downstream process has to be able to take the parts.
  • Lockout procedure for the press: the air isolation step added.
  • Maintenance plan: the lift table, the nozzle and the chute guard.
  • Risk register: the top line for the cell falls from 15 to 10, with the date and the MOC number.
  • Training record: both shifts and the relief operators, signed before their first run on the new method.

The pre-startup safety review took half an hour at the cell. It found one thing: the air valve was fitted and labelled, but the lockout procedure posted on the press was still the old revision. Start-up waited forty minutes for a printout. That is a PSSR doing its job.

Then the team filmed the new method and filled in the same sheet again. The numbers above are predictions until that second study confirms them. A measured cycle of 43 seconds, or a posture nobody expected at the turntable, would send the team back to step 4.

A new method from a time study is a change

Industrial engineers change how work is done for a living. A time study removes an element. A line rebalance moves work from station 4 to station 5. A new layout halves the walking. Each of these is a change to the method, and method is one of the things a safety assessment was written around. The awkward truth is that most of these changes never see an MOC form, because they look like productivity work and no equipment was bought.

The fix is one rule: when the element list changes, the documents built on it are redone before the new method runs. The table shows which ones, for the changes that come out of time and motion work.

What to redo when the method changes

ChangeJob safety analysisErgonomic scoreStandard workTime standardRisk register line
An element removed or automatedRedoRedoRedoRedoRedo
Work moved between stations in a line rebalanceRedoRedoRedoRedoCheck
Takt time or line speed changed, same methodCheckRedoRedoCheckCheck
New layout or moved equipmentRedoRedoRedoRedoRedo
New fixture, tool or lift aidRedoRedoRedoRedoCheck
New part number or heavier variant on the stationCheckRedoCheckRedoCheck
One operator now runs two machinesRedoRedoRedoRedoRedo
Like-for-like replacement of a worn partNoNoNoNoNo

A matrix of eight kinds of method change against five documents: job safety analysis, ergonomic score, standard work, time standard and risk register line. Each cell says redo, check or no.

Yellow: write it again for the new method. Pale: read it against the new method and sign that it still holds. Almost every method change touches the ergonomic score, because repetition and duration move even when the posture does not.
  • A rebalance is the easiest one to miss. The element being moved was assessed at the station it left. At the new station it sits next to different equipment, is done by a person already carrying other work, and may push a posture that was fine for 20 seconds a cycle to 35.
  • A faster cycle changes likelihood. The hazard and its severity are the same, but a hand that passes a pinch point 75 times an hour now passes it about 88 times.
  • A new method needs the old controls checked. If the step that included "check the clamp" was removed as waste, something else must now make sure the clamp is closed.
  • The time standard waits for the safety review. Set the standard on the method that passed the MOC, not on the method the engineer first proposed.

Two tools sit either side of the MOC. Before the change, the study that proposes it. After the change, change point management: the shift-level habit of logging every change to man, machine, material and method and checking the product more closely until the change is proven. The 4M change management sheet is the log for that. It is a quality tool and it does not replace an MOC, but the two work well together: the MOC approves a planned change, and the 4M sheet records the day it went live and the extra checks that followed.

The re-study is quick if the first study was filmed. In LeanSuite you upload the film of the new method, and the time and motion study compares two studies side by side with their value-added percentages. The ergonomic study lets you re-score the job after a layout or tooling change. Both analyse uploaded files and give you drafts to review. The MOC decision, the job safety analysis and the sign-off stay with your team.

The traps

  • The form arrives after the change. If the MOC is written the week after installation, it is a record, not a control. Tie the purchase order or the work order to an approved MOC number.
  • "It's like for like." Most uncontrolled changes are replacements that were nearly the same. Make someone check the specification, not the description.
  • Improvements get waved through. A safety fix or a kaizen is still a change, and good intentions do not guard a pinch point.
  • Temporary changes with no end date. Keep a register of them and review it every week.
  • The assessment only covers normal running. Ask about jams, cleaning, setup and maintenance for the changed equipment, every time.
  • No operator in the review. The people who will live with the change see problems a drawing does not show.
  • Start-up before training. The night shift meets the new method with nobody there to explain it.
  • Documents never catch up. Six months later the work instruction, the lockout procedure and the risk register describe a cell that no longer exists.
  • Emergency approval as the normal route. If a third of your changes are emergencies, the plan is the problem.
  • So heavy that people avoid it. A forty-page form for a moved bin teaches everyone to stop asking. Keep a one-page version for small changes, and make the screening step fast.
  • Many small changes, each harmless. Ten approved tweaks to one cell in a year can add up to a different process. Re-study the whole job now and then, not only the last change.

Templates and related guides

FAQ

Questions about management of change (MOC)

  1. MOC stands for management of change. It is the written process a site uses to make sure a change to equipment, materials, methods, layout, procedures or staffing is assessed for its effect on safety and health and approved before it is made, and that documents and training are updated before the changed work starts.

  2. Raise a change request, screen it as a change or a replacement in kind, record the technical basis, assess the effect on safety and health with the people who do the work, list the actions, get approval, make the change, update documents and train people, hold a pre-startup safety review, then start up and close out. Work stops at approval and at the pre-startup review until someone signs.

  3. PSSR stands for pre-startup safety review. It is the final check on a new or modified process before it runs: that it was built to the approved design, that procedures are in place, that the hazard review's actions are closed and that the people involved are trained. The term comes from OSHA's process safety management rule, 29 CFR 1910.119(i), which applies to covered chemical processes.

  4. For processes covered by OSHA's process safety management standard, yes: 29 CFR 1910.119(l) requires written procedures to manage changes other than replacements in kind. That standard covers processes with highly hazardous chemicals above set quantities. Most discrete manufacturing is outside it, so there MOC is good practice or a requirement of a system such as ISO 45001 clause 8.1.3. Check which rules apply to your site.

  5. A replacement that satisfies the design specification, in the words of OSHA's process safety rule. Swapping a worn part for an identical one is a replacement in kind and does not need an MOC. A part from a different maker, in a different material or of a different type is a change, even if it is sold as equivalent, and should be screened before it is fitted.

  6. Yes. Removing, combining or re-ordering elements changes where hands go, which postures are held and which checks get done, even when no equipment is bought. Before the new method runs, redo the job safety analysis and the ergonomic score, update the standard work and train the operators. Set the new time standard on the method that passed that review.

  7. In safety, management of change controls technical and operational changes: equipment, chemicals, methods, layout and staffing are assessed for hazards before they change. Change management, in the organisational sense, is about helping people adopt a new way of working. An MOC needs some of the second to succeed, because a change nobody was told about is a hazard however well it was assessed.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.