Practical guide · Standard work, SOPs and training
Standard work combination table: how to fill it in from a time study and read it
Short answer
A standard work combination table lists one operator's work elements in order and draws each one on a time line: a solid bar for manual work, a dashed line for a machine running alone, a wavy line for walking. A vertical line marks takt time. The work must end before it.
To fill it in, take three times for each element from the time study: manual, machine and walking. Start the first row at zero. Draw the manual time as a bar, then from the end of the bar draw the machine time as a dashed line and the walk as a wavy line. Start the next row where the walk ended. Add manual and walking time for the operator's cycle and compare it with the takt line. In the example on this page the first draft came to 63 seconds against a 60 second takt time. Moving one rack cut the last walk from 8 seconds to 3 and the cycle to 58.
Last reviewed:
What is a standard work combination table?
A finished standard work combination table, with every mark named
Example numbersManual work. A solid bar as long as the hands-on time. The operator cannot leave while it lasts.
Machine runs alone. A dashed line from the moment the operator presses start to the moment the machine stops.
Walking. A wavy line from the end of the manual bar to the start of the next row.
Waiting. A box for time the operator stands idle. Here it is the 2 s left before takt.
Takt time. One vertical line, usually red, down the whole sheet. The operator's work must end at or before it.
1. Load the housing in the press, start itManual 7 s, machine 10 s, walk 2 s
2. Fit the gears and the coverManual 16 s, walk 2 s
Starts at 9 s, where the walk from row 1 ended
3. Load the nutrunner, start itManual 6 s, machine 14 s, walk 3 s
4. Unload and load the tester, start itManual 8 s, machine 45 s, walk 2 s
Still running at 60 s, so the line carries on from 0 and ends at 29 s
5. Label and pack, pick up a housingManual 9 s, walk 3 s
Operator cycleManual 46 s + walk 12 s = 58 s, wait 2 s
The gear pump cell: five elements on a time line from 0 to 70 seconds with takt time at 60 seconds. Manual work and walking add up to 58 seconds. The tester runs for 45 seconds from 44 seconds, passes the end of the cycle and finishes 29 seconds into the next one, before the operator returns to it at 36 seconds.
A standard work combination table is a time line of one operator's cycle. The left side lists the work elements in the order they are done, with the time for each. The right side draws those times as lines across a scale in seconds. It is also called a standard work combination sheet, a standardized work combination table or a work combination chart.
The word combination is the point. The Lean Enterprise Institute's Lean Lexicon describes the form as showing the combination of manual work time, walk time and machine processing time. A list of element times tells you how long the work is. The table shows what the person and the machines are each doing at the same moment, which is what you need to know before asking one operator to run three or four machines.
It is the second of the three standard work documents. The process capacity table comes first and checks the machines. The combination table checks the operator. The standard work chart then shows the result on the layout. From time study to standard work covers all three. This page stays with the table.
The three time columns, and where each comes from
Every row has up to three times. They are timed separately in the study, because they are done by different things: the operator's hands, the machine on its own, and the operator's feet.
| Column | What counts | How to time it | What does not count |
|---|---|---|---|
| Manual | Any time the operator's hands are needed: load, unload, press start, assemble, check, pack. | From reaching for the part to letting go of the start button. Time ten cycles or so and take the time that repeats. | Walking, and waiting for a machine. |
| Machine (auto) | Time the machine runs with nobody at it. | From start pressed to the cycle finishing. A few readings are enough, or read it from the program. | Any part of the cycle where the operator must hold, guide or watch. That is manual time. |
| Walk | Moving from this stop to the next, hands free or carrying the part. | From leaving one stop to arriving at the next. Write it on the row the operator walks away from. | Reaching within arm's length. That belongs to the manual time. |
Christoph Roser, describing Toyota's sheet, gives a rule of thumb of two steps a second for estimating walks. Time the real walk if you can.
Where the three time columns come from: element 1, load the press
Example numbersTime the hands-on work on each cycle, from reaching for the part to pressing start.
- 7
- 8
- 7
- 7
- 9
- 7
- 8
- 7
- 7
- 10
Manual: 7 s
Shortest time that repeats: 7 s appears six times in ten. The 9 and the 10 had a cause, a housing that stuck in the tray.
Time the machine from start pressed to ram back up. The operator has walked away.
- 10
- 10
- 10
- 10
- 10
Machine: 10 s
A machine cycle barely varies. A few readings are enough, or take it from the program.
Time the walk from the press to the assembly bench, hands free or carrying the part.
- 2
- 2
- 3
- 2
- 2
Walk: 2 s
About three steps. Write the walk on the row it leaves from.
Three lanes for one element. Manual: ten readings of 7, 8, 7, 7, 9, 7, 8, 7, 7 and 10 seconds give 7 seconds. Machine: five readings of 10 seconds give 10 seconds. Walk: readings of 2, 2, 3, 2 and 2 seconds give 2 seconds.
Which manual time to write down is a choice. Toyota-style standard work usually takes the shortest time the operator can repeat, and investigates the slow cycles instead of averaging them in. Classic work measurement uses a rated average plus allowances to build a standard time. Use one basis for the whole sheet and note it in the header.
The symbols
The table uses very few marks, and they have been stable for decades. A hand-drawn sheet and a spreadsheet version should look the same.
| Mark | Means | How it is drawn |
|---|---|---|
| Solid bar or solid line | Manual work | As long as the manual time, starting where the operator arrives at the stop. |
| Dashed line | Machine running alone | From the end of the manual bar, as long as the machine time. |
| Wavy line | Walking | From the end of the manual bar to the start of the next row. On paper it runs diagonally down to the next row. |
| Box, or a double-headed arrow | Waiting | Wherever the operator stands idle, as long as the wait. |
| Vertical line, usually red | Takt time | One line down the whole sheet at the takt time. |
These are the marks described for Toyota's sheet. Some plants add marks of their own, such as a diamond for a quality check on the row where it is done.
How to fill it in from a time study
You need the time study sheet with manual, machine and walking time for each element, and the takt time. Draw one table per operator.
- 1
Fill in the header
Part, process, operator position, date, who drew it, the takt time and how it was worked out: working time in the shift divided by demand.
- 2
List the elements in order
One row per element, in the sequence the operator does them, each starting with a verb. An element ends where the operator can walk away.
- 3
Write the three times
Manual, machine and walk for each row, in seconds. Leave machine blank where there is none.
- 4
Draw the takt line
Set the scale so takt time sits near the right edge. Draw one vertical line at takt time down the whole sheet.
- 5
Draw row 1 from zero
A bar for the manual time. From its end, a dashed line for the machine time and a wavy line for the walk.
- 6
Start each row where the last walk ended
Row 2 starts at row 1's manual time plus walk. Carry on down the sheet. The bars step down and to the right like a staircase.
- 7
Close the cycle
Add manual and walking time. That is the operator's cycle. If it is under takt time, draw the difference as waiting. If it is over, the job does not fit yet.
- 8
Check every machine
For each dashed line, find when the operator next arrives at that machine. The line must have ended by then.
How one row is drawn: row 3, load the nutrunner
Example numbers- 1
Start at 27 s. That is where the walk from row 2 ended, so the operator has just arrived.
- 2
Draw the manual bar 6 s long, to 33 s. The operator presses start as it ends.
- 3
From 33 s, draw the walk as a wavy line 3 s long. The next row starts where it ends, at 36 s.
- 4
Also from 33 s, draw the machine as a dashed line 14 s long, to 47 s. It runs while the operator is at the tester.
Row 3 of the gear pump table, enlarged from 24 to 50 seconds. The row starts at 27 seconds. A manual bar runs from 27 to 33 seconds. From 33 seconds a wavy walking line runs to 36 seconds, and a dashed machine line runs to 47 seconds.
| Element | Manual | Machine | Walk | Row starts at |
|---|---|---|---|---|
| 1. Load the housing in the press, start it | 7 | 10 | 2 | 0 |
| 2. Fit the gears and the cover | 16 | 0 | 2 | 9 |
| 3. Load the nutrunner, start it | 6 | 14 | 3 | 27 |
| 4. Unload and load the tester, start it | 8 | 45 | 2 | 36 |
| 5. Label and pack, pick up a housing | 9 | 0 | 3 | 46 |
Manual: 7 + 16 + 6 + 8 + 9 = 46 seconds. Walking: 2 + 2 + 3 + 2 + 3 = 12 seconds. Operator cycle: 58 seconds. Waiting: 60 minus 58 = 2 seconds. Takt time: 27,000 seconds / 450 pumps = 60 seconds.
Machine time is not totalled. It is not the operator's time, and adding the four machines together means nothing. What matters for each machine is whether it finishes before the operator returns.
When a machine runs past the end of the cycle
Row 4 is the case that stops people. The operator starts the tester at 44 seconds and it runs for 45, so it finishes at 89 seconds. The sheet ends at 60.
The cycle repeats every takt time, so 89 seconds is 29 seconds into the next cycle. Draw the dashed line from 44 to the takt line, then carry it on from zero to 29 on the same row. Now check it against the operator: the next arrival at the tester is at 36 seconds, and the test ended at 29. It is done, with 7 seconds to spare.
A machine time longer than the operator's cycle is not a problem in itself. A machine that needs longer than takt time for one piece is: it cannot keep up however the operator is organised. That needs a second machine, a second nest or a shorter cycle, and it should have shown up on the process capacity table.
Worked example: a first draft that ran over
Illustrative numbers. A cell assembles and tests a small gear pump. The shift has 450 minutes of working time, 27,000 seconds, and the customer needs 450 pumps: takt time is 60 seconds. One operator loads a press, assembles at a bench, loads a nutrunner, loads a tester, then labels and packs.
The first draft, drawn straight from the time study, came to 46 seconds of manual work and 17 seconds of walking: 63 seconds, 3 over takt time. At that pace the cell makes 27,000 / 63 = 428 pumps in a shift, about 21 short.
The table showed where to look. Four of the five walks were 2 or 3 seconds. The last was 8: after packing, the operator walked to a rack of housings at the far end and back to the press. The rack was moved beside the packing bench. The last walk became 3 seconds, walking fell to 12 and the cycle to 58. No manual element changed.
The first draft ran over takt. The table showed where.
Example numbers- Manual work
- Machine runs alone
- Walking
- Waiting
- Takt time
Before
63 s of work in a 60 s takt time
The cell falls 3 s further behind on every piece, which is about 21 pieces short over a 450 minute shift.
1. Load the housing in the press, start itManual 7 s, machine 10 s, walk 2 s
2. Fit the gears and the coverManual 16 s, walk 2 s
3. Load the nutrunner, start itManual 6 s, machine 14 s, walk 3 s
4. Unload and load the tester, start itManual 8 s, machine 45 s, walk 2 s
5. Label and pack, pick up a housingManual 9 s, walk 8 s
8 s walk back to the housing rack: the bar ends past the red line
Operator cycleManual 46 s + walk 17 s = 63 s, 3 s over takt
After
58 s of work, 2 s of waiting
Same five elements, same manual times. Only the last walk changed.
1. Load the housing in the press, start itManual 7 s, machine 10 s, walk 2 s
2. Fit the gears and the coverManual 16 s, walk 2 s
3. Load the nutrunner, start itManual 6 s, machine 14 s, walk 3 s
4. Unload and load the tester, start itManual 8 s, machine 45 s, walk 2 s
5. Label and pack, pick up a housingManual 9 s, walk 3 s
Rack moved beside the packing bench: 3 s walk
Operator cycleManual 46 s + walk 12 s = 58 s, wait 2 s
Two combination tables of the gear pump cell with takt time at 60 seconds. Before: the operator's cycle is 63 seconds, 3 seconds over takt, and the last walk takes 8 seconds. After the housing rack is moved next to the packing bench the last walk takes 3 seconds and the cycle is 58 seconds.
That order is worth copying. Take out walking and waiting before you touch manual work, and touch manual work before you add a person. If the cycle were still over takt time after that, the next question is the one in how many operators a line needs, and for several operators a yamazumi chart is the better picture.
How to read a finished table
Look at the shape first. A sound table has dark bars stepping down from the top left and ending a little before the takt line, short wavy lines between them, and every dashed line finished before the operator is back.
- Compare the end of the last walk with the takt line. That gap, or overrun, is the headline.
- Find the longest wavy line. It is the cheapest time on the sheet to remove.
- Find the longest solid bar. Ask whether part of it could be done while a machine runs, or by the machine.
- Follow each dashed line to its end and check the operator has not come back before it.
- Add up the waiting. A few seconds is slack. A third of the cycle is half a job.
Four shapes to recognise on a combination table
Bars run past the takt line
More work than one takt time holds. The cell falls behind every cycle.
Take out walking and waste first. If it still does not fit, move an element to another operator.
A wide gap before the takt line
The operator finishes early and waits on every cycle.
Give that time real work, such as a check or feeding the next cell, or combine two jobs.
A dashed line still running when the operator is back
The operator returns before the machine has finished, and has to stand and wait for it.
Change the sequence so the long machine is loaded earlier, or shorten its cycle.
Long wavy lines between short bars
A large share of the cycle is walking. The layout is costing time on every piece.
Move the stations closer or change the order of the loop. Walking is the cheapest time to remove.
The Lexicon notes that the table can be recalculated as takt time changes. That is its second use. When demand moves, redraw the takt line first and see whether the same sequence still fits before you change anything on the floor.
Common mistakes
- Starting every row at zero. The sheet becomes a bar chart of element times and no longer shows the sequence.
- Adding machine time to the operator's cycle. The total then says the job does not fit when it does.
- Counting watched machine time as machine time. If the operator has to stand there, draw it as manual.
- Leaving out the walk back to the first stop. The last walk closes the loop and is often the longest.
- Hiding the waiting. If the cycle is 58 seconds and takt time is 60, the sheet should show 2 seconds of waiting, not a cycle stretched to 60.
- One table for two operators. Draw one per person, then lay them side by side to see hand-offs.
- Drawing it once. The table is only true for one takt time and one method. Date it and redraw it when either changes.
- Using it where the work does not repeat. With no cycle there is nothing to draw against takt time. It also shows nothing about posture or effort: a sequence can fit takt time and still be a bad job.
Where software helps
The table is quick to draw once you have the times. Getting the times is the slow part. With LeanSuite's Time and Motion Study you film the cycle and the AI drafts the element times on a timeline that links back to the video, for you to check and certify. The combination table itself is a free LeanSuite template: download the standard work combination table and fill it in from the study.
Standardized work software
Keep standard work current in LeanSuite
LeanSuite covers most of the cycle in one platform: working out the standard with Vision AI, keeping it current with SOPs and work instructions, and training and auditing it.
Go deeper
This page is the short version. These guides cover each part in full.
- Standard Work Tools: Combination Sheet, Standardized Work Chart, Job BreakdownThe combination sheet next to the other standard work forms.
- The Three Elements of Standard Work: Takt Time, Work Sequence, Standard WIPTakt time and work sequence, the two elements the table puts on one page.
- Standard Work in Manufacturing: The Complete GuideWhere the table fits in rolling standard work out across a plant.
All our articles on this subject are in the standard work, sops and training topic.
Free templates and tools
- Standard work combination tableOne operator's manual, machine, walk and wait time on a time chart against takt, with machine cycles and a process capacity sheet.
- Process capacity sheet templateEach machine in a part's routing with manual, auto and tool change time, its capacity per shift, and the step that limits the cell against demand.
- Standard work sheet templateTakt time, each element's manual, machine and walk time on a time chart, key points and standard WIP.
- Time study sheetTime each element over 10 cycles and work out the average, lowest repeatable and standard time. Excel does the sums.
- Takt time calculatorThe pace a line must hit to meet customer demand, from shift time, breaks and daily demand.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
- Line balancing calculatorLine efficiency, balance delay and the minimum number of stations from station times and takt.
Doing this in LeanSuite
Time and Motion Study
Film the station and the AI times every element on a timeline that links to the video. You check it and certify it.
See Time and Motion StudyLine Balancing
Drop in a video of your line and get a Yamazumi chart, a takt comparison and rebalancing recommendations.
See Line Balancing
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about standard work combination table
It is a sheet that lists one operator's work elements in order and draws each on a time line: a solid bar for manual work, a dashed line for a machine running alone and a wavy line for walking, with a vertical line at takt time. It shows whether one person can do the whole sequence inside takt time.
List the elements in sequence with manual, machine and walking time for each. Draw the takt line. Start row 1 at zero with a bar for manual time, then a dashed line for machine time and a wavy line for the walk. Start each next row where the last walk ended. Add manual and walking time and compare the total with takt time.
A solid bar or line is manual work. A dashed line is a machine running with nobody at it. A wavy line is walking. A box or double-headed arrow is waiting. A vertical line, usually red, marks takt time. The operator's manual work and walking must end at or before the takt line.
The job as drawn cannot keep up with demand, and the cell falls further behind on every piece. Look for the longest walk and any waiting first, since those are the cheapest to remove. Then look at the manual elements. If it still does not fit, part of the work has to move to another operator.
Draw the dashed line to the takt line, then continue it from zero on the same row for the time that is left. A test started at 44 seconds that runs 45 seconds, on a 60 second cycle, ends 29 seconds into the next cycle. It is fine as long as it ends before the operator returns to that machine.
A combination table follows one operator through time and shows machines running alongside. A yamazumi chart, or operator balance chart, stacks each operator's work into a bar so several operators can be compared against takt time. The Lean Lexicon calls the combination table the more precise of the two. Use the yamazumi to share work out and the table to design each person's cycle.
Related guides and tools
- Standard work combination table template: the blank sheet, free to download
- From time study to standard work: all three documents filled in from one study
- Standard work: the three elements the table is built on
- Standard WIP: counting the pieces the sequence needs
- Takt time: how to get the number for the red line
- Yamazumi chart: the picture to use when several operators share the work
- How many operators a line needs: when one cycle will not fit takt time
- Time and motion study: the methods behind the element times
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk
Or browse the topics, the full library and the lean glossary.
Rather see it on your own problem?
Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.