Skip to content
LeanSuite

Standard work combination table: how to fill it in from a time study and read it

Short answer

A standard work combination table lists one operator's work elements in order and draws each one on a time line: a solid bar for manual work, a dashed line for a machine running alone, a wavy line for walking. A vertical line marks takt time. The work must end before it.

To fill it in, take three times for each element from the time study: manual, machine and walking. Start the first row at zero. Draw the manual time as a bar, then from the end of the bar draw the machine time as a dashed line and the walk as a wavy line. Start the next row where the walk ended. Add manual and walking time for the operator's cycle and compare it with the takt line. In the example on this page the first draft came to 63 seconds against a 60 second takt time. Moving one rack cut the last walk from 8 seconds to 3 and the cycle to 58.

Last reviewed:

What is a standard work combination table?

A finished standard work combination table, with every mark named

Example numbers
  • Manual work. A solid bar as long as the hands-on time. The operator cannot leave while it lasts.

  • Machine runs alone. A dashed line from the moment the operator presses start to the moment the machine stops.

  • Walking. A wavy line from the end of the manual bar to the start of the next row.

  • Waiting. A box for time the operator stands idle. Here it is the 2 s left before takt.

  • Takt time. One vertical line, usually red, down the whole sheet. The operator's work must end at or before it.

  1. 1. Load the housing in the press, start itManual 7 s, machine 10 s, walk 2 s

  2. 2. Fit the gears and the coverManual 16 s, walk 2 s

    Starts at 9 s, where the walk from row 1 ended

  3. 3. Load the nutrunner, start itManual 6 s, machine 14 s, walk 3 s

  4. 4. Unload and load the tester, start itManual 8 s, machine 45 s, walk 2 s

    Still running at 60 s, so the line carries on from 0 and ends at 29 s

  5. 5. Label and pack, pick up a housingManual 9 s, walk 3 s

  6. Operator cycleManual 46 s + walk 12 s = 58 s, wait 2 s

The gear pump cell: five elements on a time line from 0 to 70 seconds with takt time at 60 seconds. Manual work and walking add up to 58 seconds. The tester runs for 45 seconds from 44 seconds, passes the end of the cycle and finishes 29 seconds into the next one, before the operator returns to it at 36 seconds.

Five marks carry the whole sheet. The operator's bars and wavy lines step down from left to right and stop at 58 s, 2 s before takt. Row 4 shows the one case that confuses people: a machine that runs past the end of the cycle.

A standard work combination table is a time line of one operator's cycle. The left side lists the work elements in the order they are done, with the time for each. The right side draws those times as lines across a scale in seconds. It is also called a standard work combination sheet, a standardized work combination table or a work combination chart.

The word combination is the point. The Lean Enterprise Institute's Lean Lexicon describes the form as showing the combination of manual work time, walk time and machine processing time. A list of element times tells you how long the work is. The table shows what the person and the machines are each doing at the same moment, which is what you need to know before asking one operator to run three or four machines.

It is the second of the three standard work documents. The process capacity table comes first and checks the machines. The combination table checks the operator. The standard work chart then shows the result on the layout. From time study to standard work covers all three. This page stays with the table.

The three time columns, and where each comes from

Every row has up to three times. They are timed separately in the study, because they are done by different things: the operator's hands, the machine on its own, and the operator's feet.

The three time columns of a combination table
ColumnWhat countsHow to time itWhat does not count
ManualAny time the operator's hands are needed: load, unload, press start, assemble, check, pack.From reaching for the part to letting go of the start button. Time ten cycles or so and take the time that repeats.Walking, and waiting for a machine.
Machine (auto)Time the machine runs with nobody at it.From start pressed to the cycle finishing. A few readings are enough, or read it from the program.Any part of the cycle where the operator must hold, guide or watch. That is manual time.
WalkMoving from this stop to the next, hands free or carrying the part.From leaving one stop to arriving at the next. Write it on the row the operator walks away from.Reaching within arm's length. That belongs to the manual time.

Christoph Roser, describing Toyota's sheet, gives a rule of thumb of two steps a second for estimating walks. Time the real walk if you can.

Where the three time columns come from: element 1, load the press

Example numbers
  1. Time the hands-on work on each cycle, from reaching for the part to pressing start.

    • 7
    • 8
    • 7
    • 7
    • 9
    • 7
    • 8
    • 7
    • 7
    • 10

    Manual: 7 s

    Shortest time that repeats: 7 s appears six times in ten. The 9 and the 10 had a cause, a housing that stuck in the tray.

  2. Time the machine from start pressed to ram back up. The operator has walked away.

    • 10
    • 10
    • 10
    • 10
    • 10

    Machine: 10 s

    A machine cycle barely varies. A few readings are enough, or take it from the program.

  3. Time the walk from the press to the assembly bench, hands free or carrying the part.

    • 2
    • 2
    • 3
    • 2
    • 2

    Walk: 2 s

    About three steps. Write the walk on the row it leaves from.

Three lanes for one element. Manual: ten readings of 7, 8, 7, 7, 9, 7, 8, 7, 7 and 10 seconds give 7 seconds. Machine: five readings of 10 seconds give 10 seconds. Walk: readings of 2, 2, 3, 2 and 2 seconds give 2 seconds.

One element gives up to three numbers, and they are timed separately. Mix manual and machine time into one reading and the table can no longer show what the operator does while the machine runs.

Which manual time to write down is a choice. Toyota-style standard work usually takes the shortest time the operator can repeat, and investigates the slow cycles instead of averaging them in. Classic work measurement uses a rated average plus allowances to build a standard time. Use one basis for the whole sheet and note it in the header.

The symbols

The table uses very few marks, and they have been stable for decades. A hand-drawn sheet and a spreadsheet version should look the same.

Marks on a standard work combination table
MarkMeansHow it is drawn
Solid bar or solid lineManual workAs long as the manual time, starting where the operator arrives at the stop.
Dashed lineMachine running aloneFrom the end of the manual bar, as long as the machine time.
Wavy lineWalkingFrom the end of the manual bar to the start of the next row. On paper it runs diagonally down to the next row.
Box, or a double-headed arrowWaitingWherever the operator stands idle, as long as the wait.
Vertical line, usually redTakt timeOne line down the whole sheet at the takt time.

These are the marks described for Toyota's sheet. Some plants add marks of their own, such as a diamond for a quality check on the row where it is done.

How to fill it in from a time study

You need the time study sheet with manual, machine and walking time for each element, and the takt time. Draw one table per operator.

  1. 1

    Fill in the header

    Part, process, operator position, date, who drew it, the takt time and how it was worked out: working time in the shift divided by demand.

  2. 2

    List the elements in order

    One row per element, in the sequence the operator does them, each starting with a verb. An element ends where the operator can walk away.

  3. 3

    Write the three times

    Manual, machine and walk for each row, in seconds. Leave machine blank where there is none.

  4. 4

    Draw the takt line

    Set the scale so takt time sits near the right edge. Draw one vertical line at takt time down the whole sheet.

  5. 5

    Draw row 1 from zero

    A bar for the manual time. From its end, a dashed line for the machine time and a wavy line for the walk.

  6. 6

    Start each row where the last walk ended

    Row 2 starts at row 1's manual time plus walk. Carry on down the sheet. The bars step down and to the right like a staircase.

  7. 7

    Close the cycle

    Add manual and walking time. That is the operator's cycle. If it is under takt time, draw the difference as waiting. If it is over, the job does not fit yet.

  8. 8

    Check every machine

    For each dashed line, find when the operator next arrives at that machine. The line must have ended by then.

How one row is drawn: row 3, load the nutrunner

Example numbers
  1. 1

    Start at 27 s. That is where the walk from row 2 ended, so the operator has just arrived.

  2. 2

    Draw the manual bar 6 s long, to 33 s. The operator presses start as it ends.

  3. 3

    From 33 s, draw the walk as a wavy line 3 s long. The next row starts where it ends, at 36 s.

  4. 4

    Also from 33 s, draw the machine as a dashed line 14 s long, to 47 s. It runs while the operator is at the tester.

Row 3 of the gear pump table, enlarged from 24 to 50 seconds. The row starts at 27 seconds. A manual bar runs from 27 to 33 seconds. From 33 seconds a wavy walking line runs to 36 seconds, and a dashed machine line runs to 47 seconds.

Every row is drawn the same way. The only number you carry from one row to the next is where the walk ended.
Illustrative: the gear pump cell after the fix, takt time 60 seconds
ElementManualMachineWalkRow starts at
1. Load the housing in the press, start it71020
2. Fit the gears and the cover16029
3. Load the nutrunner, start it614327
4. Unload and load the tester, start it845236
5. Label and pack, pick up a housing90346

Manual: 7 + 16 + 6 + 8 + 9 = 46 seconds. Walking: 2 + 2 + 3 + 2 + 3 = 12 seconds. Operator cycle: 58 seconds. Waiting: 60 minus 58 = 2 seconds. Takt time: 27,000 seconds / 450 pumps = 60 seconds.

Machine time is not totalled. It is not the operator's time, and adding the four machines together means nothing. What matters for each machine is whether it finishes before the operator returns.

When a machine runs past the end of the cycle

Row 4 is the case that stops people. The operator starts the tester at 44 seconds and it runs for 45, so it finishes at 89 seconds. The sheet ends at 60.

The cycle repeats every takt time, so 89 seconds is 29 seconds into the next cycle. Draw the dashed line from 44 to the takt line, then carry it on from zero to 29 on the same row. Now check it against the operator: the next arrival at the tester is at 36 seconds, and the test ended at 29. It is done, with 7 seconds to spare.

A machine time longer than the operator's cycle is not a problem in itself. A machine that needs longer than takt time for one piece is: it cannot keep up however the operator is organised. That needs a second machine, a second nest or a shorter cycle, and it should have shown up on the process capacity table.

Worked example: a first draft that ran over

Illustrative numbers. A cell assembles and tests a small gear pump. The shift has 450 minutes of working time, 27,000 seconds, and the customer needs 450 pumps: takt time is 60 seconds. One operator loads a press, assembles at a bench, loads a nutrunner, loads a tester, then labels and packs.

The first draft, drawn straight from the time study, came to 46 seconds of manual work and 17 seconds of walking: 63 seconds, 3 over takt time. At that pace the cell makes 27,000 / 63 = 428 pumps in a shift, about 21 short.

The table showed where to look. Four of the five walks were 2 or 3 seconds. The last was 8: after packing, the operator walked to a rack of housings at the far end and back to the press. The rack was moved beside the packing bench. The last walk became 3 seconds, walking fell to 12 and the cycle to 58. No manual element changed.

The first draft ran over takt. The table showed where.

Example numbers
  • Manual work
  • Machine runs alone
  • Walking
  • Waiting
  • Takt time

Before

63 s of work in a 60 s takt time

The cell falls 3 s further behind on every piece, which is about 21 pieces short over a 450 minute shift.

  1. 1. Load the housing in the press, start itManual 7 s, machine 10 s, walk 2 s

  2. 2. Fit the gears and the coverManual 16 s, walk 2 s

  3. 3. Load the nutrunner, start itManual 6 s, machine 14 s, walk 3 s

  4. 4. Unload and load the tester, start itManual 8 s, machine 45 s, walk 2 s

  5. 5. Label and pack, pick up a housingManual 9 s, walk 8 s

    8 s walk back to the housing rack: the bar ends past the red line

  6. Operator cycleManual 46 s + walk 17 s = 63 s, 3 s over takt

After

58 s of work, 2 s of waiting

Same five elements, same manual times. Only the last walk changed.

  1. 1. Load the housing in the press, start itManual 7 s, machine 10 s, walk 2 s

  2. 2. Fit the gears and the coverManual 16 s, walk 2 s

  3. 3. Load the nutrunner, start itManual 6 s, machine 14 s, walk 3 s

  4. 4. Unload and load the tester, start itManual 8 s, machine 45 s, walk 2 s

  5. 5. Label and pack, pick up a housingManual 9 s, walk 3 s

    Rack moved beside the packing bench: 3 s walk

  6. Operator cycleManual 46 s + walk 12 s = 58 s, wait 2 s

Two combination tables of the gear pump cell with takt time at 60 seconds. Before: the operator's cycle is 63 seconds, 3 seconds over takt, and the last walk takes 8 seconds. After the housing rack is moved next to the packing bench the last walk takes 3 seconds and the cycle is 58 seconds.

Nothing about the hands-on work changed. Moving one rack cut the last walk from 8 s to 3 s, and the cycle went from 63 s to 58 s. On the table the fix is easy to spot: the longest wavy line is the place to look first.

That order is worth copying. Take out walking and waiting before you touch manual work, and touch manual work before you add a person. If the cycle were still over takt time after that, the next question is the one in how many operators a line needs, and for several operators a yamazumi chart is the better picture.

How to read a finished table

Look at the shape first. A sound table has dark bars stepping down from the top left and ending a little before the takt line, short wavy lines between them, and every dashed line finished before the operator is back.

  • Compare the end of the last walk with the takt line. That gap, or overrun, is the headline.
  • Find the longest wavy line. It is the cheapest time on the sheet to remove.
  • Find the longest solid bar. Ask whether part of it could be done while a machine runs, or by the machine.
  • Follow each dashed line to its end and check the operator has not come back before it.
  • Add up the waiting. A few seconds is slack. A third of the cycle is half a job.

Four shapes to recognise on a combination table

  • Bars run past the takt line

    More work than one takt time holds. The cell falls behind every cycle.

    Take out walking and waste first. If it still does not fit, move an element to another operator.

  • A wide gap before the takt line

    The operator finishes early and waits on every cycle.

    Give that time real work, such as a check or feeding the next cell, or combine two jobs.

  • A dashed line still running when the operator is back

    The operator returns before the machine has finished, and has to stand and wait for it.

    Change the sequence so the long machine is loaded earlier, or shorten its cycle.

  • Long wavy lines between short bars

    A large share of the cycle is walking. The layout is costing time on every piece.

    Move the stations closer or change the order of the loop. Walking is the cheapest time to remove.

Read the shape before the numbers. Each of these shows up in seconds on the drawing and takes minutes to find in a column of times.

The Lexicon notes that the table can be recalculated as takt time changes. That is its second use. When demand moves, redraw the takt line first and see whether the same sequence still fits before you change anything on the floor.

Common mistakes

  • Starting every row at zero. The sheet becomes a bar chart of element times and no longer shows the sequence.
  • Adding machine time to the operator's cycle. The total then says the job does not fit when it does.
  • Counting watched machine time as machine time. If the operator has to stand there, draw it as manual.
  • Leaving out the walk back to the first stop. The last walk closes the loop and is often the longest.
  • Hiding the waiting. If the cycle is 58 seconds and takt time is 60, the sheet should show 2 seconds of waiting, not a cycle stretched to 60.
  • One table for two operators. Draw one per person, then lay them side by side to see hand-offs.
  • Drawing it once. The table is only true for one takt time and one method. Date it and redraw it when either changes.
  • Using it where the work does not repeat. With no cycle there is nothing to draw against takt time. It also shows nothing about posture or effort: a sequence can fit takt time and still be a bad job.

Where software helps

The table is quick to draw once you have the times. Getting the times is the slow part. With LeanSuite's Time and Motion Study you film the cycle and the AI drafts the element times on a timeline that links back to the video, for you to check and certify. The combination table itself is a free LeanSuite template: download the standard work combination table and fill it in from the study.

Standardized work software

Keep standard work current in LeanSuite

LeanSuite covers most of the cycle in one platform: working out the standard with Vision AI, keeping it current with SOPs and work instructions, and training and auditing it.

FAQ

Questions about standard work combination table

  1. It is a sheet that lists one operator's work elements in order and draws each on a time line: a solid bar for manual work, a dashed line for a machine running alone and a wavy line for walking, with a vertical line at takt time. It shows whether one person can do the whole sequence inside takt time.

  2. List the elements in sequence with manual, machine and walking time for each. Draw the takt line. Start row 1 at zero with a bar for manual time, then a dashed line for machine time and a wavy line for the walk. Start each next row where the last walk ended. Add manual and walking time and compare the total with takt time.

  3. A solid bar or line is manual work. A dashed line is a machine running with nobody at it. A wavy line is walking. A box or double-headed arrow is waiting. A vertical line, usually red, marks takt time. The operator's manual work and walking must end at or before the takt line.

  4. The job as drawn cannot keep up with demand, and the cell falls further behind on every piece. Look for the longest walk and any waiting first, since those are the cheapest to remove. Then look at the manual elements. If it still does not fit, part of the work has to move to another operator.

  5. Draw the dashed line to the takt line, then continue it from zero on the same row for the time that is left. A test started at 44 seconds that runs 45 seconds, on a 60 second cycle, ends 29 seconds into the next cycle. It is fine as long as it ends before the operator returns to that machine.

  6. A combination table follows one operator through time and shows machines running alongside. A yamazumi chart, or operator balance chart, stacks each operator's work into a bar so several operators can be compared against takt time. The Lean Lexicon calls the combination table the more precise of the two. Use the yamazumi to share work out and the table to design each person's cycle.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.