Skip to content
LeanSuite

Designing a future workstation from a time study

Short answer

Take the element log from a time study, strike out the walking, reaching and holding, and redraw the station so those elements cannot happen. Check the new work content against takt, build it in cardboard, time real cycles on the mock-up, check reach and posture, then build.

A time study tells you where the seconds go. A future workstation is designed by deciding, element by element, which of those seconds should not exist. Classify every element as value-added, necessary or waste. Use ECRS (eliminate, combine, rearrange, simplify) to design each loss out, and write the time you expect for what remains. Compare the new total with takt to decide what work the station should hold. Then build a full-size mock-up from cardboard and tape, run and time at least ten cycles with the operators, check reach and posture, fix what the trial shows, and only then order benches and fixtures. In the example here, one assembly station goes from 58 seconds and 11.8 metres of walking a cycle to 40 seconds and none, while taking on a 5 second task from its neighbour.

Last reviewed:

Why design the station on paper first

From a time study to a station you can build

Example numbers
  1. 1Study

    Start from the element log

    Ten cycles on video, one row for each element
  2. 2Study

    Classify every element

    Value-added, necessary or waste
  3. 3Paper

    Remove the losses on paper

    A layout change and an expected time for each loss
  4. 4Paper

    Decide the station's contents from takt

    Paper cycle against takt: move work in or out
  5. 5Cardboard

    Draw the layout and build it in cardboard

    Full size, with the real parts and tools
  6. 6Cardboard

    Run the mock-up and time it again

    Ten cycles each, compared with paper
  7. 7Cardboard

    Check reach and posture

    Reach, height and the worst posture
  8. 8Build

    Sign off, build, and study it again

    Every function signs the layout drawing

Steps 5 to 7 repeat until the mock-up meets takt and passes the posture check.

Time study, today58.0 s13 elements
Paper design38.5 sLosses removed, label task added
Mock-up, timed40.0 sMean of ten cycles
Takt time45.0 sPlanned load 40.5 s
Paper is cheap and a little optimistic, cardboard is nearly as cheap and honest. In the example the study measures 58.0 s, the paper design says 38.5 s and the timed mock-up says 40.0 s, against a takt of 45.0 s.

Most workstations are never designed. A bench is bought, parts arrive in whatever container the supplier uses, a tool gets hung where there was a hook, and the operator works out a method around what is there. A time study of that station measures the result. It does not have to be the end of the story.

The same study is a design brief. Every element in the log has a time and a cause, and most of the causes are things about the layout: a bin too far away, a tool shared with the next bench, a part delivered on the floor. Change those on paper and you can add up a new cycle before spending anything. Then test the paper with cardboard, because paper is always a little optimistic.

The order matters. Changing a drawing costs minutes. Changing a mock-up costs an hour and a roll of tape. Changing a welded bench with air lines and a fixture bolted to it costs weeks, so it rarely happens, and the station stays wrong. This guide follows one station from the study to sign-off. The design principles behind each choice are in the workstation design guide.

The method in eight steps

Plan on two or three working days for one station: half a day with the video and the log, half a day on the paper design, a day on the mock-up and trials. Do it with the operators and the team leader in the room, not for them.

  1. 1

    Start from the element log

    Film at least ten cycles and break one cycle into elements with a time for each. If you have no study yet, how to conduct a time study covers it. Add two columns the stopwatch does not give you: distance walked and where the hand had to go.

  2. 2

    Classify every element

    Mark each element as value-added (it changes the product in a way the customer pays for), necessary (it adds no value but the job cannot be done without it today) or waste. Be strict: walking, reaching, searching, holding, turning the part over and waiting are waste, however normal they look.

  3. 3

    Remove the losses on paper

    Take each waste and necessary element through ECRS: can it be eliminated, combined with another, rearranged in the sequence or simplified? Write the layout change that makes it possible and the time you expect afterward. Leave the value-added times alone unless the method itself changes.

  4. 4

    Decide the station's contents from takt

    Add up the paper cycle and compare it with takt time. If the station is now well under takt, pull work in from an overloaded neighbour. If it is still over, move work out or split the station. Settle this before you draw the bench, because the contents decide which parts and tools need space.

  5. 5

    Draw the layout and build it in cardboard

    Draw the bench top to scale with the reach arcs on it, then build it full size from cardboard, tape, real bins and the real parts. Set the height with blocks or pallets. Hang the real tool from a string if there is no balancer yet.

  6. 6

    Run the mock-up and time it again

    Have two or three operators each run the job on the mock-up until it feels routine, then time at least ten cycles. Compare each element with its paper time. Where the mock-up is slower, find out why and change the cardboard, not the stopwatch.

  7. 7

    Check reach and posture

    Measure every pick point from the shoulder and compare it with the reach of your smallest operator. Check the height of the work against each operator's elbow. Score the worst posture that is left with REBA or RULA and compare it with the score before.

  8. 8

    Sign off, build, and study it again

    Walk the mock-up with production, maintenance, quality, safety and materials, and get each to sign the layout drawing. Build it. In the first week of running, repeat the time study and update the standard work to match.

Steps 5 to 7 are a loop. Expect to go round it two or three times in a day, and count that as the method working.

Step 1 and 2 on a real log: where the 58 seconds go

Illustrative example. Station 3 on a pump line fits a gasket and a cover to a 3 kg housing with four screws. The line has 27,000 seconds of working time a shift and customers take 600 pumps, so takt is 27,000 / 600 = 45 seconds. The time study gives station 3 a cycle of 58 seconds, which is why it runs overtime. Here is one cycle from the video, averaged over ten.

Illustrative: the element log for station 3 before the redesign
#ElementTime (s)ClassWalking (m)Motions
1Walk to the rack, bend, take a housing from the floor tote6.0Waste3.05
2Set the housing on the bench and hold it2.0Necessary02
3Reach for a gasket3.0Waste03
4Fit the gasket4.0Value-added02
5Reach for a cover3.0Waste03
6Position the cover3.0Value-added02
7Pick four screws, one at a time8.0Waste012
8Start the four screws by hand6.0Value-added04
9Fetch the driver from the shared hook4.0Waste2.43
10Drive the four screws8.0Value-added04
11Take the driver back3.0Waste2.43
12Inspect and wipe3.0Necessary02
13Carry the unit to the outbound cart5.0Waste4.04
Total58.011.849

Motions are counted from the video: each reach, grasp, move, position or release of a hand, and each walk, counts as one. Value-added 21.0 s (36%), necessary 5.0 s (9%), waste 32.0 s (55%).

One cycle at station 3: 58.0 seconds, element by element

Example numbers
0 sElement numbers as in the table58.0 s
21.0 sValue-added, 36%: fit, position, start, drive
5.0 sNecessary, 9%: hold, inspect and wipe
32.0 sWaste, 55%: walk, bend, reach, fetch, carry

A strip of one 58.0 second cycle split into 13 elements. Value-added work is 21.0 seconds (36 percent), necessary work 5.0 seconds (9 percent) and waste 32.0 seconds (55 percent).

Only the dark segments change the product. Every yellow segment is caused by where something was put: 7 elements, 32.0 of the 58.0 seconds.

Read it as a designer. Only 21 of the 58 seconds change the product. The other 37 are the layout talking: a tote on the floor behind the operator, three bins at the back of the bench, one driver shared between two stations and a cart two metres away. At 600 units a shift the walking alone comes to 11.8 x 600 = 7,080 metres, about 7 kilometres a shift for one person who never leaves the station.

Step 3: remove the losses on paper

Go down the log one loss at a time and ask the four ECRS questions in order. Eliminate comes first because an element that no longer exists needs no bin, no fixture and no training. For each loss, write the change to the station and the time you expect once it is made. Take the expected times from somewhere real: a similar motion elsewhere in the same video, a quick trial at a spare bench, or a predetermined time system if your plant uses one.

Illustrative: each loss at station 3, the change that removes it and the time expected on paper
Loss in the logECRSChange to the stationBefore (s)Paper (s)
Walk, bend and take a housing from a floor toteSimplifyGravity flow rack at the left of the bench, pick point at waist height6.01.5
Left hand holds the housingEliminateA nest fixture holds it; the element becomes seating the housing2.01.5
Two separate long reaches for gasket and coverCombineBoth bins inside the forearm sweep, one each side, picked together with two hands6.02.0
Four trips to a far bin for screwsSimplifyShallow screw tray in front of the fixture; four taken in one grasp8.02.0
Fetch and return a shared driverEliminateThe station gets its own driver on a balancer above the fixture7.01.5
Carry the finished unit to a cartEliminateA chute at bench height to the next station5.01.0
Inspect and wipeKeepNo change3.03.0
Four value-added elementsKeepNo change to the method21.021.0
Total58.033.5

The paper total is a forecast. It becomes a number you can plan with only after the mock-up has been timed.

Station 3 from above, before and after

Example numbers
BeforeBins at the back, three walks
Station 3 before, top viewThree bins beyond the reach arcs and three dashed walking routes to a floor tote, a shared driver and an outbound cart.Gasket 70 cmScrews 60 cmCover 65 cmHand holds the partFloor totewalk 3.0 mShared driverwalk 4.8 mOutbound cartwalk 4.0 m
Walking a cycle11.8 m
Longest reach70 cm
Motions a cycle49
Items in the normal area0 of 6
AfterEverything inside the forearm sweep
Station 3 after, top viewA flow rack, two bins, a screw tray, a hanging driver, a label dispenser and a chute, all inside the inner reach arcs.RackLabelDriverScrewsGasketCoverChuteNo walkingSupply, tool and exit are all at the bench
Walking a cycle0 m
Longest reach40 cm
Motions a cycle27
Items in the normal area7 of 7

Two top views at the same scale. Before: the gasket, cover and screw bins sit 60 to 70 centimetres from the shoulder, outside the maximum working area, and the housing tote, the shared driver and the outbound cart each need a walk, 11.8 metres a cycle in total. After: a flow rack, both bins, the screw tray, the driver, a label dispenser and a chute all sit within 40 centimetres, inside the normal working area, with no walking.

Same bench, same operator, same arcs (400 mm and 555 mm). Before, nothing the job needs is inside the pale zone. After, everything is, and the three walks are gone. Yellow is the fixture at the work point.

Notice what was not done. Nobody asked the operator to fit the gasket faster. The four value-added elements keep their 21 seconds, and all 24.5 seconds of saving come from things the layout used to force on her. That is the argument to make on the floor when people hear the words time study and expect a speed-up.

Notice also that each change is a design requirement with a dimension attached. The flow rack has to put the housing inside the normal working area. The two bins have to sit at equal distances so the hands arrive together. The balancer has to hang where it does not hit the rack. Those details are what the mock-up is for.

Step 4: decide what the station holds from takt

A redesigned station is rarely the right size by accident. Before drawing the bench, compare the paper cycle with takt and decide what work belongs here. The Lean Enterprise Institute's Lean Lexicon describes the aim for each operator as work very nearly equal to takt time but slightly less. How much less is a plant decision. This line plans each station at no more than 90 percent of takt, to leave room for small stops.

Illustrative: sizing station 3 against takt
StepWorkingResult
Takt time27,000 s / 600 units45.0 s
Planned load, 90% of takt45.0 x 0.9040.5 s
Station 3 todayFrom the time study58.0 s, 13.0 s over takt
Station 3 on paperFrom the table above33.5 s
Room under the planned load40.5 minus 33.57.0 s
Work moved inApply the label, from station 45.0 s
Station 3 paper design33.5 + 5.038.5 s

Station 4 is over takt today. Moving its 5 second label task here is line balancing done at the design stage.

Sizing the station against takt, on paper

Example numbers
Station 3 cycle time against taktTime study, today: 58.0 seconds. On paper, losses removed: 33.5 seconds. Paper, plus the label task: 38.5 seconds. Takt 45.0 seconds, planned load 40.5 seconds.Planned load 40.5 sTakt 45.0 sTime study, today58.0 sOn paper, losses removed33.5 sPaper, plus the label task38.5 s015304560 s

Three bars against a takt of 45.0 seconds and a planned load of 40.5 seconds: the time study at 58.0 seconds, the paper design at 33.5 seconds, and the paper design with the label task at 38.5 seconds.

With the losses removed the station would sit 7.0 s under its planned load, so it takes the 5 s label task from station 4 and lands at 38.5 s.

Without this step the team would have built a 33.5 second station on a 45 second line and left 11.5 seconds of every cycle idle, while station 4 stayed overloaded. With it, the label dispenser goes on the layout drawing now, not as a bracket added later. If you are changing several stations at once, do this for the whole line with a yamazumi chart, as the line balancing guide shows.

Steps 5 and 6: mock it up in cardboard and time it again

The cardboard mock-up comes from 3P, the production preparation process. In the Lean Lexicon's description, a cross-functional team develops several alternatives for each process step, judges them against lean criteria, and mocks up the process with simple materials to test it before any equipment is ordered. 3P is normally used for a new product or a whole new line, over several days, and practitioners often ask for as many as seven alternatives for each step. For one existing station you are borrowing its central habit: try the design at full size, with real people, while it is still cheap to be wrong.

  • Build at full size. A scale model shows flow. Only full size shows reach, height and whether a gloved hand fits the bin.
  • Use the real parts, the real containers and the real tool. Their sizes and weights are what the layout has to cope with.
  • Set the work height with blocks, pallets or an adjustable table, and mark it once it feels right for the shortest and tallest operator.
  • Tape the reach arcs on the surface before placing anything, then place every-cycle items inside the inner arc.
  • Keep a knife and tape at hand. If moving a bin takes more than a minute, people stop suggesting moves.
  • Let the operators run it and change it. Their second idea is usually better than the engineer's first.
  • Time it only once the motion is routine, and time at least ten cycles for each person.

At station 3 the first trials find three things the paper missed. The flange of the housing catches on the lip of the flow rack, so the lane is widened and the pick still takes a little longer than planned. Picking a gasket and a cover at the same moment is slower than two confident single picks until the bins are tilted toward the hands. And the label needs a second press at one corner. The driver, the chute and the screw tray work as drawn.

Illustrative: station 3 as designed, paper times against the mock-up (mean of ten cycles)
#ElementClassPaper (s)Mock-up (s)Motions
1Take a housing from the flow rackNecessary1.52.02
2Seat it in the fixtureNecessary1.51.51
3Pick gasket and cover, one in each handNecessary2.02.52
4Fit the gasketValue-added4.04.02
5Position the coverValue-added3.03.02
6Take four screws in one graspNecessary2.02.02
7Start the four screws by handValue-added6.06.04
8Pull down the driver on its balancerNecessary1.01.01
9Drive the four screwsValue-added8.08.04
10Release the driverNecessary0.50.51
11Inspect and wipeNecessary3.03.02
12Apply the label (moved from station 4)Value-added5.05.53
13Slide the unit down the chuteNecessary1.01.01
Total38.540.027

Value-added 26.5 s (66%), necessary 13.5 s (34%), waste 0 s. No walking. The mock-up is 1.5 s slower than paper and 0.5 s inside the 40.5 s planned load.

Paper against the mock-up

Example numbers
Station 3 cycle time against taktTime study, today: 58.0 seconds. On paper, losses removed: 33.5 seconds. Paper, plus the label task: 38.5 seconds. Mock-up, timed over ten cycles: 40.0 seconds. Takt 45.0 seconds, planned load 40.5 seconds.Planned load 40.5 sTakt 45.0 sTime study, today58.0 sOn paper, losses removed33.5 sPaper, plus the label task38.5 sMock-up, timed over ten cycles40.0 s015304560 s

Four bars against a takt of 45.0 seconds and a planned load of 40.5 seconds: the time study at 58.0 seconds, the paper design at 33.5 and 38.5 seconds, and the timed mock-up at 40.0 seconds.

The mock-up runs 1.5 s slower than paper and still 0.5 s inside the planned load. Had the team built from the paper number alone, they would have had no warning of how thin that margin is.

The mock-up time is the one to plan with. It is a trial on cardboard by people who have done the new method for an hour, so it is still not a standard time. Set that from a fresh study once the real station has run for a week, with the usual rating and allowances.

Some plants run a digital simulation before or in place of the cardboard: a quick human model placed in a 3D layout to check walk paths, heights and reach. It is useful for a first screen of many stations and for equipment too large to mock up. Its weakness is the same as paper's. Review every simulation with the people who do the job, and still let them try the critical stations with their own hands.

Step 7: the ergonomic check

A faster station that hurts people is a failed design, and the mock-up is the cheapest moment to find out. Check three things: reach, height and the worst posture left in the cycle. For reach, measure each pick point on the layout from the point under the shoulder that reaches for it, and compare it with the arm lengths of your smallest operator. The team here uses the 5th percentile figures for women in Bodyspace: 40 cm for the normal working area and 55.5 cm for the maximum.

Illustrative: where the hand has to go at station 3, before and after
ItemBeforeAfter (mock-up)
HousingFloor tote behind the operator: a walk and a bend38 cm, at waist height
Gasket bin70 cm30 cm
Cover bin65 cm30 cm
Screws60 cm, four trips25 cm, one trip
DriverShared hook 1.2 m away: a walk35 cm, on a balancer
Label dispenserNot at this station35 cm
OutboundCart 2 m away: a walk40 cm, to the chute

Before: three items needed a walk and the other three sat beyond the 55.5 cm maximum reach of a small operator, so every one of them meant a lean. After: all seven are within 40 cm.

The reach check: every pick point against the two limits

Example numbers
Pick point distances before and afterDots on a distance scale with the normal and maximum reach limits marked.NormalMaximumLeanBeforeplus 3 walksAfter0204055.580 cmDistance from the point under the shoulder

A scale from 0 to 80 centimetres from the shoulder. The normal working area ends at 40 centimetres and the maximum at 55.5. Before, the three bench items sit at 70, 65, 60 centimetres, beyond the maximum, and 3 more items need a walk. After, all 7 items sit between 25 and 40 centimetres.

Limits are for a small operator: 40 cm normal, 55.5 cm maximum. Before, each of the three bins on the bench meant a lean. After, the farthest item is the chute at 40 cm.

For posture, score the worst moment before and after with the same method. Before, that moment was the grip on a housing in the floor tote: trunk bent more than 60 degrees, neck tipped back, arms reaching forward. With REBA that scores 7, the top of the medium band. After, the worst posture is a slight forward lean over the fixture with the head down while driving screws, which scores 3, low. The ergonomic assessment guide shows how those scores are built, and when the job needs a different method such as the NIOSH lifting equation.

Check the height with the people, not the average. The work sits 5 to 10 cm below standing elbow height for light assembly. If the tallest and shortest operators cannot both get there, the bench needs to adjust, and that goes on the drawing before sign-off.

Step 8: sign-off

Sign-off is a walk through the mock-up, not a meeting about it. Each function looks for the thing only it will notice, and signs the layout drawing when it is satisfied.

  • Operators from every shift: can I run it at pace, and what still annoys me?
  • Team leader: can a new person learn it, and can I see from the aisle whether it is running to standard?
  • Materials: can the rack and bins be refilled from outside the station, in the containers we really receive?
  • Maintenance: can I reach the fixture, the driver and the air supply to service them?
  • Quality: are look-alike parts separated, and is the inspection point lit and in view?
  • Safety: reach, height and posture checked, no trip points from platforms or hoses, nothing stored above shoulder height.
  • Industrial engineering: mock-up time recorded against takt, work content agreed with the neighbouring stations, drawing dimensioned.

Keep the sign-off sheet with the drawing, the mock-up timings and a photo of the cardboard. When someone asks in a year why the bin is where it is, that is the answer.

Before and after

Here is station 3 on the measures that were written down at the start, with the before column from the time study and the after column from the timed mock-up.

Illustrative: station 3 before the redesign and on the timed mock-up
MeasureBeforeAfterChange
Cycle time58.0 s40.0 s18.0 s less, with the label task added
Against a 45 s takt13.0 s over5.0 s underInside the 40.5 s planned load
Walking in one cycle11.8 m0 mAbout 7 km a shift removed
Motions in one cycle492722 fewer
Longest reach70 cm40 cmEvery item inside the normal working area
Value-added share of the cycle36%66%21.0 s of 58.0, then 26.5 s of 40.0
Worst posture, REBA7 (medium)3 (low)No bend to the floor
Units in a 27,000 s shift465675Demand is 600

Like for like, without the label task, the mock-up cycle is 34.5 s against 58.0 s.

Station 3, before and after

Example numbers

Cycle time, with the label task added

Before
58.0 s
After
40.0 s

Takt is 45.0 s

Walking in one cycle

Before
11.8 m
After
0 m

About 7 km a shift removed

Motions in one cycle

Before
49
After
27

Counted from the video

Longest reach

Before
70 cm
After
40 cm

Normal working area ends at 40 cm

Worst posture, REBA score

Before
7 (medium)
After
3 (low)

Medium band to low band

465 units a shift before, 675 afterDemand is 600. The station stops needing overtime and takes 5 s of work off its neighbour.
Four of the five bars shrink because the layout changed, not because anyone worked faster. The four value-added elements take 21.0 s in both columns.

The before column explains the overtime: 27,000 / 58 gives 465 units, 135 short of demand. The after column meets demand with room to spare, takes five seconds of work off station 4, and has cost some cardboard and two days. Whatever the final bench, rack, fixture and balancer cost, the team now knows what they are buying and what it will return.

Common mistakes and limits

  • Trusting the paper. Paper times are forecasts. At station 3 the mock-up was 1.5 seconds slower, and on a tight line that is the difference between meeting takt and missing it.
  • Designing from one cycle. One cycle hides the part that jams every tenth time. Use the average of ten or more and ask what happened in the slow ones.
  • Cutting value-added time first. It is the hardest time to remove and the first thing operators fear. Take out the waste and leave the craft alone.
  • Improving the station and ignoring the line. If the next station cannot take the output, the saving turns into a pile of stock or idle time.
  • Mocking up at scale, or with stand-in parts. Reach and height problems only show at full size with the real container.
  • Leaving the operators out until the unveiling. They know the variants, the bad batches and the reason the last change was undone.
  • Skipping the posture check because the cycle is shorter. A faster cycle repeats every motion more often in a shift.
  • Treating the mock-up time as the standard. Set the standard from a study of the real station, at a normal pace, with allowances.

The method has edges. It suits manual and semi-manual stations with a repeating cycle. Where a machine sets the cycle, the gain is in loading, unloading and what the operator does while the machine runs. Where the work is long and varied, such as maintenance or one-off builds, a mock-up of one station says little, and work sampling or a spaghetti diagram of the whole area is a better start. And cardboard cannot tell you whether a process is capable: torque, fit and cleanliness still need a real trial.

Tools and related guides

LeanSuite's time and motion study builds the element log from a phone video, splits it into value-added, necessary and waste, and ranks ECRS findings by the seconds they recover. Film the mock-up the same way and you have the before and after from one tool. You review and certify every study.

FAQ

Questions about designing a future workstation

  1. Break the cycle into elements and mark each as value-added, necessary or waste. For every waste element, write the layout change that removes it and the time you expect afterward. Add up the new cycle, compare it with takt and adjust the work content. Then build the layout full size in cardboard, time ten or more cycles on it, check reach and posture, and fix what the trial shows before building.

  2. A cardboard mock-up is a full-size, throwaway model of a workstation or cell built from cardboard, tape and the real parts and tools. Operators run the job on it so that reach, height, sequence and timing can be tested and changed in minutes. It comes from 3P, the production preparation process, and is sometimes called a cardboard city when a whole line is modelled.

  3. 3P stands for production preparation process. A cross-functional team designs the production process for a new product, or redesigns one from scratch, by developing several alternatives for each step, judging them against criteria such as takt time and cost, and testing the best with simple full-size mock-ups before any equipment is ordered. It is usually run as an event of several days.

  4. Eliminate, combine, rearrange, simplify. It is the order of questions to ask about each element of a job: can it be removed altogether, joined with another element, moved to a better place in the sequence, or made easier? Eliminate comes first because an element that no longer exists needs no tooling, space or training.

  5. Slightly under it. The Lean Enterprise Institute's Lean Lexicon describes the aim as work for each operator very nearly equal to takt time but slightly less. How much less is a plant decision that depends on how often small stops happen. The example in this guide plans each station at no more than 90 percent of takt, which is that line's own rule, not a standard.

  6. No. A mock-up time is a trial by people who learned the new method an hour ago, on cardboard, usually without a full shift of fatigue or real material problems. Use it to decide whether the design meets takt. Set the standard time from a new time study of the real station after it has run for about a week, with rating and allowances.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.