Practical guide · Value stream mapping and flow
SMED: how to cut changeover time with a study from video
Short answer
SMED, single-minute exchange of die, is a method for cutting changeover time. You film a changeover, list every task, move the tasks that do not need the machine stopped to before or after the stop, then shorten what is left. The aim is a changeover under 10 minutes.
SMED stands for single-minute exchange of die. It cuts changeover time, measured from the last good part of one product to the first good part of the next, in three stages. Separate internal work (needs the machine stopped) from external work (can be done while it runs). Convert internal work to external where you can. Streamline everything that remains with quick clamps, presets and people working in parallel. Single-minute means a single digit number of minutes, so under 10. In the worked example on this page a 90 minute mold change drops to 38.
Last reviewed:
What is SMED?
SMED in one picture: the same mold change before and after
Example numbers90 min
Press stopped today, last good part to first good part
38 min
Press stopped after one round of SMED
58% less
52 minutes back on every changeover
Before: every task done with the press stopped
After: only internal work inside the stop
- Internal: needs the press stopped
- External: fetching, finding, clearing up
- Waiting for the mold to heat, now done on a cart beforehand
- Press running product A, then B
Two timelines on the same scale. Before: the press is stopped for 90 minutes while all 12 tasks are done in order. After: the press is stopped for 38 minutes for seven internal tasks. Tasks 1 and 2 and the mold preheat are done before the stop while the old product still runs, and tasks 5 and 8 after the restart. The press runs the new product for the 52 minutes it used to stand still.
SMED stands for single-minute exchange of die. It is a method for shortening the time a machine or line is stopped to change from one product to the next. The name comes from stamping presses, where the die is the tool that gets exchanged, but the method applies to any changeover: a mold, a filler format, a print job, a CNC fixture, an operating theatre between patients.
Single-minute does not mean one minute. It means a single digit number of minutes: under 10. Few plants get there on the first pass, and they do not have to. Halving a changeover is already worth a great deal.
The method rests on one observation. Much of what happens during a changeover does not need the machine to be stopped. Fetching the next tool, finding the wrench, warming the mold and filling in the paperwork can all happen while the machine is still making parts. SMED finds that work and moves it. Then it shortens what is left.
How changeover time is measured
Changeover time runs from the last good part of the old product to the first good part of the new one. That is the Lean Enterprise Institute's definition, and the two words that matter are good and first. The clock does not stop when the new tool is bolted in. It stops when the machine makes a part you can ship. Trial shots, adjustments and waiting for approval are all inside the changeover. Many plants go one step further and run the clock until the machine is back at normal speed, because a slow run-up is lost output too. Pick one definition and write it at the top of the study.
Where the changeover clock starts and stops
Example numbers- 0:00Last good part of product A. The clock starts.
- 0:52New mold clamped and connected. Many plants stop the clock here.
- 1:30First approved part of product B. The clock stops.
A timeline of the mold change. The clock starts at the last good part of the old job, 0:00. The new mold is clamped and connected at 0:52. The first approved part of the new job comes at 1:30. Changeover time is the whole 90 minutes, not the 52 minutes to tool in.
Where SMED came from: Shigeo Shingo
The name and the written method come from Shigeo Shingo, a Japanese industrial engineer who taught and consulted for Toyota and its suppliers. His book A Revolution in Manufacturing: The SMED System was published in English in 1985.
By Shingo's own account the idea arrived in three episodes. In 1950, at Toyo Kogyo (now Mazda), he watched a large press stand idle while someone hunted for a missing bolt, and saw that setup work comes in two kinds: work that needs the machine stopped and work that does not. In 1957, at a Mitsubishi Heavy Industries shipyard, he had a second table built for a planer so the next engine bed could be set up while the machine was still cutting. In 1969, at Toyota, he says a 1,000 ton press that took four hours to change was brought down to 90 minutes and then, after a challenge from management, to three minutes.
Read the story with some care. People who worked at Toyota have said that Taiichi Ohno's teams were shortening die changes through the 1950s and 1960s, and that Shingo recorded and generalized the practice more than he invented it. The detail does not change the method. The stages below are the ones in his book, and they are what plants use today.
Internal vs external setup
Every task in a changeover is one of two kinds. Internal work can only be done with the machine stopped. External work can be done while the machine is running, before the stop or after the restart. The whole method turns on sorting tasks into these two piles honestly.
| Internal | External | |
|---|---|---|
| Definition | Can only be done with the machine stopped | Can be done while the machine runs |
| When it should happen | During the stop, and nowhere else | Before the stop or after the restart |
| Examples | Unclamp and remove the old tool, mount and clamp the new one, connect services, first trial part | Fetch the next tool, collect hand tools and fasteners, bring material, preheat, print labels, return the old tool, paperwork |
| The test | Would doing this with the machine running be unsafe or impossible? | Could someone do this while the last parts of the old run are still coming off? |
| What SMED does with it | Shortens it | Moves it out of the stop, then shortens it too |
A third pile turns up on every video: work that is not needed at all, such as walking back for a forgotten tool or adjusting something that was already right. Remove it.
Shingo's book gives his own estimate of where the time goes in a traditional setup: about 30 percent on preparation, checking materials and tools, and clearing up afterwards; about 5 percent on actually removing and mounting the tooling; about 15 percent on centring, measuring and setting; and about 50 percent on trial runs and adjustments. Those are his figures, not a law, and your video will give you your own. The pattern is the useful part. The exchange itself is the smallest slice. Preparation and adjustment are where the minutes are.
Where setup time goes: Shingo's estimate and one filmed changeover
Example numbersShingo's estimate of a traditional setup
Prep 30% · Swap 5% · Set 15% · Trials 50%
The 90 minute mold change on this page
Prep 23% · Swap 39% · Set 6% · Trials 32%
- Prep: preparation, checking and clearing up
- Swap: removing and mounting the tooling
- Set: centring, measuring and setting
- Trials: trial runs and adjustments, with waiting
Shingo's estimate of a traditional setup: Preparation, checking and clearing up 30 percent, Removing and mounting the tooling 5 percent, Centring, measuring and setting 15 percent, Trial runs and adjustments, with waiting 50 percent. The filmed mold change on this page: Preparation, checking and clearing up 23 percent, 21 minutes; Removing and mounting the tooling 39 percent, 35 minutes; Centring, measuring and setting 6 percent, 5 minutes; Trial runs and adjustments, with waiting 32 percent, 29 minutes.
The stages of SMED
Shingo describes a starting condition and three stages. Most plants add a fourth step, standardize, because a faster changeover that only one setter can do is not a result yet.
| Stage | What you do | How | What it costs |
|---|---|---|---|
| Preliminary: not separated | Internal and external work are mixed together inside the stop | Film the changeover as it is done today. This is the baseline. | A camera and two hours |
| 1. Separate | Take external work out of the stop | A pre-changeover checklist, a stocked tool cart, the next tool staged at the machine, the old one taken away after restart | Almost nothing: it is organization |
| 2. Convert | Turn internal work into external work | Preheat tooling off the machine, preset tools and gauges on a bench, duplicate fixtures, standard heights so no shimming is needed | Some: carts, a preheat station, a second fixture |
| 3. Streamline | Shorten every task that remains, internal first | One-turn and quick-release clamps, quick couplers, locating pins and stops, two people working in parallel, settings saved so adjustment goes away | Most: hardware and engineering time |
| 4. Standardize | Make the new way the normal way | A written sequence with times and who does what, a checklist, training on every shift, a second film to confirm | Time and discipline |
Work through them in order. Stage 1 is nearly free and usually the largest single gain, so buying quick clamps before the tool cart exists spends money in the wrong order.
The stages as a ladder: what moves, what disappears, what shrinks
Step 1: Film the changeover
From the last good part of the old product to the first good part of the new one.
The machine stops for 18 blocks; the activities inside the stop are not yet sorted.
Step 2: Label every activity
I needs the machine stopped. E could be done while it runs. U adds nothing.
The machine stops for 18 blocks: 9 internal, 6 external, 3 unnecessary.
Step 3: Move external work before the stop
Do it while the old product still runs. Strike out the unnecessary.
The machine stops for 9 blocks: 9 internal. 6 blocks of external work run before the stop, while the machine is still producing. 3 blocks of unnecessary work are removed.
Step 4: Shorten what is left
Internal work first: quick clamps, presets, two people to a written split.
The machine stops for 6 blocks: 6 internal. 4 blocks of external work run before the stop, while the machine is still producing.
Step 5: Validate, standardize, expand
Check against the baseline, weigh benefit against cost, write the standard, take it to the next machine.
Machine-down time at each stage. Baseline: machine down 18 blocks, running alongside 0; After step 3: machine down 9 blocks, running alongside 6; After step 4: machine down 6 blocks, running alongside 4; Standard: machine down 6 blocks, running alongside 4.
- Production
- Internal: machine stopped
- External: machine can run
- Unnecessary
- Removed
- Blocks are illustrative units, not minutes.
How to run a changeover study from video
The video is what makes SMED work. People who do a changeover every week cannot see the waiting and the walking in it, and nobody remembers a 90 minute job in enough detail to argue about. A film settles it. Plan on one changeover filmed, half a day to analyse it with the crew and a second changeover to prove the new sequence.
A changeover study from the first film to the second
- 1
Pick the changeover and brief the crew
- 2
Film from the last good part to the first good part
- 3
List every element with start and stop times
- 4
Classify each element
- 5
Move the external work out of the stop
- 6
Convert internal work to external
- 7
Streamline what is left
- 8
Write the standard and film it again
- 1
Pick the changeover and brief the crew
Choose a machine where changeover time limits output or forces big batches, and a changeover that is typical, not the hardest one. Tell the setters and operators why you are filming: the method is on trial, not the people. Ask them to do it exactly as they normally do.
- 2
Film from the last good part to the first good part
Start the camera before the last good part of the old run and do not stop it until the first good part of the new one. Follow the person, not the machine, because the lost time is in the walking. Use one camera per person if two people work. Keep a clock or the phone's timestamp in view, and say out loud what is happening when it is not obvious.
- 3
List every element with start and stop times
Play the video back with the crew and write down each task as its own line: what was done, when it started, when it ended. Break at every change of activity: fetching, unbolting, lifting, waiting, adjusting. Record walking, searching and waiting as their own lines. Check that the lines add up to the total.
- 4
Classify each element
Mark every line internal, external or not needed. Then mark the internal lines that could become external with a change of equipment or method. The crew will argue about some. That argument is the study doing its job.
- 5
Move the external work out of the stop
Write a pre-changeover checklist of everything that must be at the machine before it stops: next tool, hand tools, fasteners, material, paperwork. Decide who does it and when. Put the clearing up after the restart.
- 6
Convert internal work to external
Take each line marked could be external and ask what would have to be true for it to happen while the machine runs. Typical answers are a preheat station, a presetting bench, a second set of fixtures, and standard tool heights.
- 7
Streamline what is left
Go down the remaining internal lines from longest to shortest. For each, look at clamping, positioning, connecting and adjusting, and ask whether a second person working in parallel would shorten it. Then give the external lines the same treatment.
- 8
Write the standard and film it again
Put the new sequence on one page with a time against each step and a name against each role. Train every shift. Film the next changeover and compare it with the baseline line by line. Keep going until the time is stable, then repeat the study from the new baseline.
A changeover involves energy sources, heavy tooling and people reaching into machines. Lockout and guarding steps are internal work by nature, and they are never the place to save time. If a study shows people skipping them, that is the first finding. See lockout tagout for how those steps are managed.
A worked SMED example: 90 minutes to 38
Illustrative example. An injection molding press changes molds 10 times a week. One setter does the change alone. The plant measures changeover from the last good part of the old job to the first approved part of the new one, and the filmed changeover took 90 minutes.
The element log from the video
The element log from the video: 12 tasks, 90 minutes
Example numbersTask 1: Collect tools, hoses and eye bolts from the crib0:00 to 0:04 · 4 min
ExternalTool cart stocked and parked at the press before the stopTask 2: Fetch the next mold from the rack0:04 to 0:12 · 8 min
ExternalMold staged at the press before the stopTask 3: Drain and disconnect water lines and ejector0:12 to 0:18 · 6 min
InternalQuick couplers on a manifold: 4 minTask 4: Unbolt eight clamps, lift the old mold out0:18 to 0:29 · 11 min
InternalOne-turn clamps and a second person on the far side: 7 minTask 5: Take the old mold to the rack0:29 to 0:34 · 5 min
ExternalDone after the restartTask 6: Lift in the new mold, centre it, bolt eight clamps0:34 to 0:46 · 12 min
InternalLocating ring, one-turn clamps and the second person: 8 minTask 7: Connect water lines and ejector0:46 to 0:52 · 6 min
InternalColour-coded quick couplers: 4 minTask 8: Put tools away, fill in the changeover sheet0:52 to 0:56 · 4 min
ExternalDone after the restartTask 9: Find the setup sheet, key in the settings0:56 to 1:01 · 5 min
InternalSettings saved as a recipe on the press: 2 minTask 10: Wait for the mold to reach temperature1:01 to 1:13 · 12 min
Internal, can be externalMold preheated on a cart before the stop: 0 minTask 11: Trial shots and adjustments1:13 to 1:25 · 12 min
InternalHot mold and saved settings mean fewer shots: 9 minTask 12: Wait for first-part approval1:25 to 1:30 · 5 min
InternalInspector called when trial shots start, gauge at the press: 4 min
Sorting the 90 minutes
| Pile | Elements | Minutes | Share |
|---|---|---|---|
| External work done with the press stopped | 1, 2, 5, 8 | 4 + 8 + 5 + 4 = 21 | 23% |
| Internal work that can become external | 10 | 12 | 13% |
| Internal work that has to stay internal | 3, 4, 6, 7, 9, 11, 12 | 6 + 11 + 12 + 6 + 5 + 12 + 5 = 57 | 63% |
| Total | All 12 | 90 | 100% |
Shares are rounded to the nearest whole percent, so they add to 99. A third of the stop, 33 of 90 minutes, did not need the press to be stopped.
Stage by stage
Stage by stage: 90 minutes stopped down to 38
Example numbersBaseline
Everything done with the press stopped
1. Separate
Elements 1 and 2 done before the stop, 5 and 8 after the restart
2. Convert
Mold preheated on a cart, so the wait in element 10 disappears
3. Streamline
Seven internal elements shortened: 2 + 4 + 4 + 2 + 3 + 3 + 1
4. Standardize
The 38 minute sequence written down, trained and filmed again
Bars of the time the press is stopped at each stage: Baseline, 90 minutes; 1. Separate, 69 minutes; 2. Convert, 57 minutes; 3. Streamline, 38 minutes; 4. Standardize, 38 minutes.
Every task on one clock: 90 minutes stopped, then 38
Example numbersBefore: every task done with the press stopped
After: only internal work inside the stop
- Internal: needs the press stopped
- External: fetching, finding, clearing up
- Waiting for the mold to heat, now done on a cart beforehand
- Press running product A, then B
Two timelines on the same scale. Before: the press is stopped for 90 minutes while all 12 tasks are done in order. After: the press is stopped for 38 minutes for seven internal tasks. Tasks 1 and 2 and the mold preheat are done before the stop while the old product still runs, and tasks 5 and 8 after the restart. The press runs the new product for the 52 minutes it used to stand still.
Two things in the result are worth a second look. First, the work did not shrink as much as the stop did. The 21 external minutes are still done. They are done while the press makes parts. Second, the second person on elements 4 and 6 cuts clock time, not labour: 7 minutes with two people is 14 labour minutes against 11 before. That trade is right when the press is the constraint and wrong when it is not, which is what the next section is about.
At 38 minutes this is not yet a single-minute changeover. The next round starts from the new video. Trial shots and approval are now 13 of the 38 minutes, so that is where it would look first.
Where the minutes come from: the techniques
Shingo lists eight techniques. The first two are stages 1 and 2. The other six are the toolbox for stage 3. Here they are as questions to ask of each line in the log.
- Pre-staging. Is everything the changeover needs at the machine, checked and in order of use, before the stop? A cart with a shadow board and a checklist does most of this.
- Function checks before the stop. Has the next tool been inspected and repaired since its last run? A changeover that discovers a damaged tool is a breakdown.
- Standard function, not standard shape. Can every tool present the same clamping height, the same locating point and the same connections, so nothing has to be shimmed or re-plumbed?
- Quick-release clamping. A bolt only holds on its last turn, and every turn before that is waste. One-turn clamps, slotted washers, cams, toggle clamps and hydraulic clamping remove it.
- Intermediate jigs. Can the part or tool be mounted on a standard plate away from the machine, so only the plate is exchanged?
- Parallel operations. On a large machine one person walks round it dozens of times. Two people with a written split of who does what, and a clear signal before anything moves, cut the walking out.
- No adjustment. Adjustment and trial runs are often half the stop. Fixed stops, scales with numbers, saved settings and presetting off the machine turn a judgement into a position.
- Mechanization, last. Powered clamps and tool carts with rollers help, but only after the free and cheap gains are in. Mechanizing a bad method makes it a fast bad method.
Stage 3, task by task: where 19 minutes came out
Example numbersDrain and disconnect water lines and ejectorQuick couplers on a manifold
6 to 4 min
Unbolt eight clamps, lift the old mold outOne-turn clamps and a second person on the far side
11 to 7 min
Lift in the new mold, centre it, bolt eight clampsLocating ring, one-turn clamps and the second person
12 to 8 min
Connect water lines and ejectorColour-coded quick couplers
6 to 4 min
Find the setup sheet, key in the settingsSettings saved as a recipe on the press
5 to 2 min
Trial shots and adjustmentsHot mold and saved settings mean fewer shots
12 to 9 min
Wait for first-part approvalInspector called when trial shots start, gauge at the press
5 to 4 min
Before and after for the seven internal tasks: Drain and disconnect water lines and ejector, 6 to 4 minutes, Quick couplers on a manifold; Unbolt eight clamps, lift the old mold out, 11 to 7 minutes, One-turn clamps and a second person on the far side; Lift in the new mold, centre it, bolt eight clamps, 12 to 8 minutes, Locating ring, one-turn clamps and the second person; Connect water lines and ejector, 6 to 4 minutes, Colour-coded quick couplers; Find the setup sheet, key in the settings, 5 to 2 minutes, Settings saved as a recipe on the press; Trial shots and adjustments, 12 to 9 minutes, Hot mold and saved settings mean fewer shots; Wait for first-part approval, 5 to 4 minutes, Inspector called when trial shots start, gauge at the press.
The gallery of 16 SMED examples shows these techniques on presses, molding machines, fillers and CNC machines, before and after.
What a changeover costs: the arithmetic
A changeover costs the output the machine did not make while it was stopped. Work it out before the project so you know what a minute is worth, and after it so you can say what you got.
Lost output per changeover = changeover minutes x parts per minute. Weekly changeover time = changeovers a week x changeover minutes.
| Step | Before | After |
|---|---|---|
| Rate of the press | 30 s cycle, 2 cavities: 4 parts a minute | 4 parts a minute |
| Changeover time | 90 min | 38 min |
| Output lost per changeover | 90 x 4 = 360 parts | 38 x 4 = 152 parts |
| Changeovers a week | 10 | 10 |
| Press stopped for changeovers | 10 x 90 = 900 min (15.0 h) | 10 x 38 = 380 min (6.3 h) |
| Share of 4,800 scheduled minutes | 18.8% | 7.9% |
| Time freed a week | 900 less 380 = 520 min (8.7 h) | |
| Parts that time can make | 520 x 4 = 2,080 parts |
The press is scheduled for two 8 hour shifts, five days a week: 2 x 480 x 5 = 4,800 minutes. Scrap from trial shots and the setter's labour come on top and are not counted here.
What ten changeovers a week cost, before and after
Example numbersBefore: stopped for changeovers 900 min (15.0 h), 18.8% of the week
After: stopped for changeovers 380 min (6.3 h), 7.9% of the week
Time freed a week = changeovers a week x minutes saved per changeover
Then multiply by the rate of the machine to turn minutes into parts.
- Saved per changeover =90 less 38= 52 min
- Freed a week =10 x 52= 520 min (8.7 h)
- As parts =520 x 4 parts a minute= 2,080 parts
- Or as changeovers =900 / 38= 23 in the time 10 took
Of 4,800 scheduled minutes a week, changeovers took 900 before and 380 after, freeing 520 minutes, which is 2,080 parts at 4 parts a minute.
Two ways to spend the time
The freed 520 minutes can be used in two ways, and it is a choice. If the press is the bottleneck and there are orders for the parts, run it: 2,080 more parts a week. At an example contribution of $1.50 a part, that is 2,080 x 1.50 = $3,120 a week. If the press is not the constraint, more parts are just more stock, and the money figure is zero.
The other way is to keep the changeover time where it was and change over more often. The 900 minutes that paid for 10 changeovers now pay for 900 / 38 = 23. Batches can be less than half the size, which means less finished stock, shorter lead times and a schedule that follows orders. This is the reason Toyota wanted quick changeovers in the first place: small lots, not more press hours. It is also what makes just-in-time and level scheduling possible.
The SMED changeover calculator runs these sums for your own machine, and the EPEI and batch size calculator turns a shorter changeover into a new batch size.
Mistakes that stall a SMED project
- Stopping the clock when the tool is in. The changeover ends at the first good part. Trial runs and approval are often the largest block, and this definition hides them.
- Working from memory. Without a video, the log is a list of what people think they do. The walking, the waiting and the second trip to the crib never make it onto paper.
- Buying hardware first. Quick clamps on a changeover that still starts with a search for the wrench save little. Stage 1 costs almost nothing and comes first.
- Studying a machine that is not a constraint and then counting the freed hours as money. If the output is not needed, the gain is smaller batches. Say so.
- Filming the best setter on the best day. The standard has to work for the night shift too. Film a normal one.
- Leaving the crew out of the analysis. They know why each step exists, and they are the ones who will have to do it the new way.
- Cutting a safety step. Lockout, guarding checks and lifting rules are not waste.
- No written standard. Six weeks later the time is back where it started, and nobody can say which step slipped.
- Declaring victory after one round. Each pass exposes the next layer. The second video usually has as much in it as the first.
- Not telling the planners. A 38 minute changeover scheduled in 90 minute blocks and run in the same batch sizes changes nothing.
Templates, tools and software for SMED
- SMED changeover worksheet: the element log with internal and external columns, ready to fill in from the video.
- Changeover checklist: the pre-changeover and changeover steps in order, for the new standard.
- Changeover matrix template: which product should follow which, so the sequence itself shortens the changeovers.
- SMED changeover calculator: time saved, capacity freed a week and the smaller batch it allows.
- Video time study filming checklist: camera position, what to keep in frame and what to tell the crew.
- SMED examples: 16 changeovers, before and after.
The log is the slow part of a study, and it is the part software can draft. In LeanSuite's SMED module you film one changeover on a phone and upload it. The AI marks each task internal or external, keeps the clip behind every call, flags tasks that can run in parallel and proposes a shorter sequence. Your team corrects the draft, and the agreed sequence becomes the checklist operators run at the machine, with a time logged against every step.
Go deeper
This page is the short version. These guides cover each part in full.
- The Best Strategies to Reduce Changeover Time in ManufacturingThe wider set of changeover strategies around the SMED study, including scheduling and sequencing.
- SMED in JIT Manufacturing: Single-Minute Exchange of DieWhy just-in-time depends on short changeovers and where SMED sits in the system.
- Heijunka in JIT: Leveling Mixed-Model ProductionUsing short changeovers to level the mix, so every product is made every day.
- One-Piece Flow in JIT: Eliminating Batch QueuesWhat smaller batches do to queues and lead time once changeovers allow them.
- Manufacturing Bottleneck Elimination: 5 Proven StrategiesDeciding whether the machine you are about to study is the constraint.
All our articles on this subject are in the value stream mapping and flow topic.
Free templates and tools
- SMED changeover worksheetChangeover steps with times, internal or external, what can move, ideas and before/after totals.
- Changeover checklist25 checks for every changeover, a record of planned and actual times, and a log of changeover time against target.
- Changeover matrix templateA from-to matrix of changeover minutes with the clean each transition needs (allergen, color, format), and a weekly planner that totals the order and suggests a shorter one.
- EPEI and batch size calculatorHow often each part can come round on a shared machine (EPEI) and how big each batch must be, from demand, cycle times and changeovers, now and after SMED.
- Video time study filming checklistA pre-shoot checklist and shot log for filming a time study on video: camera, light, people, settings, power and review.
- SMED changeover calculatorTime saved by moving changeover steps from internal to external, capacity freed per week and the smaller batch it allows.
- Downtime cost calculatorWhat an hour, an event and a year of unplanned downtime cost, from lost output, idle labour, scrap and overtime.
- OEE calculatorOverall equipment effectiveness from shift time, downtime, ideal cycle time and part counts.
Doing this in LeanSuite
SMED
Runs each changeover as a timed checklist, and AI splits a filmed changeover into internal and external tasks.
See SMEDAI Video Analysis
Turns video of real work into time studies, line balance charts, changeover splits and other studies you review and certify.
See AI Video Analysis
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about sMED
SMED stands for single-minute exchange of die. It is a method for cutting the time a machine is stopped to change from one product to the next. Single-minute means a single digit number of minutes, so under 10, not one minute. The die is the tool exchanged on a stamping press, where the method started.
In lean manufacturing SMED is the method that makes small batches affordable. Shorter changeovers let a machine switch products more often without losing output, which cuts stock and lead time and allows level, just-in-time production. It works by moving setup tasks out of the machine stop and shortening the ones that remain.
Shingo describes a preliminary condition, where internal and external work are mixed, and three stages. Stage 1 separates internal from external work. Stage 2 converts internal work to external. Stage 3 streamlines all remaining work. Most plants add a fourth step: standardize the new sequence, train it and confirm it with a second film.
Internal setup is work that can only be done with the machine stopped, such as removing the old tool and clamping the new one. External setup is work that can be done while the machine runs, such as fetching the next tool, collecting hand tools, preheating and paperwork. SMED moves external work out of the stop and shortens internal work.
From the last good part of the old product to the first good part of the new one. Trial runs, adjustments and waiting for first-part approval are inside the changeover. Some plants extend the clock until the machine is back at normal speed. Write the definition down before the study so the before and after figures compare.
A 90 minute mold change on an injection molding press. Filming it shows 21 minutes of fetching and clearing up that can move outside the stop, and a 12 minute wait for the mold to heat that a preheat cart removes. Quick couplers, one-turn clamps, a second person and saved settings take out another 19 minutes. The press is stopped for 38.
Multiply the changeover minutes by the parts the machine makes per minute to get the output lost. A 90 minute changeover on a press making 4 parts a minute loses 360 parts. Multiply by changeovers a week for the weekly loss. Count that output as money only if the machine is a bottleneck and the parts would sell.
No. The name comes from stamping, but the method applies to any changeover where a machine or line is stopped to switch products: injection molds, filling and packaging lines, printing, CNC machining, mixing and coating. The same internal and external split works anywhere one job has to stop before the next can start.
Related guides and tools
- SMED examples: 16 changeovers, before and after
- SMED changeover calculator: time saved, capacity freed and the smaller batch
- SMED changeover worksheet: the element log to fill in from the video
- Time and motion study: the family of methods a changeover study belongs to
- How to conduct a time study: breaking work into elements and timing them
- Just-in-time manufacturing: why small lots need short changeovers
- Best SMED software: changeover tools compared
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk
Or browse the topics, the full library and the lean glossary.
Rather see it on your own problem?
Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.