SMED: how to cut changeover time with a study from video

Short answer

SMED, single-minute exchange of die, is a method for cutting changeover time. You film a changeover, list every task, move the tasks that do not need the machine stopped to before or after the stop, then shorten what is left. The aim is a changeover under 10 minutes.

SMED stands for single-minute exchange of die. It cuts changeover time, measured from the last good part of one product to the first good part of the next, in three stages. Separate internal work (needs the machine stopped) from external work (can be done while it runs). Convert internal work to external where you can. Streamline everything that remains with quick clamps, presets and people working in parallel. Single-minute means a single digit number of minutes, so under 10. In the worked example on this page a 90 minute mold change drops to 38.

Last reviewed:

What is SMED?

SMED in one picture: the same mold change before and after

Example numbers

90 min

Press stopped today, last good part to first good part

38 min

Press stopped after one round of SMED

58% less

52 minutes back on every changeover

Before: every task done with the press stopped

After: only internal work inside the stop

  • Internal: needs the press stopped
  • External: fetching, finding, clearing up
  • Waiting for the mold to heat, now done on a cart beforehand
  • Press running product A, then B

Two timelines on the same scale. Before: the press is stopped for 90 minutes while all 12 tasks are done in order. After: the press is stopped for 38 minutes for seven internal tasks. Tasks 1 and 2 and the mold preheat are done before the stop while the old product still runs, and tasks 5 and 8 after the restart. The press runs the new product for the 52 minutes it used to stand still.

The yellow work never needed the press stopped, so it moves under the running press. The lavender wait is turned into preparation. The dark work that is left gets shortened. The green block on the right is 52 minutes of production won back on every changeover.

SMED stands for single-minute exchange of die. It is a method for shortening the time a machine or line is stopped to change from one product to the next. The name comes from stamping presses, where the die is the tool that gets exchanged, but the method applies to any changeover: a mold, a filler format, a print job, a CNC fixture, an operating theatre between patients.

Single-minute does not mean one minute. It means a single digit number of minutes: under 10. Few plants get there on the first pass, and they do not have to. Halving a changeover is already worth a great deal.

The method rests on one observation. Much of what happens during a changeover does not need the machine to be stopped. Fetching the next tool, finding the wrench, warming the mold and filling in the paperwork can all happen while the machine is still making parts. SMED finds that work and moves it. Then it shortens what is left.

How changeover time is measured

Changeover time runs from the last good part of the old product to the first good part of the new one. That is the Lean Enterprise Institute's definition, and the two words that matter are good and first. The clock does not stop when the new tool is bolted in. It stops when the machine makes a part you can ship. Trial shots, adjustments and waiting for approval are all inside the changeover. Many plants go one step further and run the clock until the machine is back at normal speed, because a slow run-up is lost output too. Pick one definition and write it at the top of the study.

Where the changeover clock starts and stops

Example numbers
  1. 0:00Last good part of product A. The clock starts.
  2. 0:52New mold clamped and connected. Many plants stop the clock here.
  3. 1:30First approved part of product B. The clock stops.

A timeline of the mold change. The clock starts at the last good part of the old job, 0:00. The new mold is clamped and connected at 0:52. The first approved part of the new job comes at 1:30. Changeover time is the whole 90 minutes, not the 52 minutes to tool in.

A plant that stops the watch when the tool is in would call this a 52 minute changeover. The press made nothing it could ship until 1:30. Settings, heating, trial shots and approval are inside the changeover, and they are often where the most time is.

Where SMED came from: Shigeo Shingo

The name and the written method come from Shigeo Shingo, a Japanese industrial engineer who taught and consulted for Toyota and its suppliers. His book A Revolution in Manufacturing: The SMED System was published in English in 1985.

By Shingo's own account the idea arrived in three episodes. In 1950, at Toyo Kogyo (now Mazda), he watched a large press stand idle while someone hunted for a missing bolt, and saw that setup work comes in two kinds: work that needs the machine stopped and work that does not. In 1957, at a Mitsubishi Heavy Industries shipyard, he had a second table built for a planer so the next engine bed could be set up while the machine was still cutting. In 1969, at Toyota, he says a 1,000 ton press that took four hours to change was brought down to 90 minutes and then, after a challenge from management, to three minutes.

Read the story with some care. People who worked at Toyota have said that Taiichi Ohno's teams were shortening die changes through the 1950s and 1960s, and that Shingo recorded and generalized the practice more than he invented it. The detail does not change the method. The stages below are the ones in his book, and they are what plants use today.

Internal vs external setup

Every task in a changeover is one of two kinds. Internal work can only be done with the machine stopped. External work can be done while the machine is running, before the stop or after the restart. The whole method turns on sorting tasks into these two piles honestly.

Internal and external setup work, with examples
InternalExternal
DefinitionCan only be done with the machine stoppedCan be done while the machine runs
When it should happenDuring the stop, and nowhere elseBefore the stop or after the restart
ExamplesUnclamp and remove the old tool, mount and clamp the new one, connect services, first trial partFetch the next tool, collect hand tools and fasteners, bring material, preheat, print labels, return the old tool, paperwork
The testWould doing this with the machine running be unsafe or impossible?Could someone do this while the last parts of the old run are still coming off?
What SMED does with itShortens itMoves it out of the stop, then shortens it too

A third pile turns up on every video: work that is not needed at all, such as walking back for a forgotten tool or adjusting something that was already right. Remove it.

Shingo's book gives his own estimate of where the time goes in a traditional setup: about 30 percent on preparation, checking materials and tools, and clearing up afterwards; about 5 percent on actually removing and mounting the tooling; about 15 percent on centring, measuring and setting; and about 50 percent on trial runs and adjustments. Those are his figures, not a law, and your video will give you your own. The pattern is the useful part. The exchange itself is the smallest slice. Preparation and adjustment are where the minutes are.

Where setup time goes: Shingo's estimate and one filmed changeover

Example numbers

Shingo's estimate of a traditional setup

Prep 30% · Swap 5% · Set 15% · Trials 50%

The 90 minute mold change on this page

Prep 23% · Swap 39% · Set 6% · Trials 32%

  • Prep: preparation, checking and clearing up
  • Swap: removing and mounting the tooling
  • Set: centring, measuring and setting
  • Trials: trial runs and adjustments, with waiting

Shingo's estimate of a traditional setup: Preparation, checking and clearing up 30 percent, Removing and mounting the tooling 5 percent, Centring, measuring and setting 15 percent, Trial runs and adjustments, with waiting 50 percent. The filmed mold change on this page: Preparation, checking and clearing up 23 percent, 21 minutes; Removing and mounting the tooling 39 percent, 35 minutes; Centring, measuring and setting 6 percent, 5 minutes; Trial runs and adjustments, with waiting 32 percent, 29 minutes.

The upper bar is Shingo's own estimate from his book, not a measurement of your plant. The lower bar is the mold change worked through below. The two differ, which is the reason to film. They agree on the lesson: taking the tool out and putting one in is well under half the stop.

The stages of SMED

Shingo describes a starting condition and three stages. Most plants add a fourth step, standardize, because a faster changeover that only one setter can do is not a result yet.

The stages of SMED: what each one does and how
StageWhat you doHowWhat it costs
Preliminary: not separatedInternal and external work are mixed together inside the stopFilm the changeover as it is done today. This is the baseline.A camera and two hours
1. SeparateTake external work out of the stopA pre-changeover checklist, a stocked tool cart, the next tool staged at the machine, the old one taken away after restartAlmost nothing: it is organization
2. ConvertTurn internal work into external workPreheat tooling off the machine, preset tools and gauges on a bench, duplicate fixtures, standard heights so no shimming is neededSome: carts, a preheat station, a second fixture
3. StreamlineShorten every task that remains, internal firstOne-turn and quick-release clamps, quick couplers, locating pins and stops, two people working in parallel, settings saved so adjustment goes awayMost: hardware and engineering time
4. StandardizeMake the new way the normal wayA written sequence with times and who does what, a checklist, training on every shift, a second film to confirmTime and discipline

Work through them in order. Stage 1 is nearly free and usually the largest single gain, so buying quick clamps before the tool cart exists spends money in the wrong order.

The stages as a ladder: what moves, what disappears, what shrinks

  1. Step 1: Film the changeover

    From the last good part of the old product to the first good part of the new one.

    The machine stops for 18 blocks; the activities inside the stop are not yet sorted.

  2. Step 2: Label every activity

    I needs the machine stopped. E could be done while it runs. U adds nothing.

    The machine stops for 18 blocks: 9 internal, 6 external, 3 unnecessary.

  3. Step 3: Move external work before the stop

    Do it while the old product still runs. Strike out the unnecessary.

    The machine stops for 9 blocks: 9 internal. 6 blocks of external work run before the stop, while the machine is still producing. 3 blocks of unnecessary work are removed.

  4. Step 4: Shorten what is left

    Internal work first: quick clamps, presets, two people to a written split.

    The machine stops for 6 blocks: 6 internal. 4 blocks of external work run before the stop, while the machine is still producing.

  5. Step 5: Validate, standardize, expand

    Check against the baseline, weigh benefit against cost, write the standard, take it to the next machine.

    Machine-down time at each stage. Baseline: machine down 18 blocks, running alongside 0; After step 3: machine down 9 blocks, running alongside 6; After step 4: machine down 6 blocks, running alongside 4; Standard: machine down 6 blocks, running alongside 4.

  • Production
  • Internal: machine stopped
  • External: machine can run
  • Unnecessary
  • Removed
  • Blocks are illustrative units, not minutes.
Read down. The stop is the bracketed part of each strip. Separating takes the external blocks out from under it, the unnecessary ones are struck out, and streamlining shortens what is left. The worked example below does the same thing in minutes.

How to run a changeover study from video

The video is what makes SMED work. People who do a changeover every week cannot see the waiting and the walking in it, and nobody remembers a 90 minute job in enough detail to argue about. A film settles it. Plan on one changeover filmed, half a day to analyse it with the crew and a second changeover to prove the new sequence.

A changeover study from the first film to the second

  1. 1

    Pick the changeover and brief the crew

  2. 2

    Film from the last good part to the first good part

  3. 3

    List every element with start and stop times

  4. 4

    Classify each element

  5. 5

    Move the external work out of the stop

  6. 6

    Convert internal work to external

  7. 7

    Streamline what is left

  8. 8

    Write the standard and film it again

Steps 1 to 4 find out where the time goes. Steps 5 to 7 are the three stages. Step 8 makes the result stick.
  1. 1

    Pick the changeover and brief the crew

    Choose a machine where changeover time limits output or forces big batches, and a changeover that is typical, not the hardest one. Tell the setters and operators why you are filming: the method is on trial, not the people. Ask them to do it exactly as they normally do.

  2. 2

    Film from the last good part to the first good part

    Start the camera before the last good part of the old run and do not stop it until the first good part of the new one. Follow the person, not the machine, because the lost time is in the walking. Use one camera per person if two people work. Keep a clock or the phone's timestamp in view, and say out loud what is happening when it is not obvious.

  3. 3

    List every element with start and stop times

    Play the video back with the crew and write down each task as its own line: what was done, when it started, when it ended. Break at every change of activity: fetching, unbolting, lifting, waiting, adjusting. Record walking, searching and waiting as their own lines. Check that the lines add up to the total.

  4. 4

    Classify each element

    Mark every line internal, external or not needed. Then mark the internal lines that could become external with a change of equipment or method. The crew will argue about some. That argument is the study doing its job.

  5. 5

    Move the external work out of the stop

    Write a pre-changeover checklist of everything that must be at the machine before it stops: next tool, hand tools, fasteners, material, paperwork. Decide who does it and when. Put the clearing up after the restart.

  6. 6

    Convert internal work to external

    Take each line marked could be external and ask what would have to be true for it to happen while the machine runs. Typical answers are a preheat station, a presetting bench, a second set of fixtures, and standard tool heights.

  7. 7

    Streamline what is left

    Go down the remaining internal lines from longest to shortest. For each, look at clamping, positioning, connecting and adjusting, and ask whether a second person working in parallel would shorten it. Then give the external lines the same treatment.

  8. 8

    Write the standard and film it again

    Put the new sequence on one page with a time against each step and a name against each role. Train every shift. Film the next changeover and compare it with the baseline line by line. Keep going until the time is stable, then repeat the study from the new baseline.

A changeover involves energy sources, heavy tooling and people reaching into machines. Lockout and guarding steps are internal work by nature, and they are never the place to save time. If a study shows people skipping them, that is the first finding. See lockout tagout for how those steps are managed.

A worked SMED example: 90 minutes to 38

Illustrative example. An injection molding press changes molds 10 times a week. One setter does the change alone. The plant measures changeover from the last good part of the old job to the first approved part of the new one, and the filmed changeover took 90 minutes.

The element log from the video

The element log from the video: 12 tasks, 90 minutes

Example numbers
  1. Task 1: Collect tools, hoses and eye bolts from the crib0:00 to 0:04 · 4 min

    ExternalTool cart stocked and parked at the press before the stop
  2. Task 2: Fetch the next mold from the rack0:04 to 0:12 · 8 min

    ExternalMold staged at the press before the stop
  3. Task 3: Drain and disconnect water lines and ejector0:12 to 0:18 · 6 min

    InternalQuick couplers on a manifold: 4 min
  4. Task 4: Unbolt eight clamps, lift the old mold out0:18 to 0:29 · 11 min

    InternalOne-turn clamps and a second person on the far side: 7 min
  5. Task 5: Take the old mold to the rack0:29 to 0:34 · 5 min

    ExternalDone after the restart
  6. Task 6: Lift in the new mold, centre it, bolt eight clamps0:34 to 0:46 · 12 min

    InternalLocating ring, one-turn clamps and the second person: 8 min
  7. Task 7: Connect water lines and ejector0:46 to 0:52 · 6 min

    InternalColour-coded quick couplers: 4 min
  8. Task 8: Put tools away, fill in the changeover sheet0:52 to 0:56 · 4 min

    ExternalDone after the restart
  9. Task 9: Find the setup sheet, key in the settings0:56 to 1:01 · 5 min

    InternalSettings saved as a recipe on the press: 2 min
  10. Task 10: Wait for the mold to reach temperature1:01 to 1:13 · 12 min

    Internal, can be externalMold preheated on a cart before the stop: 0 min
  11. Task 11: Trial shots and adjustments1:13 to 1:25 · 12 min

    InternalHot mold and saved settings mean fewer shots: 9 min
  12. Task 12: Wait for first-part approval1:25 to 1:30 · 5 min

    InternalInspector called when trial shots start, gauge at the press: 4 min
Each bar sits where the task happened on the changeover clock. Yellow tasks (21 min) never needed the press stopped. The lavender one (12 min) can be moved with a preheat cart. Only the dark bars (57 min) are true internal work. The 12 lines add up to 90 minutes. Only elements 4 and 6, 23 minutes together, are the exchange itself.

Sorting the 90 minutes

Illustrative: the 90 minutes sorted
PileElementsMinutesShare
External work done with the press stopped1, 2, 5, 84 + 8 + 5 + 4 = 2123%
Internal work that can become external101213%
Internal work that has to stay internal3, 4, 6, 7, 9, 11, 126 + 11 + 12 + 6 + 5 + 12 + 5 = 5763%
TotalAll 1290100%

Shares are rounded to the nearest whole percent, so they add to 99. A third of the stop, 33 of 90 minutes, did not need the press to be stopped.

Stage by stage

Stage by stage: 90 minutes stopped down to 38

Example numbers
  1. Baseline

    Everything done with the press stopped

  2. 1. Separate

    Elements 1 and 2 done before the stop, 5 and 8 after the restart

  3. 2. Convert

    Mold preheated on a cart, so the wait in element 10 disappears

  4. 3. Streamline

    Seven internal elements shortened: 2 + 4 + 4 + 2 + 3 + 3 + 1

  5. 4. Standardize

    The 38 minute sequence written down, trained and filmed again

Bars of the time the press is stopped at each stage: Baseline, 90 minutes; 1. Separate, 69 minutes; 2. Convert, 57 minutes; 3. Streamline, 38 minutes; 4. Standardize, 38 minutes.

The dashed gap is what each stage took out. 90 less 38 is 52 minutes saved, a 58 percent reduction. Stage 1 gave 21 of the 52 and needed a cart and a checklist.

Every task on one clock: 90 minutes stopped, then 38

Example numbers

Before: every task done with the press stopped

After: only internal work inside the stop

  • Internal: needs the press stopped
  • External: fetching, finding, clearing up
  • Waiting for the mold to heat, now done on a cart beforehand
  • Press running product A, then B

Two timelines on the same scale. Before: the press is stopped for 90 minutes while all 12 tasks are done in order. After: the press is stopped for 38 minutes for seven internal tasks. Tasks 1 and 2 and the mold preheat are done before the stop while the old product still runs, and tasks 5 and 8 after the restart. The press runs the new product for the 52 minutes it used to stand still.

Numbers are the tasks in the log. Tasks 1 and 2 and the preheat (10) now happen before the stop, 5 and 8 after the restart, and the seven dark blocks are each shorter than they were.

Two things in the result are worth a second look. First, the work did not shrink as much as the stop did. The 21 external minutes are still done. They are done while the press makes parts. Second, the second person on elements 4 and 6 cuts clock time, not labour: 7 minutes with two people is 14 labour minutes against 11 before. That trade is right when the press is the constraint and wrong when it is not, which is what the next section is about.

At 38 minutes this is not yet a single-minute changeover. The next round starts from the new video. Trial shots and approval are now 13 of the 38 minutes, so that is where it would look first.

Where the minutes come from: the techniques

Shingo lists eight techniques. The first two are stages 1 and 2. The other six are the toolbox for stage 3. Here they are as questions to ask of each line in the log.

  • Pre-staging. Is everything the changeover needs at the machine, checked and in order of use, before the stop? A cart with a shadow board and a checklist does most of this.
  • Function checks before the stop. Has the next tool been inspected and repaired since its last run? A changeover that discovers a damaged tool is a breakdown.
  • Standard function, not standard shape. Can every tool present the same clamping height, the same locating point and the same connections, so nothing has to be shimmed or re-plumbed?
  • Quick-release clamping. A bolt only holds on its last turn, and every turn before that is waste. One-turn clamps, slotted washers, cams, toggle clamps and hydraulic clamping remove it.
  • Intermediate jigs. Can the part or tool be mounted on a standard plate away from the machine, so only the plate is exchanged?
  • Parallel operations. On a large machine one person walks round it dozens of times. Two people with a written split of who does what, and a clear signal before anything moves, cut the walking out.
  • No adjustment. Adjustment and trial runs are often half the stop. Fixed stops, scales with numbers, saved settings and presetting off the machine turn a judgement into a position.
  • Mechanization, last. Powered clamps and tool carts with rollers help, but only after the free and cheap gains are in. Mechanizing a bad method makes it a fast bad method.

Stage 3, task by task: where 19 minutes came out

Example numbers
  1. Drain and disconnect water lines and ejectorQuick couplers on a manifold

    6 to 4 min

  2. Unbolt eight clamps, lift the old mold outOne-turn clamps and a second person on the far side

    11 to 7 min

  3. Lift in the new mold, centre it, bolt eight clampsLocating ring, one-turn clamps and the second person

    12 to 8 min

  4. Connect water lines and ejectorColour-coded quick couplers

    6 to 4 min

  5. Find the setup sheet, key in the settingsSettings saved as a recipe on the press

    5 to 2 min

  6. Trial shots and adjustmentsHot mold and saved settings mean fewer shots

    12 to 9 min

  7. Wait for first-part approvalInspector called when trial shots start, gauge at the press

    5 to 4 min

Before and after for the seven internal tasks: Drain and disconnect water lines and ejector, 6 to 4 minutes, Quick couplers on a manifold; Unbolt eight clamps, lift the old mold out, 11 to 7 minutes, One-turn clamps and a second person on the far side; Lift in the new mold, centre it, bolt eight clamps, 12 to 8 minutes, Locating ring, one-turn clamps and the second person; Connect water lines and ejector, 6 to 4 minutes, Colour-coded quick couplers; Find the setup sheet, key in the settings, 5 to 2 minutes, Settings saved as a recipe on the press; Trial shots and adjustments, 12 to 9 minutes, Hot mold and saved settings mean fewer shots; Wait for first-part approval, 5 to 4 minutes, Inspector called when trial shots start, gauge at the press.

The outline is the time on the video and the solid bar is the time after the change. No single fix is large. 19 minutes come from seven small ones, and the two tasks that got a second person, 4 and 6, gave the most.

The gallery of 16 SMED examples shows these techniques on presses, molding machines, fillers and CNC machines, before and after.

What a changeover costs: the arithmetic

A changeover costs the output the machine did not make while it was stopped. Work it out before the project so you know what a minute is worth, and after it so you can say what you got.

Lost output per changeover = changeover minutes x parts per minute. Weekly changeover time = changeovers a week x changeover minutes.

Illustrative: what the mold changes cost in capacity, before and after
StepBeforeAfter
Rate of the press30 s cycle, 2 cavities: 4 parts a minute4 parts a minute
Changeover time90 min38 min
Output lost per changeover90 x 4 = 360 parts38 x 4 = 152 parts
Changeovers a week1010
Press stopped for changeovers10 x 90 = 900 min (15.0 h)10 x 38 = 380 min (6.3 h)
Share of 4,800 scheduled minutes18.8%7.9%
Time freed a week900 less 380 = 520 min (8.7 h)
Parts that time can make520 x 4 = 2,080 parts

The press is scheduled for two 8 hour shifts, five days a week: 2 x 480 x 5 = 4,800 minutes. Scrap from trial shots and the setter's labour come on top and are not counted here.

What ten changeovers a week cost, before and after

Example numbers

Before: stopped for changeovers 900 min (15.0 h), 18.8% of the week

After: stopped for changeovers 380 min (6.3 h), 7.9% of the week

Time freed a week = changeovers a week x minutes saved per changeover

Then multiply by the rate of the machine to turn minutes into parts.

  1. Saved per changeover =90 less 38= 52 min
  2. Freed a week =10 x 52= 520 min (8.7 h)
  3. As parts =520 x 4 parts a minute= 2,080 parts
  4. Or as changeovers =900 / 38= 23 in the time 10 took
Freed each week520 min

Of 4,800 scheduled minutes a week, changeovers took 900 before and 380 after, freeing 520 minutes, which is 2,080 parts at 4 parts a minute.

Each bar is the press's 4,800 scheduled minutes in a week. The yellow slice is the 520 minutes SMED gave back. Whether that becomes 2,080 more parts or 23 changeovers in place of 10 is the plant's choice.

Two ways to spend the time

The freed 520 minutes can be used in two ways, and it is a choice. If the press is the bottleneck and there are orders for the parts, run it: 2,080 more parts a week. At an example contribution of $1.50 a part, that is 2,080 x 1.50 = $3,120 a week. If the press is not the constraint, more parts are just more stock, and the money figure is zero.

The other way is to keep the changeover time where it was and change over more often. The 900 minutes that paid for 10 changeovers now pay for 900 / 38 = 23. Batches can be less than half the size, which means less finished stock, shorter lead times and a schedule that follows orders. This is the reason Toyota wanted quick changeovers in the first place: small lots, not more press hours. It is also what makes just-in-time and level scheduling possible.

The SMED changeover calculator runs these sums for your own machine, and the EPEI and batch size calculator turns a shorter changeover into a new batch size.

Mistakes that stall a SMED project

  • Stopping the clock when the tool is in. The changeover ends at the first good part. Trial runs and approval are often the largest block, and this definition hides them.
  • Working from memory. Without a video, the log is a list of what people think they do. The walking, the waiting and the second trip to the crib never make it onto paper.
  • Buying hardware first. Quick clamps on a changeover that still starts with a search for the wrench save little. Stage 1 costs almost nothing and comes first.
  • Studying a machine that is not a constraint and then counting the freed hours as money. If the output is not needed, the gain is smaller batches. Say so.
  • Filming the best setter on the best day. The standard has to work for the night shift too. Film a normal one.
  • Leaving the crew out of the analysis. They know why each step exists, and they are the ones who will have to do it the new way.
  • Cutting a safety step. Lockout, guarding checks and lifting rules are not waste.
  • No written standard. Six weeks later the time is back where it started, and nobody can say which step slipped.
  • Declaring victory after one round. Each pass exposes the next layer. The second video usually has as much in it as the first.
  • Not telling the planners. A 38 minute changeover scheduled in 90 minute blocks and run in the same batch sizes changes nothing.

Templates, tools and software for SMED

The log is the slow part of a study, and it is the part software can draft. In LeanSuite's SMED module you film one changeover on a phone and upload it. The AI marks each task internal or external, keeps the clip behind every call, flags tasks that can run in parallel and proposes a shorter sequence. Your team corrects the draft, and the agreed sequence becomes the checklist operators run at the machine, with a time logged against every step.

FAQ

Questions about sMED

  1. SMED stands for single-minute exchange of die. It is a method for cutting the time a machine is stopped to change from one product to the next. Single-minute means a single digit number of minutes, so under 10, not one minute. The die is the tool exchanged on a stamping press, where the method started.

  2. In lean manufacturing SMED is the method that makes small batches affordable. Shorter changeovers let a machine switch products more often without losing output, which cuts stock and lead time and allows level, just-in-time production. It works by moving setup tasks out of the machine stop and shortening the ones that remain.

  3. Shingo describes a preliminary condition, where internal and external work are mixed, and three stages. Stage 1 separates internal from external work. Stage 2 converts internal work to external. Stage 3 streamlines all remaining work. Most plants add a fourth step: standardize the new sequence, train it and confirm it with a second film.

  4. Internal setup is work that can only be done with the machine stopped, such as removing the old tool and clamping the new one. External setup is work that can be done while the machine runs, such as fetching the next tool, collecting hand tools, preheating and paperwork. SMED moves external work out of the stop and shortens internal work.

  5. From the last good part of the old product to the first good part of the new one. Trial runs, adjustments and waiting for first-part approval are inside the changeover. Some plants extend the clock until the machine is back at normal speed. Write the definition down before the study so the before and after figures compare.

  6. A 90 minute mold change on an injection molding press. Filming it shows 21 minutes of fetching and clearing up that can move outside the stop, and a 12 minute wait for the mold to heat that a preheat cart removes. Quick couplers, one-turn clamps, a second person and saved settings take out another 19 minutes. The press is stopped for 38.

  7. Multiply the changeover minutes by the parts the machine makes per minute to get the output lost. A 90 minute changeover on a press making 4 parts a minute loses 360 parts. Multiply by changeovers a week for the weekly loss. Count that output as money only if the machine is a bottleneck and the parts would sell.

  8. No. The name comes from stamping, but the method applies to any changeover where a machine or line is stopped to switch products: injection molds, filling and packaging lines, printing, CNC machining, mixing and coating. The same internal and external split works anywhere one job has to stop before the next can start.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.