Ramp-up plan and the learning curve: how long to reach standard

Short answer

A learning curve says the time per unit falls by a fixed percentage each time total output doubles. On an 85% curve, a job that takes 40 hours for unit 1 takes 34 for unit 2, 28.9 for unit 4 and reaches a 16 hour standard at unit 50.

The learning curve formula is Y = a x X^b, where a is the time for the first unit, X is the unit number and b = log(learning rate) / log(2). For an 85 percent curve b is minus 0.2345. In Crawford's unit model Y is the time for unit X. In Wright's cumulative average model Y is the average time of the first X units, so the same rate gives lower times. To plan a ramp-up, work out the time for each unit, cap it at the standard time, add the units up week by week against the crew's hours, and set interim standards that step down as the count rises. Get the rate from your own data, because a few points of rate change the answer by months.

Last reviewed:

What is a learning curve?

An 85% learning curve, from the first unit to standard

Example numbers
An 85 percent learning curve with the standard time markedHours per unit against unit number for a 40 hour first unit on a 85 percent unit curve. Unit 1: 40.0 hours. Unit 2: 34.0 hours. Unit 4: 28.9 hours. Unit 8: 24.6 hours. Unit 16: 20.9 hours. Unit 32: 17.7 hours. The curve meets the 16 hour standard at unit 50 and is flat after that. The area between the curve and the standard up to unit 49 is 220.5 hours.010203040116325064Unit numberHours for the unitStandard 16 h220.5 h above standard1: 40.02: 34.04: 28.98: 24.616: 20.9Unit 50Formula, no plateau
Each labelled dot is a doubling, and each is 85% of the one before: 40.0, 34.0, 28.9, 24.6, 20.9, 17.7 hours. The curve meets the 16 hour standard at unit 50 and the plan holds it there. The shaded area is the price of learning: 220.5 labour hours more than 49 units would take at standard.

People and plants get faster at a job the more times they do it. Hands learn the motions, the fumbling stops, the tooling gets fixed, the bad instruction gets rewritten. The learning curve puts a number on how fast that happens.

The rule it uses is doubling. Each time the total number of units built doubles, the time per unit falls to a fixed share of what it was. That share is the learning rate. On an 85% curve, unit 2 takes 85% of the time of unit 1, unit 4 takes 85% of unit 2, unit 8 takes 85% of unit 4, and so on.

Two things follow, and both surprise people. A lower percentage means faster learning: an 80% curve drops 20% per doubling and a 95% curve only 5%. And the gains come early. Going from unit 1 to unit 2 saves as large a share as going from unit 500 to unit 1,000, but the second takes 500 units to arrive.

The idea comes from aircraft building. T. P. Wright published it in 1936 after noticing that the labour hours for an airframe fell by about 20% each time the number built doubled. You will also see it called the improvement curve, the progress curve and the experience curve.

For a planner it answers the launch questions that a standard time can't. The standard time says how long the job takes once people are trained. The learning curve says how long it takes until then, how many units that is, and what the first weeks will really produce.

The formula, and what the exponent means

The whole model is one line: Y = a x X^b. Here a is the time for the first unit, X is the unit number counted from the start, and b is a negative exponent that carries the learning rate.

You get b from the rate: b = log(learning rate) / log(2). Any logarithm works as long as it is the same on top and bottom. The division by log 2 is what makes the rate apply per doubling: put X = 2 into the formula and 2^b comes out as exactly the learning rate.

Learning rates and their exponents
Learning rateFall per doublingExponent bUnit 2 as a share of unit 1Unit 16 as a share of unit 1
95%5%minus 0.074095%81.5%
90%10%minus 0.152090%65.6%
85%15%minus 0.234585%52.2%
80%20%minus 0.321980%41.0%

Unit 16 is four doublings on, so its share is the rate to the fourth power.

Because Y = a x X^b is a power law, it plots as a straight line when both axes are logarithmic. That is the practical test of whether your data follows a learning curve at all: plot hours against unit number on log-log paper. If the points fall on a line, the slope is b and the rate is 2^b. If they do not, something other than learning is going on.

On log-log axes the curve is a straight line

Example numbers
Learning curves on log-log axesThe same curve on logarithmic axes, where it is a straight line, with a 80 percent curve reaching the 16 hour standard at unit 18, a 85 percent curve reaching the 16 hour standard at unit 50, a 90 percent curve reaching the 16 hour standard at unit 415.16203040141664256Unit number (each tick doubles)Hours for the unit80%: unit 1885%: unit 5090%: unit 415Unit 1: 40 hStandard 16 h
Plot hours against unit number with both axes logarithmic and a learning curve becomes a line whose slope is b. The white dots on the 85% line are the doublings, evenly spaced. The three lines start at the same 40 hours and differ only in rate, yet they reach the 16 hour standard at unit 18, unit 50 and unit 415.

Two models with the same formula: Wright and Crawford

The formula hides a choice that changes the answer a lot: what is Y? There are two standard readings, and they are not interchangeable.

The two learning curve models
Wright: cumulative average modelCrawford: unit model
Y isThe average time per unit of all units from 1 to XThe time of unit X on its own
When output doublesThe average of everything built so far falls to the learning rateThe time of the latest unit falls to the learning rate
Total time for X unitsX x a x X^bThe sum of a x n^b for n from 1 to X
Time of one unitTotal for X units minus total for X minus 1a x X^b
Fits whenYou have total hours for a batch or a contract and no unit detailYou timed individual units or small lots
Also calledCumulative average theoryUnit theory

Wright's 1936 paper used the cumulative average. Crawford's version, developed at Lockheed in the 1940s, applies the same rule to each unit. Run both with the same first unit and the same rate and Wright comes out lower, because an average that falls by 15% needs the newest units to fall by much more.

Illustrative: the same 40 hour first unit and 85% rate under each model
UnitCrawford: time of this unitCrawford: total so farWright: average so farWright: total so farWright: time of this unit
140.0 h40.0 h40.0 h40.0 h40.0 h
234.0 h74.0 h34.0 h68.0 h28.0 h
428.9 h133.8 h28.9 h115.6 h22.9 h
824.6 h237.4 h24.6 h196.5 h19.1 h
1620.9 h415.3 h20.9 h334.1 h16.1 h

Crawford's column for the unit and Wright's column for the average hold the same numbers. They mean different things.

Same first unit, same 85%, two different answers

Example numbers
  • Unit 1Crawford40.0 hWright40.0 h
  • Unit 2Crawford34.0 hWright28.0 h
  • Unit 4Crawford28.9 hWright22.9 h
  • Unit 8Crawford24.6 hWright19.1 h
  • Unit 16Crawford20.9 hWright16.1 h
  • Crawford, unit model: the time of unit X is a x X^b
  • Wright, cumulative average model: the average of units 1 to X is a x X^b
  • Standard 16 h
Under Crawford each unit is 85% of the unit at half its number. Under Wright the running average is, so the newest unit has to be far lower to pull the average down. By unit 16 Wright says 16.1 hours and Crawford 20.9. Eight units total 196.5 hours under Wright and 237.4 under Crawford.

By unit 8 the two totals are 237.4 and 196.5 hours, a gap of 41 hours. A 16 hour unit arrives at unit 17 under Wright and at unit 50 under Crawford. So a learning rate is meaningless without its model. An 85% rate fitted to unit times is an 85% unit curve, and quoting it as a cumulative average rate will make the plan far too optimistic.

Which to use: the one that matches how the data was collected. For planning a ramp on the shop floor that is nearly always the unit model, because you time units and you need the time of the next unit. The rest of this page uses it.

Worked example: a 40 hour first unit on an 85% curve

The job is wiring and assembling a control cabinet, a new design, built by a crew of four. The first cabinet took 40.0 hours of labour. The engineered standard, from predetermined times, is 16.0 hours. The crew's last two cabinet designs followed an 85% unit curve, so that is the planning rate. All of it is illustrative.

With b = log(0.85) / log(2) = minus 0.2345, the time for any unit is 40 x X^(minus 0.2345). The table shows it by doubling.

Illustrative: unit hours by doubling, 40 hour first unit, 85% unit curve
UnitHours for this unitShare of unit 1Total hours so farAverage hours so far
140.0100%40.040.0
234.085%74.037.0
428.972.3%133.833.5
824.661.4%237.429.7
1620.952.2%415.326.0
3217.744.4%719.322.5
6415.137.7%1,237.319.3

Each row is 85% of the row above in the second column. The last row is below the 16 hour standard, which is where the plateau comes in.

When does the job reach standard? Solve the formula for X: X = (standard / first unit)^(1 / b) = (16 / 40)^(1 / minus 0.2345) = 49.8. Unit 49 takes 16.06 hours and unit 50 takes 15.98, so the crew reaches standard at unit 50.

The cost of getting there is the area between the curve and the standard. Units 1 to 49 take 1,004.5 hours in total. At standard they would take 49 x 16 = 784 hours. The difference, 220.5 hours, is the learning cost of this launch: about five and a half weeks of one person's time that has to be in the budget and the schedule.

The rate matters far more than the first unit. Keep everything else and change only the rate: at 80% the job reaches 16 hours at unit 18, at 85% at unit 50, at 90% at unit 415. Five points of learning rate is the difference between a ramp of weeks and a ramp of most of a year. That is why the rate has to come from your own records.

How to turn the curve into a ramp-up plan

A ramp-up plan says how many units come off each week until the job is at standard. The curve gives hours per unit. The plan turns that into units per week by spending the crew's hours down the list of units.

From a first unit time to a weekly plan

  1. 1

    Decide what counts as one unit and which model you are using

  2. 2

    Get the first unit time

  3. 3

    Get the learning rate from your own data

  4. 4

    Set the plateau

  5. 5

    Build the unit table

  6. 6

    Convert to weeks

  7. 7

    Set interim standards for each block of units

  8. 8

    Track actual against plan every week and refit

Steps 1 to 4 are the inputs. Steps 5 and 6 are arithmetic. Steps 7 and 8 are how the plan gets used.
  1. 1

    Decide what counts as one unit and which model you are using

    One cabinet, one lot of ten, one shift's output. Use the unit model if you time units. Write both down next to the rate.

  2. 2

    Get the first unit time

    Use the measured hours of the first unit or the first lot. If nothing is built yet, estimate it from the first unit of the most similar past job, not from the standard.

  3. 3

    Get the learning rate from your own data

    Fit it to the unit hours of a similar past launch, or to this job's pilot units. Plot on log-log axes and check the points make a line before you trust the slope.

  4. 4

    Set the plateau

    The engineered standard time is the floor. The curve stops there, and no unit is planned faster than standard.

  5. 5

    Build the unit table

    Time for each unit from the formula, capped at the standard, with a running total of hours.

  6. 6

    Convert to weeks

    Work out the labour hours the crew has each week. A unit is finished in the week its running total is reached.

  7. 7

    Set interim standards for each block of units

    Give supervisors and the schedule a target for the block they are in, stepping down as the count rises.

  8. 8

    Track actual against plan every week and refit

    Plot actual unit hours on the same chart. After 8 or 10 units, refit the rate and reissue the plan.

For the cabinet job the crew of four has 4 x 40 = 160 labour hours a week. At standard that is 160 / 16 = 10 cabinets a week.

Illustrative: weekly ramp-up plan, 160 labour hours a week, 16 hour standard
WeekCabinets finishedTotal so farShare of the standard rate
14440%
271170%
381980%
482780%
593690%
61046100%
7 onward1056 and up100%

A cabinet counts in the week it is finished. Unit 50, the first at standard, is finished early in week 7.

The ramp-up plan, week by week

Example numbers
Weekly output during the ramp-upCabinets finished each week with 160 labour hours a week: week 1 4, week 2 7, week 3 8, week 4 8, week 5 9, week 6 10, week 7 10, week 8 10. At standard the crew makes 10 a week. The first six weeks fall 14 short of that.02468104147211831984279536106461075610866At standard: 10 a weekCabinets finishedWeek, running total under it
  • Finished, still on the curve
  • Finished, at the standard rate
  • Short of a plan at standard
The same 160 labour hours buy 4 cabinets in week 1 and 10 from week 6. The dashed boxes are what a plan at standard would have promised and the crew can't yet deliver: 14 cabinets over the first six weeks. Better to show that gap to the customer before the launch than after it.

Six weeks produce 46 cabinets where a plan at standard would have promised 60. If the customer was told 10 a week from the first Monday, the order book is 14 cabinets short before anything has gone wrong. That is the conversation the ramp-up plan exists to have early.

The learning curve and ramp-up workbook does these sums for up to 500 units under both models, fits the rate from your own points and builds the weekly plan with a plateau.

Interim standards during the ramp

During the ramp the final standard is the wrong yardstick. Measured against 16 hours, the crew is at 40% in week 1 and looks like a failure while doing exactly what the plan expects. An interim standard is a temporary target for a block of units, taken from the curve.

Illustrative: interim standards for the cabinet job by block of units
UnitsCurve at the start of the blockCurve at the endInterim standard (block average)Hours for the block
1 to 440.0 h28.9 h33.5 h133.8
5 to 827.4 h24.6 h25.9 h103.6
9 to 1623.9 h20.9 h22.2 h177.9
17 to 3220.6 h17.7 h19.0 h303.9
33 to 4917.6 h16.1 h16.8 h285.3
50 onward16.0 h16.0 h16.0 h, the standard

Blocks follow the doublings, so each step down is about the same size. The five blocks add up to the 1,004.5 hours for units 1 to 49.

Interim standards: a staircase down the curve

Example numbers
Interim standards stepped down the learning curveInterim standards as steps over the learning curve: units 1 to 4 33.5 hours, units 5 to 8 25.9 hours, units 9 to 16 22.2 hours, units 17 to 32 19.0 hours, units 33 to 49 16.8 hours, units 50 to onward 16.0 hours.01020304018163249Unit numberHours for the unit33.5 h22.2 h19.0 h16.8 h16.0 h
  • Interim standard for the block
  • Learning curve, capped at the standard
The dashed line is the learning curve and each step is the interim standard for a block of units, set at the block's average: 33.5, 25.9, 22.2, 19.0, 16.8, 16.0 hours. Steps follow the doublings, so they come quickly at first and then spread out. The crew is early in a block when above its step and late in it when below, which is what the plan expects.
  • Step by units built, not by the calendar. Learning follows repetitions. A week lost to a parts shortage should not move the target.
  • Publish all the steps before the start. A target that drops without warning feels like a rate cut. A staircase people saw on day one is a plan.
  • Use them for scheduling, costing and judging the launch. Be careful about tying pay to them. If you do, that is a matter for your agreements and local rules, not for a formula.
  • When the crew beats a step, find out what they changed and put it in the method. When they miss one, look for a method problem before you look at effort.
  • End them. Once the times stop falling, set the real standard with a time study on the settled method.

The plateau: where the curve stops

The formula never stops falling. Left alone it says unit 500 of the cabinet takes 9.3 hours and unit 1,000 takes 7.9, on a job whose engineered standard is 16. Nobody should plan on that. At some point the operator is doing the method as designed at a normal pace, and what is left is the work itself.

So planners cap the curve. The usual cap is the standard time: the curve applies until it reaches the standard, and the standard applies after that. Researchers have built the same idea into the formula. De Jong's version adds a factor for the share of the job that can't be compressed, such as machine time, so the curve levels off towards a floor. Another variant, known as Stanford-B, shifts the curve to allow for experience the crew brings from earlier products, which makes the first units less steep.

A plateau is not the end of improvement. It is the end of free improvement from repetition. Times can still fall, but only because someone changes the method, the tooling or the design. That is kaizen, and it shows on the chart as a step down, not as more of the same curve.

Watch for a plateau that arrives early. If the times flatten at 22 hours when the standard says 16, either the standard was wrong or something is holding the crew back that practice can't fix. Go and look, as described in the section on telling learning from method problems in the pilot run guide.

Forgetting: what a break in production costs

Learning is lost when the work stops. After a gap between orders, a long shutdown or a crew change, the next unit takes longer than the last one did, and the crew has to climb part of the curve again. Controlled experiments on repetitive tasks have confirmed it: the longer the break, the more is lost.

A method widely used in cost estimating comes from George Anderlohr, who wrote it up in 1969. You estimate a lost-learning factor, the share of the learning that the break wiped out, by looking at five things: the people, the supervision, the continuity of production, the methods and the tooling. Then you move the job back up its own curve.

  1. 1

    Find the learning achieved

    First unit time minus the time the next unit would have taken with no break. The cabinet job stops after unit 20. Unit 21 would have taken 19.59 hours, so the learning achieved is 40.00 minus 19.59 = 20.41 hours.

  2. 2

    Estimate the share lost

    Judge each of the five things and weight them. Say the result is 40%: two of the four people are new and the jigs were stored. Learning lost is 0.40 x 20.41 = 8.16 hours.

  3. 3

    Add it to the next unit

    The first unit after the break is expected to take 19.59 + 8.16 = 27.75 hours.

  4. 4

    Find that time on the original curve

    27.75 hours sits between unit 4 and unit 5. Unit 5 takes 27.43 hours, so the job restarts as if it were at unit 5: a setback of 16 units.

  5. 5

    Replan from there

    Unit 21 is planned at unit 5's time, unit 22 at unit 6's, and so on. The 16 hour standard now arrives at unit 66, not unit 50.

After a break, the job climbs part of the curve again

Example numbers
What a production break does to the learning curveHours per unit with and without a production break after unit 20. Without the break unit 21 would take 19.59 hours and the standard arrives at unit 50. With 40 percent of the learning lost, unit 21 takes 27.43 hours, the time of unit 5, and the standard arrives at unit 66. The break costs 106 extra hours.010203040120506680Unit numberHours for the unit20: 19.821: 27.4 h after the break106 extra hoursUnit 50Unit 66
  • Plan with the break
  • Plan with no break
  • Extra hours caused by the break
Production stops after unit 20. With 40% of the learning judged lost, unit 21 is planned at the time of unit 5, a setback of 16 units. The dotted line is where the job would have gone. The shaded area is the cost: 106 extra hours, and the standard arrives at unit 66, not unit 50.

The break costs 106 extra labour hours spread over units 21 to 65, on top of the gap itself. The 40% is a judgement, and the answer is only as good as it is. What the method does well is make the judgement explicit and show its cost, so the break can be argued about before it happens.

The practical lessons are plain. Keep the crew together across a gap if you can. Keep the jigs, the instructions and the video of the method, because the method and tooling parts of learning are the ones you can store. And when a job restarts, plan the first units on interim standards again.

Get the rate from your own data

Learning rates in books are averages over industries and decades. Your rate depends on how much of the job is manual, how complete the instructions and tooling were on day one, how experienced the crew is and how stable the design stays. Two plants building the same product can have quite different rates.

  • From a past launch: take the labour hours of each unit or lot of the most similar job you have run. Plot hours against unit number on log-log axes, fit a line, and the rate is 2 to the power of the slope.
  • From this job's first units: the same fit on the pilot or the first week. Five points is the least to fit, and ten is better.
  • Check the fit. R squared near 1 means the points follow a curve. A poor fit means something else is driving the times, and no rate will describe them.
  • Fit only clean units. Leave out a unit that waited two days for a part, or note it. One bad point early on swings the slope.
  • Keep the model with the rate. A rate fitted to unit hours belongs to the unit model.

Machine-controlled time does not learn. If half of a job's cycle is a machine running, only the manual half follows the curve, and the rate for the whole job will be much closer to 100% than the rate for the hand work. Split the job before you fit.

When learning curve maths is the wrong tool

The model assumes the same job, done repeatedly, by the same people, without long gaps, where people set the pace. Take any of those away and the curve will mislead.

When the learning curve fits and when it does not
SituationWhy the curve failsUse this
Machine-paced work: a press, a moulding machine, a filling lineThe cycle is set by the machine. Operators learn the tending, not the rateA start-up curve from OEE losses: availability, speed and quality by week
Short cycles at high volume: an assembly line doing hundreds a dayOperators pass through hundreds of doublings in days. The ramp is limited by stoppages, parts and defects, not by practiceA weekly efficiency plan from the pilot run and past launches, with the losses tracked by cause
A design that keeps changingEach change puts part of the job back at unit 1Treat each major revision as a new start for the elements it touches
One-offs and very small runsThere are not enough repeats for a rate to mean anythingAn estimate with a range, and a review after each unit
High turnover or a rotating crewThe people who learned are not the people buildingIndividual training curves per operator, from the skills matrix
A ramp held back by something elseMaterial, tooling or quality problems hide any learningThe issue list. Fix the causes, then look at the times

The second row deserves a word, because it is where most plants meet the problem. On a manual assembly line each operator repeats a one minute job several hundred times a shift. In the pilot run example a 30 second element was at its planning time within 40 units. Operator learning on a line like that is mostly done in days. What takes weeks is everything around it: balance, parts presentation, small stops, defects. Plan those weeks with an efficiency figure per week, as in planning operators and stations for a new line, and use the learning curve for the long-cycle jobs it was made for.

There is a people side too. A curve is an average, and individuals vary around it. Use it to plan the launch and to judge the launch, not to rank operators in their first weeks. Show the crew the curve and the interim steps at the start. People who know that week 1 is meant to be slow, and can see where they are heading, learn faster than people who are told they are behind.

Filming the first units helps both sides. LeanSuite's Time and Motion Study times each element from video, so you can see which elements are still falling and which have stopped. That is the difference between waiting for learning and fixing a method.

Templates and tools for ramp-up planning

FAQ

Questions about ramp-up plan and the learning curve

  1. An 85 percent learning curve means that each time the total number of units built doubles, the time per unit falls to 85 percent of what it was, a 15 percent reduction. If unit 1 takes 40 hours, unit 2 takes 34, unit 4 takes 28.9 and unit 8 takes 24.6. The lower the percentage, the faster the learning.

  2. Y = a x X^b, where a is the time for the first unit, X is the unit number and b = log(learning rate) / log(2). For an 85 percent curve b is minus 0.2345. In the unit model Y is the time of unit X. In the cumulative average model Y is the average time of units 1 to X.

  3. Both use Y = a x X^b. In Wright's cumulative average model Y is the average time of all units up to X. In Crawford's unit model Y is the time of unit X alone. With the same first unit and rate, Wright gives lower times: for 100 hours and 80 percent, eight units total 409.6 hours under Wright and 534.6 under Crawford.

  4. In economics the learning curve is the fall in labour time or cost per unit as cumulative output rises, first measured on aircraft by T. P. Wright in 1936. The wider version, the experience curve, applies the same idea to total unit cost. It explains why early units of a new product cost more and why volume can lower cost.

  5. In everyday speech a steep learning curve means something is hard to pick up. In manufacturing the term is exact: it is the rate at which time per unit falls as more units are built. There, a steep curve is good news, because it means time is falling fast.

  6. Training texts usually list four shapes: diminishing returns, where gains are fast and then slow; increasing returns, slow then fast; the S-curve, slow, fast and slow again; and the complex curve with several plateaus. Manufacturing planning uses the first shape, in two forms: Wright's cumulative average model and Crawford's unit model.

  7. Solve the curve for the unit at which the time equals the standard: X = (standard / first unit time)^(1 / b). With a 40 hour first unit, a 16 hour standard and an 85 percent unit curve, X is 49.8, so unit 50. Then convert units to weeks with the crew's hours. The answer swings widely with the rate, so use your own.

  8. Some of the learning is lost and the next unit takes longer than the last one before the break. A common planning method estimates the share lost from changes in people, supervision, continuity, methods and tooling, adds the lost hours to the next unit, and restarts the job further back on its original curve.

  9. Do not use it for machine-paced work, where the machine sets the cycle; for one-offs with too few repeats; for a design that keeps changing; or for short-cycle lines, where operators finish most of their learning in days and the ramp is held back by stoppages and defects. Use a weekly efficiency plan with losses tracked by cause.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?