Practical guide · Standard work, SOPs and training
Ramp-up plan and the learning curve: how long to reach standard
Short answer
A learning curve says the time per unit falls by a fixed percentage each time total output doubles. On an 85% curve, a job that takes 40 hours for unit 1 takes 34 for unit 2, 28.9 for unit 4 and reaches a 16 hour standard at unit 50.
The learning curve formula is Y = a x X^b, where a is the time for the first unit, X is the unit number and b = log(learning rate) / log(2). For an 85 percent curve b is minus 0.2345. In Crawford's unit model Y is the time for unit X. In Wright's cumulative average model Y is the average time of the first X units, so the same rate gives lower times. To plan a ramp-up, work out the time for each unit, cap it at the standard time, add the units up week by week against the crew's hours, and set interim standards that step down as the count rises. Get the rate from your own data, because a few points of rate change the answer by months.
Last reviewed:
What is a learning curve?
An 85% learning curve, from the first unit to standard
Example numbersPeople and plants get faster at a job the more times they do it. Hands learn the motions, the fumbling stops, the tooling gets fixed, the bad instruction gets rewritten. The learning curve puts a number on how fast that happens.
The rule it uses is doubling. Each time the total number of units built doubles, the time per unit falls to a fixed share of what it was. That share is the learning rate. On an 85% curve, unit 2 takes 85% of the time of unit 1, unit 4 takes 85% of unit 2, unit 8 takes 85% of unit 4, and so on.
Two things follow, and both surprise people. A lower percentage means faster learning: an 80% curve drops 20% per doubling and a 95% curve only 5%. And the gains come early. Going from unit 1 to unit 2 saves as large a share as going from unit 500 to unit 1,000, but the second takes 500 units to arrive.
The idea comes from aircraft building. T. P. Wright published it in 1936 after noticing that the labour hours for an airframe fell by about 20% each time the number built doubled. You will also see it called the improvement curve, the progress curve and the experience curve.
For a planner it answers the launch questions that a standard time can't. The standard time says how long the job takes once people are trained. The learning curve says how long it takes until then, how many units that is, and what the first weeks will really produce.
The formula, and what the exponent means
The whole model is one line: Y = a x X^b. Here a is the time for the first unit, X is the unit number counted from the start, and b is a negative exponent that carries the learning rate.
You get b from the rate: b = log(learning rate) / log(2). Any logarithm works as long as it is the same on top and bottom. The division by log 2 is what makes the rate apply per doubling: put X = 2 into the formula and 2^b comes out as exactly the learning rate.
| Learning rate | Fall per doubling | Exponent b | Unit 2 as a share of unit 1 | Unit 16 as a share of unit 1 |
|---|---|---|---|---|
| 95% | 5% | minus 0.0740 | 95% | 81.5% |
| 90% | 10% | minus 0.1520 | 90% | 65.6% |
| 85% | 15% | minus 0.2345 | 85% | 52.2% |
| 80% | 20% | minus 0.3219 | 80% | 41.0% |
Unit 16 is four doublings on, so its share is the rate to the fourth power.
Because Y = a x X^b is a power law, it plots as a straight line when both axes are logarithmic. That is the practical test of whether your data follows a learning curve at all: plot hours against unit number on log-log paper. If the points fall on a line, the slope is b and the rate is 2^b. If they do not, something other than learning is going on.
On log-log axes the curve is a straight line
Example numbersTwo models with the same formula: Wright and Crawford
The formula hides a choice that changes the answer a lot: what is Y? There are two standard readings, and they are not interchangeable.
| Wright: cumulative average model | Crawford: unit model | |
|---|---|---|
| Y is | The average time per unit of all units from 1 to X | The time of unit X on its own |
| When output doubles | The average of everything built so far falls to the learning rate | The time of the latest unit falls to the learning rate |
| Total time for X units | X x a x X^b | The sum of a x n^b for n from 1 to X |
| Time of one unit | Total for X units minus total for X minus 1 | a x X^b |
| Fits when | You have total hours for a batch or a contract and no unit detail | You timed individual units or small lots |
| Also called | Cumulative average theory | Unit theory |
Wright's 1936 paper used the cumulative average. Crawford's version, developed at Lockheed in the 1940s, applies the same rule to each unit. Run both with the same first unit and the same rate and Wright comes out lower, because an average that falls by 15% needs the newest units to fall by much more.
| Unit | Crawford: time of this unit | Crawford: total so far | Wright: average so far | Wright: total so far | Wright: time of this unit |
|---|---|---|---|---|---|
| 1 | 40.0 h | 40.0 h | 40.0 h | 40.0 h | 40.0 h |
| 2 | 34.0 h | 74.0 h | 34.0 h | 68.0 h | 28.0 h |
| 4 | 28.9 h | 133.8 h | 28.9 h | 115.6 h | 22.9 h |
| 8 | 24.6 h | 237.4 h | 24.6 h | 196.5 h | 19.1 h |
| 16 | 20.9 h | 415.3 h | 20.9 h | 334.1 h | 16.1 h |
Crawford's column for the unit and Wright's column for the average hold the same numbers. They mean different things.
Same first unit, same 85%, two different answers
Example numbers- Unit 1Crawford40.0 hWright40.0 h
- Unit 2Crawford34.0 hWright28.0 h
- Unit 4Crawford28.9 hWright22.9 h
- Unit 8Crawford24.6 hWright19.1 h
- Unit 16Crawford20.9 hWright16.1 h
- Crawford, unit model: the time of unit X is a x X^b
- Wright, cumulative average model: the average of units 1 to X is a x X^b
- Standard 16 h
By unit 8 the two totals are 237.4 and 196.5 hours, a gap of 41 hours. A 16 hour unit arrives at unit 17 under Wright and at unit 50 under Crawford. So a learning rate is meaningless without its model. An 85% rate fitted to unit times is an 85% unit curve, and quoting it as a cumulative average rate will make the plan far too optimistic.
Which to use: the one that matches how the data was collected. For planning a ramp on the shop floor that is nearly always the unit model, because you time units and you need the time of the next unit. The rest of this page uses it.
Worked example: a 40 hour first unit on an 85% curve
The job is wiring and assembling a control cabinet, a new design, built by a crew of four. The first cabinet took 40.0 hours of labour. The engineered standard, from predetermined times, is 16.0 hours. The crew's last two cabinet designs followed an 85% unit curve, so that is the planning rate. All of it is illustrative.
With b = log(0.85) / log(2) = minus 0.2345, the time for any unit is 40 x X^(minus 0.2345). The table shows it by doubling.
| Unit | Hours for this unit | Share of unit 1 | Total hours so far | Average hours so far |
|---|---|---|---|---|
| 1 | 40.0 | 100% | 40.0 | 40.0 |
| 2 | 34.0 | 85% | 74.0 | 37.0 |
| 4 | 28.9 | 72.3% | 133.8 | 33.5 |
| 8 | 24.6 | 61.4% | 237.4 | 29.7 |
| 16 | 20.9 | 52.2% | 415.3 | 26.0 |
| 32 | 17.7 | 44.4% | 719.3 | 22.5 |
| 64 | 15.1 | 37.7% | 1,237.3 | 19.3 |
Each row is 85% of the row above in the second column. The last row is below the 16 hour standard, which is where the plateau comes in.
When does the job reach standard? Solve the formula for X: X = (standard / first unit)^(1 / b) = (16 / 40)^(1 / minus 0.2345) = 49.8. Unit 49 takes 16.06 hours and unit 50 takes 15.98, so the crew reaches standard at unit 50.
The cost of getting there is the area between the curve and the standard. Units 1 to 49 take 1,004.5 hours in total. At standard they would take 49 x 16 = 784 hours. The difference, 220.5 hours, is the learning cost of this launch: about five and a half weeks of one person's time that has to be in the budget and the schedule.
The rate matters far more than the first unit. Keep everything else and change only the rate: at 80% the job reaches 16 hours at unit 18, at 85% at unit 50, at 90% at unit 415. Five points of learning rate is the difference between a ramp of weeks and a ramp of most of a year. That is why the rate has to come from your own records.
How to turn the curve into a ramp-up plan
A ramp-up plan says how many units come off each week until the job is at standard. The curve gives hours per unit. The plan turns that into units per week by spending the crew's hours down the list of units.
From a first unit time to a weekly plan
- 1
Decide what counts as one unit and which model you are using
- 2
Get the first unit time
- 3
Get the learning rate from your own data
- 4
Set the plateau
- 5
Build the unit table
- 6
Convert to weeks
- 7
Set interim standards for each block of units
- 8
Track actual against plan every week and refit
- 1
Decide what counts as one unit and which model you are using
One cabinet, one lot of ten, one shift's output. Use the unit model if you time units. Write both down next to the rate.
- 2
Get the first unit time
Use the measured hours of the first unit or the first lot. If nothing is built yet, estimate it from the first unit of the most similar past job, not from the standard.
- 3
Get the learning rate from your own data
Fit it to the unit hours of a similar past launch, or to this job's pilot units. Plot on log-log axes and check the points make a line before you trust the slope.
- 4
Set the plateau
The engineered standard time is the floor. The curve stops there, and no unit is planned faster than standard.
- 5
Build the unit table
Time for each unit from the formula, capped at the standard, with a running total of hours.
- 6
Convert to weeks
Work out the labour hours the crew has each week. A unit is finished in the week its running total is reached.
- 7
Set interim standards for each block of units
Give supervisors and the schedule a target for the block they are in, stepping down as the count rises.
- 8
Track actual against plan every week and refit
Plot actual unit hours on the same chart. After 8 or 10 units, refit the rate and reissue the plan.
For the cabinet job the crew of four has 4 x 40 = 160 labour hours a week. At standard that is 160 / 16 = 10 cabinets a week.
| Week | Cabinets finished | Total so far | Share of the standard rate |
|---|---|---|---|
| 1 | 4 | 4 | 40% |
| 2 | 7 | 11 | 70% |
| 3 | 8 | 19 | 80% |
| 4 | 8 | 27 | 80% |
| 5 | 9 | 36 | 90% |
| 6 | 10 | 46 | 100% |
| 7 onward | 10 | 56 and up | 100% |
A cabinet counts in the week it is finished. Unit 50, the first at standard, is finished early in week 7.
The ramp-up plan, week by week
Example numbers- Finished, still on the curve
- Finished, at the standard rate
- Short of a plan at standard
Six weeks produce 46 cabinets where a plan at standard would have promised 60. If the customer was told 10 a week from the first Monday, the order book is 14 cabinets short before anything has gone wrong. That is the conversation the ramp-up plan exists to have early.
The learning curve and ramp-up workbook does these sums for up to 500 units under both models, fits the rate from your own points and builds the weekly plan with a plateau.
Interim standards during the ramp
During the ramp the final standard is the wrong yardstick. Measured against 16 hours, the crew is at 40% in week 1 and looks like a failure while doing exactly what the plan expects. An interim standard is a temporary target for a block of units, taken from the curve.
| Units | Curve at the start of the block | Curve at the end | Interim standard (block average) | Hours for the block |
|---|---|---|---|---|
| 1 to 4 | 40.0 h | 28.9 h | 33.5 h | 133.8 |
| 5 to 8 | 27.4 h | 24.6 h | 25.9 h | 103.6 |
| 9 to 16 | 23.9 h | 20.9 h | 22.2 h | 177.9 |
| 17 to 32 | 20.6 h | 17.7 h | 19.0 h | 303.9 |
| 33 to 49 | 17.6 h | 16.1 h | 16.8 h | 285.3 |
| 50 onward | 16.0 h | 16.0 h | 16.0 h, the standard |
Blocks follow the doublings, so each step down is about the same size. The five blocks add up to the 1,004.5 hours for units 1 to 49.
Interim standards: a staircase down the curve
Example numbers- Interim standard for the block
- Learning curve, capped at the standard
- Step by units built, not by the calendar. Learning follows repetitions. A week lost to a parts shortage should not move the target.
- Publish all the steps before the start. A target that drops without warning feels like a rate cut. A staircase people saw on day one is a plan.
- Use them for scheduling, costing and judging the launch. Be careful about tying pay to them. If you do, that is a matter for your agreements and local rules, not for a formula.
- When the crew beats a step, find out what they changed and put it in the method. When they miss one, look for a method problem before you look at effort.
- End them. Once the times stop falling, set the real standard with a time study on the settled method.
The plateau: where the curve stops
The formula never stops falling. Left alone it says unit 500 of the cabinet takes 9.3 hours and unit 1,000 takes 7.9, on a job whose engineered standard is 16. Nobody should plan on that. At some point the operator is doing the method as designed at a normal pace, and what is left is the work itself.
So planners cap the curve. The usual cap is the standard time: the curve applies until it reaches the standard, and the standard applies after that. Researchers have built the same idea into the formula. De Jong's version adds a factor for the share of the job that can't be compressed, such as machine time, so the curve levels off towards a floor. Another variant, known as Stanford-B, shifts the curve to allow for experience the crew brings from earlier products, which makes the first units less steep.
A plateau is not the end of improvement. It is the end of free improvement from repetition. Times can still fall, but only because someone changes the method, the tooling or the design. That is kaizen, and it shows on the chart as a step down, not as more of the same curve.
Watch for a plateau that arrives early. If the times flatten at 22 hours when the standard says 16, either the standard was wrong or something is holding the crew back that practice can't fix. Go and look, as described in the section on telling learning from method problems in the pilot run guide.
Forgetting: what a break in production costs
Learning is lost when the work stops. After a gap between orders, a long shutdown or a crew change, the next unit takes longer than the last one did, and the crew has to climb part of the curve again. Controlled experiments on repetitive tasks have confirmed it: the longer the break, the more is lost.
A method widely used in cost estimating comes from George Anderlohr, who wrote it up in 1969. You estimate a lost-learning factor, the share of the learning that the break wiped out, by looking at five things: the people, the supervision, the continuity of production, the methods and the tooling. Then you move the job back up its own curve.
- 1
Find the learning achieved
First unit time minus the time the next unit would have taken with no break. The cabinet job stops after unit 20. Unit 21 would have taken 19.59 hours, so the learning achieved is 40.00 minus 19.59 = 20.41 hours.
- 2
Estimate the share lost
Judge each of the five things and weight them. Say the result is 40%: two of the four people are new and the jigs were stored. Learning lost is 0.40 x 20.41 = 8.16 hours.
- 3
Add it to the next unit
The first unit after the break is expected to take 19.59 + 8.16 = 27.75 hours.
- 4
Find that time on the original curve
27.75 hours sits between unit 4 and unit 5. Unit 5 takes 27.43 hours, so the job restarts as if it were at unit 5: a setback of 16 units.
- 5
Replan from there
Unit 21 is planned at unit 5's time, unit 22 at unit 6's, and so on. The 16 hour standard now arrives at unit 66, not unit 50.
After a break, the job climbs part of the curve again
Example numbers- Plan with the break
- Plan with no break
- Extra hours caused by the break
The break costs 106 extra labour hours spread over units 21 to 65, on top of the gap itself. The 40% is a judgement, and the answer is only as good as it is. What the method does well is make the judgement explicit and show its cost, so the break can be argued about before it happens.
The practical lessons are plain. Keep the crew together across a gap if you can. Keep the jigs, the instructions and the video of the method, because the method and tooling parts of learning are the ones you can store. And when a job restarts, plan the first units on interim standards again.
Get the rate from your own data
Learning rates in books are averages over industries and decades. Your rate depends on how much of the job is manual, how complete the instructions and tooling were on day one, how experienced the crew is and how stable the design stays. Two plants building the same product can have quite different rates.
- From a past launch: take the labour hours of each unit or lot of the most similar job you have run. Plot hours against unit number on log-log axes, fit a line, and the rate is 2 to the power of the slope.
- From this job's first units: the same fit on the pilot or the first week. Five points is the least to fit, and ten is better.
- Check the fit. R squared near 1 means the points follow a curve. A poor fit means something else is driving the times, and no rate will describe them.
- Fit only clean units. Leave out a unit that waited two days for a part, or note it. One bad point early on swings the slope.
- Keep the model with the rate. A rate fitted to unit hours belongs to the unit model.
Machine-controlled time does not learn. If half of a job's cycle is a machine running, only the manual half follows the curve, and the rate for the whole job will be much closer to 100% than the rate for the hand work. Split the job before you fit.
When learning curve maths is the wrong tool
The model assumes the same job, done repeatedly, by the same people, without long gaps, where people set the pace. Take any of those away and the curve will mislead.
| Situation | Why the curve fails | Use this |
|---|---|---|
| Machine-paced work: a press, a moulding machine, a filling line | The cycle is set by the machine. Operators learn the tending, not the rate | A start-up curve from OEE losses: availability, speed and quality by week |
| Short cycles at high volume: an assembly line doing hundreds a day | Operators pass through hundreds of doublings in days. The ramp is limited by stoppages, parts and defects, not by practice | A weekly efficiency plan from the pilot run and past launches, with the losses tracked by cause |
| A design that keeps changing | Each change puts part of the job back at unit 1 | Treat each major revision as a new start for the elements it touches |
| One-offs and very small runs | There are not enough repeats for a rate to mean anything | An estimate with a range, and a review after each unit |
| High turnover or a rotating crew | The people who learned are not the people building | Individual training curves per operator, from the skills matrix |
| A ramp held back by something else | Material, tooling or quality problems hide any learning | The issue list. Fix the causes, then look at the times |
The second row deserves a word, because it is where most plants meet the problem. On a manual assembly line each operator repeats a one minute job several hundred times a shift. In the pilot run example a 30 second element was at its planning time within 40 units. Operator learning on a line like that is mostly done in days. What takes weeks is everything around it: balance, parts presentation, small stops, defects. Plan those weeks with an efficiency figure per week, as in planning operators and stations for a new line, and use the learning curve for the long-cycle jobs it was made for.
There is a people side too. A curve is an average, and individuals vary around it. Use it to plan the launch and to judge the launch, not to rank operators in their first weeks. Show the crew the curve and the interim steps at the start. People who know that week 1 is meant to be slow, and can see where they are heading, learn faster than people who are told they are behind.
Filming the first units helps both sides. LeanSuite's Time and Motion Study times each element from video, so you can see which elements are still falling and which have stopped. That is the difference between waiting for learning and fixing a method.
Templates and tools for ramp-up planning
- Learning curve and ramp-up workbook: both models, a fit from your own data with R squared, the unit that reaches standard and a weekly ramp plan.
- Operator staffing calculator: headcount once the line is at standard.
- Training matrix template and skills matrix template: who is at what level on which job during the ramp.
- Time study sheet: for the standard, once the times stop falling.
- New product time study playbook and new product introduction for industrial engineers: where the ramp-up sits in the launch.
Go deeper
This page is the short version. These guides cover each part in full.
- Closing Plant-Wide Skill Gaps: A 90-Day FrameworkPlanned training that shortens the ramp for the people side of learning.
- TWI Job Instruction: Training Method for Standard WorkHow to teach a job so new operators start lower on the curve.
- Standard Work in Manufacturing: A Complete GuideHolding the method steady so that what is learned stays learned.
- Why One Employee Absence Shuts Down Production LinesWhat happens to output when the people who learned the job are not the ones on it.
All our articles on this subject are in the standard work, sops and training topic.
Free templates and tools
- Learning curve and ramp-up workbookBoth learning curve models side by side, a fit from your own observed hours, batch hours, the unit that reaches standard and a weekly ramp plan.
- Operator staffing calculatorTakt, work content, the operators a line needs, a check of your station plan and the roster with absence cover, from your own demand and element times.
- Training matrix template with expiry datesPeople by required trainings with expiry dates, OK, due, expired and missing flags, compliance by person and area, cover per training and a renewal list.
- Skills matrix templatePeople by tasks on a 0 to 4 scale, coverage and gaps per task and shift, and a training plan that closes them.
- Time study sheetTime each element over 10 cycles and work out the average, lowest repeatable and standard time. Excel does the sums.
- Standard time calculatorObserved times, a rating and an allowance in; normal time, standard time, units per hour, pieces per shift and labour cost per unit out, with the working.
- Time study sample size calculatorHow many cycles of an element to time, from your first readings, with the t formula, the ILO formula and the range method.
- Overall labor effectiveness (OLE) calculatorHow well paid labor hours turn into good output: availability, performance and quality of the crew.
Doing this in LeanSuite
Time and Motion Study
Film the station and the AI times every element on a timeline that links to the video, split into value-added, necessary and waste.
See Time and Motion StudyAI Video Analysis
Turns video of real work into time studies, line balance charts, changeover splits and other studies you review and certify.
See AI Video Analysis
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about ramp-up plan and the learning curve
An 85 percent learning curve means that each time the total number of units built doubles, the time per unit falls to 85 percent of what it was, a 15 percent reduction. If unit 1 takes 40 hours, unit 2 takes 34, unit 4 takes 28.9 and unit 8 takes 24.6. The lower the percentage, the faster the learning.
Y = a x X^b, where a is the time for the first unit, X is the unit number and b = log(learning rate) / log(2). For an 85 percent curve b is minus 0.2345. In the unit model Y is the time of unit X. In the cumulative average model Y is the average time of units 1 to X.
Both use Y = a x X^b. In Wright's cumulative average model Y is the average time of all units up to X. In Crawford's unit model Y is the time of unit X alone. With the same first unit and rate, Wright gives lower times: for 100 hours and 80 percent, eight units total 409.6 hours under Wright and 534.6 under Crawford.
In economics the learning curve is the fall in labour time or cost per unit as cumulative output rises, first measured on aircraft by T. P. Wright in 1936. The wider version, the experience curve, applies the same idea to total unit cost. It explains why early units of a new product cost more and why volume can lower cost.
In everyday speech a steep learning curve means something is hard to pick up. In manufacturing the term is exact: it is the rate at which time per unit falls as more units are built. There, a steep curve is good news, because it means time is falling fast.
Training texts usually list four shapes: diminishing returns, where gains are fast and then slow; increasing returns, slow then fast; the S-curve, slow, fast and slow again; and the complex curve with several plateaus. Manufacturing planning uses the first shape, in two forms: Wright's cumulative average model and Crawford's unit model.
Solve the curve for the unit at which the time equals the standard: X = (standard / first unit time)^(1 / b). With a 40 hour first unit, a 16 hour standard and an 85 percent unit curve, X is 49.8, so unit 50. Then convert units to weeks with the crew's hours. The answer swings widely with the rate, so use your own.
Some of the learning is lost and the next unit takes longer than the last one before the break. A common planning method estimates the share lost from changes in people, supervision, continuity, methods and tooling, adds the lost hours to the next unit, and restarts the job further back on its original curve.
Do not use it for machine-paced work, where the machine sets the cycle; for one-offs with too few repeats; for a design that keeps changing; or for short-cycle lines, where operators finish most of their learning in days and the ramp is held back by stoppages and defects. Use a weekly efficiency plan with losses tracked by cause.
Related guides and tools
- Learning curve and ramp-up workbook: both models, a fit from your data and a weekly plan
- Pilot run and line trial: where the first unit times and the learning rate come from
- Planning operators and stations for a new line: staffing the ramp-up weeks
- Standard time: the level the curve flattens out at
- New product time study playbook: which study to run at each stage of a launch
- Time and motion study: the family of methods and when to use each
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk
Or browse the topics, the full library and the lean glossary.
Rather see it on your own problem?
Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.