Pre-task plan (PTP): the five-minute briefing before the work

Short answer

A pre-task plan is a short talk at the job, before the work starts, in which the crew agrees what they are about to do, what is different today, what could hurt them and what stops the job. It takes about five minutes.

A pre-task plan (PTP), also called a pre-job brief, is the crew's own briefing at the job before work starts. It answers seven questions: what are we doing and in what order, what is different today, what could hurt us most, what stops each hazard, who does what, what stops the job, and what happens if it goes wrong. Each person says back their part. The JSA, method statement and permit were written earlier. The pre-task plan checks them against the conditions the crew actually finds, and it is the one place today's changes get on paper. General practice, not a legal requirement we could find.

Last reviewed:

What is a pre-task plan?

A pre-task plan is a briefing and a record. The crew stands at the job with the person leading the work, goes through the task and its hazards in their own words, and signs a short card. It is done before the first step, every time the task starts, and it is the crew's own. A supervisor can join but should not run it from a chair.

It exists because every document written earlier is out of date by the time the crew arrives. The JSA assumed a normal day. The permit was issued for the plant as it was at 07:00. On the morning, a forklift route has moved, the floor is wet, a fitter is new, and the part that was meant to arrive has not. Nothing on the earlier paper says so. The pre-task plan is where those facts are said out loud and written down.

The name varies. US industrial and construction sites say pre-task plan or PTP. Power, nuclear and engineering sites often say pre-job brief or pre-job briefing: the US Department of Energy's Human Performance Improvement Handbook (DOE-HDBK-1028-2009) lists it as one of its tools, alongside a post-job review. Tailgate meeting and toolbox talk are the everyday names for any short meeting at the job, and the difference matters, as the table shows.

Which document works at which moment of a job

DocumentPlanning, days beforeStart of the jobDuring the workHand-back
JSA or SOPHow is this kind of task done safely?Write onceRead
SWMS or method statementHow will this high-risk job be done?Write for the jobBrief and signCheck the work against it
Permit to workIs the plant safe, and may the job start?RequestIssue at the jobHold, suspend, hand overHand back and cancel
Pre-task planWhat is different today?Brief the crew
Field level risk assessmentIs this step safe right now?Before each step

A table of five safety documents against four moments: planning, the start of the job, during the work and hand-back. The job safety analysis and the method statement are written in planning. The permit is requested in planning, issued at the start, held during the work and handed back at the end. The pre-task plan is a briefing at the start. The field level risk assessment is a check before each step.

The pre-task plan is the only document that is made at the job, by the crew, on the day. Everything to its left was written for a day that has already changed.
The pre-task plan and the checks around it
CheckWhenWhoWhat it is for
JSA or SOPWritten once per kind of taskSupervisor and operatorsHow this kind of task is done safely: steps, hazards, controls
[SWMS](/learn/safe-work-method-statement) or method statementWritten for one high-risk jobThe business doing the workHow this job will be done, and how it will be checked
[Permit to work](/learn/permit-to-work)Issued before the job startsIssuer and permit holderWhether the job may start, with the plant made safe
Pre-task planAt the job, before the first stepThe crew, led by the person in chargeWhat is different today, and does everyone know their part
[Field level risk assessment](/learn/field-level-risk-assessment)Before each step, and when something changesEach individualIs this step safe right now
Toolbox talkPlanned, often weeklySupervisor, to the teamOne safety topic chosen in advance, not tied to today's task

The first four are about the job. The last two are about the moment and the topic.

The seven questions

A pre-task plan is only as good as its questions. These seven are our recommended format. Use your site's card if it has one, and check that it covers the same ground.

Seven questions, then the say-back

  1. 1

    What are we doing, in what order?

  2. 2

    What is different today?

  3. 3

    What could hurt us most?

  4. 4

    What stops each one?

  5. 5

    Who does what?

  6. 6

    What stops the job?

  7. 7

    What if it goes wrong?

Question 2 is the one the earlier documents cannot answer. The briefing ends when each person has said their part, not when the leader stops talking.
  1. 1

    What are we doing, in what order?

    The person leading says the job in four to eight steps, from the JSA or method statement, pointing at the equipment. If they cannot say it without reading, the job is not understood yet.

  2. 2

    What is different today?

    Weather, traffic, other work nearby, a new person, a changed part, a tool that has been swapped, a permit with a note on it. This is the question the earlier documents cannot answer, and the one that makes the card worth writing.

  3. 3

    What could hurt us most?

    Ask for the worst thing that could happen, not a list of every hazard. The crew names two or three: what is overhead, what could start, what is hot, what could fall. Naming the worst case focuses the rest.

  4. 4

    What stops each one?

    For each hazard, the control, and who checks it before work starts. Prefer controls that are visible: a lock on, a barrier up, a guard fitted. Protective equipment goes last. See the hierarchy of controls.

  5. 5

    Who does what?

    One person is in charge. Each person has a named job: who rigs, who isolates, who watches, who signals. A crew where nobody owns the watching role has nobody watching.

  6. 6

    What stops the job?

    Say it before it happens: a lock removed, a person under the load, a smell of solvent, a change in the plan. And say that anyone may call the stop, with no questions asked. See stop work authority.

  7. 7

    What if it goes wrong?

    The nearest alarm point, who to call, where the first aid kit and the assembly point are, and who goes to meet the ambulance. Thirty seconds, said out loud, each time.

Then the last move, which is not on the card: each person says back their own part, in their own words. The briefing is over when everyone can do it, not when the leader has finished talking. Some site pre-job briefing procedures, such as one published by SLAC, ask the lead to have workers summarize the key points for exactly this reason.

A filled pre-task plan: the gearbox job

Illustrative example. The crew in the permit to work guide is about to replace the agitator gearbox on tank T-3. The permit PTW-0457 has been issued and accepted at 07:00, and the isolations are on. At 07:05 the holder, K. Brandt, calls the crew of three together at the tank for the pre-task plan. All names, equipment and times are made up.

A filled pre-task plan: the gearbox job, 07:05

Example numbers
1. What are we doing, in what order?
Swap the agitator gearbox on T-3. Hoist out, fit new unit and coupling, guard on, test run.
2. What is different today?
Forklift deliveries through the hall from 10:00. Floor wet by the V-12 bleed. New fitter on the crew. Hoist inspection tag due next week, in date.
3. What could hurt us most?
An 85 kg gearbox falling from the hoist. Steam left in the jacket. Someone starting the agitator.
4. What stops each one?
Chain hoist rated and checked, nobody under the load. Steam isolation proven at gauge PI-3. Locks L-031 to L-033 on, each person's own lock on box LB-2.
5. Who does what?
Brandt leads and signs the permit. Imai rigs and hoists. Dube is the isolator. New fitter works beside Imai.
6. What stops the job?
Any lock off, anyone under the load, steam seen at the bleed, a forklift in the barriered area. Anyone may call it.
7. If it goes wrong?
Call point at the mezzanine stairs. Control room on radio channel 1. Assembly point Gate A.

A pre-task plan card with seven questions and answers for the tank T-3 gearbox job: the task and its order, what is different today, what could hurt most, the controls, who does what, what stops the job, and the emergency arrangements.

The second question does the most work. The JSA and the permit were written days ago. This line is the only place today's forklift traffic, wet floor and new fitter get on paper.

Look at questions 2 and 6 in the card. Nothing on the permit mentions the forklift deliveries from 10:00, the wet floor by the bleed valve or the new fitter. All three are reasons to change who stands where, and one of them (a forklift entering the barriered area) is written as a reason to stop the job.

The briefing takes five minutes by the clock, and it changes the work in two ways. The new fitter is paired with the person who rigs, instead of working alone at the coupling. And the forklift route for the 10:00 delivery is moved by a call to the shift lead. Both changes cost a few minutes, and neither would have been made from the permit alone.

How to run it in five minutes

Five minutes is enough for most tasks. The split below is our suggestion. A new or complex job takes longer, and a short repeated task can use a shorter form of questions 2, 6 and 7.

A 5-minute briefing, minute by minute

Example numbers
  1. 1 min Task and order
  2. 1 min What is different today
  3. 1.5 min Hazards and controls
  4. 0.5 min Roles and stop triggers
  5. 1 min Each person says back their part

A stacked bar of a five minute briefing: task and order 1 minute, what is different today 1 minute, hazards and controls 1.5 minutes, roles and stop triggers half a minute, and each person saying back their part 1 minute.

Our suggested split, not a standard. The last minute is what separates a briefing from a reading: nobody has understood it until they can say their part back.
  • Hold it at the job. Where the crew can see the equipment, the access, the hoist and the isolator. A briefing in a meeting room is a different conversation.
  • Stand together, the person in charge last to speak. Ask questions before answering them: "What is different today?" gets better answers than "Any concerns?".
  • Use the JSA or method statement as the reference, in hand. The plan checks the paper against the day. It does not read the paper aloud.
  • Keep the card short. Seven lines, one page. The signatures are on the back or at the bottom, after the say-back, never before.
  • Keep it where the work is, and keep the finished cards for a short time as a record. Your own procedure sets how long.

When to do one, and when to do it again

  • Before any non-routine task, and before any task covered by a permit or a method statement.
  • At the start of each shift on a longer job, with the new crew, not the one before.
  • When a person joins the crew mid-job, for that person at least.
  • After any stop, when the job restarts: the stop is the proof that something was different from the plan.
  • When the plan changes: a different method, a different access, a different tool. Treat it as a new job.
  • For routine production tasks, a short form at the start of the shift is enough, and the field level risk assessment covers the rest. If the task never changes, standard work already holds the steps.

A change that is large enough to alter the equipment or the method goes through management of change first, before a crew is asked to brief it.

Why it turns into a ritual, and how to stop that

  • Read aloud, not asked. The leader reads the card in a monotone and the crew nods. Fix: ask each question and wait.
  • Signed first. The card goes round before anyone has heard anything. Fix: signatures after the say-back.
  • The same answers every day. If question 2 says "nothing" fifty times, nobody is looking. Fix: the supervisor reads a sample of cards weekly and asks about an answer.
  • Cards counted as a target. Counting completed cards rewards filling them in. Count the changes they led to instead: a route moved, a person re-paired, a job stopped.
  • Nobody acts on what is written. A crew that raises a concern and sees nothing change learns what the card is worth. Fix: the supervisor answers every concern, in writing or in person, the same day.
  • Done in the break room. Fix: at the job, with the equipment in view.

What it cannot do

A pre-task plan does not make a bad plan good. If the JSA missed a hazard, the crew might catch it at the job, and might not. If isolation is wrong, a briefing does not fix it: that is what the permit and its proof are for. The plan is the last check before the work, which is also its weakness. People who have been briefed feel prepared, and a crew that has said every right thing is not necessarily a crew that has seen the hazard.

LeanSuite's safety improvement tools run inspections and lockout checks from templates, and raise a safety tag when an item fails. They do not write or store pre-task plans. This guide is general practice, not legal advice. We did not find a standard that requires a pre-task plan by that name. Check the rules that apply to your site.

Templates and related guides

Doing this in LeanSuite

See it on your own lines

Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.

FAQ

Questions about pre-task plan (PTP)

  1. A pre-task plan is a short briefing at the job, before the work starts, where the crew agrees the steps, what is different today, what could hurt them, what controls are in place, who does what, what stops the job and what to do in an emergency. It ends with each person saying back their part and a short signed card. It takes about five minutes.

  2. A JSA is written in advance for a kind of task and lists its steps, hazards and controls. A pre-task plan is done at the job, each time, and checks the JSA against today's conditions: the weather, the people, the equipment and other work nearby. The JSA is the reference. The pre-task plan is the conversation that confirms it still fits the day.

  3. A pre-job brief is the same idea under a name used in power, nuclear and engineering work. The US Department of Energy's Human Performance Improvement Handbook (DOE-HDBK-1028-2009) lists pre-job briefing as a tool, with a post-job review to follow. Some site procedures ask the lead to have workers summarize the key points, so understanding is confirmed, not assumed.

  4. No. A toolbox talk, sometimes called a tailgate meeting, is usually a planned safety topic given to a team, such as ladders or manual handling, and is not tied to the task about to start. A pre-task plan is about the specific job the crew is about to do today. Many sites hold both: the topic talk weekly, the pre-task plan before each task.

  5. About five minutes for most tasks. A suggested split is one minute on the task and its order, one on what is different today, a minute and a half on hazards and controls, half a minute on roles and stop triggers, and a minute for each person to say back their part. New or complex jobs take longer. If it takes under two minutes, the questions are probably not being asked.

  6. We did not find a standard that requires a pre-task plan by that name. Some employers, clients and contractors require one as a condition of work, and regulators in some countries ask for documented risk assessment and communication with workers before higher-risk work. Check the rules that apply to your site and the terms of your contract. This is general guidance, not legal advice.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.